The meeting discussed the progress of elevator installation works at PKG 89/1 & 89/2. For both packages, mechanical works were completed but electrical works were stopped due to the lack of a permanent power source. Arabtec and DMC were tasked with coordinating with suppliers to provide required components like RCDs. Schindler would submit documents and certificates by certain dates and estimated 10 days per elevator to complete electrical works and testing. Arabtec and DMC would review schedules to provide handover timelines.

Uploaded by

baparis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views3 pages

Mom Z3

The meeting discussed the progress of elevator installation works at PKG 89/1 & 89/2. For both packages, mechanical works were completed but electrical works were stopped due to the lack of a permanent power source. Arabtec and DMC were tasked with coordinating with suppliers to provide required components like RCDs. Schindler would submit documents and certificates by certain dates and estimated 10 days per elevator to complete electrical works and testing. Arabtec and DMC would review schedules to provide handover timelines.

Uploaded by

baparis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

MOM – Coordination Meeting ( Elevator works @ PKG 89/1 & 89/2)

Upon our Concurrent meeting on Tuesday November 2, 2021 @ Uptown Cairo


regarding follow up Elevators works @ PKG 89/1 & 89/2 in presence of:

1- Eng., Yasser Fathi rmc – Senior Electrical Engineer.


2- Eng., Ahmed abd elrahman ATC – MEP Manager.
3- Eng., Soliman Ziyad DMC – Senior Electrical Engineer.
4- Eng., Amr Abdel Hady Schindler –Lead Project Manager.

All Messer discuss the current status of elevator works regarding each phase as
the following:-

 Execution
ExecutionProgress
Progress

A- PKG 89/1 (Bldg. 5, 6) & (Bldg. 7, 8) (Bldg., 9, 10, 11).


A_1: All Mech. Works (Brackets – Guide Rails “cabinet & counter weight “–
Elevator Machine – Threshold door frame only ) have been finished.

A_2: Elec. Works are stopping because there is no permanent electrical power
source 3 phase in the site, Schindler informed that there is no objection in
using Diesel Generator is allowable via Arabtec provided that ( permanent
cable feeder for elevator is done , Lighting fixtures inside the shaft shall be
executed with deviator switch in up & down shaft , disconnect switch for
elevator shall be existed and the dedicated MCCB @ EMDB Panel board for
Bldg. ( 5,6,7,8 ) and Service Panels for Bldg. (9,10,11) shall be provided with
RCD 300 milli amper as a machine protection from current leakage “ Not
Found as per IFC drawing – knowing that EMDBs are delivered in site”.

A_3: Arabtec shall send RFI regarding Schindler requirements for RCDs to
coordinate with GILA – Factory (panel builder supplier) to provide these
RCDs inside the panel boards (EMDBs & Service panels)

A_4: Schindler will provide with all factory test certificates for all elevators’
parts (Elevator by Elevator) max Thursday November 11, 2021.

A_5: Arabtec will complete all remaining works in elevator shaft (install
deviator wiring devices – shaft’s luminaires – Earthing works – Data’s cables
regarding IP telephone).

A_6: Arabtec will study with Schindler to complete electrical works in all
elevators by providing temporary devices (Disconnect Switches and RCDs)
till EMAAR provide in the site and test & commissioning will be performed in
case of completing all missing items as permanent.

Page 1
6 b o u l o s h a n n a │ t h i r d f l o o r │ d o k k i g i z a │ e g y p t
t e l + 2 0 2 . 7 6 0 . 7 9 3 3 │ f a x + 2 0 2 . 7 6 0 . 7 5 9 3
MOM – Coordination Meeting ( Elevator works @ PKG 89/1 & 89/2)

A_7: Arabtec informed that the permanent electrical current will be ready via
transformers after finishing all Landscape works above MV- Cables as per
EMAAR ‘s instructions to be protected from any damage may be occur “ i.e.
all transformer & infrastructure works @ Village Z3 in Arabtec Scope”.

A_8 : Schindler informed that will finish Elevator threshold doors after
Arabtec shall scavenge shaft elevators knowing that all elevator cabinet still
hold till providing all items are mentioned in clause A_2.

A_9: Schindler informed that each elevator will take 10 days / team for
remaining works (Electrical & QC TEST) to be ready for test &
commissioning.

A_10: Schindler obligates with informing both MC & consultant that the
elevators are ready to be tested in presence of Schindler QC audit.

A_11: Arabtec will review time schedule as whole including elevators’ works
to feedback us the accurate times for elevators’ handover.

B- PKG 89/2 (Bldg. 1, 2, 3, 4).

B_1: All Mech. Works (Brackets – Guide Rails “cabinet & counter weight “–
Elevator Machine – Threshold door frame only ) have been finished.

B_2: Elec. Works are stopping because there is no permanent electrical power
source 3 phase in the site, Schindler informed that there is no objection in
using Diesel Generator is allowable via DMC provided that ( permanent cable
feeder for elevator is done , Lighting fixtures inside the shaft shall be executed
with deviator switch in up & down shaft , disconnect switch for elevator shall
be existed and the dedicated MCCB @ EMDB Panel board shall be provided
with RCD 300 milli amper as a machine protection from current leakage “ Not
Found as per IFC drawing – knowing that EMDBs are delivered in site”.

B_3: DMC shall send RFI regarding Schindler requirements for RCDs to
coordinate with Hager – Factory (panel builder supplier) to provide these
RCDs inside the panel boards (EMDBs & Service panels) also deviator
switches inside all shafts.

Page 2
6 b o u l o s h a n n a │ t h i r d f l o o r │ d o k k i g i z a │ e g y p t
t e l + 2 0 2 . 7 6 0 . 7 9 3 3 │ f a x + 2 0 2 . 7 6 0 . 7 5 9 3
MOM – Coordination Meeting ( Elevator works @ PKG 89/1 & 89/2)

B_4: Schindler obligates with submitting all approved documents “scanned


copy” to DMC & rmc – Consultant on Thursday November 4, 2021.

B_5: Schindler will provide with all factory test certificates for all elevators’
parts (Elevator by Elevator) max Thursday November 11, 2021.

B_6: DMC will enable Schindler to install Threshold elevator doors by


erecting scaffolds building by building ASAP.

B_7: Schindler obligates with informing both MC & consultant that the
elevators are ready to be tested in presence of Schindler QC audit.

B_8: Schindler informed that each elevator will take 10 days / team for
remaining works (Electrical & QC TEST) to be ready for test &
commissioning.

B_9: DMC will study with Schindler to complete electrical works in all
elevators by providing temporary devices (Disconnect Switches and RCDs)
till EMAAR provide in the site and test & commissioning will be performed in
case of completing all missing items as permanent.

B_10: DMC will review time schedule as whole including elevators’ works to
feedback us the accurate times for elevators’ handover.