Prepared by:
Catahan, Alexander Lenard D.
Cunan, Yna Marielle C.
Lingat, Mark Jefferson M.
2.4 MASONRY WORKS (CHB laying w/ Plastering) for 4'' CHB Pelayo, Prince Royce S.
Qty 226.22 sq.m
A. MATERIAL COST
142 bags Portland Cement @ Php 225 /bag Php 31950
13 cu.m Washed sand @ Php 400 /cu.m Php 5200
2828 pcs 4" CHB @ Php 8.5 /pc Php 24038
593 kgs 10mmØ Def. bars @ Php 40 /kg Php 23720
10 bd.ft # 16 G.I. tie wire @ Php 60 /kg Php 600
Php 85508
B. LABOR COST
1 Project Engineer @ Php 600 /day Php 600
1 Construction Foreman Php 450 /day Php 450
4 Mason Php 375 /day Php 1500
6 Laborer Php 250 /day Php 1500
Php 4050
Php 4050 x 15 day Php 60750
SUMMARY
A. MATERIAL COST Php 85508
B. LABOR COST Php 60750
Php 146258
plus: 7% OC Php 10238.06
8% CP Php 11700.64
12% VAT Php 17550.96
Prepared by:
Catahan, Alexander Lenard D.
Cunan, Yna Marielle C.
Lingat, Mark Jefferson M.
Pelayo, Prince Royce S.
Php 168196.7
Unit Cost = Php 168196.7 / 226.22 sq.m Php 743.5094
Total Item Cost = Php 743.5094 x 226.22 sq.m Php 168196.7
Prepared by:
Catahan, Alexander Lenard D.
Cunan, Yna Marielle C.
Lingat, Mark Jefferson M.
Pelayo, Prince Royce S.
2.4 MASONRY WORKS (CHB laying w/ Plastering) for 6'' CHB
Qty 260.505 sq.m
A. MATERIAL COST
163 bags Portland Cement @ Php 225 /bag Php 36675
14 cu.m Washed sand @ Php 400 /cu.m Php 5600
3257 pcs 6" CHB @ Php 10.5 /pc Php 34198.5
683 kgs 10mmØ Def. bars @ Php 40 /kg Php 27320
11 bd.ft # 16 G.I. tie wire @ Php 60 /kg Php 660
Php 104453.5
B. LABOR COST
1 Project Engineer @ Php 600 /day Php 600
1 Construction Foreman Php 450 /day Php 450
4 Mason Php 375 /day Php 1500
6 Laborer Php 250 /day Php 1500
Php 4050
Php 4050 x 17 day Php 68850
SUMMARY
A. MATERIAL COST Php 104453.5
B. LABOR COST Php 68850
Php 173303.5
plus: 7% OC Php 12131.25
8% CP Php 13864.28
Prepared by:
Catahan, Alexander Lenard D.
Cunan, Yna Marielle C.
Lingat, Mark Jefferson M.
Pelayo, Prince Royce S.
12%
VAT Php 20796.42
Php 199299
Unit Cost = Php 199299 / 260.505 sq.m Php 765.0488
Total Item Cost
= Php 765.0488 x 260.505 sq.m Php 199299