RREIS CY 2017-HHIS Revised (Actual Cost) 2
RREIS CY 2017-HHIS Revised (Actual Cost) 2
RREIS CY 2017-HHIS Revised (Actual Cost) 2
REGION/PMO : REGION 8
PROJECT TITLE : RRENIS - 2017
SYSTEMS CATEGORY : HHIS
( NIS/CIS, NIP/SIP )
PROJECT DESCRIPTION : Construction of Canal Lining, Check Structures & Fab./Inst of Steelgates
I. GENERAL INFORMATION
1. Project Location 6. Overall Project Cost
a. Region VIII a. Peso Counterpart (PM)
b. Municipality Hindang b. Loan Procceds (PM)
c. Province Leyte c. Others (Equity)
Total
2. Service Area
a. New Area 7. Physical Target
b. Rehab Area 351 Has a. New Area
c. Restored b. Restored Area
3. Source of Water Salog River c. Repair Works: (specify for rehab)
c.1. Earth Canal (km.)
4. Type of Irrigation 5. PT of Diversion c.2. Lined Canal (km.)
( Pls. check the type of irrigation) Latitude Longitude c.3. Structures (units)
a. Run-off the River c.4. Fab./Inst. Of Steelgates (pcs)
b. Reservoir c.5. Concrete Service Road (km)
c. Groundwater Pump c.6. PCCP Pavement Plain (km)
c.7. Other Repair Works (Repair of Diversion Dam
c.8. Rehab Area ha (attribution)
d. Other Activities (Pls. specify)
8. Overall Implementation Period
a. Physical Starting Date
b. Completion Date
Original Revised
2,599,977.60
2,599,977.60
0.775
1
Steelgates (pcs)
Original Revised
: February 15, 2017
: Nov. 30, 2017
feb
sept 30
ROGELIO F. BALLESTEROS oct 31
Engineering Assistant A nov 30
dec
Submitted By : 288
Recommending Approval :
ESTRELITA SUMILE
Acting Division Manager - EOD
APPROVED :
FERMINA B. ALING
Acting Regional Manager
Republika ng Pilipinas
Pambansang Pangasiwaan ng Patubig
(NATIONAL IRRIGATION ADMINISTRATION)
HINDANG-HILONGOS IRRIGATION SYSTEM (HHIS), HINDANG, LEYTE
SUMMARY OF CY 2017 PROGRAM OF WORK (POW)
REGION/PMO : REGION 8
PROJECT TITLE : RRENIS - 2017
SYSTEMS CATEGORY : HHIS
( NIS/CIS, NIP/SIP )
PROJECT DESCRIPTION : Construction of Canal Lining, Check Structures & Fab./Inst of Steelgates
I. GENERAL INFORMATION
1. Project Location 6. Overall Project Cost
a. Region VIII a. Peso Counterpart (PM)
b. Municipality Hilongos b. Loan Procceds (PM)
c. Province Leyte c. Others (Equity)
Total
2. Service Area
a. New Area 7. Physical Target
b. Rehab Area 370 has a. New Area
c. Restored b. Restored Area
3. Source of Water Salog River c. Repair Works: (specify for rehab)
c.1. Earth Canal (km.)
4. Type of Irrigation 5. PT of Diversion c.2. Lined Canal (km.)
( Pls. check the type of irrigation) Latitude Longitude c.3. Structures (units)
a. Run-off the River c.4. Fab./Inst. Of Steelgates (pcs)
b. Reservoir c.5. Concrete Service Road (km)
c. Groundwater Pump c.6. PCCP Pavement Plain (km)
c.7. Other Repair Works (Repair of Diversion D
c.8. Rehab Area ha (attribution)
d. Other Activities (Pls. specify)
8. Overall Implementation Period
a. Physical Starting Date
b. Completion Date
9. CONTINGENCIES - -
TOTAL FOR HILONGOS, LEYTE 2,400,000.01 2,400,000.01
TOTAL DIRECT COST 2400000.01 2400000.01
2. LOAN PROCEEDS
Attachment "A"
Program No.: 1
Date : November 8,2016
2,400,000.01
feb
Earth Canal (km.)
Construction of Canal Lining (km.) 0.828
Structures (units)
Fab./Inst. Of Steelgates (pcs)
Concrete Service Road (km)
PCCP Pavement Plain (km)
Other Repair Works (Repair of Diversion Works)
Rehab Area ha (attribution) Jan
r Activities (Pls. specify) Feb 13
mar 31
apr 30
Prepared by : may 31
jun 30
jul 31
aug 31
sept 30
ROGELIO F. BALLESTEROS oct 31
Engineering Assistant A nov 30
dec
Submitted By : 288
Recommending Approval :
ESTELITA S. SUMILE
Acting Division Manager - EOD
APPROVED :
NOTED :
FERMINA B. ALING
Acting Regional Manager
NATIONAL IRRIGATION ADMINISTRATION
BITO RIS, Abuyog, Leyte
DETAILED BREAKDOWN OF FY-2017 PROGRAM OF WORKS
REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM, FY-2017,(TIER-2)
Attachment "D"
WORK TO BE DONE
ACTIVITY Unit Quantity Unit Cost Estimated Cost
A. DIRECT COST
I Contract works
1 CIVIL WORKS
1.a. ABUYOG, LEYTE
1.a.a CANAL SYSTEM
Supplementary Farmditch and Lateral Canal
Clearing an sq.m. - 7.59 -
Structure E cu.m. - 170.63 -
170 kscm Re cu.m. - 9,732.19 -
RSB
Furnishing kls - 73.24 -
Cutting and kls - 13.45 -
Structure ba cu.m. 175.00 1,157.21 202,511.75
Sub-total 202,511.75
1.a.b CHECK STRUCTURE/ULHAY CHECKGATES
Clearing an cu.m. 1,509.44 7.59 11,456.65
Structure E cu.m. - 195.00 -
Diversion an cu.m. - 210.00 -
170 kscm Pl cu.m. - 6,576.07 -
211 kscm Re cu.m. - 10,425.35 -
RSB -
Furnishing kgs - 73.24 -
Cut, Bend,a kgs - 13.45 -
Rubble Mas cu.m. - 5,960.21 -
RCP. 18" Di pcs. - 894.92 -
Sluicegates pcs. - 93,164.20 -
Intakegates pcs. - 72,035.71 -
Structure ba cu.m. 69.20 1,157.21 80,078.93
Sub-total 91,535.58
1.a.c FABRICATION/INSTALLATION OF STEEL GATES
Fabrication/ pcs. 4.00 72,035.71 288,142.84
Sub-total 288,142.84
Sub total Direct cost Abuyog, Leyte 582,190.17
INSTITUTIONAL DEVELOPMENT PROGRAM (1% of Direct Cost) 5,821.90
CONSTRUCTION SURVEY (1% of Direct Cost) 5,821.90
FSSM (3% of Direct Cost) 17,465.71
TOTAL COST FOR ABUYOG, LEYT 611,299.68
1.b. JAVIER, LEYTE
1.b.a CANAL SYSTEM
Supplementary Farmditch and Lateral Canal
Clearing an sq.m. - 7.59 -
Structure E cu.m. - 170.63 -
170 kscm Re cu.m. - 9,732.19 -
RSB
Furnishing kls - 73.24 -
Cutting and kls - 13.45 -
Structure ba cu.m. 145.00 1,157.21 167,795.45
Sub-total 167,795.45
1.a.c FABRICATION/INSTALLATION OF STEEL GATES
Fabrication/ pcs 5.00 72,035.71 360,178.55
Sub-total 360,178.55
Sub total Direct cost Abuyog, Leyte 527,974.00
INSTITUTIONAL DEVELOPMENT PROGRAM (1% of Direct Cost) 5,279.74
CONSTRUCTION SURVEY (1% of Direct Cost) 5,279.74
FSSM (3% of Direct Cost) 15,839.22
TOTAL COST FOR ABUYOG, LEYT 554,372.70
TOTAL CIVIL WORK, (Abuyog & Javier) 1,110,164.17
TOTAL Contract Work
FORCE ACCOUNT WORKS
1 CIVIL WORKS
2 INSTITUTIONAL DEVELOPMENT PROGRAM (1% of Direct Cost) 11,101.64
3 CONSTRUCTION SURVEY (1% of Direct Cost) 11,101.64
4 PARCELLARY SURVEY (1% of Direct Cost)
SUB - TOTAL FORCE ACCOUNT WORKS
III. RIGHT OF WAY ACQUISITION / DAMAGES
1. LAND ACQUISITION
2. PLANT DAMAGE
3. PROPERTY DAMAGES
SUB - TOTAL (R.O.W.)
IV. PROCUREMENT OF EQUIPMENT & VEHICLES
V. FSSM (3% of Direct Cost) 33,304.93
VI. CONSULTING SERVICES
VII. TAXES (for selected FAPs)
9. CONTINGENCIES
Physical Contingencies
Financial Contingencies
VIII. CONTINGENCIES
B. INDIRECT COST
I. MANAGEMENT FEE (5%
TOTAL INDIRECT COST 1,165,672.38
GRAND TOTAL 1,165,672.38
Prepared By: Submitted By:
11,456.65 ###
-
-
-
-
-
-
-
-
-
-
-
80,078.93 226.51 200.51
91,535.58 ###
243.23
###
258.28
###
###
###
#REF! #REF!
#REF!
#REF! ### 1,044.94
### ###
###
### ### ###
23.13
### ### ### ###
###
8.46 ### ###
59.10 ### ###
10.28 1,656.71
###
km. Err:508 - Err:508
km. Err:508 - Err:508
km. Err:508 - Err:508
km. Err:508 - Err:508
CMD FORM Y-2A HHIS HINDANG, LEYTE
FY 2017 SCHEDULE EXPENDITURES AND STATUS FY-2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
I. CONTRACT WORKS
Projected - 84,133.44 126,200.16 210,333.60 841,334.38 631,000.79 631,000.79 420,667.19 631,000.79 420,667.19 210,333.60
A. CANAL SYSTEM 4206671.91 84.133438 Actual 100
Projected 108,216.88 216,433.76 162,325.32 54,108.44
B. CHECK STRUCTUTURES 541084.39 10.821688 Actual 90
Projected - - - -
Actual 80
Projected - - - -
Actual 70
Projected 2,834.18 5,668.35 4,251.26 1,417.09
II FORCE ACCOUNT WORKS 14170.88 0.2834176 Actual - - - - - 60
Projected 11,904.76 23,809.53 11,904.76
A. INSTITUTIONAL DEVELOPMENT PRO 47619.05 0.952381 Actual - - - - - - 50
Projected 11,904.76 23,809.53 11,904.76
B. CONSTRUCTION SURVEY 47619.05 0.952381 Actual - - - - - 40
Projected 9,998.43 25,710.25 35,708.68 35,708.68 25,710.25 9,998.43
III. FSSM 142834.72 2.8566944 Actual - - - - - 30
- Projected - - - - - - -
IV. CONTENGENCY 0 Actual 20
Projected
Actual 10
Projected 0.676159 3.149255 3.7143672 9.2495208 20.587399 13.9021532 12.6200158 8.4133438 12.6200158 8.4133438 4.206672 0
5000000 100.00 Actual
Projected 33,807.95 157,462.75 293,935.24 462,476.04 1,029,369.95 695,107.66 631,000.79 420,667.19 631,000.79 420,667.19 210,333.60 -
CY FINANCIAL STATUS
Republika ng Pilipinas
Pambansang Pangasiwaan ng Patubig
(NATIONAL IRRIGATION ADMINISTRATION)
HINDANG-HILONGOS IRRIGATION SYSTEM (HHIS), HINDANG, LEYTE
SUMMARY OF CY 2017 PROGRAM OF WORK (POW)
Attachment "A"
REGION/PMO : REGION 8 Program No.: 1
PROJECT TITLE : RRENIS - 2017 Date : July 31, ,2018
SYSTEMS CATEGORY : HINDANG - HILONGOS IS
( NIS/CIS, NIP/SIP )
PROJECT DESCRIPTION : Construction of Canal Lining, Check Structures & Fab./Inst of Steelgates
I. GENERAL INFORMATION
1. Project Location 6. Overall Project Cost Original Revised
a. Region VIII a. Peso Counterpart (PM) 5,000,000.00 1.00
b. Municipality Hindang & Hilongos b. Loan Procceds (PM)
c. Province Leyte c. Others (Equity)
Total 5,000,000.00
2. Service Area
a. New Area 7. Physical Target
b. Rehab Area 710 a. New Area
c. Restored b. Restored Area
3. Source of Water Salog River c. Repair Works: (specify for rehab)
c.1. Earth Canal (km.)
4. Type of Irrigation 5. PT of Diversion c.2. Lined Canal (km.) 1.60
( Pls. check the type of irrigation) Latitude Longitude c.3. Structures (units) 1
a. Run-off the River c.4. Fab./Inst. Of Steelgates (pcs)
b. Reservoir c.5. Concrete Service Road (km)
c. Groundwater Pump c.6. PCCP Pavement Plain (km)
c.7. Other Repair Works (Repair of Diversion Dam)
c.8. Rehab Area ha (attribution)
d. Other Activities (Pls. specify)
8. Overall Implementation Period Original Revised
a. Physical Starting Date : February 15, 2017
b. Completion Date : Nov. 30, 2017
5,000,000.00
5,000,000.00
0
feb
Jan
Feb
mar 13
31
apr 30
may 31
jun 30
jul 31
aug 31
oct 31
nov 30
dec
I. CONTRACT WORKS
Projected - 2.00 5.00 10.00 30.00 45.00 60.00 70.00 85.00 95.00 100.00
Projected
Actual 70
Projected
II FORCE ACCOUNT WORKS Actual 60
Projected 25.00 75.00 100.00 100.00 100.00 100.00
Projected 0.67808091 3.83628658 9.73170002 19.0075099 39.6534231 53.5950893 50.623539 59.0607954 71.7166802 80.1539367 84.3725649 0
CY PHYSICAL STATUS 4985829.12 100 Actual
NEW AREA Projected
(Has.) Actual
REHAB RESTORED Projected
AREA GENERATION 100 (Has.) (Has.) Actual
MASTERLIST OF WORK TO BE DONE
HINDANG-HILONGOS IRRIGATION SYSTEM
REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM FY-2017
Structure
Backfill w/
Resto Rehab
Compactio
n (HB)
cu.m. ha. ha.
40 5
35 8
48 7
16 5 71.5 #REF!
139 25
59 8 67.5
90 12
75 9
52 9
65.76 11
341.76 49
880.08 2 12 599.73 1 1 15
880.08 2.00 12.00 599.73 1 1 0 15.00
MASTERLIST OF ACTIVITIES
Clearing
STATION Structure Str. Backfill 211 KGSC
Length & Concrete
PARTICULARS Grubbing Desilting Demolitio Excavation w/ Plain
(cu.m.)/ Manual Compaction Concrete
FROM TO (KM) Manual n (cu.m.)
(cu.m.) (HB) (cu.m.) (cu.m.)
(sq.m.)/
FORCE ACCOUNT WORKS
Hindang RIS (Abuyog)
A. Canal System
Desilting (Manual) @ Lateral Do 0+000 0+218 0.218 136.25
14170.88
136.25 14,170.00
MASTERLIST OF ACTIVITIES
- -
DERIVATION OF UNIT COST, DESILTING, (Manual)
HINDANG - HILONGOS IRRIGATION SYSTEM
Hindang, Leyte
Desilting (Manual)
1) LABOR COST
Crew: 1 Laborer
Capability of one tea 2.5 cu.m./day/man
1 laborer @ 260 per day = 260 per day
Unit Cost: 260 per day / 2.5 cu.m./day/man = 104 per cu.m.
SUMMARY
I. ESTIMATED DIRECT COST
A. MATERIAL COST = -
B. LABOR COST = 104.00 per cu.m.
C. EQUIPMENT COST = -
TOTAL EST= 104.00 per cu.m.
ROSALYN S. DELFIN
Engineer A
IRRIGATION ADMINISTRATION
HHIIS Hindang, Leyte
OWN OF FY-2017 PROGRAM OF WORKS
TING IRRIGATION SYSTEM, FY-2017,(TIER-2)
Attachment "D"
INDIRECT COST TOTAL
VAT TOTAL UNIT COST PROJECT COST
7.45 14,690.88
168.12 26,058.60
9,776.10 1,232,766.21
72.80 413,103.60
12.95 73,484.78
1,156.72 160,853.58
- - 1,920,957.65
7.45 4,467.99
194.45 8,750.25
209.54 8,381.60
10,446.28 120,967.92
-
72.80 64,069.82
12.95 11,397.04
5,970.50 71,646.00
3,235.74 6,471.48
93,000.00 93,000.00
72,000.00 72,000.00
1,156.72 79,932.29
- - 541,084.39
- - 2,462,042.04
14,170.88
14,170.88
14,170.88
24,761.91
24,761.91
74,263.26
123,787.08
2,600,000.00
INDIRECT COST TOTAL
VAT TOTAL UNIT COST PROJECT COST
7.45 15,915.66
194.45 35,195.45
9,776.10 1,317,329.48
72.80 441,441.00
12.95 78,525.56
1,156.72 397,307.11
2,285,714.26
- - 2,285,714.26
22,857.14
22,857.14
68,571.46
114,285.74
2,400,000.00
4,761,927.18
47,619.05
47,619.05
142,834.72
5,000,000.00
5,000,000.00
JOJO A. ARCEŇO
OIC IS / BHHD-BIG-DGM Satellite Office
NATIONAL IRRIGATION ADMINISTRATION
HHIS Hindang, Leyte
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017
5. Procurement of Equipment
& Vehicles
6. Consulting Services
8. Contingencies
Attachment "C-1"
March 2017 1ST QUARTER TOTAL
PC LP PC LP
FO CO FO CP F.O. C.O. FO CO
1 3
234,417.04 - 318,550.48 - - -
2,834.18 2,834.18
11,904.76 47,619.05
11,904.76 47,619.05 - -
- -
35,708.68 71,417.36 - -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
296,769.42 488,040.12
NATIONAL IRRIGATION ADMINISTRATION
HHIS Hindang, Leyte
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
3. Construction Survey -
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services
9. Contingencies
Attachment "C-2"
June 2017 2ND QUARTER TOTAL
PC LP PC LP
FO CO FO CO FO CO FO CO
1 3
685,109.23 - 2,115,536.29
1,417.09 11,336.70
- -
- -
9,998.43 71,417.36
- -
696,524.75 2,198,290.35
NATIONAL IRRIGATION ADMINISTRATION
HHIS Hindang, Leyte
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
3. Construction Survey -
4. FSSM -
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services
9. Contingencies
Attachment "C-3"
September 2017 TOTAL 3rd QUARTER
PC LP PC LP
FO CO FO CO FO CO FO CO
1 3
- -
631,000.79 1,682,668.77
- -
- -
- -
- - - -
- -
- - - -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
631,000.79 1,682,668.77 - -
NATIONAL IRRIGATION ADMINISTRATION
HHIS Hindang, Leyte
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
3. Construction Survey - - -
4. FSSM - - -
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services
9. Contingencies
- -
TOTAL DIRECT COST 420,667.19 210,333.57
RRIGATION ADMINISTRATION
HIS Hindang, Leyte
QUIPMENT REQUIREMENT & CASH REQUIREMENT
R/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
Attachment "C-4"
4th QUARTER TOTAL GRAND TOTAL
PC LP PC LP
FO CO FO CO FO CO FO CO
3 12
-
631,000.76 4,747,756.30
- 14,170.88
- 47,619.05
-
- 47,619.05
-
- 142,834.72
-
-
-
-
-
-
-
-
-
-
- -
631,000.76 5,000,000.00
NATIONAL IRRIGATION ADMINISTRATION
BITO RIS ABUYOG, LEYTE
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-20
No. of
I. MANPOWER REQUIREMENT
Personnel GRAND TOTAL
1. Monthly Personnel
2. Daily Personnel 2
3. Contractual 3
4. FSSM 142,834.72
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services
9. Contingencies
Prepared By : Submitted By :
ROGELIO F. BALLESTEROS
Engineering Assistant A
NATIONAL IRRIGATION ADMINISTRATION
BITO RIS ABUYOG, LEYTE
REMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
K ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
Attachment "C-5"
- -
LP-Cash TOTAL
C.O. PC LP TOTAL
- 4,747,756.30 - 4,747,756.30
14,170.88 14,170.88
47,619.05 47,619.05
47,619.05 47,619.05
142,834.72 142,834.72
5,000,000.00 - 5,000,000.00
Submitted By :
SANTOS D. MERACAP, JR
Principal Engineer A
NATIONAL IRRIGATION ADMINISTRATION
HHIS Hindang, Leyte
DETAILED BREAKDOWN OF CY 2017 PROGRAM OF WORK (BY ACTIVITIES)
A. DIRECT COST
1. CIVIL WORKS
a. Contract Works 4,747,756.30
b. Force Account Works 14,170.88
9. Contingencies
- - - -
Prepared by:
ROSALYN S. DELFIN
Engineer A
VITIES)
Attachment "B"
TRACT WORKS PROCUREME
ROW TRAINING/AC EQUIPMENT NT OF TAXES CONTENGENCIES TOTAL
Consulting TIVITIES TOOLS EQUIPMENT
Services VEHICLES
4,747,756.30
14,170.88
14,285.72 47,619.05
47,619.05
142,834.72
14,285.72 5,000,000.00
Submitted by
JOJO A. ARCEŇO
OIC IS / BHHD-BIG-DGM Satellite Office
APPROVED BUDGET FOR THE CONTRACT
HHIS Hindang, Leyte
REPAIR/REHAB. OF EXISTING IRRIGATION SYSTEM - 2017
ITEMS OF WORK UNIT QTY. UNIT COST ESTIMATED DIRECTCONTRACTOR'S VATTOTAL COST UNIT COST
(1) (2) (3) (4) (5) (6) (7) (8)
PACKAGE # 2
HHIS
a CANAL SYSTEM
Canal Lining SFD#4, Lat. D, Sta.0+000 to Sta.0+100(100m)SAMAGLANO IA,Canal Lining SFD#1, Lat. C, Sta.0+000 to Sta.0+250,(250m), BUNGSANMA IA,
Canal Lining SFD#3, Lat. D4a,Sta.1+100 to Sta.1+280(180m) SAMAGLANO IA,Canal Lining SFD#5, Lat. D4, Sta.0+180 to Sta. 0+328,(148m) SAMAGLANO IA,
Canal Lining SFD#5, Lat. D4a, Sta. 0+000 Sta.0+150,(150m), SAMAGLANO IA
Clearing and Grubbing sq.m. 2,136.33 7.45 12,347.99 3,567.67 15,915.66 7.45
Structure Excavation cu.m. 181.00 194.45 23,530.00 11,665.45 35,195.45 194.45
170 kscm Re-inforced Concrete cu.m. 134.75 9,776.10 - 1,317,329.48 1,317,329.48 9,776.10
RSB -
Furnishing of RSB kgs 6,063.75 72.80 338,357.25 103,083.75 441,441.00 72.80
Cutting and Bending kgs 6,063.75 12.95 62,153.44 16,372.12 78,525.56 12.95
Structure backfill (HB) cu.m. 343.48 1,156.72 302,842.88 94,639.05 397,481.93 1,157.22
Sub-total 739,231.56 1,546,657.52 2,285,889.08
TOTAL CONTRACT AMOUNT 739,231.56 1,546,657.52 2,285,889.08
2,285,889.08
2,285,889.08
APPROVED BUDGET FOR THE CONTRACT
HHIS Hindang, Leyte
REPAIR/REHAB. OF EXISTING IRRIGATION SYSTEM - 2017
Contract Reference Number :
Name of Contract : Improvement of Irrig. Facilities
HHIS Location of the Contract : HHIS Hindang, Leyte
NATIONAL IRRIGATION ADMINISTRATION Contract Duration : 330 Cal. Days
ITEMS OF WORK UNIT QTY. UNIT COST ESTIMATED DIRECTCONTRACTOR'S VATTOTAL COST UNIT COST
(1) (2) (3) (4) (5) (6) (7) (8)
PACKAGE # 1
HHIS
a CONSTRUCTION OF CHECKGATE
Check Structures @ Bukana Creek
Clearing & Grubbing (Manual) sq.m. 599.73 7.45 3,466.44 1,001.55 4,467.99 7.45
Structure Excavation (Manual) cu.m. 45.00 194.45 6,685.71 2,089.29 8,775.00 195.00
Diversion and care of river cu.m. 40.00 209.54 6,400.00 2,000.00 8,400.00 210.00
211 kscm Class A Concrete cu.m. 11.58 10,446.28 92,179.46 28,788.46 120,967.92 10,446.28
RSB - -
Furnishing of RSB kls 880.08 72.80 49,108.46 14,961.36 64,069.82 72.80
Cutting and Bending of Bars kls 880.08 12.95 9,020.82 2,376.22 11,397.04 12.95
Rubble Masonry cu.m. 12.00 5,970.50 54,595.91 17,050.09 71,646.00 5,970.50
RCP 18" Diameter pcs 2.00 3,235.74 4,931.50 1,518.72 6,450.22 3,225.11
Fab./inst of Sluice gate pc 1.00 93,000.00 70,982.25 22,181.95 93,164.20 93,164.20
Fab./inst of Intake gate pc 1.00 72,000.00 54,884.35 17,151.36 72,035.71 72,035.71
Structure Backfill w/ compaction (HB) cu.m. 69.07 1,156.72 60,898.33 19,030.86 79,929.19 1,157.22
Sub-total 418,381.65 128,149.86 546,531.51
b CANAL SYSTEM
Canal Lining SFD#3 Lat. D1,Sta.0+000 to Sta.0+200(200m) PMT IA,Canal Lining SFD#4,Lat. D1, Sta.0+000 to Sta.0+200,(200m), PMT IA
Canal Lining Bukana Div. Chckgt, Sta.0+000 to Sta.0+300(300m) PMT IA, Canal Lining SFD#3, Lat. D02, Sta.0+350 to Sta.0+425,(75m), MATANDO IA
Clearing and Grubbing sq.m. 1,971.93 7.45 11,397.76 3,293.12 14,690.88 7.45
Structure Excavation cu.m. 155.00 168.12 20,150.00 5,908.60 26,058.60 168.12
170 kscm Re-inforced Concrete cu.m. 126.10 9,776.10 939,298.59 293,467.62 1,232,766.21 9,776.10
RSB
Furnishing of RSB kgs 5,674.50 72.80 316,637.10 96,466.50 413,103.60 72.80
Cutting and Bending kgs 5,674.50 12.95 58,163.63 15,321.15 73,484.78 12.95
Structure backfill (HB) cu.m. 139.00 1,156.72 122,554.91 38,298.67 160,853.58 1,157.22
Sub-total 1,468,201.99 452,755.66 1,920,957.65
TOTAL CONTRACT AMOUNT 1,886,583.64 580,905.52 2,467,489.16
413103.6
73484.775
160,853.58 2,077,029.31
2,682,837.76 2,467,489.16
NATIONAL IRRIGATION ADMINISTRATION
HHIS Hindang, Leyte
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
Attachment "C-5"
CY___,(Previous Year) CY-2017,(Current Year) CY_____, (Future Year) OVERALL PROJECT COST
PC LP PC LP PC LP PC LP
PARTICULARS DESCRIPTION FO CO FO CO FO CO FO CO FO CO FO CO FO CO FO CO
I. MAN POWER REQUREMENT No. of Personnel
1. Monthly Personnel
2. Daily Personnel
3. Contractual 1 1 1 3
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services -
-
8. Taxes (for selected FAPs) -
-
9. Contingencies
-
- - -
TOTAL DIRECT COST - 4,985,829.12 4,985,829.12
DERIVATION OF UNIT COST
DAGUITAN-GUINARONA-MARABONG RIVER IRRIGATION SYSTEM
JULITA, LEYTE
[CONTRACT WORKS ]
I CONSTRUCTION MATERIALS
A. HAULING OF CEMENT
Ave.Hauling distance: = 45 km.from office to source to warehouse and nearest point accessible
by truck (field bodega)
Utilize: 6-7 tons cargo truck with five laborers
Ave.Hauling Distance: 45.00 kms.
Base Cost of cement: P 260.00 / bag
Capacity of Cargo Truck = 200 bags/trip]
Rental rate= P 851 / hr.(Acel 2009 Edition 24)
Baremonth= P 110,604 / month
= 110,604/baremonth x 1 month / 25 days x 1 day / 8 hrs.
= 553.02 / hr.
Laborer rate @ P 260.00 / day
CYCLE TIME:
EQUIPMENT:
Rental: [ P 851.00 / hr. x 3.96 hr./trip ] / [ 200 bags/trip ]= 16.85 / bag
12% VAT
0.12 x 553.02 / hr. x 3.96 hr./trip ] / [ 200 bags/trip ]= 1.31 / bag
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
CYCLE TIME:
LABOR COST:
Laborer:[5xP 260.00 / day x 4.63 hr./trip ] / [ 8 hrs./day x 250pc/trip]= 3.01 / pc.
LABOR COST…………. 3.01 / pc.
EQUIPMENT:
Rental: [ P 851.00 / hr. x 4.63 hr./trip ] / [ 250 pcs./trip]= 15.76 / pc.
12% VAT
0.12 x 553.02 / hr. x 4.63 hr./trip ] / [ 250 bags/trip ]= 1.23 / pc. OK
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
w/ manual hauling
SUMMARY : Plywood G.I.Sheet
A. Base Cost = 750.00 / pc. 310.00 / pc.
B. Labor Cost = 5.07 / pc. 5.07 / pc.
Page 47 of 100
C. Equipment Cost = 15.76 / pc. 15.76 / pc.
D. 12% VAT = 1.59 / pc. 1.59 / pc.
UNIT COST….....= P 772.42 / pc. 332.42 / pc. OK
CYCLE TIME:
LABOR COST:
Laborer:[5xP 260.00 / day x 3.31 hr./trip ] / [ 8 hrs./day x 4000 bd.ft./trip ] = P 0.13 / bd.ft.
LABOR COST…………. 0.13 / bd.ft.
EQUIPMENT:
Rental: [ P 851.00 / hr. x 3.31 hr./trip ] / [ 4000.00 bd.ft./trip 0.70 / bd.ft.
12% VAT
0.12 x 553.02 / hr. x 3.31 hr./trip ] / [ 4000 bags/trip ]= 0.05 / bd.ft. OK
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
CYCLE TIME:
Loading : [ 6000 kgs./trip x 60 min./hr.] /[ 6000 kgs./ hr. = 60.00 min./ trip
Unloading [ 6000 kgs./trip x 60 min./hr.] /[ 7000 kgs./ hr. = 51.43 min./ trip
LABOR COST:
Laborer:[5xP 260.00 / day x 4.48 hr./trip ] / [ 8 hrs./day x 7000.00 0.10 / kgs.
LABOR COST…………. 0.10 / kgs.
EQUIPMENT:
Rental: [ P 851.00 / hr. x 4.48 hr./trip ] / [ 6000.00 kgs./trip 0.64 / kgs.
12% VAT
0.12 x 553.02 / hr. x 4.48 hr./trip ] / [ 6000.00 bags/trip ]= 0.05 / kgs.
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
w/ manual hauling
SUMMARY : RSB CW NAILS TIE WIRE
A. Base Cost = 55.00 / kg. 75.00 / kg. 75.00 / kg.
B. Labor Cost = 0.43 / kg. 0.43 / kg. 0.43 / kg.
C. Equipment Cost = 0.64 / kg. 0.64 / kg. 0.64 / kg.
D. 12% VAT = 0.06 / kg. 0.06 / kg. 0.06 / kg.
UNIT COST….....= P 56.13 / kg. 76.13 / kg. 76.13 / kg.
LABOR COST:
Laborer:[1xP 260.00 / day x 1.89 hr./trip ] / [ 8 hrs/day x 4.00 cu.m./trip 15.36 / cu.m.
LABOR COST…………. 15.36 / cu.m.
EQUIPMENT:
Rental: [ P 743.00 / hr. x 1.89 hr./trip ] / [ 4.00 cu.m./trip 351.07 / cu.m.
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
w/ manual hauling
SUMMARY : SAND GRAVEL
A. Base Cost = 550.00 / cu.m. 850.00 / cu.m.
B. Labor Cost = 15.36 / cu.m. 15.36 / cu.m.
C. Equipment Cost = 351.07 / cu.m. 351.07 / cu.m.
D. Manual Hauling = 173.33 / cu.m. 173.33 / cu.m.
UNIT COST….....= P 1089.76 / cu.m. 1389.76 / cu.m.
b) Common Borrow
Loading : [ 2.5 cu.m/trip x 60 min./hr.] /[ 20 cu.m/ hr. = 7.50 min./ trip
Unloading [ 2.5 cu.m/trip x 60 min./hr.] /[ 25 cu.m/ hr. = 6.00 min./ trip
Loading : [ 4 cu.m/trip x 60 min./hr.] /[ 5 cu.m/ hr. = 48.00 min./ trip
Unloading [ 4 cu.m/trip x 60 min./hr.] /[ 8 cu.m/ hr. = 30.00 min./ trip
Laborer:[1xP 260.00 / day x 1.53 hr./trip ] / [ 8 hrs/day x 4.00 cu.m./trip 12.43 / cu.m.
EQUIPMENT:
Rental: [ P 743.00 / hr. x 1.53 hr./trip ] / [ 4.00 cu.m./trip 284.20 / cu.m.
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
C) Boulders
Loading : [ 2.5 cu.m/trip x 60 min./hr.] /[ 20 cu.m/ hr. = 7.50 min./ trip
Page 49 of 100
Unloading [ 2.5 cu.m/trip x 60 min./hr.] /[ 25 cu.m/ hr. = 6.00 min./ trip
Loading : [ 4 cu.m/trip x 60 min./hr.] /[ 3 cu.m/ hr. = 80.00 min./ trip
Unloading [ 4 cu.m/trip x 60 min./hr.] /[ 4 cu.m/ hr. = 60.00 min./ trip
min./ trip
TOTAL TIME………… 153.50 min./ trip
2.56 hrs./ trip
LABOR COST:
Laborer:[1xP 260.00 / day x 2.56 hr./trip ] / [ 8 hrs/day x 4.00 cu.m./trip 20.80 / cu.m.
LABOR COST…………. 20.80 / cu.m.
EQUIPMENT:
Rental: [ P 743.00 / hr. x 2.56 hr./trip ] / [ 4.00 cu.m./trip 475.52
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
Page 50 of 100
pcs. per meter
10 3.696 133 491.568 38 399 107.95455 0.616 6 3.696
12 5.328 47 250.416 19 199.5 37.443694 0.888 6 5.328
16 9.474 19 180.006 14 147 15.516149 1.579
20 14.796 26 384.696 29 304.5 20.579886 2.466
total 1306.686 100 1050 12.8592
47.527603
105
#REF!
47
180 18.8 60
13 110
60 230
125 110
13 60
60 570 0.8 5.7 9.12
13 5.64 0.3 1.692
100 10.812
80 5.328
80 57.606336
724 5.328
10.812
Page 51 of 100
12.8592
1.1 1.21
2 4
5.21
5.21√
2.2825424
Page 52 of 100
BITO RIVER IRRIGATION SYSTEM
Abuyog,Leyte
CY 2017 POW
(By Contract Works)
Attachment "G"
DERIVATION OF COST OF CONSTRUCTION MATERIALS
LOCAL MINOR CONTRACT
Position Rate per day (P) Position Rate per day (P)
Foreman 400.00 Heavy Equipment Operator 350.00
Carpenter 350.00 Light Equipment Operator 300.00
Mason 350.00 Driver/Bar Cutter 300.00
Steelman/Welder 350.00 Laborer/Helper (per Minimum Wage 260.00
Board as of July 1, 2012)
SUMMARY
A. Base Cost = 270.00 per bag
B. Labor Cost = 0.81 per bag
C. Equipment Cost = 15.40 per bag
Plus 5% VAT (Exc. Mat'l Cost) = 0.81 per bag
TOTAL = 287.02 per bag
CONSTRUCTION MATERIALS RSB, C.W. NAILS, TIE WIRES & ANGLE BARS
Rough Road:
With Load : 0.00 km/trip / 20.00 km./hr. = 0.00 hr./trip
W/o Load : 0.00 km/trip / 25.00 km./hr. = 0.00 hr./trip
2.30 hr./trip
Baremonth = P96564/bare month x 1month /25 days x 1 day / 8hrs. = P 482.82 /hr.
Cycle Time
Concrete Road:
With Load : 15.00 km/trip / 35.00 km./hr. = 0.43 hr./trip
W/o Load : 15.00 km/trip / 45.00 km./hr. = 0.33 hr./trip
= 0.76
Rough Road:
With Load : 5.00 km/trip / 20.00 kms./hr. = 0.25 hr./trip
W/o Load : 5.00 km/trip / 25.00 kms./hr. = 0.20 hr./trip
Loading, Spot & manuver, unloading & delay = 0.20 hr./trip
= 0.65 hr./trip
TOTAL = 1.41 hr./trip
B. LABOR COST
1 Helper x 260.00 /day 1.41 hr./trip
8.00 hrs./day x 4.00 cu.m./trip = 11.46 per cu.m.
5% VAT = 11.46 x 0.05 = 0.57 per cu.m.
C. EQUIPMENT COST
Rental = 743.00 /hr. x 1.41 hr./trip
4.00 cu.m./trip = 261.91 per cu.m.
VAT 0.05 x 743.00 /hr. x 1.41 hr./trip = 13.10 per cu.m.
4.00 cu.m./trip
SUMMARY Boulder
A. Base Cost = 500.00 per cu.m.
B. Labor Cost = 4.17 per cu.m.
C. Equipment Cost = 173.30 per cu.m.
Plus 12% VAT (Exc. Mat'l Cost) = 8.88 per cu.m.
Total = 686.35 per cu.m.
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = 5,801.28 per cu.m.
B. LABOR COST = 1,405.71 per cu.m.
1. Cutting, Bending & Placing of RSB = - per cu.m.
2. Fabrication, placing and dismantling of forms = 497.14 per cu.m.
3. Concreting and Curing = 908.57 per cu.m.
C. EQUIPMENT COST = 258.00 per cu.m.
1. Concrete Mixer = 258.00 per cu.m.
TOTAL ESTIMATED DIRECT COST = 7,464.99 per cu.m.
II. INDIRECT COST
A. PROFIT & OCM (20% OF EDC) = 1,493.00 per cu.m.
B. VAT (12% OF LABOR COST) = 171.93 per cu.m.
1. Labor Cost (Cutting,Bending & Placing, Fabrication, = 168.69 per cu.m.
Placing & Dismantling of forms, Concreting & Curing
2. Labor Cost ( Hauling of Materials ) = 3.24 per cu.m.
C. VAT (12% OF EQUIPMENT RENTAL ) = 61.76 per cu.m.
1. Equipment Rental Cost using ( Concrete Mixer ) = - per cu.m.
2. Equipment Rental Cost using ( Hauling of Materials ) = 41.68 per cu.m.
D. VAT (12% OF PROFIT & OCM ) = 179.16 per cu.m.
TOTAL INDIRECT COST = 1,905.85 per cu.m.
TOTAL UNIT COST = 9,370.84 per cu.m.
2. REINFORCING STEEL BARS, All Sizes
Reinforcing Steel Bars (RSB), Grade 40
A. Furnishing and Stockpiling
RSB @ 55.64 per kg = 55.64 per kg
Total Material Cost = 55.64 per kg
SUMMARY
I. DIRECT COST
A. Furnishing and Stockpiling = 55.64
TOTAL ESTIMATED DIRECT COST = 55.64 per kgs
II. INDIRECT COST
A. PROFIT & OCM (20% OF EDC) = 11.13 per kg
B. VAT (12% OF LABOR COST) = - per kg
1. Labor Cost ( Hauling of Materials ) = - per kg
C. VAT (12% OF EQUIPMENT RENTAL ) = 0.03 per kg
1. Equipment Rental Cost using ( Hauling of Materials ) = 0.03 per kg
D. VAT (12% OF PROFIT & OCM ) = 1.34 per kg
TOTAL INDIRECT COST = 12.50 per kgs
TOTAL UNIT COST = 68.14 per kgs
B. Installation Cost
1. Cut, Bend and Place of RSB
1 Steelman @ 350.00 per day = 350.00 per day
1 Laborer @ 260.00 per day = 260.00 per day
Total = 610.00 per day
Capability 10.00 kgs/hr x 8 hrs/day = 80.00 kgs/day
SUMMARY
I. ESTIMATED DIRECT COST
A. MATERIAL COST = -
B. LABOR COST = 6.50 per sq.m.
C. EQUIPMENT COST = -
TOTAL ESTIMATED DIRECT COST = 6.50 per sq.m.
II. INDIRECT COST
A. PROFIT & OCM (2% OF EDC) = 1.30 per sq.m.
B. VAT (12% OF LABOR COST) = 0.78 per sq.m.
C. VAT (12% OF RENTAL ) = -
D. VAT (12% OF PROFIT & OCM ) = 0.16 per sq.m.
TOTAL INDIRECT COST = 2.24 per sq.m.
TOTAL UNIT COST = 8.74 per sq.m.
SUMMARY :
I. ESTIMATED DIRECT COST
A. MATERIAL COST = -
B. LABOR COST = 140.00 per sq.m.
C. EQUIPMENT COST =
TOTAL ESTIMATED DIRECT COST = 140.00 per sq.m.
II. INDIRECT COST
A. PROFIT & OCM (20% OF EDC) = 28.00 per sq.m.
B. VAT (12% OF LABOR COST) = 16.80 per sq.m.
C. VAT (12% OF RENTAL ) = -
D. VAT (12% OF PROFIT & OCM ) = 3.36 per sq.m.
TOTAL INDIRECT COST = 48.16 per sq.m.
TOTAL UNIT COST = 188.16 per sq.m.
Spreading:
Equipment Used 1-Unit DOZER D60A-11 (155 HP)
Capability = 90.00 cu.m./hr.
Operated Rental Rate P 2,594.00 /hr.
Bare Month P 337,194.00
= 337,194.00 /month /25 days x 1 day / 8hrs.
1,685.97 /hr.
Operated Re2,594.00 /hr / 90.00 cu.m./hr. = 28.82 /cu.m.
I. DIRECT COST
A. MATERIAL COST
1. Material Cost 773.37 per cu.m.
A. EQUIPMENT COST
3. Spreading = 28.82 per cu.m.
4. Compaction = 24.55 per cu.m.
53.37 per cu.m.
TOTAL ESTIMATED DIRECT COST = 826.74 per cu.m.
B. LABOR COST
1. Fabrication, placing and dismantling of forms
1 Carpenter @ 350.00 per day = 350.00 per day
1 Laborer @ 260.00 per day = 260.00 per day
Total = 610.00 per day
Capability 4.5 cu.m./day
Labor cost = 135.56 per cu.m.
2. Concreting with curing
Time of Mixer = 7.5bags/cum x 4.5cum/day x 10min/bag = 5.63 hrs/day
60min/hr
a With concrete mixer
1 Foreman @ 400.00 per day = 400.00 per day
2 Mason @ 350.00 per day = 700.00 per day
8 Laborer @ 260.00 per day = 2,080.00 per day
Total = 3,180.00 per day
Capability 4.5 cu.m./day
Labor Cost = 706.67 per cu.m.
C. EQUIPMENT COST
Capability 4.5 cu.m./day
Rental = 172 per hr. x 5.25 hrs/day = 200.67 per cu.m.
4.5 cu.m./day
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = 3,770.10 per cu.m.
B. LABOR COST = 842.23 per cu.m.
1. Fabrication, placing and dismantling of forms = 135.56 per cu.m.
2. Concreting and Curing = 706.67 per cu.m.
C. EQUIPMENT COST = 200.67 per cu.m.
1. Concrete Mixer = 200.67 per cu.m.
TOTAL ESTIMATED DIRECT COST = 4,813.00 per cu.m.
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = 4,562.77 per cu.m.
B. LABOR COST = 842.23 per cu.m.
1. Cutting, Bending & Placing of RSB = - per cu.m.
2. Fabrication, placing and dismantling of forms = 135.56 per cu.m.
3. Concreting and Curing = 706.67 per cu.m.
C. EQUIPMENT COST = 200.67 per cu.m.
1. Concrete Mixer = 200.67 per cu.m.
TOTAL ESTIMATED DIRECT COST = 5,605.67 per cu.m.
II. INDIRECT COST
A. PROFIT & OCM (2% OF EDC) = 1,121.13 per cu.m.
B. VAT (12% OF LABOR COST) = 26.14 per cu.m.
1. Labor Cost (Cutting,Bending & Placing, Fabrication, = 101.07 per cu.m.
Placing & Dismantling of forms, Concreting & Curing
2. Labor Cost ( Hauling of Materials ) = 2.94 per cu.m.
C. VAT (12% OF EQUIPMENT RENTAL ) = 55.24 per cu.m.
1. Equipment Rental Cost using ( Concrete Mixer ) = 15.62 per cu.m.
2. Equipment Rental Cost using ( Hauling of Materials ) = 39.62 per cu.m.
D. VAT (12% OF PROFIT & OCM ) = 134.54 per cu.m.
TOTAL INDIRECT COST = 1,337.05 per cu.m.
TOTAL UNIT COST = 6,942.72 per cu.m.
9. RUBBLE MASONRY
A. MATERIAL COST (per cu.m.)
Cement 4.50 bags @ 286.21 per bag = 1,287.95
Gravel 0.45 cu.m. @ 1123.37 per cu.m. = 505.52
Sand 0.225 cu.m. @ 773.37 per cu.m. = 174.01
Boulder 0.95 kgs @ 677.47 per cu.m. = 643.60
Total Material Cost = 2,611.08 per cu.m.
B. LABOR COST
1. Laying of Materials
1 Laborer @ 260.00 per day = 260.00 per day
Total = 260.00 per day
Capability 1.5 cu.m./day
Labor Cost = 173.33 per cu.m.
2. Concreting with curing
Time of Mixer = 4.5bags/cum x 5.0cum/day x 10min/bag = 3.75 hrs/day
60min/hr
a With concrete mixer
1 Foreman @ 400.00 per day = 400.00 per day
2 Mason @ 350.00 per day = 700.00 per day
8 Laborer @ 260.00 per day = 2,080.00 per day
Total = 3,180.00 per day
Labor Cost = 636.00 per cu.m.
Capability 5 cu.m./day
C. EQUIPMENT COST
Capability 5 cu.m./day
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = 2,611.08 per cu.m.
B. LABOR COST = 809.33 per cu.m.
1. Laying of Materials = 173.33 per cu.m.
2. Concreting and Curing = 636.00 per cu.m.
C. EQUIPMENT COST = 129.00 per cu.m.
1. Concrete Mixer = 129.00 per cu.m.
TOTAL ESTIMATED DIRECT COST = 3,549.41 per cu.m.
II. INDIRECT COST
A. PROFIT & OCM 20% OF EDC) = 709.88 per cu.m.
B. VAT (12% OF LABOR COST) = 98.98 per cu.m.
C. VAT (12% OF RENTAL ) = 42.06 per cu.m.
D. VAT (12% OF PROFIT & OCM ) = 85.19 per cu.m.
TOTAL INDIRECT COST = 936.11 per cu.m.
TOTAL UNIT COST = 4,485.52 per cu.m.
A. CONSTRUCTION OF SLPOE PROTECTION WORK @ DAGUITAN DAM DOWNSTREAM RIGHT EMBANKMENT FACING UPSTREAM
STATIONING
FROM TO LENGTH (mAREA (sq.m.) St AREA (sq.m.) BackfAREA (sq.m.) Emb.AREA (sq.m.)AREA (sq.m.) DewLength (l.m.) Clearing & Grub AREA (sq.m.)
Vert. Bars Hor. Bars (12mVolume (cu.m.) St Volume (cu.m.) BVolume (cu.m.) Em
Volume (cu.m.Volume (cu.m.Area (sq.m.) Cl Volume (cu.m.)Vert. Bars Hor. Bars (12mm
DOWNSTREAM RIGHT SIDE EMBANKMENT FACING UPSTREAM
0 + 000 2.00 2.10 0.00 3.04 1.80 15.00 0.47 3.35 53
0 + 000 0 + 003.50 3.5 2.20 11.90 0.00 3.04 1.80 15.00 0.47 3.35 53 7.35 24.50 0.00 10.64 6.30 52.50 1.65 208.24 179.70
0 + 003.5 0 + 009 5.5 5.90 6.30 0.00 3.04 1.80 15.00 0.47 3.35 53 22.28 50.05 0.00 16.72 9.90 82.50 2.59 327.23 282.38
0 + 009 0 + 010 1 2.50 16.10 0.00 3.04 1.80 15.00 0.47 3.35 53 4.20 11.20 0.00 3.04 1.80 15.00 0.47 59.50 51.34
0 + 010 0 + 020 10 4.30 3.30 0.00 3.04 1.80 15.00 0.47 3.35 53 34.00 97.00 0.00 30.40 18.00 150.00 4.70 594.96 513.43
0 + 020 0 + 040 5 12.41 5.80 0.00 3.04 1.80 15.00 0.47 3.35 53 41.78 22.75 0.00 15.20 9.00 75.00 2.35 297.48 256.71
0 + 040 0 + 060 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SUB-TOTAL 25 109.61 205.50 0.00 76.00 45.00 375.00 11.76 1,487.41 1,283.56
TOTAL 25 109.61 205.50 0.00 76.00 45.00 375.00 11.76 2770.97
B. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 0 + 340 - 1 + 018 L = 261.15 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 3.34
L = 261.15 3.04 0.15
V = 0.07*3.34*261.15
V = 61.06 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 3.34 0.15
L = 261.15
V = 0.07*3.34*261.15 3.04 0.15
V = 61.06 cu.m.
c. Filter Drain
Area = 0.18 sq.m.
L = 261.15
V = 0.18*261.15
V = 47.00 cu.m.
C. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 2 + 501 - 3 + 094 L = 22 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 2.28
L = 22 1.98 0.15
V = 0.07*2.28*22
V = 3.51 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 2.28 0.15
L = 22
V = 0.07*2.28*22 1.98 0.15
V = 3.51 cu.m.
D. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 4 + 552 - 4 + 568 L = 20 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 2.28
L = 20 1.98 0.15
V = 0.07*2.28*20
V = 3.19 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 2.28 0.15
L = 20
V = 0.07*2.28*20 1.98 0.15
V = 3.19 cu.m.
E. REPAIR OF CANAL LINING OF DAGUITAN LATERAL D STA 3 + 972 - 3 + 988 L = 16 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 3.5
L = 16 3.2 0.15
V = 0.07*3.5*16
V = 3.92 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 3.5 0.15
L = 16
V = 0.07*3.5*16 3.2 0.15
V = 3.92 cu.m.
Prepared by:
JOJO A. ARCENO
Senior Engineer A
Summary
A.
Program Amount
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Clearing & Grubbing (Mechanized) sq.m. 375.00 12.78 4,792.50
b. Dewatering cu.m. 45.00 618.10 27,814.50
d. Common Excavation-Mechanized cu.m. 461.13 146.17 67,403.37
d. Filter drain cu.m. 11.76 1,715.67 20,176.28
e. 211kgsc. Concrete cu.m. 76.00 11,425.49 868,337.24
f. Furnishing of RSB kgs. 6,650.31 66.91 444,972.24 6650.31
g. Cutting,Bendin & Placing of RSB kgs. 6,054.85 16.14 97,725.28
h. Supply & Installation of Steel Sheet Piles pcs. - - 6054.85
h. Backfill w/ Compaction ( SB )-Mechanized cu.m. 205.50 69.87 14,358.29
i. Emb. Const'n. & Comp. ( ECC ) ( HB )-Mechanized cu.m. - 1,254.54 -
TOTAL 1,545,579.70 1,478,176.33
B.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 55.18 624.93 34,483.64
b. 169kgsc. Plain Concrete cu.m. 55.18 7,974.41 440,027.94
c. Filter drain cu.m. 42.48 1,715.67 72,881.66
TOTAL 547,393.24
c.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 2.55 624.93 1,593.57
b. 169kgsc. Plain Concrete cu.m. 2.55 7,974.41 20,334.75
TOTAL 21,928.32
d.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 2.55 624.93 1,593.57
b. 169kgsc. Plain Concrete cu.m. 2.55 7,974.41 20,334.75
TOTAL 21,928.32
E.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 1.96 624.93 1,224.86
b. 169kgsc. Plain Concrete cu.m. 1.96 7,974.41 15,629.84
TOTAL 16,854.70
F.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 2.50 624.93 1,562.33
b. 169kgsc. Plain Concrete cu.m. 2.50 7,974.41 19,936.03
TOTAL 21,498.36
G.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.16 624.93 99.99
b. 169kgsc. Plain Concrete cu.m. 0.16 7,974.41 1,275.91
TOTAL 1,375.90
H.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.24 624.93 149.98
b. 169kgsc. Plain Concrete cu.m. 0.24 7,974.41 1,913.86
TOTAL 2,063.84
i.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.16 624.93 99.99
b. 169kgsc. Plain Concrete cu.m. 0.16 7,974.41 1,275.91
TOTAL 1,375.90
j.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.16 624.93 99.99
b. 169kgsc. Plain Concrete cu.m. 0.16 7,974.41 1,275.91
TOTAL 1,375.90
k.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.32 624.93 199.98
b. 169kgsc. Plain Concrete cu.m. 0.32 7,974.41 2,551.81
TOTAL 2,751.79
l.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Common Excavation cu.m. 1.50 194.43 291.65
b. 211kgsc. Concrete cu.m. 0.43 11,425.49 4,912.96
c. Furnishing of RSB kgs. 15.18 66.91 1,015.69
d. Cutting,Bendin & Placing of RSB kgs. 15.18 16.14 245.01
e. Backfill w/ Compaction ( HB ) cu.m. 9.00 1,502.70 13,524.30
TOTAL 19,989.61
M.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Common Excavation cu.m. 1.50 194.43 291.65
b. 211kgsc. Concrete cu.m. 0.43 11,425.49 4,912.96
c. Furnishing of RSB kgs. 15.18 66.91 1,015.69
d. Cutting,Bendin & Placing of RSB kgs. 15.18 16.14 245.01
e. Backfill w/ Compaction ( HB ) cu.m. 3.60 1,502.70 5,409.72
TOTAL 11,875.03 2,148,587.24
(1,351,312.76)
Prepared by: 2,215,990.61000 -9244.802353424
3,499,900.0000
1,283,909.3900000000000
JOJO A. ARCENO 8,783.6723677909300
Senior Engineer A 9,244.8023677909
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
#REF!
DETAILED COMPUTATION
Construction of downstream slope protection L/S facing downstream of Daguitan Dam
Sta 0 + 000 + 0 + 026
Brgy. Cantimawa, Burauen, Leyte
I. DIVERSION WORKS
A. Clearing & Grubbing ( Mechanized )
STATIONING Width Thickness No. of Area
FROM TO Name of Canal LENGTH (m) (m) Units (sq.m.)
0 + 000 0 + 026 Daguitan Dam 26 15 390
E. Filter Drain
STATIONING Width Thickness No. of Area
FROM TO Name of Canal LENGTH (m) (m) Units (sq.m.)
0 + 000 0 + 003.5 Daguitan Dam 3.5 0.47
0 + 003.5 0 + 009 Daguitan Dam 5.5 0.47
0 + 009 0 + 010 Daguitan Dam 1 0.47
0 + 010 0 + 026 Daguitan Dam 16 0.47
Total Volume for Filter Drain 26
a b c d
Bar Size Bar Section Length per cut bars (m)
b
a
b
a
a
c
12 mm dia Deformed Ba 0.3 0.76 0.04 1.1
a
12 mm dia Deformed Ba 27 27
c. Filter Drain
Area = 0.18 sq.m.
L = 261.15
V = 0.18*261.15
V = 47.00 cu.m.
B. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 2 + 501 - 3 + 094 L = 22 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 2.28
L = 22 1.98 0.15
V = 0.07*2.28*22
V = 3.51 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 2.28 0.15
L = 22
V = 0.07*2.28*22 1.98 0.15
V = 3.51 cu.m.
C. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 4 + 552 - 4 + 568 L = 20 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 2.28
L = 20 1.98 0.15
V = 0.07*2.28*20
V = 3.19 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 2.28 0.15
L = 20
V = 0.07*2.28*20 1.98 0.15
V = 3.19 cu.m.
D. REPAIR OF CANAL LINING OF DAGUITAN LATERAL D STA 3 + 972 - 3 + 988 L = 16 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 3.5
L = 16 3.2 0.15
V = 0.07*3.5*16
V = 3.92 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 3.5 0.15
L = 16
V = 0.07*3.5*16 3.2 0.15
V = 3.92 cu.m.
Volume Remarks
(cu.m.)
inclined wall
VOLUME Remarks
FILL
Volume Remarks
(cu.m.)
80.60 inclined wall
4.29 cut-off wall
84.89
Volume Remarks
(cu.m.)
1.65 inclined wall
2.59 inclined wall
0.47 inclined wall
7.52 inclined wall
12.23
Volume Remarks
(cu.m.)
cut-off wall
No of pcs. Total Length (m) Unit weight of RS Total No. of Kil Remarks
1. Surveying:
Profile:
Capability per team = 3.5 km/day
Plotting :
Capability per team = 1.5 km/day
Cross-Section:
Capability per team = 2 km/day
Plotting :
Capability per team = 1 km/day
Equipment Cost:
Particulars Rate/trip No. km/day Cost
Equipment Rental = 3,220.40 3 = 1,073.47
Driver = 636.36 3 = 212.12
Fuel = 284.00 3 = 94.67
Oil 30% of Fuel Cost = 28.40
Total Equipment Cost per kilometers = 1,408.66 km
Summary :
I. SURVEY WORKS
a. Profilling km 1.603 1532.64 2456.82192
b. Crossectioning km 1.603 3015.77 4,834.28
2. Service Vehicles km 30.373 1408.66 42,785.23
TOTAL COST 47,619.51
DERIVATION OF UNIT COST
HHIS Hindang, Leyte
Institutional Development Program
1. Personnel Services
1 - IDO = 19,047.62
Sub-Total 19,047.62
2. MOOE
2.a. Office Supplies = 4,761.91
2.b. Fuel & Oil = 2,380.95
2.c. Equipment Rental = 4,761.91
2.d. Spare Parts = 2,380.95
2.e. Trainings = 14,285.72
Sub-Total 28,571.44
SUB-TOTAL 27,823.29 3,000.00 2,225.86 3,338.79 2,150.00 262.50 150.00 - - - 38,950.44 111,293.16 12,000.00 8,903.45 13,355.18 600.00 1,050.00 600.00 11,774.43 5,000.00 164,576.22 203,526.66
COS Employees
1 Jonathan G. Setosta Survey Aide RREIS - DGM RIS - CS 6 587.31 74,001.06 - - - 600.00 - - - - 74,601.06 587.31 74,001.06 - - - - 600.00 - - - 74,601.06 149,202.12
2 Romwell Ogana Survey Aide RREIS - DGM RIS - CS 6 587.31 74,001.06 600.00 74,601.06 587.31 74,001.06 600.00 74,601.06 149,202.12
3 Louie A. Tonido WRFT Tender A RREIS - DGM RIS - SUBSIDY 5 546.31 68,835.06 600.00 69,435.06 546.31 68,835.06 600.00 69,435.06 138,870.12
4 Domingo Simborios Driver Mechanic B RREIS - DGM RIS - SUBSIDY 7 631.36 79,551.36 600.00 80,151.36 631.36 79,551.36 600.00 80,151.36 160,302.72
5 Andres Dela Cruz Driver Mechanic B RREIS - DGM RIS - SUBSIDY 7 631.36 79,551.36 600.00 80,151.36 631.36 79,551.36 600.00 80,151.36 160,302.72
6 Constanti Advincula Utility Worker A RREIS - DGM RIS - SUBSIDY 4 472.77 59,569.02 600.00 60,169.02 472.77 59,569.02 600.00 60,169.02 120,338.04
7 Jessie Leuterio Utility Worker A RREIS - DGM RIS - CS 4 472.77 59,569.02 600.00 60,169.02 472.77 59,569.02 600.00 60,169.02 120,338.04
8 Rico Agner Utility Worker B RREIS - DGM RIS - CS 3 409.09 51,545.34 600.00 52,145.34 409.09 51,545.34 600.00 52,145.34 104,290.68
9 Ruel C. Verzosa Utility Worker B RREIS - DGM RIS - CS 3 409.09 51,545.34 600.00 52,145.34 409.09 51,545.34 600.00 52,145.34 104,290.68
10 Danilo Tuang Utility Worker B RREIS - DGM RIS - CS 3 409.09 51,545.34 600.00 52,145.34 409.09 51,545.34 600.00 52,145.34 104,290.68
11 Melchor Abbe Natulla RAB RREIS - DGM RIS - IDP 8 678.68 85,513.68 600.00 86,113.68 678.68 85,513.68 600.00 86,113.68 172,227.36
12 Mia Lee T. Planillo RAB RREIS - DGM RIS - IDP 8 678.68 85,513.68 600.00 86,113.68 678.68 85,513.68 600.00 86,113.68 172,227.36
SUB-TOTAL 939,879.36 - - - - 11,400.00 - - - - 951,279.36 939,879.36 - - - - 11,400.00 - - - 951,279.36 1,902,558.72
GRANDTOTAL 967,702.65 3,000.00 2,225.86 3,338.79 2,150.00 11,662.50 150.00 - - - 990,229.80 1,051,172.52 12,000.00 8,903.45 13,355.18 600.00 12,450.00 600.00 11,774.43 5,000.00 1,115,855.58 2,106,085.38
b. Labor Cost
b.1 Cutting, Grinding and Laying of Frame
Crew: 2- Welder ; 2- Laborers
Capability: 2.80 days/unit
b.2 Drilling of Anchor bolts & Retainer bolts, molding of Lifting Stem guide.
Crew: 1- Machinest ; 2- Laborers
Capability: 2.40 days/unit
b.3 Assembling & Welding of Frame
Crew: 2- Welder ; 3- Laborers
Capability: 3.00 days/unit
b.4 Fabrication of Lifting Mechanism / Pedestal Guide
Crew: 2- Machinest ; 3- Laborers
Capability: 3.00 days/unit
b.5 Assembling of Gates
Crew: 2- Welder ; 2- Laborers
Capability: 4.00 days/unit
b.6 Cleaning of Materials / Paints Works
Crew: 1- Painter ; 2- Laborers
Capability: 1.60 days/unit
Rate Labor
Personnel
per
Involved
Cutting, Grinding and Laying of Frame Drilling of Anchor bolts & Retainer bAssembling & Welding of Frame
Day No. COST No. COST No. COST
Machinest 400.00 1 400
Welder 350.00 2 700.00 2 700
Painter 350
Laborer 253.00 2 506.00 2 506 3 759
Total Cost 1,206.00 906 1459
Unit Cost 3,376.80 2174.4 4377
Rate Labor
per
Personnel Inv Fabrication of Lifting Mechanism / Pedestal Guide Assembling of Gates Cleaning of Materials / Paints Works
Day No. COST No. COST No. COST
Machinest 400.00 2 800
Welder 350.00 2 700
Painter 350 1 350
Laborer 253.00 3 759 2 506 2 506
Total Cost 1559 1206 856
Unit Cost 4677 4824 1369.6
Sub-Total Unit Cost (For Labor) 20798.8
c. Equipment Cost
c.1 Equipment to be used: Power Rental: P180.00 /hr.
TIME OF POWER SAW
Status Using No. of hours to bhrs./ days/
Power Saw used per unit day unit
25 8 3.125
Installation
b. Hauling Cost
Average hauling distance is 185.35 kms. from Maasin to jobsite
Type of Road: Concrete Road = 180.00 kms.
Poor Maintained Road = 0.30 kms.
Utilized 6-7 tonner Cargo Truck w/ 4 laborers
Rental: P851.00 / hr.
Cycle Time
Status kms. min. kms. min.
using per trip per hr. per hr. per trip
Concrete Road
w/ load 180 * 60 / 35 = 308.57
w/o load 180 * 60 / 45 = 240.00
Poor maintained gravel road
w/ load 0.3 * 60 / 20 = 0.90
w/o load 0.3 * 60 / 25 = 0.72
Manual Hauling, Loading & Unloading = 30.00
TOTAL 580.19 min./trip
9.67 hrs./trip
1.21 day/trip
Labor Cost:
Personnel Peso day unit Peso
Involved per day per trip per trip per unit
1-Driver @
320.00 320.00 * 1.21 * 1 = 387.20
4-Laborer @
253.00 1,012.00 * 1.21 * 1 = 1224.52
TOTAL 1,611.72 /unit
Equipment Cost:
Cost/ Hrs./ Liter/ Cost/ unit/ Cost/
Particulars hr. day hr. liter day unit
Fuel 9.67 * 10.00 * 58.37 * ### = 5,644.38
Oil 30% of Fuel Cost = 1,693.31
Rental 851.00 * 9.67 * ### = 8,229.17
SUMMARY
Materials = 77471 = 77,471.00
Labor = 20,798.80 + 1,362.00 + 1,611.72 = 23,772.52
Equipment = 54,140.00 = 54,140.00
Fuel = 5,644.38 + 1,693.31 = 7,337.69
Rental = 8,229.17 = 8,229.17
Total Estimated Cost P170,950.38
9% O.C.M. P15,385.53
8% Profit P13,676.04
TOTAL P200,011.94
12% VAT P11,217.53
Total Unit Cost P211,229.47
Unit Cost for Proc./Fab. & Inst. of Steel Gate at Intake and Back to River (1.00 m. X 1.15 m.) P211,229.47 / unit
SUMMARY
I. DIRECT COST
A. MATERIAL COST P0.00 / unit
1. Without Fabrication 0.00
2. With Fabrication 0.00
700
759
1459
4377
s / Paints Works
COST
350
506
856
1369.6
20798.8
Name of Project : CONSTRUCTION OF CANAL LINING
GANTT CHART
Package # 2
Total Duration : 120 Cal Days
2017
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt
Item Items of Work, (Should be in accordEstimated Cost Percent WeNo. of D
I. PACKAGE #2
2. CANAL LINING @ SUPLLEMENTARY FARMDITCHES & LAT. CANAL
2017
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt qrt
ItemItems of Work, (Should be in accordan
Estimated Cost Percent WNo. of
I. PACKAGE #1
1. CONSTRUCTION OF CHECKGATE
Check Structures @ Ulhay Creek
Clearing & Grubbing (Manual) 4,467.99 0.18% 14
Structure Excavation (Manual) 8,775.00 0.36% 35
Diversion and care of river 8,400.00 0.34% 35
211 kscm Class A Concrete 120,967.92 4.91% 77
Furnishing of RSB 64,069.82 2.60% 21
Cutting and Bending of Bars 11,397.04 0.46% 63
Rubble Masonry 71,646.00 2.91% 56
RCP 18" Diameter 6,450.22 0.26% 14
Fab./inst of Sluice gate 93,164.20 3.78% 21
Fab./inst of Intake gate 72,035.71 2.93% 21
Structure Backfill w/ compaction (HB 79,929.19 3.25% 70
Sub-total 541,303.09 22.18% 90
2. CANAL LINING @ SUPLLEMENTARY FARMDITCHES & LAT. CANAL
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capabilit 11.00 pcs. /day
Rate
Personnel Involved per Labor
Day No. Cost
Foreman 400.00 1 400.00
Mason 350.00 1 350.00
L.E. Operat 320.00 1 320.00
Steelman 300.00 1 300.00
Laborer 253.00 12 3,036.00
Total Cost 4,406.00
Unit Cost 400.55
12% VAT P48.07
c. Equipment Cost
c.1 Equipment to be used: 1- Bagger Concrete Mixer
Capability: 11 pcs./day
Operated Rental Rate : 172 /hr. (Based on ACEL 2009 Editon 24)
Fuel Consumption : 1.25 liters/hr.
Fuel Cost : P55.28 /liter
= 102.9 /hr.
TIME OF MIXER/DAY
Status Using pcs./ bags/ min./ min./ hrs./
Mixer day pc. bag hr. day
11 * 1.22 * 10 / 60 = 2.24
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capabilit 14.00 pcs. /day
Rate
Personnel Involved per Labor
Day No. Cost
Foreman 400.00 1 400.00
Mason 350.00 1 350.00
L.E. Operat 320.00 1 320.00
Steelman 300.00 1 300.00
Laborer 253.00 12 3,036.00
Total Cost 4,406.00
Unit Cost 314.71
12% VAT P37.77
c. Equipment Cost
c.1 Equipment to be used: 1- Bagger Concrete Mixer
Capability: 14 pcs./day
Operated Rental Rate : 172 /hr. (Based on ACEL 2009 Editon 24)
Fuel Consumption : 1.25 liters/hr.
Fuel Cost : P55.28 /liter
= 102.9 /hr.
TIME OF MIXER/DAY
Status Using pcs./ bags/ min./ min./ hrs./
Mixer day pc. bag hr. day
14.00 * 0.45 * 10 / 60 = 1.05
SUMMARY
I. DIRECT COST
A. MATERIAL COST = 445.00 /pc.
1. Materials Cost = 445.00 /pc
B. LABOR COST = 314.71 /pc.
1. Installation of RCP = 314.71 /pc
C. EQUIPMENT COST = 12.90 /pc.
1. Concrete Mixer = 12.90 /pc
TOTAL ESTIMATED DIRECT COST = 772.61 /pc. ###
II. INDIRECT COST
A. PROFIT & OCM 17% OF EDC) = 131.34 /pc
B. VAT (12% OF LABOR COST) = 98.98 /pc
C. VAT (12% OF RENTAL ) = 42.06 /pc
D. VAT (12% OF PROFIT & OCM ) = 15.76 /pc
TOTAL INDIRECT COST = 288.14 /pc. ###
Unit Cost for Installation of 18" dia. RCP = 1,060.75 /pc.
b. Labor Cost
b.1 Cutting, Grinding and Laying of Frame
Crew: 2- Welder ; 2- Laborers
Capability: 2.80 days/unit
b.2 Drilling of Anchor bolts & Retainer bolts, molding of Lifting Stem guide.
Crew: 1- Machinest ; 2- Laborers
Capability: 2.40 days/unit
b.3 Assembling & Welding of Frame
Crew: 2- Welder ; 3- Laborers
Capability: 3.00 days/unit
b.4 Fabrication of Lifting Mechanism / Pedestal Guide
Crew: 2- Machinest ; 3- Laborers
Capability: 3.00 days/unit
b.5 Assembling of Gates
Crew: 2- Welder ; 2- Laborers
Capability: 4.00 days/unit
b.6 Cleaning of Materials / Paints Works
Crew: 1- Painter ; 2- Laborers
Capability: 1.60 days/unit
Rate Labor
Personnel
per
Involved
Cutting, Grinding and Laying of Frame Drilling of Anchor bolts & Retainer bolts, moAssembling & Welding of Frame
Day No. COST No. COST No. COST
Machinest 400.00 1 400
Welder 350.00 2 700.00 2 700
Painter 350
Laborer 253.00 2 506.00 2 506 3 759
Total Cost 1,206.00 906 1459
Unit Cost 3,376.80 2174.4 4377
Rate Labor
Personnel
per
Involved
Fabrication of Lifting Mechanism / PedestalAssembling of Gates Cleaning of Materials / Paints W
Day No. COST No. COST No. COST
Machinest 400.00 2 800
Welder 350.00 2 700
Painter 350 1 350
Laborer 253.00 3 759 2 506 2 506
Total Cost 1559 1206 856
Unit Cost 4677 4824 1369.6
Sub-Total Unit Cost (For Labor) 20798.8
c. Equipment Cost
c.1 Equipment to be used: Power Saw Rental: P180.00 /hr.
TIME OF POWER SAW
Status Using No. of hours to be hrs./ days/
Power Saw used per unit day unit
25 8 3.125
Installation
b. Hauling Cost
Average hauling distance is 185.35 kms. from Maasin to jobsite
Type of Road: Concrete Road = 180.00 kms.
Poor Maintained Road = 0.30 kms.
Utilized 6-7 tonner Cargo Truck w/ 4 laborers
Rental: P851.00 / hr.
Cycle Time
Status kms. min. kms. min.
using per trip per hr. per hr. per trip
Concrete Road
w/ load 180 * 60 / 35 = 308.57
w/o load 180 * 60 / 45 = 240.00
Poor maintained gravel road
w/ load 0.3 * 60 / 20 = 0.90
w/o load 0.3 * 60 / 25 = 0.72
Manual Hauling, Loading & Unloading = 30.00
TOTAL 580.19 min./trip
9.67 hrs./trip
1.21 day/trip
Labor Cost:
Personnel Peso day unit Peso
Involved per day per trip per trip per unit
1-Driver @
320.00 320.00 * 1.21 * 1 = 387.20
4-Laborer @
253.00 1,012.00 * 1.21 * 1 = 1224.52
TOTAL 1,611.72 /unit
Equipment Cost:
Cost/ Hrs./ Liter/ Cost/ unit/ Cost/
Particulars hr. day hr. liter day unit
Fuel 9.67 * 10.00 * 58.37 * 1.00 = 5,644.38
Oil 30% of Fuel Cost = 1,693.31
Rental 851.00 * 9.67 * 1.00 = 8,229.17
SUMMARY
I. DIRECT COST
A. MATERIAL COST 152409.8 / unit
1. Without Fabrication 77471
2. With Fabrication 74938.8
= 102.9 /hr.
TIME OF MIXER/DAY
Status Using pcs./ bags/ min./ min./ hrs./
SUMMARY
Labor
12% VAT Rental
OCM
Unit Cost for Fabrication and Installation of 18" RCP #REF! + #REF! =
5. FILTER DRAIN
A. MATERIAL COST (per cu.m.)
2" dia. PV 0.15 cu.m. @ Err:509 per cu.m. = Err:509
Fine Sand 0.65 cu.m. @ Err:509 per cu.m. = Err:509
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = Err:509 per cu.m.
B. LABOR COST = Err:509 per cu.m.
1. Laying of Materials = Err:509 per cu.m.
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capability 14.00 pcs. /day
Rate
Personnel Involved per Labor
Day No. Cost
Foreman 400.00 1 400.00
Mason 350.00 1 350.00
L.E. Operat 320.00 1 320.00
Steelman 300.00 1 300.00
Laborer 253.00 12 3,036.00
Total Cost 4,406.00
Unit Cost 314.71
#REF!
#REF!
#REF!
#REF! #REF!
#REF!
#REF! #REF!
#REF!
#REF! #REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF! /pc.
ok
0.08 86.08
0.00 17.29
0.07 224.33
0.00 3.33
0.15 331.03
Proc./Fab. & Inst of 18" dia. RCP
I Fabrication
a. Materials Cost
Hauling from Source to Jobsite
Materials Unit Qty' Base Cost Labor Rental HAULING COS
Cement cu.m. 1.22 353.80 9.72 8.97 372.49
Sand cu.m. 0.05 27.50 7.57 6.36 41.43
Gravel cu.m. 0.10 80.00 15.14 12.71 107.85
G.I. Sheet pc 0.19 66.50 0.59 2.03 69.12
F.Lumber bd.ft 0.36 10.80 0.68 0.17 11.65
Hardware kgs 0.20 15.00 0.08 0.08 15.16
RSB kgs 7.72 424.60 3.24 2.93 430.77
Total 978.20 37.02 33.25 1,048.47
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capability: 11.00 pcs. /day
Labor
Personnel Involved rate/day No. Cost
Foreman 500.00 1 500.00
Mason 450.00 1 450.00
Steelman 300.00 1 300.00
Laborer 260.00 12 3,120.00
Total Cost 4,370.00
Unit Cost 397.27
c. Equipment Cost
c.1 Equipment to be used: 1- Bagger Concrete Mixer
Capability: 11 pcs./day
Operated Rental Rate : 172 /hr. (Based on ACEL 2009 Editon 24)
172.00 per hr x 8 hrs.day
Rental = P11.00 cu.m./day = 125.090909090909 /pc.
SUMMARY
I. ESTIMATED DIRECT COST
A. MATERIAL COST = 978.20
B. LABOR COST
1. Fabrication of RCP = 434.29
C. EQUIPMENT COST
1. Concrete Mixer = 158.34
TOTAL ESTIMATED DIRECT COST = 1,570.83
II. INDIRECT COST
A. OCM (15% OF EDC) = 235.62
B. PROFIT (10% OF EDC) = 157.08
C. VAT (5% OF EDC + PROFIT + OCM) = 98.18
TOTAL INDIRECT COST = 490.88
Unit Cost for Fabrication of 18" dia. RCP = 2,061.71
II Installation
a. Materials Cost
Hauling from Source to Jobsite
Materials Per pc. Base Cost Labor Rental Total Cost
Cement 0.45 130.5 3.59 3.31 137.40
Sand 0.02 11 3.03 2.54 16.57
Gravel 0.04 32 6.06 5.08 43.14
F.Lumber 2 60 3.80 0.96 64.76
Hardware 0.2 15 0.08 0.08 15.16
RSB 3.65 200.75 1.53 1.39 203.67
Tie Wire 0.05 3.75 0.02 0.02 3.79
Total 453 18.11 13.38 484.49
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capability: 14.00 pcs. /day
Labor
Personnel Involved Rate/day No. Cost
Foreman 500.00 1 500.00
Mason 450.00 1 450.00
Steelman 300.00 1 300.00
Laborer 260.00 12 3,120.00
Total Cost 4,370.00
Unit Cost 312.14
c. Equipment Cost
c.1 Equipment to be used: 1- Bagger Concrete Mixer
Capability: 14 pcs./day
Operated Rental Rate : 172 /hr. (Based on ACEL 2009 Editon 24)
172.00 per hr x 8 hrs.day
Rental = P14.00 pcs/day = 98.2857142857143 /pc.
SUMMARY
I. DIRECT COST
A. MATERIAL COST = 453.00
B. LABOR COST
1. Installation of RCP = 330.25
C. EQUIPMENT COST
1. Concrete Mixer = 111.67
TOTAL ESTIMATED DIRECT COST = 894.92
II. INDIRECT COST
A. OCM (15% OF EDC) = 134.24
B. PROFIT (10% OF EDC) = 89.49
C. VAT (5% OF EDC+PROFIT+OCM ) = 44.75
TOTAL INDIRECT COST = 268.48
Unit Cost for Installation of 18" dia. RCP = 1,163.40
Unit Cost for Fabrication and Installation of 18" RCP = 3,225.11 /pc
REPAIR/REHAB OF NATIONAL IRRIGATION SYSTEM
HHIS HINDANG, LEYTE CY - 2017
IRRIGATION FACILITIES
1. Lateral Canals
a. Earth Canal
b. Concrete Canal
2. Supplementery Farmditch
a. Earth Canal
b. Concrete Canal 1.603
No. of IA Organized 5
Farmer Benefeciaries 889