0% found this document useful (0 votes)
1K views35 pages

How To Perform The Load Flow Analysis of IEEE 9 Bus System MATPOWER

The document discusses how to perform load flow analysis of a test power system using the MATPOWER toolbox. It describes various load flow methods, provides instructions to download and install MATPOWER, and lists many test cases that are built into the toolbox.

Uploaded by

Muhammet Alkaş
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views35 pages

How To Perform The Load Flow Analysis of IEEE 9 Bus System MATPOWER

The document discusses how to perform load flow analysis of a test power system using the MATPOWER toolbox. It describes various load flow methods, provides instructions to download and install MATPOWER, and lists many test cases that are built into the toolbox.

Uploaded by

Muhammet Alkaş
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 35

How to Perform Load Flow

Analysis of IEEE-9 Bus Test


System using MATPOWER

By: Dr. J. A. Laghari


 Load Flow Analysis of IEEE-9 Bus System Using

Newton
Gauss-Seidel
Raphson
Method
Method

Fast
Decoupled
Method
How to Download &
Install MATPOWER
Toolbox Completely
Free
By: Dr. J. A. Laghari
Built-in 59 Cases of Various Test
Systems in MATPOWER Toolbox
 Built-in Case List in MATPOWER Toolbox
 All of the functions (cases) listed in MATPOWER Toolbox can be found in
<MATPOWER>/data.
Table D-18: Small Transmission System Test Cases
Case Name Description
case4gs 4-bus example case from Grainger & Stevenson

case5 modified 5-bus PJM example case from Rui Bo

case6ww 6-bus example case from Wood & Wollenberg

case9 9-bus example case from Chow

case9Q case9 with reactive power costs

Source: MATPOWER User Manual 7.0, Page 188


 Built-in Case List in MATPOWER Toolbox
Table D-18: Small Transmission System Test Cases
Case Name Description
modified case9, target for example continuation power flow
case9target
case14 IEEE 14-bus case

case24_ieee_rts IEEE RTS 24-bus case

case30 30-bus case, based on IEEE 30-bus case

case_ieee30 IEEE 30-bus case

case30pwl case30 with piecewise linear costs

case30Q case30 with reactive power costs

Source: MATPOWER User Manual 7.0, Page 188


 Built-in Case List in MATPOWER Toolbox
Table D-18: Small Transmission System Test Cases
Case Name Description
case39 39-bus New England case

case57 IEEE 57-bus case

case_RTS_GMLC 96-machine, 73-bus Reliability Test System

case118 IEEE 118-bus case

case145 IEEE 145-bus case, 50 generator dynamic test


case
case300 IEEE 300-bus case

Source: MATPOWER User Manual 7.0, Page 188


 Built-in Case List in MATPOWER Toolbox
Table D-19: Small Radial Distribution System Test Cases
Case Name Description
case4_dist 4-bus example radial distribution system case

case18 18-bus radial distribution system from Grady,


Samotyj and Noyola
case22 22-bus radial distribution system from Raju,
Murthy and Ravindra
case33bw 33-bus radial distribution system from Baran
and Wu
case69 69-bus radial distribution system from Das

case85 85-bus radial distribution system from Das,


Kothari and Kalam
case141 141-bus radial distribution system from Khodr,
Olsina, De Jesus and Yusta
Source: MATPOWER User Manual 7.0, Page 188
 Built-in Case List in MATPOWER Toolbox
Table D-20: ACTIV Synthetic Grid Test Cases
Case Name Description
case_ACTIVSg200 200-bus Illinois synthetic model

case_ACTIVSg500 500-bus South Carolina synthetic model

case_ACTIVSg2000 2000-bus Texas synthetic model

case_ACTIVSg10k 10,000-bus US WECC synthetic model

case_ACTIVSg25k 25,000-bus US Northeast/Mid-Atlantic synthetic


model
case_ACTIVSg70k 70,000-bus Eastern US synthetic model

Case_SyntheticUSA 82,000-bus continental USA synthetic model

Source: MATPOWER User Manual 7.0, Page 189


 Built-in Case List in MATPOWER Toolbox
Table D-20: ACTIV Synthetic Grid Test Cases
Case Name Description
contab_ACTIVSg200 contingency table for case ACTIVSg200

contab_ACTIVSg500 contingency table for case ACTIVSg500

contab_ACTIVSg2000 contingency table for case ACTIVSg2000

contab_ACTIVSg10k contingency table for case ACTIVSg10k

scenarios_ACTIVSg200 one year of hourly zonal load scenarios for case


ACTIVSg200
scenarios_ACTIVSg2000 one year of hourly area load scenarios for case
ACTIVSg2000

Source: MATPOWER User Manual 7.0, Page 189


 Table D-21: Polish System Test Cases
Case Name Description
case2383wp Polish system - winter 1999-2000 peak

case2736sp Polish system - summer 2004 peak

case2737sop Polish system-summer 2004 off-peak

case2746wop Polish system - winter 2003-04 off-peak

case2746wp Polish system - winter 2003-04 evening peak

case3012wp Polish system - winter 2007-08 evening peak

case3120sp Polish system - summer 2008 morning peak

case3375wp Polish system plus - winter 2007-08 evening


peak
Source: MATPOWER User Manual 7.0, Page 189
 Built-in Case List in MATPOWER Toolbox
Table D-22: PEGASE European System Test Cases
Case Name Description
case89pegase 89-bus portion of European transmission
system from PEGASE project
case1354pegase 1354-bus portion of European transmission
system from PEGASE project
case2869pegase 2869-bus portion of European transmission
system from PEGASE project
case9241pegase 9241-bus portion of European transmission
system from PEGASE project*
case13659pegase 13659-bus portion of European transmission
system from PEGASE project

Source: MATPOWER User Manual 7.0, Page 190


 Table D-23: RTE French System Test Cases
Case Name Description
case1888rte 1888-bus snapshot of VHV French transmission
system from RTE
case1951rte 1951-bus snapshot of VHV French transmission
system from RTE
case2848rte 2848-bus snapshot of VHV French transmission
system from RTE
case2868rte 2868-bus snapshot of VHV French transmission
system from RTE
case6468rte 6468-bus snapshot of VHV and HV French
transmission system from RTE
case6470rte 6470-bus snapshot of VHV and HV French
transmission system from RTE
case6495rte 6495-bus snapshot of VHV and HV French
transmission system from RTE
case6515rte 6515-bus snapshot of VHV and HV French
transmission system from RTE
Source: MATPOWER User Manual 7.0, Page 190
 How to Load data of any case
 Syntax to Load a Case:
 mpc = loadcase(casefilename);
 Where mpc stands for matpower case.

 Syntax to Load IEEE-9 Bus Test System Case:


 The M-file name for IEEE-9 Bus test name is case9 as mentioned in the
previous Table. Therefore, its syntax will become:
 mpc = loadcase(case9);
 This will open the structure file of IEEE 9 bus test system with its all data.

Source: MATPOWER User Manual 7.0, Page 20


 How to Open M-file of a case:
 All of the functions (cases) listed in MATPOWER Toolbox can be found in
<MATPOWER>/data.
 Go to <MATPOWER>/data folder in MATLAB. Double click on any M-file of a
case. It will be opened.

Source: MATPOWER User Manual 7.0, Page 20


 Single Line Diagram of IEEE 9 Bus Test System:
Bus2 T2 Bus7 Bus8 Bus9 T3 Bus3
250 MVA 150 MVA
Gen 2 19 kV / 230 kV 13.8 kV / 230 kV

Gen 3

Bus5 Bus6

Bus4

T1
100 MVA
16.5 kV / 230 kV

Bus1

Gen1
 Line Data of
IEEE 9 Bus
Test System:
 It is also known as Western
System Coordinating
Council (WECC)
3-Machine, 9-bus system

Source: Power System Control and Stability


by P. M. Anderson, Chapter 2. Page No. 38
 Line Data
of IEEE 9
Bus Test
System:

Source: Power System Dynamics and


Stability by Peter W. Sauer and M. A. Pai,
Chapter 7. Example 7.1, Page No. 164-165.
 Bus Data of IEEE-9 Bus System
Bus No. Bus Code Voltage Generation Load
(P.U.) MW Mvar MW Mvar
1 3 (Slack) 1.04 0 0 0 0
2 2 (PV) 1.025 163 6.7 0 0
3 2 (PV) 1.025 85 -10.9 0 0
4 1 (PQ) 1 0 0 0 0
5 1 (PQ) 1 0 0 125 50
6 1 (PQ) 1 0 0 90 30
7 1 (PQ) 1 0 0 0 0
8 1 (PQ) 1 0 0 100 35
9 1 (PQ) 1 0 0 0 0
 In MATPOWER Toolbox, Bus Code 1 = PQ bus; Bus Code 2 = PV Bus
 Bus Code 3 = Slack Bus
 Line or Branch Data of IEEE-9 Bus System
Line Line
R X ½B B
From To
1 4 0 0.0576 0 0
4 5 0.01 0.085 0.088 0.176
4 6 0.017 0.092 0.079 0.158
6 9 0.039 0.17 0.179 0.358
5 7 0.032 0.161 0.153 0.306
9 3 0 0.0586 0 0
7 2 0 0.0625 0 0
9 8 0.0119 0.1008 0.1045 0.209
7 8 0.0085 0.072 0.0745 0.149
 How to Perform Load Flow Analysis in MATPOWER
 Syntax to Run the load flow analysis of a Case:
 runpf('casefilename');
 Syntax to Run Load Flow Analysis of IEEE9 Bus Test System Case:
 The M-file name for IEEE-9 Bus test name is case9 as mentioned in the
previous Table. Therefore, its syntax will become:
 runpf('case9');
 By default it will perform the Load Flow Analysis using Newton Raphson
Method.

Source: MATPOWER User Manual 7.0, Page 20


 Voltage, Power
Flows of IEEE
9 Bus Test
System:

Source: Power System Control and Stability


by P. M. Anderson, Chapter 2. Page No. 38
 Voltage, Power Flows of IEEE 9 Bus Test System:

Source: Power System Dynamics and


Stability by Peter W. Sauer and M. A. Pai,
Chapter 7. Example 7.1, Page No. 164-165.
 Load Flow Solution of IEEE-9 Bus System
Bus No. Generation Load Bus Voltage
MW Mvar MW Mvar Voltage(p.u.) Angle
1 71.6 27.0 0 0 1.04 0
2 163 6.7 0 0 1.025 9.3°
3 85 -10.9 0 0 1.025 4.7°
4 0 0 0 0 1.026 -2.2°
5 0 0 125 50 0.996 -4.0°
6 0 0 90 30 1.013 -3.7°
7 0 0 0 0 1.026 3.7°
8 0 0 100 35 1.016 0.7°
9 0 0 0 0 1.032 2.0°
How to Perform Load Flow
Analysis using Gauss-Seidel Method
 How to Perform Load Flow Analysis in MATPOWER
 Syntax to Change the Type of Load Flow Method of a Case:
 mpopt = mpoption('pf.alg', 'LFName');
 results = runpf('casefilename', mpopt);
 Where mpopt = matpower option.
 Pf.alg = power flow analysis algorithm.
 Lfname = name of the load flow analysis method.

Source: MATPOWER User Manual 7.0, Page 20


 Table 4-2: Power Flow Options
Name Default Description

model 'AC' AC vs. DC modeling for power flow and OPF formulation
'AC' --- use AC formulation and corresponding alg options
'DC' ---- use DC formulation and corresponding alg options
pf.alg 'NR' AC Power Flow algorithm:
'NR' --- Newtons's method (formulation depends on values of
pf.current_balance and pf.v_cartesian options)
'NR-SC' --- Newtons's method (power mismatch, cartesian)
'NR-IP' --- Newtons's method (current mismatch, polar)
'NR-IC' --- Newtons's method (current mismatch, cartesian)
'FDXB' --- Fast-Decoupled (XB version)
'FDBX' --- Fast-Decouple (BX version)
'GS' --- Gauss-Seidel

Source: MATPOWER User Manual 7.0, Page 45


 How to Perform Load Flow Analysis in MATPOWER

 Syntax to Change the Load Flow Method to Gauss


Seidel Method for IEEE-9 Bus Test System:

 mpopt = mpoption('pf.alg', 'GS');


 results = runpf('case9', mpopt);
How to Perform Load Flow Analysis
using Fast Decoupled Method
 How to Perform Load Flow Analysis in MATPOWER

 Syntax to Change the Load Flow Method to Fast Decoupled


Method (BX Version) for IEEE-9 Bus Test System:

 mpopt = mpoption('pf.alg', 'FDBX');


 results = runpf('case9', mpopt);
 How to Perform Load Flow Analysis in MATPOWER

 Syntax to Change the Load Flow Method to Fast Decoupled


Method (XB Version) for IEEE-9 Bus Test System:

 mpopt = mpoption('pf.alg', 'FDXB');


 results = runpf('case9', mpopt);
How to Perform Load Flow Analysis
using Newton Raphson Method
 How to Perform Load Flow Analysis in MATPOWER

 Syntax to Change the Load Flow Method to Newton


Raphson Method for IEEE-9 Bus Test System:

 mpopt = mpoption('pf.alg', 'NR');


 results = runpf('case9', mpopt);
 Performance Comparison of Different Load Flow
Methods
THANK YOU VERY MUCH