I. Payback Period Same CF Project A Different CF Project B
I. Payback Period Same CF Project A Different CF Project B
FIN242 , CHAPTER 12
JUN19
i. Payback Period
Same CF Different CF
Project A Project B
50 000 4+(80 000−70 000)
PP = PP =
15 000 70 000
= 3.3 years = 4.1 years
Same CF Different CF
A B
NPV = (0 × (10%,1)) + ((0 × (10%,2)) + (70 000 ×
NPV = 15 000 (PVIFA, 10%, 5) – PVIF (10%,3)) + (0× (10%,4))
50 000 + (70 000 × (10%,5)) – 80 000
= 15 000 (3.7908) – 50 000
= RM 6 862 = (70 000 × (0.7513)) + (70 000 ×
(0.6209)) - 80 000
= RM 52 591 + RM 43 463 - 80 000
= RM 16 054
50 000 = 15 000
(PVIFA, 5) = 50 000/15 000
(PVIFA, 5) = 3.3333
Do Interpolation :
15% = 3.3522
? = 3.3333
16% = 3.2743
% = 15.24%
iv. For NPV, Project with higher NPV are preferred. NPV(B) is higher than NPV (A). While, for PP,
the Shortest P.P is favorable. In this Case, Project A is better due to shortest payback period
(P.P).
DEC18
i. Payback Period
Same CF Different CF
Machine B Machine A
120 000 3+(120 000−105 000)
PP = PP =
40 000 30 000
Same CF Different CF
Machine B Machine A
NPV = (40 000 × (PVIF 12%,1)) + (35 000 × (PVIF
NPV = 40 000 (PVIFA, 12%, 5) – 12%,2)) + (30 000 × PVIF (12%,3)) + (25 000 ×
50 000 (10%,4))
= 40 000 (3.6048) – 120 000 + (20 000 × (12%,5)) – 120 000
= RM 24 192
= (40 000 × (0.8929)) + (35 000 × (0.7972)) +
(30 000 × (0.7118)) + (25 000 × (0.6355))
+ (20 000 × (0.5674)) – 120 000
iii. IRR
Do Interpolation
18% = 3.1272
? = 3.000
20% = 2.9906
iv. For NPV, Project with higher NPV are preferred. NPV(B) is higher than NPV (A). While, for PP,
the Shortest P.P is favorable. In this Case, Machine B is better due to shortest payback period
(P.P).
JUN18
i. Payback Period
Same CF Different CF
Project Q Project p
480 000 3+( 400 000−280 000)
PP = PP =
132 000 100 000
Same CF Different CF
Project Q Project P
NPV = (80 000 × (PVIF 12%,1)) + (100 000 × (PVIF
NPV = 132 000 (PVIFA, 12%, 5) – 480 12%,2)) + (100 000 × PVIF (12%,3)) + (200 000 ×
000 (10%,4)) + (100 000 × (12%,5)) – 480 000
= 132 000 (3.6048) – 480 000
= RM 4 166.4 *Unprofitable (-ve) = (80 000 × (0.8929)) + (100 000× (0.7972)) + (100
000 × (0.7118)) + (200 000 × (0.6355)) + (100 000 ×
(0.5674)) – 480 000
Do Interpolation
11% = 3.6959
? = 3. 6363
12% = 3.6048
iv. ∴ Project with higher NPV are preferred. NPV (P) is higher than NPV (Q).
JAN18
i. Payback Period
Same CF Different CF
System B System A
45 000 4+(45 000−44 000)
PP = PP =
15 000 12000
Same CF Different CF
System B System A
NPV = (25 000 × PVIF (10%,1)) + (-7 000 × (10%,2)) +
NPV = 15 000 (PVIFA, 10%, 5) – 45 000 (14 000 × PVIF (10%,3)) + (12 000 × (10%,4)) + (20 000
= 15 000 (3.7908) – 45 000 × (10%,5)) – 80 000
= RM 11 862
= (25 000 × (0.9091)) + (-7 000 × (0.8264)) + (14
000 × 0.7513)) + (12 000 × (0.6830)) + (20 000 ×
(0.6209)) – 45 000
iii. IRR
Do Interpolation
18% = 3.1272
? = 3.000
20% = 2.9906
iv. For NPV, Project with higher NPV are preferred. NPV(B) is higher than NPV (A). While, for PP,
the Shortest P.P is favorable. In this Case, System B is better due to shortest payback period
(P.P).
MAC17
i. Net Present Value
Same CF Different CF
Machine X Machine Y
NPV = (100 000 × (PVIF 12%,1)) + (109 000 × (PVIF
NPV = 80 000 (PVIFA, 12%, 5) – 245 000 12%,2)) + (95 000 × PVIF (12%,3)) + (80 000 × (10%,4))
= 80 000 (3.0373) – 245 000 – 269 000
= RM 2 016 *Unprofitable (-ve)
= (100 000 × (0.8929)) + (109 000× (0.7972)) + (95
000 × (0.7118)) + (80 000 × (0.6355)) – 480 000
Same CF Different CF
Machine X Machine Y
245 000 2+(269 000−209 000)
PP = PP =
80 000 109 000
iii. IRR
Do Interpolation
11% = 3.1024
? = 3.0625
12% = 3.0373
iv. For , Payback Period the Shortest P.P is favorable. In this Case, Machine Y is better due to
shortest payback period (P.P). While, for NPV the machine with higher NPV are preferred.
NPV(Y) is higher than NPV (X).
OCT16
i. Payback Period
Same CF Different CF
Molding B Molding A
10 000 1+(10 000−7 000)
PP = PP =
4 000 7 000
∴ Payback Period the Shortest P.P is favorable. In this Case, Molding A is better due to
shortest payback period (P.P).
Same CF Different CF
Molding B Molding A
NPV = (7 000 × PVIF (10%,1)) + (3 500 × (10%,2)) + (3
NPV = 4 000 (PVIFA, 10%, 5) – 10 000 000 × PVIF (10%,3)) + (1 500 × (10%,4)) + (2 500 ×
= 4 000 (3.7908) – 10 000 (10%,5)) – 10 000
= RM 5 163.2
= (7 000 × (0.9091)) + ( 3 500 × (0.8264)) + (3 000
× 0.7513)) + (1 500 × (0.6830)) + (2 500 × (0.6209)) –
10 000
∴ NPV the machine with higher NPV are preferred. NPV(B) is higher than NPV (A).
Do Interpolation
28% = 2.5320
? = 2.5000
32% = 2.3452