0% found this document useful (0 votes)
398 views1 page

Work Inspection Request

This document is a request for MEP clearance inspection for ceiling works in the first floor bedroom 3 of the JARALLAH villa project located in RAYYAN. (2) The inspection is to check mechanical works including highlighted PPR pipes, valves, and a water hammer arrester, as well as a GI duct with riser connection. (3) The electrical works to be inspected include installations for a wifi point, curtain control, lighting control, and a lighting system.

Uploaded by

Mohammed Javid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
398 views1 page

Work Inspection Request

This document is a request for MEP clearance inspection for ceiling works in the first floor bedroom 3 of the JARALLAH villa project located in RAYYAN. (2) The inspection is to check mechanical works including highlighted PPR pipes, valves, and a water hammer arrester, as well as a GI duct with riser connection. (3) The electrical works to be inspected include installations for a wifi point, curtain control, lighting control, and a lighting system.

Uploaded by

Mohammed Javid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Name: Code: Location:

JARALLAH RAYYAN
MEP CLEARANCE
Ref. No: LCC-MEP-CLRNC-001 Rev. 0 Date: 15/09/2021
Contractor: CANADIAN BUILDING & CONSTRUCTIONS Consultant: AL FEREEJ CONSULTANCY & DESIGNS
Sub-Contractor: LEAD COOLING & CONTRACTING
LOCATION:VILLA LEVEL: FF Area/Grid Lines: As per Highlighted
Architechtura
Discipline: Structural ✘ MEP Others
l

Shop Drawing Ref: __________As per attached____________ Method Statement _ Material Submittal__________________ Others: _______________________

WORK TO BE INSPECTED:
MEP CLEARANCE PRIOR TO CEILING WORKS (FF BEDROOM 3)

MECHANICAL WIR Ref.No ELECTRICAL WIR Ref.No


LCC-MECH-WIR-018 (Highlighted PPR Pipes with riser connection, valves & water
hammer arrester at Ff mock up bathroom 03B) LCC-ELEC-WIR-018 (Installation for wifi point at Mockup first floor
bedroom 3)

LCC-MECH-WIR-019 (GI Duct with Riser Connection at FF mockup bedroom 03) LCC-ELEC-WIR-017 Installation for Curtain control at Mockup first
floor bedroom 3

LCC-ELEC-WIR-020 Installation for lighting control at Mockup first


floor bedroom 3
LCC-ELEC-WIR-019 Installation of lighting system at Mockup first
floor bedroom 3

✘ Mechanical Fire Fighting Name/Sign: Javid Remarks:

Con/Sub-contractor: Lead Cooling Contracting


✘ Electrical ✘ Plumbing
Date:30/06/2021
Safety Clearance: Name & Sign: Date: Consultant:

Requested by Engineer: Javid Date: 15/09/2021 Time: Received By:


We hereby confirm that the works have been internally inspected and are in accordance with approved drawings and specifications issued for construction.

CONSULTANTS RESPONSE

A-
Approved C - Resubmit
A - Approved with
D - Not approved
comments

Name: Signature: Date & Time: