Sample Website Project Charter

This document authorizes a project to consolidate multiple agency websites into a single site. It outlines the project scope, goals to improve customer experience and save costs, budget of $amount, and tight deadline. The project manager is tasked with developing a detailed plan, monitoring progress, and addressing risks like limited resources and content migration.

Uploaded by

ljv ljv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
237 views4 pages

Sample Website Project Charter

This document authorizes a project to consolidate multiple agency websites into a single site. It outlines the project scope, goals to improve customer experience and save costs, budget of $amount, and tight deadline. The project manager is tasked with developing a detailed plan, monitoring progress, and addressing risks like limited resources and content migration.

Uploaded by

ljv ljv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Website Consolidation Project

Charter

Agency

Office

Date
OFFICE OF XYZ

Authorization

This Charter formally authorizes a project to develop a [consolidated web presence] for
[XYZ] lines of business in the Office. A Project Plan will be developed and submitted to the
Project Sponsor for approval. Project activities will begin once the Project Plan and the
resources to execute it are approved by the Project Sponsor.

To be included in the Project Plan:

 Scope;
 Schedule;
 Cost estimate;
 Budget; and
 Provisions for project control and management of scope, resources, quality, risk,
schedule, stakeholder communications, and procurement.

Purpose / Mission

The purpose of the Project is to consolidate [XYZ] websites into one site.

This project meets the following business needs:

 Provide customers … ;
 Improve the agency’s ability to … ;
 Save … ;
 Increase … ; and
 Etc.

Scope

The [websites] included in this project are:

 abc.gov
 xyz.gov
 etc.

This [consolidation] project involves [XYZ pages of content].

Design Principles

The [consolidated website] will have the following attributes, features or functionality:

 Written in plain language, with a consistent editorial tone throughout;


 Integrates current websites into a common look and feel:
o Common design templates
o Highly sophisticated search across all sites
o Global navigation
o Easy to find/move from one topic/service to another
o Uses a consistent common terminology/data dictionary
 Leads the visitor to [guidance, requirements, tools and training] to [implement XYZ];
 Easy to use – usability-tested and test results incorporated into design;
OFFICE OF XYZ

 Uses an open-source content management system, or other systems and platforms


already supported by the agency;
 Is Section 508 and WCAG 2.0 priority AA-compliant and accessible;
 Secure, vulnerability free;
 Uses “open” templates that the agency can modify if needed;
 Has ability to change/expand as new content/services are created;
 Incorporates social tools such as blogging, tagging, and integration with third-party
social networks;
 Follows OMB policies for federal public websites.

Project Management

The Project Manager, [Name], is hereby authorized to interface with management,


negotiate for resources, delegate responsibilities within the framework of the project, and
communicate with all contractors and management, as required, to ensure successful and
timely completion of the project. The Project Manager is responsible for developing the
project plan, monitoring the schedule, cost, and scope of the project during implementation,
and maintaining project control by measuring performance and taking corrective action.

Project Schedule

A completed project plan will be developed and submitted to the Project Sponsor for
approval by [date]. Upon approval of this plan, resources will be assigned to the project,
and work will commence within 3 business days. Work will be performed according to the
approved project plan schedule. The Project Manager will obtain approval from the Project
Sponsor for any schedule changes which might impact project completion.

Budget

The budget for the Project is [$amount]. It will be funded from [funding source].

Requirements

This project must meet the following requirements in order to achieve success – it must be:

 Tested in the staging environment prior to deployment;


 Usability and 508 tested to agency standards; and
 Implemented without disruption to operations.

Additional requirements may be added as necessary, with project sponsor approval, as the
project moves forward.

Constraints

The following constraints pertain to the Project:

 The project deadline is extremely tight;


 Existing resources are stretched very thin;
 All software must be compatible with our current IT platforms;
 New or redesigned components include, but are not limited to, HTML templates and
CSS style sheets, which must use existing infrastructure for content push, hosting;
OFFICE OF XYZ

 A minimum of [#] HTML and CSS developers who are familiar with [open-source
tool] workflow will be required for application development associated with
implementation of the new design and style sheets; and
 The new website must be integrated with the existing web analytics tool [e.g., GA or
WebTrends] and enterprise search capability [USAsearch].

Assumptions

The following are a list of assumptions. Upon agreement and signature of this document, all
parties acknowledge that these assumptions are true and correct:

 This project has the full support of the project sponsor, stakeholders, and all
divisions;
 The [IT Division] is authorized to contract for additional resources;
 Funding for resources is available; and
 Knowledge of existing websites’ site maps and content management models must be
successfully transferred to the developers prior to the implementation phase.

Risks

The following risks for the Project have been identified. The project manager will determine
and employ risk mitigation/avoidance strategies as appropriate to minimize the likelihood of
these risks:

 Existing resources are stretched thin, particularly in the [IT Division], where
development resources are needed to implement design solutions;
 [Current .gov site] has a very strong brand and is widely recognized as a model
throughout government. Re-branding the website, and integrating additional content
without losing the current focus and loyal customer base will be tricky;
 The amount of content that needs to be migrated may cause schedule challenges for
the launch date;
 The roles and responsibilities of [content and tech teams] are not yet fully defined;
 Resources for [508 testing; long-term project support, etc.] have not yet been
identified;
 The number of stakeholders involved adds to the degree and complexity of project
management required to reach consensus on project steps; and
 Additional contracting may be needed to properly resource development activities.

Sponsor Acceptance

Approved by the Project Sponsor:

______________________________________ Date:
Name
Title