Manual For Induction Motors and Generators
Manual For Induction Motors and Generators
Manual For Induction Motors and Generators
—
Safety instructions — AMA, AMB, AMD, AMG, AMH, AMI, AMK,
AMZ, AXR, HXR, M3BM, NMH, NMI, NMK, NXR
1. General
General safety regulations, specific agreements made for each work site and safety precautions shown in this
document must be observed at all times.
NOTE: If there are any conflicts between these safety instructions and the user manual, these
safety instructions prevail.
2. Intended use
Electric machines have dangerous live and rotating parts and may have hot surfaces. It is not allowed to
climb on the machine. All operations serving transport, storage, installation, connection, commissioning,
operation and maintenance shall be carried out by responsible skilled persons (in conformity with
EN 50 110-1 / DIN VDE 0105 / IEC 60364). Improper handling may cause serious personal injury and damage to
property. Danger!
These machines are intended for industrial and commercial installations as components as defined in the Machinery
Directive (MD) 2006/42. Commissioning is prohibited until conformity of the end product with this directive has
been established (follow particular local safety and installation rules as, for example, EN 60204).
These machines comply with the harmonized series of standards EN 60034 / DIN VDE 0530. Their use in explosive
atmosphere is prohibited unless they are expressly designed for such use (follow additional instructions).
On no account, use degrees of protection ≤ IP23 outdoors. Air-cooled models are typically designed for ambient
temperatures of -20°C up to +40°C and altitudes of ≤ 1000 m above sea level. Ambient temperature for air-/water-
cooled models should be not less than +5°C (for sleeve-bearing machines, see manufacturer's documentation). By
all means, take note of deviating information on the rating plate. Field conditions must conform to all rating plate
markings.
3. Transport, storage
Immediately report damage established after delivery to transport company. Stop commissioning, if necessary.
Lifting eyes are dimensioned for the weight of the machine, do not apply extra loads. Ensure the use of correct lifting
eyes. If necessary, use suitable, adequately dimensioned means of transport (for example, rope guides). Remove
shipping braces (for example, bearing locks, vibration dampers) before commissioning. Store them for further use.
When storing machines, make sure of dry, dust and vibration free location (danger of bearing damage at rest).
Measure insulation resistance before commissioning. At values of ≤ 1 kΩ per volt of rated voltage, dry winding. Follow
the manufacturer's instructions. Long term storage procedures must always be considered properly.
4. Installation
Take care of even support, solid foot or flange mounting, and exact alignment. Avoid resonances with rotational
frequency and double mains frequency as a result of assembly. Turn rotor and listen for abnormal slip noises. Check
direction of rotation in uncoupled state.
Follow the manufacturer's instructions when mounting or removing couplings or other drive elements and cover
them with a touch guard. For trial run in uncoupled state, lock or remove the shaft end key. Avoid excessive radial and
axial bearing loads (note manufacturer's documentation). The balance of the machine is indicated as H = Half and F
= Full key. In half key cases coupling must be half key balanced. In full key cases coupling must be balanced without a
key. In case of protruding, visible part of the shaft end key, establish mechanical balance.
Make necessary ventilation and cooling system connections. The ventilation must not be obstructed and the exhaust
air, also of neighbouring sets, not taken in directly.
SAFETY INSTRUCTIONS — AMA, AMB, AMD, AMG, AMH, AMI, AMK, AMZ, AXR, HXR, M3BM, NMH, NMI, NMK, NXR 3
5. Electrical connection
All operations must be carried out only by skilled persons on the machine at rest. Before starting work, the following
safety rules must be strictly applied:
• De-energize!
• Provide safeguard against reclosing!
• Verify safe isolation from supply!
• Connect to earth and short!
• Cover or provide barriers against neighbouring live parts!
• De-energize auxiliary circuits (for example, anti-condensation heating)!
Exceeding limit values of zone A in EN 60034-1 / DIN VDE 0530-1 — voltage ± 5%, frequency ± 2%, waveform and
symmetry — leads to higher temperature rise and affects electromagnetic compatibility. Note rating plate markings
and connection diagram in the terminal box.
The connection must be made so that permanent safe electrical connection is maintained. Use appropriate cable
terminals. Establish and maintain safe equipotential bonding.
The clearances between uninsulated live parts and between such parts and earth must not be below the values of
appropriate standards and values possibly given in manufacturer's documentation.
No presence of foreign bodies, dirt or moisture is allowed in the terminal box. Close unused cable entrance holes and
the box itself in a dust- and watertight manner. Lock the key when the machine is run without coupling. For machines
with accessories, check satisfactory functioning of these before commissioning.
Proper installation (for example, segregation of signal and power lines, screened cables etc.) lies within the installer's
responsibility.
When current transformers are fitted, the following applies to a netural terminal arrangement: Adequate precautions
must be taken to ensure that the secondary circuits of the current transformers are always connected to a load.
6. Operation
Vibration severity in the "satisfactory" range (Vrms ≤ 4.5 mm/s) according to ISO 3945 is acceptable in coupled-
mode operation. (Piston engine generators according to ISO 8528-9). In case of deviations from normal operation -
for example, elevated temperature, noises, vibrations - disconnect machine, if in doubt. Establish cause and consult
manufacturer, if necessary.
Do not defeat protective devices, not even in trial run. In case of heavy dirt deposits, clean cooling system at regular
intervals. Open blocked condensate drain holes from time to time.
Grease the bearings during commissioning before start-up. Regrease antifriction bearings while the machine is
running. Follow instructions on lubrication plate. Use right kind of grease. In case of sleeve-bearing machines,
observe time-limit for oil-change and if equipped with oil supply system make sure the system is working.
8. Frequency converter
In frequency converter applications motor frame external earthing must be used for equalising the potential between
the motor frame and the driven machine, unless the two machines are mounted on the same metallic base. For motor
frame sizes over IEC 280, use 0.75 x 70 mm flat conductor or at least two 50 mm² round conductors. The distance of
the round conductors must be at least 150 mm from each other.
This arrangement has no electrical safety function; the purpose is to equalise the potentials. When the motor and the
gearbox are mounted on a common steel fundament, no potential equalisation is required.
4 MANUAL FOR INDUCTION MOTORS AND GENERATORS
1. Potential equalisation
2. Driven machinery
3. Plate/strip
4. Cables/wires.
To comply with EMC-requirements, use only cables, connectors and cable lead in approved for this purpose. (See
instruction for frequency converters.)
WARNING: The terminals of a machine with frequency converter supply may be energized even when
the machine is at a standstill.
WARNING: Do not exceed the maximum allowed speed of the machine. See product specific manuals.
WARNING: Only qualified personnel familiar with the relevant safety requirements are allowed to open
and maintain permanent magnet synchronous machines.
WARNING: It is not allowed to remove the rotor of a permanent magnet synchronous machine without
the special tools designed for this purpose.
WARNING: Magnetic stray fields, caused by an open or disassembled permanent magnet synchronous
machine or by a separate rotor of such a machine, may disturb or damage other electrical
or electromagnetic equipment and components, such as cardiac pacemakers, credit cards
and equivalent.
WARNING: Loose metallic parts and waste must be prevented from entering the interior of the
permanent magnet synchronous machine as well as getting into contact with the rotor.
WARNING: Before closing an opened permanent magnet synchronous machine, all parts which does
not belong to the machine and wastes must be removed from the interior of the machine.
NOTE: Beware of magnetic stray fields and possible induced voltages when rotating the separate
rotor of a permanent magnet synchronous machine as they may cause damage to
surrounding equipment, for example lathes or balancing machines.
SAFETY INSTRUCTIONS — AMA, AMB, AMD, AMG, AMH, AMI, AMK, AMZ, AXR, HXR, M3BM, NMH, NMI, NMK, NXR 5
6 MANUAL FOR INDUCTION MOTORS AND GENERATORS
NOTE: These instructions must be followed to ensure safe and proper installation, operation
and maintenance of the motor. They should be brought to the attention of anyone who
installs, operates or maintains this equipment. Ignoring these instructions may invalidate
the warranty.
WARNING: Motors for explosive atmospheres are specially designed to comply with official
regulations concerning the risk of explosion. If the motors are used improperly, connected
badly, or altered, no matter how minimally, their reliability can be in doubt.
Standards relating to the connection and use of electrical apparatus in explosive
atmospheres must be taken into consideration, especially national standards
for installation (see standards EN 60079-14, EN 60079-17, GOST-R 52350.14,
GOST IEC 60079-14, GOST 31610.17, GOST IEC 60079-17, GB3836.15, IEC 60079-14,
IEC 60079-17). All repairs and overhauls must be carried out according to standards
IEC 60079-19, EN 60079-19, GOST 31610.19 and GB 3836.13. Only trained personnel familiar
with these standards should handle this type of apparatus.
Declaration of conformity
All ABB Ex-machines intended for explosive atmospheres comply with the ATEX Directive 2014/34/EU and have a CE-
mark on the rating plate.
Validity
These instructions are valid for the following ABB electric motor types when the motors are used in explosive
atmospheres.
Increased safety Ex e, Ex eb
Pressurized enclosure Ex e px, Ex e pz, Ex nA pz, Ex px, Ex pz, and Ex eb pxb, Ex eb pzc, Ex ec pzc, Ex pxb, Ex pzc
Dust ignition protection Ex t (DIP, Ex tD), Class II Div 2, Class II Zone 22, Class III
(Additional information may be required for some machine types used in special applications or with special design.)
• EN 60079-0
• IEC 60079-0
• GB 3836.1
• GOST 31610.0
• EN 60079-1
• IEC 60079-1
• GB 3836.2
• GOST IEC 60079-1
• EN 60079-2
• IEC 60079-2
• GB 3836.5
• GOST IEC 60079-2
• EN 60079-7
• IEC 60079-7
• GB 3836.3
• GOST 31610.7
• EN 60079-15
• IEC 60079-15
• GB 3836.8
• GOST 31610.15
8 MANUAL FOR INDUCTION MOTORS AND GENERATORS
• EN 61241-1; EN 60079-31
• IEC 61241-1; IEC 60079-31
• GB 12476.1
• GOST-R IEC 61241-0; GOST-R IEC 61241-1-1; GOST IEC 60079-31
• NFPA 70
• C 22-2
TR CU Technical Regulation in Customs Union (Russia, Belarus, Armenia, Kyrgyzstan and Kazakhstan):
• TR CU 012/2011
• TR CU 004/2011.
Some AMD machines can also be installed in group I (Mine) areas. Forr more details, see the hazardous area
certificate of the machine.
Atmosphere (EN)
Arrival inspection
• Immediately upon receipt check the machine for external damage. In case of damages, inform the forwarding
agent without delay.
• Confirm all rating plate data, especially voltage, winding connection (star or delta), category, type of protection
and temperature marking.
WARNING: Disconnect power and lock out the power switch before working on the machine or
the driven equipment. Ensure that no explosive atmosphere is present while work is in
progress.
Special conditions
• The special conditions mentioned in the certificates of the motors and separately certified apparatus must be
conformed to. Letter “x” in the certificate number typically indicates that special conditions are included.
WARNING: Substitution of components may impair suitability for Class I Division 2 and other Ex
protection types.
SAFETY INSTRUCTIONS — AMA, AMB, AMD, AMG, AMH, AMI, AMK, AMZ, AXR, HXR, M3BM, NMH, NMI, NMK, NXR 9
• The maximum number of allowed sequential starts has been declared in the machine’s technical documents.
• A new starting sequence is allowed after the machine has cooled to ambient temperature (cold starts) or to
operating temperature (warm starts).
• Check before starting that all earthing and equipotentialing cables have been effectively connected.
• Do not remove any earthing or equipotentialing cables that have been installed by the manufacturer.
• Do not make any removals or adjustments in terminal boxes; this could decrease clearances or creepage
distances between parts.
• Do not install any new equipment to terminal boxes without asking for advice from ABB.
• Be sure that the air gap between rotor and stator is measured after any maintenance on the rotor or bearings.
The air gap shall be the same at any point between stator and rotor.
• Centralize the fan to the center of the fan cover or the air guide after any maintenance activity. The clearance
must be at least 1% of the maximum diameter of the fan and in accordance with standards.
• All connections in main terminal boxes must be made with Ex-approved connectors, which are delivered with
the machine by the manufacturer. In case of any other connectors, ask for advice from ABB.
• All connections in auxiliary terminal boxes, marked as intrinsically safe circuits (Ex i), must be connected to
proper safety barriers.
• Energy-limited circuits (Ex nL) and intrinsically safe circuits (Ex i) have to be separated from other electrical
circuits with a separator plate or a 50 mm greepage distance. For more information, see the connection
diagram and terminal box drawings of the motor.
Space heaters
• If an anti-condensation heater, without self-regulation, is turned on immediately after the motor is shut down,
take suitable measures to control the inside motor housing temperature. The anti-condensation heaters can
only operate in a temperature-controlled environment.
• The anti-condensation heaters must be interlocked in such a way that they can only be energized when the
motor is de-energized.
Pre-start ventilation
• Ex ec, Ex eb, Ex nA and Ex e machines may, or in some cases have to, be equipped with a provision for pre-start
ventilation.
• Before starting, check the need to purge the machine enclosure to make sure that the enclosure is free of
flammable gases. Based on risk assessment, the customer and/or the local authorities make the decision on
whether to use pre-start ventilation or not.
WARNING: To minimize the risk of hazards caused by electrostatic charges, clean the motors only with
a damp cloth or by non-frictional means.
• AMD machines cannot be modified, and the flameproof joints cannot be repaired in any way. This applies to
the components of the sub-assemblies related to the protection mode or to the surface temperature (frame
and end shileds, covers, flame seals, input devices to the terminal boxes, winding, etc.). When substantial
modification is absolutely necessary, the standard requires new certification by a Notified Body. For details,
see EN 60079-19 / IEC 60079-19.
• The gaps of the flame paths are less than the maximum gaps given in the tables of EN 60079-1, IEC 60079-1.
• The width of flameproof joints exceeds the minimum widths given in the tables of EN 60079-1, IEC 60079-1.
10 MANUAL FOR INDUCTION MOTORS AND GENERATORS
—
Contents
Safety instructions — AMA, AMB, AMD, AMG, AMH, AMI, AMK, AMZ, AXR, HXR, M3BM, NMH, NMI, NMK, NXR..............2
1. General..................................................................................................................................................................................2
2. Intended use....................................................................................................................................................................... 2
3. Transport, storage............................................................................................................................................................ 2
4. Installation.......................................................................................................................................................................... 2
5. Electrical connection.........................................................................................................................................................3
6. Operation............................................................................................................................................................................ 3
7. Maintenance and servicing.............................................................................................................................................. 3
8. Frequency converter......................................................................................................................................................... 3
Additional safety instructions for permanent magnet synchronous machines.......................................................4
Electrical connection and operation..................................................................................................................................4
Maintenance and servicing.................................................................................................................................................. 4
Additional safety instructions for electrical motors for explosive atmospheres.................................................... 6
Declaration of conformity....................................................................................................................................................6
Validity...................................................................................................................................................................................... 6
Conformity with standards..................................................................................................................................................7
Arrival inspection................................................................................................................................................................... 8
Note the following rules during any operation!............................................................................................................. 8
Chapter 1 Introduction............................................................................................................................................................14
1.1 General information........................................................................................................................................................ 14
1.2 Important note................................................................................................................................................................ 14
1.3 Limitation of liability...................................................................................................................................................... 14
1.4 Documentation................................................................................................................................................................ 15
1.4.1 Documentation of the machine.................................................................................................................15
1.4.2 Information not included in documentation.......................................................................................... 15
1.4.3 Units used in this User’s Manual.............................................................................................................. 15
1.5 Identification of the machine.......................................................................................................................................15
1.5.1 Serial number of the machine....................................................................................................................15
1.5.2 Rating plate................................................................................................................................................... 16
Chapter 6 Operation................................................................................................................................................................63
6.1 General.............................................................................................................................................................................. 63
6.2 Normal operating conditions...................................................................................................................................... 63
6.3 Number of starts............................................................................................................................................................63
6.4 Supervision...................................................................................................................................................................... 64
6.4.1 Bearings......................................................................................................................................................... 64
6.4.2 Vibrations...................................................................................................................................................... 64
6.4.3 Temperatures............................................................................................................................................... 64
6.4.4 Heat exchanger............................................................................................................................................64
6.4.5 Slip ring unit.................................................................................................................................................64
6.5 Follow-up..........................................................................................................................................................................64
6.6 Shut down........................................................................................................................................................................65
Chapter 7 Maintenance........................................................................................................................................................... 66
7.1 Preventive maintenance................................................................................................................................................ 66
7.2 Safety precautions......................................................................................................................................................... 66
7.3 Maintenance program....................................................................................................................................................67
7.3.1 Recommended maintenance program.................................................................................................... 68
7.4 Maintenance of general constructions...................................................................................................................... 72
7.4.1 The tightness of fastenings.......................................................................................................................72
7.4.2 Vibration and noise..................................................................................................................................... 73
7.4.3 Bearing housing vibrations........................................................................................................................73
7.4.4 Shaft vibrations............................................................................................................................................75
7.5 Maintenance of bearings and lubrication system................................................................................................... 75
7.5.1 Sleeve bearings............................................................................................................................................. 75
7.5.2 Lubrication of sleeve bearings..................................................................................................................76
7.5.3 Rolling bearings............................................................................................................................................ 77
7.5.4 Bearing insulation and bearing insulation resistance check..............................................................80
7.6 Maintenance of stator and rotor windings.............................................................................................................. 82
7.6.1 Particular safety instructions for winding maintenance..................................................................... 83
7.6.2 The timing of the maintenance................................................................................................................ 83
7.6.3 The correct operating temperature.........................................................................................................83
7.6.4 Insulation resistance test.......................................................................................................................... 84
7.6.5 Insulation resistance measurement for auxiliaries.............................................................................. 87
7.6.6 The polarization index................................................................................................................................ 87
7.6.7 Other maintenance operations................................................................................................................ 88
7.7 Maintenance of slip rings and brush gear................................................................................................................ 88
7.7.1 Care of slip rings..........................................................................................................................................88
7.7.2 Care of brush gear...................................................................................................................................... 88
7.8 Maintenance of cooling units...................................................................................................................................... 89
7.8.1 Maintenance instructions for machines with open air cooling..........................................................89
7.8.2 Maintenance instructions for air-to-water heat exchangers............................................................. 90
7.8.3 Maintenance instructions for air-to-air heat exchangers................................................................... 90
7.8.4 Maintenance of external blower motors................................................................................................ 91
7.9 Repairs, disassembly and assembly........................................................................................................................... 91
—
Chapter 1 Introduction
Introduction
NOTE: Some customer specific items may not be included in this User’s Manual. Additional
documentation will be found in the project documentation.
Actions described in this manual are only to be performed by trained personnel with previous experience in similar
tasks, and authorized by the user.
This document and parts thereof must not be reproduced or copied without the express written permission of ABB,
and the contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
ABB constantly strives to improve the quality of the information provided in this User’s Manual, and will welcome
any improvement suggestions. For contact information, see Chapter 9.1.3 Contact information for Motors and
Generators Service.
NOTE: These instructions must be followed to ensure safe and proper installation, operation
and maintenance of the machine. They should be brought to the attention of anyone who
installs, operates or maintains this equipment. Ignoring the instruction invalidates the
warranty.
NOTE: To avoid accidents, safety measures and devices required at the installation site must be
in accordance with the instructions and regulations stipulated for safety at work. This
applies to general safety regulations of the country in question, specific agreements made
for each work site and safety instructions included in this manual and separate safety
instructions delivered with the machine.
NOTE: The warranty issued is not valid, if the operation conditions of the machine are changed or
any changes in the construction of the machine, or repair work to the machine have been
made without prior written approval from the ABB factory, which supplied the machine.
INTRODUCTION 15
NOTE: Local ABB sales offices may hold different warranty details, which are specified in the sales
terms, conditions or warranty terms.
For contact information, please see the back page of this User’s Manual. Please remember to provide the serial
number of the machine when discussing machine specific issues.
1.4 Documentation
NOTE: The documentation is delivered to the ordering customer. For additional copies of these
documents, please contact your local ABB office or the After Sales department, see Chapter
9.1.3 Contact information for Motors and Generators Service.
In addition to this manual, each machine is supplied with a Dimension Drawing, an Electrical Connection Diagram and
a Data Sheet indicating the following:
• Mounting and outline dimensions of the machine
• Machine weight and load on the foundation
• Location of lifting eyes of the machine
• Instrumentation and location of accessories
• Bearing oil and lubricant requirements
• Main and auxiliary connections.
NOTE: Some customer specific items may not be included in this User’s Manual. Additional
documentation will be found in the project documentation. In case of conflict between this
manual and the additional documentation of the machine, additional documentation will
prevail.
Figure 1 Rating plate for direct on line machines manufactured according to IEC (Ex-machine according to ATEX
Directive)
Figure 2 Rating plate for frequency converter machines manufactured according to IEC
INTRODUCTION 17
Figure 3 Rating plate for direct on line machines manufactured according to NEMA
1. Type designation
2. Manufacturing year
3. Duty
4. Type of connection
5. Insulation class
6. Machine weight [kg] or [lbs]
7. Degree of protection [IP class]
8. Type of cooling [IC code]
9. Mounting arrangement [IM code] (IEC)
10. Additional info
11. Manufacturer
12. Serial number
13. Output [kW] or [HP]
14. Stator voltage [V]
15. Frequency [Hz]
16. Rotating speed [rpm]
17. Stator current [A]
18. Power factor [cosf]
19. CSA marking
20. Standard
21. Designation for locked-rotor kVA/ HP (NEMA)
22. Ambient temperature [°C] (NEMA)
23. Service factor (NEMA).
18 MANUAL FOR INDUCTION MOTORS AND GENERATORS
—
Chapter 2 Transport and unpacking
Transport and unpacking
2.1.1 General
The following protective measures are taken before delivery of the machine from the factory. The same protective
measures should be taken, whenever the machine is moved:
• Some machines, and all machines with sleeve or roller bearings, have transport locking devices installed.
• Ball and roller bearings are greased with lubricant indicated on the bearing plate, which is attached to the
machine frame, see Chapter 2.1.2 Bearing plate.
• Sleeve bearings are flooded with oil and drained. All oil in- and outlets, as well as oil tubes are plugged. This
gives sufficient protection against corrosion.
• Air-to-water coolers are drained and the cooler in- and outlets are plugged.
• Machined metal surfaces, such as the shaft extension, are protected against corrosion with an anti-corrosive
coating.
• In order to protect the machine properly against water, salt spray, moisture, rust and vibration damages during
loading, sea transport and unloading of the machine, the machine should be delivered in a seaworthy package.
• The D-end bearing and a possible ND-end bearing are greased with a lubricant indicated on the bearing plate
attached to the machine frame.
• If the ND-end bearing is oil-filled (self-lubricated):
Any time the machine is transported, the lubrication oil must first be drained from the bearing, or it could
ingress through the seals to the inside of the machine from the ND-bearing.
NOTE: The information given on the bearing plate must imperatively be followed. Failure to do so
will void the warranty for the bearings.
NOTE: Use only the lifting lugs or eyes intended for lifting the complete machine. Do not use any
small additional lifting lugs or eyes available, as they are there only for service purposes.
NOTE: The center of gravity of machines with the same frame may vary due to different outputs,
mounting arrangements and auxiliary equipment.
NOTE: Check that eyebolts or the lifting lugs integrated with the machine frame are undamaged
before lifting. Damaged lifting lugs must not be used.
NOTE: Lifting eyebolts must be tightened before lifting. If needed the position of the eyebolt
must be adjusted with suitable washers.
NOTE: When lifting the machine from the bottom, use only lifting spots marked with
ISO 7000-0625- standard mark see Figure 6 Sling here - mark (ISO 7000-0625).
TRANSPORT AND UNPACKING 21
Figure 7 Lifting of horizontal and vertical machines in seaworthy packages when lifting by crane from the eyebolts
of the machine
Figure 8 Lifting of horizontal and vertical machines on pallets when lifting by crane from the eyebolts of the
machine
Figure 10 Lifting the roof of the cooler top, 4 lifting points, max. α = 90 °
Use lifting eyes marked with 1 only for lifting the cooler top roof, if the roof is removable. Lifting eyes for lifting the
actual cooler top are located under the top roof and will be visible after removing the top roof, in case it is removable.
Use lifting eyes marked with 2 for lifting the removable air guides or silencers of the cooler top.
2.5 Installation instructions for main terminal box and cooler parts
These instructions are applied, when the machine is delivered on site with disassembled main components, such as
the main terminal box or cooler parts. Refer to the Dimension Drawing included in the project documentation for the
correct positions of the parts. All bolts, nuts and washers are included in the delivery.
Mechanical assembly should be done only by experienced personnel. Electrically active parts such as stator cables
should be installed by skilled persons only.
Safety instructions must be observed at all times, for more information see Safety Instructions.
To ensure that the warranty terms agreed in the purchase order contract of the project are not invalidated, these
instructions should be followed carefully.
26 MANUAL FOR INDUCTION MOTORS AND GENERATORS
2.6 Storage
If the machine needs to be stored outdoors, the machine must never be left ‘as is’ in its transportation package.
Instead the machine must be
• Taken out from its plastic wrap.
• Covered, as to completely prevent rain from entering the machine. The cover should allow ventilation of the
machine.
• Placed on at least 100 mm (4”) high rigid supports, as to make sure that no moisture can enter the machine
from below.
• Provided with good ventilation. If the machine is left in its transportation package, large enough ventilation
openings must be made in the package.
• Protected from harmful insects and vermin.
Use checklists in Appendix Storage in Appendix Commissioning report.
Machines with so-called water jacket cooling are to be filled with a mixture of water and glycol with a minimum of
50% glycol. Instead of glycol, another similar liquid can be accepted. Make sure that the liquid mixture tolerates the
storage temperature without freezing. The liquid inlets and outlets are to be closed after filling.
NOTE: A too high tightening torque on the transport locking device will damage the bearing.
NOTE: The type of bearings used are found on the bearing plate, see Chapter 2.1.2 Bearing plate,
and axially locating bearing information from the dimension drawing.
NOTE: A too high tightening torque on the transport locking device will damage the bearing.
Table 3 Tightening torque (lubricated screw). Axially locating bearing carries the locking force
2.6.5 Openings
If there are any openings where cables are not connected to terminal boxes or flanges that are not connected to the
piping, they are to be sealed. The coolers and the piping within the machine are to be cleaned and dried before they
are sealed. The drying is made by blowing warm and dry air through the pipes.
—
Chapter 3 Installation and alignment
Installation and alignment
3.1 General
Good planning and preparation result in simple and correct installation and assure safe running conditions and
maximum accessibility.
Following paragraph for protection type: All machines for hazardous areas
Standards relating to the connection and use of electrical apparatus in hazardous areas must be taken into
consideration, especially national standards for installation (see standard IEC 60079-14).
NOTE: General, as well as local work safety instructions must be followed during installation.
3.2.1 General
The design of the foundation should assure safe running conditions with maximum accessibility. Sufficient free
space should be left around the machine to ensure easy access for maintenance and monitoring. The cooling air
should flow to and away from the machine without obstruction. Care has to be taken to ensure that other machines
or equipment nearby do not heat the machine cooling air or constructions such as bearings.
The foundation must be strong, rigid, flat and free from external vibration. The possibility of machine resonance with
the foundation has to be verified. In order to avoid resonance vibrations with the machine, the natural frequency of
the foundation together with machine must not be within a ±20% range of the running speed frequency.
A concrete foundation is preferred, however, a correctly designed steel construction is also acceptable. The
anchorage to the foundation, the provision of air, water, oil and cable channels as well as the location of the grouting
holes should be considered prior to construction. The position of the grouting holes and the height of the foundation
must agree with the corresponding dimensions on the provided dimensional drawing.
The foundation shall be designed to permit 2 mm (0.8 inch) shim plates under the feet of the machine in order to
ensure an adjustment margin, and facilitate the possible future installation of a replacement machine. Machine shaft
height and foundation feet location have a certain manufacturing tolerance, which are compensated with the 2 mm
(0.8 inch) shim plate.
NOTE: The calculation and design of the foundation is not included in the ABB scope of supply
and the customer or a third party is therefore responsible for it. Furthermore, the grouting
operation is also normally outside the scope and responsibility of ABB.
• Fill the sleeve bearings with appropriate oil. For suitable oils, see Chapter 7.5.2.4 Oil qualities. Clean the sleeve
bearings before filling in oil if the machine has been stored for a long period (over two months) and the
bearings have been treated against corrosion.
• Remove the anti-corrosive coating on the shaft extension, and machine feet with white spirit.
• Install the coupling half as described in Chapter 3.3.4 Assembly of the coupling half.
• Check that the drain plugs at the lowest part of both ends of the machine are in open position, see Chapter
3.3.6 Drain plugs.
Alternative 1
• The transport locking device is a heavy unit, weighing approximately 100 kg.
• Support the transport locking device properly when removing the fasteners.
• Dismantle the whole rotor locking gear, bar and studs from the D-end.
32 MANUAL FOR INDUCTION MOTORS AND GENERATORS
Alternative 2
• Unscrew the locking bolt (tagged with a red label) on the D-end bearing by 5 mm and re-lock using a jam nut.
NOTE: In order to avoid bearing damages, the transport locking device must be fitted to the
machine whenever the machine is moved, transported to another location or stored. See
Chapter 2.1 Protective measures prior to transport.
Machines with rolling bearings must be connected to the driven machine with flexible couplings, e.g. pin couplings, or
gear couplings.
If the axially locked bearing is at the N-end (see dimension drawing), make sure that a continuous free axial
movement is possible between the coupling halves in order to permit thermal expansion of the machine shaft
INSTALLATION AND ALIGNMENT 33
without damaging the bearings. The expected axial thermal expansion of the rotor can be calculated as defined in
the Chapter 3.6.4 Correction for thermal expansion.
Vertical machines may be designed to carry some load from the shaft of the driven machine. If this is the case, the
coupling halves have to be locked against slipping in the axial direction by a lock plate on the end of the shaft.
NOTE: The machine is not suitable for belt, chain or gear connection unless it is specifically
designed for such use. The same applies for high axial thrust applications.
Following paragraph for bearing type: Sleeve bearing with axial float
The sleeve bearing construction allows the rotor to move axially between the mechanical end float limits. Standard
bearings cannot withstand any axial forces from the driven machine. Any axial force from the load will cause bearing
damage. Therefore, all axial forces must be carried by the driven machine and the coupling must be of limited axial
float type.
3.3.4.2 Assembly
The following instructions must be taken into account when assembling the coupling half.
• Follow the general instructions of the coupling supplier.
• The weight of the coupling half can be considerable. A suitable lifting gear may be needed.
• Clean the shaft extension of its anti-corrosive coating, and check the measurements of the extension and the
coupling against the provided drawings. Ensure also that the keyways in the coupling and the shaft extension
are clean and free from burrs.
• Coat the shaft extension and hub bore with a thin layer of oil as to facilitate the mounting of the coupling half.
Never coat mating surfaces with molybdenum disulphide (Molykote) or similar products.
• The coupling must be covered with a touch guard.
NOTE: In order not to damage the bearings, no additional forces should be applied to the
bearings when assembling the coupling half.
NOTE: Suitability of the shaft end and the bearings for the belt drive must be always checked
before use. Do not exceed the radial force specified in the order definitions.
34 MANUAL FOR INDUCTION MOTORS AND GENERATORS
For horizontal machines, two drain plugs are fitted at both ends of the machine.
For vertical machines, two drain plugs are fitted to the lower end shield.
The main terminal box has one drain plug at the lowest part of the box which has to be closed during operation.
NOTE: Machines are delivered with jacking screws for vertical adjustment at each foot.
NOTE: To ensure that the foundation studs will be satisfactorily attached to the concrete, they
must be unpainted and free from pollution and dust.
In order to assemble the foundation stud or sole plate set, the machine must be suspended above the floor by a
crane. Proceed as follows, see Figure 18 Typical foundation stud assembly:
• Clean the parts protected by an anti-corrosive coating with white spirit.
• Screw the greased leveling screws into the foundation studs (part 5) or sole plates.
• Wrap a layer of tape around the upper part of the anchor bolts (part 2) according to Figure 18 Typical
foundation stud assembly. The tape will prevent the upper part of the bolt from being stuck in the concrete and
enables it to be retightened after the concrete has set.
• Fit the anchor bolt (part 2) in the foundation plates (part 1) or sole plates so that the top of the anchor bolts is
1...2 mm (40...80 mil) above the upper surface of the nuts (part 4).
• Fit the anchor flange (part 3) and the lower nut (part 4) to the anchor bolts (part 2). Bridge the anchor flange
(part 3) to the bolts by welding and tighten the nuts. If the bridging cannot be done, lock the anchor flange
between two nuts.
• After the assembly of the foundation plates is done; the machine should be lifted up and suspended above
the floor. The machine feet, and the side and bottom surfaces of the foundation plates as well as anchor bolts
should be cleaned with white spirit.
• Mount the assembled foundation studs or sole plates under the machine feet with the mounting bolt (part
6) and washer (part 3). Center the mounting bolt (part 6) in the hole of the machine by wrapping e.g. paper,
cardboard or tape on the upper part of the bolt.
• Place the 2 mm (0.8 inch) shim (part 7) between the foot and the plate (part 1). Fasten the plate tightly against
the foot with the mounting bolt (part 6).
• Place the leveling plate (part 8) under the leveling screw (part 5).
• Check that the space between the plate (part 1) and the anchor bolts (part 2) is tight. If concrete penetrates
through this interstice up to the nuts, the retightening cannot be done.
NOTE: The tape and the steel plate are not included in the delivery of the foundation studs.
3.4.5 Alignment
The alignment is made as described in Chapter 3.6 Alignment.
3.4.6 Grouting
The grouting of the machine into the foundation is a very important part of the installation. The instructions of the
grouting compound supplier must be followed.
Please use high-quality non-shrinking grouting materials to avoid difficulties with the grouting in the future. Cracks
in the grouting compound or a poor attachment to the concrete foundation cannot be accepted.
After the machine has been erected, aligned and its accessories are installed, check carefully that no tools or foreign
objects have been left inside of the enclosures. Clean also any dust or debris.
Check that all sealing strips are intact when installing the covers.
Store the alignment and assembly accessories together with the transport locking devices for future use.
3.5.4 Alignment
The alignment is made as described in Chapter 3.6 Alignment.
After the machine has been erected, aligned and its accessories are installed, check carefully that no tools or foreign
objects have been left inside of the enclosures. Clean also any dust or debris.
Check that all sealing strips are intact when installing the covers.
Store the alignment and assembly accessories together with the transport locking devices for future use.
The machine is lifted and placed onto the mounting flange. The mounting bolts are tightened lightly.
3.6 Alignment
3.6.1 General
In order to ensure a long and satisfactory lifetime of both the driving and the driven machine, the machines need to
be properly aligned to each other. This means that the radial, as well as the angular deviation between the two shafts
of the machines have to be minimized. The alignment must be performed with great caution because alignment
errors will lead to bearing and shaft damages.
Before the alignment procedure is started, the coupling halves have to be installed, see Chapter 3.3.4 Assembly of
the coupling half. The coupling halves of the driving and driven machines must be bolted together loosely in order to
move freely in respect to each other during the alignment.
The following text refers to installation on both concrete and steel foundations. Shimming is not necessary in case of
a concrete foundation if the alignment and grouting is done correctly.
INSTALLATION AND ALIGNMENT 39
1. Machine foot
2. Shim
3. Foundation
4. Fixing bolt
5. Jacking screw.
Figure 20 Vertical positioning of machine foot
Bracket plates are placed against the foundation edge and tied down with expansion bolts, see Figure 22 Mounting
of the bracket plate. Move the machine by using the adjusting screws until the shaft centerline and the driven
machine centerline are aligned roughly and the desired distance between the coupling halves is reached. Leave all
adjusting screws only lightly tightened.
NOTE: Figure 22 Mounting of the bracket plate shows bracket plate mounted to concrete
foundation, place similar bracket plate on steel foundation.
Following paragraph and figure for bearing type: Sleeve bearing with axial float
The sleeve bearing in the D-end is equipped with a pointer for showing running center, which is marked with a groove
on the shaft. There are also grooves on the shaft for rotor mechanical end float limits. The position is correct when
the tip of the pointer is in line with the machined running center groove on the shaft, see Figure 23 Markings on shaft
and running center pointer. Notice that the running center is not necessarily the same as the magnetic center as the
fan may pull the rotor from the magnetic center.
INSTALLATION AND ALIGNMENT 41
1. Pointer
2. Outer seal
3. Running center
4. Rotor end float limits.
3.6.4.1 General
Running temperatures have a considerable influence on the alignment, and should therefore be considered during
the alignment. The machine temperature is lower during erection than under operating conditions. For this reason,
the shaft center will be higher, i.e. further away from the feet during operation than standstill.
It may therefore be necessary to use heat compensated alignment depending on the operating temperature of the
driven machine, coupling type, distance between machines, etc.
NOTE: Consider the thermal expansion of the driven machine in respect to the electrical machine
in order to define the total thermal expansion.
42 MANUAL FOR INDUCTION MOTORS AND GENERATORS
NOTE: Make sure that continuous free axial movement is possible between the coupling halves
(excluding rigid couplings) to permit axial thermal expansion of the machine shaft as not to
damage the bearings.
3.6.5.1 General
In the following, the final alignment is made with dial gauges, although there is other and more exact measuring
equipment on the market. The reason for using dial gauges in this text is to provide some alignment theory.
NOTE: Measurements should be made only after proper shimming and with fixing bolts properly
tightened.
NOTE: The final alignment measurements should always be recorded for future reference.
1. Parallel misalignment ∆r
2. Angular misalignment ∆b
3. Axial misalignment ∆a.
Figure 25 Definition of misalignment
3.6.5.4 Alignment
The alignment of the machine is performed according to these guidelines.
44 MANUAL FOR INDUCTION MOTORS AND GENERATORS
1 Radial alignment
2 Angular alignment.
NOTE: Tolerances given by the coupling manufacturers indicate tolerances for the coupling,
not for the driving-driven machine alignment. The tolerances given by the coupling
manufacturer should be used as a guideline for the alignment only if they are narrower than
the maximum permissible misalignments shown in Table 4 Recommended permissible
misalignments.
INSTALLATION AND ALIGNMENT 45
NOTE: External vibration will damage the bearing rolling surfaces and therefore shorter the
bearing lifetime.
NOTE: External vibration will damage the bearing sliding surfaces and therefore shorter the
bearing lifetime.
46 MANUAL FOR INDUCTION MOTORS AND GENERATORS
—
Chapter 4 Mechanical and electrical connections
Mechanical and electrical connections
4.1 General
Mechanical and electrical connections are made after the installation and alignment procedures. The mechanical
connections include the connection of air ducts, water tubes and/or oil supply system where applicable.
The electrical connections include the connection of main and auxiliary cables, earthing cables and possible external
blower motors.
In order to determine proper actions, please read the Dimensional Drawing, the Connection Diagram and the Data
Sheet provided with the machine.
NOTE: Additional installation holes or threads should never be drilled through the frame, as this
may damage the machine.
Standard values for the cooling water to be used in the cooling system:
• pH 7.0 - 9.0
• Alkalinity (CaCO3) > 1 mmol/kg
• Chloride (Cl) < 20 mg/kg
• Sulphate < 100 mg/kg
• KMnO4-concentration < 20 mg/kg
• Al-concentration < 0.3 mg/kg
• Mn-concentration < 0.05 mg/kg.
In most of the cases, normal tap water, i.e. water for domestic consumption, fulfils all these requirements.
The cooling water must also be inhibited with an agent protecting the cooling system against corrosion, fouling and
when necessary, against freezing. All materials in touch with the cooling water (pipes, heat exchanger, etc.) must be
taken into account when selecting a suitable inhibitor.
Recommended inhibitor:
Manufacturer ASHLAND
Product RD-25
which is suitable for steel, copper, aluminium and many other materials.
Use only suitable and high-class connection parts and seals to connect the machine to the water circuit. Check for
possible leaks after the piping and joints have been connected.
NOTE: Do not drill holes through the frame during the installation of the pipes or any other
equipment, as this can damage the machine seriously.
Fill the oil supply system with appropriate oil with correct viscosity. The correct type of oil and viscosity is indicated
on the dimensional drawing. If in any doubt of the cleanness of the oil, use a 0.01 mm (0.4 mil) mesh to filter
unwanted debris from the oil.
Turn the oil supply on, and check the oil circuit for possible leaks prior to starting the machine. The normal oil level is
obtained when half of the oil sight glass is covered.
NOTE: Running the machine without lubricant will result in immediate bearing damage.
1. Air outlet
2. Potential equalisation.
• Air inlet: connect only to one side of frame, use all three connections
• Air outlet: connect to cooler on one side.
Air inlet and air outlet must be connected to the opposite side and opposite ends of the motor.
50 MANUAL FOR INDUCTION MOTORS AND GENERATORS
1. Air outlet
2. Air inlet
3. Top view
4. D-end
5. N-end.
Figure 28 Air inlet and air oulet connections for HXR machines
Following chapter for bearing type: Antifriction bearing with oil mist lubrication
NOTE: Do not drill holes through the frame during the installation of the pipes or any other
equipment, as this can cause serious damage to the machine.
Fill the oil supply system with appropriate oil with correct viscosity. The correct type of oil and viscosity are indicated
in the dimensional drawing. If you are not sure that the oil is clean, use a 0.01 mm (0.4 mil) mesh to filter debris from
the oil.
Turn the oil supply on and check the oil circuit for possible leaks before starting the machine.
NOTE: Do not run the machine without lubricant, as it will damage the bearings.
MECHANICAL AND ELECTRICAL CONNECTIONS 51
NOTE: Prior to installation work, it is important to check that the incoming cables are separated
from the supply network, and that the cables are connected to protective earth.
NOTE: Check all rating plate data, especially the voltage and winding connection.
Machines are intended only for variable speed drives, i.e. to be supplied by frequency converters. The frequency
converter must be designed to operate with a permanent magnet synchronous machine. If there is uncertainty
concerning the compatibility of the permanent magnet synchronous machine and the frequency converter, please
contact ABB Sales Office.
4.3.2 Safety
Electrical work must be carried out only by skilled persons. The following safety rules must be applied:
• De-energize all equipment, including auxiliary equipment
• Provide safeguard against re-energizing the equipment
• Verify that all parts are isolated from their respective supply
• Connect all parts to protective earth and short the circuits
• Cover or provide barriers against live parts in the surrounding area
• If the secondary circuit of the current transformer is extended, make sure that it does not become open-
circuited in use.
• The permanent magnet synchronous machine produces voltage when the shaft is rotating. Prevent rotation of
the shaft before opening the terminal box. Do not open or touch the unprotected terminals while the shaft of
the machine is rotating. Follow Safety Instructions.
Some main terminal boxes can be turned in 90 degrees steps. Before turning, check that the length of the cables
between the stator winding and the terminal box is sufficient.
NOTE: For Ex-machines, cable glands or cable bushings for supply cables must be Ex certified.
Glands or bushings are not included in the manufacturer’s delivery.
NOTE: Prior to installation work, it is important to check that the incoming cables are separated
from the supply network, and that the cables are connected to protective earth.
The stator terminals are marked with letters U, V and W according to IEC 60034-8 or T1, T2, and T3 according to
NEMA MG-1. The neutral terminal is marked with N (IEC) or with T0 (NEMA). Stripping, splicing and insulating of the
high-voltage cables must be performed in accordance with instructions by the cable manufacturer.
The cables must be supported so that no stress is applied to the bus bars in the terminal box.
NOTE: Permanent magnet synchronous machines must be cabled by using shielded symmetrical
cables and cable glands providing 360° bonding (also called EMC glands).
MECHANICAL AND ELECTRICAL CONNECTIONS 53
NOTE: Study the connection diagram delivered with the machine carefully before connecting any
cables.
Following note for protection type: All machines for hazardous areas
NOTE: For Ex-machines, cable glands or cable bushings for supply cables must be Ex certified.
Glands or bushings are not included in manufacturer’s delivery.
NOTE: Study the connection diagram delivered with the machine carefully before connecting
any cables. The connection and functioning of accessories must be checked before
commissioning.
NOTE: Label terminals of accessories, which are normally under voltage when the machine is
switched off, correspondingly.
54 MANUAL FOR INDUCTION MOTORS AND GENERATORS
NOTE: Check visually the direction of rotation of the external blower motor (fan) before starting
the main machine. If the blower motor is running in the wrong direction, the phase
sequence of the blower motor must be changed.
NOTE: The earthing must be carried out according to local regulations before the machine is
connected to the supply voltage.
NOTE: The warranty does not cover destroyed bearings due to improper earthing or cabling.
Mark the machine and terminal boxes with earth symbols according to relevant national standards.
NOTE: 360° high-frequency earthing of cable entries is made in order to suppress electromagnetic
disturbances. In addition, cable screens have to be connected to protective earth (PE) in
order to meet safety regulations.
—
Chapter 5 Commissioning and start-up
Commissioning and start-up
5.1 General
A commissioning report is a vital tool for future service, maintenance and fault finding.
The commissioning is not to be considered finalized before an acceptable commissioning report has been
documented and filed.
The commissioning report has to be available in warranty requests in order to obtain warranty for the machine. For
contact information, see Chapter 9.1.3 Contact information for Motors and Generators Service.
The recommended commissioning report can be found in Appendix Commissioning report.
NOTE: If the machine is delivered without a main terminal box, see Chapter 4.3.4.1 Delivery
without main terminal box.
56 MANUAL FOR INDUCTION MOTORS AND GENERATORS
Following note for protection type: All machines for hazardous areas
5.5.1 General
The machine is equipped with temperature detectors to be connected to a temperature monitoring and protection
system. The location and type, as well as the settings for these detectors, can be found on the dimensional drawing,
and the connection diagram of the machine.
The temperature alarm level for resistance temperature detectors (RTD, Pt-100) should be set as low as possible.
The level can be determined based on the test results, or the noticed operating temperature. The temperature alarm
can be set 10K (20°F) higher than the operating temperature of the machine during maximal load at highest ambient
temperature.
If a two-function temperature monitoring system is used, the lower level is normally used as an alarm level and the
higher as a trip level.
NOTE: In case the machine trips, the reason must be found and eliminated before the machine
is restarted. In case of an alarm, find the reason and correct the situation. Use the trouble
shooting guide, see Chapter 8.1 Trouble shooting.
NOTE: Permanent magnet synchronous machines are equipped with Pt100 resistance elements
and/or thermistors. The use of these protective elements is mandatory to avoid the risk of
overloading the machine.
5.5.2.1 General
The stator windings are manufactured according to temperature rise class F, which has a temperature limit of 155°C
(300°F). A high temperature will age the insulation and shorten the lifetime of the winding. Therefore, thorough
consideration should be made when deciding the temperature trip and alarm levels for the winding.
For determining the temperature settings, see the Connection Diagram delivered with the machine. It is
recommended to apply the method described in Chapter 5.5.1 General when setting the temperature alarm.
5.5.2.3 Thermistors
If the machine is equipped with thermistors (PTC), the operating temperature of the thermistors is found on the
Connection Diagram. The operating function can be chosen to be an alarm or a trip signal. If the machine is equipped
with six thermistors, both alarm and trip signals can be used respectively.
COMMISSIONING AND START-UP 57
5.5.3.1 General
The bearings can be equipped with temperature detectors for monitoring the bearing temperatures. The viscosity
of the grease or oil used will become smaller as a function of higher temperature. When the viscosity falls below a
certain limit, the ability to form a lubricating film inside the bearing will cease, and the bearing will fail, and possibly,
shaft damage will occur as a result.
If the machine is equipped with resistance temperature detectors, the temperature of the bearings should preferably
be monitored continuously. If the temperature of a bearing unexpectedly starts to rise, the machine should be shut
down immediately, as the temperature rise might indicate a bearing failure.
For determining the temperature settings, see the Connection Diagram delivered with the machine. It is
recommended to apply the method described in Chapter 5.5.1 General when setting the temperature alarm.
5.5.3.3 Thermistors
If the rolling bearings are equipped with thermistors (PTC), the operating temperature of the thermistors is found on
the Connection Diagram. The operating function can be chosen to be an alarm or a trip signal. If the rolling bearings
are equipped with two thermistors, both alarm and trip signals can be used respectively.
NOTE: The machine manufacturer is not responsible for the adjusting the protection equipment
at the site.
5.6.1 General
The first test start is a standard procedure after the installation and alignment procedure is finished, the mechanical
and electrical connections are made, the commissioning procedure is gone through and the protective devices are
active.
NOTE: If possible, the first start is made with uncoupled coupling between the driving and driven
machine. The load on the machine must in any case be as small as possible.
Before the test start, the following checks and measures must be made:
• If the coupling half is not assembled, the shaft extension key is either locked or removed.
• The sleeve bearing oil reservoirs and possible oil supply systems are filled with recommended oil to the correct
level. The oil supply system is turned on.
• The rotor is turned by hand, and it is verified that no abnormal noises are heard from the bearings. To turn a
rotor with sleeve bearings, a simple lever arm is needed.
Following bullet for bearing type: Rolling bearing with oil mist
• The oil supply systems are filled with recommended oil to the correct level. The oil supply system is turned on.
• In case of water-cooled machines, the cooling water is turned on. The tightness of the flanges and the cooling
unit is checked.
• The cabling, cables and bus bar connections are verified to be according to the connection diagram.
• The earth connections and earthing devices are verified.
• The starting, control, protection, and alarm relays of each device are inspected.
• The insulation resistance of the windings and other equipment verified.
• The machine covers are assembled, and the shaft seals are tightly fitted in.
• The machine and the environment are cleaned.
• Ex machine enclosure has been purged and it is pressurized. Refer to the purging and pressurizing system
instructions.
5.6.3 Starting
The first start should last only about one (1) second, during which the direction of rotation of the machine is verified.
The direction of rotation of possible external blower motors must also be verified. It is also verified that the rotating
parts do not touch any stationary parts.
NOTE: If the machine does not have an axially locating bearing, and the machine is started
uncoupled, it is normal that the shaft will move axially before stabilizing.
NOTE: Failure in starting the machine without checking the adjustments of the complete slip ring
gear can result in serious damage! The connections to the starter and its functions shall
also be verified.
NOTE: The brush-lifting device must be in starting position before starting the machine.
NOTE: If resistance temperature detector (RTD, Pt-100) or equivalent is not available, the surface
temperature of the bearing area shall, if possible, be measured. The bearing temperature is
approximately 10°C (20°F) higher than the surface temperature.
In case of any deviations from expected normal operation, e.g. elevated temperatures, noise or vibration, shut down
the machine, and find the reason for the deviations. If necessary, consult the manufacturer of the machine.
NOTE: Do not disengage any protective devices during running of the machine, or during search
for a reason for unexpected function of the machine.
5.7.3 Bearings
The rotating electrical machines manufactured by ABB are equipped with either rolling or sleeve bearings.
1. D-END
2. N-END.
Figure 30 Example of lubrication channel through bearing arrangement of horizontal machine
NOTE: Start-up greasing may take several grease portions (3-10 times amount mentioned at the
lubrication plate).
The type of original grease used is found on the bearing plate on the machine. Acceptable types of grease can be
found in Chapter 7.5.3 Rolling bearings.
NOTE: Do not mix greases! There must be only one type of grease inside the bearing - not mixture
of two or more greases.
The temperature of the bearings will initially increase because of the excess grease. After few hours, the excess
grease will be discharged through the lubrication valve and the temperature of the bearing will return to normal
running temperature.
If available, and after the machine has been running for several hours, measure the vibrations or SPM-values from the
SPM-nipples, and record the values for future reference use.
NOTE: The lubrication system should be constructed so that the pressure inside the bearing is
equal to the atmospheric (outside) pressure. Air pressure entering the bearing from either
inlet or outlet oil pipes will cause bearing oil leakages.
5.7.4 Vibrations
For a comprehensive discussion on vibrations, see Chapter 7.4.2 Vibration and noise.
• On water cooled machines, switch off the cooling water flow to avoid condensation inside the machine.
OPERATION 63
—
Chapter 6 Operation
Operation
6.1 General
To ensure trouble-free running a machine must be looked after and carefully supervised.
Always before starting up the machine ensure that:
• The bearings are greased or filled with oil to a correct level in accordance with the manufacturer’s technical
specifications and the dimensional drawing
• The cooling system is functioning
• The machine enclosure has been purged and is pressurized if applicable
• No maintenance is ongoing
• The personnel and equipment associated with the machine are ready to start up the machine.
For start-up procedure, see Chapter 5.6.3 Starting.
In case any deviations from expected normal operation are noticed, e.g. elevated temperatures, noise or vibration,
shut down the machine, and find the reason for the deviations. If necessary, consult the manufacturer of the
machine.
NOTE: The machine may have hot surfaces when running with load.
NOTE: Overloading the machine may cause demagnetization of the permanent magnets as well as
winding damages.
NOTE: The safety precautions shown in Safety Instructions must be observed at all times.
NOTE: The safety precautions shown in the Safety Instructions must be observed at all times.
64 MANUAL FOR INDUCTION MOTORS AND GENERATORS
6.4 Supervision
The operating personnel should inspect the machine at regular intervals. This means that they should listen, feel and
smell the machine and its associated equipment in order to obtain a feeling for normal operating condition.
The object of the supervision inspection is to familiarize the personnel with the equipment. This is essential in order
to detect and fix abnormal occurrences in time.
The difference between supervision and maintenance is rather diffuse. Normal supervision of operation includes
logging of operating data such as load, temperatures and vibrations. This data is useful basis for maintenance and
service.
• During the first period of operation (- 200 hours) supervision should be intensive. Temperatures of bearings
and windings, load, current, cooling, lubrication and vibration shall be checked frequently.
• During the following duty period (200 - 1000 hours), a check-up once a day is sufficient. A record of supervision
inspections should be filed and saved for further reference. The time between inspections may be extended if
the operation is continuous and stable.
For relevant check-lists, see Appendix Commissioning report.
6.4.1 Bearings
The bearing temperatures and lubrication should be monitored closely, see Chapter 5.7.3 Bearings.
6.4.2 Vibrations
The vibration levels of the driving-driven machine system should be monitored, see Chapter 7.4.3 Bearing housing
vibrations.
6.4.3 Temperatures
The temperatures of the bearings, stator windings and cooling air should be checked when the machine is running,
see Chapter 5.7.5 Temperature levels.
6.5 Follow-up
The follow-up of operation includes logging of operating data such as load, temperatures and vibrations. This data is
useful basis for maintenance and service.
OPERATION 65
For machines with water-cooling, the cooling water supply must be switched off in order to avoid condensation
inside the machine.
NOTE: Voltage may be connected to the terminal box for heating element.
66 MANUAL FOR INDUCTION MOTORS AND GENERATORS
—
Chapter 7 Maintenance
Maintenance
Following three paragraphs for protection type: All machines for hazardous areas
Machines for hazardous areas are specially designed to comply with official regulations concerning the risk of
explosion. If improperly used, badly connected, or altered, no matter how minor, their reliability could be in doubt.
Standards relating to the connection and use of electrical apparatus in hazardous areas must be taken into
consideration, especially national standards for installation (see standards: IEC 60079-14, IEC 6000-17 and
IEC 6007-19). Only trained personnel familiar with these standards should handle this type of apparatus.
Disconnect and lock out before working on the machine or the driven equipment. Ensure that no explosive
atmosphere is present while the work is in progress.
NOTE: The terminals of a machine with frequency converter supply may be energized even when
the machine is at standstill.
Equivalent operating hours (Eq. h) = Actual operating hours + Number of starts x 20.
Level 1 (L1)
Level 1 or L1 maintenance consists of visual inspections and light maintenance. The purpose of this maintenance
is to do a quick check whether problems are beginning to develop before they cause failures and unscheduled
maintenance breaks. It gives also suggestions what maintenance issues must be performed in the next larger
overhaul.
The maintenance can be estimated to last approximately 4 - 8 hours, depending on the type and installation of the
machine and the depth of the inspections. Tools for this maintenance include normal servicing tools i.e. wrenches
and screw drives. The preparations consist of opening the inspection covers. It is recommended that at least the
Operational spare part package is available when commencing this maintenance. The packages are shown in Chapter
9.2.5 Typical recommended spare parts in different sets.
68 MANUAL FOR INDUCTION MOTORS AND GENERATORS
The first Level 1 maintenance should be performed after 4 000 equivalent operating hours or six months
after commissioning. Subsequently the L1 maintenance should be performed yearly halfway between Level 2
maintenances, see Table 5 Maintenance intervals.
Level 2 (L2)
Level 2 or L2 maintenance consists mainly of inspections and tests and small maintenance tasks. The purpose of this
maintenance is to find out whether there are problems in the operation of the machine and to do small repairs to
ensure uninterrupted operation.
The maintenance can be estimated to last approximately 8 - 16 hours, depending on the type and installation of the
machine and the amount of servicing to be done. Tools for this maintenance include normal servicing tools, multi
meter, torque wrench and insulation resistance tester. The preparations consist of opening the inspection covers
and bearings if necessary. Spare parts suitable for this level of maintenance are included in the Operational spare
part package. The packages are shown in Chapter 9.2.5 Typical recommended spare parts in different sets.
The first Level 2 maintenance should be performed after 8 000 equivalent operating hours or one year after
commissioning. Subsequently the L2 maintenance should be performed yearly or after every 8 000 equivalent
operating hours, see Table 5 Maintenance intervals.
Level 3 (L3)
Level 3 or L3 maintenance consists of performing extensive inspections, tests and larger maintenance tasks that
have come up during L1 and L2 maintenances. The purpose of this maintenance is to repair encountered problems
and replace parts subjected to wear.
The maintenance can be estimated to last approximately 16 - 40 hours, depending on the type and installation of
the machine and the amount of repairs and replacements to be done. Tools for this maintenance include the same
tools as for L2 and in addition an endoscope and an oscilloscope. The preparations consist of opening the inspection
covers, the bearings and the water cooler, if applicable. Spare parts suitable for this level of maintenance are
included in the Recommended spare parts package. The packages are shown in Chapter 9.2.5 Typical recommended
spare parts in different sets.
The Level 3 maintenance should be performed after every 24 000 equivalent operating hours or at a three to five year
interval. When L3 maintenance is conducted it replaces the L1 or L2 maintenance otherwise scheduled, and it leaves
their rotation unaffected, see Table 5 Maintenance intervals.
Level 4 (L4)
Level 4 or L4 maintenance consists of performing extensive inspections and maintenance tasks. The purpose of this
maintenance is to restore the machine into a reliable operating condition.
The maintenance can be estimated to last approximately 40 - 80 hours, depending mostly on the condition of the
machine and the needed reconditioning actions. Tools for this maintenance include the same tools as for L3, and
in addition, the rotor removal equipment. The preparations consist of opening the inspection covers, bearings and
water cooler, if applicable, and the removal of rotor.
The amount of spare parts required for this level of maintenance needs to be determined before the maintenance. At
least the Recommended spare part is needed. Spare parts included in the capital spare part package would ensure a
fast and successful execution of this maintenance.
The Level 4 maintenance should be performed after every 80 000 equivalent operating hour. When a L4 maintenance
is conducted it replaces the L1, L2 or L3 maintenance otherwise scheduled, and it leaves their rotation unaffected, see
Table 5 Maintenance intervals.
MAINTENANCE INTERVAL
In equivalent operating hours or time period, whichever comes first
L1 L2 L3 L4
4,000 8,000 24,000 80,000
12,000 16,000
20,000
28,000
Biannual Annual 3-5 years Overhaul
NOTE: It is not recommended that totally enclosed machines are dismantled and inspected
internally more often than every 3-5 years (L3).
7.3.1.4 Auxiliaries
Maintenance object L1 L2 L3 L4 Check / Test
Pt-100 elements V V/T V/T V/T Resistance
(stator, cooling air,
bearing)
Anticondensation V V/T V/T V/T Operation, insulation resistance
heaters
Encoders V V V/T V/T Operation, general condition, alignment
Auxiliary terminal V V/T V/T V/T General condition, terminals, wiring condition
boxes
NOTE: The values in Table 6 General tightening torques are general, and do not apply to various
items, such as diodes, support insulators, bearings, cable terminals or pole fastenings,
bus bar terminals, surge arrestors, capacitors, current transformers, rectifier and thyristor
bridges, or if some other value is given elsewhere in this manual.
Measurement equipment
The measurement equipment shall be capable of measuring broad-band r.m.s. vibration with flat response over a
frequency range of at least 10 Hz to 1 000 Hz, in accordance with the requirements of ISO 2954. Depending on the
vibration criteria, this may require measurements of displacement or velocity or combinations of these (see ISO
10816-1). However, for machines with speeds approaching or below 600 r/min, the lower limit of the flat response
frequency range shall not be greater than 2 Hz.
Measurement locations
Measurements will usually be taken on exposed parts of the machine that are normally accessible. Care shall be taken
to ensure that measurements reasonably represent the vibration of the bearing housing and do not include any local
resonances or amplification. The locations and directions of vibration measurements shall be such that they provide
adequate sensitivity to the machine dynamic forces. Typically, this will require two orthogonal radial measurement
locations on each bearing cap or housing, as shown in Figure 31 Measuring points. The transducers may be placed at
any angular position on the bearing housings. Vertical and horizontal directions are usually preferred for horizontally
mounted machines. For vertical or inclined machines, the location that gives the maximum vibration reading shall
be one of those used. In some cases it may be recommended to measure also in the axial direction. The specific
locations and directions shall be recorded with the measurement.
74 MANUAL FOR INDUCTION MOTORS AND GENERATORS
7.4.3.3 Evaluation
ISO 10816-1 provides a general description of the two evaluation criteria used to assess vibration severity on various
classes of machines. One criterion considers the magnitude of observed broad-band vibration; the second considers
changes in magnitude, irrespective of whether they are increases or decreases.
Evaluation zones
The following evaluation zones are defined to permit a qualitative assessment of the vibration of a given machine
and provide guidelines on possible actions.
Zone A: The vibration of newly commissioned machines would normally fall within this zone.
Zone B: Machines with vibration within this zone are normally considered acceptable for unrestricted long-term
operation.
Zone C: Machines with vibration within this zone are normally considered unsatisfactory for long-term continuous
operation. Generally, the machine may be operated for a limited period in this condition until a suitable opportunity
arises for remedial action.
Zone D: Vibration values within this zone are normally considered severe enough to cause damage to the machine.
MAINTENANCE 75
Table 7 Classification of vibration severity zones for large machines with rated power above 300 kW and not more
than 50 MW; electrical machines with shaft height H/315 mm or higher
Operational limits
For long-term operation, it is a common practice to establish operational vibration limits. These limits take the form
of ALARMS and TRIPS.
Table 8 Initial ALARM and TRIP vibration velocity values for bearing housing vibration in mm/s r.m.s. shows the
initial ALARM and TRIP values for machines based on experience with similar machines. After a period of time the
steady-state baseline value on-site will be established and the ALARM setting should be adjusted accordingly (see
ISO 100816-3).
Table 8 Initial ALARM and TRIP vibration velocity values for bearing housing vibration in mm/s r.m.s.
NOTE: These values are standard values that can be adjusted when additional information on the
machine type and application is available.
If necessary, refill with suitable lubricant, see Chapter 7.5.2.4 Oil qualities.
The correct oil level of a flood-lubricated sleeve bearing is the same as for a self-lubricated bearing. In flood-
lubricated bearings, the oil sight glass might be exchanged for an oil outlet flange.
NOTE: The minimum ambient temperature in starting (without oil heater) is 0°C (32° F).
In doubtful cases, an oil sample may be sent to the laboratory to determine viscosity, acid number, foaming
tendency, etc.
NOTE: Verify the correct oil quality from the bearing plate and the dimension drawing.
NOTE: It is essential that the information provided on the bearing plate is taken into account
when using and maintaining the machine.
NOTE: Regardless of the re-greasing interval, the bearings need to be re-greased at least once per
year.
The re-greasing intervals are calculated for an operating temperature of 70°C (160°F). If the operating temperature is
lower or higher than the assumed, the re-grease interval has to be altered accordingly. Higher operating temperature
decreases the re-greasing interval.
NOTE: An increase in the ambient temperature raises the temperature of the bearings
correspondingly. The values for the re-greasing interval should be halved for every 15°C
(30°F) increase in bearing temperature and may be once doubled for a 15°C (30°F) decrease
in bearing temperature.
Higher speed operation, e.g. in frequency converter applications, or lower speed with heavy load will require shorter
lubrication intervals or a special lubricant. Consult ABB Motors and Generators Service in such cases.
NOTE: The constructional maximum speed of the machine must not be exceeded. The suitability
of the bearings for high-speed operation must be checked.
7.5.3.4 Re-greasing
All rolling bearings of rotating electrical machines need to be re-greased, see Chapter 7.5.3.3 Re-greasing intervals.
The re-greasing can be performed either manually or by means of an automatic system. In either case, it has to be
verified that a suitable amount of the correct grease is entering the bearing at suitable intervals.
NOTE: Grease can cause skin irritation and eye inflammation. Follow all safety precautions
specified by the grease manufacturer.
Machines suited for manual re-greasing are equipped with grease nipples. In order to prevent debris from entering
the bearings, the grease nipples, as well as the surrounding area has to be cleaned thoroughly before re-greasing.
MAINTENANCE 79
Preferably, re-grease the machine while it is running. If this is not possible, or considered dangerous, the re-greasing
has to be carried out while the machine is at a standstill. In this case:
Automatic re-greasing
A variety of automatic re-lubrication systems is available on the market. However, ABB recommends only the use of
electromechanical re-lubrication systems. The quality of the grease entering the bearing has to be checked at least
once per year: the grease has to look and feel like new grease. Any separation of the base oil from the soap is not
acceptable.
NOTE: If an automatic re-greasing system is used, double the amount of grease indicated on the
bearing plate.
NOTE: Do not mix greases! There must be only one type of grease inside the bearing - not a
mixture of two or more greases.
NOTE: Grease additives are recommended. However, a written guarantee should be obtained
from the lubricant manufacturer stating that the additives do not damage the bearings
or the properties of the grease in the field of the operating temperature. This is especially
important for EP additives.
Re-greasing intervals should be halved for other greases fulfilling the required properties.
If the bearing operating temperature is above 100°C (210°F), please consult the manufacturing ABB factory for
suitable greases.
insulation is short-circuited by an earthing cable during normal operation; see Figure 32 D-end bearing earthing
cable.
NOTE: Machines with insulated bearings have a sticker indicating the insulated bearing.
7.5.4.1 Procedure
For machines with an insulated drive end bearing, the short-circuit earthing cable in the drive end bearing must be
removed prior to commencing the non-drive end bearing insulation resistance test. If the drive end bearing is not
insulated, it is required to perform the non-drive end bearing insulation resistance test, to remove the drive-end
bearing shells or the bearing shield and to lift the shaft. This ensures that there is no electrical contact between the
shaft and any other part, for example, frame or bearing housing.
For all machines any optional shaft earthing brush, rotor earth fault brush and coupling (if it is made out of
conductive material) must be removed. Measure the insulation resistance from the shaft to earth using no more
than 100 VDC, see Figure 33 Measuring the insulation resistance of a sleeve bearing and Figure 34 Measuring the
insulation resistance of a roller bearing. The measuring points over the bearing insulation are circled in the figures.
The insulation resistance is acceptable if the resistance value is more than 10 kΩ.
NOTE: There are special instructions for handling dangerous substances during maintenance
work. These instructions must be followed.
NOTE: As a thumb rule, an insulation resistance test should be made once a year. This should
suffice for most machines in most operating conditions. Other tests should only be
conducted if problems arise.
A maintenance program for the complete machine, including windings, is presented in Chapter 7.3 Maintenance
program. This maintenance program however, should be adapted to the customer's particular circumstances, i.e.
servicing of other machines and operating conditions as long as recommended servicing intervals are not exceeded.
For air-cooled machines, it is important to monitor the cleanliness of the air filters. The cleaning and change interval
of the air filters should be planned according to the local operating environment.
84 MANUAL FOR INDUCTION MOTORS AND GENERATORS
The stator operating temperatures must be monitored with resistance temperature detectors. Significant
temperature differences among the detectors could be a sign of damage in the windings. Make sure that the
changes are not caused by the drifting of the measuring channel.
NOTE: Windings should be earthed briefly immediately after measurement in order to avoid risk of
electric shock.
R = 30 MΩ measured at 20°C
k = 0.25
R40 = 0.25 x 30 MΩ = 7.5 MΩ
Table 9 Temperature values in degrees Celsius (ºC) and degrees Fahrenheit (ºF)
°C 0 10 20 30 40 50 60 70 80 90 100 110
°F 32 50 68 86 104 122 140 158 176 194 212 230
NOTE: The insulation resistance indicated in the test report is normally considerably higher than
the values measured on site.
NOTE: Carbon dust on slip rings and naked copper surfaces lower the insulation resistance values
of the rotor.
• Stator.
For new stators: R(1-10 min at 40 °C) > 1000 MΩ. If the measuring conditions are extremely warm and humid, R(1-10 min at 40
°C) values above 100 MΩ can be accepted.
NOTE: If the values given here are not reached, the reason for the low insulation resistance should
be determined. A low insulation resistance value is often caused by excess humidity or dirt,
although the actual insulation is intact.
86 MANUAL FOR INDUCTION MOTORS AND GENERATORS
NOTE: If the insulation resistance of the winding is in the range of several thousands of MΩ, the
polarization index is not a meaningful criterion of the condition of the insulation, and it can
be disregarded.
88 MANUAL FOR INDUCTION MOTORS AND GENERATORS
7.7.1.2 Wear
In case that the slip rings have become coarse or uneven, they should be ground or turned on a lathe. The asymmetry
of the whole ring diameter should be less than 1.0 mm, but for a short distance, a value of maximum 0.2 mm is
allowed. In case of the slip rings are worn out or badly burned, new rings should be assembled.
Measure the eccentricity of the slip-rings using a dial indicator gage. Let the measuring point lie on the slip ring
or on the outer surface of a brush. The highest and lowest values during one turn of the shaft are recorded. The
difference of the maximum and minimum values should be no more than 1.0 mm and locally no more than 0.2 mm.
The difference of the outer diameters of the two slip rings shall preferably not be more than 2 mm.
should be 18-20 mN/mm2 (180-200 g/cm2). Use a spring-balance to measure the brush pressure. Attach a spring
balance to the tip of the lever pressing the brush and pull in a radial direction until the pressure is just relieved from
the brush. Use a piece of paper between brush and press lever to detect when pressure is relieved, see Figure 39
Checking brush pressure with spring balance.
Following chapters for cooling type: Open air, Air-to-water and Air-to-air
The machine can be equipped with temperature detector(s) for monitoring the internal cooling air. If the
temperature detectors show normal temperature, no additional maintenance to the supervision inspection is usually
required for the cooling system.
If the temperature detectors show abnormal temperature or close to the alarm level in winding or in cooling air, the
cooling system has to be checked. If the coolers have to be cleaned, see the instructions below.
7.8.3.2 Cleaning
Some fouling of the cooling surface and the tube wall will eventually occur. This fouling reduces the cooling capacity.
The heat exchanger should therefore be cleaned at regular intervals, to be determined from case to case, depending
of the properties of the cooling air. During the initial period of operation, the heat exchanger should be inspected
frequently.
Blow the heat exchanger clean with compressed air or clean it with a suitable brush. Do not use a steel brush in
aluminium tubes as it can damage the tubes; a soft round brass wire brush can be used instead.
Following note for protection type: All machines for hazardous areas
NOTE: Machines in hazardous areas must only be serviced by repair shops qualified and
authorized by ABB.
NOTE: When disassembling the permanent magnet synchronous machine, always contact ABB
Motors and Generators Service for more instructions.
92 MANUAL FOR INDUCTION MOTORS AND GENERATORS
—
Chapter 8 Trouble shooting
Trouble shooting
Noise
• • • Insufficient lubrication Low oil level Check bearing for leakage, add oil
• • • • Unsuitable oil quality Check ABB oil recommendations
• • Oil quality is reduced Incorrect oil change Clean bearing and change oil
period
• • • • Excessive axial load Faulty coupling or Check coupling, mounting and
mounting alignment
• • • Machine misalignment Realign machine
• • Incorrectly assembled bearing Verify correct bearing assemblage and
adjustments
• • • Excessive amount of oil Clean bearing and add correct amount
of lubricant
• • • Damaged bearing shells Oil impurities Change oil, check bearing condition,
replace bearing shells
• • Bearing currents Restore bearing insulation, replace
bearing shells
• • Complete bearing failure Replace bearing parts
• • Normal wearing Replace bearing shells
• • Operating speed too low Check the operating speed range of
bearing
• Faulty instrumentation Faulty temperature Check bearing temperature
detector measurement system
• Damaged or worn-out bearing seals Replace bearing seals
• External vacuum Rotating equipment Check pressure levels, relocate rotating
nearby equipment
• • Internal over pressure Pressure compensation Remove cause for internal over pressure
failure
• Damaged machine seal Replace or repair machine seal
• Poor oil ring or disc operation Open bearing and adjust operation
• • Foreign matter inside the bearing Clean bearing and check seal condition
TROUBLE SHOOTING 95
• • • Insufficient lubrication Oil flow malfunction Check oil pump, oil reduction valve and
oil filter
• Oil viscosity too high Check oil temperature and oil type
• • • • Unsuitable oil quality Check ABB oil recommendations
• Oil inlet temperature too high Check lubrication system and adjust oil
temperature
• • Oil quality is reduced Incorrect oil change Clean bearing and change oil
period
• • • • Excessive axial load Faulty coupling or Check coupling, mounting and
mounting alignment
• • • Machine misalignment Realign machine
• • Incorrectly assembled bearing Verify correct bearing assemblage and
adjustments
• • • Damaged bearing shells Oil impurities Change oil, check bearing condition,
replace bearing shells
• • Bearing currents Restore bearing insulation, replace
bearing shells
• • Complete bearing failure Replace bearing parts
• • Normal wearing Replace bearing shells
• • Operating speed too low Check the operating speed range of
bearing
• Faulty instrumentation Faulty temperature Check bearing temperature
detector measurement system
• Damaged or worn-out bearing seals Replace bearing seals
• Oil flow too high Faulty regulator settings Check and correct oil flow
• Problem in oil return Faulty oil piping Check oil return pipe inclination
flow
• External vacuum Rotating equipment Check pressure levels, relocate rotating
nearby equipment
• • Internal over pressure Pressure compensation Remove cause for internal over pressure
failure
• Damaged machine seal Replace or repair machine seal
• Faulty assembled or maintained lubrication piping Check pipeline connections and oil filter
tightness
• • Foreign matter inside the bearing Clean bearing and check seal condition
NOTE: For oil leakage of sleeve bearings, see Chapter 8.2 Oil leakage of sleeve bearings.
96 MANUAL FOR INDUCTION MOTORS AND GENERATORS
• • High intake air temperature Ambient temperature too Add ventilation to decrease ambient
high temperature
• • Exiting air is pulled back in Ensure sufficient clear distances surrounding
the machine
• • Heat source nearby Place heat sources further away, check
ventilation
• • Faulty air flow Dirty machine interior Clean machine parts and air gaps
• • Faulty cooling arrangement Inspect cooling arrangement condition and
correct assembly
• • Air intakes are blocked Clear air intakes of debris
• • Air filter is clogged Clean or replace air filters
• • Damaged cooling fan(s) Replace fan(s)
• • Cooling fan rotating in the wrong direction Replace fan(s) or change rotating direction of
external fan
• Overload Control system setting Check machine controls, eliminate overload
• • Overspeed Check actual speed and ABB speed
recommendations
• Network unbalance Check that network balance fulfils
requirements
• • Faulty instrumentation or Check measurements, sensors and wiring
measurement system
• Winding fault Check windings
NOTE: For high bearing temperatures, see Chapter 8.1.2 Lubrication system and bearings.
TROUBLE SHOOTING 97
NOTE: For high bearing temperatures, see Chapter 8.1.2 Lubrication system and bearings.
98 MANUAL FOR INDUCTION MOTORS AND GENERATORS
NOTE: For high bearing temperatures, see Chapter 8.1.2 Lubrication system and bearings.
TROUBLE SHOOTING 99
NOTE: For high bearing temperature, see Chapter 8.1.2 Lubrication system and bearings.
8.2.1 Oil
In order for the bearings to function as expected, the oil has to meet certain criteria like viscosity and cleanliness, see
Chapter 7.5.2.2 Control of the lubricant and Chapter 7.5.2.3 Recommended control values for the lubricating oil.
Viscosity
The bearings are designed to run with an oil of a certain viscosity, which is mentioned in the documentation provided
with the electrical machine.
Incorrect viscosity will lead to lubrication failures, and can damage the bearings, as well as the shaft.
Bearing housing
The bearing housing consists of an upper and lower half, which are joined together. In addition, labyrinth seals are
mounted at the bearing housing entrance of the shaft. This construction is not completely hermetic, and therefore
very small leakages have to be tolerated.
A tolerable amount of leakage for self-lubricating bearings is such that the bearing does not need a top-up between
the oil change intervals.
Sealant
In order to prevent the oil from leaking from the bearing through any split lines, sealant is applied on the split lines.
ABB recommends the Hylomar Blue Heavy sealing compound. Curil T or other similar compounds can be used as well.
Following chapter for bearing type: Sleeve bearing with flood lubrication
Oil container
The oil container can be either a separate container, or in some cases, the crankcase of a diesel engine. In both cases,
the container has to be well below the bearings, in order for the oil to flow to the container from the bearing.
TROUBLE SHOOTING 101
The oil container should be constructed in such a way that no pressure can enter the oil return piping from the
container towards the bearing.
Oil piping
The function of the oil return piping is to allow the oil to return to the oil tank with as little of friction as possible.
This is normally obtained by choosing a piping diameter of a large enough diameter, so that the flow of the oil in the
return line does not exceed 0.15 m/s (6 inch/s) based on the pipe cross section.
Install the oil outlet pipes downwards from the bearings at a minimum angle of 15° which corresponds to a slope of
250 - 300 mm/m (3 – 3½ inch/ft).
The assembling of the piping must be performed in such-a-way that above mentioned slope is present at all points of
the piping.
Following chapter for bearing type: Sleeve bearing with flood lubrication
The atmospheric pressure inside the oil container must be verified. The pressure may not be larger than the pressure
outside the bearing. If this is the case, a breather must be installed to the oil container.
Oil piping
It should be verified that the piping has a sufficient diameter, is not clogged, and that the slope is downward and
sufficient throughout the oil return piping.
8.2.6 Use
Causes for bearing leakages, apart from being installation-related, some causes are 'use' related.
Following paragraphs for bearing type: Sleeve bearing with flood lubrication
Oil pressure
The inlet oil pressure for each bearing is calculated according to the desired oil flow, and therefore the oil pressure
should be adjusted accordingly during commissioning.
The specific oil pressure value for each machine must be verified from the documentation provided with the machine.
Following paragraph for bearing type: Sleeve bearing with self lubrication
Oil level
The oil level of a self-lubricated sleeve bearing needs to be checked regularly, see Chapter 7.5.1.1 Oil level.
Oil temperature
The correct lubrication oil temperature is essential in keeping the bearing at the correct operating temperature, in
ensuring sufficient lubrication effect, and correct viscosity of the lubrication oil, see Chapter 7.5.2.1 Lubrication oil
temperature. See also the connection diagram and dimensional drawing.
Vibrations
All machines are subjected to, and designed to withstand vibrations. Large vibrations might cause the various parts
in the bearing to function different as intended.
Heavy vibrations can cause different phenomena in the oil film between the shaft and the white metal, but this will
rather seldom lead to oil leakages, but to bearing failures.
102 MANUAL FOR INDUCTION MOTORS AND GENERATORS
Heavy vibrations can cause the bearing housing parts to set, or to 'loosen up' just enough to allow the oil to enter the
split surface between the upper and the lower bearing housing halves. The vibrations will cause the bearing housing
parts to move in respect of each other. This can cause a 'pumping' effect in such a way, that oil will be pumped in and
out from the split surface. This will eventually remove the sealant, and cause the bearings to leak.
The bearing housing is not a hermetic compartment, and therefore any overpressure inside the bearing housing will
escape the bearing housing via the labyrinth seals. In escaping, the air will bring oil mist with it, thus causing the
bearing to leak.
Overpressure inside the bearing is normally caused by other components than the bearing itself. The most common
reason for overpressure inside the bearing is overpressure in the oil return piping.
Similar to overpressure inside the bearing, under pressure outside the bearing will 'suck' air out from inside the
bearing, thus bringing oil with it, and causing the bearing to leak oil.
Under pressure inside the bearing is normally not caused by the bearing itself, but by parts outside the bearing.
Under pressure near the bearing housing is caused by rotational parts moving the air next to them in such a way that
a local under pressure is formed next to the exit of the shaft of the bearing.
Oil
Following paragraphs for bearing type: Sleeve bearing with flood lubrication
The inlet pressure of the oil must be verified and adjusted accordingly.
The normal value for the oil pressure is 125 kPa ± 25 kPa (1.25 bar ± 0.25 bar), but the specific oil pressure value for
each machine must be verified from the documentation provided with the machine.
Following paragraphs for bearing type: Sleeve bearing with self lubrication
The temperature of the oil must be verified. A too high temperature will cause the viscosity of the oil to diminish,
thus making it easier to escape from the bearing.
NOTE: Bearings with only one Pt-100 temperature detector normally detect the temperature of
the bearing, not the oil. The temperature of the oil is approximately 10°C (20°F) lower than
the bearing temperature.
Following paragraph for bearing type: Sleeve bearing with flood lubrication
The normal oil inlet temperature is 45 °C (113 °F), but must be verified from the documentation provided with the
machine.
Vibrations
Vibration readings of the bearing housings should be taken in three directions: axial, transversal (horizontal) and
vertical, see Chapter 7.4.3 Bearing housing vibrations.
The air pressures inside and outside the bearings should be verified.
Overpressure is, as stated above, normally caused by overpressures in the oil tank. The overpressure from the oil tank
is then transmitted to the bearing via the oil return piping.
The best way to measure the pressure inside a bearing, is from the oil fill entrance or the inspection glass on top of
the bearing.
TROUBLE SHOOTING 103
In case overpressure inside the bearing is found, the following measures should be taken in the following order:
• Mount breather in the oil tank if possible. This is not suitable for diesel engine crankcases.
• Make sure the oil return pipe enters the oil tank below the oil level. This is essential for diesel engine
crankcases.
• Make a U-shaped 'water lock' on the oil return piping.
• Install a breather on top of the bearing housing.
The air pressure near the exit of the shaft from the bearing needs to be verified. This is especially important if the
bearing is flange mounted to the machine, or if the shaft is mounted inside a cover or other construction which
might form a 'centrifugal fan' together with the shaft.
Flange bearings have two canals between the bearing housing and the flange, which normally are enough to
compensate for any under pressure near the exit of the shaft from the bearing housing. However, if for some reason
a very large under pressure is present near this area, the two canals might not be enough, and some air is additionally
sucked from inside the bearing. This is especially likely to happen to sleeve bearings with axial thrust pads, as the oil
flow in these bearings is larger than in pure radial bearings.
If a large under pressure is noticed or suspected, the air pressure has to be measured near the exit of the shaft from
the bearing housing.
In order to verify that the under pressure outside the bearing can cause the leakage, the pressure outside the bearing
(p0) inside the bearing (p2), and the pressure in the area between the end shield and the machine seal (p1) must be
measured as well. When measuring (p1), the tube has to be inserted as deep as possible, and the canals must be
temporarily closed, see Figure 41 Verification of air pressure inside and outside of a sleeve bearing.
In order to analyze the situation, p1 and p2 have to be compared with p0, which has to be measured free from any
disturbances or turbulence near the machine. The following situations can appear:
• p0 = p1 = p2. If all pressure readings are the same, the leakage is not caused by pressure differences. However,
bear in mind what has been stated about diesel engines earlier.
• p2 > p1(= p0). If the pressure inside the bearing is larger than the outside pressure, there is only a situation with
overpressure inside the bearing.
• p2 (= p0) > p1. If the pressure outside the bearing is smaller the pressure elsewhere, there is under pressure
near the bearing.
• p2 > p0 > p1. If all pressure readings are different, there might be a situation where both overpressure inside
the bearing, and under pressure outside the bearing are present.
104 MANUAL FOR INDUCTION MOTORS AND GENERATORS
If a large under pressure is found to be inside the machine, e.g. between the end shield and the machine seal, the
situation is tricky; it is normally very difficult to remove the machine seal, and to re-seal it.
NOTE: In no case should a breather be installed to remedy under pressure in the bearing, as it will
only make the leakage worse.
There are two possible remedies for stator Pt-100 detector damage. If there are operational spare detectors
remaining in the stator core, they can be taken into use. If all the working factory assembled detectors are in use, a
new detector can be retrofitted in the winding end.
If the winding or cooling air temperature detectors show an abnormal temperature, a check of the cooling system
has to be done. Two separate maintenance issues affect the cooling system. The apparent part is to ensure the
uninterrupted and correct operation of the heat exchanger. This task is accomplished by periodically cleaning and
checking the heat exchanger for correct operation.
The air or water flow through the heat exchanger must also be checked. If the cooler is equipped with an external
blower fan, its operation needs also to be checked.
The less apparent but equally important part is to ensure good air circulation in the primary cooling circuit inside
the machine. This task can be fulfilled by cleaning and checking the machine interior during overhauls or if problems
arise.
Other possible causes for poor heat exchanger performance might include elevated ambient temperature, high
intake air or water temperature, and low air or water flow.
In addition, lubrication or bearing malfunction might lead to high bearing temperature. A seemingly high
temperature might also be caused by a problem in the temperature measurement system Chapter 8.3.2 Pt-100
resistance temperature detectors.
108 MANUAL FOR INDUCTION MOTORS AND GENERATORS
—
Chapter 9 Life cycle services for motors and generators
Life cycle services for motors and generators
NOTE: If available, please add the serial number of the machine (seven digits, starting with
46#####) to your e-mail for reference information.
The following chapters for product family: AXR, HXR and NXR
The following chapters for product family: AMA, AMB, AMI, NMH and NMI
—
Chapter 10 Recycling
Recycling
10.1 Introduction
ABB is committed to its environmental policy. ABB continuously strives to make its products more environmentally
sound by applying results obtained in recyclability and life cycle analyses. Products, manufacturing processes and
even logistics have been designed to take environmental aspects into account. ABB's environmental management
system, certified to ISO 14001, is the tool for carrying out the environmental policy.
The following instructions should only be seen as recommendations for environmentally sound disposal of machines.
It is the customer's responsibility to ensure that local regulations are followed. Some customer-specific items may
not be included in this User’s Manual. Additional documentation will be found in the project documentation.
Heat treatment
Duration: After obtaining 90% of the target temperature, the object shall stay a minimum of five hours at this
temperature.
Flow rate: The binder fumes shall stay a minimum of three seconds in the burning chamber.
NOTE: The emission consists mainly of O2-, CO-, CO2-, NOx-, CxHy-gases and microscopic particles.
It is on the user's responsibility to ensure that the process complies with the local
legislation.
NOTE: The heat treatment process and the maintenance of the heat treatment equipment
require special care in order to avoid any risk for fire hazards or explosions. Due to various
installations used for the purpose it is not possible for ABB to give detailed instructions
of the heat treatment process, or the maintenance of the heat treatment equipment and
these aspects must be taken care of by the customer.
WARNING: Magnetic stray fields, caused by an open or disassembled permanent magnet synchronous
machine or by a separate rotor of such a machine, may disturb or damage other electrical
or electromagnetic equipment and components, such as cardiac pacemakers, credit cards
and equivalent.
—
Appendix Commissioning report
Commissioning report
Customer:
Customer address:
Contact person:
Telephone:
Mobile phone:
Fax:
Email:
COMMISSIONING REPORT 117
Transportation
General:
Arrival date of the machine:
Inspection date and location:
Signature of consignee:
Open box inspection: no yes, done by:
Damages:
Packing list: no yes, missing items:
Machine: no yes, what kind of:
Package: no yes, what kind of:
Accessories: no yes, what kind of:
Spare parts + tools: no yes, what kind of:
Actions taken in response to damages:
Photographed: no yes, date:
Reported to the transportation company: no yes, to whom: date:
Reported to the supplier: no yes, to whom: date:
Reported to the insurance company: no yes, to whom: date:
Method of transportation:
Comments:
118 MANUAL FOR INDUCTION MOTORS AND GENERATORS
Storage
General:
Storage: no yes, begin:_______________end:_____________________
Storage time longer than 6 months: no yes
Person responsible for storage:
Storage place:
indoors outdoors
Mechanical installation
Foundation is checked according to no yes, drawing number:_____________________________
machine drawing:
Possible foundation anchor bolts or no yes
sole plates are mounted according to
instructions:
Air gap is measured, if applicable: For D-end N-end Exciter N-end
pedestal bearings, mark values 1-4,
top top top
and for flanged bearings, values A-D 1
____________ A ____________ 2 ____________
B ____________ 3 ____________ C
____________ 4 ____________ D ____________
For alignment of the coupling, use either Radial alignment of coupling Angular alignment of coupling
values 1-4 or values A-D 1 ____________ 2
top top
____________ 3 ____________ 4 ____________
A ____________ B ____________ C
____________ D ____________
______mm ______mm
Lubrication check
Self lubrication
Bearing oil: Manufacturer:__________________ Type:_________________________
The oil quality is the same as no yes
recommended:
Bearing oil is filled up to the indicated
level:
Please mark the level in the sight glass Sight Glass
circle on the right
Flood lubrication
Bearing oil: Manufacturer:__________________ Type:_________________________
The oil quality is the same as no yes
recommended:
Lubrication rings rotate freely: no yes
Flood lubrication oil pressure: ___________kPa
Oil flow: ___________liters/min
Rotation of the pumps checked: no yes
Jack-up pumps checked: no yes, alarm setting:_____kPa, relief valve setting:______kPa
Oil filters checked: no yes
Electrical installation
Network variation: no yes, voltage:______-______V, frequency:_____-______Hz
Space heater operation: no manual automatic, controlled by:_________________
Space heater for slip ring unit: no yes, voltage:_____________V, power:_______________W
The resistance test cannot be used to test the space heaters, because the heaters are based on self-limiting
thermistors. Instead, the testing of the heating performance is used.
Test requirements:
Test run
Comments:
Observations:
124 MANUAL FOR INDUCTION MOTORS AND GENERATORS
Machine approval
Machine approved for use Date:
Commissioning done by:
Approved by:
126 MANUAL FOR INDUCTION MOTORS AND GENERATORS
—
Appendix Typical position of plates
Typical position of plates
—
Appendix Typical main power cable connections
Typical main power cable connections
Connection screw
1. Screw: M16-bronze
2. Hexagon nut: M16-brass.
Tightening torque 40 Nm.
www.abb.com/motors&generators
Original instructions.
Unauthorized translations forbidden.
Copyright 2020 ABB.
All rights reserved.