0% found this document useful (0 votes)
86 views1 page

Project Charter

The document discusses improving an online meeting application. It aims to increase downloads and ratings by targeting students and youth. Key dates and milestones are provided for measurement, analysis, improvement and control phases to enhance the app experience and competitive advantage by November 4th 2021.

Uploaded by

Shouvik Dutta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views1 page

Project Charter

The document discusses improving an online meeting application. It aims to increase downloads and ratings by targeting students and youth. Key dates and milestones are provided for measurement, analysis, improvement and control phases to enhance the app experience and competitive advantage by November 4th 2021.

Uploaded by

Shouvik Dutta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Product or Service Online Meeting

Impacted Platform
applicaton
COMPANY ZOOM MEETING APP
NAME
Start Date 17-10-2021 Target 4-11-2021
Element Description Team Charter
The process in
which opportunity A mobile and desktop application for meeting This help to
1. Process:
exists. connect among the individuals with lot of features
specially used in academic purpose. Our target is to
youths and students.
Bhagwati Industries manufactures around 700 to 800 sets of
Expected financial
Orfeo interiors on daily basis. Many a times there are few errors
2. Business Cases: improvement, or
which if passed on to customers may result into incurring
other justification
financial loss and customer dissatisfaction.
3. Project
Due to massive use of Google meet because of easy-to-use
Description: what
Problem statement features. The popularity of zoom as Chinese app going down.
is the “Practical
Problem”
Project's Baseline GOAL Units
What improvement
Rework Rate 40% 8% Percent
is targeted?
The “Statistical
4. Objective
Problem” - the
Sigma Level 3.1 3.5 Sigma Level
measurable
variable(s)
Rework Cost 10,600 2120 Rupees
Names and roles of
5. Team members: Mohit Kumar Mahato, Rahul Raj, Shouvik Dutta, Anuska Paul
team members?
Which part of the
process will be
6. Project Scope:
investigated and Higher number of downloads on google and app store
excluded. Targeting on getting 4-5 stars rating on app store.
Future planning to add new interactive features.
Who are the final
customers, what
7. Benefit to
are their key Improve in rating in app stores, better user experience,
External
measures, and what Competitive advantages, better brand and company image
Customers
benefits will they?
see?
Give the key
Project Start "D" Phase 17-10-2021
milestones/dates
M- Measurement “M” Completion 25-10-2021
8. Schedule A- Analysis “A” Completion 28-10-2021
I- Improvement “I” Completion 2-11-2021
C- Control “C” Completion 4-11-2021