Module 4 Construction Estimates
Module 4 Construction Estimates
Construction
Estimates
by
Rolls Grant Vasquez ,CE
CEM 302 – CE31S1
1
Cost of Construction Facility
The cost of construction facility to the owner include:
• Initial capital cost
• Operation and maintenance cost
2
Cost of Construction Facility
Initial Capital Cost
• Land acquisition
• Planning and feasibility studies
• Architectural and engineering design
• Construction, including materials, equipment and
labor
• Field supervision of construction
• Construction financing
• Insurance and taxes during construction
• Owner’s general office overhead
• Equipment and furnishing of facility
• Inspection and testing
3
Cost of Construction Facility
Operation and Maintenance Cost
• Land rent
• Operating staff
• Labor and materials for maintenance and repair
• Periodic renovations
• Insurance and taxes
• Financing cost
• Utilities
• Owner’s other expenses
4
Cost Estimation
Cost Engineering – area of engineering practice where
engineering judgment and experience are utilized in
the application of scientific principles and techniques
to the problem of cost estimation, control and
profitability
5
Cost Estimation
Cost Estimation – one of the most important steps in
project management
– a complex process of collecting
available and pertinent information about project
scope, expected resource consumption, and future
changes in resource cost
6
Cost Estimation
Process of Cost Estimation
Conversion of information
to forecast cost of facility
Synthesis of information through visualization of
the construction process
7
Cost Estimation
Qualifications of cost estimator
8
Cost Estimation
Types of Cost Estimate (general)
9
Cost Estimation
Conceptual estimate
• Used at the outset of the project when scope are in
early stages of development
• Used to assess potential cost to determine
economic desirability
10
Cost Estimation
Detailed estimate
• Estimates that are prepared after scope of works of
project are clearly defined
• Requires effort in gathering information and
forecasting cost
• Prepared for bid purposes or definitive budgeting
• Fairly accurate projections of construction costs
• Used for decision making and commitment
11
Cost Estimation
Types of Cost Estimate (function)
1. Design Estimate
2. Bid Estimate
3. Control Estimate
12
Cost Estimation
1. Design Estimate – used by the owner or design
professional during the planning and design stage
13
Cost Estimation
2. Bid Estimate – used by the contractor for submission
to the owner either for bidding or negotiation
– consists of direct construction cost,
job site and general overhead and profit margin,
and may be derived from:
o Subcontractor quotation – basis of cost estimate for
tasks that are subcontracted by the gencon
o Quantity takeoffs – estimate of materials and labor for
tasks that will be performed by the gencon based on
plans provided by owner
o Construction procedures – assess the actual cost of
construction considering actual procedure to be
used if the project is different from typical design
14
Cost Estimation
3. Control Estimate – used by the owner for planning
long term finances
– used by the contractor for
monitoring expenses during construction
15
Methods of Cost Estimation
1. Simple Unit Cost
𝑢𝑖 𝑄𝑖
16
Methods of Cost Estimation
1. Simple Unit Cost
4.1 Foundation Structures (FTB / Column Footing)
17
Methods of Cost Estimation
2. Labor, Material & Equipment Cost
𝑄𝑖 𝑀𝑖 + 𝐸𝑖 + 𝑊𝑖 𝐿𝑖
𝑄𝑖 - quantity of element i
𝑀𝑖 - unit cost of material for task i
𝐸𝑖 - unit equipment rate for task i
𝑊𝑖 - wage rate
𝐿𝑖 - labor required per unit of task i
18
Methods of Cost Estimation
2. Labor, Material & Equipment Cost
Unit Rate Amount Total
PAY ITEM DESCRIPTION Quantity Unit
Materials Labor Materials Labor Amount
Excavation
Concrete cutting and demolition 780.0 l.m. - 100.00 - 78,000.00 78,000.00
Earth excavation 1025.0 cu.m. - 600.00 - 615,000.00 615,000.00
19
Methods of Cost Estimation
3. Allocation of Joint Cost
o Proration of joint cost to various elements of the
project in proportion to element’s cost
o Joint costs are indirect costs which cannot be
directly charged to an activity
• field supervision
• field office cost
• general operating overhead
20
Methods of Cost Estimation
4. Estimate Based on Engineer’s List of Quantities
o Based on a list of items and associated quantities
from which the total construction cost is derived
o List is made available to bidders and unit prices
are solicited from each bidder
21
Methods of Cost Estimation
4. Estimate Based on Engineer’s List of Quantities
A General Requirement
1. Mobilization / Demobilization 1 lot 0
2. CARI / Insurance 1 lot 0
3. Clearing / Hauling of Debris 1 lot 0
4. VAT / Taxes 1 lot 0
B CEILING WORKS
1. Supply / Installation of 12mm thk Plain Gypsum Board/
Echo Stop Board / Aluminum Composite Ceiling on
standard metal frames , hanger, including metal reveal ,
corner beads . Painted finish
a. Plain Gypsum Low Ceiling sq.m. 0
b. Plain Gypsum High Ceiling sq.m. 0
c. Echo Stop Low Ceiling sq.m. 0
d. Echo Stop High Ceiling sq.m. 0
e. Aluminum Composite sq.m. 0
f. Plain Gypsum Canal l. m. 0
h. Covelight l. m. 0
i. Barrel Vault l. m. 0
e. Toilet (Moisture Resistant) sq.m. 0
2. Installation of Owner supplied Ceiling Manholes 60 pc 0 22
Methods of Cost Estimation
1. Simple Unit Cost
2. Labor, Materials and Equipment Cost
3. Allocation of Joint Cost
4. Estimate Based on Engineer’s List of Quantities
23
Sample Problem
1. Conceptual Estimate
A residential condominium is to be constructed
with a total gross floor area of 77,384 m2. Parking space
is estimated to be 10% of the total gross floor area.
Estimate the projected budget with the following
historical data:
24
Sample Problem
1. Conceptual Estimate
o Labor
o Materials
o Equipment
26
Detailed Estimate
Labor Resource
• Refers to various human craft or skill resources that
actually build the project
• Cost of labor:
a) Identify skill to be used & determine hourly cost –
wage rate
b) Estimate rate of work – labor productivity
c) Divide labor rate by productivity to determine
labor cost per physical unit of work
27
Detailed Estimate
Labor Resource
28
Detailed Estimate
Labor Productivity (industry estimate)
Activity Productivity
Concreting of flooring (plain, w/o reinf.) 2 men pour 1.2 m3 per
day
Concreting of flooring, w/ reinforcement 2 men pour 0.84 m3
per day
Concreting (columns/beams) 2 men pour 0.50 m3
per day
Floor finishing 36 m2 per day
Finishing of CHB joints (tooled joint) 210 pcs CHB per day
Plastering of CHB 4 m2 per day
Laying of CHB 50 pcs CHB per day
29
Sample Problem
2. Detailed Estimate (Labor)
Two masons and one labor can install 415
pieces of hollow blocks 400x200x150mm (LxWxH) in one
day (8 hours). Determine the unit labor cost for 1 m2 of
hollow blocks installation. The wage rate is P 68/hr for
mason and P 52/hr for labor.
30
Detailed Estimate
Equipment Cost
• Equipment may either be purchased or leased
31
Detailed Estimate
Equipment Cost
• Equipment economics include:
o Production rates – output per unit time
o Equipment cost – includes direct and indirect
equipment cost
• Direct cost – cost of ownership and operation
of equipment
• Indirect cost – costs that occur in support of
the overall fleet of the equipment but cannot
be specifically assigned to a particular
equipment
32
Detailed Estimate
Capabilities of Equipment (industry estimate)
33
Sample Problem
3. Detailed Estimate (Equipment)
Determine the cost effectiveness of selecting
an equipment over manual labor for excavation with
the following data:
Back hoe: Manual labor:
Rental – P 2,000/day* Productivity – 0.41 m3/hr
Operator wage – P 100/hr Wage rate – P 55/hr
Productivity – 3.5 m3/hr
34
Detailed Estimate
Materials Estimate
• Estimator must be able to read & interpret drawings
& specs to develop a complete list of materials
required
35
Detailed Estimate
Unit of Measure
• Measurements are simplified to reduce the
probability of committing error when several digits
are being used.
36
Detailed Estimate
Estimating Concrete
37
38
Detailed Estimate
Estimating Concrete
39
Detailed Estimate
Estimating Concrete
• Concrete estimate by Floor Area
o categorized as conceptual estimate
o given a floor area, one can generally have an
idea of the total volume of concrete of the
structure
40
Detailed Estimate
Estimating Concrete
• Concrete estimate by Volume Method
o all concrete structures are estimated using its
volume
o know the dimension of the structure by referring
to the plan
o neglect the volume occupied by the
reinforcement
41
Sample Problem
4. Detailed Estimate (Concrete)
A concrete road 15 meters wide, 5 kilometers
long, is designed with a thickness as shown in the
following cross-section. Determine the quantity of
materials required if the plan specified a Class A
concrete.
6”
6”
6” 8”
42
Detailed Estimate
Estimating Masonry
• Standard concrete hollow block (CHB) has three
void cells and two half cells, making it four void cells
L
43
Detailed Estimate
Estimating Masonry
• We want to know quantity of materials for a certain
masonry work made of CHB, which generally
comprises the following:
o CHB
o Cement and sand (mortar) for block laying
o Cement, sand and gravel for filling hollow cores and
pouring stiffener columns and beams
o Reinforcing steel bars
o Tie wires
44
Detailed Estimate
Estimating Masonry
45
Detailed Estimate
Estimating Masonry
46
Detailed Estimate
Estimating Masonry
L – 4”
T – 2” 4
47
Detailed Estimate
Estimating Masonry
48
Detailed Estimate
Estimating Masonry
49
Detailed Estimate
Estimating Masonry
50
Sample Problem
5. Detailed Estimate (Masonry)
51
Sample Problem
From the following figure, prepare the bill of materials
using class “B” mixture for concrete and mortar.
25.00 M 0.2 M
0.2 M
10 cm. CHB
25.00 M
3M 2.5 M
GROUND
0.1 M
0.15 M 0.40 M
0.60 M
5.00 M
POST CHB
PLAN
52