Electricity (Network Safety) Regulations 2015 - (00-E0-01)
Electricity (Network Safety) Regulations 2015 - (00-E0-01)
Electricity (Network Safety) Regulations 2015 - (00-E0-01)
Contents
Part 1 — Preliminary
1. Citation 1
2. Commencement 1
3. Terms used 1
4. Network operators 4
5. Persons for whom a network operator or contractor
is responsible 6
Part 2 — Network safety
Division 1 — General safety requirements
6. Duty of network operator to manage prescribed
activities 8
7. Duty of contractor to manage prescribed activities 9
8. Duty of persons carrying out prescribed activities 10
9. Duties relating to certain risks to safety 10
Division 2 — Certain network operators
required to have safety management
systems
10. Network operators to whom this Division applies 11
11. When this Division commences to apply to a
network operator 12
12. Transfer of operation of network 13
13. Requirement to have safety management system 14
14. Requirement to revise safety management system 14
15. Requirement to comply with safety management
system 15
16. Compliance with safety management system
evidence of compliance with regulation 6 or 7 16
Contents
Contents
Contents
Part 1 — Preliminary
1. Citation
These regulations are the Electricity (Network Safety)
Regulations 2015.
2. Commencement
These regulations come into operation as follows —
(a) regulations 1 and 2 — on the day on which these
regulations are published in the Gazette;
(b) the rest of the regulations — on the day after that day.
3. Terms used
(1) In these regulations, unless the contrary intention appears —
AS followed by a designation consisting of a number and a
reference to a year refers to the text, as from time to time
amended and for the time being in force, of the document so
designated, published by Standards Australia;
AS 5577 means AS 5577-2013 Electricity network safety
management systems;
AS/NZS followed by a designation consisting of a number and a
reference to a year refers to the text, as from time to time
amended and for the time being in force, of the document so
designated, jointly published by Standards Australia and
Standards New Zealand;
r. 3
r. 3
r. 4
r. 4
r. 5
(2) For the purposes of subregulation (1)(e), the Robe River Joint
Venture participants are —
(a) Mitsui Iron Ore Development Pty Ltd
(ACN 008 734 361);
(b) Nippon Steel & Sumikin Resources Australia Pty. Ltd.
(ACN 001 444 604);
(c) Nippon Steel & Sumitomo Metal Australia Pty Ltd
(ACN 001 445 049);
(d) North Mining Limited (ACN 000 081 434);
(e) Robe River Mining Co. Pty. Ltd. (ACN 008 694 246).
(3) For the purposes of subregulation (1)(g), the Newman Joint
Venture participants are —
(a) BHP Billiton Minerals Pty Ltd (ACN 008 694 782);
(b) Mitsui-Itochu Iron Pty Ltd (ACN 008 702 761);
(c) Itochu Minerals & Energy of Australia Pty Ltd
(ACN 009 256 259).
[Regulation 4 amended: Gazette 1 Aug 2017 p. 4110.]
r. 5
(c) the Director has not, within 5 working days after the day
on which the Director was notified, prohibited the
testing.
(2) If a network operator proposes to carry out destructive testing of
particular physical evidence to which regulation 23(3) applies,
the Director may nominate a person to witness the testing.
(3) The network operator must permit a person nominated under
subregulation (2) to witness the testing.
Penalty: a fine of $250 000.
(5) The network operator must ensure that the statement remains
published on a website maintained by the network operator for
4 years.
Penalty: a fine of $250 000.
(6) For a network operator that is a network operator on the day on
which this regulation comes into operation, subregulations (1)
and (2) are modified so that the first statement under
subregulation (1) must —
(a) be given and published before 1 October 2015; and
(b) cover the financial year commencing on 1 July 2015 and
the next 2 financial years.
r. 34
r. 36
r. 36
(d) set out any submissions that the person wishes to make
in relation to the review.
(3) If a request for review is made under subregulation (1)(b), the
CEO must convene a technical review panel unless satisfied that
the request is frivolous or vexatious.
(4) The State Administrative Tribunal or the technical review panel
(whichever is relevant) may suspend the operation or effect of
the decision until the determination of the review.
(5) If the decision is sent back to the Director under the State
Administrative Tribunal Act 2004 section 29(3)(c)(ii) for
reconsideration —
(a) the Director must make a new decision, in accordance
with any directions or recommendations of the State
Administrative Tribunal, within 20 working days after
the day on which the Director receives notice of the
Tribunal’s determination; and
(b) the new decision is not subject to review under
regulation 35; and
(c) the State Administrative Tribunal Act 2004 section 29(4)
does not apply in relation to the new decision.
(6) On a review under subregulation (1)(b), the technical review
panel may determine the review by confirming, varying or
cancelling the decision, and the determination of the panel is
final.
(7) If the technical review panel cancels the decision, the Director
may make a new decision, in accordance with the panel’s
determination, within 20 working days after the day on which
the Director receives notice of the panel’s determination, and
the new decision is not subject to review under regulation 35.
r. 37
r. 39
r. 40
Part 5 — Miscellaneous
40. Defence for certain network operators
(1) Subregulation (2) applies in relation to the companies listed in
regulation 4(2) (that is, the Robe River Joint Venture
participants).
(2) If one of the companies is charged with an offence constituted
by a breach of an obligation under these regulations (other than
regulation 41), it is a defence to prove that another of the
companies complied with that obligation.
(3) Subregulation (4) applies in relation to the companies listed in
regulation 4(3) (that is, the Newman Joint Venture participants).
(4) If one of the companies is charged with an offence constituted
by a breach of an obligation under these regulations (other than
regulation 41), it is a defence to prove that another of the
companies complied with that obligation.
r. 41
(c) setting out the person’s ACN (or equivalent) and contact
details; and
(d) listing all related bodies corporate.
Penalty: a fine of $250 000.
(3) A person who is to become the network operator of particular
transmission or distribution works after the day on which this
regulation comes into operation must, at least 30 working days
before the day on which the person will become the network
operator of those works, give the Director a notice —
(a) stating that the person is to become the network operator
of those works; and
(b) setting out the day on which that is to occur; and
(c) setting out the person’s ACN (or equivalent) and contact
details; and
(d) listing all related bodies corporate.
Penalty: a fine of $250 000.
(4) A network operator who is to cease to be an operator of
particular transmission or distribution works must, at least
30 working days before the day on which the network operator
ceases to be the operator of the works, give the Director a
notice —
(a) stating that the person will cease to be the operator of
the works; and
(b) setting out the day on which that is to occur.
Penalty: a fine of $250 000.
(5) If there is a change in the name or contact details of a network
operator, the network operator must, within 10 working days
after the day on which the change occurs, give the Director a
notice setting out the new name or contact details.
Penalty: a fine of $250 000.
r. 41
an
Division 1 — General
Code of Practice, Safe Low Voltage Work Practices by Electricians, issued by
the Director in April 2008, as from time to time amended and for the time being
in force.
Utility Providers Code of Practice for Western Australia, produced by the
Utility Providers Services Committee and applicable from 1 February 2010, as
from time to time amended and for the time being in force.
WA Electrical Requirements, published by the Director in January 2014, as
from time to time amended and for the time being in force.
AS 1824.1-1995 Insulation coordination — Definitions, principles and rules.
AS 1824.2-1985 Insulation coordination (phase-to-earth and phase-to-phase,
above 1 kV) — Application guide.
AS 2676.1-1992 Guide to the installation, maintenance, testing and replacement
of secondary batteries in buildings — Vented cells.
AS 2676.2-1992 Guide to the installation, maintenance, testing and replacement
of secondary batteries in buildings — Sealed cells.
AS 5577-2013 Electricity network safety management systems.
AS/NZS 3000:2018 Electrical installations (known as the Australian/New
Zealand Wiring Rules).
AS/NZS 3013:2005 Electrical installations — Classification of the fire and
mechanical performance of wiring system elements.
AS/NZS 3100:2009 Approval and test specification — General requirements
for electrical equipment.
AS 3865-1991 Calculation of the effects of short-circuit currents.
AS/NZS 3931:1998 Risk analysis of technological systems — Application
guide.
Division 1 — General
AS 1882-2002 Earth and bonding clamps.
AS 1931.1-1996 High-voltage test techniques — General definitions and test
requirements.
AS 2067-2008 Substations and high voltage installations exceeding 1 kV a.c.
AS 3011.1-1992 Electrical installations — Secondary batteries installed in
buildings — Vented cells.
AS 3011.2-1992 Electrical installations — Secondary batteries installed in
buildings — Sealed cells.
AS 3851-1991 The calculation of short-circuit currents in three-phase
a.c. systems.
AS/NZS 3863:2002 Galvanised mild steel wire for armouring cables.
AS 4741-2010 Testing of connections to low voltage electricity networks.
AS 4836:2011 Safe working on or near low-voltage electrical installations and
equipment.
AS 60529-2004 Degrees of protection provided by enclosures (IP Code).
ENA Doc 025-2010 EG-0 Power system earthing guide — Part 1: management
principles, version 1.
ENA NENS 03-2006 National guidelines for safe access to electrical and
mechanical apparatus.
ENA NENS 04-2006 National guidelines for safe approach distances to
electrical and mechanical apparatus.
ENA NENS 05-2006 National fall protection guidelines for the electricity
industry.
ENA NENS 07-2006 National guidelines for manual reclosing of high voltage
electrical apparatus following a fault operation (Manual Reclose Guidelines).
ENA NENS 08-2006 National guidelines for aerial surveillance of overhead
electricity networks.
ENA NENS 09-2006 National guidelines for the selection, use and maintenance
of personal protective equipment for electrical hazards.
ENA NENS 10-2005 National Guidelines for Contractor Occupational Health
and Safety Management.
Notes
1
This is a compilation of the Electricity (Network Safety) Regulations 2015 and
includes the amendments made by the other written laws referred to in the
following table.
Compilation table
Citation Gazettal Commencement
Electricity (Network Safety) 5 Aug 2015 r. 1 and 2: 5 Aug 2015
Regulations 2015 p. 3141-96 (see r. 2(a));
Regulations other than r. 1 and 2:
6 Aug 2015 (see r. 2(b))
Electricity (Network Safety) 1 Aug 2017 r. 1 and 2: 1 Aug 2017
Amendment Regulations 2017 p. 4110-12 (see r. 2(a));
Regulations other than r. 1 and 2:
1 Nov 2017 (see r. 2(b))
Electricity Amendment 2 Oct 2018 1 Jan 2019 (see r. 2(b))
Regulations 2018 Pt. 4 p. 3784-94
Defined terms
Defined terms
[This is a list of terms defined and the provisions where they are defined.
The list is not part of the law.]
Defined term Provision(s)
applicable standard ............................................................................................. 28
AS .................................................................................................................... 3(1)
AS 2067 .............................................................................................................. 28
AS 5577 ........................................................................................................... 3(1)
AS/NZS............................................................................................................ 3(1)
AS/NZS 3000...................................................................................................... 28
AS/NZS 7000...................................................................................................... 28
CEO ................................................................................................................. 3(1)
commencement day ............................................................................................ 45
conductor ............................................................................................................ 28
contact ................................................................................................................. 22
contact details ................................................................................................ 41(1)
contractor ......................................................................................................... 3(1)
distribution licence ........................................................................................... 3(1)
electricity inspector .......................................................................................... 3(1)
employee .......................................................................................................... 3(1)
ENA ................................................................................................................. 3(1)
evidentiary provision ..................................................................................... 17(1)
good work practice.............................................................................................. 22
HB .................................................................................................................... 3(1)
implementation day, for a network operator, ................................................... 3(1)
integrated regional licence ............................................................................... 3(1)
investigate ........................................................................................................ 9(1)
network ............................................................................................................ 3(1)
network operator .............................................................................................. 3(1)
network safety performance incident ....................................................... 28, 30(1)
notifiable incident ............................................................................................... 22
obligatory provision ....................................................................................... 17(1)
pole .................................................................................................................. 3(1)
prescribed activity ............................................................................................ 3(1)
prior network operator ................................................................................... 12(1)
protective device ................................................................................................ 22
quarter .............................................................................................................. 3(1)
repealed regulations ............................................................................................ 45
risk to safety ..................................................................................................... 9(1)
safety ................................................................................................................ 3(1)
safety management system .............................................................................. 3(1)
subcontractor.................................................................................................... 3(1)
third party............................................................................................................ 22
transmission licence ......................................................................................... 3(1)
Defined terms
unassisted failure................................................................................................. 28
working day ..................................................................................................... 3(1)