A Note on Surveying-I
TRIANGULATION AND TRILATERATION
The horizontal positions of points is a network developed to provide accurate control for topographic
mapping, charting lakes, rivers and ocean coast lines, and for the surveys required for the design and
construction of public and private works of large extent. The horizontal positions of the points can be
obtained in a number of different ways and are:
1. Traversing
2. Triangulation
3. Trilateration
4. Intersection
5. Resection and
6. Satellite positioning
Triangulation, a method of surveying
is based on the trigonometric
proposition that if one side and two
angles of a triangle are known, the
remaining sides can be computed.
Furthermore, if the direction of one
side is known, the directions of the
remaining sides can be determined. A triangulation system consists of a series of joined or overlapping
triangles in which an occasional side is measured and remaining sides are calculated from angles
measured at the vertices of the triangles. The vertices of the triangles are known as triangulation
stations. The side of the triangle, whose length is predetermined, is called the base line. The lines of
triangulation system form a network that ties together all the triangulation stations (Fig. 1.1).
A trilateration system also consists of a series of joined or overlapping triangles. However, for
trilateration the lengths of all the sides of the triangle are measured and few directions or angles are
measured to establish azimuth. Trilateration has become feasible with the development of electronic
distance measuring (EDM) equipment which has made possible the measurement of all lengths with
high order of accuracy under almost all field conditions.
A combined triangulation and trilateration system consists of a network of triangles in which all the
angles and all the lengths are measured. Such a combined system represents the strongest network for
creating horizontal control
Since a triangulation or trilateration system covers very large area, the curvature of the earth has to be
taken into account. These surveys are, therefore, invariably geodetic. Triangulation surveys were first
carried out by Snell, a Dutchman, in 1615.
Field procedures for the establishment of trilateration station are similar to the procedures used for
triangulation, and therefore, henceforth in this chapter the term triangulation will only be used.
Prepared By: Er. Bishnu Prasad Devkota 1
A Note on Surveying-I
PRINCIPLE OF TRIANGULATION
Fig. 1.2 shows two interconnected triangles ABC and BCD. All the angles in both the triangles and the
length L of the side AB have been measured. Also the azimuth θ of AB has been measured at the
triangulation station A, whose coordinates (XA, YA), are known. The objective is to determine the
coordinates of the triangulation stations B, C, and D by the method of triangulation. Let us first calculate
the lengths of all the lines.
By sine rule in, ABC ∆ we have
From the known length of the sides and azimuths, the consecutive and independent coordinates can be
computed as:
It would be found that the length of side can be computed
Prepared By: Er. Bishnu Prasad Devkota 2
A Note on Surveying-I
more than once following different routes, and therefore, to achieve a better accuracy, the mean of the
computed lengths of a side is to be considered.
OBJECTIVES OF TRIANGULATION SURVEYS
The main objective of triangulation or trilateration surveys is to provide a number of stations whose
relative and absolute positions, horizontal as well as vertical, are accurately established. More detailed
location or engineering survey is then carried out from these stations.
The triangulation surveys are carried out
(i) To establish accurate control for plane and geodetic surveys of large areas, by terrestrial methods,
(ii) To establish accurate control for photogrammetric surveys of large areas,
(iii) To assist in the determination of the size and shape of the earth by making observations for
latitude, longitude and gravity, and
(iv) To determine accurate locations of points in engineering works such as :
(a) Fixing centre line and abutments of long bridges over large rivers.
(b) Fixing centre line, terminal points, and shafts for long tunnels.
(c) Transferring the control points across wide sea channels, large water bodies, etc.
(d) Detection of crustal movements, etc.
(e) Finding the direction of the movement of clouds.
CLASSIFICATION OF TRIANGULATION SYSTEM
Based on the extent and purpose of the survey, and consequently on the degree of accuracy desired,
triangulation surveys are classified as first-order or primary, second-order or secondary, and third-order
or tertiary.
Prepared By: Er. Bishnu Prasad Devkota 3
A Note on Surveying-I
First-order triangulation is used to determine the shape and size of the earth or to cover a vast area like
a whole country with control points to which a second-order triangulation system can be connected. A
second-order triangulation system consists of a network within a first-order triangulation. It is used to
cover areas of the order of a region, small country, or province. A third-order triangulation is a
framework fixed within and connected to a second-order triangulation system. It serves the purpose of
furnishing the immediate control for detailed engineering and location surveys
TRIANGULATION FIGURES AND LAYOUTS:
The basic figures used in triangulation networks are the triangle, braced or geodetic quadrilateral, and
the polygon with a central station (Fig 1.3)
The triangles in a triangulation system can be arranged in a number of ways: some of the commonly
used arrangements, also called layouts, are as follows:
1. Single chain of triangles
2. Double chain of triangles
3. Braced quadrilaterals
4. Central triangles and polygons
5. A combination of above systems.
Single Chain of triangles:
When the control points are required to be established in a narrow strip of terrain such as a valley
between ridges, a layout consisting of single chain of triangles is generally used as shown in Fig. 1.4. This
system is rapid and economical due to its simplicity of sighting only four other stations, and does not
involve observations of long diagonals. On the other hand, simple triangles of a triangulation system
provide only one route through which distances
can be computed, and hence, this system does not
provide any check on the accuracy of
observations. Check base lines and astronomical
observations for azimuths have to be provided at
frequent intervals to avoid excessive accumulation
of errors in this layout
Prepared By: Er. Bishnu Prasad Devkota 4
A Note on Surveying-I
Double chain of triangles:
A layout of double chain of triangle is
shown in fig 1.5. This arrangement is
used for covering the larger width of
belt. This system also has disadvantages
of single chain of triangles system.
Braced Quadrilaterals:
A triangulation system consisting of
figures containing four corner stations
and observed diagonals shown in Fig. 1.6
is known as a layout of braced
quadrilaterals. In fact, braced
quadrilateral consists of overlapping
triangles. This system is treated to be the
strongest and the best arrangement of
triangles, and it provides a means of
computing the lengths of the sides using different combinations of sides and angles. Most of the
triangulation systems use this arrangement.
CENTERED TRIANGLES AND POLYGONS:
A triangulation system which consists of
figures containing interior stations in
triangle and polygon as shown in Fig.
1.7, is known as centered triangles and
polygons. This layout in a triangulation
system is generally used when vast area
in all directions is required to be
covered. The centered figures generally
are quadrilaterals, pentagons, or
hexagons with central stations. Though
this system provides checks on the
accuracy of the work, generally it is not as strong as the braced quadrilateral arrangement. Moreover,
the progress of work is quite slow due to the fact that more settings of the instrument are required.
A COMBINATION OF ALL ABOVE SYSTEMS
Sometimes a combination of above systems may be used which may be according to the shape of the
area and the accuracy requirements
Prepared By: Er. Bishnu Prasad Devkota 5
A Note on Surveying-I
LAYOUT OF PRIMARY TRIANGULATION FOR LARGE COUNTRIES
The following two types of frameworks of primary triangulation are provided for a large country to cover
the entire area.
1. Grid iron system
2. Central system
Grid Iron System
In this system, the primary triangulation is laid in series of
chains of triangles, which usually runs roughly along
meridians (north-south) and along perpendiculars to the
meridians (east-west), throughout the country (Fig. 1.8).
The distance between two such chains may vary from 150
to 250 km. The area between the parallel and
perpendicular series of primary triangulation, are filled by
the secondary and tertiary triangulation systems. Grid iron
system has been adopted in India and other countries like
Austria, Spain, France, etc.
Central system
In this system, the whole area is covered by a network of
primary triangulation extending in all directions from the
initial triangulation figure ABC, which is generally laid at
the centre of the country (Fig. 1.9). This system is
generally used for the survey of an area of moderate
extent. It has been adopted in United Kingdom and
various other countries.
CRITERIA FOR SELECTION OF THE LAYOUT OF TRIANGLES
The under mentioned points should be considered while deciding and selecting a suitable layout of
triangles.
1. Simple triangles should be preferably equilateral.
2. Braced quadrilaterals should be preferably approximate squares.
3. Centered polygons should be regular.
4. The arrangement should be such that the computations can be done through two or more
independent routes.
5. The arrangement should be such that at least one route and preferably two routes form well-
conditioned triangles.
Prepared By: Er. Bishnu Prasad Devkota 6
A Note on Surveying-I
6. No angle of the figure, opposite a known side should be small, whichever end of the series is used for
computation.
7. Angles of simple triangles should not be less than 45°, and in the case of quadrilaterals, no angle
should be less than 30°. In the case of centered polygons, no angle should be less than 40°.
8. The sides of the figures should be of comparable lengths. Very long lines and very short lines should
be avoided.
9. The layout should be such that it requires least work to achieve maximum progress.
10. As far as possible, complex figures should not involve more than 12 conditions.
It may be noted that if a very small angle of a triangle does not fall opposite the known side it does not
affect the accuracy of triangulation.
WELL-CONDITIONED TRIANGLES
The accuracy of a triangulation system is greatly affected by the arrangement of triangles in the layout
and the magnitude of the angles in individual triangles. The triangles of such a shape, in which any error
in angular measurement has a minimum effect upon the computed lengths, is known as well-
conditioned triangle. In any triangle of a triangulation system, the length of one side is generally
obtained from computation of the adjacent triangle. The error in the other two sides if any, will affect
the sides of the triangles whose computation is based upon their values. Due to accumulated errors,
entire triangulation system is thus affected thereafter. To ensure that two sides of any triangle are
equally affected, these should, therefore, be equal in length. This condition suggests that all the
triangles must, therefore, be isoceles. Let us consider an isosceles triangle ABC whose one side AB is of
known length (Fig. 1.10). Let A, B, and C be the three angles of the triangle and a, b, and c are the three
sides opposite to the angles, respectively.
………………1.2
If an error of δA in the angle A, and δC in angle C introduce
the errors δa1 and δa2, respectively, in the side a, then differentiating above equation partially, we get
………………………………..1.3
………………………………..1.4
Prepared By: Er. Bishnu Prasad Devkota 7
A Note on Surveying-I
Hence, the best shape of an isosceles triangle is that triangle whose base angels are 56 014’ each.
However trom practical considerations, an equilateral triangle may be treated as a well-conditional
triangle. In actual practice, the triangles having an angle less than 300 or more than 1200 should not be
considered.
ROUTINE OF TRIANGULATION SURVEY
The routine of triangulation survey, broadly consists of
a) Field work and b) computations.
The field work of triangulation is divided into the following operations:
1. Reconnaissance
2. Erection of signals and towers
SIGNALS
Signals are centered vertically over the station mark, and the observations are made to these
signals from other stations. The accuracy of triangulation is entirely dependent on the degree of
accuracy of centering the signals. Therefore, it is very essential that the signals are truly vertical,
and centered over the station mark. Greatest care of centering the transit over the station mark
will be useless, unless some degree of care in centering the signal is impressed upon.
Classification of signals
The signals may be classified as under:
(i) Non-luminous, opaque or daylight signals
(ii) Luminous signals.
Prepared By: Er. Bishnu Prasad Devkota 8
A Note on Surveying-I
Non-luminous signals
Non-luminous signals are used during
day time and for short distances. These
are of various types, and the most
commonly used are of following types.
(a) Pole signal (Fig. 1.24): It consists of a round pole painted black and white in alternate strips,
and is supported vertically over the station mark, generally on a tripod. Pole signals are suitable
up to a distance of about 6 km.
(b) Target signal (Fig. 1.25): It consists of a pole carrying two squares or rectangular targets
placed at right angles to each other. The targets are generally made of cloth stretched on
wooden frames. Target signals are suitable up to a distance of 30 km
(c) Pole and brush signal (Fig. 1.26): It consists of a straight pole about 2.5 m long with a bunch
of long grass tied symmetrically round the top making a cross. The signal is erected vertically
over the station mark by heaping a pile of stones, up to 1.7 m round the pole. A rough coat of
white wash is given to make it more conspicuous to be seen against black background. These
signals are very useful, and must be erected over every station of observation during
reconnaissance.
(d) Stone cairn (Fig. 1.27): A pile of stone heaped in a conical shape about 3 m high with a cross
shape signal erected over the stone heap, is stone cairn. This white washed opaque signal is very
useful if the background is dark
(e) Beacons (Fig. 1.28): It consists of red and white cloth tied round the three straight poles. The
beacon can easily be centered over the station mark. It is very useful for making simultaneous
observations
Luminous signals
Luminous signals may be classified into two types:
Prepared By: Er. Bishnu Prasad Devkota 9
A Note on Surveying-I
(i) Sun signals
(ii) Night signals.
(a) Sun signals (Fig. 1.29): Sun signals reflect the rays of the sun towards the station of
observation, and are also known as heliotropes. Such signals can be used only in day time in
clear weather
(b) Night signals: When the observations are required to be made at night, the night signals of
following types may be used.
1. Various forms of oil lamps with parabolic reflectors for sights less than 80 km.
2. Acetylene lamp designed by Capt. McCaw for sights more than 80 km.
3. Magnesium lamp with parabolic reflectors for long sights.
4. Drummond’s light consisting of a small ball of lime placed at the focus of the parabolic
reflector, and raised to a very high temperature by impinging on it a stream of oxygen.
5. Electric lamps.
TOWERS
A tower is erected at the triangulation station when the station or the signal or both are to
be elevated to make the observations possible form other stations in case of problem of
intervisibility. The height of tower depends upon the character of the terrain and the length
of the sight. The towers generally have two independent structures. The outer structure is
for supporting the observer and the signal whereas the inner one is for supporting the
instrument only. The two structures are made entirely independent of each other so that
the movement of the observer does not disturb the instrument setting. The two towers may
be made of masonary, timber or steel. For small heights, masonary towers are most
suitable. Timber scaffolds are most commonly used, and have been constructed to heights
over 50 m. Steel towers made of light sections are very portable, and can be easily erected
and dismantled
3. Measurement of base line
The accuracy of an entire triangulation system depends on that attained in the measurement of
the base line and, therefore, the measurement of base line forms the most important part of
the triangulation operations. As base line forms the basis for computations of triangulation
system it is laid down with great accuracy in its measurement and alignment. The length of the
base line depends upon the grade of the triangulation. The length of the base is also determined
by the desirability of securing strong figures in the base net. Ordinarily the longer base, the
easier it will be found to secure strong figures.
4. Measurement of horizontal angles
The instruments used for triangulation surveys, require great degree of precision. Horizontal
angles are generally measured with an optical or electronic theodolite in primary and secondary
triangulation. For tertiary triangulation generally transit or Engineer’s transit having least count
of 20" is used. The horizontal angles of a triangulation system can be observed by the following
methods:
(i) Repetition method
Prepared By: Er. Bishnu Prasad Devkota 10
A Note on Surveying-I
(ii) Reiteration method
5. Measurement of vertical angles
Measurement of vertical angles is required to compute the elevation of the triangulation
stations
6. Astronomical observations to determine the azimuth of the lines.
To determine the azimuth of the initial side, intermediate sides, and the last side of the
triangulation net, astronomical observations are made
Prepared By: Er. Bishnu Prasad Devkota 11