BOD - Final Rates Standardization
BOD - Final Rates Standardization
BOD - Final Rates Standardization
Bureau of Design
1.0 INTRODUCTION
1.1 Background
The Department of Public Works and Highways (DPWH), as the engineering and
construction arm of the Government, is widely engaged in consulting services for
various proposed infrastructure projects. The Bureau of Design (BOD), under the
Technical Services of the DPWH, is among the offices of the Department constantly
engaged in procuring and administering consulting services contracts.
While reviewing and preparing proposed Approved Budgets for the Contracts (ABCs)
for consultancy projects, difficulties have been continuously encountered which
hamper down either the preparation or the review process. Such are attributed to
the lack of established Standardized Billing Rates which should have been a reliable
and easy reference for the preparation of ABCs or for the review of such documents
referred to the Bureau.
Thus, this study hereby presents the Standardization of Remuneration Rates for the
preparation of ABCs for Consulting Services for Detailed Engineering Design (DED)
and/or other Special Studies to be proposed by or delegated to the BOD. Such rates
shall also be used as reference for other ABCs for Master Planning, Feasibility
Studies, and DED referred to this Bureau for review.
1.2 Rationale
In addition, the DPWH shall have a single approved reference document which shall
uphold accuracy and consistency both in the preparation of ABCs for Consultancy
Standardization of Remuneration Rates for Consulting Services for
Locally Funded Infrastructure Projects Proposed by the DPWH
Page 2 of 25
Contracts to be administered by the BOD, and in the review of ABCs being proposed
by DPWH Implementing Units (IUs) and other agencies being referred to the Bureau.
Ultimately, the standardized rates shall help meet the Department’s earnest desire to
observe timely and successful implementation of various DPWH proposed
infrastructure projects and services, especially those requiring consulting services,
which shall improve the lives of the Filipino people.
1.3 Objectives
Specifically, this proposal aims to establish standard remuneration rates for Key
Personnel and their Support Staff using relevant guidelines and references discussed
in this study.
The study focused on remuneration rates for consulting services for locally-funded
infrastructure projects under master planning, feasibility studies, and detailed
engineering design.
For purposes of this proposal, the following terms or words and phrases shall mean
or be understood as follows:
Approved Budget for the - refers to the proposed budget for the consultancy
Contract (ABC) project approved by the Head of the Procuring
Entity
Social Charges - cost items for the welfare and benefit of the
consultant’s staff in accordance with the policies of
the consultant and the government. They are
expressed as a percentage of the basic rates of the
consultant’s personnel
In the preparation of the proposed Remuneration Rates, the following three references were
used to derive a set or remuneration rates from each:
Department Order No. 151 s.2016 prescribes the use of 2016 DPWH Procurement
Manual in the procurement of Contracts for Infrastructure, Consulting Services, and
Goods and Services. The said procurement manual comes in four volumes. Volume 3
Standardization of Remuneration Rates for Consulting Services for
Locally Funded Infrastructure Projects Proposed by the DPWH
Page 4 of 25
specifies relative guidelines for Consulting Services including the preparation of ABCs
under which the first set of remuneration rates is based. The procurement manual is
consistent with the provisions of Republic Act No. 9184 (Government Procurement
Reform Act) and its Implementing Rules and Regulations.
The second set of proposed remuneration rates were obtained using previously
approved ABCs for locally funded DPWH Consulting Services for Master Planning,
Feasibility Studies, and Detailed Engineering Design.
The third set of derived remuneration rates were obtained from the standard range
of rates used by the Council of Engineering Consultants of the Philippines
(CECOPHIL) – an organization in the local consulting industry, consisting of Filipino
and multi-national engineering firms doing various technical consulting work for both
the government and private sectors in the Philippines and abroad.
Three sets were obtained which thereafter were averaged to obtain a single set of
remuneration rates herein specified to be the standard remuneration rates for the
procurement of consulting services for locally funded infrastructure projects proposed by the
Department.
Using the abovementioned references, a set of remuneration rates was derived from each,
totaling to three (3) sets. Each set was derived differently from each other considering the
nature of the reference used. In order to arrive at a single set of remuneration rates, the
three sets were then averaged to derive the final set of rates.
For simplicity and consistency of the study and its application in view of the number and
diversity of position titles of the consultant’s personnel, the study grouped the various
consultant position titles, with their corresponding derived final set of rates, under the
following categories:
Administrative Officer
ADMINSTRATIVE
SUPPORT STAFF
Secretary/Encoder
The DPWH Procurement Manual describes remuneration costs as the product of the
basic salary rates of the staff multiplied by a billing factor. Such billing factor is
derived from several components which are projected as percentage of the Basic
Salaries. Corresponding limits, for the components and the resulting billing factors
for both Technical and Administrative Personnel, as specified by the manual is
summarized by the table below:
Since the Billing Factor Range is the primary determinant of the projected social
charges, overhead, and management fee, the maximum limits prescribed by the
manual were used. Thus, 2.50 for Technical Personnel and 1.80 for Administrative
Personnel.
In order to come up with a basic salary rates for the consultant’s personnel, each
group/category of consultant staffing were assigned a comparable DPWH position
title together its corresponding Salary Grade (SG) at Step 01. Such were based in
the modified Standard Salary Schedule for the current year 2017 as specified by
Executive Order 201 s. 2016 which presents the existing prevailing government
salary rates at the time of study. Appendix “A” shows the entire salary
standardization schedule as reference.
The table below shows the matrix of Consultant’s position titles and the assigned
basic salaries from DPWH Position titles compared to each group of personnel:
Standardization of Remuneration Rates for Consulting Services for
Locally Funded Infrastructure Projects Proposed by the DPWH
Page 6 of 25
KEY STAFF
Currently, there is no CAD Operator item in DPWH. However, per DBM Classification
and Position Titles (Appendix “B”), Draftsman III was selected as comparable
position title in government.
The tables on the following pages shows the derivation of billing rates for the
Technical Personnel using DPWH Procurement Manual:
Standardization of Remuneration Rates for Consulting Services for Locally Funded Infrastructure Projects Proposed by the DPWH
Page 7 of 25
3. Senior Infra Positions Engineer V SG 24-01 64,416.00 12,883.20 61,195.20 138,494.40 20,774.16 159,268.56 2.47
4. Other Infra Positions Engineer IV SG 22-01 52,783.00 10,556.60 50,143.85 113,483.45 17,022.52 130,505.97 2.47
5. Junior Infra Positions Engineer II SG 16-01 30,044.00 6,008.80 28,541.80 64,594.60 9,689.19 74,283.79 2.47
6. CAD Operator Draftsman III SG 11-01 19,620.00 3,924.00 18,639.00 42,183.00 6,327.45 48,510.45 2.47
Since values assigned were only an indicative projection, the Overhead was given a percentage value at a multiple of 5%. The Social Charges
and Management Fee were prioritized and given their respective maximum allowable values, since they cater to the basic needs of the
personnel and the profit-orientation of private consultancy firms, respectively. The Overhead was then adjusted to obtain a billing factor
nearest to the target billing factor 2.50 as discussed earlier. 2.47 was the computed billing factor resulting from the assigned values of the
billing factor components. Column (F) shows the proposed billing rate obtained using 20%, 95%, and 15% values for Social Charges,
Overhead, and Management Fee, respectively.
Standardization of Remuneration Rates for Consulting Services for Locally Funded Infrastructure Projects Proposed by the DPWH
Page 8 of 25
The following table shows the derivation of billing rates for the Administrative Support Staff:
Admin. Officer
1. Administrative Officer SG 15-01 27,565.00 5,513.00 9,647.75 42,725.75 6,408.86 49,134.61 1.78
IV
2. Secretary/Encoder Admin. Aide VI SG 06-01 13,851.00 2,770.20 4,847.85 21,469.05 3,220.36 24,689.41 1.78
Applying the same procedures as that from the Technical Staff, Column (F) shows the proposed billing rate obtained using 20%, 35%, and
15% values for Social Charges, Overhead, and Management Fee, respectively, to meet a target billing factor not greater than 1.80. 1.78 was
the computed billing factor resulting from the assigned values.
Standardization of Remuneration Rates for Consulting Services for
Locally Funded Infrastructure Projects Proposed by the DPWH
Page 9 of 25
In summary, the computed remuneration rates using DPWH Procurement Manual are
as follows:
COMPUTED BILLING
CATEGORY
RATES (PHP)
KEY STAFF
Secretary/Encoder 24,689.41
The second set of remuneration rates were derived using DPWH approved billing
rates from ABCs for locally-funded consulting services for infrastructure projects from
the past years. Data were gathered from different implementing units of consultancy
contracts. Locally-funded Master Planning, Feasibility Studies, and Detailed
Engineering Design Consultancy Services were considered and selected as reference
for this purpose. Appendix “C” lists the previous projects used in this study.
The said billing rates from the ABCs were compared. Corresponding and equivalent
position titles from the said ABCs were examined to select the highest approved rate
to be used in this study. In case the highest approved rate was used in different
years, the year wherein the rate was initially approved was selected as the reckoning
year in view of the application of inflation rates.
Considering also that the selected rates were approved and implemented different
years in the past, inflation was considered and factored in the computation to
estimate the present value of each billing rate. Average yearly inflation rates used
were the summarized rates supplied by the Philippine Statistics Authority (PSA) to
the Bangko Sentral ng Pilipinas (BSP) shown in the next page:
Standardization of Remuneration Rates for Consulting Services for Locally Funded Infrastructure Projects Proposed by the DPWH
Page 10 of 25
34 INFLATION RATES
(2006 = 100)
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Average 9.4 6.0 6.7 5.3 2.7 2.3 4.8 6.5 5.5 2.9 8.3 4.2 3.8 4.6 3.2 3.0 4.1 1.4 1.8 3.1
January 6.6 10.7 5.5 5.8 3.3 1.9 2.9 7.3 5.9 3.8 4.6 7.1 3.9 4.0 4.0 3.1 4.2 2.4 1.3 2.7
February 7.7 9.3 5.6 5.8 2.9 2.3 2.9 7.3 6.5 2.9 5.1 7.2 3.9 4.7 2.7 3.4 4.1 2.5 0.9 3.3
March 8.2 7.9 5.9 5.8 3.3 2.1 3.1 7.1 6.6 2.6 5.9 6.6 3.9 4.9 2.6 3.2 3.9 2.4 1.1 3.4
April 8.7 7.4 6.2 5.5 3.4 2.2 3.2 7.2 6.3 2.6 7.3 5.6 4.0 4.7 3.0 2.6 4.1 2.2 1.1 3.4
May 9.6 6.3 6.5 5.5 3.2 2.2 3.6 7.3 6.0 2.7 8.2 4.3 3.9 4.9 3.0 2.6 4.5 1.6 1.6 3.1
r
June 10.2 5.3 6.1 5.9 2.6 2.8 4.1 6.7 5.9 2.6 9.4 3.2 3.6 5.2 2.9 2.7 4.4 1.2 1.9 2.7
July 10.1 5.1 6.5 6.0 2.5 2.3 5.5 6.0 5.5 2.9 10.2 2.2 3.7 4.9 3.2 2.5 4.9 0.8 1.9 2.8
August 10.1 4.8 6.8 5.7 2.7 2.2 5.7 6.1 5.2 2.7 10.5 1.7 4.1 4.6 3.8 2.1 4.9 0.6 1.8
September 10.2 4.9 6.5 5.7 2.5 2.2 6.2 6.0 4.9 2.9 10.1 2.3 3.8 4.7 3.7 2.7 4.4 0.4 2.3
October 10.0 5.2 6.7 5.2 2.3 2.3 6.3 6.2 4.7 2.9 9.7 2.9 3.2 5.2 3.2 2.9 4.3 0.4 2.3
November 10.6 3.9 7.8 4.2 2.1 2.4 6.8 6.2 4.2 3.1 9.1 3.5 3.7 4.7 2.8 3.3 3.7 1.1 2.5
December 10.0 3.9 8.7 3.7 2.1 2.5 7.1 5.9 4.1 3.7 7.8 4.4 3.6 4.2 3.0 4.1 2.7 1.5 2.6
http://www.bsp.gov.ph/statistics/spei_new/tab34_inf.htm
Standardization of Remuneration Rates for Consulting Services for Locally Funded Infrastructure Projects Proposed by the DPWH
Page 11 of 25
The table below shows the highest approved billing rates for each position titles used in different MP, FS, and DED projects. The table also
shows the year they were initially approved/used in projects. Inflation was factored in accordingly.
INFLATION RATES
APPROVED
PERSONNEL BILLING YEAR 2010 2011 2012 2013 2014 2015 2016 2017
RATE
3.80% 4.60% 3.20% 3.00% 4.10% 1.40% 1.80% 3.10%
KEY STAFF
Team Leader/Project
150,000.00 2010 150,000.00 156,900.00 161,920.80 166,778.42 173,616.34 176,046.97 179,215.81 184,771.50
Manager
Senior Highway Engineer 95,000.00 2013 95,000.00 98,895.00 100,279.53 102,084.56 105,249.18
Senior Coastal Engineer 154,800.00 2013 154,800.00 161,146.80 163,402.86 166,344.11 171,500.77
Senior Transport
100,000.00 2015 100,000.00 101,800.00 104,955.80
Planner/Traffic Engineer
Senior Slope/ Landslide
90,000.00 2013 90,000.00 93,690.00 95,001.66 96,711.69 99,709.75
Engineer
Senior Geotechnical
125,000.00 2016 125,000.00 128,875.00
Engineer
Standardization of Remuneration Rates for Consulting Services for Locally Funded Infrastructure Projects Proposed by the DPWH
Page 12 of 25
Senior Soils/Materials
120,000.00 2016 120,000.00 123,720.00
Engineer
Senior Electronic
90,000.00 2013 90,000.00 93,690.00 95,001.66 96,711.69 99,709.75
Communication Engineer
Agricultural/Irrigation
80,000.00 2015 80,000.00 81,440.00 83,964.64
Engineer
Senior Cost/Specs/Quantity
120,000.00 2016 120,000.00 123,720.00
Engineer
Senior Environment
120,000.00 2016 120,000.00 123,720.00
Specialist
Community Development
130,000.00 2015 130,000.00 132,340.00 136,442.54
Specialist
Resettlement
120,000.00 2016 120,000.00 123,720.00
Specialist/Sociologist
TECHNICAL SUPPORT STAFF
Document Specialist
60,000.00 2015 60,000.00 61,080.00 62,973.48
(Support Staff)
ADMINISTRATIVE SUPPORT STAFF
From all the ABCs considered, it can be noted that the prevailing rates for the position titles of were obtained from approved MP, FS,
and DED consultancy projects since year 2013, except for the Project Manager of which the highest approved billing rate of
Php150,000.00 was already used since 2010. Respective inflation rates of the succeeding years were factored in and compounded for
each billing rate to obtain the projected current value for each rate.
Standardization of Remuneration Rates for Consulting Services for
Locally Funded Infrastructure Projects Proposed by the DPWH
Page 14 of 25
In summary, the computed remuneration rates using the highest approved rates are
shown below:
COMPUTED
CATEGORY BILLING RATES
(PHP)
KEY STAFF
Architect 99,709.75
Senior Electrical Engineer 104,955.80
Mechanical Engineer 104,955.80
Socio-Economist 99,708.01
Gender Specialist 123,720.00
Standardization of Remuneration Rates for Consulting Services for
Locally Funded Infrastructure Projects Proposed by the DPWH
Page 15 of 25
Secretary/Encoder 31,927.55
Researcher 52,477.90
Utility man 20,991.16
Considering the purpose of this study, the specified minimum rates for Government
contracts were selected. In preparation of the third set of remuneration rates,
inflation was also considered in the same manner as that of the preceding derivation
for the second set.
GOVERNMENT
RATES
(Minimum) AVERAGE INFLATION RATES
(Php per
POSITION/LEVEL Month)
2016 2017
2015
1.80% 3.10%
1.0 PRINCIPAL
3.1 Engineer/Architect
In summary, the derived current values for the 2015 CECOPHIL Rates Table are as follows:
COMPUTED BILLING
CATEGORY
RATES (PHP)
1.0 PRINCIPAL
3.1 Engineer/Architect
Standardization of Remuneration Rates for Consulting Services for
Locally Funded Infrastructure Projects Proposed by the DPWH
Page 19 of 25
From the three sets of remuneration rates derived using various guidelines and
references, a final set of billing rates was obtained therefrom by averaging. This final
set shall be specified as the standard monthly remuneration for locally funded
consulting services for Master Planning, Feasibility Studies and Detailed Engineering
Design.
In order to reconcile the three sets, the position titles were grouped according to the
categories discussed in Section 3 of this study. Rates of corresponding position titles
were averaged to obtain a single value. For simplicity, the resulting rate was then
rounded to the nearest multiple of Php5000.00. The following table shows the
consolidated rates using the three sets derived from DPWH Highest Approved Rates,
DPWH Procurement Manual, and CECOPHIL Rates:
Standardization of Remuneration Rates for Consulting Services for Locally Funded Infrastructure Projects Proposed by the DPWH
Page 21 of 25
DPWH AVERAGE
DPWH AVERAGE
Highest CECOPHIL RATE per
POSITION TITLE / CATEGORY Procurement RATE per Say
Approved Rates Position
Manual Position Title
Rates Category
KEY STAFF
Project Manager / Team Leader 184,771.50 195,228.60 163,731.05 181,243.72 181,243.72 180,000.00
Deputy Project Manager / Team Leader 134,030.00 176,724.41 - 155,377.21 155,377.21 155,000.00
The table below shows the resulting proposed Remuneration Rates for the position
titles/categories proposed by this study and shall be specified as the standard reference for
monthly remuneration rates for locally-funded consulting services for Master Planning,
Feasibility Studies and Detailed Engineering Design.
REMUNERATION
POSITION TITLE / CATEGORY
(PHP per Month)
KEY STAFF
Secretary/Encoder 35,000.00
Standardization of Remuneration Rates for Consulting Services for
Locally Funded Infrastructure Projects Proposed by the DPWH
Page 25 of 25
5.0 SUMMARY
REMUNERATION
POSITION TITLE / CATEGORY
(PHP per Month)
KEY STAFF
Project Manager / Team Leader 180,000.00
Deputy Project Manager / Team Leader 155,000.00
Senior Infra Positions 135,000.00
Other Infra Positions 120,000.00
TECHNICAL SUPPORT STAFF
Junior Infra Positions 90,000.00
CAD Operator 60,000.00
ADMINISTRATIVE SUPPORT STAFF
Administrative Officer 55,000.00
Secretary/Encoder 35,000.00
6.0 RECOMMENDATIONS
Since this study scoped only the standardization of remuneration rates for consulting
services for master planning, feasibility studies, and detailed engineering design for
locally-funded infrastructure projects, it is recommended that the standardization of
rates for construction supervision and foreign-funded infrastructure projects be
explored in further studies. It is also recommended that further studies may also
focus on standardization of rates for highly technical projects.
Prepared by:
DANTE B. POTANTE
Director IV
Bureau of Design
REFERENCES
Approved DPWH Rates for Consulting Services. DPWH BAC for Consulting Services and Various
Consultancy Implementing Units.
DPWH Procurement Manual Volume 3: Consulting Services. Department of Public Works and
Highways.
Executive Order 201 s. 2016: Modifying the Salary Schedule for Civilian Government Personnel
and Authorizing the Grant of Additional Benefits for Both Civilian and Military and Uniformed
Personnel. Official Gazette of the Republic of the Philippines.
<http://www.officialgazette.gov.ph/2016/02/19/executive-order-no-201-s-2016/>
Second Tranche
Salary
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Step 7 Step 8
Grade
1 9,981 10,072 10,165 10,258 10,352 10,453 10,543 10,640
2 10,667 10,761 10,856 10,952 11,049 11,147 11,245 11,345
3 11,387 11,488 11,589 11,691 11,795 11,899 12,004 12,110
4 12,155 12,262 12,371 12,480 12,591 12,702 12,814 12,927
5 12,975 13,117 13,206 13,322 13,440 13,559 13,679 13,799
6 13,851 13,973 14,096 14,221 14,347 14,474 14,602 14,731
7 14,785 14,916 15,048 15,181 15,315 15,450 15,587 15,725
8 15,818 15,969 16,121 16,275 16,430 16,586 16,744 16,903
9 16,986 17,142 17,299 17,458 17,618 17,780 17,943 18,108
10 18,217 18,385 18,553 18,724 18,896 19,095 19,244 19,421
11 19,620 19,853 20,088 20,326 20,567 20,811 21,058 21,307
12 21,387 21,626 21,868 22,113 22,361 22,611 22,864 23,120
13 23,257 23,517 23,780 24,047 24,315 24,587 24,863 25,141
14 25,290 25,573 25,859 26,149 26,441 26,737 27,036 27,339
15 27,565 27,887 28,214 28,544 28,877 29,214 29,557 29,902
16 30,044 30,396 30,751 31,111 31,474 31,843 32,215 32,592
17 32,747 33,131 33,518 33,909 34,306 34,707 35,113 35,524
18 35,693 36,111 36,532 36,960 37,392 37,829 38,272 38,719
19 39,151 39,685 40,227 40,776 41,333 41,898 42,470 43,051
20 43,250 43,841 44,440 45,047 45,662 46,285 46,917 47,559
21 47,779 48,432 49,094 49,764 50,443 51,132 51,831 52,539
22 52,783 53,503 54,234 54,975 55,726 56,487 57,258 58,040
23 58,310 59,106 59,913 60,732 61,561 62,402 63,255 64,118
24 64,416 65,296 66,187 67,092 68,008 68,937 69,878 70,832
25 71,476 72,452 73,441 74,444 75,461 76,491 77,536 78,595
26 78,960 80,039 81,132 82,240 83,363 84,502 85,657 86,825
27 87,229 88,420 89,628 90,852 92,093 93,351 94,625 95,925
28 96,363 97,679 99,013 100,366 101,736 103,126 104,534 105,962
29 106,454 107,908 109,382 110,875 112,390 113,925 115,481 117,058
30 117,601 119,208 120,836 122,486 124,159 125,855 127,573 129,316
31 152,325 154,649 157,008 159,404 161,836 164,305 166,812 169,357
32 177,929 180,700 183,513 186,372 189,274 192,221 195,215 198,255
33 215,804 222,278
APPENDIX “B”
Consultancy Services for the Feasibility Study of Ortigas Avenue - Santolan Road
2016
Interchange Project
Quality Assurance Consultant in the Conduct of Civil Works Project Assessment/
2015
Inspection in Luzon Area
Consulting Services for the Feasibility Study of Selected Missing Gap/Road
2015
Opening Projects (Package 1)
Consulting Services for the Conduct of A Comprehensive Study for a Metro Cebu
2015
Integrated Flood and Drainage System Master Plan
Consultancy Services for the Conduct of Feasibility Study of Selected Missing
2015
Gap/ Road Opening Projects, Package III (Re-Bidding)
Conduct of Feasibility Study of Selected Missing Gap/ Road Opening Projects,
2015
Package 2 (re-bidding)
Consulting Services for the Conduct of Master Plan and Feasibility Study of Flood
Management and Water Infrastructure for Sta. Rosa, Biñan and Carmona River 2015
Basins Project
Consultancy Services to Prepare the Feasibility Study, Preliminary Engineering
Design for Bridge Construction Replacement Program II (BCRP II), And To
2015
Preparation of Bidding Documents, Terms of Reference, Approved Budget for the
Contract and Program of Works for BCRP I and II, Design and Build Bridges
Consultancy Services for the Conduct of Master Plan and Feasibility Study of
Flood Control and Drainage Project of Selected River Basins, Nationwide, 2013
Package 1, Batch 2
Consultancy Services for the Conduct of Master Plan and Feasibility Study of
Flood Control and Drainage Project of Selected River Basins, Nationwide, 2013
Package 2, Batch 2
Consultancy Services for the Conduct of Master Plan and Feasibility Study of
2013
Flood Management and Drainage System in Lemery, Batangas
Consultancy Services for the Conduct of Master Plan and Feasibility Study of
2013
Flood Management and Urban Drainage System of Dipolog City
Consultancy Services for the Conduct of Master Plan and Feasibility Study of
2013
Koronadal City Urban Drainage and Flood Control Project
Consultancy Services for the Feasibility Study for the Completion of Metro Manila
Circumferential Road 5 (C-5) and other Priority Road/ Interchange Project (PRIP)
2013
and Traffic Mitigating Measures Cum Environmental, Social and Gender Aspect
(C-5 & PRIP)
Consultancy Services for the Updating of the Feasibility Study of the Agno River
2013
Flood Control Project, Phase III
Consulting Services for the Conduct of Master Plan and Feasibility Study of Flood
2013
Management and Drainage System of Catbalogan City
Consulting Services for the Feasibility Study for the Improvement/ Widening of
General Luis Road from Quirino Highway in Quezon City to Mcarthur Highway in 2013
Valenzuela City (Re-bidding)
Consulting Services for the Updating Feasibility Study for Valenzuela-Obando-
Meycauayan (VOM) Flood Control and Drainage Improvement & Related Works 2013
(Re-Bidding)
Consulting Services for the Detailed Engineering for Bacolod-Silay Airport Access
2015
Road, Phase II (BSAAR II) Project
Consultancy Services for the Upgrading of Standard Plans for 2,3 and 4 Storey
DepEd School Building and Detailed Engineering Design for the Aesthetically 2014
Improed Municipal Hall Building, Public Market and Civic Center.
Consultancy Services for the Detailed Engineering Design for the Proposed
Construction/Road Opening of Mindoro Island Circumferential Road, Barangay
2013
Talipan, Puerto Galera, Oriental Mindoro to Occidental Mindoro Boundary of
Barangay Camurong, Abra De Ilog
Consultancy Services for the Strengthening/ Retrofitting of the Premier Guest
2013
House (PGH) Phase III in Malacañang Compound