The Use of Osterberg Cell Load Tests To Predict Piles Resistance
The Use of Osterberg Cell Load Tests To Predict Piles Resistance
The Use of Osterberg Cell Load Tests To Predict Piles Resistance
© 2013
2013 Taylor & Francis
Francis Group,
Group, London, ISBN 978-0-415-62136-
978-0-415-62136-6
6
1 INTRODUCTION
1773
2 CASE HISTORY 2.3 Main design and execution criteria
As main design criteria it was considered the need
2.1 Introduction
to avoid the executions of ground anchors below
The presented case history relates to the bored the ground water table, as well as the control of the
pile–raft foundation of a high rise building at the ground water inflow to the excavation pit. This cri-
Luanda bay, in Angola. The excavation works teria led to the development of a solution of periph-
comprised an area of about 1800 m2, with a rec- eral 0.60 m diaphragm walls, with 8 m of embedment
tangular shape of about 50 × 36 m2 and 10 m length. The walls were braced during the excavation
of overall depth, necessary for the construction works by a 3 m thickness horizontal jet grouting
of 3 underground floors and 26 upper floors sealing slab, located below the excavation final level.
(Fig. 3). Additional support of the diaphragm wall was pro-
vided by three levels of reinforced concrete bracing
slabs, acting as stiff diaphragms, located at the level
2.2 Geologic and geotechnical settings
of the basement floors, and cast against the ground
The geological and geotechnical conditions com- during the excavation works. Those slabs will become
prised high permeability sandy soils with the part of the basement structure. The jet grouting seal-
ground water table located about 1.5 m below the ing slab would also be used for limiting the ground
5 ground surface, and oscillating due to the influence water inflow through the excavation base. For the
1
0 of the tides at the Luanda bay. The sands resist- building structure foundations, 1 m diameter bored
2
e ance increased with depth, as assessed through piles with 20 to 30 m length were adopted, being
n several bore holes and in-situ SPT tests, as well as capped by a reinforced concrete raft with 0.6 to 2.0 m
u
J
6 through laboratorial identification tests from the thickness (Figs. 4 – 6). The piles were built before the
2 collected samples (Fig. 4). excavation works (Pinto & Pita (2011)).
1
5
:
9
0
t
a
]
a
i
l
a
r
t
s
u
A
s
r
e
e
n
i
g
n
E
[
y
b
d
e
d
a
o
l
n Figure 3. Building location and perspective.
Figure 5. Plan of the adopted bracing solution.
w
o
D
1774
The design of both, earth retaining and foun-
dations solutions, was performed using 2D FEM
programs (Plaxis V8 and SAP2000-V14).
1775
at the upward direction, and from 100 to 160 kPa 4 CONVENTIONAL STATIC TOP—
at the downward direction (sands with N SPT blows BOTTOM LOAD TEST
bigger than 60).
The tested pile behavior was calculated for a 4.1 Conventional static top—bottom load test
combined shaft and end bearing load of approx- The test device comprised one working pile with 1 m
imately 5.9MN (7.5 MPa). For a top loading of of diameter and a reaction system with two reaction
3.5MN, the adjusted test data indicated that the piles, with also 1 m of diameter, connected to a steel
pile would settle approximately 6.2 mm, of which beam, bridging a span of 8 m. At the top of each
2.8 mm was the estimated to be due to the addi- reaction pile four steel strands, sealed on the reaction
tional elastic compression (Figs. 2, 10 and 11). piles allowed the direct connection to the reaction
beams. The reaction system was designed to accom-
modate a load of about 4.8MN (Figs. 12 and 13).
3.2 W4 O-cell test remarks
Taking into account the previous four O-cell
The obtained results allowed for the confirma- tests, only the vertical head displacements of the
tion of both the suitability of the construction pile were monitored. The load was applied by a
method, as well as the assumptions for the design hydraulic jack and controlled by a load cell. The
shaft and end bearing resistance. It was possible to complete measurement system was divided in two
5 verify that the values of the shaft resistance were independent ones: the main system and the refer-
1 in accordance with the geological information ence measurement system. The measurement sys-
0
2 regarding the sandy materials, with bigger values, tems were fixed on the pile head as well as on the
e
n about 160 kPa, at the more compact sands. measure beams.
u
J
6
2
1
5
:
9
0
t
a
]
a
i
l
a
r
t
s
u
A
s
r
e
e
n
i
g
n
E
[
y
b
d
e
d
a Figure 10. O-cell test: Mobilized downward shaft Figure 12. Conventional top—bottom static test layout.
o
l resistance.
n
w
o
D
1776
A maximum load of approximately 4.8MN
(6.1 MPa) was achieved, corresponding to approx-
imately 1.5 times de working load. The main
results fulfilled the test requirements, confirming
also both the geological information and the O-cell
tests results.
For the service load and for the maximum load
of 4775 kN, the vertical displacement was about
6.1 and 12.6 mm, respectively, very similar to the
one obtained through the W4 O-cell test ( Fig. 14).
The test also confirmed that the creep was very
low for all the load stages, including the maximum
load at the 4th cycle. At this cycle the maximum
deformation was 0.47 mm in 7 hours, leading to a
rate of 0.067 mm/hour, much lesser than the creep
criteria of 0.25 mm/hour (Fig. 15). Figure 16. Comparison of results of the conventional
test and the O-cell static load test.
5 4.2 Conventional load test remarks
1
0
2 The obtained results allowed the confirmation
e maximum deformation value of 6.1 mm and 12.6 mm
n of the very good correlation between the conven-
u for the service load (3.5MN) and the 1.5 times the
J tional load test and the W4 O-cell test, mainly the
6 service load, respectively (Figs. 14 – 16).
2
1
5
:
9
0 5 ANALYTIC FEM MODEL
t
a
] An analytic model was used to predict the pile
a
i
l behavior. For this purpose an axisymmetric FEM
a
r
t model was used (Plaxis V8), with hardening soil
s
u failure criteria. The soil parameters were calibrated
A
s trough a back analysis (Fig. 17) in order to match
r
e the load tests results.
e
n
i The obtained displacement for the service load,
g about 6 mm, is compatible with the good per-
n
E
[ formance of the building structure under service
y conditions.
b
d It should also be pointed out the good correla-
e
d tion between the FEM analytic model and both the
a Figure 14. Conventional top—bottom static test:
o
l conventional top load test and the O-cell load test
n load—head displacement. (Fig. 18).
w
o
D
6 MAIN CONCLUSIONS
1777
Figure 17. FEM model and main geotechnical Figure 19. Comparison between the conventional and the
parameters. O-cell static load tests: Main advantages and limitations.
5
1
0
2
e
n
u
J
6
2
1
5
:
9
0
t
a
]
a
i
l
a
r
t
s
u
A
s
r Figure 18. Displacement—load curves: Analytical
e
e model, conventional top load test and O-cell test. Figure 20. View of the initial excavation works.
n
i
g
n
E
[ In this code the values of the partial safety factors on works, were concluded, allowing the beginning of
y
b the resistance side could be decreased in function of the excavation works (Fig. 20).
d the overall number of full scale load tests, leading to
e
d an optimization of the piles design.
a
o
l It should be stressed that the validation of the ACKNOWLEDGMENT
n
w pile design, enabled by the performed full scale
o load tests, allowed the measurement and validation The authors thank to the owners of the described
D
of the piles end bearing and shaft resistance, con- case history their permission for the presentation
firming the prediction of the building foundations of this paper.
good performance under service loads.
Finally it should be point out the versatility of the
O-cell load tests, with both economical and schedule REFERENCES
advantages, comparing with the conventional static
load tests (Fellenius (2001)). However, when neces- Fellenius, B.H. 2001. The O-cell—An Innovative Engi-
sary in more complex geological scenarios, as the neering Tool. Geotechnical News Magazine. Vol. 19.
one at the present case history, the O-cell load test Nº2. 32–33.
should be complemented and its results calibrated Pinto, A. & Pita, X. 2011. Deep Excavations in Luanda
City Centre. 15th African Regional Conference Confer-
by the execution of conventional top—bottom load
ence on Soil Mechanics and Geotechnical Engineering,
tests (Fig. 19), as well as through analytical FEM Session 5—Lateral Support and Retaining Structures:
back analysis, allowing the optimization of the piles 269–274. Maputo, Mozambique.
design and execution methods. Schmertmann, J.H. & Hayes, J.A. 1997. The Osterberg
In June 2012 all the foundations works, piles Cell and Bored Piled Testing. The Third Geotechnical
and jet grouting, as well as the diaphragm walls Engineering Conference, Cairo University, Egypt.
1778