Unit 1 Section 1.1 Introduction To Chemical Processing Plants
Unit 1 Section 1.1 Introduction To Chemical Processing Plants
UNIT 1: 10 / 102
OUTLINE
UNIT 1: 11 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
UNIT 1: 12 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
UNIT 1: 13 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
2 Add-on project:
They are built within an existing complex or built around the main
project, such projects could be an addition of a new facility or, a
backward or, a forward integration or, altogether a new product line
around an existing or, expanded structure of utilities.
UNIT 1: 15 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
UNIT 1: 16 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
UNIT 1: 17 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
DEFINITIONS
UNIT 1: 18 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
Process Design
UNIT 1: 19 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
Process Design
UNIT 1: 20 / 102
INTRODUCTION TO CHEMICAL PROCESSING PLANTS
Process Equipment
UNIT 1: 21 / 102
PROCESS DEVELOPMENT
UNIT 1: 22 / 102
PROCESS DEVELOPMENT
UNIT 1: 23 / 102
PROCESS DEVELOPMENT
It is the creative part of the design process. This part is concerned with
the generation of possible solutions for analysis, evaluation, and selection
(ways of meeting objective problems).
Source of solutions:
1 Past experiences.
2 Tried and tested methods.
UNIT 1: 25 / 102
PROCESS DEVELOPMENT
In some cases, the performance model may include a pilot plant or other
facility for predicting plant performance and collecting design data.
Once the designer has identified a few candidate designs that meet the
customer objective, then the process of design selection can begin. The
primary criterion for design selection is usually economic performance,
although factors such as safety and environmental impact may also play a
strong role. The economic evaluation usually entails analyzing the capital
and operating costs of the process to determine the return on investment
(R.O.I).
When all of the candidate designs have been optimized, the best design
can be selected. Very often, the design engineer will find that several
designs have very close economic performance, in which case the safest
design or that which has the best commercial track record will be chosen.
UNIT 1: 27 / 102
PROCESS DEVELOPMENT
UNIT 1: 28 / 102
PROCESS DEVELOPMENT
When the details of the design have been finalized, the equipment can be
purchased and the plant can be built. Procurement and construction are
usually carried out by an EPC firm (Engineering, Procurement, and
Construction) unless the project is very small. Because they work on many
different projects each year, the EPC firms are able to place bulk orders for
items such as piping, wire, valves, etc., and can use their purchasing power
to get discounts on most equipment.
Design Constraints
When considering possible ways of achieving the objective the designer will
be constrained by many factors which are called the design constraints.
Design constraints are divided into two types Fig.below shows possible
constraints:
1 Internal constraints: over which the designer has some control.
2 External constraints: fixed, invariable
UNIT 1: 30 / 102
PROCESS DEVELOPMENT
Design Constraints
UNIT 1: 31 / 102
STAGES OF PROCESS PLANT DESIGN
UNIT 1: 32 / 102
STAGES OF PROCESS PLANT DESIGN
Conceptual Design
UNIT 1: 33 / 102
STAGES OF PROCESS PLANT DESIGN
Equipment Design
UNIT 1: 34 / 102
STAGES OF PROCESS PLANT DESIGN
Equipment design
UNIT 1: 35 / 102
STAGES OF PROCESS PLANT DESIGN
Hazard analysis
Environment
Figure: Environment
UNIT 1: 37 / 102
STAGES OF PROCESS PLANT DESIGN
A large body of rules has been developed over the years to ensure the
safe and economical design, fabrication, and testing of equipment,
structures, and materials.
Codification of these rules has been done by associations organized
for just such purposes, by professional societies, trade groups,
insurance underwriting companies, and government agencies.
In engineering standardization covers:
Materials, properties and composition
Testing procedures for performance, composition and quality
Preferred sizes, for example, tubes, plates, selection, etc.
Methods for design, inspection and fabrication
Codes of practice for plant operation and safety
UNIT 1: 38 / 102
STAGES OF PROCESS PLANT DESIGN
UNIT 1: 39 / 102
STAGES OF PROCESS PLANT DESIGN
Advantages of standardization
UNIT 1: 40 / 102
STAGES OF PROCESS PLANT DESIGN
Disadvantages of standardization
UNIT 1: 41 / 102
STAGES OF PROCESS PLANT DESIGN