Checklist For Post Tensioning 1

The document is a checklist for the installation, stressing, and grouting of post-tensioning (PT) tendons. It contains 20 items to check for installation, including checking materials, strand specifications, layout, and safety permits. It also contains 10 items to check for stressing, such as equipment cleaning, concrete strength, stressing calculations, and elongation recording. Finally, it lists 9 items to check for grouting, such as strand cutting, grout mix design, grout strength testing, and safety permits.

Uploaded by

Mahendra Babre
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views2 pages

Checklist For Post Tensioning 1

The document is a checklist for the installation, stressing, and grouting of post-tensioning (PT) tendons. It contains 20 items to check for installation, including checking materials, strand specifications, layout, and safety permits. It also contains 10 items to check for stressing, such as equipment cleaning, concrete strength, stressing calculations, and elongation recording. Finally, it lists 9 items to check for grouting, such as strand cutting, grout mix design, grout strength testing, and safety permits.

Uploaded by

Mahendra Babre
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

TATA PROJECTS LIMITED

Name of Project : Proposed Development of Sahyadri Park-2 (SP2) at Plot No.:5,


MIDC SEZ, RGIP Hinjewadi, Phase-III, Pune.

Check List for Installation of Post Tension(PT)

Name of work : Date :

Location :

Drawing Ref. No. :

Checked
Sl.No. Item Remarks
Yes No NA

1 Is the approved method statement available ?

2 Are the approved GFC drawings available?


Is the materials received at site are approved from client /
3 consultant?
Is the manufactures certificates available for the strands
4 received at site?

5 Is the diameter of strands found ok?

6 Is the thickness of sheathings are as per method statement ?


Is the cleanliness of the strands, sheathings & wedges found
7 ok?

8 Is the stacking of material done neetly and category wise?

9 Are the beam soffit levels are as per drawing?


Is the position of anchorages fixed & marked with paint as per
10 dwg?
Are the profile chairs , supporting rebar's provided & tied
11 properly?
12 Is the no.of tendons provided as per GFC drawings?
Is the no.of strands per tendons are placed & aligned as per
13 GFC drawing ?
14 Is the spacing of the tendons maintained as per drawing?
Is the horizontal & vertical profile of the tendons maintained
15 as per dwg?
Is the stressing end & dead end of tendons maintained as per
16 the GFC drawing?
Is the minimum grip length ( 750 mm) maintained at
17 stressing end for stressing the tendons?

18 Is the inlets & outlets hose provision made for grouting ?

19 Is the safety permits available for the work?

20 Is the basic PPE's available at site?

Remarks :

Execution Engineer TPL FQE TCSL/TCE


Name:
Signature:

Format No.: FQ/348, Rev.No.:R0


TATA PROJECTS LIMITED

Name of Project : Proposed Development of Sahyadri Park-2 (SP2) at Plot No.:5,


MIDC SEZ, RGIP Hinjewadi, Phase-III, Pune.

Check List for Stressing & Grouting of Post Tension(PT)

Name of work : Date :

Location :

Drawing Ref. No. :

Checked
Sl.No. Item Remarks
Yes No NA
A STRESSING

1 Is the approved method statement available ?


Is the stressing equipment cleaned & checked before stressing
2 operation?

3 Are the calibration certificates for pressure gauges available?


Is the required compressive strength of concrete attained
4 before stressing?

5 Are the wedges and wedge plates fixed?

6 Is 25 % of initial load is applied for slack removal in strands?


Is the stressing calculations report available with the vendor at
7 site?
Are all the tendons are stressed to the required force with
8 specified intervals?
9 Is the elongation of strand recorded?
Is the pressure released when the jack has reached desired
10 load.?
B GROUTING
1 Is the extra length of strands cut after stressing work?
2 Is the grout mix was as per method statement?
Is the anchorage recess patched with rich cement mortar as
3 per method statement?

4 Is the W/C ratio of 0.45 for grout mix maintained properly?

Is the consistency of grout mix was maintained through out


5 the operation?
Are the cubes have been casted to ensure the compressive
6 strength of grout ?
Is the viscosity of flow grout was tested with flow cone at
7 site?

8 Is the safety permits available for the work?

9 Is the basic PPE's available at site?

Remarks :

Execution Engineer TPL FQE TCSL/TCE


Name:
Signature:

Format No.: FQ/349, Rev.No.:R0