TF 700-R-07 - Slab - On - Ground
TF 700-R-07 - Slab - On - Ground
TF 700-R-07 - Slab - On - Ground
Prepared for:
Copyright, Wire Reinforcement Institute
Wire Reinforcement Institute
942 Main Street
Hartford, CT 06103
Phone (800) 552-4WRI [4974]
Fax (860) 808-3009
Authored By:
Walter L. Snowden, P.E.
2613 Passion Flower Pass
Cedar Park, TX 78613
Phone: 512-331-6159
Fax: 512-331-6002
Email: [email protected]
This procedure was developed by Walter L. Snowden, P. E., Consulting Engineer, of Austin, Texas, over a period
of some 15 years. It is empirically derived by observing slab performance and writing or modifying equations to give
results which approximate the foundations which had been found to give satisfactory results.
In addition, Mr. Snowden, has served on the Pre-Stress Concrete Institute Ad Hoc Committee for the development
of “ Tentative Recommendations for Pre-Stressed Slabs-on-Ground” and as a Consultant to the Building Research
Advisory Board Committee on Residential Slabs-On-Ground.
Designs done by this method should be economical yet give quite satisfactory results with a minimum of deflection
and resulting superstructure distress.
While this publication deals only with foundations reinforced with reinforcing bars and/or welded wire reinforce-
ment, the procedure has been developed to be independent of the type of reinforcing used.
Table of Contents
INTRODUCTION 1
EARLY DEVELOPMENTS 1
SOILS INVESTIGATIONS 2
LABORATORY TESTING 3
OTHER PARAMETERS 5
WARNING 6
LOADING CONSIDERATIONS 7
SUPPORT CONSIDERATIONS 7
SLAB REINFORCING 13
BEAM REINFORCING 13
SITE PREPARATION 14
SLAB FORMING 15
STEEL PLACEMENT 16
SPECIAL CONDITIONS 19
CONCRETE PLACING 20
INSPECTION 22
SHRINKAGE CRACKS 23
APPENDIX A NOTATION
APPENDIX C REFERENCES
TF 700-R-07 • Page 1
In the design procedure to be presented The final report, Building Research Advisory
herein, adjustments are made to the BRAB Board (BRAB) Report #33 en-titled Criteria
procedure which allow the use of this simple for Selection and Design of Residential slab-
procedure with larger slabs and further sim- on-ground, was issued in 1968 and was
plify the design engineer’s problem of design- widely discussed by builders. First designs
ing an adequate foundation at a reasonable to follow the BRAB Report required foun-
cost, both in terms of the engineer’s time, dations heavier even than the San Antonio
and cost of the installation itself. FHA office standard LAS-22 ( Fig. 1). LAS-
22 was thought to be the heaviest design
The intent of this handbook is to provide a ever needed, but a local study showed it was
design procedure which could be used in any inadequate perhaps 30% of the time. There
Consulting engineer’s office to give adequate was naturally, great resistance to the added
designs for economical construction without costs of design and construction required by
the use of large computers, or the neces- the BRAB Report.
sity for site investigations so extensive as
to make the use of engineered foundations
economically prohibitive. The following pro-
TF 700-R-07 • Page 2
The next important contribution also oc- slab enjoyed compared to the heavier F.H.A.
curred in 1968 when a full scale post-ten- San Antonio “Standard Slab”.
sioned slab was built and tested to destruc-
tion. A subsequent report established the Variations from the BRAB Report #33 were
feasibility of using post-tensioning in slab-on- developed to maintain a reasonable ratio
ground construction and verified many of the between cost of the slab-on-ground and the
BRAB assumptions. value of the house it supported. The varia-
tions presented later in this paper have been
In 1965 the writer developed a complete, derived empirically.
overall design system, later modified to con-
form, in format, to BRAB Report #33 and fur- SOIL INVESTIGATIONS
ther influenced by the work done by H. Platt It is considered imperative that a soils inves-
Thompson, P.E. This system gained wide tigation be made on any site on which a
use in both Austin and San Antonio because design is to prepared.
of the lower cost which the post-tensioned
ALL RESIDENTIAL SLAB-ON- CONCRETE: 2500 PSI MIN. COMPRESSIVE STRENGTH. LAPS
GROUND CONSTRUCTION OR SPLICES: MINIMUM 30 DIAMETERS.
SHALL COMPLY WITH THESE SLAB: 4” MINIMUM THICKNESS WITH W OR D9 WIRE 10”
MINIMUMS. VARIATIONS ARE O.C. BOTH WAYS. MAXIMUM CLEAR PANEL BETWEEN
ACCEPTABLE WHERE SOIL BEAMS IS 15 FEET.BEAMS: 10” WIDE BY 30” DEEP. (24”
INVESTIGATION OF THE DEEP FOR ATTACHED GARAGE. CARPORT, OR PORCH
BUILDING SITE, CLIMATIC BEAMS) REINFORCE WITH TWO #6 BARS TOP AND TWO
RATINGS, AND ENGINEERING #6 BARS BOTTOM, CONTINUOUS. SPACE ALL STIRRUPS
ANALYSIS INDICATE A SLAB OF 22” O.C. ALL BEAMS SHALL PENETRATE MINIMUM 6” INTO
LIGHTER OR HEAVIER DESIGN UNDISTURBED SOIL.
IS SUITABLE. CORNER BARS: PROVIDE #6 CORNER BARS IN ALL CORNERS
OF THE PERIMETER OR EXTERIOR BEAMS. INSTALL ONE
AT TOP, OUTSIDE. AND ONE AT BOTTOM, OUTSIDE.
FIGURE 1
TF 700-R-07 • Page 3
For a small site with one structure, the unconfined strength of 1 ton is usually suf-
minimum is obviously one test boring, which ficient for single story frame houses such as
should be made where the worst soil condi- those under consideration. For commercial
tion is anticipated; ie, where fill is located, and multi-story, 2 tons is usually adequate to
or where the worst clay is suspected. If it is insure against bearing capacity failure.
not obvious, then more than one test hole
is indicated. In no case should a design be During field investigation it is important to
attempted without an adequate soils investi- make notes of existing fill, trees, thickets, old
gation of the site. fence lines, roads, slope of each lot, topog-
raphy, seeps, sinks, rock outcrops, and any
For large sites with large structures or more area which may require fill to bring it up to
than one structure, several test holes must grade before construction. Grading and drain-
be used. In planning the investigation, plan age plans, when available, may be helpful in
for the worst. It is always possible to omit identifying some of these significant fea-
borings in the field, based on data as it devel- tures. Note these fill lots or even suspected
ops. fill lots in the report so that proper care may
be exercised by the insuring agency, city offi-
For a subdivision, there can be no fixed cials, design engineers, et. al. Uncompacted
minimum number of borings. The work done fill under the beams of an engineered slab
should be that which is required to get the will almost certainly create problems. Specify
answer. In general, locating holes about one that all fill be acceptable material, properly
to every four or Five lots, if the subdivision is compacted. H.U.D. projects and subdivisions
reasonably uniform, will be adequate. Should are supposed to require that fill be placed in
different materials be encountered, additional accordance with “Data Sheet 79-G”. 15
borings must be placed to provide more
complete information of the underlying soils.
In some cases it is necessary to drill each LABORATORY TESTING
lot. When a contact between a high P.I. soil After the proper field investigations have been
and limestone is discovered, for instance, made, it is necessary to run laboratory tests
each lot which the contact crosses must be on samples from the various strata taken
designed as though the entire lot were the in the field. It is important that all strata be
worst soil condition. correctly identified and tested. Identification
should be in accordance with the unified soil
As drilling progresses, samples should be classifications chart shown in Fig. 2. Such
taken at 2’ intervals and at each different terms as “caliche,” “fat clays,” “loam” and
soil strata encountered, to a depth of at least other colloquialisms should be avoided or
15’ If it is likely that some soil will be cut used only as extra comment. Plotting liquid
from the lot, borings should be deepened limits and plasticity indices on the classifi-
appropriately. Perhaps all borings should cation chart will confirm field evaluations. If
be 20 feet deep to allow for any cut, but at proper testing and Identification are done,
present, 15’ borings are considered suffi- some degree of uniformity can be applied to
cient. Undisturbed samples should be taken, Slab-on-Ground designs.
where possible, to allow evaluation of uncon-
fined fined strengths of the various strata. As
TF
TF 700-R-07
700-R-03 •• Page
Page 41
GROUP TYPICAL
MAJOR DIVISIONS SYMBOLS NAMES
Well-graded gravels and
GW gravel-sand mixtures,
CLEAN little or no fines
GRAVELS GRAVELS Poorly graded gravels
More than 50% retained on No. 200 sieve*
Figure 2
TF 700-R-07 • Page 5
DETERMINING THE “EFFECTIVE P.I.” rock layers can reduce the “effective P.I.”
The BRAB report bases its design procedure excessively making it appear to be a very
on the soil plasticity index (P.I.). This design innocuous site, It is probably best never to
procedure also uses the P.I. because it is a use zero for a P.I. Since BRAB recognizes 15
relatively simple-pIe test which is routinely as a breaking point for Type Ill slabs, some
performed in all testing laboratories. minimum value such as 15 should always
be used for those layers with little or no P.I.
Since the soil is not always constant with BRAB recognized the problem by utilizing the
depth, it is necessary to find the “effective P.l. immediately below the slab if it was high-
P.I.” of the underlying 15 Feet. BRAB Report er than the P.I. of the lower layers. This very
#33 suggests a weighing system (Fig.3). conservative approach will always yeld good,
safe designs, considerably overdesigned.
OTHER PARAMETERS
Once the “effective P.I.’s” for
each boring are calculated,
they need to be modified by
some other parameters. The
slope of the lot should be
used to increase the “effective
P.I.” Figure 4 can be used to
determine coefficients based
on slope.
The degree of over-consoli-
dation of the natural material
Figure 3 can be estimated from the
WARNING
It should be recognized that there are certain
conditions which neither this procedure nor
any other will be able to anticipate. Examples
of such problems which might cause diffi-
culty, even to a well designed slab, would be
the location of an old fence row beneath the
foundations, a broken water pipe, improper
Unconfined Compressive Strength (qu) TSF drainage away from the foundation, a slab
Figure 5 located on top of of previously existing tree
or thicket, massive erosion or loss of support
Other factors are known to require consid- due to lack of compliance with proper site
eration; moisture condition at time of con- preparation standards, poor maintenance,
struction, geologic formation, percentage of or improper installation. There are numer-
soil passing #40 sieve, percentage passing ous documented cases where slabs have
#200 exhibited less than the desired results due
sieve, all of these affect the potential volume to one or more of these causes. Most of the
change of the underlying soil. The correct causes mentioned above can be mitigated
value of “effective P.I.” is that from the equa- by proper construction and inspection. The
tion: others, such as old fence lines, trees, or
Eff. P.I. ( ) = Effective PI x Cs x Co x Cy x Cz • • • • • Cn thickets are generally unknown to the Soils
Engineer and the Design Engineer, and, in
Much work needs to done in this area. many cases, cannot be anticipated at all. It
is felt that the present state of the art make
The ultimate performance of a slab reflects these conditions fall beyond those for which
how well the soil analysis was done. Slab the designer can properly be considered
design is only as good as the soil data on responsible. The problem with this line of
which it is based. Some engineers say reasoning is that by the time it becomes
they do not need soil data to do a design. apparent there is a problem with the slab, it is
They are either deceiving themselves or not possible in most cases to determine that
are over-designing their slabs in which case the problem is one of those which could not
they delude their clients and ultimately, the be anticipated. The owner is having difficulty,
purchaser of the structure. There are few and he is seeking relief, and quite often,
circumstances where the engineer is justified revenge and restitution. These cases usually
in over-designing and wasting the client’s end up being decided by a jury. This is one
money. There are no circumstances where very good reason for not trying to reduce the
the engineer is justified in under-designing-- design standards too far and for trying to get
even at the client’s request. a good standard adopted so it will be clearly
defined when the engineer has done all that
he can be reasonably expected to do.
TF 700-R-07 • Page 7
SUPPORT CONDITIONS
Prior to the time the BRAB report was issued,
the writer had been working on the problem
Superstructure Loads some years and had developed a working
Figure 6
design procedure.
Loads in Fig.6 are only the loads applied to The procedure involved an area of loss of
the top of the slab. To these must be added support, (Fig. 8 ) the diameter of which was
the weight of the slab, edge beams, and inte- a function of the soil (P.I., degree of compac-
rior stiffening beams. (see Fig.7). tion, etc.) and which was allowed to move
to any position under the building. The most
critical locations, of course, were under load
bearing walls and columns. The equation
had been adjusted to give both positive and
negative movements.
Slab Configuration
Figure 7
To the soil underneath, these loads are not Area of Support Loss
nearly so clearly defined. For the small slabs Figure 8
TF 700-R-07 • Page 8
a. Cantilever
pletely empirical approach, it was easy to use the positive and negative moments used in
and gave good results. design. It seems that a large number of engi-
neers feel that the positive moment is not
It has been noted during previous research as significant a design parameter as is the
concerning slab-on-ground construction that negative moment. Numerous proposals have
the large slabs tend to reach an equilibrium been offered for the reduction of the positive
in the center portion and fluctuate only with moment. A look at the loading conditions on
seasonal moisture change. most slabs will offer support to this reduction
theory, and some experimental work has
Some routine testing during the time of the been undertaken by this firm to evaluate this
soils investigations can reasonably define proposal. The results observed indicate that
the depth of the zone of seasonal moisture some reductions are justified and allowable.
change which, many say, is roughly equal To date, no findings have been brought forth,
to the horizontal distance moisture may backed by any performance data, to indicate
pene-trate under a slab and cause differen- what magnitude of reduction should be con-
tial movement or pressure. While this does sidered.
indeed give a cantilever action such as was
previously described, the point of maximum
moment is not located at a distance from
the edge equal to the depth of the seasonal
moisture change and nato distance of L (1-C).
Much work has been done trying to 2
define this cantilever distance. This
design procedure has developed an empiri-
cal curve which, when used with the equa-
tions set out later, gives good results. Again,
it makes no difference whether the cantilever
theory is used or the BRAB equations are
used, so long as the proper input is supplied
for either criteria.
(1-C) vs. Cantilever Length (lc)
Figure 12
The BRAB equations utilizing an effective
length, as opposed to the total length, were
used for years and gave good results. Since
the P.C.I. and P.T.I. have advocated a can-
tilever approach, this procedure has been
modified to use a cantilever (see Fig. 12)
which gives the same results as the modified
BRAB equations. Note that in cases both
positive and negative reinforcing are sup-
plied.
from 15 in west Texas to as high as 30 in These calculations are performed for both
east Texas. This chart reflects the stability of the “Long” and “Short” directions. The actual
the moisture content which may be expected value of L and L’ are used when they refer
in the soil due to the climatic conditions which to the width of the slab. The most critical of
may vary from year to year. A very low num- these is deflection. A slab which deflects too
ber indicates an arid climate which will be very much will cause serious problems for the
low humidity and low ground moisture except superstructure, even though the slab does
for a few weeks or months of the year when not actually break. In general then, it is best
a heavy rainfall will occur and the ground to solve first for “I required”.
will take on a considerable amount of mois-
ture creating a potential
for a large volumetric
change in a short period
of time. The larger num-
bers, such as those in
east Texas, indicate in
general a more humid
climate where the mois-
ture content of the soil
tends to remain more
uniform the year round.
Refer to the BRAB report
for a more complete de-
scription of this chart.
BEAM SPACING AND LOCATION very conservative values. They are to apply
Almost all houses, if not a basic rectangle, can to any slab on soil with P.I. of 15 or above.
be divided into two or more rectangles. If the This is a very rigid requirement. Perhaps a
building under consideration is a combination more rational approach is one such as is
of two or more rectangles, a set of calcula- shown in Fig. 17.
tions must be done for each rectangle. The
rectangles are then overlaid and the heavier
design governs the common areas as shown
in Fig. 16. Obviously there will be times when
good engineering judgement is required, as
all houses are not nice neat modules.
Slab Segments and Combined With the number of beams known, a width
Figure 16 for each can be selected, and a calculation
made for the moment of inertia. If desired, a
On some occasions the geometry of the very good first approximation can be made
house will dictate where the beams are to by using the following formulas.
be placed. When this is the case, the beams
can be located, and the calculations carried
out for width and depth based on the known
number of beams in each rectangle.
These solutions will give you “N” no. of that shown in Fig. 17, it is possible to use
beams “b” inches wide and “d” inches deep less slab reinforcing.
which will give you an “I” in the order of mag-
nitude required to limit deflection to 1/480*. It
is pointless to argue about the relative merits
of 1/360 vs. 1/480. In most cases depths
based on 1/360 will not be economical when
it comes to selecting reinforcing.
BEAM REINFORCING
Solve for top beam steel based on negative
moment, include slab steel falling within the
1-C vs. Asfy cooperating slab area. (see Fig. 20).
Figure 18
Solve for the bottom steel based on calculat- simultaneous cut and fill operation can be
ed (reduced if feasible) positive moment. Put arranged, it will save the owner-developer
the same size bars in a beam if 2 or more are quite a bit in site preparation costs.
required. It is usually best not to use more
than 3 bottom bars in each beam. If that When, for some reason, this operation can-
much steel is required, deepen the beams to not be arranged, it is necessary to stockpile
increase the lever arms or add more beams or waste the excavated material. Stockpiles
or both. should be made on prepared sites. They
should be cleared the same as a building
SITE PREPARATION site. Wasting should be in an area which will
Often the most overlooked part of the entire not be utilized later for building and which will
operation is the site preparation. The proper not be subject to erosion or create drainage
sequence should include the following: blockage.
Inadequate attention to any of these phases Fill selection is usually governed by the
can cause foundation problems even years expansive qualities of the natural soil. Fill
after the slab is built. should always be as good or better than
the on-site material on which it is placed.
It is very important that the site be cleared Sometimes more than one type of fill may be
of all grass, weeds, old decaying or decayed used.
organics, roots and trash. This material when
left under the slab can and will continue to In general, lot preparation in subdivisions is
decay and cause settlement at later dates. It poorly done. Side slope lots requiring cut and
is surprising how little settlement is required fill on each lot are usually done without any
to cause superstructure distress. The remov- effort to select the best material or supply any
al of approximately six inches of top soil is compaction to the fill.
usually adequate to remove grass, weeds,
etc. and their roots. Trees and large bushes
generally require grubbing to greater depths
to insure adequate removal. This site clear-
ing should be done prior to beginning any
required excavation.
* Not universally accepted, even by all HUD/VA offices, but currently used in San Antonio-Central Texas area.
**There is much discussion over the membrane requirement, but it currently is a HUD/VA requirement.
TF 700-R-07 • Page 16
STEEL PLACEMENT
1. For the most part, steel placement in the beams will be two bars in the top and two in the
bottom (Fig. 25). The bars will be held in position by stirrups at appropriate spacing. The
spacing should be that which will assure the proper positioning of the steel. The bottom
bars should be set on concrete bricks or blocks to keep them raised above the bottom
of the beams. Corner bars equal in size to the larger size (maximum size - #6 bars) of
any bars meeting at an exterior corner (Fig. 26) should be provided both top and bottom.
Where interior beams dead end into exterior beams, corner bars should be supplied for
bottom reinforcing only and should be the same size as the bottom bars in the interior
beam or #6 bar maximum. (Fig. 27)
2. After the beam steel is in place, the slab steel is placed. If it is necessary to lop slab steel,
the laps in adjacent bars should be staggered at least 5’ - 0” (Fig. 28)
The slab steel is run continuously from side form to side form (lapping 24 diameters mm.
where splices are required), allowing 1-1/2” cover over the ends of the bars. On the edges
where the bars run parallel to the form, the first bar should be placed a maximum of 12”
from the outside form. All slab steel should be securely tied and blocked up by chairs or
concrete briquettes. (Figures 29 & 30 )
3. To insure the lowest possible foundation cost the use of welded wire reinforcement for
slab reinforcement should be investigated. Different styles of WWR can furnish the same
steel area and the following are suggested for design example:
TF 700-R-07 • Page 18
Welded Plain Welded Wire the one space + 2 inches or 6” minimum will
Reinforcement prevail. This means that for a 12” wire spac-
ASTM Specification A 185, fy = 65 KSI ing the minimum side lap splice would be 14”
but by spacing the 2 edge wires at 4” the lap
As req’d = .098 x 40/65 = .060 in2/ft.
is reduced to the minimum of 6”. In addition
Est. wt. = 42#/CSF
the lapping of 2 wires in the splice length
WWR 4 x 4 - W2 x W2
will provide twice the required steel area.
6 x 6 - W3 x W3
By reducing the area of the 2 edge wires by
12 x 12 - W6 x W6
50%, the required As is provided uniformly
12 x 12 - W6 x W6 with 2-W3 outside
throughout the width of the slab. This reduc-
edge wires @ 4” c/c each side.
tion in wire size does not reduce the capacity
of the splice because ASTM Specification
Welded Deformed Welded Wire
A-185 provides that the weld strength shall
Reinforcement
be not less than 35,000 times the area of the
ASTM Specification A497, fy = 80 KSI
larger wire. These tonnage saving features
apply only to side laps but many welded
As req’d = .098 x 40/70 = .056 in2/ft. est.
wire reinforcement manufacturers can pro-
wt. 36#/CSF
vide sheets with variable transverse wire
spacings and the length of end laps can be
WWR 16 x 16 - D6.5 x D6.5 with one
reduced even though wire sizes cannot.
D3.8 outside edge wire each side.
The length of splice for deformed welded
The two welded wire reinforcement styles
wire reinforcement is determined by the size
with 12” spacing for smooth wire and 16”
and spacing of the spliced wires, and only
spacing for deformed wire have been recent-
the outside cross wire is lapped. While the
ly developed to further improve the efficiency
lap length cannot be changed, the size of
of welded wire reinforcement. The larger
the outside cross wire can be reduced with-
wire spacings make it possible to install the
out changing the strength of the lap. ASTM
welded wire reinforcement at the desired
Specification A497 stipulates that the weld
location in the slab because it permits the
shear strength shall not be less than 35,000
workmen to stand in the openings and raise
times the area of the larger wire. These engi-
the welded wire reinforcement to place the
neered welded wire reinforcement styles are
supports.
not generally available for small foundation
slabs, but, when numerous small buildings
All welded wire reinforcement sheets must
or large slabs are being considered, it is
be spliced at both sides and ends to develop
prudent to check with welded wire reinforce-
the full design fy. For smooth welded wire
ment suppliers because substantial savings
reinforcement ACI 318-77 requires that the
in cost can often be accomplished. As with
two outside cross wires of each sheet be
rebar reinforcing, welded wire reinforcement
overlapped a minimum of 2 inches and the
must be chaired or supported on brick or
splice length equals one spacing plus 2 inch-
blocks to insure proper placement in the
es with a minimum length of 6 inches or 1.5
slab.
Id whichever is greater. For slabs on ground
TF 700-R-07 • Page 19
SPECIAL CONDITIONS
the additional top reinforcing be added 5. Other special conditions may arise from
as shown; otherwise the beam may be time to time but they are too numerous to
broken off. be covered here.
This 2500 PSI is a generally accepted fig- the bull floating, the final finishing should not
ure in the industry, since it has become an begin until bleed water has risen and evapo-
accepted figure for HUD/VA construction. rated, and the water sheen has disappeared
from the surface. At the time the concrete
In keeping the water cement ratio low, add shall be stiff enough to sustain a man’s foot
mixtures can be of particular benefit. This is pressure without indentation.
particularly true with respect to air entrain-
ment, retardants and accelerators. With regard to final finishing operations, the
accumulation and evaporation of bleed water
Calcium chloride is a common cold weather will vary considerably with weather conditions
additive to accelerate settling and hardening. and types of mixes. When bleed water is too
It should properly only be added to the mix in slow to evaporate, it may be pulled off with a
the mixing water. It is important to emphasize hose, or blotted with burlap. The surface of a
that calcium chloride is not to be used in a foundation should never be dried with what
foundation which is pre-stressed. The use is commonly called dusting. This is a method
of calcium chloride in foundations with rebar whereby dry cement and, sometimes, dry
reinforcing or welded wire reinforcing must cement and sand is placed on the slab to blot
be limited to a minimum of 2% by weight of the bleed water. This will cause a weak sur-
cement. face and, possibly, subsequent deterioration
of the surface.
Several operations need to completed before
beginning the placing of concrete. Screeds Immediately after the foundation has been fin-
should be set inside the form area to estab- ished, a curing compound should be placed
lish finished slab grade prior to beginning to inhibit further evaporation of water from
concrete placing. This will improve the level the concrete mix. This will tend to reduce
of the finished slab and eliminate much of the amount of shrinkage cracking which will
the unevenness of the slabs currently found. occur in the foundation.
Keys for joints may, on certain occasions,
be used as screeds, since they need to be When using a liquid curing membrane, it is
placed at proper intervals in large slabs to important to select a compound that will not
eliminate or control the shrinkage cracking. interfere with future bonding of floor finishes.
There are several such compounds on the
When the concrete is delivered it should be market.
placed as close as possible to its final posi-
tion in the foundation. It should be spread Forms should remain on the finished concrete
with short handle, square ended shovels and slab for a minimum of 24 hours. Removal prior
not by the use of rakes. Internal vibration at to that time can cause damage to the con-
the time of placing should be mandatory, as crete. After 24 hours the forms can be care-
this allows a stiffer mix to be used and facili- fully removed without damaging the concrete.
tates placing.
INSPECTION
The most general problem encountered was Cities should require adequate inspection,,
lack of suitable field inspection and control. If either by their own forces, or by the design
the foundations are not constructed in accord engineer who should, after all, be most famil-
with the design drawings and specifications, iar with his own design.
then benefits to be derived from improve-
ments in codes or the state of the art will be When the Engineer is not permitted to check
diminished.” 20 the construction, one of the other inspectors
should furnish a certificate to the Engineer
Before placing, the contractor should call for that the slab is properly installed in accor-
an inspection by some inspection agency. dance with the Engineer s plan. The following
For FHA-VA single family construction, this is is a partial list of points which should be veri-
handled by the FHA or VA. For non FHA/VA fied by the inspector.
houses it is, or should be, handled by the
city, but most cities, especially small ones, do
not have enough staff.
NOTATION
Ac = Gross Area of Concrete Cross-Section
Ass = Area of Steel Reinforcing in Slab
Asbb = Area of Steel Reinforcing in Bottom of Beam
Astb = Area of Steel Reinforcing in Top of Beam
a = Depth of Stress Block ( ult. strength)
bb = Width of Beam Portion of Cross-Section
bs = Width of Slab Portion of Cross-Section
B = Total Width of all Beams of Cross-Section
Cw = Climatic Rating
db = Depth of Beam Portion of Cross-Section
ds = Depth of Slab Portion of Cross-Section
E = Modulus of Elasticity of Concrete
Ec = Creep Modulus of Elasticity of Concrete
f’c = 28 Day Compressive Strength of Concrete
fy = Yield Strength of Reinforcing
Ig = Gross Moment of Inertia of Cross-Section
Io = Moment of Inertia of Segments of Slab Cross-Section
kI = Length Modification Factor-Long Direction
ks = Length Modification Factor-Short Direction
L = Total Length of Slab in Prime Direction
L’ = Total Length of Slab (width) Perpendicular to L
Lc = Design Cantilever Length (Ick)
Ic = Cantilever Length as Soil Function
MI = Design Moment in Long Direction in kft
Ms = Design Moment in Short Direction in kft
NI = Number of Beams in Long Direction
Ns = Number of Beams in Short Direction
PI = Plasticity Index
S = Maximum Spacing of Beams
V = Design Shear Force (Total)
v = Design Shear Stress (Unit)
vc = Permissible Concrete Shear Stress
w = Weight per sq. ft. of House and Slab
q allow = Allowable Soil Bearing
qu = Unconfined Compressive Strength of Soil
i-c = Soil/Climatic Rating Factor
allow = Allowable Deflection of Slab, in.
TF 700-R-07 • Appendix A-2
L’
DESIGN EXAMPLES
For comparison to BRAB Report #33, assume for a design example the same single story
residence located in San Antonio, Texas, which was used in BRAB Report #33.
Assume:
BL = 3 x 9 = 27”
Bs = 4 x 9 = 36” Geometry of house causes 5 beams Bs = 45
26”
1/2”
2”
9” 24” 32” 9” 32” 24” 9”
Using fy = 60,000
or using fy = 40,000
2”
For fy = 60,000
Assume: 6 - #4 bars As = 1.20
Mu = l.20 x 60 x (26’- 4”) / 12 = 132
M = 132 / 12 = 82.5 > 64
For fy = 40,000
6 x 6 W2.9 x W2.9
12 x 12 W4.5 x W4.5 (80kft) or
2# 4 BARS or
6 x 6 W2.9 x W2.9 (65kft)
2# 5 BARS
TOP EACH BEAM
4”
26”
# stirrups or
WW stirrups 2# 5 BARS or
2# 6 BARS
BOTTOM EACH BEAM
8” 8” 8”
TF 700-R-07 • Appendix B-5
For fy = 60,000
a= 2.00 x 60 = 0.235”
0.85 x 2.5 x 240
For fy = 40,000
a= 3.10 x 40 = 0.243”
0.85 x 2.5 x 240
TF 700-R-07 • Appendix B-6
Solve for steel in top of beams: Short direction slab steel same as long direction
For fy = 60,000
For fy = 40,000
SUMMARY:
2 #4 or 2 #5 bars bottom.
REFERENCES
12. Matlock, Hudson, “GRDBM 23, Random 18.” Structural Failures: Modes, Causes,
Direction Beam System Computer Responsibilities”, A Compilation of
Program”, unpublished class notes, The Papers Presented at the “ASCE National
University of Texas, Austin, Texas, 1965. Meeting on Structural Engineering”,
Cleveland, Ohio, April 1972.
14. Lytton, R.L. and Meyer, Kirby T., 20. Olson, Ray E., “A Study of Foundation
“Stiffened Mats on Expansive Clays”, Failures & Distress”, Report for National
Journal, Soil Mechanics and Foundation Bureau of Standards, Gaithersberg,
Division, ASCE Vo. 97, No. SM7, July Maryland, July, 1973.
1971.