Final WTP Staff Quarters-2 Bhainsa 26.08.2021
Final WTP Staff Quarters-2 Bhainsa 26.08.2021
Final WTP Staff Quarters-2 Bhainsa 26.08.2021
Name of the work : Providing Drinking Water to Habitations in SRSP Adilabad Segment in Adilabad District
Name of Sub Work: Comparative statement for 6000KL Sump at Bhainsa Head Works
1 Removal of Hard rock by Machine which 7457.91 3310715.00 5896.29 2617461.00 -693254.00 As per actuals
require blasting
Sand filling in basement with watering and
2 tamping etc. complete. including Cost and 220.90 187345.00 0.00 0.00 -187345.00 As per actuals
conveyance of the all materials etc.
3 M30 grade design mix using 20mm HG metal As per approved drawing
of SE, TDWSP, Circle-
Nirmal, Dt: 15.02.2016
Foundations - Raft - M30 grade 905.93 8443902.00 881.64 8217502.00 -226400.00
Side wall
Haunch width 0.15
Haunch Portion 2.93 27310.00 8.10 75498.00 48188.00
instead of 0.3
1st step with 400 mm thick 19.59 221034.00 14.64 165183.00 -55851.00 As per site condition
2ndstep to 4th step with 400 mm thick 281.64 3411336.00 263.86 3195978.00 -215358.00
Rectangular Beams - M30 grade 75.60 839237.00 1.00 303626.00 -535611.00
Rectangular Columns - M30 grade 29.70 330076.00 1.00 35206.00 -294870.00
Top Slab - M30 Grade 314.56 3193633.00 300.44 413282.00 -2780351.00
Beams 0.00 0.00 73.22 812817.00 812817.00
Ventilator column 0.00 0.00 1.70 18872.00 18872.00
for Pre cast slab 0.00 0.00 7.26 73709.00 73709.00
Head room column 0.00 0.00 0.79 8780.00 8780.00
M30 grade for Head room 0.00 0.00 2.46 27309.00 27309.00
Head room slab & chajja 0.00 0.00 3.43 34824.00 34824.00
Page 1 of 230
Sl. As per approved WE As per Work done
No Description Excess/Less Remarks
Qty Amount Qty Amount
7 Cost of steel and Fabrication charges of steel 135.245 6950592.00 128.74 6616383.00 -334209.00 As per actuals
Page 2 of 230
Sl. As per approved WE As per Work done
No Description Excess/Less Remarks
Qty Amount Qty Amount
Page 3 of 230
HSD WSP date Material WSP of HSD
1/1/2015 HSD (EURO IV) 55.46109
1/16/2015 HSD (EURO IV) 55.38489
2/1/2015 HSD (EURO IV) 52.81096
2/16/2015 HSD (EURO IV) 50.96560
3/1/2015 HSD (EURO IV) 54.76571
3/16/2015 HSD (EURO IV) 54.76571
4/1/2015 HSD (EURO IV) 54.77896
4/16/2015 HSD (EURO IV) 51.99969
5/1/2015 HSD (EURO IV) 54.66645
5/16/2015 HSD (EURO IV) 57.71579
6/1/2015 HSD (EURO IV) 57.71686
6/16/2015 HSD (EURO IV) 56.19754
7/1/2015 HSD (EURO IV) 55.40911
7/16/2015 HSD (EURO IV) 52.88293
8/1/2015 HSD (EURO IV) 48.74227
8/16/2015 HSD (EURO IV) 47.47301
9/1/2015 HSD (EURO IV) 46.93023
9/16/2015 HSD (EURO IV) 46.93023
10/1/2015 HSD (EURO IV) 47.47302
10/16/2015 HSD (EURO IV) 48.50431
11/1/2015 HSD (EURO IV) 48.52971
11/16/2015 HSD (EURO IV) 49.48056
12/1/2015 HSD (EURO IV) 49.23542
12/16/2015 HSD (EURO IV) 48.75778
1/1/2016 HSD (EURO IV) 47.60707
1/16/2016 HSD (EURO IV) 46.68432
2/1/2016 HSD (EURO IV) 46.64876
2/16/2016 HSD (EURO IV) 46.64876
3/1/2016 HSD (EURO IV) 48.52629
3/16/2016 HSD (EURO IV) 48.52629
4/1/2016 HSD (EURO IV) 50.56434
4/16/2016 HSD (EURO IV) 50.22108
5/1/2016 HSD (EURO IV) 53.37467
5/16/2016 HSD (EURO IV) 53.37467
6/1/2016 HSD (EURO IV) 57.19322
6/16/2016 HSD (EURO IV) 58.55928
7/1/2016 HSD (EURO IV) 57.99576
7/16/2016 HSD (EURO IV) 57.55311
8/1/2016 HSD (EURO IV) 55.37392
8/16/2016 HSD (EURO IV) 53.20557
9/1/2016 HSD (EURO IV) 56.10032
9/16/2016 HSD (EURO IV) 55.72084
10/1/2016 HSD (EURO IV) 55.63412
10/16/2016 HSD (EURO IV) 58.63928
11/1/2016 HSD (EURO IV) 58.63928
11/16/2016 HSD (EURO IV) 57.78323
12/1/2016 HSD (EURO IV) 57.63144
12/16/2016 HSD (EURO IV) 57.63144
1/1/2017 HSD (EURO IV) 59.91922
1/16/2017 HSD (EURO IV) 62.45636
2/1/2017 HSD (EURO IV) 62.45636
2/16/2017 HSD (EURO IV) 62.45636
3/1/2017 HSD (EURO IV) 62.45636
3/16/2017 HSD (EURO IV) 62.45636
4/1/2017 HSD (EURO IV) 58.76489
4/16/2017 HSD (EURO IV) 60.08788
5/1/2017 HSD (EURO IV) 60.65200
5/16/2017 HSD (EURO IV) 58.00258
6/1/2017 HSD (EURO IV) 59.13036
6/16/2017 HSD (EURO IV) 57.51459
7/1/2017 HSD (EURO IV) 56.33156
7/16/2017 HSD (EURO IV) 58.09320
8/1/2017 HSD (EURO IV) 58.45085
8/16/2017 HSD (EURO IV) 59.74899
9/1/2017 HSD (EURO IV) 59.05329
9/16/2017 HSD (EURO IV) 61.14872
10/1/2017 HSD (EURO IV) 62.48726
10/16/2017 HSD (EURO IV) 60.15551
11/1/2017 HSD (EURO IV) 60.41084
11/16/2017 HSD (EURO IV) 61.96173
12/1/2017 HSD (EURO IV) 62.95121
12/16/2017 HSD (EURO IV) 62.81021
1/1/2018 HSD (EURO IV) 63.54770
1/16/2018 HSD (EURO IV) 65.41312
2/1/2018 HSD (EURO IV) 66.68261
2/16/2018 HSD (EURO IV) 65.39141
3/1/2018 HSD (EURO IV) 64.22010
3/16/2018 HSD (EURO IV) 64.69731
4/1/2018 HSD (EURO IV) 66.41088
4/16/2018 HSD (EURO IV) 67.59302
5/1/2018 HSD (EURO IV) 69.74041
5/16/2018 HSD (EURO IV) 71.92705
6/1/2018 HSD (EURO IV) 74.77939
6/16/2018 HSD (EURO IV) 72.65369
7/1/2018 HSD (EURO IV) 71.37392
7/16/2018 HSD (EURO IV) 73.12414
8/1/2018 HSD (EURO IV) 71.69255
8/16/2018 HSD (EURO IV) 72.68192
9/1/2018 HSD (EURO IV) 74.36296
9/16/2018 HSD (EURO IV) 77.98532
10/1/2018 HSD (EURO IV) 79.24339
10/16/2018 HSD (EURO IV) 81.17766
11/1/2018 HSD (EURO IV) 79.47308
11/16/2018 HSD (EURO IV) 75.37200
12/1/2018 HSD (EURO IV) 67.90300
12/16/2018 HSD (EURO IV) 63.61946
1/1/2019 HSD (EURO IV) 62.12280
1/16/2019 HSD (EURO IV) 63.73876
2/1/2019 HSD (EURO IV) 67.06500
2/16/2019 HSD (EURO IV) 68.44300
3/1/2019 HSD (EURO IV) 70.66585
3/16/2019 HSD (EURO IV) 68.96300
4/1/2019 HSD (EURO IV) 67.69400
4/16/2019 HSD (EURO IV) 68.31240
5/1/2019 HSD (EURO IV) 70.30757
5/16/2019 HSD (EURO IV) 69.43905
6/1/2019 HSD (EURO IV) 70.52133
6/16/2019 HSD (EURO IV) 66.63868
7/1/2019 HSD (EURO IV) 64.58900
7/16/2019 HSD (EURO IV) 69.44981
7/17/2019 HSD (EURO IV) 69.44981
7/18/2019 HSD (EURO IV) 69.44981
7/19/2019 HSD (EURO IV) 69.44981
7/20/2019 HSD (EURO IV) 69.44981
7/21/2019 HSD (EURO IV) 69.44981
7/22/2019 HSD (EURO IV) 69.44981
7/23/2019 HSD (EURO IV) 69.44981
7/24/2019 HSD (EURO IV) 69.44981
7/25/2019 HSD (EURO IV) 69.44981
7/26/2019 HSD (EURO IV) 69.44981
7/27/2019 HSD (EURO IV) 69.44981
7/28/2019 HSD (EURO IV) 69.44981
7/29/2019 HSD (EURO IV) 69.44981
7/30/2019 HSD (EURO IV) 69.44981
7/31/2019 HSD (EURO IV) 69.44981
Leads statement
TELANGANA WATER GRID - SANGAREDDY SEGMENT IN MEDAK DISTRICT
Municipal allowence 0%
Total cost
Conveyance- with
Name of the Blasting Machine seignorag
Sl. No Description of material lead (km) Initial cost Excluding Stacking
Quarry charges crushing e/1.1361 embedded
13.615%
5 tax
1 40mm size HBG (SS5) Nirmal 65 845.00 837.39 44.01 1726.40
2 20mm size HBG metal Nirmal 65 1365.00 837.39 44.01 2246.40
3 CR Stone Nirmal 55 262.00 634.78 44.01 940.79
4 RR Stone Nirmal 55 252.00 634.78 44.01 930.79
5 Bond stone (25x25x45 Cm) Nirmal 55 1387.00 744.97 44.01 2175.98
6 Sand for concrete items Peddavagu 138 422.00 1476.30 35.21 1933.51
7 Sand for mortar Peddavagu 138 566.00 1476.30 35.21 2077.51
8 Sand for filling Local 15 302.00 313.16 35.21 650.37
9 Bricks Khanapur 15 5000.00 669.98 33.89 5703.86637
10 Cement 6200 6200.00
11 Steel Fe 500 of SAIL, TATA, Jindal 40000 40000.00
12 Steel I Beams 40000 40000.00
13 6 mm size HBG metal Nirmal 55 735.00 744.97 44.01 1523.98
14 12mm size HBG metal Nirmal 55 1097.00 744.97 44.01 1885.98
15 10mm size HBG metal Nirmal 55 935.00 744.97 44.01 1723.98
16 uncoursed rubble stone Nirmal 55 330.00 634.78 44.01 1008.79
17 Gravel Local 10 103.00 258.15 19.36 380.51
18 Shabad stone thandur 150 240.00 2139.59 2.20 2381.79
19 Present Pig Iron Cost as per BOC 26000
20 Present Coke Cost as per SSR 36570
21 Binding wire 70 70.00
22 Water 77 77.00
23 Paint 276 276.00
24 White Cement 29 29.00
25 Snowcem 55 55.00
26 Synthetic enamel Paint 175 175.00
27 Synthetic enamel Paint 276 276.00
28 Accoproof Powder 75 75.00
29 Emulsion Piant 225 225.00
30 Wood Primer 158 158.00
31 Epoxy protective coating 633 633.00
32 Gelatin 80% 73 73.00
33 Detonetor Electric 13 13.00
34 GI pipe 32mm 250.2 250.20
35 MS Angles 40 40.00
36 SS Railing 40mm dia Pipe 391 391.00
37 Aluminium anodized Sections for frames 321 321.00
This is to certify that the leads are correct to the best of my knowledge
Asst. Executive Engineer Dy. Executive Engineer Executive Engineer Superintending Engineer
TDWSP Medchal TDWSP Sub division TDWSP Division TDWSP Circle
Medchal Hyderabad Hyderabad
1 Binding wire M072, 70 PHSSR-p19
2 Delifting charges 41 Lift charges 134 with SSR 2015-16
3 Slab up to 150mm 1 sqmt 389 bldg.92
3 Slab above 150mm upto 300mm 1 sqmt 399 bldg.92
4 Slab above 300mm 1 sqmt 418 bldg.89
5 Centering Charges Footing/BedBlocks 750 bldg.89 305 Bed blocks
6 Lifting charges (Concrete) 134
7 Mason Ist Class 415 PHSSR-p6
8 Mason II nd class/Work Inspector 370 PHSSR-p6
9 Men mazdoor 310 p11
10 Woman Mazdoor 310 p11
11 Centering Charges Ring Beam/Cir Col 1206 PHSSR-p46
12 Centering Charges Doome 2670.00 PHSSR-p46 1643 Roof slab
13 Earth work Initial rate (up to 3M) Manual Excavation 112.84 R&B.Ch.11/1
14 Earth work Initial rate(3-6m) Manual Excavation 145.08 R&B.Ch.11/2/A
15 Earth work Initial rate(above-6m) Manual Excavation 193.44 R&B.Ch.11/3/A
16 Sand filling Charges Manual Refilling 96.10 R&B.Ch.11/2/A
17 Water 77.00 M 189
18 dome slabs centering 6302.00 buildings
19 Beams 3428.00 bldg.89
20 Column/Braces centering charges 1099.00 PH P-301
20a Brace centering charges(Circular) 1206.00 PH p-47
21 Columns 2041.00 bldg.89
22 Column above 3.6mt 2381.15 bldg.89
23 Beams above 3.66m height 3999.31 bldg.89
24 Lintels 2344.00 bldg.89 1068 Pedestrals
25 Sun shades 0.6m Width 410.00 bldg.89
26 Roof slab up to 150mm thick 389.00 bldg.89 650 above 3.66m 201
27 Roof slab 150-300mm thick 399.00 bldg.89 669 above 3.66m 209
28 Roof slab above 300.0mm thick 418.00 bldg.89 408 upto 3.66mts height 219
29 Helical Stair case 1 sqmt 480.00 bldg.89
30 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity 338.90 P-49 CSSR item 16
31 Cost of Diesel for Miller per Lts 59.10 C-SSR p-30
32 Cost of Petrol for Vibrator per Lts 74.73 C-SSR p-21 above 3.66m
33 RCC Vertical wall of circular surface GLSR/Sump 1115.00 1449.50 1469
34 Side walls curved surfaces. ELSR 2463.00 PH p-8 1909.7
35 Side walls St Surface ELSR 2192.00 PH p-48
36 Lifting charges (Mortar) 71.80 60.9
37 Pig Iron as per SSR 26000 PH p-72
38 Coke as per SSR 36570 PH p-72
39 CI specials per Kg as per SSR 73.70 PH p-72
40 Seignorage charges Gravel 22.00
RCC Vertical wall of plane surfaces GLSR/Sump 876.00 876 both faces
41 wood primer 158.00 Bld SSR-31-S.No371
42 cost of Syenthetic Enamil paint Grade-I 276.00 Bld SSR-28-S.No382
43 cost of white cement 29.00 Bld SSR-88-S.No943
44 Snowcem @ 55.00 Bld SSR-27-S.No376 water proof cement
45 Rooling Shutters80x1.25mm 3576.00 Bld SSR-28-S.No137
46 Painter 1st class 480.00
47 Acco Proof powder 75.00 (water proofing compound) as per buildings ssr
48 weigh Batcher hire charges 0.5 Cum ( 6 Cum/hr) 548.30
49 Aluminium anodized Sections for frames 321.00
RSF Rate
As per SSR 2015-16
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out,
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and
construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50
1 1 disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated
m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical
suitable material as per Technical Specification 305 MORD / 304 MORTH ordianry gravelly soils for
Specification 305 MORD / 304 MORTH ordianry gravelly soils for foundations .
foundations .
Removal of Hard rock by Machine which require blasting such as hard rock, sheet rock and boulders for Structures Removal of Hard rock by Machine which require blasting such as hard rock, sheet rock and boulders for
2 2
including cost and conveyance of all material and labour charges etc completed Structures including cost and conveyance of all material and labour charges etc completed
Hard rock
(III) Hard rock (requiring blasting) (III)
(requiring blasting)
Upto 3 m depth
Upto 3 m depth including 1.5
including 1.5 m
m depth in hard rock
depth in hard rock
Page 52 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
c) Material c) Material
Gelatin 80% kg 3.50 73.00 255.50 Gelatin 80% kg 3.50 56.68 198.38
Detonator electric Nos. 14.00 13.00 182.00 Detonator electric Nos. 14.00 10.09 141.26
d&e) Overheads & Contractors Profit 3907.20 d&e) Overheads & Contractors Profit 3809.35
Sand filling inside shaft upto Ground level including watering, Ramming including cost & Conveyance of all materials Sand filling inside shaft upto Ground level including watering, Ramming including cost & Conveyance of all
3 3
labour charges etc completed as per standard specification. materials labour charges etc completed as per standard specification.
1.00 cum cost of sand @ Rs. 650.37 per cum 650.37 1.00 cum cost of sand @ Rs. 635.99 per cum 635.99
0.31 cum Labour charges Rs. 310.00 96.10 R&B.Ch.11/2/A 0.31 cum Labour charges Rs. 310.00 96.10
WQ --- 0% 0.00 WQ --- 0% 0.00
Contractor's Profit 13.615% 101.63 Contractor's Profit 13.615% 99.67
Total rate per cum Rs. 848.10 Total rate per cum Rs. 831.76
of all materials and labour charges ,seigniorage charges using concret mixer etc complete of all materials and labour charges ,seigniorage charges using concret mixer etc complete
162 kg Cement Rs. 6200.00 cum 1004.40 162 kg Cement Rs. 4813.29 cum 779.75
0.9 cum Coarse aggregate 40 mm Rs. 1726.40 cum 1553.76 0.9 cum Coarse aggregate 40 Rs. 1726.40 cum 1553.76
0.45 cum Sand for concrete Rs. 1933.51 each 870.08 0.45 cum Sand for concrete Rs. 1913.41 each 861.04
1.2 kl Water (including for curing) Rs. 77.00 each 92.40 SSr Pg.41 1.2 kl Water (including for Rs. 73.33 each 88.00
1 hour Concrete Mixer 10 / 7 cft (0.2 Rs. 338.90 each 338.90 SSr Pg.49 1 hour Concrete Mixer 10 / 7 Rs. 338.90 each 338.90
0.10 day Mason 1st class Rs. 415.00 41.50 SSr Pg.14 0.10 day Mason 1st class Rs. 415.00 41.50
1.39 day Mazdoor (unskilled) Rs. 310.00 Cum 430.90 SSr Pg.16 1.39 day Mazdoor (unskilled) Rs. 310.00 Cum 430.90
WQ Water Charges 1% 4.72 WQ Water Charges 1% 4.72
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 590.44 Contractor's Profit 13.615% 558.02
Total Rs. 4927.10 Total Rs. 4656.59 270.51
4
CC(1:3:6) using 40 mm HG metal icluding all cost and conveyance of all materials labour charges etc 4 CC(1:3:6) using 40 mm HG metal icluding all cost and conveyance of all materials labour charges etc
completed as per standard specification. For foundation & leveling course completed as per standard specification. For foundation & leveling course
220 kg Cement Rs. 6200.00 cum 1364.00 220 kg Cement Rs. 4813.29 cum 1058.92
Coarse aggregate 40 mm & Coarse aggregate
0.9 cum Rs. 1726.40 cum 1553.76 0.9 cum Rs. 1726.40 cum 1553.76
20 mm 40 mm & 20 mm
0.45 cum Sand for concrete Rs. 1933.51 each 870.08 0.45 cum Sand for concrete Rs. 1913.41 each 861.04
Page 53 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
1.2 kl Water (including for curing) Rs. 77.00 each 92.40 1.2 kl Water (including for Rs. 73.33 each 88.00
1 hour Concrete Mixer 10 / 7 cft (0.2 Rs. 338.90 each 338.90 1 hour Concrete Mixer 10 / 7 Rs. 338.90 each 338.90
0.10 day Mason 1st class Rs. 415.00 41.50 0.10 day Mason 1st class Rs. 415.00 41.50
1.39 day Mazdoor (unskilled) Rs. 310.00 Cum 430.90 1.39 day Mazdoor (unskilled) Rs. 310.00 Cum 430.90
Water Charges 1% 4.72 Water Charges 1% 4.72
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 639.40 Contractor's Profit 13.615% 596.03
Total Rs. 5335.66 Total Rs. 4973.77
4 Cement concrete (1:3:6)prop using 40 mm 60% and 20mm 40% gauge HG metal including cost &conveyance 4
of all materials and labour charges ,seigniorage charges using concret mixer etc complete
220 kg Cement Rs. 6200.00 cum 1364.00
0.54 cum Coarse aggregate 40 mm Rs. 1726.40 cum 932.26
5 Construction of Randam rubble stone masonry in CM(1:6) 2nd sort including cost and 5 Construction of Randam rubble stone masonry in CM(1:6) 2nd sort including cost and
conveyance of all materials and labour charges ,seigniorage charges etc complete. conveyance of all materials and labour charges ,seigniorage charges etc complete.
79.2 kg Cement Rs. 6200.00 kg 491.04 79.2 kg Cement Rs. 4813.29 kg 381.21
0.44 cum CR Stone Rs. 940.79 cum 413.95 0.44 cum CR Stone Rs. 928.31 cum 408.46
0.5 cum Rough Stone Rs. 930.79 cum 465.39 0.5 cum Rough Stone Rs. 918.79 cum 459.39
Page 54 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
0.16 cum Bond Stones 7Nos 0.25 x 0.25 x Rs. 2175.98 cum 348.16 0.16 cum Bond Stones 7Nos 0.2 Rs. 2109.93 cum 337.59
0.33 cum Sand for Mortar Rs. 2077.51 cum 685.58 0.33 cum Sand for Mortar Rs. 2050.55 cum 676.68
1.2 day Mason 1st class Rs. 415.00 day 498.00 1.2 day Mason 1st class Rs. 415.00 day 498.00
2 day Mazdoor (unskilled) Rs. 310.00 day 620.00 2 day Mazdoor (unskilled) Rs. 310.00 day 620.00
WQ/Comp --- 0% 0.00 WQ/Comp --- 0% 0.00
Contractor's Profit 13.615% 479.54 Contractor's Profit 13.615% 460.37
Total rate per cum Rs. 4001.65 Total rate per cum Rs. 3841.70 159.95
6 Construction of course rubble stone masonry in CM(1:6) 2nd sort including cost and 6 Construction of course rubble stone masonry in CM(1:6) 2nd sort including cost and
conveyance of all materials and labour charges ,seigniorage charges etc complete. conveyance of all materials and labour charges ,seigniorage charges etc complete.
0.94 cum Intial cost of CR stone @ Rs. 940.79 cum 884.34 0.94 cum Intial cost of CR sto Rs. 928.31 cum 872.61
0.16 cum Bond Stones 7Nos 0.24 x 0.24 x Rs. 2175.98 cum 348.16 0.16 cum Bond Stones 7Nos 0.2 Rs. 2109.93 cum 337.59
0.32 cum Sand for Mortar Rs. 2077.51 cum 664.80 0.32 cum Sand for Mortar Rs. 2050.55 cum 656.18
1.50 nos. masons 1st class @ Rs. 415.00 each 622.50 1.50 nos. masons 1st class @ Rs. 415.00 each 622.50
2.32 nos. man and woman mazdoor @ Rs. 310.00 each 719.20 2.32 nos. man and woman ma Rs. 310.00 each 719.20
0.0768 MT cost of cement @ Rs. 6200.00 MT 476.16 0.0768 MT cost of cement @ Rs. 4813.29 MT 369.66
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 505.82 Contractor's Profit 13.615% 487.11
Total rate per cum Rs. 4220.98 Total rate per cum Rs. 4064.85 156.13
7 Construction of super stucture with brick masonary in (1:6) using 2nd class bricks including 7 Construction of super stucture with brick masonary in (1:6) using 2nd class bricks including
cost and conveyance of all materials,labour charges and seign. charges etc. complete. cost and conveyance of all materials,labour charges and seign. charges etc. complete.
520 nos. cost of bricks Rs. 5703.87 per 1000 2966.01 520 nos. cost of bricks Rs. 5703.87 per 1000 2966.01
0.21 cum Sand for Mortar Rs. 2077.51 cum 436.28 0.21 cum Sand for Mortar Rs. 2050.55 cum 430.62
0.24 nos. brick layer 1st class @ Rs. 415.00 each 99.60 0.24 nos. brick layer 1st class Rs. 415.00 each 99.60
0.56 nos. brick layer 2nd class @ Rs. 370.00 each 207.20 0.56 nos. brick layer 2nd class Rs. 370.00 each 207.20
1.89 nos. man and woman mazdoor @ Rs. 310.00 each 585.90 1.89 nos. man and woman ma Rs. 310.00 each 585.90
0.0504 MT cost of cement @ Rs. 6200.00 MT 312.48 50.4 0.0504 MT cost of cement @ Rs. 4813.29 MT 242.59
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 627.31 Contractor's Profit 13.615% 617.02
Total rate per cum Rs. 5234.77 Total rate per cum Rs. 5148.94 85.83
Thickness 230 mm Thickness 230 mm
Above GL Above GL
0-3 m 0 5234.77 0-3 m 0 5148.94 85.83
3-6m 71.76 624.00 708.96 5943.73 3-6m 71.76 624.00 708.96 5857.90 85.83
6-9m 97.71 849.65 965.33 6793.38 6-9m 0 0.00 0.00 5857.90
9-12m 123.66 1075.30 1221.70 7868.68 9-12m 0 0.00 0.00 5857.90
12-15m 149.62 1301.04 1478.18 9169.72 12-15m 0 0.00 0.00 5857.90
15-18m 175.57 1526.70 1734.56 10696.42 15-18m 0 0.00 0.00 5857.90
18-21m 201.52 1752.35 1990.93 12448.77 18-21m 0 0.00 0.00 5857.90
21-24m 227.47 1978.00 2247.30 14426.77 21-24m 0 0.00 0.00 5857.90
24-27m 253.42 2203.65 2503.68 16630.42 24-27m 0 0.00 0.00 5857.90
27-30m 279.38 2429.39 2760.15 19059.81 27-30m 0 0.00 0.00 5857.90
8 Cement concrete(1:1.5:3) prop using 20mm gauge HG metal including cost and conveyance 8 Cement concrete(1:1.5:3) prop using 20mm gauge HG metal including cost and conveyance
of all materials and labour charges ,seign. charges etc.complete. of all materials and labour charges ,seign. charges etc.complete.
FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth) FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)
0.9 cum 20mm HBG graded metal Rs. 2246.40 cum 2021.76 0.9 cum 20mm HBG graded m Rs. 2246.40 cum 2021.76
Page 55 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
0.45 cum Sand for concrete Rs. 1933.51 cum 870.08 0.45 cum Sand for concrete Rs. 1913.41 cum 861.04
400 Kgs Cement Rs. 6200.00 Kgs 2480.00 400 Kgs Cement Rs. 4813.29 Kgs 1925.32
0.133 day 1st Class Mason Rs. 415.00 day 55.20 0.133 day 1st Class Mason Rs. 415.00 day 55.20
0.267 day 2nd Class Mason Rs. 370.00 day 98.79 0.267 day 2nd Class Mason Rs. 370.00 day 98.79
3.6 day Mazdoor (Both Men and Wom Rs. 310.00 day 1116.00 3.6 day Mazdoor (Both Men Rs. 310.00 day 1116.00
1 hour Concrete Mixer 10 / 7 cft (0.2 Rs. 338.90 hour 338.90 1 hour Concrete Mixer 10 / 7 Rs. 338.90 hour 338.90
0.133 Liters Cost of Diesel for Miller Rs. 59.10 Liters 7.86 0.133 Liters Cost of Diesel for Mil Rs. 59.10 Liters 7.86
0.667 Liters Cost of Petrol for Vibrator 74.73 Liters 49.84 0.667 Liters Cost of Petrol for Vibrator 74.73 Liters 49.84
1.2 kl Water (including for curing) 77.00 kl 92.40 1.2 kl Water (including for curing) 73.33 kl 88.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 970.86 Contractor's Profit 13.615% 893.51
Total rate per cum 8101.69 Total rate per cum 7456.21 645.48
9 COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS 9 COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS
0.9 cum 20mm HBG graded metal 2246.40 cum 2021.76 0.9 cum 20mm HBG graded metal 2246.40 cum 2021.76
0.45 cum Sand for concrete 1933.51 cum 870.08 0.45 cum Sand for concrete 1913.41 cum 861.04
400.0 Kgs Cement 6200.00 Kgs 2480.00 400.0 Kgs Cement 4813.29 Kgs 1925.32
0.167 day 1st Class Mason 415.00 day 69.31 0.167 day 1st Class Mason 415.00 day 69.31
0.167 day 2nd Class Mason 370.00 day 61.79 0.167 day 2nd Class Mason 370.00 day 61.79
4.7 day Mazdoor (Both Men and Women) 310.00 day 1457.00 4.7 day Mazdoor (Both Men and Women) 310.00 day 1457.00
1 hour Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) ca 338.90 hour 338.90 1 hour Concrete Mixer 10 / 7 cft (0.2 / 0. 338.90 hour 338.90
1.2 kl Water (including for curing) 77.00 kl 92.40 1.2 kl Water (including for curing) 73.33 kl 88.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 1006.32 Contractor's Profit 13.615% 928.97
8397.60 7752.10 645.50
Page 56 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
12 W.Quarter 12 W.Quarter
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
charges, centering etc., complete but excluding cost of steel and its fabrication charges for
centering etc., complete but excluding cost of steel and its fabrication charges for floor slab of
floor slab of
125 mm thick 125 mm thick
1.25 Cum Cost of VCC (1:1.5:3) 7279.00 1 cum 9098.75 1.25 Cum Cost of VCC (1:1.5:3) 6633.50 1 cum 8291.88
10.00 sqm Centering charges 389.00 1 Sqm 3890.00 10.00 sqm Centering charges 389.00 1 Sqm 3890.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 529.62 Contractor's Profit 13.615% 529.62
Sundies Sundies
Total 10sqmt 13518.37 Total 10sqmt 12711.50 806.87
Columns above 3.0 m (1:1.5:3) 8397.60 2381.15 324.19 11102.95 /1Cum Columns above (1:1.5:3) 7752.10 2381.15 324.19 10457.45 /1Cum 645.50
Beams (1:1.5:3) 7279.00 3428.00 466.72 11173.72 /1Cum Beams (1:1.5:3) 6633.50 3428.00 466.72 10528.22 /1Cum 645.50
Beams above 3.66m he(1:1.5:3) 7279.00 3999.31 544.51 11822.82 /1Cum Beams above 3. (1:1.5:3) 6633.50 3999.31 544.51 11177.32 /1Cum 645.50
Lintels (1:1.5:3) 8397.60 2344.00 319.14 11060.74 /1Cum Lintels (1:1.5:3) 7752.10 2344.00 319.14 10415.24 /1Cum 645.50
Sun shades 0.075m thi(1:1.5:3) 6298.20 4100.00 558.22 10956.42 /10 sqmt Sun shades 0.07(1:1.5:3) 5814.08 4100.00 558.22 10472.29 /10 sqmt 484.13
Roof slab 150mm thick(1:1.5:3) 10918.50 3890.00 529.62 15338.12 /10 sqmt Roof slab 150mm (1:1.5:3) 9950.25 3890.00 529.62 14369.87 /10 sqmt 968.25
Roof slab 200 mm thic (1:1.5:3) 14558.00 3990.00 543.24 19091.24 /10 sqmt Roof slab 200 m(1:1.5:3) 13267.00 3990.00 543.24 17800.24 /10 sqmt 1291.00
Roof slab 250 mm thic (1:1.5:3) 18197.50 3990.00 543.24 22730.74 /10 sqmt Roof slab 250 m(1:1.5:3) 16583.75 3990.00 543.24 21116.99 /10 sqmt 1613.75
Roof slab 300 mm thic (1:1.5:3) 21837.00 3990.00 543.24 26370.24 /10 sqmt Roof slab 300 m(1:1.5:3) 19900.50 3990.00 543.24 24433.74 /10 sqmt 1936.50
Roof slab 350.0mm thi(1:1.5:3) 25476.50 4180.00 569.11 30225.61 /10 sqmt Roof slab 350.0 (1:1.5:3) 23217.25 4180.00 569.11 27966.36 /10 sqmt 2259.25
Bed blocks (1:1.5:3) 8101.69 305 41.53 8448.22 /1Cum Bed blocks (1:1.5:3) 7456.21 305.00 41.53 7802.74 /1Cum 645.48
Pedestals (1:1.5:3) 8101.69 1068 145.41 9315.10 /1Cum Pedestals (1:1.5:3) 7456.21 1068.00 145.41 8669.62 /1Cum 645.48
5 Cost of CM(1:3) prop including cost and conveyance of all materials and labour 5 Cost of CM(1:3) prop including cost and conveyance of all materials and labour
charges etc., complete. charges etc., complete.
0.48 MT Cost of cement @ Rs. 6200.00 MT 2976.00 0.48 MT Cost of cement @ Rs. 4813.29 MT 2310.38
1.05 cum cost of sand @ Rs. 2077.51 cum 2181.38 1.05 cum cost of sand @ Rs. 2050.55 cum 2153.08
0.20 Nos mixing charges @ Rs. 310.00 each 62.00 0.20 Nos mixing charges @ Rs. 310.00 each 62.00
--- 0% 0.00 --- 0% 0.00
Total rate per cum Rs. 5219.38 Total rate per cum Rs. 4525.46
15 Cost of CM(1:4) prop including cost and conveyance of all materials and labour 15 Cost of CM(1:4) prop including cost and conveyance of all materials and labour
charges etc., complete. 10.08 charges etc., complete.
0.36 MT Cost of cement @ Rs. 6200.00 MT 2232.00 0.36 MT Cost of cement @ Rs. 4813.29 MT 1732.78
1.05 cum cost of sand @ Rs. 2077.51 cum 2181.38 1.05 cum cost of sand @ Rs. 2050.55 cum 2153.08
0.20 Nos mixing charges @ Rs. 310.00 each 62.00 0.20 Nos mixing charges @ Rs. 310.00 each 62.00
--- 0% 0.00 --- 0% 0.00
Total rate per cum Rs. 4475.38 Total rate per cum Rs. 3947.87 527.51
16 Cost of CM(1:5) prop including cost and conveyance of all materials and labour 16 Cost of CM(1:5) prop including cost and conveyance of all materials and labour
charges etc., complete. charges etc., complete.
Page 57 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
0.288 MT Cost of cement @ Rs. 6200.00 MT 1785.60 0.288 MT Cost of cement @ Rs. 4813.29 MT 1386.23
1.05 cum cost of sand @ Rs. 2077.51 cum 2181.38 1.05 cum cost of sand @ Rs. 2050.55 cum 2153.08
0.20 Nos mixing charges @ Rs. 310.00 each 62.00 0.20 Nos mixing charges @ Rs. 310.00 each 62.00
--- 0% 0.00 --- 0% 0.00
Total rate per cum Rs. 4028.98 Total rate per cum Rs. 3601.31 427.67
17 Cost of CM(1:6) prop including cost and conveyance of all materials and labour 17 Cost of CM(1:6) prop including cost and conveyance of all materials and labour
charges etc., complete. charges etc., complete.
0.24 MT Cost of cement @ Rs. 6200.00 MT 1488.00 0.24 MT Cost of cement @ Rs. 4813.29 MT 1155.19
1.05 cum cost of sand @ Rs. 2077.51 cum 2181.38 1.05 cum cost of sand @ Rs. 2050.55 cum 2153.08
0.20 Nos mixing charges @ Rs. 310.00 each 62.00 0.20 Nos mixing charges @ Rs. 310.00 each 62.00
--- 0% 0.00 --- 0% 0.00
Total rate per cum Rs. 3731.38 Total rate per cum Rs. 3370.27 361.11
18 Flush pointing with CM(1:3) prop for stone/brick masonry including cost and conveyance of all 18 Flush pointing with CM(1:3) prop for stone/brick masonry including cost and conveyance of all
materials,labour charges and seign. chargesetc. complete. materials,labour charges and seign. chargesetc. complete.
0.03 cum cost of sand @ Rs. 2077.51 cum 62.33 0.03 cum cost of sand @ Rs. 2050.55 cum 61.52
0.5 nos. masons 2nd class @ Rs. 370.00 each 185.00 0.5 nos. masons 2nd class @ Rs. 370.00 each 185.00
0.74 nos. man and woman mazdoor @ Rs. 310.00 each 229.40 0.74 nos. man and woman ma Rs. 310.00 each 229.40
0.0144 MT cost of cement @ Rs. 6200.00 MT 89.28 0.0144 MT cost of cement @ Rs. 4813.29 MT 69.31
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 77.06 Contractor's Profit 13.615% 74.23
Total rate per 10 sqm 643.07 Total rate per 10 sqm 619.46 23.61
19 Plastering with CM(1:3) prop 20mm thick to brick wall including cost&coveyance of all 19 Plastering with CM(1:3) prop 20mm thick to brick wall including cost&coveyance of all
materials, lalbour charges,seign.charges etc.complete. (1:3)-20mm (1:5)-20mm materials, lalbour charges,seign.charges etc.complete. (1:3)-20mm (1:5)-20mm
0.21 Cum Cost of CM(1:3) 5219.38 cum 1096.07 846.09 0.21 Cum Cost of CM(1:3) 4525.46 cum 950.35 756.28
0.94 Nos. Mason 2nd class 370.00 each 347.80 347.8 0.94 Nos. Mason 2nd class 370.00 each 347.80 347.8
1.60 Nos. Man Mazdoor 310.00 each 496.00 496.00 1.60 Nos. Man Mazdoor 310.00 each 496.00 496.00
--- 0% 0.00 0.00 --- 0% 0.00 0.00
Contractor's Profit 13.615% 264.11 230.08 Contractor's Profit 13.615% 244.27 217.85
Total rate per 10 sqm 2204.00 1919.96 Total rate per 10 sqm 2038.40 1817.93 102.03
20 Impervous coat with Plastering in CM(1:3) prop 12/20 mm thick including cost&coveyance of all 20 Impervous coat with Plastering in CM(1:3) prop 12/20 mm thick including cost&coveyance of all
materials lalbour charges,seign.charges etc.complete for wearing coat. 12mm thick 20mm thick materials lalbour charges,seign.charges etc.complete for wearing 12mm thick 20mm thick
0.15 cum Cost of CM(1:3) 5219.38 782.91 1096.07 0.15 cum Cost of CM(1:3) 4525.46 678.82 950.35
0.6 nos. mason 1st class @ 415.00 249.00 390.1 0.6 nos. mason 1st class @ 415.00 249.00 390.1
0.96 nos. man and woman mazdoor @ 310.00 297.60 496 0.96 nos. man and woman ma 310.00 297.60 496
1.50 Kg accoproof chemical @ 75.00 112.50 150 1.50 Kg accoproof chemical 0.00 0.00 0
--- 0% 0.00 0.00 --- 0% 0.00 0.00
Contractor's Profit 13.615% 196.33 290.29 Contractor's Profit 13.615% 166.84 250.03
Total rate per 10 Sqm 1638.30 2422.46 Total rate per 10 Sqm 1392.30 2086.48 335.98
21 Impervous coat with Plastering in CM(1:3) prop 12mm thick including cost&coveyance of all 21 Impervous coat with Plastering in CM(1:3) prop 12mm thick including cost&coveyance of all
materials lalbour charges,seign.charges etc.complete for wearing coat.above 3.0m height materials lalbour charges,seign.charges etc.complete for wearing coat.above 3.0m height
Rate up to 3.0m heighr 1638.30 Rate up to 3.0m heighr 1392.30
add lift charges 71.80 add lift charges 71.80
--- 0% 0.00 --- 0% 0.00
Page 58 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
22 Flooring with CM(1:3) prop 20 mm thick over bed of 100 mm thick,CC (1:4:8) prop 22 Flooring with CM(1:3) prop 20 mm thick over bed of 100 mm thick,CC (1:4:8) prop
using 40mm HG metal including cost and conveyance of all materials and seignorage using 40mm HG metal including cost and conveyance of all materials and seignorage
charges etc., complete. charges etc., complete.
1.00 Cum Cost of CC (1:4:8) prop. Rs. 4927.10 /1Cum 4927.10 1.00 Cum Cost of CC (1:4:8) pr Rs. 4656.59 /1Cum 4656.59
10 sqm Cost of CM(1:3) 20mm thick Rs. 2204.00 /10sqmt 2204.00 10 sqm Cost of CM(1:3) 20m Rs. 2038.40 /10sqmt 2038.40
Total rate per 10 sqm 7131.10 Total rate per 10 sqm 6694.99 436.11
23 Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm 23 Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm
thick and second coat in CM(1:3) prop 4mm thick including cost and conveyance thick and second coat in CM(1:3) prop 4mm thick including cost and conveyance
of all materials and labour charges etc., complete of all materials and labour charges etc., complete
1.108 0.11 cum Cost of CM(1:5) Prop 8mm Rs. 4028.98 /1Cum 443.19 0.11 cum Cost of CM(1:5) Pro Rs. 3601.31 /1Cum 396.14
0.998 0.04 cum Cost of CM(1:3) Prop 4mm Rs. 5219.38 /1Cum 208.78 0.04 cum Cost of CM(1:3) Pro Rs. 4525.46 /1Cum 181.02
0.63 nos. Mason 1st class @ Rs. 415.00 /each 261.45 0.63 nos. Mason 1st class @ Rs. 415.00 /each 261.45
1.47 nos. Mason 2nd class @ Rs. 370.00 /each 543.90 1.47 nos. Mason 2nd class @ Rs. 370.00 /each 543.90
3.9 nos. man and woman mazdoor @ Rs. 310.00 /each 1209.00 3.9 nos. man and woman ma Rs. 310.00 /each 1209.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 363.02 Contractor's Profit 13.615% 352.83
Total rate per 10 Sqm 3029.33 Total rate per 10 Sqm 2944.35 84.98
Above GL Above GL
0-3 m 0 3029.33 0-3 m 0 2944.35 84.98
3-6m 71.80 71.8 81.58 3110.91 3-6m 71.80 71.8 81.58 3025.93 84.98
6-9m 97.7 97.7 111.00 3208.61 6-9m 97.7 97.7 111.00 3123.63 84.98
24 Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm 24 Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm
thick and second coat in CM(1:3) prop 4mm thick including cost and conveyance thick and second coat in CM(1:3) prop 4mm thick including cost and conveyance
of all materials and labour charges etc., complete above 3.0m height of all materials and labour charges etc., complete above 3.0m height
Rate up to 3.0m height 3029.33 Rate up to 3.0m height 2944.35
Lift charges 1st Floor 71.80 Lift charges 1st Floor 71.80
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 9.78 Contractor's Profit 13.615% 9.78
Total rate per 10 Sqm 3110.90 Total rate per 10 Sqm 3025.90 85.00
10 Painting to new wood work with one primary coat including 10 Painting to new wood work with one primary coat including
cost and conveyance of all materials and labour charges etc. complete. cost and conveyance of all materials and labour charges etc. complete.
0.70 ltr wood primer Rs. 158.00 /1 ltr 110.60 0.70 ltr wood primer Rs. 122.66 /1 ltr 85.86
0.70 nos. painters Rs. 480.00 each 336.00 0.70 nos. painters Rs. 480.00 each 336.00
Sundries including
Sundries including brushes,
1% 4.47 1% brushes, soap, 4.22
soap, putty etc.,
putty etc.,
Painting to new wood work with synthetic enamel paint two coats over a primary coat including cost and Painting to new wood work with synthetic enamel paint two coats over a primary coat
25 25
conveyance of all materials and labour charges etc. complete. including cost and conveyance of all materials and labour charges etc. complete.
Page 59 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
1.00 10sqm cost of primary coat Rs. 451.10 /1 ltr 451.10 1.00 10sqm cost of primary coat Rs. 426.10 /1 ltr 426.10
2.80 litres cost of paint Rs. 276.00 /1 ltr 772.80 2.80 litres cost of paint Rs. 214.27 /1 ltr 599.95
1.20 nos. painters 1st class Rs. 480.00 each 576.00 1.20 nos. painters 1st class Rs. 480.00 each 576.00
Sundries including
1% Sundries including brushes, 13.49 1% 11.76
brushes, soap,
soap, putty etc.,
putty etc.,
26 White washing with white cement two coats including cost and conveyance of all materials 26 White washing with white cement two coats including cost and conveyance of all materials
and labour charges etc complete. and labour charges etc complete.
2.00 kg cost of white cement Rs. 29.00 /1kg 58.00 2.00 kg cost of white cement Rs. 22.51 /1kg 45.03
Gum, Conjee water or prickly pear juice including necessary firewood 0.58 Gum, Conjee water or prickly pear juice including necessary fir 0.45
0.21 nos. Painter 1st class @ Rs. 480.00 each 100.80 0.21 nos. Painter 1st class @ Rs. 480.00 each 100.80
0.32 nos. man and woman mazdoor Rs. 310.00 each 99.20 0.32 nos. man and woman maz Rs. 310.00 each 99.20
Sundries including
Sundries including brushes,
2.59 brushes, soap, 2.45
soap, putty etc.,
putty etc.,
26 Blue &bluff colour wash two coats to basement for 10 Sqm white wash with white cement 26 Blue &bluff colour wash two coats to basement for 10 Sqm white wash with white cement
296.70 281.70
Add 50% extra for colour 148.35 Add 50% extra for colour 140.85
0.01 0.01
Total Rs. 445.06 Total Rs. 422.56 22.50
6 Painting with Snowcem paint 2 coats over a primary coat including cost and conveyance of all materials and labour 6 Painting with Snowcem paint 2 coats over a primary coat including cost and conveyance of all materials
charges, etc., complete and labour charges, etc., complete
3.5 kg Snowcem @ Rs. 55.00 per kg 192.50 3.5 kg Snowcem @ Rs. 55.00 per kg 192.50
0.5 nos Painter 1st class @ Rs. 480 per each 240.00 0.5 nos Painter 1st class @ Rs. 480 per each 240.00
1.5 nos Mazdoor @ Rs. 310 per each 465.00 1.5 nos Mazdoor @ Rs. 310 per each 465.00
Sundries including brushes, etc., 8.98 Sundries including brushes, etc., 8.98
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 123.42 Contractor's Profit 13.615% 123.42
Per 10 Sqm Total Rs. 1029.90 Per 10 Sqm Total Rs. 1029.90
Cost of steel and Fabrication charges of steel including cutting bending and binding the steel with contractors binding Cost of steel and Fabrication charges of steel including cutting bending and binding the steel with
7 7
wire with placing in position for premeasurements etc complete contractors binding wire with placing in position for premeasurements etc complete
as per standard specification steel Steel beams as per standard specification steel Steel beams
1.05 MT Cost of steel 40000.00 42000.00 42000.00 1.05 MT Cost of steel 33863.87 35557.06 35557.06
6.00 Binding wire 70.00 kg 420.00 6.00 Binding wire 59.26 kg 355.57
Page 60 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Supply and placing of the Design Mix Concrete corresponding to IS 456 using WEIGH
Supply and placing of the Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER
BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse
8 with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry 8
aggregate) from approved quarry including cost and conveyance of all materials like cement,
including cost and conveyance of
FOUNDATIONS, all materials
PLINTH, like cement,
PEDESTALS for M-30 grade
(Below Plinth) FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)
for M-30 grade
0.8 cum 20mm HBG graded metal 2246.40 1 cum 1797.12 0.8 cum 20mm HBG graded m 2246.40 1 cum 1797.12
0.4 cum Sand 1933.51 1 cum 773.40 0.4 cum Sand 1913.41 1 cum 765.36
400 Kgs Cement 6200.00 1 Kgs 2480.00 400 Kgs Cement 4813.29 1 Kgs 1925.32
0.133 day 1st Class Mason 415.00 1 day 55.20 0.133 day 1st Class Mason 415.00 1 day 55.20
0.267 day 2nd Class Mason 370.00 1 day 98.79 0.267 day 2nd Class Mason 370.00 1 day 98.79
4.6 day Mazdoor (Both Men and Wom 310.00 1 day 1426.00 4.6 day Mazdoor (Both Men 310.00 1 day 1426.00
Weigh Batcher hire
1.333 hour Weigh Batcher hire charges 548.30 1 hour 730.88 1.333 hour 548.30 1 hour 730.88
charges
0 Liters Cost of Diesel for Miller 59.10 1 Liters 0.00 0 Liters Cost of Diesel for Mil 59.10 1 Liters 0.00
0 Liters Cost of Petrol for Vibrator 74.73 1 Liters 0.00 0 Liters Cost of Petrol for Vi 74.73 1 Liters 0.00
1.2 kl Water (including for curing) 77.00 1 kl 92.40 1.2 kl Water (including for 73.33 1 kl 88.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 1014.83 Contractor's Profit 13.615% 937.62
Total 8468.60 Total 7824.30
9 COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS 9 COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS
0.8 cum 20mm HBG graded metal 2246.40 1 day 1797.12 0.8 cum 20mm HBG graded m 2246.40 1 day 1797.12
0.4 cum Sand 1933.51 1 day 773.40 0.4 cum Sand 1913.41 1 day 765.36
400.0 Kgs Cement 6200.00 1 MT 2480.00 400.0 Kgs Cement 4813.29 1 MT 1925.32
0.167 day 1st Class Mason 415.00 1 day 69.31 0.167 day 1st Class Mason 415.00 1 day 69.31
0.167 day 2nd Class Mason 370.00 1 day 61.79 0.167 day 2nd Class Mason 370.00 1 day 61.79
5.6 day Mazdoor (Both Men and Wom 310.00 1 day 1736.00 5.6 day Mazdoor (Both Men 310.00 1 day 1736.00
Weigh Batcher hire
1.333 hour Weigh Batcher hire charges 548.30 1 day 730.88 1.333 hour 548.30 1 day 730.88
charges
1.2 kl Water (including for curing) 77.00 1 day 92.40 1.2 kl Water (including for 73.33 1 day 88.00
Page 61 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete excluding cost and M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
10 10
fabrication of steel for Raft , Side wall Shaft 'complete excluding cost and fabrication of steel for Raft , Side wall Shaft
1.00 Cum Cost of M 30 grade mix 8468.60 1 Sqm 8468.60 1.00 Cum Cost of M 30 grade m 7824.30 1 Sqm 7824.30
1.00 Cum Centering charges 750.00 1 Cum 750.00 1.00 Cum Centering charges 750.00 1 Cum 750.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 102.11 Contractor's Profit 13.615% 102.11
Sundies Sundies
Total 9320.70 Total 8676.40
Below GL Below GL
0-3 m 9320.70 0-3 m 8676.40 644.30
3-4m 41 46.58 9367.28 3-4m 41 46.58 8722.98 644.30
4-5m 41 46.58 9413.86 4-5m 41 46.58 8769.56 644.30
5-6m 41 46.58 9460.44 5-6m 41 46.58 8816.14 644.30
M30 using 20mm HBG metal including cost and conveyance of all material, labour charges,
M30 using 20mm HBG metal including cost and conveyance of all material, labour charges, centering etc.,
36 36 centering etc., complete but excluding cost of steel and its fabrication charges for Haunch
complete but excluding cost of steel and its fabrication charges for Haunch portion
portion
1.00 Cum Cost of M 30 grade mix 8468.60 1 Sqm 8468.60 1.00 Cum Cost of M 30 grade m 7824.30 1 Sqm 7824.30
1.00 Cum Centering charges 750.00 1 Cum 750.00 1.00 Cum Centering charges 750.00 1 Cum 750.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 102.11 Contractor's Profit 13.615% 102.11
M30using 20mm HBG metal including cost and conveyance of all material, labour charges, centering etc., M30using 20mm HBG metal including cost and conveyance of all material, labour charges,
37 37
complete but excluding cost of steel and its fabrication charges for side wall of centering etc., complete but excluding cost of steel and its fabrication charges for side wall of
Page 62 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Intake well 1200 mm thick Circular Intake well 1200 mm thick Circular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
0.83 Sqm Centering charges 1115.00 1 Sqm 929.17 0.83 Sqm Centering charges 1115.00 1 Sqm 929.17
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 126.51 Contractor's Profit 13.615% 126.51
Total 9850.50 Total 9206.20 644.30
Below GL Circular Below GL Circular
0-3 m 9850.50 0-3 m 9206.20 644.30
3-4m 41 46.58 9897.08 3-4m 41 46.58 9252.78 644.30
4-5m 41 46.58 9943.66 4-5m 41 46.58 9299.36 644.30
5-6m 41 46.58 9990.24 5-6m 41 46.58 9345.94 644.30
SUMP, OHBR 300 mm thick Circular SUMP, OHBR 300 mm thick Circular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
3.33 Sqm Centering charges 1115.00 1 Sqm 3716.67 3.33 Sqm Centering charges 1115.00 1 Sqm 3716.67
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 506.02 Contractor's Profit 13.615% 506.02
Total 13017.50 Total 12373.20 644.30
Below GL Circular Below GL Circular
0-3 m 13017.50 0-3 m 12373.20 644.30
3-4m 41 46.58 13064.08 3-4m 41 46.58 12419.78 644.30
4-5m 41 46.58 13110.66 4-5m 41 46.58 12466.36 644.30
5-6m 41 46.58 13157.24 5-6m 41 46.58 12512.94 644.30
11
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete excluding 11
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete
cost and fabrication of steel for excluding cost and fabrication of steel for
SUMP, OHBR 400 mm thick Circular SUMP, OHBR 400 mm thick Circular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
2.50 Sqm Centering charges 1115.00 1 Sqm 2787.50 2.50 Sqm Centering charges 1115.00 1 Sqm 2787.50
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 379.52 Contractor's Profit 13.615% 379.52
Total 11961.80 Total 11317.50 644.30
Below GL Circular Below GL Circular
0-3 m 11961.80 0-3 m 11317.50 644.30
3-4m 41 46.58 12008.38 3-4m 41 46.58 11364.08 644.30
4-5m 41 46.58 12054.96 4-5m 41 46.58 11410.66 644.30
5-6m 41 46.58 12101.54 5-6m 41 46.58 11457.24 644.30
SUMP, OHBR 500 mm thick Circular SUMP, OHBR 500 mm thick Circular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
2.00 Sqm Centering charges 1115.00 1 Sqm 2230.00 2.00 Sqm Centering charges 1115.00 1 Sqm 2230.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 303.61 Contractor's Profit 13.615% 303.61
Total 11328.40 Total 10684.10 644.30
Below GL Circular Below GL Circular
0-3 m 11328.40 0-3 m 10684.10 644.30
3-4m 41 46.58 11374.98 3-4m 41 46.58 10730.68 644.30
4-5m 41 46.58 11421.56 4-5m 41 46.58 10777.26 644.30
5-6m 41 46.58 11468.14 5-6m 41 46.58 10823.84 644.30
Page 63 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
42 Sump, GLBR 450 mm thick Rectangular 42 Sump, GLB 450 mm thick Rectangular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
2.22 Sqm Centering charges 876.00 1 Sqm 1946.67 2.22 Sqm Centering charges 876.00 1 Sqm 1946.67
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 265.04 Contractor's Profit 13.615% 265.04
Total 11006.50 Total 10362.20 644.30
43 Sump, GLBR 400 mm thick Rectangular 43 Sump, GLB 400 mm thick Rectangular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
2.50 Sqm Centering charges 876.00 1 Sqm 2190.00 2.50 Sqm Centering charges 876.00 1 Sqm 2190.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 298.17 Contractor's Profit 13.615% 298.17
Total 11283.00 Total 10638.70 644.30
44 Sump, GLBR 300 mm thick Rectangular 44 Sump, GLB 300 mm thick Rectangular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
3.33 Sqm Centering charges 876.00 1 Sqm 2920.00 3.33 Sqm Centering charges 876.00 1 Sqm 2920.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 397.56 Contractor's Profit 13.615% 397.56
Total 12112.40 Total 11468.10 644.30
45 Sump, GLBR 200 mm thick Rectangular 45 Sump, GLB 200 mm thick Rectangular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
5.00 Sqm Centering charges 876.00 1 Sqm 4380.00 5.00 Sqm Centering charges 876.00 1 Sqm 4380.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 596.34 Contractor's Profit 13.615% 596.34
Total 13771.10 Total 13126.80 644.30
Below GL Below GL
0-3 m 13771.10 0-3 m 13126.80 644.30
3-4m 41 46.58 13817.68 3-4m 41 46.58 13173.38 644.30
Above GL Above GL
0-3 m 13771.10 0-3 m 13126.80 644.30
3-4m 134 152.24 13923.34 3-4m 134 152.24 13279.04 644.30
M30using 20mm HBG metal including cost and conveyance of all material, labour charges, centering etc., M30using 20mm HBG metal including cost and conveyance of all material, labour charges,
46 46
complete but excluding cost of steel and its fabrication charges for side wall of centering etc., complete but excluding cost of steel and its fabrication charges for side wall of
PH 450 mm thick Rectangular PH 450 mm thick Rectangular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
2.22 Sqm Centering charges 876.00 1 Sqm 1946.67 2.22 Sqm Centering charges 876.00 1 Sqm 1946.67
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 265.04 Contractor's Profit 13.615% 265.04
Total 11006.50 Total 10362.20 644.30
Below GL Below GL
0-3 m 11006.50 0-3 m 10362.20 644.30
3-4m 41 46.58 11053.08 3-4m 41 46.58 10408.78 644.30
4-5m 41 46.58 11099.66 4-5m 41 46.58 10455.36 644.30
5-6m 41 46.58 11146.24 5-6m 41 46.58 10501.94 644.30
Page 64 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
2.50 Sqm Centering charges 876.00 1 Sqm 2190.00 2.50 Sqm Centering charges 876.00 1 Sqm 2190.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 298.17 Contractor's Profit 13.615% 298.17
Total 11283.00 Total 10638.70 644.30
48 Sump 300 mm thick Rectangular 48 Sump 300 mm thick Rectangular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
3.33 Sqm Centering charges 876.00 1 Sqm 2920.00 3.33 Sqm Centering charges 876.00 1 Sqm 2920.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 397.56 Contractor's Profit 13.615% 397.56
Total 12112.40 Total 11468.10 644.30
49 Sump 200 mm thick Rectangular 49 Sump 200 mm thick Rectangular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
5.00 Sqm Centering charges 876.00 1 Sqm 4380.00 5.00 Sqm Centering charges 876.00 1 Sqm 4380.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 596.34 Contractor's Profit 13.615% 596.34
Total 13771.14 Total 13126.84 644.30
49 Sump 250 mm thick Rectangular 49 Sump 250 mm thick Rectangular
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
4.00 Sqm Centering charges 876.00 1 Sqm 3504.00 4.00 Sqm Centering charges 876.00 1 Sqm 3504.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 477.07 Contractor's Profit 13.615% 477.07
Total 12775.87 Total 12131.57 644.30
M30 using 20mm HBG metal including cost and conveyance of all material, labour charges, centering etc., M30 using 20mm HBG metal including cost and conveyance of all material, labour charges,
50 50
complete but excluding cost of steel and its fabrication charges for Columns centering etc., complete but excluding cost of steel and its fabrication charges for Columns
I.W/
I.W/ Sump/PH mm or any size mm or any size
Sump/PH
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
1.00 Cum Centering charges 1 Sqm 0.00 1.00 Cum Centering charges 1 Sqm 0.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 0.00 Contractor's Profit 13.615% 0.00
Total 8794.80 Total 8150.50 644.30
Below GL Centring Charges Below GL Centring Charges
0-3 m 0 2041 2318.88 11113.68 0-3 m 0 2041 2318.88 10469.38 644.30
3-4m 41 46.58 11160.26 3-4m 41 46.58 10515.96 644.30
4-5m 41 46.58 11206.85 4-5m 41 46.58 10562.55 644.30
5-6m 41 46.58 11253.43 5-6m 41 46.58 10609.13 644.30
M 30 using 20mm HBG metal including cost and conveyance of all material, labour charges, centering etc., M 30 using 20mm HBG metal including cost and conveyance of all material, labour charges,
51 51
complete but excluding cost of steel and its fabrication charges for beam centering etc., complete but excluding cost of steel and its fabrication charges for beam
Beam Beam
Page 65 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
1.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 7206.30 1.00 Cum Cost of M 30 grade m 6561.90 1 Cum 6561.90
1.00 Cum Centering charges 1 Cum 0.00 1.00 Cum Centering charges 1 Cum 0.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 0.00 Contractor's Profit 13.615% 0.00
Total 7206.30 Total 6561.90 644.40
Below GL Below GL
0-3 m 0 3428 3894.72 11101.02 0-3 m 0 3428 3894.72 10456.62 644.40
3-4m 41 46.58 11147.60 3-4m 41 46.58 10503.20 644.40
4-5m 41 46.58 11194.19 4-5m 41 46.58 10549.79 644.40
5-6m 41 46.58 11240.77 5-6m 41 46.58 10596.37 644.40
Above GL Above GL
0-3 m 0 3428 3894.72 11101.02 0-3 m 0 3428 3894.72 10456.62 644.40
3-4m 134 152.24 11253.27 3-4m 134 152.24 10608.87 644.40
4-5m 134 152.24 11405.51 4-5m 134 152.24 10761.11 644.40
5-6m 134 152.24 11557.75 5-6m 134 152.24 10913.35 644.40
M 30 using 20mm HBG metal including cost and conveyance of all material, labour charges, M 30 using 20mm HBG metal including cost and conveyance of all material, labour
52 centering etc., complete but excluding cost of steel and its fabrication charges for pump 52 charges, centering etc., complete but excluding cost of steel and its fabrication
house Floor/Top slab charges for pump house Floor/Top slab
IW 300 mm thick 4 to 5 m IW 300 mm thick 4 to 5 m
1.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 7206.30 1.00 Cum Cost of M 30 grade m 6561.90 1 Cum 6561.90
3.33 Sqm Centering charges 399.00 1 Sqm 1330.00 3.33 Sqm Centering charges 399.00 1 Sqm 1330.00
2.00 4-5m Add lifting charges 134.00 1 Cum 268.00 2.00 4-5m Add lifting charges 134.00 1 Cum 268.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 217.57 Contractor's Profit 13.615% 217.57
Total 1 Cum 9021.90 Total 1 Cum 8377.50 644.40
1.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 7206.30 1.00 Cum Cost of M 30 grade m 6561.90 1 Cum 6561.90
6.67 Sqm Centering charges 389.00 1 Sqm 2593.33 6.67 Sqm Centering charges 389.00 1 Sqm 2593.33
0.00 Add lifting charges 134.00 1 Cum 0.00 0.00 Add lifting charges 134.00 1 Cum 0.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 353.08 Contractor's Profit 13.615% 353.08
Total 1 Cum 10152.70 Total 1 Cum 9508.30 644.40
1.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 7206.30 1.00 Cum Cost of M 30 grade m 6561.90 1 Cum 6561.90
6.67 Sqm Centering charges 389.00 1 Sqm 2593.33 6.67 Sqm Centering charges 389.00 1 Sqm 2593.33
2.00 Add lifting charges 134.00 1 Cum 268.00 2.00 Add lifting charges 134.00 1 Cum 268.00
Page 66 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
1.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 7206.30 1.00 Cum Cost of M 30 grade m 6561.90 1 Cum 6561.90
5.00 Sqm Centering charges 399.00 1 Sqm 1995.00 5.00 Sqm Centering charges 399.00 1 Sqm 1995.00
2.00 Add lifting charges 134.00 1 Cum 268.00 2.00 Add lifting charges 134.00 1 Cum 268.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 308.11 Contractor's Profit 13.615% 308.11
Total 1 Cum 9777.40 Total 1 Cum 9133.00 644.40
59 Bailing out water from well with oil engine driven and wages of driver and helper etc., 59 Bailing out water from well with oil engine driven and wages of driver and helper
complete as per standard specification etc., complete as per standard specification
Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material,
37 charges, centering etc., complete but excluding cost of steel and its fabrication charges for side wall of 872 labour charges, centering etc., complete but excluding cost of steel and its fabrication charges
(Circular) for side wall of (Circular)
Sump 150 mm thick Sump 150 mm thick
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
6.67 Sqm Centering charges 1115.00 1 Sqm 7433.33 6.67 Sqm Centering charges 1115.00 1 Sqm 7433.33
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 1012.05 Contractor's Profit 13.615% 1012.05
Total 17240.20 Total 16595.90 644.30
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
charges, centering etc., complete but excluding cost of steel and its fabrication charges for side
centering etc., complete but excluding cost of steel and its fabrication charges for side wall of (Circular)
wall of (Circular)
Sump-Flat 150 mm thick Sump-Flat 150 mm thick
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
6.67 Sqm Centering charges 1115.00 1 Sqm 7433.33 6.67 Sqm Centering charges 1115.00 1 Sqm 7433.33
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 1012.05 Contractor's Profit 13.615% 1012.05
Total 17240.20 Total 16595.90 644.30
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all
charges, centering etc., complete but excluding cost of steel and its fabrication charges for material, labour charges, centering etc., complete but excluding cost of steel and
Sump top slab its fabrication charges for Sump top slab
150 mm thick Sump-Flat 150 mm thick Sump-Flat
1.50 Cum Cost of M 30 grade mix 7206.30 1 Cum 10809.45 1.50 Cum Cost of M 30 grade m 6561.90 1 Cum 9842.85
6.67 Sqm Centering charges 389.00 1 Sqm 2593.33 6.67 Sqm Centering charges 389.00 1 Sqm 2593.33
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 353.08 Contractor's Profit 13.615% 353.08
Total 10sqmt 13755.90 Total 10sqmt 12789.30 966.60
Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material,
charges, centering etc., complete but excluding cost of steel and its fabrication charges for side wall of labour charges, centering etc., complete but excluding cost of steel and its fabrication charges
(Circular) for side wall of (Circular)
GLBR Side Wall 200 mm thick GLBRSide Wall 200 mm thick
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
5.00 Sqm Centering charges 1115.00 1 Sqm 5575.00 5.00 Sqm Centering charges 1115.00 1 Sqm 5575.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 759.04 Contractor's Profit 13.615% 759.04
Total 15128.80 Total 14484.50 644.30
Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material,
Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour
60 60 labour charges, centering etc., complete but excluding cost of steel and its fabrication charges
charges, centering etc., complete but excluding cost of steel and its fabrication charges for top dome
for top dome
GLBR-Doome 150 mm thick GLBR-Doome 150 mm thick
Page 68 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
1.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 7206.30 1.00 Cum Cost of M 30 grade m 6561.90 1 Cum 6561.90
1.00 cum Centering charges (as per bldg 6302.00 1 cum 6302.00 1.00 cum Centering charges (as 6302.00 1 cum 6302.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 858.02 Contractor's Profit 13.615% 858.02
Total 14366.30 Total 13721.90 644.40
Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material,
charges, centering etc., complete but excluding cost of steel and its fabrication charges for top ring beam labour charges, centering etc., complete but excluding cost of steel and its fabrication charges
of for top ring beam of
Ring Beam Ring Beam
1.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 7206.30 1.00 Cum Cost of M 30 grade m 6561.90 1 Cum 6561.90
1.00 Cum Centering charges 3428.00 1 Cum 3428.00 1.00 Cum Centering charges 3428.00 1 Cum 3428.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 466.72 Contractor's Profit 13.615% 466.72
Total 11101.00 Total 10456.60 644.40
Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour Cost of M 30 grade mix using 20mm HBG metal including cost and conveyance of all material,
charges, centering etc., complete but excluding cost of steel and its fabrication charges for side wall of labour charges, centering etc., complete but excluding cost of steel and its fabrication charges
(Circular) for side wall of (Circular)
GLBR-Flat 150 mm thick GLBR-Flat 150 mm thick
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
6.67 Sqm Centering charges 1115.00 1 Sqm 7433.33 6.67 Sqm Centering charges 1115.00 1 Sqm 7433.33
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 1012.05 Contractor's Profit 13.615% 1012.05
Total 17240.18 Total 16595.88 644.30
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all
charges, centering etc., complete but excluding cost of steel and its fabrication charges for material, labour charges, centering etc., complete but excluding cost of steel and
GLBR top slab its fabrication charges for GLBR top slab
150 mm thick GLBR-Flat 150 mm thick GLBR-Flat
1.50 Cum Cost of M 30 grade mix 7206.30 1 Cum 10809.45 1.50 Cum Cost of M 30 grade m 6561.90 1 Cum 9842.85
6.67 Sqm Centering charges 389.00 1 Sqm 2593.33 6.67 Sqm Centering charges 389.00 1 Sqm 2593.33
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 353.08 Contractor's Profit 13.615% 353.08
Total 10sqmt 13755.87 Total 10sqmt 12789.27 966.60
Intake-Canal 1000 mm thick- Side Wall Canal Intake-Cana #REF! mm thick- Side Wall Canal
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
1.00 Sqm Centering charges 1115.00 1 Sqm 1115.00 1.00 Sqm Centering charges 1115.00 1 Sqm 1115.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 303.61 Contractor's Profit 13.615% 303.61
Total 10213.41 Total 9569.11 644.30
Page 69 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Ph.Side Wall 200 mm thick Canal Ph.Side Wal 200 mm thick Canal
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
5.00 Sqm Centering charges 1115.00 1 Sqm 5575.00 5.00 Sqm Centering charges 1115.00 1 Sqm 5575.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 759.04 Contractor's Profit 13.615% 759.04
Total 15128.80 Total 14484.50 644.30
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all
initial lift initial lift
62 charges, centering etc., complete but excluding cost of steel and its fabrication charges for ### material, labour charges, centering etc., complete but excluding cost of steel and
3mts 3mts
collection well Floor Slab its fabrication charges for collection well Floor Slab
300 mm thick Canal 300 mm thick Canal
3.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 21618.90 3.00 Cum Cost of M 30 grade m 6561.90 1 Cum 19685.70
3.33 Sqm Centering charges 399.00 1 Sqm 1330.00 3.33 Sqm Centering charges 399.00 1 Sqm 1330.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 181.08 Contractor's Profit 13.615% 181.08
Total 10sqmt 23130.00 Total 10sqmt 21196.80 1933.20
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges, VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour
centering etc., complete but excluding cost of steel and its fabrication charges for ring beam -Gfloor Level charges, centering etc., complete but excluding cost of steel and its fabrication charges for ring
Works beam -Gfloor Level Works
1.00 Cum Cost of M 30 grade mix 7206.30 1 Cum 7206.30 1.00 Cum Cost of M 30 grade m 6561.90 1 Cum 6561.90
1.00 Cum Centering charges 3428.00 1 Cum 3428.00 1.00 Cum Centering charges 3428.00 1 Cum 3428.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 466.72 Contractor's Profit 13.615% 466.72
Total 11101.00 Total 10456.60 644.40
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all
63 charges, centering etc., complete but excluding cost of steel and its fabrication charges for ### material, labour charges, centering etc., complete but excluding cost of steel and
pump house top slab its fabrication charges for pump house top slab
200 mm thick Canal 200 mm thick Canal
2.00 Cum Cost of CC (1:1.5:3) 7279.00 1 Cum 14558.00 2.00 Cum Cost of CC (1:1.5:3) 6633.50 1 Cum 13267.00
5.00 Sqm Centering charges 399.00 1 Sqm 1995.00 5.00 Sqm Centering charges 399.00 1 Sqm 1995.00
1.00 Add lifting charges 134.00 1 Cum 134.00 1.00 Add lifting charges 134.00 1 Cum 134.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 289.86 Contractor's Profit 13.615% 289.86
Total 10sqmt 16976.90 Total 10sqmt 15685.90 1291.00
Page 70 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Ph.Side Wall 100 mm thick SSTank Ph.Side Wal 100 mm thick SSTank
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
10.00 Sqm Centering charges 1115.00 1 Sqm 11150.00 10.00 Sqm Centering charges 1115.00 1 Sqm 11150.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 3036.15 Contractor's Profit 13.615% 3036.15
Total 22980.90 Total 22336.60 644.30
M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour M 30 grade mix using 20mm HBG metal including cost and conveyance of all
charges, centering etc., complete but excluding cost of steel and its fabrication charges for material, labour charges, centering etc., complete but excluding cost of steel and
collection wellFloor Slab its fabrication charges for collection wellFloor Slab
200 mm thick Canal 200 mm thick Canal
2.00 Cum Cost of M 30 grade mix 7279.00 1 Cum 14558.00 2.00 Cum Cost of M 30 grade m 6633.50 1 Cum 13267.00
5.00 Sqm Centering charges 399.00 1 Sqm 1995.00 5.00 Sqm Centering charges 399.00 1 Sqm 1995.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 271.62 Contractor's Profit 13.615% 271.62
Total 10sqmt 16824.60 Total 10sqmt 15533.60 1291.00
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all
charges, centering etc., complete but excluding cost of steel and its fabrication charges for material, labour charges, centering etc., complete but excluding cost of steel and
pump house top slab200 mm thick Canal its fabrication charges
200 mmfor pump house top slab
thick Canal
2.00 Cum Cost of M 30 grade mix 7279.00 1 Cum 14558.00 2.00 Cum Cost of M 30 grade m 6633.50 1 Cum 13267.00
5.00 Sqm Centering charges 399.00 1 Sqm 1995.00 5.00 Sqm Centering charges 399.00 1 Sqm 1995.00
1.00 Add lifting charges 134.00 1 Cum 134.00 1.00 Add lifting charges 134.00 1 Cum 134.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 289.86 Contractor's Profit 13.615% 289.86
Total 10sqmt 16976.90 Total 10sqmt 15685.90 1291.00
M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour charges, M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour
62 centering etc., complete but excluding cost of steel and its fabrication charges for ring beam -Gfloor Level ### charges, centering etc., complete but excluding cost of steel and its fabrication charges for ring
Works
Sump 0.30 0.25 beam
Sump-Gfloor Level Works 0.30 0.25
1.00 Cum Cost of M 30 grade mix 8468.60 1 Cum 8468.60 1.00 Cum Cost of M 30 grade m 7824.30 1 Cum 7824.30
1.00 Cum Centering charges 3999.31 1 Cum 3999.31 1.00 Cum Centering charges 3999.31 1 Cum 3999.31
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 544.51 Contractor's Profit 13.615% 544.51
Total 13012.42 Total 12368.12 644.30
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Phenail columns M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
12 12
on Top Dome excluding cost and fabrication of steel 'complete for Phenail columns on Top Dome excluding cost and fabrication of steel
mm thick mm thick
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
1.00 Cum Centering charges 2041.00 1 Cum 2041.00 1.00 Cum Centering charges 2041.00 1 Cum 2041.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 277.88 Contractor's Profit 13.615% 277.88
M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour
M 30 grade mix using 20mm HBG metal including cost and conveyance of all material, labour charges,
charges, centering etc., complete but excluding cost of steel and its fabrication charges for side
centering etc., complete but excluding cost of steel and its fabrication charges for side wall of (St)
wall of (St)
Sump 200 mm thick Sump 200 mm thick
1.00 Cum Cost of M 30 grade mix 8794.80 1 Cum 8794.80 1.00 Cum Cost of M 30 grade m 8150.50 1 Cum 8150.50
5.00 Sqm Centering charges 876.00 1 Sqm 4380.00 5.00 Sqm Centering charges 876.00 1 Sqm 4380.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 596.34 Contractor's Profit 13.615% 596.34
Total 13771.14 Total 13126.84 644.30
Page 72 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
13
Acco proof Plastering with CM (1:3) 12mm thick including cost and conveyance of all material, labour charges 13
Acco proof Plastering with CM (1:3) 12mm thick including cost and conveyance of all
etc., complete material, labour charges etc., complete
0.15 Cum Cost of CM(1:3) 5219.38 1 Cum 782.91 0.15 Cum Cost of CM(1:3) 4525.46 1 Cum 678.82
0.60 Nos. Mason 415.00 Each 249.00 0.60 Nos. Mason 415.00 Each 249.00
0.96 Nos. Man Mazdoor 310.00 Each 297.60 0.96 Nos. Man Mazdoor 310.00 Each 297.60
1.50 Kg Acco proof powder 75.00 1 Kg 112.50 1.50 Kg Acco proof powder 58.23 1 Kg 87.34
--- 0% 0.00 7.2 --- 0% 0.00
Contractor's Profit 13.615% 196.33 Contractor's Profit 13.615% 178.73
66 Plastering with CM (1:3) 12mm thick including cost and conveyance of all material, labour charges etc., ### Plastering with CM (1:3) 12mm thick including cost and conveyance of all material, labour
complete charges etc., complete
0.15 Cum Cost of CM(1:3) 5219.38 1 Cum 782.91 0.15 Cum Cost of CM(1:3) 4525.46 1 Cum 678.82
0.60 Nos. Mason 415.00 Each 249.00 0.60 Nos. Mason 415.00 Each 249.00
0.96 Nos. Man Mazdoor 310.00 Each 297.60 0.96 Nos. Man Mazdoor 310.00 Each 297.60
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 181.01 Contractor's Profit 13.615% 166.84
14 Epoxy protective coating with procoat SNF (item 279 SSR) paint 3 coat over water proof plastering. 14 Epoxy protective coating with procoat SNF (item 279 SSR) paint 3 coat over water proof
including conveyance of all m/labour charges etc…, complete plastering .including conveyance of all m/labour charges etc…, complete
3.50 Kg Epoxy protective coating, procoat SNF 633 2215.50 3.50 Kg Epoxy protective coating, procoat 491.42 1719.98
0.50 Nos Painters 480.00 240.00 0.50 Nos Painters 480.00 240.00
0.50 Nos Man Mazdoor 310 155.00 0.50 Nos Man Mazdoor 310.00 155.00
1.00 Nos Woman mazdoor 310 310.00 1.00 Nos Woman mazdoor 310.00 310.00
0% 0.00 0% 0.00
Contractor's Profit 13.615% 397.63 Contractor's Profit 13.615% 330.16
Cost for 1 sqm 3318.13 Cost for 1 sqm 2755.14
Rate per sqm 331.81 Rate per sqm 275.51
Valve Chambers Valve Chambers
Cement concrete (1:4:8)prop using 40 mm gauge HG metal including cost &conveyance of all materials Cement concrete (1:4:8)prop using 40 mm gauge HG metal including cost &conveyance of all
61 61
and labour charges ,seigniorage charges etc complete Hand Mixing materials and labour charges ,seigniorage charges etc complete Hand Mixing
162.00 Kgs Cost of Cement 6200.00 1 MT 1004.40 162.00 Kgs Cost of Cement 4813.29 1 MT 779.75
0.90 cum Intial rate of 40mm metal @ 1726.40 /cum 1553.76 0.90 cum Intial rate of 40mm 1726.40 /cum 1553.76
0.45 cum Cost of Sand 1933.51 /cum 870.08 0.45 cum Cost of Sand 1913.41 /cum 861.04
1.20 Kl Water 77.00 Kl 92.40 1.20 Kl Water 73.33 Kl 88.00
0.10 Kl Masons 1st class@ 415.00 /each 41.50 0.10 Kl Masons 1st class@ 415.00 /each 41.50
2.36 No Mazdoor 310.00 /each 731.60 2.36 No Mazdoor 310.00 /each 731.60
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 584.59 Contractor's Profit 13.615% 552.18
Total Rs. 4878.33 Total Rs. 4607.82 270.51
Page 73 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
charges, centering etc., complete but excluding cost of steel and its fabrication charges for side
centering etc., complete but excluding cost of steel and its fabrication charges for side wall of (Circular)
wall of (Circular)
Chambers 150 mm thick Chambers 150 mm thick
1.00 Cum Cost of CC (1:1.5:3) 8397.60 1 Cum 8397.60 1.00 Cum Cost of CC (1:1.5:3) 7752.10 1 Cum 7752.10
6.67 Sqm Centering charges 1115.00 1 Sqm 7433.33 6.67 Sqm Centering charges 1115.00 1 Sqm 7433.33
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 2024.10 Contractor's Profit 13.615% 2024.10
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
64 64 charges, centering etc., complete but excluding cost of steel and its fabrication charges for slab
centering etc., complete but excluding cost of steel and its fabrication charges for slab of Chambers
of Chambers
100 mm thick 100 mm thick
1.00 Cum Cost of VRCC (1:1.5:3) 7279.00 1 Cum 7279.00 1.00 Cum Cost of VRCC (1:1.5:3 6633.50 1 Cum 6633.50
10.00 Sqm Centering charges 399.00 1 Sqm 3990.00 10.00 Sqm Centering charges 399.00 1 Sqm 3990.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 543.24 Contractor's Profit 13.615% 543.24
Sundies Sundies
Total 11812.24 Total 11166.74 645.50
200 mm thick 200 mm thick
1.00 Cum Cost of VRCC (1:1.5:3) 7279.00 1 Cum 7279.00 1.00 Cum Cost of VRCC (1:1.5:3 6633.50 1 Cum 6633.50
5.00 Sqm Centering charges 399.00 1 Sqm 1995.00 5.00 Sqm Centering charges 399.00 1 Sqm 1995.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 271.62 Contractor's Profit 13.615% 271.62
Sundies Sundies
Page 74 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank bottom VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
slab dome at 30 m height Tank bottom slab dome at 30 m height
0.15 0.15
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
6.667 Sqm cetering charges 2670.00 17800.00 6.667 Sqm cetering charges 2670.00 17800.00
9.00 Lift charges 134 1206 9.00 Lift charges 134.00 1206
extra allowance on centring ch 30% 5340.00 extra allowance on c 30% 5340.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 3314.71 Contractor's Profit 13.615% 3314.71
Total 34867.01 Total 34222.61 644.40
15
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for 15
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
Bottom Dome excluding cost and fabrication of steel 'complete for Bottom Dome excluding cost and fabrication of steel
0.2 0.2
1 Cum Intial Rate 7206.30 7206.30 1 Cum Intial Rate 6561.90 6561.90
5.000 Sqm cetering charges 2670.00 13350.00 5.000 Sqm cetering charges 2670.00 13350.00
9.00 Lift charges 134 1206 9.00 Lift charges 134 1206
extra allowance on centring ch 30% 4005.00 extra allowance on c 30% 4005.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 2527.08 Contractor's Profit 13.615% 2527.08
Total 28294.38 Total 27649.98
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank bottom VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
slab dome at 30 m height Tank bottom slab dome at 30 m height
0.3 0.3
Page 75 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank bottom VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
slab dome at 25 m height Tank bottom slab dome at 25 m height
0.3 0.3
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
3.333 Sqm cetering charges 2670.00 8900.00 3.333 Sqm cetering charges 2670.00 8900.00
22.00 Lift charges 134 2948 22.00 Lift charges 134.00 2948
extra allowance on centring ch 27% 2403.00 extra allowance on c 27% 2403.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 1940.27 Contractor's Profit 13.615% 1940.27
Total 23397.57 Total 22753.17 644.40
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank Top VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
slab DOME at 33.00 Mts Tank Top slab DOME at 33.00 Mts
0.15 0.15
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
6.667 Sqm cetering charges 2670.00 17800.00 6.667 Sqm cetering charges 2670.00 17800.00
12.00 Lift charges 134 1608 12.00 Lift charges 134.00 1608
extra allowance on centring ch 30% 5340.00 extra allowance on c 30% 5340.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 3369.44 Contractor's Profit 13.615% 3369.44
Total 35323.74 Total 34679.34 644.40
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank Top VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
slab DOME at 36.00 Mts Tank Top slab DOME at 36.00 Mts
0.15 0.15
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
6.667 Sqm cetering charges 2670.00 17800.00 6.667 Sqm cetering charges 2670.00 17800.00
33.00 Lift charges 134 4422 33.00 Lift charges 134.00 4422
extra allowance on centring ch 30% 5340.00 extra allowance on c 30% 5340.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 3752.57 Contractor's Profit 13.615% 3752.57
Page 76 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
16
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Ring 16 M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
beam excluding cost and fabrication of steel 'complete for Ring beam excluding cost and fabrication of steel
30 m height 0.60 0.75 30 m height 0.60 0.75
1 Cum Intial Rate 7206.30 7206.30 1 Cum Intial Rate 6561.90 6561.90
4.33 Sqm centering charges 1206.00 1 Sq mt 5226.00 4.33 Sqm centering charges 1206.00 1 Sq mt 5226.00
9.00 Lift charges 134.00 1206.00 9.00 Lift charges 134.00 1206.00
17
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Ring 17
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
beam excluding cost and fabrication of steel 'complete for Ring beam excluding cost and fabrication of steel
33 m height 0.65 0.45 33 m height 0.65 0.45
1 Cum Intial Rate 7206.30 7206.30 1 Cum Intial Rate 6561.90
5.98 Sqm centering charges 1206.00 1 Sq mt 7215.38 5.98 Sqm centering charges 1206.00 1 Sq mt 7215.38
10.00 Lift charges 134.00 1340.00 10.00 Lift charges 134.00 1340.00
18
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Ring 18
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
beam excluding cost and fabrication of steel 'complete for Ring beam excluding cost and fabrication of steel
36 m height 0.20 0.20 36 m height 0.20 0.20
Page 77 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
1 Cum Intial Rate 7206.30 7206.30 1 Cum Intial Rate 6561.90 6561.90
15.00 Sqm centering charges 1206.00 1 Sq mt 18090.00 15.00 Sqm centering charges 1206.00 1 Sq mt 18090.00
11.00 Lift charges 134.00 1474.00 11.00 Lift charges 134.00 1474.00
19
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Ring 19 M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
beam excluding cost and fabrication of steel 'complete for Ring beam excluding cost and fabrication of steel
33 m height 0.23 0.23 33 m height 0.23 0.23
1 Cum Intial Rate 7206.30 7206.30 1 Cum Intial Rate 6561.90 6561.90
13.04 Sqm centering charges 1206.00 1 Sq mt 15730.43 13.04 Sqm centering charges 1206.00 1 Sq mt 15730.43
10.00 Lift charges 134.00 1340.00 10.00 Lift charges 134.00 1340.00
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank Ring VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
beam at 30.00 Mts Tank Ring beam at 30.00 Mts
30 m height 0.40 0.50 30 m height 0.40 0.50
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
6.50 Sqm centering charges 1206.00 1 Sq mt 7839.00 6.50 Sqm centering charges 1206.00 1 Sq mt 7839.00
9.00 Lift charges 134 1206.00 9.00 Lift charges 134.00 1206.00
20
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Top 20 M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
Ring Beam excluding cost and fabrication of steel 'complete for Top Ring Beam excluding cost and fabrication of steel
36 m height 0.45 0.45 36 m height 0.45 0.45
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
6.67 Sqm centering charges 1206.00 1 Sq mt 8040.00 6.67 Sqm centering charges 1206.00 1 Sq mt 8040.00
11.00 Lift charges 134 1474.00 11.00 Lift charges 134.00 1474.00
Page 78 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank Ring VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
beam at 30.00 Mts Tank Ring beam at 30.00 Mts
30 m height 0.45 0.50 30 m height 0.45 0.50
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
6.22 Sqm centering charges 1206.00 1 Sq mt 7504.00 6.22 Sqm centering charges 1206.00 1 Sq mt 7504.00
9.00 Lift charges 96.1 864.90 9.00 Lift charges 96.10 864.90
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank Ring VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
beam at 32.00 Mts Tank Ring beam at 32.00 Mts
32.00 Mt 0.35 0.30 32.00 Mt 0.35 0.30
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
9.52 Sqm centering charges 1206.00 1 Sq mt 11485.71 9.52 Sqm centering charges 1206.00 1 Sq mt 11485.71
9.00 Lift charges 134 1206.00 9.00 Lift charges 134.00 1206.00
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for inner shaft VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
side Wall inner shaft side Wall
0.15 0.15
1 Cum Intial Rate 8794.80 1 Cum Intial Rate 8150.50
6.67 Sqm side wall cetering charges 2463.00 16420.00 6.67 Sqm side wall cetering ch 2463.00 16420.00
9.00 Lift charges 134 1206 9.00 Lift charges 134 1206
extra allowance on centring ch 30% 4926.00 extra allowance on c 30% 4926.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 3070.45 Contractor's Profit 13.615% 3070.45
Total 34417.25 Total 33772.95 644.30
21
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Top 21
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
Dome excluding cost and fabrication of steel 'complete for Top Dome excluding cost and fabrication of steel
at 33-36 mytr 0.15 0.15
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
6.67 Sqm Slab cetering charges 2670.00 17800.00 6.67 Sqm Slab cetering charges 2670.00 17800.00
11.00 Lift charges 134 1474 11.00 Lift charges 134 1474
extra allowance on centring ch 30% 5340.00 extra allowance on c 30% 5340.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 3351.20 Contractor's Profit 13.615% 3351.20
Total 35171.50 Total 34527.10
22
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Inner 22 M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
Shaft excluding cost and fabrication of steel 'complete for Inner Shaft excluding cost and fabrication of steel
at 33Mtrs 0.15 at 33Mtrs 0.15
1 Cum Intial Rate 7206.30 7206.30 1 Cum Intial Rate 6561.90 6561.90
6.67 Sqm Slab cetering charges 399.00 2660.00 6.67 Sqm Slab cetering charges 399.00 2660.00
10.00 Lift charges 134 1340 10.00 Lift charges 134 1340
extra allowance on centring ch 30% 798.00 extra allowance on c 30% 798.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 653.25 Contractor's Profit 13.615% 653.25
Total 12657.55 Total 12013.15
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank Top VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
Slab Tank Top Slab
0.125 Flat 0.125 Flat
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
8.000 Sqm cetering charges 1643.00 13144.00 8.000 Sqm cetering charges 1643.00 13144.00
10.00 Lift charges 134 1340 10.00 Lift charges 134 1340
extra allowance on centring ch 30% 3943.20 extra allowance on c 30% 3943.20
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.62% 2508.86 Contractor's Profit 13.62% 2508.86
Page 80 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank Top VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
Dome Tank Top Dome
0.100 Flat 0.100 Flat
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
10.000 Sqm cetering charges 2427.00 24270.00 10.000 Sqm cetering charges 2427.00 24270.00
9.00 Lift charges 134 1206 9.00 Lift charges 134 1206
extra allowance on centring ch 30% 7281.00 extra allowance on c 30% 7281.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 4459.87 Contractor's Profit 13.615% 4459.87
Total 44423.20 Total 43778.80 644.40
M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc 'complete for Phenail on Top M30 grade design mix using 20 mm HG metal 'including cost,conveyance and labour etc
23 23
Dome excluding cost and fabrication of steel 'complete for Phenail on Top Dome excluding cost and fabrication of steel
35mtr 0.100 Flat 0.100 Flat
1 Cum Intial Rate 7206.30 1 Cum Intial Rate 6561.90
10.000 Sqm cetering charges 0.00 0.00 10.000 Sqm cetering charges 0.00 0.00
11.00 Lift charges 134 1474 11.00 Lift charges 134 1474
extra allowance on centring ch 30% 0.00 extra allowance on c 30% 0.00
--- 0% 0.00 --- 0% 0.00
Contractor's Profit 13.615% 200.69 Contractor's Profit 13.615% 200.69
Total 8880.99 Total 8236.59
Supply and placing of mild steel structural steel angles, channels and I- sections including cost & convyance
24 Supply and placing of mild steel structural steel angles, channels and I- sections including cost & convyance of all 24 of all materials labour and fabrication charges etc..
materials labour and fabrication charges etc..
Supply,Fabrication, fixing of MS Gates Using of ISMB,ISA,ISMC BEAMS Etc..
Manufacturing, supply, delivery and fixing the lightening protective system with 25mm dia copper rod 4 feet
Manufacturing, supply, delivery and fixing the lightening protective system with 25mm dia copper rod 4 feet
length100mm dia ball with 4" spikes 5 nos with base plate 6"x6"x6" mm thick copper strip size 25x6mm
length100mm dia ball with 4" spikes 5 nos with base plate 6"x6"x6" mm thick copper strip size 25x6mm thick and
25 25 thick and connectors with protective including suitable Earthing arrangements as per the standard
connectors with protective including suitable Earthing arrangements as per the standard specifications including cost
specifications including cost and conveyance of all materials and taxes etc complete for finished item of
and conveyance of all materials and taxes etc complete for finished item of work
work
Lightineng protective systemm 1 1 49800 No 49800 Lightineng protective systemm 1 1 42203.39 No 42203.39
Page 81 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Providing and fixing water level indicator up to 2.5m/3m/4m height including MS enamelied guage plate
Providing and fixing water level indicator up to 2.5m/3m/4m height including MS enamelied guage plate 150mm wide
150mm wide and 6mm thick, copper float, providing and fixing required accessories such as pointer, pullies,
26 and 6mm thick, copper float, providing and fixing required accessories such as pointer, pullies, nylon thread as per the 26
nylon thread as per the standard specifications including cost and convyance of all materials and taxes etc
standard specifications including cost and convyance of all materials and taxes etc complete for finished item of work.
complete for finished item of work.
Water level Indicator 1 1 3300 Each 33000 Water level Indicator 1 1 2796.61 Each 2796.61
Supply & Fixing of MS Door /window fabricated MS frame with agles of Size 40mmx40mmx5mm thick and
Supply & Fixing of MS Door /window fabricated MS frame with agles of Size 40mmx40mmx5mm thick and 18mm
18mm gauge MS sheet including outer frame embeded in the wall with 16mm soliid bar for locking
27 gauge MS sheet including outer frame embeded in the wall with 16mm soliid bar for locking arrangement as per the 27
arrangement as per the standard specifications including cost & Conveyance of all materials and taxes etc
standard specifications including cost & Conveyance of all materials and taxes etc complete for finished item of work
complete for finished item of work
MS Door /Windows 1 1 9800 sqm 9800 MS Door /Windows 1 1 8305.08 sqm 8305.08
Supply and Fixing of Mosquito mesh to air vent openings with protected bedding wood at edges of the mesh as per Supply and Fixing of Mosquito mesh to air vent openings with protected bedding wood at edges of the
28 the standard specifications including cost and convyance of all material and taxes etc complete for finished item of 28 mesh as per the standard specifications including cost and convyance of all material and taxes etc complete
work for finished item of work
Mosquito mesh 1 1 300 sqm 300 Mosquito mesh 1 1 254.24 sqm 254.24
Name board Lettering on structure with paint as per the standard specifications including cost & convyance of all Name board Lettering on structure with paint as per the standard specifications including cost & convyance
29 29
materials and taxes etc complete for finished item of work of all materials and taxes etc complete for finished item of work
Name board lettering 1 1 1150 sqm 1150 Name board lettering 1 1 974.58 sqm 974.58
As per
Supply, fabrication and erection of SS hand rail of 1mt height (40mm dia) vertical for every 1mt spacing and 2 rows procs no: Supply, fabrication and erection of SS railing of 1mt height(40mm dia) vertical for every 1mt spacing and 2
30 25mm dia horizontal in between of SS - 304 grade, 40S. As per the standard spectification including cost and AEE3/DE- 30 rows 25mm dia horizontal in between of SS - 304 grade, 40S. As per the standard spectification including
conveyance of all materials completed for finished item of work II/GRID/RA cost and conveyance of all materials completed for finished item of work
TEAPPROV
AL/PHASE-
II/2019-20,
DATED: 23-
01-2020
SS Railing 1 1 3100 Each 3100 SS Railing 1 1 2627.12 Each 2627.12
Supply, Delivery and fixing of Aluminium frame with 8mm thick glass fixing over the clear water Supply, Delivery and fixing of Aluminium frame with 8mm thick glass fixing over the clear
collection chamber including cost and conveyance of all materials and labour charges etc., complete water collection chamber including cost and conveyance of all materials and labour charges
etc., complete
9.00 Supply of Aluminium anodized Sections for frames 321.00 2889.00 9.00 Supply of Aluminium anodized Sections for frames 271.73 2445.61
Labour charges for making, fabricating any aluminium
1.00 Labour charges for making, fabricating any aluminium fixtures 428.00 428.00 1.00 428.00 428.00
fixtures
provision for fixtures - hinges, handle etc. 829.25 provision for fixtures - hinges, handle etc. 718.40
1.00 Glass 8mm thick 932.00 932.00 1.00 Glass 8mm thick 932.00 932.00
5078.25 4524.01
add contractor profit 13.615% 691.4 add contractor profit 13.615% 615.94
5769.65 Sqm 5139.95
Page 82 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Supply, Delivery and fixing of Aluminium frame door with 8mm thick glass fixing over the clear water Supply, Delivery and fixing of Aluminium frame windowswith 8mm thick glass fixing over
Filter Area including cost and conveyance of all materials and labour charges etc., complete the clear water Filter Area including cost and conveyance of all materials and labour charges
etc., complete
6.55 Supply of Aluminium anodized Sections for frames 321.00 2103.19 2.52 12.00 Supply of Aluminium anodized Sections for frames 271.73 3260.81
1.00 Labour charges for making, fabricating any aluminium fixtures 428.00 428.00 6.6 1.00 Labour charges for making, fabricating any aluminium 428.00 428.00
provision for fixtures - hinges, handle etc. 632.7975 2.62 fixtures
provision for fixtures - hinges, handle etc. 922.2025
1.00 Glass 8mm thick 932.00 932.00 1.00 Glass 8mm thick 932.00 932.00
4095.99 5543.01
add contractor profit 13.615% 557.67 add contractor profit 13.615% 754.68
4653.66 Sqm 6297.69
Supply and fixing Aluminium Anodised sections of Series C sections of 8774 of size 63 x
Supply and fixing Aluminium Anodised sections of Series C sections of 8774 including all labour
33x1.5 mt all labour charges for fixing the fixtures with required no.of screws, bolts and
charges for fixing the fixtures with required no.of screws, bolts and nuts and including labour charges for
nuts and including labour charges for fixing the frame in position, fixing shutter to frame
fixing the frame in position, fixing shutter to frame etc. completed for finished item of work for
etc. completed for finished item of work
A) MATERIAL REQUIREMENT A) MATERIAL REQUIREMENT
ALUMINIUM SECTION 5.66 kgs 321.00 1818.14 ALUMINIUM SECTION 5.66 kgs 271.73 1539.10
B) LABOUR CHARGES B) LABOUR CHARGES
Power Saw Cutter - Hand Operated -
Power Saw Cutter - Hand Operated - Operator 0.347 No 415.00 144.01 0.347 No 415.00 144.01
Operator
Power Drill - Hand Operated - Operator 0.347 No 415.00 144.01 Power Drill - Hand Operated - Operator 0.347 No 415.00 144.01
Unskilled Mazdoor 1.042 No 310.00 323.02 Unskilled Mazdoor 1.042 No 310.00 323.02
C) Machinery C) Machinery
Power Saw Cutter - Hand Operated - Hire
Power Saw Cutter - Hand Operated - Hire charges 2.778 hrs 22.50 62.51 2.778 hrs 22.50 62.51
charges
Power Drill - Hand Operated - Hire
Power Drill - Hand Operated - Hire Charges 2.778 hrs 22.50 62.51 2.778 hrs 22.50 62.51
Charges
Supervision Charges 0.347 No 590.00 204.73 Supervision Charges 0.347 No 590.00 204.73
2758.91 2479.87
add Contractors profit @ 13.615% 375.63 add Contractors profit @ 13.615% 337.63
3134.54 sqm 2817.50 sqm
Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved drawing
Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved drawing with aluminium
with aluminium anodised sections of Jindal sections and outer frame top horizontals & both
anodised sections of Jindal sections and outer frame top horizontals & both verticals of 2408 of size 101.6
verticals of 2408 of size 101.6 x 44.75 x 3.18 mm Shutter frame top, bottom and verticals of
x 44.75 x 3.18 mm Shutter frame top, bottom and verticals of 4504 of size 44.45 mm x 47.62 mm x 3.18
4504 of size 44.45 mm x 47.62 mm x 3.18 and Middle lock rail of 4621 of size 49.91 x
and Middle lock rail of 4621 of size 49.91 x 44.45 x 3 mm with plain clear float glass 5 mm thick fixed
25 44.45 x 3 mm with plain clear float glass 5 mm thick fixed including supply and fixing
including supply and fixing aluminium handles of 100 mm for each shutter, floor springs/ hydraulic door
aluminium handles of 100 mm for each shutter, floor springs/ hydraulic door closure
closure assembly and all labour charges for fixing the fixtures with required no.of screws, bolts and nuts
assembly and all labour charges for fixing the fixtures with required no.of screws, bolts and
and including labour charges for fixing the frame in position, fixing shutter to frame etc. completed for
nuts and including labour charges for fixing the frame in position, fixing shutter to frame
finished item of work
etc. completed for finished item of work
Page 83 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Unskilled Mazdoor 1.042 No 310.00 323.02 Unskilled Mazdoor 1.042 No 310.00 323.02
C) Machinery C) Machinery
Power Saw Cutter - Hand Operated - Hire
Power Saw Cutter - Hand Operated - Hire charges 2.778 hrs 22.50 62.51 2.778 hrs 22.50 62.51
charges
Power Drill - Hand Operated - Hire
Power Drill - Hand Operated - Hire Charges 2.778 hrs 22.50 62.51 2.778 hrs 22.50 62.51
Charges
Supervision Charges 0.347 No 590.00 204.73 Supervision Charges 0.347 No 590.00 204.73
5532.17 4978.21
add Contractors profit @ 13.615% 753.20 add Contractors profit @ 13.615% 677.78
6285.37 sqm 5655.99 sqm
Supply and fixing Aluminium Anodised two track sliding Windows as per approved drawing with Supply and fixing Aluminium Anodised two track sliding Windows as per approved
aluminium anodised sections of Series C sections and outer frame top horizontals & both verticals of drawing with aluminium anodised sections of Series C Jindal sections and outer frame top
8774 of size 62 x 29.5 mm and bottom horizontal - two track frame of 8773 of size 62 x 29.5 mm, Shutter horizontals & both verticals of 8774 of size 62 x 29.5 mm and bottom horizontal - two track
frame top, bottom and verticals of 8304 of size 50 mm x 20 mm and Weather interlocking frame of 8306 frame of 8773 of size 62 x 29.5 mm, Shutter frame top, bottom and verticals of 8304 of size
of size 50 x 20 with plain clear float glass 8 mm thick fixed including supply and fixing aluminium 50 mm x 20 mm and Weather interlocking frame of 8306 of size 50 x 20 with plain clear
handles each shutter, nylon rollers assembly and all labour charges for fixing the fixtures with required float glass 8 mm thick fixed including supply and fixing aluminium handles each shutter,
no.of screws, bolts and nuts and including labour charges for fixing the frame in position, fixing shutter to nylon rollers assembly and all labour charges for fixing the fixtures with required no.of
frame etc. completed for finished item of work screws, bolts and nuts and including labour charges for fixing the frame in position, fixing
shutter to frame etc. completed for finished item of work
A) MATERIAL REQUIREMENT A) MATERIAL REQUIREMENT
ALUMINIUM SECTION 7.85 kgs 353.00 2771.05 ALUMINIUM SECTION 14.60 kgs 353.00 5153.80
GLAZING with GLASS 8mm 1.00 sqm 932.00 932.00 GLAZING with GLASS 8mm 1.00 sqm 932.00 932.00
RUBBER BEADING 5.00 Rmt 2.00 10.00 RUBBER BEADING 4.00 Rmt 2.00 8.00
Nylon rollers 4.00 Nos 15.00 60.00 Nylon rollers 6.00 Nos 15.00 90.00
Alum.Anodised.PC Handles 2.00 each 45.00 Alum.Anodised.PC Handles 2.00 each 45.00
Supply of 7.5mm thick Aluminium Grill 1.00 sqm 1112.00 1112.00 Supply of 7.5mm thick Aluminium Grill 1.00 sqm 1112.00 1112.00
B) LABOUR CHARGES B) LABOUR CHARGES
Power Saw Cutter - Hand Operated - Operator 0.347 No 415.00 144.01 Power Saw Cutter - Hand Operated - 0.347 No 415.00 144.01
Power Drill - Hand Operated - Operator Operator
Power Drill - Hand Operated - Operator
0.347 No 415.00 144.01 0.347 No 415.00 144.01
Unskilled Mazdoor 1.042 No 310.00 323.02 Unskilled Mazdoor 1.042 No 310.00 323.02
C) Machinery C) Machinery
Power Saw Cutter - Hand Operated - Hire charges 2.778 hrs 22.50 62.51 Power Saw Cutter - Hand Operated - Hire 2.778 hrs 22.50 62.51
Power Drill - Hand Operated - Hire Charges charges
Power Drill - Hand Operated - Hire
2.778 hrs 22.50 62.51 2.778 hrs 22.50 62.51
Charges
Supervision Charges 0.347 No 590.00 204.73 Supervision Charges 0.347 No 590.00 204.73
5825.82 8236.57
5825.82 8236.57
add Contractors profit @ 13.615% 793.19 add Contractors profit @ 13.615% 1121.41
6619.01 sqm 9357.98 sqm
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for
VRCC(M30) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Landing slab
Landing slab
0.150 0.150
Page 84 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC (M30) using 20mm HBG metal including cost and conveyance of all material, labour charges, VRCC (M30) using 20mm HBG metal including cost and conveyance of all material, labour
centering etc., complete but excluding cost of steel and its fabrication charges for steps Risers-50mm charges, centering etc., complete but excluding cost of steel and its fabrication charges for
thick 0.05 steps Risers-50mm thick 0.05
1 Cum Intial Rate 8794.80 1 Cum Intial Rate 8150.50
40.0 1Cum coulmn cetering charges 480.00 1 Sq mt 19200.00 40.0 1Cum coulmn cetering charges 480.00 1 Sq mt 19200.00
extra allowance on centring charges 0.00 extra allowance on centring charges 0.00
--- 0.00 0.00 --- 0.00 0.00
Contractor's Profit 13.6% 2614.08 Contractor's Profit 13.6% 2614.08
Page 85 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Side Wall
(upto 3mts below and 3mts above GL)
#REF!
1.00 Cum Cost of CC (1:1.5:3) 8794.80 1 Cum 8794.80
#REF! Sqm Centering charges 1115.00 1 Sqm #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
- 0 - 3 Mts Total #REF!
#REF! Centering charges 1909.7 1 Sqm #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Lifting 3 - 4 Mts 134 #REF! 152.24 #REF!
4 - 5 Mts #REF! 152.24 #REF!
5 - 6 Mts #REF! 152.24 #REF!
6-7 Mts #REF! 152.24 #REF!
7-8 Mts #REF! 152.24 #REF!
8-9mts #REF! 152.24 #REF!
9-10mts #REF! 152.24 #REF!
10-11mts #REF! 152.24 #REF!
11-12mts #REF! 152.24 #REF!
12-13mts #REF! 152.24 #REF!
13-14mts #REF! 152.24 #REF!
14-15mts #REF! 152.24 #REF!
15-16mts #REF! 152.24 #REF!
16-17mts #REF! 152.24 #REF!
17-18mts #REF! 152.24 #REF!
18-19mts #REF! 152.24 #REF!
19-20mts #REF! 152.24 #REF!
20-21mts #REF! 152.24 #REF!
21-22mts #REF! 152.24 #REF!
22-23mts #REF! 152.24 #REF!
23-24mts #REF! 152.24 #REF!
24-25mts #REF! 152.24 #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Side Wall
#REF!
1.00 Cum Cost of CC (1:1.5:3) 8794.80 1 Cum 8794.80
#REF! Sqm Centering charges 1115.00 1 Sqm #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
- 0 - 3 Mts Total #REF!
3 -4 Mts 134 #REF! 18.24 #REF!
#REF! Centering charges 1909.7 #REF!
Page 87 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Side Wall
#REF!
1 Cum Intial rate 8794.80
#REF! Sqm side wall cetering charges 1115.00 #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
0-3mts #REF!
#REF! side wall cetering charges 1909.7 1 Sqm #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Lifting 3 - 4 Mts 134 #REF! 152.24 #REF!
4 - 5 Mts #REF! 152.24 #REF!
5 - 6 Mts #REF! 152.24 #REF!
6-7 Mts #REF! 152.24 #REF!
7-8 Mts #REF! 152.24 #REF!
8-9mts #REF! 152.24 #REF!
9-10mts #REF! 152.24 #REF!
10-11mts #REF! 152.24 #REF!
11-12mts #REF! 152.24 #REF!
12-13mts #REF! 152.24 #REF!
13-14mts #REF! 152.24 #REF!
14-15mts #REF! 152.24 #REF!
15-16mts #REF! 152.24 #REF!
16-17mts #REF! 152.24 #REF!
17-18mts #REF! 152.24 #REF!
18-19mts #REF! 152.24 #REF!
19-20mts #REF! 152.24 #REF!
20-21mts #REF! 152.24 #REF!
21-22mts #REF! 152.24 #REF!
22-23mts #REF! 152.24 #REF!
23-24mts #REF! 152.24 #REF!
24-25mts #REF! 152.24 #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Side Wall
0.25
1.00 Cum Cost of CC (1:1.5:3) 8794.80 1 Cum 8794.80
4.00 Sqm Centering charges 1115.00 1 Sqm 4460.00
--- 0% 0.00
Contractor's Profit 14% 607.23
- 0 - 3 Mts Total 13862.03
4.00 Centering charges 1909.7 1 Sqm 7638.80
Page 88 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
--- 0% 0.00
Contractor's Profit 14% 1040.02
Lifting 3 - 4 Mts 134 17473.62 152.24 17625.87
4 - 5 Mts 17625.87 152.24 17778.11
5 - 6 Mts 17778.11 152.24 17930.35
6-7 Mts 17930.35 152.24 18082.60
7-8 Mts 18082.60 152.24 18234.84
8-9mts 18234.84 152.24 18387.09
9-10mts 18387.09 152.24 18539.33
10-11mts 18539.33 152.24 18691.58
11-12mts 18691.58 152.24 18843.82
12-13mts 18843.82 152.24 18996.06
13-14mts 18996.06 152.24 19148.31
14-15mts 19148.31 152.24 19300.55
15-16mts 19300.55 152.24 19452.80
16-17mts 19452.80 152.24 19605.04
17-18mts 19605.04 152.24 19757.28
18-19mts 19757.28 152.24 19909.53
19-20mts 19909.53 152.24 20061.77
20-21mts 20061.77 152.24 20214.02
21-22mts 20214.02 152.24 20366.26
22-23mts 20366.26 152.24 20518.50
23-24mts 20518.50 152.24 20670.75
24-25mts 20670.75 152.24 20822.99
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Side Wall
0.20
1 Cum Intial Rate' 8794.80
5.00 Sqm side wall cetering charges 1115.00 5575.00
--- 0.00 0.00
Contractor's Profit 0.14 759.04
0-3mts 15128.84
5.00 side wall cetering charges 1909.7 1 Sqm 9548.50
--- 0% 0.00
Contractor's Profit 13.62% 1300.03
Lifting 3 - 4 Mts 134 19643.33 152.24 19795.57
4 - 5 Mts 19795.57 152.24 19947.82
5 - 6 Mts 19947.82 152.24 20100.06
6-7 Mts 20100.06 152.24 20252.30
7-8 Mts 20252.30 152.24 20404.55
8-9mts 20404.55 152.24 20556.79
9-10mts 20556.79 152.24 20709.04
10-11mts 20709.04 152.24 20861.28
11-12mts 20861.28 152.24 21013.53
12-13mts 21013.53 152.24 21165.77
13-14mts 21165.77 152.24 21318.01
14-15mts 21318.01 152.24 21470.26
15-16mts 21470.26 152.24 21622.50
Page 89 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Side Wall Not updated
#REF!
1 Cum Intial rate 8794.80
#REF! Sqm side wall cetering charges 1115.00 #REF!
#REF! Lift charges 134 #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
#REF! 134 Total #REF!
#REF! (Lift Charges #REF! 18.24 #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Pump
House Side Wall
#REF!
1 Cum Intial rate 8397.60
#REF! Sqm side wall cetering charges 1115.00 #REF!
#REF! Lift charges 134 #REF!
--- 0% #REF!
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for pump house top slab
#REF! mm thick
#REF! Cum Cost of CC (1:1.5:3) 7279.00 1 Cum #REF!
#REF! Sqm Centering charges #REF! 1 Sqm #REF!
18.00 Add lifting charges 134.00 1 Cum 2412.00
--- 0% #REF!
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for Floor Slab
#REF! mm thick
#REF! Cum Cost of CC (1:1.5:3) 7279.00 1 Cum #REF!
#REF! Sqm Centering charges #REF! 1 Sqm #REF!
13.00 Add lifting charges 134.00 1 Cum 1742.00
Page 90 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
--- 0% #REF!
Contractor's Profit 14% #REF!
Total 10sqmt #REF!
89 VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for ring beam
OHBR
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for OHBR Ring Beam
#REF! #REF!
1.0 Cum cost of RCC(1:11/2:3) 8468.60 1 Cum 8468.60
#REF! Sqm Centering charges 1206.00 1 Cum #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Columns
#REF! #REF!
1 Cum Intial rate 8794.80
#REF! Sqm coulmn cetering charges 1099.00 1 Sq mt #REF!
Page 91 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Braces
#REF! #REF!
1 Cum Intial rate 8794.80
#REF! Sqm Brace cetering charges 1099.00 1 Sq mt #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank
bottom ring beam
#REF! #REF!
1 Cum Intial rate 7206.30
#REF! Sqm centering charges 1206.00 #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank ring
beam
#REF! #REF!
1 Cum Intial Rate 7279.00
#REF! Sqm centering charges 1206.00 1 Sq mt #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
Page 92 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
--- 0% #REF!
Total #REF!
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for OHBR Top slab Dome
#REF!
1 Cum Intial Rate 7279.00
#REF! Sqm cetering charges 2670.00 #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for OHBR bottom Dome
#REF!
1 Cum Intial Rate 7279.00
#REF! Sqm cetering charges 2670.00 #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Total #REF!
--- 0% #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank ring
beam
#REF! #REF!
1 Cum Intial Rate 8101.69
#REF! Sqm centering charges 1206.00 1 Sq mt #REF!
0.00 Lift charges 134 0
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for shaft side wall
#REF!
1 Cum Intial Rate 8397.60
#REF! Sqm side wall cetering charges 2463.00 #REF!
0.00 Lift charges 134 0
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
0 - 3 Mts Total #REF!
3 - 4 Mts lift charges 134 #REF! #REF!
4 - 5 Mts #REF! #REF!
5 - 6 Mts #REF! #REF!
6-7 Mts #REF! #REF!
7-8 Mts #REF! #REF!
8-9 Mts #REF! #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank
bottom slab
#REF!
1 Cum Intial Rate 7279.00
#REF! Sqm cetering charges 2670.00 #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank Top
slab
0.15
1 Cum Intial Rate 7279.00
6.667 Sqm cetering charges 2670.00 17800.00
#REF! Lift charges 134 #REF!
extra allowance on centring ch 0% 0.00
--- 0% 0.00
Contractor's Profit 14% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank ring
beam
#REF! #REF!
1 Cum Intial Rate 7279.00
#REF! Sqm centering charges 1206.00 1 Sq mt #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Conical
Side Wall
#REF!
1 Cum Intial Rate 8397.60
#REF! Sqm side wall cetering charges 2463.00 #REF!
#REF! Lift charges 134 #REF!
(Average) extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Page 95 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank ring
beam
#REF! #REF!
1 Cum Intial Rate 7279.00
#REF! Sqm centering charges 1206.00 1 Sq mt #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for inner
shaft side Wall
#REF!
1 Cum Intial Rate 8397.60
#REF! Sqm side wall cetering charges 2463.00 #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for inner
shaft Flat slab
#REF!
1 Cum Intial Rate 7279.00
#REF! Sqm Slab cetering charges 1643.00 #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank top
dome
#REF!
1 Cum Intial Rate 7279.00
#REF! Sqm cetering charges 2670.00 #REF!
#REF! Lift charges 134 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
Total #REF!
VRCC(1:1.5:3) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Landing
slab
#REF!
1 Cum Intial Rate 7279.00
Page 96 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for steps treads-50mm
thick #REF!
1 cum Intial rate 7206.30
#REF! 1Cum coulmn cetering charges 480.00 #REF!
extra allowance on centring ch #REF! #REF!
--- 0% #REF!
Contractor's Profit 14% #REF!
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for steps Risers-50mm thick
#REF!
1 Cum Intial Rate 7206.30
#REF! 1Cum coulmn cetering charges 480.00 1 Sq mt #REF!
extra allowance on centring charges #REF! #REF!
--- 0.00 #REF!
Contractor's Profit 14% #REF!
Page 98 of 230
S.No Qty Description of Item Rate Amount S.NoQty Description of Item Rate Amount
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for Tie Brace
#REF! #REF!
1 Cum Intial Rate 1 Cum 7206.30
#REF! Sqm Brace cetering charges 1206.00 1 Sq mt #REF!
extra allowance on centring charges #REF! #REF!
--- 0.00 #REF!
Contractor's Profit 14% 0.00% #REF!
Sundries
0 - 5 Mts 0 lifts Total #REF!
5 - 8 Mts lift charges 402 #REF! #REF!
8 - 11 Mts #REF! #REF!
11- 14 Mts #REF! #REF!
14- 17 Mts #REF! #REF!
17- 20 Mts #REF! #REF!
20- 23 Mts #REF! #REF!
23- 26 Mts #REF! #REF!
26- 29 Mts #REF! #REF!
29- 32 Mts #REF! #REF!
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for Top flat slab
Intial rate 0.13 7279.00 0.350 7279.00 0.150
8.00 2.86 centering charges 1643.00 13144.00 4694.29 6.67
#REF! Lift charges 134 #REF! #REF!
extra allowance on centring ch #REF! #REF! #REF! #REF! #REF!
--- 0% #REF! #REF!
Contractor's Profit 14% #REF! #REF!
#REF! #REF!
SSTank
Page 99 of 230
DETAILED CUM SUB WORKING ESTIMATE FOR CONSTRUCTION OF WATCHMAN AND
OPERATOR
Name of the Project:- Providing Driiking water toQUARTERS-1
habitation in SRSP Adilabad segment in
Adilabad district
Name of the Sub work : Construction of Watch man and Operator Quarter -1 at 50 MLD WTP at Bhainsa
Est.Cost Rs 46.37 lakhs
Sl.N Dimensions
o Description Qty Rate Amount
Nos L B D
1 Earth work excavation in all type of soils with intial lead and lift etc complete.
12 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Columns upto 1st Floor.
13 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Beams for 1st Floor Slab.
15 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Beams for Water Tank.
16 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Bottom Slab for Water Tank.
17 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Side wall for Water Tank.
18 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Top Slab for Water Tank.
19 Brick Masonry with CM(1:6) using Second Class Bricks including cost and conveyance of all
the materials etc complete for Ground Floor upto Lintel Beams.
21 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
materials,but excluding the cost of the steel etc complete for Stair Case Landing.
22 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
materials,but excluding the cost of the steel etc complete for Sunshades in 1st Floor.
23 Brick Masonry with CM(1:6) using Second Class Bricks including cost and conveyance of all
the materials etc complete from Lintel Beams upto 1st Floor Beam.
25 Brick Masonry with CM(1:6) using Second Class Bricks including cost and conveyance of all
the materials etc complete for 1st floor Upto Lintel Beams
27 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
materials,but excluding the cost of the steel etc complete for Stair Case Landing in
1st Floor
28 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
materials,but excluding the cost of the steel etc complete for Sunshades in 1st Floor.
29 Brick Masonry with CM(1:6) using Second Class Bricks including cost and conveyance of all
the materials etc complete from above Lintel Beams in 1st Floor.
30 Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm thick and
second coat in CM(1:3) prop 4mm thick including cost and conveyance of all materials and
labour charges etc., complete for 1st Floor.
31 Accoproof plastering with CM(1:3), 20 mm thick including cost and conveyance of all the
materials ect complete On top slab.
32 Supply and fixing of the Sal Wood Door With angular frame CR Sheet including fixtures ,
fasteners including csot and conveyance of the all the materials , labour charges ect complete.
33 Snowcem paint two coats including cost and conveyence etc complete. For Ground Floor
Long walls 2 3 14.99 - 3.00 269.82
Deductions
Brick Masonry in Staircase area 2 1 2.40 - 3.00 14.40
Short Wall end Faces both sides sec 2 2 9.070 3.00
A-A - 108.84
Short Wall Mid 2 4 8.17 - 3.00 196.08
Deductions - 0.00
2 2
Brickwork in Living Cum Dining Area 3.05 - 3.00 36.60
Toilets Long Wall 2 2 3.05 - 3.00 36.60
Toilets Short Wall 4 2 1.80 - 3.00 43.20
Kitchen Partion Wall 2 2 1.80 - 3.00 21.60
Ceiling 1 0 0 - 0.00
Parapet Long Wall 2 14.99 2.03 - 60.86
Parapet Short Wall (Back) 2 1.5 2.03 - 6.09
Parapet Short Wall (Front) 2 0.9 2.03 - 3.65
DEDUCTIONS -
Door 1 10 1.30 - 0.23 2.99
Door 2 4 1.15 - 0.23 1.06
Main Doors 2 1.30 - 0.23 0.60
Window 1 7 1.30 - 0.23 2.09
Window 2 2 1.30 - 0.23 0.60
Window 3 1 0.85 - 0.23 0.20
Main Winows W 2 1.60 - 0.23 0.74
Ventilators 4 1.00 - 0.23 0.92
676.81 1029.9 69705.0
34 Snowcem paint two coats including cost and conveyence etc complete. For 1st Floor
Long walls 2 3 14.99 - 3.00 269.82
Deductions
Brick Masonry in Staircase area 2 1 2.40 - 3.00 14.40
Short Wall end Faces both sides sec 2 2 9.070 3.00
A-A - 108.84
Short Wall Mid 2 4 8.17 - 3.00 196.08
Deductions - 0.00
2 2
Brickwork in Living Cum Dining Area 3.05 - 3.00 36.60
Toilets Long Wall 2 2 3.05 - 3.00 36.60
Toilets Short Wall 4 2 1.80 - 3.00 43.20
Kitchen Partion Wall 2 2 1.80 - 3.00 21.60
Ceiling 1 0 0 - 0.00
Parapet Long Wall 2 14.99 2.03 - 60.86
Parapet Short Wall (Back) 2 1.5 2.03 - 6.09
Parapet Short Wall (Front) 2 0.9 2.03 - 3.65
DEDUCTIONS -
Sl.N Dimensions
o Description Qty Rate Amount
Nos L B D
Door 1 10 1.30 - 0.23 2.99
Door 2 4 1.15 - 0.23 1.06
Main Doors 2 1.30 - 0.23 0.60
Window 1 7 1.30 - 0.23 2.09
Window 2 2 1.30 - 0.23 0.60
Window 3 1 0.85 - 0.23 0.20
Main Winows W 2 1.60 - 0.23 0.74
Ventilators 4 1.00 - 0.23 0.92
676.81 1029.9 69705.00
35 Supply and fixing of the Alluminium Windows of Size 0.9 X 1.20m With angular frame CR
Sheet including fixtures , fasteners including csot and conveyance of the all the materials ,
labour charges ect complete.
36 Synthatic Enamel painting over primary coat and Enamel painting in two caots including csot
and conveyance of all the materials ect complete.
37 Supply of soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600
mm and thickness between 8-10 mm 1st quality conforming toIS:13711, IS:13712, IS:13630
(Parts 1 to 15) of any colour and finish in all shades and designs.
38 Supply and placing of the HYSD bars, fabrication including cost and conveyance of all
the materials etc complete.
41 Supply and fixing of the Ready made Ventilaters of Size 0.9 x 0.23 including csot and
conveyance of the all the materials , labour charges ect complete.
2 LS 10000.00
42 Unforeseen items
695678.04
TOTAL 4,636,562
2 Sand filling in basement with watering and tamping etc. complete. including
Cost and conveyance of the all materials etc.
for sump excavated
portion 1 1 52.100 42.400 0.100 220.90 848.10 1 Cum 187345
Plain Cement concrete (1:4:8) using 40 mm metal with hand mixing upto Plinth
3
level
for sump portion 1 1 52.10 42.40 0.30 662.71
for suction pit sides 1 1 19.10 4.40 0.30 25.21
0.00
687.92 5335.66 1 Cum 3670507
4 Construction of RR Masonary in CM (1:6) Using roug stone (BG) including cost &
convencey of all materials etc.,complete
0.00 0.00 1 Cum 0
Brick Massonary in CM (1:6) including C&C of all materials and labour charges
6 etc completed as per standard specifications.
Acco Proof cement paint of superior quality, plastering with CM(1:3) prop. 12
7 mm thick with including cost and conveyance of all materials and labour
charges etc., complete as per standard specifications for sump well
Sl. Description No. L B D Qty. Rate per Amount
Inside the sump +
haunches 1 4 50.00 3.75 750.00
1 2 40.00 3.75 300.00
Suction Pit 1 2 16.00 2.00 64.00
1 4 2.83 2.00 22.62
Bottom of the sump 1 1 50.00 40.30 2015.00
Outside above GL 1 2 50.60 1.05 106.26
1 2 40.00 1.05 84.00
Outside for top slab 1 1 50.60 40.90 2069.54
Inside the top slab 1 1 50.00 40.00 2000.00
Total 7411.42 1638.30 10 Sqm 1214213
Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm
8 thick and second coat in CM(1:3) prop 4mm thick including cost and
conveyance of all materials
0.00 0.00 10 Sqm 0
Epoxy Protective Coating with Procoat SNF (item 250 SSR) paint 3 coats over
9 water proof plastering, incl. conveyance of all m/ labour charges, etc., complete
for Botom slab, inside side walls ,columns and top & bottom of roof slab
Snowcem painting with 2 coats over a primary coat including cost and
10 conveyance of all materials and labour charges etc., complete as per standard
specifications
Inside the sump +
2 50 3.75 375.00
haunches
2 40.30 3.75 302.25
Bottom of the sump 1 50.00 40.30 2015.00
Outside above GL 2 50.60 1.05 106.26
Outside for top slab 1 50.60 40.90 2069.54
Inside the top slab 1 50.00 40.00 2000.00
Total 6868.05 1029.90 10 Sqm 707340
12 Supply and fixing of light type man hole cover with frame of size LS each 3044
0.6 x 0.6 m as per standard specification HD-35
Supply and fixing of for RCC pre-cast fly proof ventilators with
13 necessary copper wire mesh, etc., complete as per standard LS each 20000
specification
Sl. Description No. L B D Qty. Rate per Amount
Provision for RCC Central phenial of size 0.60 m dia as per standard
14 LS each 2250
specifications
15 Provision for RCC inside ladder as per the standard specifications LS each 10000
Provision for 300mm dia CI Sluice valve on 300mm dia line , inlet
17 arrangements LS each 40000
18 Provision for refilling the foundation with excavated earth, and LS Job 20000
remaining Qty for levelling area
Lakhs 363.00
Sl. DESCRIPTION ITEM CODE COEF. UNIT RATE PER UNIT Amount
No (Rs.)
1 Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any ISI brand and fixing all special such Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any ISI brand and fixing all special such as
as plain bends, off sets, door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary with plain bends, off sets, door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary with
required number of Bombay nails including cost and conveyance of all materials to site, labour charges etc.complete for finished item required number of Bombay nails including cost and conveyance of all materials to site, labour charges etc.complete for finished item of
of work at all floor levels. (APSS No. 1302 1319 & 1326) work at all floor levels. (APSS No. 1302 1319 & 1326)
(a) 75mm dia 3 Mts Single socket 75mm dia 3 Mts Single socket
Basic rate as per ssr item TBSP-H.I-01 1.00 RM 255.00 3.00 RMT 85.00 Basic rate as per ssr item TBSP-H.I-01 1.00 RM 215.99 3.00 RMT 72.00
labour charges TBSP-H.IV-01 1.00 RM 70.00 1.00 RM 70.00 labour charges TBSP-H.IV-01 1.00 RM 70.00 1.00 RM 70.00
155.00 142.00
Add Contractor's profit 13.615% 21.10 Add Contractor's profit 13.615% 19.33
Total rate per 1 RMT 176.10 Total rate per 1 RMT 161.35
(b) 90mm dia 3 Mts single socket 90mm dia 3 Mts single socket
Basic rate as per ssr item TBSP-H.I-02 1.00 RM 405.00 3.00 RMT 135.00 Basic rate as per ssr item TBSP-H.I-02 1.00 RM 342.99 3.00 RMT 114.33
labour charges TBSP-H.IV-01 1.00 70.00 1.00 0.00 70.00 labour charges TBSP-H.IV-01 1.00 70.00 1.00 0.00 70.00
205.00 184.33
Add Contractor's profit 13.615% 27.91 Add Contractor's profit 13.615% 25.10
Total rate per 1 RMT 232.95 Total rate per 1 RMT 209.45
(c) 110mm dia 3 Mts single socket 110mm dia 3 Mts single socket
Basic rate as per ssr item TBSP-H.I-03 1.00 RM 484.00 3.00 RMT 161.33 Basic rate as per ssr item TBSP-H.I-03 1.00 RM 410.00 3.00 RMT 136.67
labour charges TBSP-H.IV-01 1.00 RM 70.00 1.00 RM 70.00 labour charges TBSP-H.IV-01 1.00 RM 70.00 1.00 RM 70.00
231.33 206.67
Add Contractor's profit 13.615% 31.50 Add Contractor's profit 13.615% 28.14
Total rate per 1 RMT 262.85 Total rate per 1 RMT 234.85
2 a Supplying and fixing PPR ball valve of 25 mm dia confirming to DIN standards 8077/8092 , Indian make heavy type including cost and a Supplying and fixing PPR ball valve of 25 mm dia confirming to DIN standards 8077/8092 , Indian make heavy type including cost and
conveyance of all materials , labour charges etc. complete for finished item of work. conveyance of all materials , labour charges etc. complete for finished item of work.
Basic rate as per ssr item TBSP-J.III-185 1.00 Nos 245.00 1.00 Nos 245.00 Basic rate as per ssr item TBSP-J.III-185 1.00 Nos 207.00 1.00 Nos 207.00
labour charges BMW-F18 1.00 44.00 1.00 0.00 44.00 labour charges BMW-F18 1.00 44.00 1.00 0.00 44.00
289.00 251.00
Add Contractor's profit 13.615% 39.35 Add Contractor's profit 13.615% 34.17
Total rate per 1 No 328.35 Total rate per 1 No 285.17
3 Supplying and fixing NP/CP/PLASTIC bib taps of size 12.70mm dia of Indian make Seiko or equivalent including cost and conveyance Supplying and fixing NP/CP/PLASTIC bib taps of size 12.70mm dia of Indian make Seiko or equivalent including cost and conveyance of
of all materials, labour charges etc., complete for finished item of work in all floors. all materials, labour charges etc., complete for finished item of work in all floors.
Basic rate as per ssr item TBSP-F.I-01 1.00 Nos 245.00 1.00 Nos 245.00 Basic rate as per ssr item TBSP-F.I-01 1.00 Nos 213.99 1.00 Nos 213.99
245.00 213.99
Add Contractor's profit 13.615% 33.36 Add Contractor's profit 13.615% 29.13
Total rate per 1 Nos 278.40 Total rate per 1 Nos 243.15
4 Supplying and fixing 150.00mmx100.00mm SWG gully trap 1st class confirming to ISI 651 & 4127with CI grating and constructing single Supplying and fixing 150.00mmx100.00mm SWG gully trap 1st class confirming to ISI 651 & 4127with CI grating and constructing single
brick masonry wall chamber of size 20" x 14" x 12” in CM (1:6) prop. Over a CC (1:5:10)prop. bed, and plastering 12mm thk. in CM (1:4) brick masonry wall chamber of size 20" x 14" x 12” in CM (1:6) prop. Over a CC (1:5:10)prop. bed, and plastering 12mm thk. in CM (1:4)
prop. both inside and outside surfaces and fitted with 304.8MM X 288.6 MM (12"X9") CI frame and hinged cover including labour for prop. both inside and outside surfaces and fitted with 304.8MM X 288.6 MM (12"X9") CI frame and hinged cover including labour for
fixing and laying the SWG junctions/plugs/bends with air tightcement joints etc., complete including cost and conveyance of all fixing and laying the SWG junctions/plugs/bends with air tightcement joints etc., complete including cost and conveyance of all
materials to site, labour charges etc., materials to site, labour charges etc.,
Basic rate as per ssr item TBSP-A.I-09 1.00 Nos 568.00 1.00 Nos 568.00 Basic rate as per ssr item TBSP-A.I-09 1.00 Nos 544.01 1.00 Nos 544.01
568.00 544.01
Add Contractor's profit 13.615% 77.33 Add Contractor's profit 13.615% 74.07
Total rate per 1 No 645.33 Total rate per 1 No 618.08
5 Supplying and fixing CI Floor traps 100 mm dia Inlet- 75 mm (3") outlet pipe - 4 Kgs 1st quality ISI marked conforming to IS:1729-1979 Supplying and fixing CI Floor traps 100 mm dia Inlet- 75 mm (3") outlet pipe - 4 Kgs 1st quality ISI marked conforming to IS:1729-1979
with C.P. Grating fixing with white cement as per site requirements with standard practice for all floors including cost and conveyance with C.P. Grating fixing with white cement as per site requirements with standard practice for all floors including cost and conveyance
of all materials to site, labour charges etc., complete for finished item of work. of all materials to site, labour charges etc., complete for finished item of work.
6A Supplying and fixing 580 mm x 440 mm long Orissa pan white glazed Water Closet 1st qualityISI marked confirming to IS:2556-Part-3- Supplying and fixing 580 mm x 440 mm long Orissa pan white glazed Water Closet 1st qualityISI marked confirming to IS:2556-Part-3-
1981 with "P" or "S" trap Hindware / Parryware / Neycer with brick masonry seat, complete for finished item of work. 1981 with "P" or "S" trap Hindware / Parryware / Neycer with brick masonry seat, complete for finished item of work.
Basic rate as per ssr item TBSP-E.I-03 1.00 Nos 1584.00 1.00 Nos 1584.00 Basic rate as per ssr item TBSP-E.I-03 1.00 Nos 1313.98 1.00 Nos 1313.98
1584.00 1313.98
Add Contractor's profit 13.615% 215.66 Add Contractor's profit 13.615% 178.90
1799.66 1492.88
7 Supply, Installation and commissioning approved make floor mounted Close Coupled wash down EWC conforming to IS:2556 (Part 8)- Supply, Installation and commissioning approved make floor mounted Close Coupled wash down EWC conforming to IS:2556 (Part 8)-
2004 suit with 'P' or 'S' trap with dual flush porcelain cistern fixed on wash down EWC with all internal parts of dual flush cistern, ultra 2004 suit with 'P' or 'S' trap with dual flush porcelain cistern fixed on wash down EWC with all internal parts of dual flush cistern, ultra
solid seat cover of approved make with rubber buffer and cap & 15 mm angle stop cock & 450 mm long PVC inter connection pipe wall solid seat cover of approved make with rubber buffer and cap & 15 mm angle stop cock & 450 mm long PVC inter connection pipe wall
flanges all of approved make etc. complete for finished item of work in all respects: White Colour flanges all of approved make etc. complete for finished item of work in all respects: White Colour
Basic rate as per ssr item TBSP-E.II-04 1.00 Nos 9000.00 1.00 Nos 9000.00 Basic rate as per ssr item TBSP-E.II-04 1.00 Nos 7465.78 1.00 Nos 7465.78
labour charges TBSP-E.VIII-06 1.00 Nos 269.00 1.00 Nos 269.00 labour charges TBSP-E.VIII-06 1.00 Nos 269.00 1.00 Nos 269.00
9269.00 7734.78
Add Contractor's profit 13.615% 1261.97 Add Contractor's profit 13.615% 1053.09
Total cost (A +B) 10531.00 Total cost (A +B) 8788.00
S&F Stainless steel 4" dia round Grating with frame for nahany or floor trap cover with or without hole S&F Stainless steel 4" dia round Grating with frame for nahany or floor trap cover with or without hole
Basic rate as per ssr item TBSP-F.VII-26 1.00 Nos 63.00 1.00 Nos 63.00 Basic rate as per ssr item TBSP-E.II-04 1.00 Nos 52.26 1.00 Nos 52.26
Labour Charges TBSP-C.III-07 1.00 Nos 191.00 1.00 Nos 191.00 Labour Charges TBSP-C.III-07 1.00 Nos 158.44 1.00 Nos 158.44
254.00 210.70
Add Contractor's profit 13.615% 34.58 Add Contractor's profit 13.615% 28.69
Total cost (A +B) 289.00 Total cost (A +B) 240.00
Supplying & Fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-Part-4:1972 with waste fittings like rubber Supplying & Fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-Part-4:1972 with waste fittings like rubber
plug,
Basic chain,
rate as32 mm
per ssrnominal
item size C.P. Fitting with TBSP-E.VI-01
parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal bore plug,
Basic chain,
rate as32 mm
per ssrnominal
item size C.P. Fitting with parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal bore
TBSP-E.II-04
Chromium Plated Pillar Tap of 1st quality Indian make 400 grams complete 1.00 Nos CI2713.00
with standard 1.00wooden
brackets including Nos 2713.00
block: 550 x Chromium Plated Pillar Tap of 1st quality Indian make 400 grams complete with1.00 standard
Nos 2250.52 including1.00
CI brackets Nos block: 550
wooden 2250.52
x 400
400 mm - Single C.P. Pillar cock 2713.00 mm - Single C.P. Pillar cock 2250.52
Add Contractor's profit 13.615% 369.37 Add Contractor's profit 13.615% 306.41
Total cost (A +B) 3083.00 Total cost (A +B) 2557.00
8 Supplying & fixing Kitchen stainless steel sink size 20" x18" x 8 " (508x457.2x203.2mm) 1 mm thick with Polished black Kadapa slabs of Supplying & fixing Kitchen stainless steel sink size 20" x18" x 8 " (508x457.2x203.2mm) 1 mm thick with Polished black Kadapa slabs of
all sizes between 15 - 18mm thickness accessories and Kitchen with 3' hight brick work including plastering and platform slab 50mm all sizes between 15 - 18mm thickness accessories and Kitchen with 3' hight brick work including plastering and platform slab 50mm
thick including materails and Labour charges etc. completed for finished item of work. thick including materails and Labour charges etc. completed for finished item of work.
Polished black Kadapa slabs of all sizes Polished black Kadapa slabs of all
TBSC-B.I-06 1.56 Sqm 138.00 1.00 Sqm 215.28 TBSC-B.I-06 1.56 Sqm 131.43 1.00 Sqm 205.03
between 15 - 18mm thickness sizes between 15 - 18mm thickness
Brick work 0.28 Cum 5755.72 1.00 Cum 1623.11 Brick work 0.28 Cum 5714.70 1.00 Cum 1611.55
Precast Slab 50mm thick 0.10 Cum 6729.36 1.00 Cum 666.21 Precast Slab 50mm thick 0.10 Cum 6083.88 1.00 Cum 602.30
Plastering 5.64 Sqm 300.78 1.00 Sqm 1696.42 Plastering 5.64 Sqm 291.51 1.00 Sqm 1644.12
9597.02 8713.92
Add Contractor's profit 13.615% 734.67 Add Contractor's profit 13.615% 633.22
Total rate per 1 No 10331.69 Total rate per 1 No 9347.14
9 Supply and Fixing of AC Cowls 88.9 mn dia with all necessary requirements including all operational , incidental sales and other taxes Supply and Fixing of AC Cowls 88.9 mn dia with all necessary requirements including all operational , incidental sales and other taxes
and all labour charges etc., complete including cost and convenyance of all materials complete for finished item of work for all Floors. and all labour charges etc., complete including cost and convenyance of all materials complete for finished item of work for all Floors.
Basic rate as per ssr item TBSP-J.I-29 1.00 Nos 71.00 1.00 Nos 71.00 Basic rate as per ssr item TBSP-J.I-29 1.00 Nos 71.00 1.00 Nos 71.00
71.00 71.00
Add Contractor's profit 13.615% 9.67 Add Contractor's profit 13.615% 9.67
Total rate per 1 No 80.67 Total rate per 1 No 80.67
10 Supply & Fixing 4" dia (101.6 mm) CI Plug/ PVC (Door) bends 1st quality ISI marked conforming to IS : 1729-1979 with cement caulked Supply & Fixing 4" dia (101.6 mm) CI Plug/ PVC (Door) bends 1st quality ISI marked conforming to IS : 1729-1979 with cement caulked
joints and fixing as per site requirements with standard practice including cost and conveyance of all materials to site, all labour joints and fixing as per site requirements with standard practice including cost and conveyance of all materials to site, all labour charges,
charges, sales and other taxes on all materials etc., complete for finished item of work for all floors. sales and other taxes on all materials etc., complete for finished item of work for all floors.
Basic rate as per ssr item TBSP-C.II-05 1.00 Nos 455.00 1.00 Nos 455.00 Basic rate as per ssr item TBSP-C.II-05 1.00 Nos 396.00 1.00 Nos 396.00
455.00 396.00
Add Contractor's profit 13.615% 61.95 Add Contractor's profit 13.615% 53.92
Total rate per 1 No Total rate per 1 No
516.95 449.95
11 Supply and fixing of Ashirvad/Ajay/Astral Flowgaurd or equivalent CPVC pipes and fittings to meet the requirement of ASTM-D 2846 Supply and fixing of Ashirvad/Ajay/Astral Flowgaurd or equivalent CPVC pipes and fittings to meet the requirement of ASTM-D 2846 and
and are produced in CTS( copper tube sizes 1/4" to 2" ) ashirwad flowgaurd SDR11 and SDR 13.5 pipes are made from identical CPVC are produced in CTS( copper tube sizes 1/4" to 2" ) ashirwad flowgaurd SDR11 and SDR 13.5 pipes are made from identical CPVC
components having the same physical properties for Hot and cold Water confirming to (IS 15778-2007) components having the same physical properties for Hot and cold Water confirming to (IS 15778-2007)
12 Supply & Fixing of CI Plug bends 1st quality as per site requirements including cost & conveyance of all materials and labour charges Supply & Fixing of CI Plug bends 1st quality as per site requirements including cost & conveyance of all materials and labour charges
etc completed for Finished item for all floors. etc completed for Finished item for all floors.
75mm dia Pipe 75mm dia Pipe
Basic rate as per ssr item TBSP-C.II-04 1.00 Nos 367.00 1.00 Nos 367.00 Basic rate as per ssr item TBSP-C.II-04 1.00 Nos 321.99 1.00 Nos 321.99
Add Contractor's profit 13.615% 49.97 Add Contractor's profit 13.615% 43.84
Total rate per 1 No 416.97 Total rate per 1 No 365.83
13
Supply & Fixing of Plain Tee & Plug Tee of 110mm dia as per Site requirement including cost and conveyance of all material Supply & Fixing of Plain Tee & Plug Tee of 110mm dia as per Site requirement including cost and conveyance of all material
and labour charges etc completed. and labour charges etc completed.
110mm dia Pipe 110mm dia Pipe
Basic rate as per ssr item TBSP-H.II-27 1.00 Nos 130.00 1.00 Nos 130.00 Basic rate as per ssr item TBSP-H.II-27 1.00 Nos 110.00 1.00 Nos 110.00
Add Contractor's profit 13.615% 17.70 Add Contractor's profit 13.615% 14.98
Total rate per 1 No Total rate per 1 No
147.70 124.98
14 Supply & Fixing of Plain Bend 87.5 Degree of 110mm dia as per Site requirement including cost and conveyance of all Supply & Fixing of Plain Tee & Plug Tee of 110mm dia as per Site requirement including cost and conveyance of all material
material and labour charges etc completed. and labour charges etc completed.
110mm dia Pipe 110mm dia Pipe
Basic rate as per ssr item Basic rate as per ssr item TBSP-H.II-27
TBSP-H.II-12 1.00 Nos 83.00 1.00 Nos 83.00 1.00 Nos 70.23 1.00 Nos 70.23
Add Contractor's profit Add Contractor's profit
13.615% 11.30 13.615% 9.56
Total rate per 1 No 94.30 Total rate per 1 No 79.79
15 Supply and fixing CP finish brass towel rod 600 mm long and 20 mm dia with brackets Supply and fixing CP finish brass towel rod 600 mm long and 20 mm dia with brackets
Towel Rod 110mm dia Pipe
Basic rate as per ssr item TBSP-F.VII-11 1.00 Nos 1071.00 1.00 Nos 1071.00 Basic rate as per ssr item TBSP-H.II-27 1.00 Nos 906.24 1.00 Nos 906.24
Add Contractor's profit 13.615% 145.82 Add Contractor's profit 13.615% 123.38
Total rate per 1 No 1216.82 Total rate per 1 No 1029.62
16
Supplying & fixing SINGLE PANEL 3.0 mm thick PVC door with frame and shutters including cost and conveyance of all Supplying & fixing SINGLE PANEL 3.0 mm thick PVC door with frame and shutters including cost and conveyance of all
materials and labour charges etc., complet. materials and labour charges etc., complet.
17 Supply and fixing Aluminium Anodised Three Track Sliding Windows as per approved drawing with aluminium anodised
sections of Series C Jindal sections and outer frame top horizontals & both verticals of 8774 of size 62 x 29.5 mm and
A) MATERIAL REQUIREMENT
bottom horizontal - two track frame of 8773 of size 62 x 29.5 mm, Shutter frame top, bottom and verticals of 8304 of size
ALUMINIUM
50 mm x 20 mmSECTION
and Weather interlocking frame of 8306 of size 50 x 20 with plain clear float14.60
glasskgs
5 mm thick fixed 353.00 5153.80
including supply
GLAZING and fixing
with GLASS 8mm aluminium handles of 100 mm for each shutter, nylon rollers assembly and all labour charges
1.00 sqm 932.00 932.00
for fixing the fixtures with required no.of screws, bolts and nuts and including labour charges for fixing the frame in
SILICONfixing
position, SEALANT
shutter to frame etc. completed for finished item of work 0.50 kgs 233.00 116.50
RUBBER BEADING 4.00 Rmt 2.00 8.00
Nylon rollers 6.00 Nos 15.00 90.00
Alum.Anodised.PC Handles 2.00 each 45.00
Supply of 7.5mm thick Aluminium Grill 1.00 sqm 1112.00 1112.00
B) LABOUR CHARGES
1st Class Carpenter 0.347 No 415.00 144.01
2nd Class Carpenter 1.042 No 370.00 385.54
Power Saw Cutter - Hand Operated - Operator 0.347 No 415.00 144.01
Power Drill - Hand Operated - Operator 0.347 No 415.00 144.01
Unskilled Mazdoor 1.042 No 310.00 323.02
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges 2.778 hrs 22.50 62.51
Power Drill - Hand Operated - Hire Charges 2.778 hrs 22.50 62.51
Supervision Charges 0.347 No 590.00 204.73
8882.62
Power charges for Motors 1%
8882.62
18 Supply and fixing Aluminium Anodised ventilators as per approved drawing with aluminium anodised sections and
Weather interlocking frame with plain clear float glass 8 mm thick fixed including all labour charges for fixing the fixtures
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION 8.20 kgs 353.00 2894.60
GLAZING with GLASS 8mm 1.00 sqm 932.00 932.00
SILICON SEALANT 0.50 kgs 233.00 116.50
RUBBER BEADING 4.00 Rmt 2.00 8.00
B) LABOUR CHARGES
1st Class Carpenter 0.347 No 415.00 144.01
2nd Class Carpenter 1.042 No 370.00 385.54
Power Saw Cutter - Hand Operated - Operator 0.347 No 415.00 144.01
Power Drill - Hand Operated - Operator 0.347 No 415.00 144.01
Unskilled Mazdoor 1.042 No 310.00 323.02
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges 2.778 hrs 22.50 62.51
Power Drill - Hand Operated - Hire Charges 2.778 hrs 22.50 62.51
Supervision Charges 0.347 No 590.00 204.73
5421.42
Power charges for Motors 1% 0.00
5421.42
add Contractors profit @ 13.615% 738.13
6159.55 sqm
19 Supply, delivery and fixing of teak wood frames with hard board laminated shutters including ironmongery and fixtures etc, cost and
conveyance of all materials and labour charges etc., complete - for doors of size
CBR door - Frames 0.90 x 2.08m CBR door - Frames 0.90 x 2.08m
verticals 2 6' 10'' 3'' 4'' 1.139 verticals 2 6' 10'' 3'' 4'' 1.139
Horizontals 1 2' 11" 3'' 4'' 0.243 Horizontals 1 2' 11" 3'' 4'' 0.243
1.382 cft 3903.73 5394.74 1.382 cft 3485.47 4816.73
MDF Board: exterior-30 mm thick MDF Board: exterior-30 mm thick
1 0.90 2.08 1.872 sqm 2013.00 3768.34 1 0.90 2.08 1.872 sqm 1797.32 3364.59
Ironmongery Ironmongery
Brass Tower bolts - 150mm long 1 No. 260.00 260.00 Brass Tower bolts - 150mm long 1 No. 220.00 220.00
Brass butt 5" long hinges 3 No. 290.00 870.00 Brass butt 5" long hinges 3 No. 245.39 736.17
6" long handles 2 No. 335.00 670.00 6" long handles 2 No. 283.47 566.93
12" long aldrops 1 No. 1284.00 1284.00 12" long aldrops 1 No. 1086.48 1086.48
10" long latch 1 No. 644.00 644.00 10" long latch 1 No. 544.93 544.93
10" long anchor bolts 6 No. 100.00 0.00 10" long anchor bolts 6 No. 84.62 0.00
Labour charges 1.872 m2 1183.00 2214.58 Labour charges 1.872 m2 1183.00 2214.58
15105.66 13550.41
add contractor profit 13.615% 2056.64 add contractor profit 13.615% 1844.89
17162.30 each 15395.30
MBR door - Frames 1.03 x 2.08m
verticals 2 7' 00'' 3'' 4'' 1.167
Horizontals 1 3' 5" 3'' 4'' 0.285
1.451 cft 3903.73 5665.83
MDF Board: exterior-30 mm thick
1 1.03 2.08 2.1424 sqm 2013.00 4312.65
Ironmongery
Brass Tower bolts - 150mm long 1 No. 260.00 260.00
Brass butt 5" long hinges 3 No. 290.00 870.00
6" long handles 2 No. 335.00 670.00
12" long aldrops 1 No. 1284.00 1284.00
10" long latch 1 No. 644.00 644.00
Labour charges 2.142 m2 1183.00 2534.46
16240.94
add contractor profit 13.615% 2211.20
18452.14 each
Ref S No Description Qty Unit Qty Unit Rate Rs. Amount Rs.
1 2 3 4 5 6 7 8 9
Supply and Fixing of ISI 25mm outer dia heavygrade, FRLS with IS:9537 part 3 regid PVC pipe. concealed in Roof Slabs
with all required accessories including masonary work and labour charges etc., complete. Makes : Sudhakar / GM /
1 14-15-6.1.1 Modi / AKG / VIP /
Million Plast.
a) Labour charges :
TBSE- 8.1.73 1 Skilled Electrician 2 day 1 day 440.00 880.00
TBSE - 8.1.74 2 Semi skilled Electrician 2 day 1 day 375.00 750.00
TBSE - 8.1.81 3 Helpers 1 day 1 day 345.00 345.00
Labour rate per 100 mtr 1975.00
Labour rate per 1 mtr 19.70
b) Material
Supply of PVC Junction Baxes deep size 25mm
TBSE - 1.2.32 4 12 No 1 No 25.00 300.00
Supply of 25/20mm MS Junction deep box
TBSE - 1.1.11 5 12 No 1 No 39.00 468.00
Supply of 25mm dia 1.5mm thick PVC Bend of
TBSE - 1.2.37 6 Sudhakar Make 12 No 1 No 6.00 72.00
Earthwork in excavation for structures as per drawing and technical specifications Clause
305.1 including setting out, construction of shoring and bracing, removal of stumps and
1 03/May/19 other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom
and backfilling in trenches with excavated suitable material as per Technical Specification
305 MORD / 304 MORTH ordianry gravelly soils for foundations .
Removal of Hard rock by Machine which require blasting such as hard rock, sheet rock and
2 boulders for Structures including cost and conveyance of all material and labour charges
etc completed
Columns footings 1226 2 1 6.0 2.3 2.3 0.60 19.04
07/May/19 19.04 Cum 443.92 1 Cum 8452.00 432.80 8240.00 212.00 0 0 988.8
3 CC(1:4:8) using 40 mm HG metal icluding all cost and conveyance of all materials labour
charges etc completed as per standard specification. For foundation & leveling course
VRCC (1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
4 materials,but excluding the cost of the steel etc complete for Columns footing.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
5 materials,but excluding the cost of the steel etc complete for Columns upto Ground Level.
6 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
materials,but excluding the cost of the steel etc complete for Plinth Beams
8 Construction of Randam rubble stone masonry in CM(1:6) 2nd sort including cost and
conveyance of all materials and labour charges ,seigniorage charges etc complete.
First Footing
Center line length 1226 6 1 1 43.56 0.60 1.00 26.14
Short Wall at balcony 1226 6 1 6 1.43 0.60 1.00 5.15
Short wall at front 1226 6 1 2 0.83 0.60 1.00 1.00
Deduction of rectangular raft 1226 6 1 11 1.75 0.60 0.30 -3.47
Deduction of trapezoidal raft 1226 6 1 11 1.01 0.60 0.25 -1.67
Deduction of columns 1226 6 1 10 0.23 0.45 0.45 -0.47
1226 6 26.68
Second Footing 1226 6
Center line length 1226 6 1 1 43.52 0.45 0.90 17.63
Short Wall at balcony 1226 6 1 6 1.43 0.45 0.90 3.47
Short wall at front 1226 6 1 2 0.83 0.45 0.90 0.67
Deduction of columns 1226 6 1 10 0.23 0.45 0.90 -0.93
20.84
18/May/19 47.52 Cum 4001.65 1 Cum 190158.00 3841.70 182558.00 7600.00 0 0 21906.96
Providing & filling gravel/morrum soil (CNS Soil) for foundation including braking
9 clouds,spreading in laying of 0-15 cm watering including all etc complete
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
11 materials,but excluding the cost of the steel etc complete for Columns Upto Ground Slab.
10/Jun/19 Columns 1226 12 1 18 0.23 0.45 2.55 4.75 Cum 10716.48 1 Cum 50910.00 10070.98 47844.00 3066.00 0 0 5741.28
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
12 materials,but excluding the cost of the steel etc complete for Beams for Ground Floor
Slab&Middle Beam for stair casing
Long Beams 1226 25 1 3 14.99 0.23 0.30 3.10
Long Beams-FFB3 1226 25 1 1 14.99 0.15 0.30 0.67
Short Beams 1226 25 1 6 8.96 0.23 0.30 3.71
Middle Beam for stair case 1226 25 1 1 2.4 0.23 0.43 0.23
Deductions 1226 25 1 12 0.23 0.23 0.30 -0.19
Deductions-FFB3 1226 25 1 4 0.15 0.23 0.30 -0.04
13/Jul/19 1226 25 1 7.49 Cum 11173.72 1 Cum 83688.00 10528.22 78853.00 4835.00 0 0 9462.36
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
13
materials,but excluding the cost of the steel etc complete for Slabs 125mm thick
09/Jul/19 Columns 1226 21 1 18 0.23 0.45 2.55 4.75 Cum 11102.95 1 Cum 52746.00 10457.45 49680.00 3066.00 0 0 5961.6
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
15 materials,but excluding the cost of the steel etc complete for Beams for Terrace Floor
Slab.
Long Beams 1226 19 1 3 14.99 0.23 0.30 3.10
Long Beams-FFB3 1226 19 1 1 14.99 0.15 0.30 0.67
Short Beams 1226 19 1 6 8.96 0.23 0.30 3.71
Deductions 1226 19 1 12 0.23 0.23 0.30 -0.19
Deductions-FFB3 1226 19 1 4 0.15 0.23 0.30 -0.04
25/Jun/19 7.26 Cum 11822.82 1 Cum 85776.00 11177.32 81092.00 4684.00 0 0 9731.04
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
16 materials,but excluding the cost of the steel etc complete for Roof Slab for 1st Floor.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
17
materials,but excluding the cost of the steel etc complete for Columns for Water Tank.
13/Aug/19 Columns 1226 37 1 4 0.23 0.45 0.40 0.17 Cum 11102.95 1 Cum 1839.00 10457.45 1732.00 107.00 0 0 207.84
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
18 materials,but excluding the cost of the steel etc complete for Beams for Water Tank.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
19
materials,but excluding the cost of the steel etc complete for Bottom Slab for Water Tank.
28/Aug/19 slab 150mm thick 1226 40 1 1 3.51 2.86 1.00 10.04 sqm 15338.12 10 sqm 15397.00 14369.87 14425.30 971.70 0 0 1731.036
20 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
materials,but excluding the cost of the steel etc complete for Side wall for Water Tank.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
21 materials,but excluding the cost of the steel etc complete for Top Slab for Water Tank.
Brick Masonry with CM(1:6) using Second Class Bricks including cost and conveyance of all
22 the materials etc complete for Ground Floor upto First Floor Roof Beam
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
26
materials,but excluding the cost of the steel etc complete for Stair Case Landing.
Brick Masonry with CM(1:6) using Second Class Bricks including cost and conveyance of all
28 the materials etc complete for First Floor to Terrace Bottom
Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm thick and
29 second coat in CM(1:3) prop 4mm thick including cost and conveyance of all materials and
labour charges etc., complete for Ground Floor Inside
Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm thick and
30 second coat in CM(1:3) prop 4mm thick including cost and conveyance of all materials and
labour charges etc., complete for Ground Floor Outside
Alround Building
long wall 1226 53 1 4 10.57 3 1 126.84
short wall 1226 53 1 4 6.52 3 1 78.24
Lintel Beam 1 Sunshade Top & Bottom 1226 53 1 14 1.2 0.6 1 10.08
Lintel Beam 1 Sunshade Sides 1226 53 1 14 0.6 0.087 1 0.73
Lintel Beam 2 Sunshade Top & Bottom 1226 53 1 4 1.2 0.6 1 2.88
Lintel Beam 2 Sunshade Sides 1226 53 1 4 0.6 0.087 1 0.21
Lintel Beam 3 Sunshade Top & Bottom 1226 53 1 4 0.6 1 1 2.40
Lintel Beam 3 Sunshade Sides 1226 53 1 4 0.6 0.087 1 0.21
Staircase flight 1&2 1226 54 1 4 2.55 1.2 1 12.24
Landing 1226 54 1 2 1.2 2.4 1 5.76
Open Area slab bottom 1226 54 1 2 15 1 1 30.00
Deductions 54
Door D1 1226 54 1 4 0.9 2.1 -1 -7.56
Door MD 1226 54 1 2 0.9 2.1 -1 -3.78
Windows W1 1226 54 1 2 1.2 1.2 -1 -2.88
Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm thick and
31 second coat in CM(1:3) prop 4mm thick including cost and conveyance of all materials and
labour charges etc., complete for First Floor inside
Middle Bed Room
short side wall 1226 55 1 4 3.05 2.55 1 31.11
Long side wall 1226 55 1 4 3.05 2.55 1 31.11
Slab 1226 55 1 2 3.05 3.05 1 18.61
Bed Room 55
short side wall 1226 55 1 4 3.05 2.55 1 31.11
Long side wall 1226 55 1 4 2.90 2.55 1 29.58
Slab 1226 55 1 2 3.05 2.9 1 17.69
Balcony-1 55
short side wall 1226 55 1 4 1.50 2.55 1 15.30
Long side wall-1 1226 55 1 2 3.05 2.55 1 15.56
Long side wall-2 1226 55 1 2 3.05 1.5 1 9.15
Slab 1226 55 1 2 1.50 3.05 1 9.15
Balcony-2
short side wall 1226 56 1 4 1.50 2.55 1 15.30
Long side wall-1 1226 56 1 2 2.78 2.55 1 14.18
Long side wall-2 1226 56 1 2 2.78 1.50 1 8.34
Slab 1226 56 1 2 1.50 2.78 1 8.34
Kitchen 56
short side wall 1226 56 1 4 1.80 2.55 1 18.36
Long side wall 1226 56 1 4 3.05 2.55 1 31.11
Slab 1226 56 1 2 3.05 1.8 1 10.98
Living & Dining 56
short side wall 1226 56 1 4 3.05 2.55 1 31.11
Long side wall 1226 56 1 4 4.15 2.55 1 42.33
Slab 1226 56 1 2 3.05 4.15 1 25.32
Varanda 56
short side wall 1226 56 1 4 2.28 2.55 1 23.26
Long side wall 1226 56 1 2 2.78 2.55 1 14.18
Slab 1226 56 1 2 2.28 2.78 1 12.68
Toilet
short side wall 1226 57 1 8 1.80 2.55 1 36.72
Long side wall-1 1226 57 1 8 1.20 2.55 1 24.48
Long side wall-2 1226 57 1 2 2.63 2.55 1 13.41
Slab 1226 57 1 4 1.80 1.2 1 8.64
Open Portion 57
short wall 1226 57 1 2 1.02 2.55 1 5.18
Deductions 57
Door D1 1226 57 1 10 0.90 2.1 -1.00 -18.90
Door MD 1226 57 1 2 0.90 2.1 -1.00 -3.78
Door D2 1226 57 1 4 0.75 1.8 -1.00 -5.40
Windows W1 1226 57 1 2 1.20 1.2 -1.00 -2.88
W2 1226 58 1 6 0.90 1.2 -1.00 -6.48
W3 1226 58 1 2 0.90 0.6 -1.00 -1.08
W4 1226 58 1 2 0.45 0.6 -1.00 -0.54
Ventilators 1226 58 1 4 0.60 0.3 -1.00 -0.72
24/Oct/19 Total 512.48 sqmt 3110.91 10 sqmt 159429.00 3025.93 155073.90 4355.10 0 0 18608.868
Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm thick and
32 second coat in CM(1:3) prop 4mm thick including cost and conveyance of all materials and
labour charges etc., complete for First Floor Outside
Alround Building
long wall 1226 59 1 4 10.57 3 1 126.84
short wall 1226 59 1 4 6.52 3 1 78.24
Lintel Beam 1 Sunshade Top & Bottom 1226 59 1 14 1.2 0.6 1 10.08
Lintel Beam 1 Sunshade Sides 1226 59 1 14 0.6 0.087 1 0.73
Lintel Beam 2 Sunshade Top & Bottom 1226 59 1 4 1.2 0.6 1 2.88
Lintel Beam 2 Sunshade Sides 1226 59 1 4 0.6 0.087 1 0.21
Lintel Beam 3 Sunshade Top & Bottom 1226 59 1 4 0.6 1 1 2.40
Lintel Beam 3 Sunshade Sides 1226 59 1 4 0.6 0.087 1 0.21
Door MD -1 1226 59 1 -2 0.9 0.23 1 -0.41
Door MD -2 1226 60 1 -4 0.23 2.1 1 -1.93
Door D1 Side1 1226 60 1 -4 0.9 0.23 1 -0.83
Door D1 Side2 1226 60 1 -8 0.23 2.1 1 -3.86
Window W 1226 60 1 -8 1.2 0.23 1 -2.21
W1 Side -1 1226 60 1 -12 0.9 0.23 1 -2.48
W1 Side -2 1226 60 1 -12 0.23 1.2 1 -3.31
W2 Side -1 1226 60 1 -4 0.9 0.23 1 -0.83
W2 Side -2 1226 60 1 -4 0.23 0.6 1 -0.55
W3 Side -1 1226 60 1 -4 0.45 0.23 1 -0.41
W3 Side -2 1226 60 1 -4 0.23 0.6 1 -0.55
Ventilator- side-1 1226 60 1 -8 0.6 0.23 1 -1.10
Ventilator- side-2 1226 60 1 -8 0.23 0.3 1 -0.55
Open Area slab bottom 1226 60 1 2 12.6 1.01 1 25.45
Water tank inside wall-1 1226 61 1 2 3.28 1.5 1 9.84
Water tank inside wall-2 1226 61 1 2 2.63 1.5 1 7.89
Water tank inside Slab 1226 61 1 1 3.28 2.63 1 8.63
Water tank Outside wall-1 1226 61 1 2 3.58 1.65 1 11.81
Water tank Outside wall-2 1226 61 1 2 2.93 1.65 1 9.67
Water tank Outside Slab 1226 61 1 1 3.58 2.93 1 10.49
07/Nov/19 1226 61 286.33 sqmt 3110.91 10.00 sqmt 89073.00 3025.93 86640.00 2433.00 0 0 10396.8
forspetic tank
Inner wall 1226 83 1 1 7.000 1 1.8 12.60
Partition wall 1226 83 1 2 1.500 1 1.5 4.50
Bottom Slab 1226 83 1 1 2.000 1 1.5 3.00
Outer side 1226 83 1 1 4.420 1 0.3 1.33
Top slab 1226 83 1 1 2.460 1 1.96 4.82
04/Dec/19 26.25 sqmt 3029.33 10.00 sqmt 7951.00 2944.35 7728.20 222.80 0 0 927.384
Snowcem paint two coats including cost and conveyence etc complete. For Ground Floor
33
inside
Middle Bed Room
short side wall 1226 62 1 4 3.05 2.875 1 35.08
Long side wall 1226 62 1 4 3.05 2.875 1 35.08
Slab 1226 62 1 2 3.05 3.05 1 18.61
Bed Room 62
short side wall 1226 62 1 4 3.05 2.875 1 35.08
Long side wall 1226 62 1 4 2.90 2.875 1 33.35
Slab 1226 62 1 2 3.05 2.9 1 17.69
Balcony-1 62
short side wall 1226 62 1 4 1.50 2.875 1 17.25
Long side wall-1 1226 62 1 2 3.05 2.875 1 17.54
Long side wall-2 1226 63 1 2 3.05 1.5 1 9.15
Slab 1226 63 1 2 1.50 3.05 1 9.15
Balcony-2 63
short side wall 1226 63 1 4 1.50 2.875 1 17.25
Long side wall-1 1226 63 1 2 2.78 2.875 1 15.99
Long side wall-2 1226 63 1 2 2.78 1.50 1 8.34
Slab 1226 63 1 2 1.50 2.78 1 8.34
Kitchen 63
short side wall 1226 63 1 4 1.80 2.875 1 20.70
Long side wall 1226 63 1 4 3.05 2.875 1 35.08
Slab 1226 63 1 2 3.05 1.8 1 10.98
Living & Dining 63
34 Snowcem paint two coats including cost and conveyence etc complete. For Ground Floor
Outside
Alround Building
long wall 1226 66 1 4 10.57 3 1 126.84
short wall 1226 66 1 4 6.52 3 1 78.24
Lintel Beam 1 Sunshade Top & Bottom 1226 66 1 14 1.2 0.6 1 10.08
Lintel Beam 1 Sunshade Sides 1226 66 1 14 0.6 0.087 1 0.73
Lintel Beam 2 Sunshade Top & Bottom 1226 66 1 4 1.2 0.6 1 2.88
Lintel Beam 2 Sunshade Sides 1226 66 1 4 0.6 0.087 1 0.21
Lintel Beam 3 Sunshade Top & Bottom 1226 66 1 4 0.6 1 1 2.40
Lintel Beam 3 Sunshade Sides 1226 66 1 4 0.6 0.087 1 0.21
Staircase flight 1&2 1226 67 1 4 2.55 1.2 1 12.24
Landing 1226 67 1 2 1.2 2.4 1 5.76
Open Area slab bottom 1226 67 1 2 15 1 1 30.00
Deductions
Door D1 1226 68 1 4 0.9 2.1 -1 -7.56
Door MD 1226 68 1 2 0.9 2.1 -1 -3.78
Windows W1 1226 68 1 2 1.2 1.2 -1 -2.88
Windows W2 1226 68 1 6 0.9 1.2 -1 -6.48
Windows W3 1226 68 1 2 0.9 0.6 -1 -1.08
Windows W4 1226 68 1 2 0.45 0.6 -1 -0.54
Ventilators 1226 68 1 4 0.6 0.3 -1 -0.72
Sq.mt
17/Nov/19 779.05 1029.90 10.00 sqmt 80234.00 1029.90 80234.10 -0.10 0 0 9628.092
s.
35 Snowcem paint two coats including cost and conveyence etc complete. For 1st Floor inside
Snowcem paint two coats including cost and conveyence etc complete. For 1st Floor
36
Outside
Alround Building
long wall 1226 73 1 4 10.57 3 1 126.84
short wall 1226 73 1 4 6.52 3 1 78.24
Lintel Beam 1 Sunshade Top & Bottom 1226 73 1 14 1.2 0.6 1 10.08
Lintel Beam 1 Sunshade Sides 1226 73 1 14 0.6 0.087 1 0.73
Lintel Beam 2 Sunshade Top & Bottom 1226 73 1 4 1.2 0.6 1 2.88
Lintel Beam 2 Sunshade Sides 1226 73 1 4 0.6 0.087 1 0.21
Lintel Beam 3 Sunshade Top & Bottom 1226 73 1 4 0.6 1 1 2.40
Lintel Beam 3 Sunshade Sides 1226 73 1 4 0.6 0.087 1 0.21
Open Area slab bottom 1226 74 1 2 12.6 1.01 1 25.45
Water tank Outside wall-1 1226 74 1 2 3.58 1.65 1 11.81
Water tank Outside wall-2 1226 74 1 2 2.93 1.65 1 9.67
Water tank Outside Slab 1226 74 1 1 3.58 2.93 1 10.49
Deductions
Door D1 1226 75 1 4 0.9 2.1 -1 -7.56
Door MD 1226 75 1 2 0.9 2.1 -1 -3.78
Windows W1 1226 75 1 2 1.2 1.2 -1 -2.88
Windows W2 1226 75 1 6 0.9 1.2 -1 -6.48
Flooring with CC(1:4:8) using 40mm HBG metal for 100mm thick and Top plastering with
37
CM(1:3) ,20mm thick including cost and conveyance of all the materials ect complete.
Flooring with Vetrified tiles of 1st Quality set over base coat white cement paste with full
38 depth mixed with pegment of matching shade including cost of all materials etc complete
including seignorage charges etc complete .
Ground Floor
M.Bed Room 1226 76 1 2 3.05 3.05 18.605
Bed Room 1226 76 1 2 2.90 3.05 17.69
Liv/Din Room 1226 76 1 2 4.15 3.05 25.315
Kitchen 1226 76 1 2 2.0 1.80 7.2
Toilets 1226 76 1 4 1.8 1.20 8.64
Balcony-1 1226 76 1 2 3.05 1.50 9.15
Balcony-2 1226 77 1 2 2.78 1.50 8.34
Varanda 1226 77 1 2 2.28 2.70 12.312
Kitchen Wall 1226 77 1 2 3.20 0.90 5.76
Toilets Side wall 1226 77 1 16 1.80 1.80 51.84
Deduction Door (.750 X 1.80) 1226 77 1 16 0.90 2.10 -30.24
22/Nov/19 134.61
First Floor
M.Bed Room 1226 79 2 3.05 3.05 18.605
Bed Room 1226 79 2 2.90 3.05 17.69
Liv/Din Room 1226 79 2 4.15 3.05 25.315
Kitchen 1226 79 2 2.0 1.80 7.2
Toilets 1226 79 4 1.8 1.20 8.64
Balcony-1 1226 79 2 3.05 1.50 9.15
Balcony-2 1226 79 2 2.78 1.50 8.34
Varanda 1226 80 2 2.28 2.70 12.312
Kitchen Wall 1226 80 2 3.20 0.90 5.76
Toilets Side wall 1226 80 16 1.80 1.80 51.84
Deduction Door (.750 X 1.80) 1226 80 16 0.90 2.10 -30.24
134.61
28/Nov/19 269.22 Sq.mts. 10600.59 10 Sq.mts. 285393.00 8969.87 241490.40 43902.60 0 0 28978.848
39 Supply and placing of the HYSD bars, fabrication including cost and conveyance of all the
materials etc complete.
16/Sep/19 13.10 MT 51392.60 1 MT 673064.00 43999.30 576238.00 96826.00 0 0 69148.56
Manufacturing supplying and erection off SS Hand Railingfabrication for varandha including
37
c/c of all labour charges complete.
Ground Floor
Balcony-1 1226 78 1 2 3.05 6.10
Balcony-2 1226 78 1 2 2.78 5.56
Varanda 1226 78 1 1 19.03 19.03
26/Nov/19 30.69 Rmt 3100 1 Rmt 95139.00 2627.12 80626.00 14513.00 0 0 9675.12
Supply, delivery and fixing of teak wood frames with hard board laminated shutters
including ironmongery and fixtures etc, cost and conveyance of all materials and labour
charges etc., complete - for doors of size
12/Dec/19 Doors of size 0.9m X 2.05m 1226 97 1 24 24.00 No.s 17162.30 1 No.s 411895.00 15395.30 369487.20 42407.80 0 0 44338.464
Supplying & fixing SINGLE PANEL 3.0 mm thick PVC door with frame and shutters including
cost and conveyance of all materials and labour charges etc., complet.
12/Dec/19 For Bathroom doors 1226 97 1 8 8.00 No.s 3067.61 1 No.s 24541.00 2595.71 20765.68 3775.32 0 0 2491.8816
Supply and fixing Aluminium Anodised Three Track Sliding Windows as per approved
drawing with aluminium anodised sections of Series C Jindal sections and outer frame top
horizontals & both verticals of 8774 of size 62 x 29.5 mm and bottom horizontal - two track
frame of 8773 of size 62 x 29.5 mm, Shutter frame top, bottom and verticals of 8304 of size
50 mm x 20 mm and Weather interlocking frame of 8306 of size 50 x 20 with plain clear
float glass 5 mm thick fixed including supply and fixing aluminium handles of 100 mm for
each shutter, nylon rollers assembly and all labour charges for fixing the fixtures with
required no.of screws, bolts and nuts and including labour charges for fixing the frame in
position, fixing shutter to frame etc. completed for finished item of work.
Supply and Fixing of 110 mm dia 3 M Single Socket PVC/SWR pipe -6 Kg/sq.cm with all
06/Dec/19 required accessories including fixing and labour charges etc
06/Dec/19 84 1 2 3 6.00 Rmt 262.85 1 Rmt 1577.00 234.85 1409.00 168.00 0 0 169.08
b 110 mm dia - Single Tee with Door - UPVC/SWR Pipe fittings
06/Dec/19 84 1 4 4 16.00 Nos 147.70 1 Nos 2363.00 124.98 2000.00 363.00 0 0 240
c 110 mm dia - Plain Bend 87.5 Degree - UPVC/SWR Pipe fittings
06/Dec/19 84 1 4 4 16.00 Nos 94.30 1 Nos 1509.00 79.79 1277.00 232.00 0 0 153.24
d Supply and Fixing of 90 mm dia 3 M Single Socket PVC/SWR pipe -6 Kg/sq.cm with all
required accessories including fixing and labour charges etc
06/Dec/19 84 1 4 4 16.00 Rmt 232.95 1 Rmt 3727.00 209.45 3351.00 376.00 0 0 402.12
Supply and Fixing of CPVC pipe (ISI MARK) with all required accessories including fixing
and labour charges etc.
06/Dec/19 22.2 mm CPVC Pipe (TBSP-J.III-02) 85 1 1 12 12.00 Rmt 181.78 1 Rmt 2181.00 156.79 1881.00 300.00 0 0 225.72
06/Dec/19 28.6 mm CPVE Pipe (TBSP-J.III-03) 85 1 1 12 12.00 Rmt 240.86 1 Rmt 2890.00 207.92 2495.00 395.00 0 0 299.4
Supplying & fixing CPVC ball Valve as per IS I-class heavy duty as approved by the Engineer
including cost & conveyance of all materials, labour charges, etc. complete for finished
item of work in all floors as directed by Engineer-in-charge
06/Dec/19 85 1 1 3 3.00 Nos 328.35 1 Nos 985.00 285.17 856.00 129.00 0 0 102.72
Supplying & Fixing Orissa Pan White glazed W.C 1st quality ISI marked conforming to
IS:2556-Part-3-1981 with "P" or "S" trap Hindware/ Parryware/ Neycer - ISI Mark: 580 mm
x 440 mm duly providing constructing Brick masonry seat using 2nd class bricks, CC
Squatting plate in P.C.C 1:2:4, S&F PVC Low level system with internal components & short
bend: 10 Litres capacity Single Flush, S&F of 15 mm brass angle stop valve of quarter turn
spindle type of not less than 400 grams weight with internal threaded conforming to IS
8931 and S&F 15 mm nominal size PVC connection with brass union nut C.P coated
including cost and conveyance of all materials and labour charges, overheads and
contractor's profit etc.,. complete as per standard practice for finished item of work.
06/Dec/19 86 1 4 1 4.00 Nos 1799.66 1 Nos 7199.00 1,492.88 5972.00 1227.00 0 0 716.64
S&F of 15 mm brass body CP finish bib tap of not less than 300 grams weight with quarter
turn spindle with either internal or external threaded connection conforming to IS 8931
06/Dec/19 87 1 4 7 28.00 Nos 278.40 1 Nos 7795.00 243.15 6808.00 987.00 0 0 816.96
Supply, Installation and commissioning approved make floor mounted Close Coupled wash
down EWC conforming to IS:2556 (Part 8)-2004 suit with 'P' or 'S' trap with dual flush
porcelain cistern fixed on wash down EWC with all internal parts of dual flush cistern, ultra
solid seat cover of approved make with rubber buffer and cap & 15 mm angle stop cock &
450 mm long PVC inter connection pipe wall flanges all of approved make etc. complete
for finished item of work in all respects: Coloured - Grade - I/Grade - II
06/Dec/19 87 1 4 1 4.00 Nos 10531.00 1 Nos 42124.00 8,788.00 35152.00 6972.00 0 0 4218.24
S&F Stainless steel 4" dia round Grating with frame for nahany or floor trap cover with or
without hole
06/Dec/19 88 1 4 1 4.00 Nos 10331.69 1 Nos 41327.00 9,347.14 37389.00 3938.00 0 0 4486.68
Supply and fixing CP finish brass towel rod 600 mm long and 20 mm dia with brackets
06/Dec/19 89 1 4 1 4.00 Nos 1216.82 1 Nos 4867.00 1,029.62 4118.00 749.00 0 0 494.16
Electrical
Supply and Fixing of ISI 25mm outer dia heavygrade, FRLS with IS:9537 part 3
regid PVC pipe. concealed in Roof Slabs with all required accessories
10/Dec/19 including masonary work and labour charges etc., complete.
10/Dec/19 90 1 1 61.75 61.75 Rmt 62.895 1 Rmt 3884.00 56.47 3487.00 397.00 0 0 418.44
Supply and Fixing of ISI 25mm outer dia mediumgrade, FRLS with IS:9537
part 3 regid PVC pipe. concealed in wall with all required accessories
including masonary work for light, fan and separate plug point with 8 or 9
Module Hot dip galvanized Metal Box including all labour charges etc.,
complete.
10/Dec/19 90 1 4 39.19 156.76 Rmt 57.17243 1 Rmt 8962.00 54.68 8572.00 390.00 0 0 1028.64
Supply of 14/0.3mm (1.0 Sqmm) FRLS / HFFR PVC insulated 1100V grade as
per IS:694/1990 two run of flexible copper wire for earthing in existing PVC
conduit pipe for circuit mains including labour charges (phase neutral and
earth) etc., complete as required for switch board circuit mains.
10/Dec/19 91 1 4.00 39.19 156.76 Rmt 18.74117 1 Rmt 2938.00 16.88 2646.00 292.00 0 0 317.52
Supply and run of 2 of 36/0.3 mm ( 2.5 sq.mm) FRLS / HFFR PVC insulated
1100 V grade as per IS: 694 / 1990 specifications for flexible copper cable
and for earthing in existing PVC conduit pipe for circuit mains including
labour charges (phase neutral and earth) etc., complete as required for
switch board circuit mains.
10/Dec/19 91 1 4.00 43.95 175.80 Rmt 37.363725 1 Rmt 6569.00 32.97 5797.00 772.00 0 0 695.64
Supply and run of 2 of 22/0.3 mm ( 1.5 sq.mm) FRLS / HFFR PVC insulated
1100 V grade as per IS: 694 / 1990 specifications for flexible copper cable
and for earthing in existing PVC conduit pipe for circuit mains including
supply & fixing of Gold medalof 3 plastic jumbo ceilling rose 6A isi mark flush
type switch on exisiting decolam board including all labour charges etc.,
10/Dec/19 complete. 91 1 4.00 31.46 125.84 Rmt 24.719366 1 Rmt 3111.00 21.97 2764.00 347.00 0 0 331.68
Supply and run of 2 of 4 Sq mm F.R L.S. / HFFR P.V.C. insulated flexible
copper cable 1100 V grade as per IS: 694 / 1990 specifications and 1 run of
2.50 Sq mm F.R L.S. / HFFR P.V.C. insulated flexible copper cable 1100 V
grade as per IS: 694 / 1990 specifications in the existing conduit pipe for run
of mains from main panel board to TPN DB'S with pin type lugs and
connection
10/Dec/19 92 1 1.00 95.00 95.00 Rmt 53.025905 1 Rmt 5037.00 46.31 4399.00 638.00 0 0 527.88
Supply of 1200 mm (48") sweep 5star rating ISI Mark Ceiling Fan as per IS
374 -1979 and 230V, A.C 50 Hz.Ceiling fan with 3 Blades and double ball
bearings with all standard accessories.
10/Dec/19 92 1 4.00 3.00 12.00 Nos 2257.29 1 Nos 27087.00 2036.44 24437.00 2650.00 0 0 2932.44
Supply and fixing of Modular type Stepped electronic regulator with
connections and Labour charges etc complete. (Data No.23.1.5)
10/Dec/19 92 1 4.00 3.00 12.00 Nos 537.39895 1 Nos 6449.00 511.81 6142.00 307.00 0 0 737.04
Supply and fixing of Modular cover frames Makes : Legrand Myrius / Cabtree
Thames Platinum / Million Logus / Gold Medal Curve / Anchor Roma viola /
CPL. vide page no:20
10/Dec/19 MODULAR- 4 93 1 4.00 2.00 8.00 Nos 109.07 1 Nos 873.00 103.88 831.00 42.00 0 0 99.72
10/Dec/19 MODULAR- 8 93 1 4.00 2.00 8.00 Nos 193.15 1 Nos 1545.00 183.94 1472.00 73.00 0 0 176.64
10/Dec/19 MODULAR- 12 93 1 4.00 3.00 12.00 Nos 237.46 1 Nos 2849.00 226.15 2714.00 135.00 0 0 325.68
Supply of 6A / 10A 3/2 Pin 2 Module Modular Socketwith shutter.complete
in N.R.B. / R.B. (Data No. 9.1.1) (TBSE-1.7.4)
10/Dec/19 93 1 4.00 1.00 4.00 Nos 30.67605 1 Nos 123.00 29.22 117.00 6.00 0 0 14.04
Supply and fixing of 16A ISI marked 1 Nos. modular type switch & 16A/6A 1
way 2 Module Combi Socket Modular Socket with shutter on a common
switch board with connections including cost and coveyance of all material
and all labour charges etc., complete in N.R.B. / R.B. (Data No. 9.1.1)
10/Dec/19 94 1 4.00 1.00 4.00 Nos 17566.583 1 Nos 70266.00 15223.84 60895.00 9371.00 0 0 7307.4
Supply of 40-63A 10KA DP MCB, C/D Curve ISI Mark Distribution board with
IP-43 protection (Metal Door) as per IS 13032 and suitable for 1 No. 3 phase
ELCB / RCCB / FP Isolator as incomer and 10 Nos 10kA 10-32 A SP MCBs as
outing goings including internal connection and labour charges for flush
mounting etc., complete.
10/Dec/19 94 1 4.00 1.00 4.00 Nos 5251.0861 1 Nos 21004.00 4273.70 17095.00 3909.00 0 0 2051.4
Providing independent earthling by excavating a trench to a depth of 2.1 M
in all soils, as per size specified in the Data, using 40mm dia 'B' class GI pipe
of 2.5 Mtrs length with necessary accessories with hume pipe ring duly
providing staggered holes
10/Dec/19 95 1 1.00 1.00 1.00 Nos 3891.76 1 Nos 3892.00 3706.44 3706.00 186.00 0 0 444.72
Supply and Transportation and fixing of 18/20W, 1200mm length, Low
Glare LED tube light fitting of "Havells make Model E-Lite Pride" /Equivalent
make and model as directed by Dept,with input AC 220 - 260 Volts with
>0.9 PF with driver and frosted cover etc., complete .duly erected on 2
Nos suitable clip type holders with all connections with twin core copper
wire of Finolex / RR kabel / Havells / Polycab / GM / Million / V-Guard / Gold
Medal / HPL / RPG / Payal and labour charges etc complete.
(Mod-Data No.21.1.1)s.
10/Dec/19 Inside 95 1 4.00 3.00 12.00 Nos 1278.6697 1 Nos 15344.00 1033.14 12398.00 2946.00 0 0 1487.76
10/Dec/19 Outside 95 1 4.00 2.00 8.00 Nos 1278.6697 1 Nos 10229.00 1033.14 8265.00 1964.00 0 0 991.8
Supply and fixing of batten holder / slanting holder in lieu of ceiling rose of
light point complete with all connections and all labour charges with 18 Watt
CFL bulb (for new installation).
10/Dec/19 96 1 4.00 3.00 12.00 Nos 177.25 1 Nos 2127.00 145.25 1743.00 384.00 0 0 209.16
Supply, Transportation and fixing of Integral70 W SV / MH Street light
luminaire integral with pressure diecast alluminium housing having pot
optics with IP66 protection with all standard accessories including 250W
HPSV / MH lamp and fixing of luminaire on wall with 1.0mt 40mm dia GI
pipe bracket and anti-tilting arrangements, 4 Sq.mm flexible copper cable
including masonary work and all labour charges and giving connections etc.,
complete.(Data No.14-15-22.1.3 ) (TBSE-3.1.4 )
10/Dec/19 96 1 1.00 1.00 1.00 Nos 6248.825 1 Nos 6249.00 5951.26 5951.00 298.00 0 0 714.12
Value of Work
S.N Description Work Done Value in Done in GST Value of Work Total Amount Remarks
o. VAT Period Done in GST 12%
18%
Name of the Sub work : Construction of Watch man and Operator Quar
As per Working Estimate
Sl. Dimensions Qty
Description Rate Per
No Nos L B D
1 Earth work excavation in all type of soils with intial lead and lift etc complete.
PCC (1:4:8) using 40 mm HBG metal icluding Cost and conveyance of the all
2
materials etc complete.
Column footings 18.0 1.95 1.95 0.10 6.84
6.84 Cum 4927.10 1 Cum
VRCC (1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
3 materials,but excluding the cost of the steel etc complete for Columns footing.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
4 materials,but excluding the cost of the steel etc complete for Columns upto
Ground Level.
18 0.23 0.45 1.45 2.70
2.70 Cum 8953.80 1 Cum
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
5 materials,but excluding the cost of the steel etc complete for Plinth Beams
Earth work excavation in all type of soils with intial lead and lift etc complete
6 for RR Mansonry.
Long Wall 2 15.45 0.65 0.70 14.06
Short Wall 2 10.57 0.65 0.70 9.62
deductions 4 0.65 0.65 0.70 1.18
22.50 Cum 128.20 1 Cum
PCC(1:4:8)using 40 mm HBG metal icluding Cost and conveyance of the all
7 materials etc complete For RR Masonry.
Long Wall 2 15.45 0.65 0.10 2.01
Short Wall 2 10.57 0.65 0.10 1.37
deductions 4 0.65 0.65 0.10 0.17
3.21 Cum 4927.10 1 Cum
Providing & filling gravel/morrum soil (CNS Soil) for foundation including
braking clouds,spreading in laying of 0-15 cm watering including all etc
complete
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
9 materials,but excluding the cost of the steel etc complete for Columns Upto
Ground Roof Slab.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
10 materials,but excluding the cost of the steel etc complete for Beams for
Ground Floor Slab&Middle Beam for stair casing
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
11 materials,but excluding the cost of the steel etc complete for Roof Slab for
Ground Floor.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
12 materials,but excluding the cost of the steel etc complete for Columns upto 1st
Floor.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
13 materials,but excluding the cost of the steel etc complete for Beams for
Terrace Floor Slab.
Long Beams 3 15.45 0.23 0.30 3.20
Long Beams-FFB3 1 15.45 0.15 0.30 0.70
Short Beams 6 9.07 0.23 0.30 3.75
Deductions 18 0.23 0.23 0.30 0.29
Deductions-FFB3 6 0.15 0.23 0.30 0.06
7.30 Cum 11822.82 1 Cum
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
14 materials,but excluding the cost of the steel etc complete for Columns for
Water Tank.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
15 materials,but excluding the cost of the steel etc complete for Beams for Water
Tank.
Long Beams 2 3.51 0.23 0.30 0.48
Short Beams 2 2.4 0.23 0.30 0.33
0.82 Cum 11822.82 1 Cum
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
16 materials,but excluding the cost of the steel etc complete for Bottom Slab for
Water Tank.
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
17 materials,but excluding the cost of the steel etc complete for Side wall for
Water Tank.
Long Wall 2 3.51 0.15 1.50 1.58
Short Wall 2 2.56 0.15 1.50 1.15
2.73 Cum 8397.60 1 Cum
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
18 materials,but excluding the cost of the steel etc complete for Top Slab for
Water Tank.
1 3.51 2.86 1.000 10.04
Deduction Man Hole 1 0.6 0.6 1.000 0.36
9.68 Sqmt 13518.37 10 Sqm
Spetic Tank
Brick Masonry with CM(1:6) using Second Class Bricks including cost and
19 conveyance of all the materials etc complete for Ground Floor upto First Floor
Roof Beam
Long walls 3 14.99 0.23 2.70 27.93
Deductions
Brick Masonry in Staircase area -1 2.40 0.23 2.70 -1.49
Windows2 -2 0.600 0.23 0.90 -0.25
Windows(W) -2 1.20 0.23 1.20 -0.66
Main Door(MD) -2 0.90 0.23 2.10 -0.87
Door2(D2) -2 0.75 0.23 1.80 -0.62
Door1(D1) -8 0.90 0.23 2.10 -3.48
Window1(W1) -4 0.90 0.23 1.20 -0.99
Balcony Shortwalls 6 1.50 0.23 2.70 5.59
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
20 materials,but excluding the cost of the steel etc complete for Lintel Beams in
Ground Floor.
Door 1 10x2 1.50 0.23 0.23 1.58
Door 2 4x2 1.35 0.23 0.23 0.58
Main Doors 2x2 1.50 0.23 0.23 0.32
Window 1 7x2 1.50 0.23 0.23 1.12
Window 1 7x2 1.50 0.23 0.23 1.12
Window 3 1x2 1.05 0.23 0.23 0.12
Main Winows W 2x2 1.80 0.23 0.23 0.38
Ventilators 4x2 1.20 0.23 0.23 0.50
5.72 Cum 11060.74 1 Cum
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
21 materials,but excluding the cost of the steel etc complete for Stair Case
Landing.
1st Flight 1 1.20 2.56 1.00 3.07
Landing 1 2.40 1.20 1.00 2.88
2nd Flight 1 1.20 2.56 1.00 3.07
Steps in 1st Flights 10 0.23 1.2 1 1.38
Steps in 2nd Flights 9 0.23 1.2 1 1.24
11.64 Sqmt 15338.12 10 Sqm
22 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the
materials,but excluding the cost of the steel etc complete for Sunshades
Brick Masonry with CM(1:6) using Second Class Bricks including cost and
conveyance of all the materials etc complete for First Floor to Terrace Bottom
Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm
thick and second coat in CM(1:3) prop 4mm thick including cost and
23
conveyance of all materials and labour charges etc., complete for Ground Floor
Inside
Balacony Shortwall 12 1.73 1 3.00 62.28
Balacony longwall-1 2 3.05 1 3.00 18.30
Balacony longwall-2 2 2.79 1 3.00 16.71
Balacony longwall-3 1 2.400 1 3.00 7.20
Dedictons for Door-1 -4 0.90 1 2.10 -7.56
Dedictons for Window-1 -4 0.90 1 1.20 -4.32
Bedroom Wall-1 10 3.05 1 3.00 91.50
Bedroom Wall-2 4 3.05 1 3.00 36.60
Bedroom Wall-3 4 2.90 1 3.00 34.80
Stair Case Back Side 2 2.40 1 3.00 14.40
Deductions forDoor-1 -8 0.90 1 2.10 -15.12
Deductions forDoor-2 -2 0.75 1 1.80 -2.70
Toilets Long walls 8 1.80 1 3.00 43.20
Toilets Short walls 8 1.20 1 3.00 28.80
Deductions for Door-2 -4 0.75 1 1.80 -5.40
Deduction for Ventilators -4 0.60 1 0.30 -0.72
Liv/Din Room Long wall 4 4.15 1 3.00 49.80
Liv/Din Room Short wall 4 3.05 1 3.00 36.60
Out side Long wall(0-3 Mts) 2 9.185 1 3 55.11 Sqm 3029.33 10 Sqm
Supplying & fixing SINGLE PANEL 3.0 mm thick PVC door with frame and
shutters including cost and conveyance of all materials and labour charges etc.,
complet.
Snowcem paint two coats including cost and conveyence etc complete. For
28
Ground Floor
30 Synthatic Enamel painting over primary coat and Enamel painting in two caots
including csot and conveyance of all the materials ect complete.
Door 1 2 2.00 1.05 - 4.20
Door 2 4 2.00 0.9 - 7.20
Door 3 2 2 0.75 - 3.00
Window 1 8 1.2 1.2 - 11.52
Window 2 4 0.9 1.2 - 4.32
ventilator 4 0.6 0.45 - 1.08
31.32 Sqm 2060.25 10 Sqm
Flooring with CC(1:4:8) using 40mm HBG metal for 100mm thick and Top
31 plastering with CM(1:3) ,20mm thick including cost and conveyance of all the
materials ect complete.
Balcony-I 4 3.05 1 1.5 18.30
Balcony-II 4 2.785 1 1.5 16.71
M.Bed Room 4 3.05 1 3.05 37.21
Bed Room 4 3.05 1 2.9 35.38
Statir case Back Side 2 3.05 1 2.4 14.64
Toilets 8 1.8 1 1.2 17.28
Liv/Din Room 4 4.15 1 3.05 50.63
Verenda 4 2.20 1 2.79 24.51
Flooring with Vetrified tiles of 1st Quality set over base coat of cement motor
(1:6) 12 mm thick over a C C bed already laid on RCC roof slab Including Neat &
cement slurry of Honey like consistency spread at the rate of 3.3 kgs/ m2
32 jointed neatly with white cement paste with full depth mixed with pegment of
matching shade including cost of all materials like cement, sand, water & tiles
etc complete including seignorage charges etc complete for finished item of
work.
Difference Amount
Name of the Sub work : Construction of Watch man and Operator Quarter -II at 50 MLD WTP at Bhainsa
As per Working Estimate
Amount
24414.00
33701.00
198172.00
24175.00
70707.00
2885.00
15816.00
54262.00
59894.00
91135.00
220764.00
62572.00
86314.00
189170.00
2758.00
9642.00
15397.00
22938.00
13084.00
263004.00
63267.00
17854.00
18341.00
298623.00
210942.00
210700.00
16695.00
22145.00
-982.00
-1008.00
-109.00
-112.00
-82.00
-84.00
36463.00
39560.00
121332.00
153679.60
53116
6453.00
192519.70
429518.90
719497.00
100000.00
150000.00
580866.84
4,900,000
49,00,000
49,82,935
82,935
Superintending Engineer
RWS&S Circle, Adilabad
28/Aug/19 slab 150mm thick 1226 40 1 1 3.51 2.86 1 10.0386 sqm 15338.12 10 sqm 15397.00 14369.87 14425.00 972.00 128.75
Alround Building
long wall 1226 53 1 4 10.57 3 1 126.84
short wall 1226 53 1 4 6.52 3 1 78.24
Lintel Beam 1 Sunshade Top & Bottom 1226 53 1 14 1.2 0.6 1 10.08
Lintel Beam 2 Sunshade Top & Bottom 1226 53 1 4 1.2 0.6 1 2.88
Lintel Beam 2 Sunshade Sides 1226 53 1 4 0.6 0.087 1 0.2088
Lintel Beam 3 Sunshade Top & Bottom 1226 53 1 4 0.6 1 1 2.4
Lintel Beam 3 Sunshade Sides 1226 53 1 4 0.6 0.087 1 0.2088
Staircase flight 1&2 1226 54 1 4 2.55 1.2 1 12.24
Landing 1226 54 1 2 1.2 2.4 1 5.76
Open Area slab bottom 1226 54 1 2 15 1 1 30
Deductions 54
Door D1 1226 54 1 4 0.9 2.1 -1 -7.56
Door MD 1226 54 1 2 0.9 2.1 -1 -3.78
Windows W1 1226 54 1 2 1.2 1.2 -1 -2.88
Windows W2 1226 54 1 6 0.9 1.2 -1 -6.48
Kitchen 56
short side wall 1226 56 1 4 1.8 2.55 1 18.36
Long side wall 1226 56 1 4 3.05 2.55 1 31.11
Slab 1226 56 1 2 3.05 1.8 1 10.98
Living & Dining 56
short side wall 1226 56 1 4 3.05 2.55 1 31.11
Long side wall 1226 56 1 4 4.15 2.55 1 42.33
Slab 1226 56 1 2 3.05 4.15 1 25.315
Varanda 56
short side wall 1226 56 1 4 2.28 2.55 1 23.256
Long side wall 1226 56 1 2 2.78 2.55 1 14.178
Slab 1226 56 1 2 2.28 2.78 1 12.6768
Toilet
short side wall 1226 57 1 8 1.8 2.55 1 36.72
Long side wall-1 1226 57 1 8 1.2 2.55 1 24.48
Long side wall-2 1226 57 1 2 2.63 2.55 1 13.413
Slab 1226 57 1 4 1.8 1.2 1 8.64
Open Portion 57
short wall 1226 57 1 2 1.015 2.55 1 5.1765
Deductions 57
Door D1 1226 57 1 10 0.9 2.1 -1 -18.9
Door MD 1226 57 1 2 0.9 2.1 -1 -3.78
Door D2 1226 57 1 4 0.75 1.8 -1 -5.4
Windows W1 1226 57 1 2 1.2 1.2 -1 -2.88
W2 1226 58 1 6 0.9 1.2 -1 -6.48
W3 1226 58 1 2 0.9 0.6 -1 -1.08
W4 1226 58 1 2 0.45 0.6 -1 -0.54
Ventilators 1226 58 1 4 0.6 0.3 -1 -0.72
24/Oct/19 Total 512.4833 sqmt 3110.91 10 sqmt 159429.00 3025.93 155074.00 4355.00 272.64
Alround Building
long wall 1226 59 1 4 10.57 3 1 126.84
short wall 1226 59 1 4 6.52 3 1 78.24
Lintel Beam 1 Sunshade Top & Bottom 1226 59 1 14 1.2 0.6 1 10.08
Lintel Beam 1 Sunshade Sides 1226 59 1 14 0.6 0.087 1 0.7308
Lintel Beam 2 Sunshade Top & Bottom 1226 59 1 4 1.2 0.6 1 2.88
Lintel Beam 2 Sunshade Sides 1226 59 1 4 0.6 0.087 1 0.2088
Lintel Beam 3 Sunshade Top & Bottom 1226 59 1 4 0.6 1 1 2.4
Lintel Beam 3 Sunshade Sides 1226 59 1 4 0.6 0.087 1 0.2088
Door MD -1 1226 59 1 -2 0.9 0.23 1 -0.414
Door MD -2 1226 60 1 -4 0.23 2.1 1 -1.932
Door D1 Side1 1226 60 1 -4 0.9 0.23 1 -0.828
Door D1 Side2 1226 60 1 -8 0.23 2.1 1 -3.864
Window W 1226 60 1 -8 1.2 0.23 1 -2.208
W1 Side -1 1226 60 1 -12 0.9 0.23 1 -2.484
W1 Side -2 1226 60 1 -12 0.23 1.2 1 -3.312
W2 Side -1 1226 60 1 -4 0.9 0.23 1 -0.828
W2 Side -2 1226 60 1 -4 0.23 0.6 1 -0.552
W3 Side -1 1226 60 1 -4 0.45 0.23 1 -0.414
W3 Side -2 1226 60 1 -4 0.23 0.6 1 -0.552
Ventilator- side-1 1226 60 1 -8 0.6 0.23 1 -1.104
Toilet 64
short side wall 1226 64 1 8 1.8 2.875 1 41.4
Long side wall-1 1226 64 1 8 1.2 2.875 1 27.6
Long side wall-2 1226 64 1 2 2.63 2.875 1 15.1225
Slab 1226 64 1 4 1.8 1.2 1 8.64
Open Portion 64
short wall 1226 64 1 2 1.015 2.875 1 5.83625
Deductions 65
Door D1 1226 65 1 10 0.9 2.1 -1 -18.9
Door MD 1226 65 1 2 0.9 2.1 -1 -3.78
Door D2 1226 65 1 4 0.75 1.8 -1 -5.4
Windows W1 1226 65 1 2 1.2 1.2 -1 -2.88
W2 1226 65 1 6 0.9 1.2 -1 -6.48
W3 1226 65 1 2 0.9 0.6 -1 -1.08
W4 1226 65 1 2 0.45 0.6 -1 -0.54
Ventilators 1226 65 1 4 0.6 0.3 -1 -0.72
Flooring with Vetrified tiles of 1st Quality set over base coat
white cement paste with full depth mixed with pegment of
matching shade including cost of all materials etc complete
including seignorage charges etc complete .
Ground Floor
M.Bed Room 1226 76 1 2 3.05 3.05 18.605
Bed Room 1226 76 1 2 2.9 3.05 17.69
Liv/Din Room 1226 76 1 2 4.15 3.05 25.315
Kitchen 1226 76 1 2 2 1.8 7.2
Toilets 1226 76 1 4 1.8 1.2 8.64
Balcony-1 1226 76 1 2 3.05 1.5 9.15
Balcony-2 1226 77 1 2 2.78 1.5 8.34
Varanda 1226 77 1 2 2.28 2.7 12.312
Kitchen Wall 1226 77 1 2 3.2 0.9 5.76
Toilets Side wall 1226 77 1 16 1.8 1.8 51.84
Deduction Door (.750 X 1.80) 1226 77 1 16 0.9 2.1 -30.24
22/Nov/19 134.612
36 First Floor
Supplying & fixing SINGLE PANEL 3.0 mm thick PVC door with
frame and shutters including cost and conveyance of all
materials and labour charges etc., complet.
12/Dec/19 For Bathroom doors 1226 97 1 8 8 No.s 3067.61 1 No.s 24541.00 2595.71 20766.00 3775.00
Supply and Fixing of CPVC pipe (ISI MARK) with all required
accessories including fixing and labour charges etc.
06/Dec/19 22.2 mm CPVC Pipe (TBSP-J.III-02) 85 1 1 12 12 Rmt 181.78 1 Rmt 2181.00 156.79 1881.00 300.00
06/Dec/19 28.6 mm CPVE Pipe (TBSP-J.III-03) 85 1 1 12 12 Rmt 240.86 1 Rmt 2890.00 207.92 2495.00 395.00
Supplying & fixing CPVC ball Valve as per IS I-class heavy duty
as approved by the Engineer including cost & conveyance of
all materials, labour charges, etc. complete for finished item
of work in all floors as directed by Engineer-in-charge
Supplying & Fixing Orissa Pan White glazed W.C 1st quality ISI
marked conforming to IS:2556-Part-3-1981 with "P" or "S"
trap Hindware/ Parryware/ Neycer - ISI Mark: 580 mm x 440
mm duly providing constructing Brick masonry seat using 2nd
class bricks, CC Squatting plate in P.C.C 1:2:4, S&F PVC Low
level system with internal components & short bend: 10
Litres capacity Single Flush, S&F of 15 mm brass angle stop
valve of quarter turn spindle type of not less than 400 grams
weight with internal threaded conforming to IS 8931 and S&F
15 mm nominal size PVC connection with brass union nut C.P
coated including cost and conveyance of all materials and
labour charges, overheads and contractor's profit etc.,.
complete as per standard practice for finished item of work.
S&F of 15
Supply, mm brassand
Installation body CP finish bib tap
commissioning of not less
approved makethan
floor
300 gramsClose
mounted weight with quarter
Coupled wash downturn spindle with eitherto
EWC conforming
internal (Part
IS:2556 or external
8)-2004 threaded
suit withconnection conforming
'P' or 'S' trap with dualto IS
flush
06/Dec/19 porcelain
8931 cistern fixed on wash down EWC with all internal 87 1 4 7 28 Nos 278.4 1 Nos 7795.00 243.15 6808.00 987.00
parts of dual flush cistern, ultra solid seat cover of approved
06/Dec/19 make with rubber buffer and cap & 15 mm angle stop cock & 87 1 4 1 4 Nos 10531 1 Nos 42124.00 8788 35152.00 6972.00
450 mm
Supplying
S&F long
Stainless PVC
steelinter
& Fixing Indianconnection
4" dia make
roundFlat pipe
Backwall
Grating Wash
withflanges
Handall
frame of
Basin
for
approved
1st ormake
quality
nahany etc. complete
conforming
floor trap withfor
orfinished
without item
to IS:2556-Part-4:1972
cover of work
holewith wastein all
respects:
06/Dec/19 fittings likeColoured - Grade
rubber plug, - I/Grade
chain, 32 mm- IInominal size C.P. 88 1 4 1 4 Nos 289 1 Nos 1156.00 240 960.00 196.00
Fitting with parallel pipe thread conforming to IS:2963-1979
and fitted with 15 mm nominal bore Chromium Plated Pillar
06/Dec/19 Tap of 1st quality Indian make 400 grams complete with 88 1 4 1 4 Nos 3083 1 Nos 12332.00 2557 10228.00 2104.00
Supplying
standard CI&brackets
fixing stainless steel
including sink size
wooden 36" x550
block: 18"x 400 mm -
(914.4x457.2mm)
Single C.P. Pillar cock1 mm thick with accessories
20 21 22 23 24 25 26 27 28 29
Date 28 Days
Date of Cement Cement used in
prior to Date qty
Description Grade of Total in Kg's
Sl. No of Item concreate Measurem Page No Quantity of per cum / Kgs
ent Measuremen sqm (E5*F6)
t
18=
12=11/(1 + 14=13 -11, 15=14/11%, 17=10*11*16,
10=9 /1000 11.00 28.18/100) 13.00 14A=13-12 15A=14/12 16= 15+5 17A=10*12*16 17*13.61
% 5%
1.26 6200 4813.29 5300 -900 -18.70 -13.70 -831.00 -113.14
8.95 6200 4813.29 5300 -900 -18.70 -13.70 -5898.40 -803.07
1.08 6200 4813.29 5300 -900 -18.70 -13.70 -712.10 -96.95
2.48 6200 4813.29 5300 -900 -18.70 -13.70 -1633.60 -222.41
0.98 6200 4813.29 5300 -900 -18.70 -13.70 -643.50 -87.61
3.76 6200 4813.29 5300 -900 -18.70 -13.70 -2481.50 -337.86
2.16 6200 4813.29 5300 -900 -18.70 -13.70 -1424.20 -193.90
1.90 6200 4813.29 5300 -900 -18.70 -13.70 -1252.90 -170.58
3.00 6200 4813.29 5200 -1000 -20.78 -15.78 -2274.90 -309.73
6.61 6200 4813.29 5200 -1000 -20.78 -15.78 -5020.20 -683.50
1.90 6200 4813.29 5200 -1000 -20.78 -15.78 -1442.90 -196.45
2.90 6200 4813.29 5300 -900 -18.70 -13.70 -1913.40 -260.51
6.61 6200 4813.29 5300 -900 -18.70 -13.70 -4359.10 -593.49
0.07 6200 4813.29 5200 -1000 -20.78 -15.78 -50.30 -6.85
0.30 6200 4813.29 5200 -1000 -20.78 -15.78 -227.10 -30.92
0.60 6200 4813.29 5200 -1000 -20.78 -15.78 -457.40 -62.28
1.09 6200 4813.29 5000 -1200 -24.93 -19.93 -1048.20 -142.71
3.87 6200 4813.29 5000 -1200 -24.93 -19.93 -3714.00 -505.66
1.90 6200 4813.29 5200 -1000 -20.78 -15.78 -1443.90 -196.59
0.90 6200 4813.29 5000 -1200 -24.93 -19.93 -858.80 -116.93
0.50 6200 4813.29 5200 -1000 -20.78 -15.78 -378.90 -51.59
1.14 6200 4813.29 5200 -1000 -20.78 -15.78 -867.60 -118.12
1.04 6200 4813.29 5200 -1000 -20.78 -15.78 -792.70 -107.93
2.62 6200 4813.29 5000 -1200 -24.93 -19.93 -2513.00 -342.14
0.01 6200 4813.29 4500 -1700 -35.32 -30.32 -20.90 -2.85
0.01 6200 4813.29 4500 -1700 -35.32 -30.32 -9.10 -1.24
0.01 6200 4813.29 4500 -1700 -35.32 -30.32 -18.90 -2.57
0.01 6200 4813.29 4500 -1700 -35.32 -30.32 -10.60 -1.44
2.62 6200 4813.29 5300 -900 -18.70 -13.70 -1730.50 -235.61
0.16 6200 4813.29 4500 -1700 -35.32 -30.32 -238.10 -32.42
0.16 6200 4813.29 4500 -1700 -35.32 -30.32 -238.10 -32.42
6/30/2017 7/1/2017 8/21/2017
19= 20=
19=18+17 18= 17*5% 17A*18% 17A*12%
1 2 3 4 5 6 7 8 9 10 11
12
963.32
185.81
353.92
20.74
79.01
26.54
50.56
185.14
52.26
583.97
199.46
364.79
44.24
225.31
77.04
142.45
374.27
197.31
129.97
90.46
83.17
57.89
246.86
69.68
212.35
56.00
68.30
25.87
0.00
331.83
56.00
68.30
25.87
0.00
331.83
56.00
68.30
25.87
0.00
85.88
64.16
0.00
77.13
54.85
0.00
152.63
64.16
0.00
101.75
107.11
0.00
297.64
279.87
315.61
285.60
75.08
33.76
31.10
50.77
85.24
58.91
14.39
0.00
17.15
14.33
16.71
15.60
246.86
69.68
186.19
35.83
76.58
0.00
186.19
56.00
76.58
0.00
186.19
56.00
76.58
0.00
86.41
64.16
86.41
64.16
0.00
153.58
64.16
0.00
102.38
107.11
0.00
211.63
199.29
281.52
265.24
34.37
32.15
75.08
33.76
31.10
50.77
50.69
26.31
17.00
9.96
7.54
0.00
0.00
49.78
37.68
0.00
0.00
17.78
13.40
0.00
9.96
7.54
0.00
34.85
26.38
0.00
11.61
22.40
0.00
9.96
7.54
0.00
2.49
2.09
0.00
0.83
1.78
9.80
2.77
0.00
0.00
16.16
0.00
16.16
7.99
0.00
53.62
6.36
17.91
2.73
0.00
14.85
5.45
33.28
17.34
0.00
53.62
14.31
21.96
20.22
5.45
16.76
10.40
29.96
29.96
20.70
0.00
76.03
22.77
0.00
65.96
65.29
0.00
0.00
51.92
58.03
0.00
39.70
45.81
28.43
32.38
35.14
31.20
28.53
28.91
12.53
12.25
10.93
11.10
18.20
13096.52
POL For Construction of Watch man and Operator Quarter -1 at 50 MLD WTP at Bhainsa
Embede
Sl. Date of record Description MB No. Page No. No. L B D Qty. Rate per Amount Bare Rate Bare Amount S. Charges Date 28 Days prior
Amount
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
1226/TDWSP/Nirmal/201 including setting out, construction of shoring and bracing, removal of stumps and other
1 deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and
6 backfilling in trenches with excavated suitable material as per Technical Specification 305
MORD / 304 MORTH ordianry gravelly soils for foundations
Earth work in excavation in Hard rock requring blasting,including c/c of all material charges etc
2
complete.
07 May 2019 Columns footings 1226 2 1 6.0 2.3 2.3 0.60 19.04
07 May 2019 19.04 Cum 390.72 1 Cum 7439.00 380.93 7253.00 186.00 09 April 2019
PCC (1:4:8) using 40 mm HBG metal icluding Cost and conveyance of the all materials etc
3
complete.
Column footings 1226 2 1 18 1.95 1.95 0.10 6.84
Septic Tank 1 5.00 2.50 0.10
07 May 2019 6.84 Cum 4927.10 1 Cum 33701.00 4656.59 31851.00 1850.00 585 09 April 2019
VRCC (1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
4 excluding the cost of the steel etc complete for Columns footing.
5 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Columns upto Ground Level.
6 VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Plinth Beams
PCC(1:4:8)using 40 mm HBG metal icluding Cost and conveyance of the all materials etc
complete For Plingth beam Bed
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Columns Upto Ground Slab.
11 10 June 2019 Columns 1226 12 1 18 0.23 0.45 2.55 4.75 Cum 0.00 1 Cum 0.00 0.00 0.00 0.00 406 13 May 2019
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Beams for Ground Floor Slab&Middle Beam for 0.00 0 02 December 1899
stair casing
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Columns upto 1st Floor.
0.00 0 02 December 1899
09 July 2019 Columns 1226 21 1 18 0.23 0.45 2.55 4.75 Total Rate 1 Cum #VALUE! Total Rate #VALUE!
14
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Beams for Terrace Floor Slab. 0.00 0 02 December 1899
Long Beams 1226 19 1 3 14.99 0.23 0.30 3.10
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
17
excluding the cost of the steel etc complete for Beams for Water Tank.
Long Beams 1226 40 1 2 3.51 0.23 0.275 0.44 0.00 38 02 December 1899
Short Beams 1226 40 1 2 2.4 0.23 0.275 0.30
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Bottom Slab for Water Tank.
28 August 2019 slab 150mm thick 1226 40 1 1 3.51 2.86 1.00 10.04 sqm 11822.82 10 sqm 11868.00 11177.32 11220.50
0.00 0 02 December 1899
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Side wall for Water Tank.
Short Wall 1226 42 1 2 2.56 0.15 1.50 1.15 0.00 98 02 December 1899
09 September 2019 2.73 Cum 92.40 1 Cum 252.00 88.00 240.00
20
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Top Slab for Water Tank.
125mm thick slab 1226 43 1 1 3.51 2.86 1.000 10.04
Deduction Man Hole 1226 43 1 1 0.6 0.6 1.000 -0.36 0.00 31 02 December 1899
20 September 2019 9.68 sqm 0.00 10 sqm 0.00 0.00 0.00
Brick Masonry with CM(1:6) using Second Class Bricks including cost and conveyance of all the
21
materials etc complete for Ground Floor upto First Floor Roof Beam
VRCC(1:1.5:3) using 20 mm HBG metal including cost and conveyance of all the materials,but
excluding the cost of the steel etc complete for Stair Case Landing.
1st Flight 1226 37 1 1 1.20 2.56 3.07
Landing 1226 37 1 1 2.40 1.20 2.88
2nd Flight 1226 37 1 1 1.20 2.56 3.07 0.00 262 02 December 1899
Steps in 1st Flights 1226 37 1 4 1.2 0.3 0.15 0.22
35 Manufacturing supplying and erection off SS Hand Railingfabrication for varandha including c/c 0.00
of all labour charges complete.
36 Ground Floor 0.00
37 1 974.58 29910.00
30.69 1150 Rmt 35293.50
18 19 20 21 22 23 24 25 26
9,824 0 0 1178.93
Depth from 0.00 to 3.00mt 883.62 Cum 128.20 1 Cum 113280.00 917.69 Cum 128.20 1 Cum 117648.00 0.00 4368.00 Actuals
Foundations - Raft - M30 grade 905.93 Cum 9320.70 1 Cum 8443902.00 881.64 Cum 9320.70 1 Cum 8217502.00 226400.00 0.00
Side wall
Haunch width 0.15
Haunch Portion 2.93 Cum 9320.70 1 Cum 27310.00 8.10 Cum 9320.70 1 Cum 75498.00 0.00 48188.00
instead of 0.3
1st step with 400 mm thick 19.59 Cum 11283.00 1 Cum 221034.00 14.64 Cum 11283.00 1 Cum 165183.00 55851.00 0.00 As per site condition
2ndstep to 4th step with 400 mm thick 281.64 Cum 12112.40 1 Cum 3411336.00 263.86 Cum 12112.40 1 Cum 3195978.00 215358.00 0.00
Rectangular Beams - M30 grade 75.60 Cum 11101.02 1 Cum 839237.00 1.00 Cum 303626.00 1 Cum 303626.00 535611.00 0.00
15 Fixing for RCC inside ladder as per the standard LS each each LS each 10000.00 each 0.00 LS each 0.00 10000.00 0.00
specifications
Fixing RCC OUTSIDE ladder as per the standard
16 specifications 0.83 each each LS each 5000.00 each 0.00 LS each 0.00 5000.00 0.00
Diff in
Date 28 Cement %
rate as increase 13.615%
Cement Rate as
Description of Grade of Date of Total Days prior qty in Cement used used in Rate as Bare Rate per per price or Add/ Price variation Over Head Total
Sl. No Item concreate Measurem Page No Quantity to Date of Kg's per in Kgs MTs per (K9/(1+2 Procurem variation decrease Deduct Amount Sub and VAT 5% GST 18% GST 12%
ent Measure cum / (E5*F6) Estimate 8.18/100) (M11- initial 5% total Amount
(I7/1000) ent Contractor
ment sqm L10) profit
15=14/11
7=4- 10=9 12=11/(1 + 14=13 -11, %, 17=10*11*16, 18=
1 2 3 4 5 6
28Days
8.00 9=6*8
/1000
11.00 28.18/100 13.00
14A=13-12 15A=14/1
16= 15+5
17A=10*12*16 19=18+17 18= 17*5% 19= 17A*18% 20= 17A*12%
) 17*13.615%
2%
1 PCC 1:4:8 7/5/19 2 7.78 9/4/19 162.00 1260.36 1.26 6200 4813.29 5300 -900 -14.52 -9.52 -743.60 -101.24 -844.84 0.00 0.00 -101.38
1 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
2 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
3 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
4 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
5 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
6 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
7 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
8 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
9 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
10 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
11 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
12 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
13 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
14 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
15 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
16 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
17 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
18 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
19 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
20 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
21 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
22 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
23 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
24 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
25 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
26 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
27 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
28 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
29 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
30 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
31 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
32 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
33 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
34 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
35 RCC M30 2/12/99 400.00 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
36 Brick Masonry 1:6 2/12/99 50.40 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
37 Brick Masonry 1:6 2/12/99 50.40 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
38 Brick Masonry 1:6 2/12/99 50.40 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
39 Brick Masonry 1:6 2/12/99 50.40 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
40 Brick Masonry 1:6 2/12/99 50.40 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
41 Brick Masonry 1:6 2/12/99 50.40 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
42 Acco Plastering 1:3 2/12/99 7.20 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
43 Acco Plastering 1:3 2/12/99 7.20 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
44 Acco Plastering 1:3 2/12/99 7.20 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
45 Acco Plastering 1:3 2/12/99 7.20 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
46 Acco Plastering 1:3 2/12/99 7.20 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
47 Acco Plastering 1:3 2/12/99 7.20 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
48 Acco Plastering 1:3 2/12/99 7.20 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
49 Acco Plastering 1:3 2/12/99 7.20 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
50 Plastering 1:3 2/12/99 10.08 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
51 Plastering 1:3 2/12/99 10.08 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
52 Plastering 1:3 2/12/99 10.08 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
53 Plastering 1:3 2/12/99 10.08 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
54 Plastering 1:3 2/12/99 10.08 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
55 Plastering 1:3 2/12/99 10.08 0.00 0.00 6200 4813.29 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 0.00 0.00
Asst. Executive Engineer Dy. Executive Engineer Executive Engineer Superintending Engineer
MB Grid SD Bhainsa MB Grid SD Bhainsa MB Grid SD Bhainsa MB Grid Circle Adilabad
1 2 3 4 5 6 7 8 9 10 11
Kg's
12
963.32
185.81
353.92
20.74
79.01
26.54
50.56
185.14
52.26
583.97
199.46
364.79
44.24
225.31
77.04
142.45
374.27
197.31
129.97
90.46
83.17
57.89
246.86
69.68
212.35
56
68.3
25.87
0
331.83
56
68.3
25.87
0
331.83
56
68.3
25.87
0
85.88
64.16
0
77.13
54.85
0
152.63
64.16
0
101.75
107.11
0
297.64
279.87
315.61
285.6
75.08
33.76
31.1
50.77
85.24
58.91
14.39
17.15
14.33
16.71
15.6
246.86
69.68
186.19
35.83
76.58
0
186.19
56
76.58
0
186.19
56
76.58
0
86.41
64.16
0
86.41
64.16
153.58
64.16
0
102.38
107.11
0
211.63
199.29
281.52
265.24
34.37
32.15
75.08
33.76
31.1
50.77
50.69
26.31
17
9.96
7.54
0
0
49.78
37.68
0
0
17.78
13.4
0
9.96
7.54
0
34.85
26.38
0
11.61
22.4
0
9.96
7.54
0
2.49
2.09
0
0.83
1.78
9.8
2.77
0
0
16.16
0
16.16
7.99
0
53.62
6.36
17.91
2.73
0
14.85
5.45
33.28
17.34
53.62
14.31
21.96
20.22
5.45
16.76
10.4
29.96
29.96
20.7
0
76.03
22.77
0
65.96
65.29
51.92
58.03
0
39.7
45.81
28.43
32.38
35.14
31.2
28.53
28.91
12.53
12.25
10.93
11.1
18.2
13096.52
Seigniorage Charges for Watch man and Operator Quart
21.01
60.39
7.29
16.72
6.59
0.00
14.58
12.83
20.22
44.63
12.83
19.59
44.63
0.45
2.02
4.07
7.38
26.13
0.00
0.00
0.00
7.71
7.05
0.00
0.00
0.00
0.00
0.00
43.74
0.00
0.00
379.83
DETAILED CUM ABSTRACT WORK DONE SUB-ESTIMATE
Name of the Programme: MISSION BHAGIRATHA (TDWSP)
Name of the work : Providing Drinking water to SRSP Habitations in Adilabad District
Name of the Sub work: Construction of 6000 KL Sump @ Bhainsa Head works
Estimate cost Rs. 296.40 Lakhs
Date of Page
Sl. record Description MB No. No. No. L B D Qty. Rate per Amount
0 to 3m depth(387.27 to
9/8/2016 386.88) 107 1 1 1 53.60 43.90 0.39 917.69
917.69 Cum 128.20 1 Cum 117648.00
Removal of Hard rock by Machine which require blasting such as hard rock, sheet
1)a 9/16/2016 rock and boulders for Structures including cost and conveyance of all material and
labour charges etc completed
12/21/2016 Down slope middle wall 107 9 1 1 3.00 0.30 2.00 1.80
12/21/2016 Down slope middle trangular 107 10 1 0.5 2.00 0.30 2.00 0.60
12/21/2016 side wall 300 mm 107 10 1 2 40.90 0.30 1.35 33.13
iv 1/8/2017 2st step with 300 mm thick 107 11 1 3 50.30 0.30 1.20 54.32
1/8/2017 side wall 2nd side 107 11 1 2 40.90 0.30 1.20 29.45
1/24/2017 3rd step with 300mm thick 107 13 1 3 50.00 0.3 1.20 54.00
1/24/2017 side wall 2nd side 107 13 1 2 40.90 0.30 1.20 29.45
263.86 Cum 12112.40 1 Cum 3195978.00
(v) Rectangular Columns - M30 grade
12/21/2016 Columns between Beam 107 10 1 88 0.30 0.30 1.20 9.50 Cum 11113.68 1 Cum 105580.00
1/8/2017 Columns between Beam 107 11 1 88 0.30 0.30 1.20 9.50 Cum 11113.68 1 Cum 105580.00
1/24/2017 Columns between Beam 107 13 1 88 0.30 0.30 1.05 8.32 Cum 11113.68 1 Cum 92466.00
(vi) 5/6/2017 Top Slab - M30 Grade 107 19 1 1 50.60 40.90 0.15 310.43
5/6/2017 Stair case deduction 107 19 1 1 4.00 4.50 0.15 -2.70
5/6/2017 Dedcution for Ventilator 107 19 1 60 0.90 0.90 0.15 -7.29
300.44 sqm 13755.90 10 sqm 413282.00
vii Stair case - M30 Grade
5/6/2017 1st flight beam 107 18 1 2 2.30 0.23 0.45 0.48 cum 11101.02 1 cum 5328.00
Brick Massonary in CM (1:6) including C&C of all materials and labour charges etc
5 completed as per standard specifications.
1/18/2018 Side wall 107 24 1 3 5.10 0.23 2.20 7.74
1/18/2018 Side wall 107 24 2 2 2.00 0.23 2.20 4.05
1/18/2018 Deduct for door 107 24 1 2 1.20 0.23 2.00 -1.10
1/18/2018 Deduct for ventilator 107 24 1 4 1.20 0.23 0.60 -0.66
1/18/2018 Parapet wall 107 24 1 2 4.95 0.115 0.30 0.34
1/18/2018 107 24 1 2 4.67 0.115 0.30 0.32
10.69 Cum 5234.77 1 Cum 55960.00
Acco proof Plastering with CM (1:3) 12mm thick including cost and conveyance of
7
all material, labour charges etc., complete
Epoxy protective coating with procoat SNF (item 279 SSR) paint 3 coat over water
8
proof plastering .including conveyance of all m/labour charges etc., complete
9 Painting with Snowcem paint 2 coats over a primary coat including cost and
conveyance of all materials and labour charges, etc., complete
1/28/2018 Slab bottom 107 30 1 1 50 40.00 - 2000.00
1/28/2018 Beam side 107 30 12 8 3.86 - 0.30 111.17
1/28/2018 Beam side 107 30 10 11 3.70 - 0.30 122.10
1/28/2018 Deduct for vent opening 107 30 1 60 0.90 0.90 - -48.60
1/28/2018 Head room out side 107 30 1 2 5.10 - 2.93 29.84
1/28/2018 107 30 1 2 4.90 - 2.93 28.67
1/28/2018 Inner side 107 30 1 2 4.50 - 2.50 22.50
1/28/2018 107 30 1 4 4.30 - 2.50 43.00
1/28/2018 Slab Bottom 107 31 1 1 4.50 4.30 - 19.35
1/28/2018 Beam side 107 31 1 2 4.50 - 0.30 2.70
1/28/2018 107 31 1 2 4.30 - 0.30 2.58
1/28/2018 Parapit wall Inner side 107 31 1 1 19.08 - 0.30 5.72
Total 2339.03 Sqm 1029.90 10 Sqm 240897.00
Cost and Fabrication charges of steel including cutting bending and binding the steel with
1 contractors binding wire with placing in position for premeasurements etc complete
26/09/2016 Qty at 5 % vat in MT 3-17 (As per Steel Annexure) 126.73 MT 51392.60 1 MT 6512894.00
Qty at 18% GST in MT (As per Steel Annexure) 0.000 MT 51392.60 1 MT 0.00
12/01/2018 Qty at 12% GST in MT 20-36 (As per Steel Annexure) 2.014 MT 51392.60 1 MT 103489.00
Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved
drawing with aluminium anodised sections of Jindal sections and outer frame top
horizontals & both verticals of 2408 of size 101.6 x 44.75 x 3.18 mm Shutter frame
top, bottom and verticals of 4504 of size 44.45 mm x 47.62 mm x 3.18 and Middle
lock rail of 4621 of size 49.91 x 44.45 x 3 mm with plain clear float glass 5 mm thick
11
fixed including supply and fixing aluminium handles of 100 mm for each shutter,
floor springs/ hydraulic door closure assembly and all labour charges for fixing the
fixtures with required no.of screws, bolts and nuts and including labour charges for
fixing the frame in position, fixing shutter to frame etc. completed for finished item
of work
3/1/2018 Ventilator 107 39 1 4 1.20 - 0.6 2.88 Sqm 3134.54 1 Sqm 9027.49
Supply, fabrication and erection of SS hand rail of 1mt height (40mm dia) vertical
for every 1mt spacing and 2 rows 25mm dia horizontal in between of SS - 304
14
grade, 40S. As per the standard spectification including cost and conveyance of all
materials completed for finished item of work
2/28/2018 Phenial Openings 107 38 60 4 0.9 - 0.8 172.80 Sqm 3134.54 1 Sqm 541649.20
Rs. Total Rs. 29639698.78
Page 211 of 230
Date of Page
Sl. record Description MB No. No. No. L B D Qty. Rate per Amount
Lakhs 296.40
1. The above is the TRUE EXTRACT of the Measurement Book No.121/TDWSP/NIRMAL/2015 and total work is completed
2. Total work is completed and Testing of the structure done and recorded vide M-Book No.121/TDWSP/NIRMAL/2015 Page no. 80 and
found satisfactorly.
Value of Work
Work Done Value Value of Work
S.No. Description in VAT Period 5% Done in GST Done in GST 12% Total Amount Remarks
18%
1 Work Value 23468385.00 0.00 6171309.78 29639695.00
9/8/2016 0 to 3m depth(387.27 to 386.88) 1 1 53.60 43.90 0.39 917.69 Cum 128.20 1 Cum 117648.00 128.20 1 Cum 117648.00 0.00 5882.00 0.00 0.00
Removal of Hard rock by Machine which require blasting such as hard
1a rock, sheet rock and boulders for Structures including cost and
conveyance of all material and labour charges etc completed
16-09-2016 from Level 386.88 to 384.45 1 1 53.60 43.90 2.43 5717.89 Cum 443.92 1 Cum 2538266.00 443.92 1 Cum 2538266.00 0.00 0.00 0.00 304591.92
16-09-2016 Extra suction-pits 1 1 22.30 4.00 2.00 178.40 Cum 443.92 1 Cum 79195.00 443.92 1 Cum 79195.00 0.00 0.00 0.00 9503.40
Cement concrete (1:4:8) prop using 40 mm gauge HG metal including cost
2 &conveyance of all materials and labour charges ,seigniorage charges
using concret mixer etc complete
9/26/2016 For base portion 1 1 52.40 42.70 0.30 671.24 Cum 5335.66 1 Cum 3581508.00 5335.66 1 Cum 3581508.00 0.00 179075.00 0.00 0.00
9/26/2016 For slope extra portion 1 1 28.10 0.83 0.30 6.98 Cum 5335.66 1 Cum 37243.00 5335.66 1 Cum 37243.00 0.00 1862.00 0.00 0.00
M30 grade design mix using 20mm HG metal including cost and
4 conveyance of all material, labour charges, centering etc., complete but
excluding cost of steel and its fabrication charges
9/30/2016 for sump portion 1 1 51.80 42.10 0.40 872.31 Cum 9320.70 1 Cum 8130540.00 9320.70 1 Cum 8130540.00 0.00 406527.00 0.00 0.00
9/30/2016 extra in slope area 1 1 28.10 0.83 0.40 9.33 Cum 9320.70 1 Cum 86962.00 9320.70 1 Cum 86962.00 0.00 4348.00 0.00 0.00
(ii) 12/21/2016 Haunch Portion 1 1 180.00 0.30 0.30 8.10 Cum 9320.70 1 Cum 75498.00 9320.70 1 Cum 75498.00 0.00 3775.00 0.00 0.00
12/21/2016 Down portion wall 1 1 16.30 0.40 2.00 13.04 Cum 11283.00 1 Cum 147130.00 11283.00 1 Cum 147130.00 0.00 7357.00 0.00 0.00
12/21/2016 Down slope portion wall 2 1 2.00 0.40 2.00 1.60 Cum 11283.00 1 Cum 18053.00 11283.00 1 Cum 18053.00 0.00 903.00 0.00 0.00
(iii) 12/21/2016 for 3parallel wall 1 3 50.30 0.30 1.35 61.11 Cum 12112.40 1 Cum 740189.00 12112.40 1 Cum 740189.00 0.00 37009.00 0.00 0.00
(iii) 12/21/2016 1st step with 300 mm thick 0 3 50.00 0.30 1.35 0.00 Cum 12112.40 1 Cum 0.00 12112.40 1 Cum 0.00 0.00 0.00 0.00 0.00
12/21/2016 Down slope middle wall 1 1 3.00 0.30 2.00 1.80 Cum 12112.40 1 Cum 21802.00 12112.40 1 Cum 21802.00 0.00 1090.00 0.00 0.00
12/21/2016 Down slope middle trangular 1 1 2.00 0.30 2.00 0.60 Cum 12112.40 1 Cum 7267.00 12112.40 1 Cum 7267.00 0.00 363.00 0.00 0.00
iv 12/21/2016 side wall 300 mm 1 2 40.90 0.30 1.35 33.13 Cum 12112.40 1 Cum 401284.00 12112.40 1 Cum 401284.00 0.00 20064.00 0.00 0.00
1/8/2017 2st step with 300 mm thick 1 3 50.30 0.30 1.20 54.32 Cum 12112.40 1 Cum 657946.00 12112.40 1 Cum 657946.00 0.00 32897.00 0.00 0.00
1/8/2017 side wall 2nd side 1 2 40.90 0.30 1.20 29.45 Cum 12112.40 1 Cum 356710.00 12112.40 1 Cum 356710.00 0.00 17836.00 0.00 0.00
1/24/2017 3rd step with 300mm thick 1 3 50.00 0.30 1.20 54.00 Cum 12112.40 1 Cum 654070.00 12112.40 1 Cum 654070.00 0.00 32704.00 0.00 0.00
1/24/2017 side wall 2nd side 1 2 40.90 0.30 1.20 29.45 Cum 12112.40 1 Cum 356710.00 12112.40 1 Cum 356710.00 0.00 17836.00 0.00 0.00
(v) Rectangular Columns - M30 grade
12/21/2016 Columns between Beam 1 88 0.30 0.30 1.20 9.50 Cum 11113.68 1 Cum 105580.00 11113.68 1 Cum 105580.00 0.00 5279.00 0.00 0.00
1/8/2017 Columns between Beam 1 88 0.30 0.30 1.20 9.50 Cum 11113.68 1 Cum 105580.00 11113.68 1 Cum 105580.00 0.00 5279.00 0.00 0.00
1/24/2017 Columns between Beam 1 88 0.30 0.30 1.05 8.32 Cum 11113.68 1 Cum 92466.00 11113.68 1 Cum 92466.00 0.00 4623.00 0.00 0.00
5/6/2017 Top Slab - M30 Grade 1 1 50.60 40.90 0.15 310.43 Cum 13755.90 10 Cum 427024.00 13755.90 10 Cum 427024.00 0.00 21351.00 0.00 0.00
(vi) 5/6/2017 Stair case deduction 1 1 4.00 4.50 0.15 -2.70 Cum 13755.90 10 Cum -3714.00 13755.90 10 Cum -3714.00 0.00 -186.00 0.00 0.00
5/6/2017 Dedcution for Ventilator 1 60 0.90 0.90 0.15 -7.29 Cum 13755.90 10 Cum -10028.00 13755.90 10 Cum -10028.00 0.00 -501.00 0.00 0.00
Stair case - M30 Grade
vii 5/6/2017 1st flight beam 1 2 2.30 0.23 0.45 0.48 Cum 11101.02 1 Cum 5328.00 11101.02 1 Cum 5328.00 0.00 266.00 0.00 0.00
5/6/2017 1st flight slab 2 1 3.25 1.00 0.15 0.98 Cum 10152.70 1 Cum 9950.00 10152.70 1 Cum 9950.00 0.00 498.00 0.00 0.00
5/6/2017 Landing slab 2 1 2.00 1.00 0.15 0.60 Cum 10152.70 1 Cum 6092.00 10152.70 1 Cum 6092.00 0.00 305.00 0.00 0.00
5/6/2017 steps upto 1st flight 11 1 1.00 0.25 0.16 0.44 Cum 7206.30 1 Cum 3171.00 7206.30 1 Cum 3171.00 0.00 159.00 0.00 0.00
5/6/2017 2nd flight slope 2 1 3.25 1.00 0.15 0.98 Cum 7206.30 1 Cum 7062.00 7206.30 1 Cum 7062.00 0.00 353.00 0.00 0.00
5/6/2017 steps upto slab 11 1 1.00 0.25 0.18 0.50 Cum 7206.30 1 Cum 3603.00 7206.30 1 Cum 3603.00 0.00 180.00 0.00 0.00
viii Slab beam portion
5/6/2017 Beam 1 1 8 50.00 0.30 0.30 36.00 cum 11101.02 1 cum 399637.00 11101.02 1 cum 399637.00 0.00 19982.00 0.00 0.00
5/6/2017 Beam 1 1 11 40.00 0.30 0.30 39.60 cum 11101.02 1 cum 439600.00 11101.02 1 cum 439600.00 0.00 21980.00 0.00 0.00
5/6/2017 Deduction for column junction 1 88 0.30 0.30 0.30 -2.38 cum 11101.02 1 cum -26420.00 11101.02 1 cum -26420.00 0.00 -1321.00 0.00 0.00
ix M30 Grade fo Ventilators
1/12/2018 Ventilator column 60 3 0.10 0.10 0.90 1.70 Cum 11101.02 1 Cum 18872.00 10456.62 1 Cum 17776.00 -1096.00 0.00 0.00 2133.12
1/12/2018 for Pre cast slab 60 1 1.10 1.10 0.10 7.26 Cum 10152.70 1 Cum 73709.00 9508.30 1 Cum 69030.00 -4679.00 0.00 0.00 8283.60
1/12/2018 Head room column 1 4 0.30 0.30 2.20 0.79 Cum 11113.68 1 Cum 8780.00 10469.38 1 Cum 8271.00 -509.00 0.00 0.00 992.52
x M30 grade for Head room
1/15/2018 Beam STRB2 1 3 5.10 0.30 0.30 1.38 Cum 11101.02 1 Cum 15319.00 10456.62 1 Cum 14430.00 -889.00 0.00 0.00 1731.60
1/15/2018 Beam STRB1 1 6 2.00 0.30 0.30 1.08 Cum 11101.02 1 Cum 11989.00 10456.62 1 Cum 11293.00 -696.00 0.00 0.00 1355.16
xi 1/15/2018 Slab 1 1 5.10 4.90 0.13 3.12 Cum 10152.70 1 Cum 31676.00 9508.30 1 Cum 29666.00 -2010.00 0.00 0.00 3559.92
1/15/2018 Chajja 1 1 5.10 0.60 0.10 0.31 Cum 10152.70 1 Cum 3147.00 9508.30 1 Cum 2948.00 -199.00 0.00 0.00 353.76
7 21-01-2018 Acco proof Plastering with CM (1:3) 12mm thick including cost and
conveyance of all material, labour charges etc., complete
1/20/2018 Inside the sump + haunches 1 4 50.00 - 3.75 750.00 Sqm 1638.34 10 Sqm 122876.00 1491.49 10 Sqm 111862.00 -11014.00 0.00 0.00 13423.44
1/20/2018 1 2 40.00 - 3.75 300.00 Sqm 1638.34 10 Sqm 49150.00 1491.49 10 Sqm 44745.00 -4405.00 0.00 0.00 5369.40
1/20/2018 Suction Pit 1 2 16.00 - 2.00 64.00 Sqm 1638.34 10 Sqm 10485.00 1491.49 10 Sqm 9546.00 -939.00 0.00 0.00 1145.52
1/20/2018 1 4 2.83 - 2.00 22.64 Sqm 1638.34 10 Sqm 3709.00 1491.49 10 Sqm 3377.00 -332.00 0.00 0.00 405.24
1/20/2018 Bottom of the sump 1 1 50.00 40.00 - 2000.00 Sqm 1638.34 10 Sqm 327668.00 1491.49 10 Sqm 298298.00 -29370.00 0.00 0.00 35795.76
1/20/2018 Column 1 88 1.20 - 3.45 364.32 Sqm 1638.34 10 Sqm 59688.00 1491.49 10 Sqm 54338.00 -5350.00 0.00 0.00 6520.56
1/20/2018 Deduction for Columns 1 88 0.30 0.30 -7.92 Sqm 1638.34 10 Sqm -1298.00 1491.49 10 Sqm -1181.00 117.00 0.00 0.00 -141.72
1/20/2018 Stair case bottom 1 2 3.50 1.00 - 7.00 Sqm 1638.34 10 Sqm 1147.00 1491.49 10 Sqm 1044.00 -103.00 0.00 0.00 125.28
Epoxy protective coating with procoat SNF (item 279 SSR) paint 3 coat
8 over water proof plastering .including conveyance of all m/labour charges
etc., complete
Painting with Snowcem paint 2 coats over a primary coat including cost
9 and conveyance of all materials and labour charges, etc., complete
1/28/2018 Slab bottom 1 1 50.00 40.00 - 2000.00 Sqm 1029.90 10 Sqm 205980.00 1029.90 10 Sqm 2059800.00 1853820.00 0.00 0.00 247176.00
1/28/2018 Beam side 12 8 3.86 - 0.30 111.17 Sqm 1029.90 10 Sqm 11449.00 1029.90 10 Sqm 114494.00 103045.00 0.00 0.00 13739.28
1/28/2018 Beam side 10 11 3.70 - 0.30 122.10 Sqm 1029.90 10 Sqm 12575.00 1029.90 10 Sqm 125751.00 113176.00 0.00 0.00 15090.12
1/28/2018 Deduct for vent opening 1 60 0.90 0.90 - -48.60 Sqm 1029.90 10 Sqm -5005.00 1029.90 10 Sqm -50053.00 -45048.00 0.00 0.00 -6006.36
1/28/2018 Head room out side 1 2 5.10 - 2.93 29.84 Sqm 1029.90 10 Sqm 3073.00 1029.90 10 Sqm 30732.00 27659.00 0.00 0.00 3687.84
1/28/2018 1 2 4.90 - 2.93 28.67 Sqm 1029.90 10 Sqm 2953.00 1029.90 10 Sqm 29527.00 26574.00 0.00 0.00 3543.24
1/28/2018 Inner side 1 2 4.50 - 2.50 22.50 Sqm 1029.90 10 Sqm 2317.00 1029.90 10 Sqm 23173.00 20856.00 0.00 0.00 2780.76
1/28/2018 1 4 4.30 - 2.50 43.00 Sqm 1029.90 10 Sqm 4429.00 1029.90 10 Sqm 44286.00 39857.00 0.00 0.00 5314.32
1/28/2018 Slab Bottom 1 1 4.50 4.30 - 19.35 Sqm 1029.90 10 Sqm 1993.00 1029.90 10 Sqm 19929.00 17936.00 0.00 0.00 2391.48
1/28/2018 Beam side 1 2 4.50 - 0.30 2.70 Sqm 1029.90 10 Sqm 278.00 1029.90 10 Sqm 2781.00 2503.00 0.00 0.00 333.72
1/28/2018 1 2 4.30 - 0.30 2.58 Sqm 1029.90 10 Sqm 266.00 1029.90 10 Sqm 2657.00 2391.00 0.00 0.00 318.84
1/28/2018 Parapit wall Inner side 1 1 19.08 - 0.30 5.72 Sqm 1029.90 10 Sqm 589.00 1029.90 10 Sqm 5891.00 5302.00 0.00 0.00 706.92
Cost and Fabrication charges of steel including cutting bending and
10 binding the steel with contractors binding wire with placing in position for
premeasurements etc complete
9/26/2016 As per Annexure VAT @5% 126.73 MT 51392.60 1 MT 6512894.00 51392.60 1 MT 6512894.00 0.00 325645.00 0.00 0.00
As per Annexure GST @18% 0.00 MT 51392.60 1 MT 0.00 0.00 1 MT 0.00 0.00 0.00 0.00 0.00
1/12/2018 As per Annexure GST @12% 2.01 MT 51392.60 1 MT 103489.00 43999.30 1 MT 88601.00 -14888.00 0.00 0.00 10632.12
Supply, fabrication and erection of SS hand rail of 1mt height (40mm dia)
vertical for every 1mt spacing and 2 rows 25mm dia horizontal in between
of SS - 304 grade, 40S. As per the standard spectification including cost
and conveyance of all materials completed for finished item of work
3/1/2018 Door outer frame 1 2 0.75 - 2 3.00 Sqm 6285.37 1 Sqm 18856.10 5655.99 1 cum 16968.00 -1888.10 0.00 0.00 2036.16
3/1/2018 Ventilator 1 4 1.20 - 0.6 2.88 Sqm 3134.54 1 Sqm 9027.49 2817.50 1 cum 8114.00 -913.49 0.00 0.00 973.68
2/28/2018 Phenial Openings 60 4 0.9 - 0.8 172.80 Sqm 3134.54 1 Sqm 541649.20 2817.50 1 cum 486865.00 -54784.20 0.00 0.00 58423.80
Rs. Total Rs. 29639694.78 Rs. 31577876.00 1948652.22 1173420.00 0.00 973138.92
Lakhs 296.40
Asst. Executive Engineer Dy. Executive Engineer Executive Engineer Superintending Engineer
MB Grid SD Bhainsa MB Grid SD Bhainsa MB Grid SD Bhainsa MB Grid Circle Adilabad
9/8/2016 1 0 to 3m depth(387.27 to 386.88) 1 1 53.60 43.90 0.39 917.69 Cum 128.20 1 Cum 117648.00 0.00 11/Aug/16 55.37 -6.30% -1.30% -10.00 -1.00 -11.00 -0.55 0.00 0.00
Removal of Hard rock by Machine which require blasting such as hard rock,
1a sheet rock and boulders for Structures including cost and conveyance of all
material and labour charges etc completed
16-09-2016 2 from Level 386.88 to 384.45 1 1 53.60 43.90 2.43 5717.89 Cum 443.92 1 Cum 2538266.00 0.00 19/Aug/16 53.21 -9.97% -4.97% 2215.00 302.00 2517.00 0.00 0.00 302.04
16-09-2016 2 Extra suction-pits 1 1 22.30 4.00 2.00 178.40 Cum 443.92 1 Cum 79195.00 0.00 19/Aug/16 53.21 -9.97% -4.97% 69.00 9.00 78.00 0.00 0.00 9.36
9/26/2016 3 For base portion 1 1 52.40 42.70 0.30 671.24 Cum 5335.66 1 Cum 3581508.00 57391.02 29/Aug/16 53.21 -9.97% -4.97% -748.00 -102.00 -850.00 -42.50 0.00 0.00
9/26/2016 3 For slope extra portion 1 1 28.10 0.83 0.30 6.98 Cum 5335.66 1 Cum 37243.00 596.79 29/Aug/16 53.21 -9.97% -4.97% -8.00 -1.00 -9.00 -0.45 0.00 0.00
M30 grade design mix using 20mm HG metal including cost and conveyance
4 of all material, labour charges, centering etc., complete but excluding cost of
steel and its fabrication charges
9/30/2016 7 for sump portion 1 1 51.80 42.10 0.40 872.31 Cum 9320.70 1 Cum 8130540.00 66295.56 2/Sep/16 56.10 -5.08% -0.08% -33.00 -4.00 -37.00 -1.85 0.00 0.00
9/30/2016 7 extra in slope area 1 1 28.10 0.83 0.40 9.33 Cum 9320.70 1 Cum 86962.00 709.08 2/Sep/16 56.10 -5.08% -0.08% 0.00 0.00 0.00 0.00 0.00 0.00
(ii) 12/21/2016 9 Haunch Portion 1 1 180.00 0.30 0.30 8.10 Cum 9320.70 1 Cum 75498.00 615.60 23/Nov/16 57.78 -2.23% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
12/21/2016 9 Down portion wall 1 1 16.30 0.40 2.00 13.04 Cum 11283.00 1 Cum 147130.00 991.04 23/Nov/16 57.78 -2.23% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
12/21/2016 9 Down slope portion wall 2 1 2.00 0.40 2.00 1.60 Cum 11283.00 1 Cum 18053.00 121.60 23/Nov/16 57.78 -2.23% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
(iii) 12/21/2016 9 for 3parallel wall 1 3 50.30 0.30 1.35 61.11 Cum 12112.40 1 Cum 740189.00 4644.36 23/Nov/16 57.78 -2.23% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
(iii) 12/21/2016 9 1st step with 300 mm thick 0 3 50.00 0.30 1.35 0.00 Cum 12112.40 1 Cum 0.00 0.00 23/Nov/16 57.78 -2.23% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
12/21/2016 9 Down slope middle wall 1 1 3.00 0.30 2.00 1.80 Cum 12112.40 1 Cum 21802.00 136.80 23/Nov/16 57.78 -2.23% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
12/21/2016 10 Down slope middle trangular 1 1 2.00 0.30 2.00 0.60 Cum 12112.40 1 Cum 7267.00 45.60 23/Nov/16 57.78 -2.23% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
iv 12/21/2016 10 side wall 300 mm 1 2 40.90 0.30 1.35 33.13 Cum 12112.40 1 Cum 401284.00 2517.88 23/Nov/16 57.78 -2.23% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
1/8/2017 11 2st step with 300 mm thick 1 3 50.30 0.30 1.20 54.32 Cum 12112.40 1 Cum 657946.00 4128.32 11/Dec/16 57.63 -2.48% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
1/8/2017 11 side wall 2nd side 1 2 40.90 0.30 1.20 29.45 Cum 12112.40 1 Cum 356710.00 2238.20 11/Dec/16 57.63 -2.48% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
1/24/2017 13 3rd step with 300mm thick 1 3 50.00 0.30 1.20 54.00 Cum 12112.40 1 Cum 654070.00 4104.00 27/Dec/16 57.63 -2.48% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
1/24/2017 13 side wall 2nd side 1 2 40.90 0.30 1.20 29.45 Cum 12112.40 1 Cum 356710.00 2238.20 27/Dec/16 57.63 -2.48% 0.00% 0.00 0.00 0.00 0.00 0.00 0.00
xi 1/15/2018 23 Slab 1 1 5.10 4.90 0.13 3.12 Cum 10152.70 1 Cum 31676.00 237.12 18/Dec/17 62.81 6.28% 1.28% -7.00 -1.00 -8.00 0.00 0.00 -0.96
1/15/2018 23 Chajja 1 1 5.10 0.60 0.10 0.31 Cum 10152.70 1 Cum 3147.00 23.56 18/Dec/17 62.81 6.28% 1.28% -1.00 0.00 -1.00 0.00 0.00 -0.12
Acco proof Plastering with CM (1:3) 12mm thick including cost and
7 21-01-2018
conveyance of all material, labour charges etc., complete
QVP NO: 25,26,27
1/20/2018 25 Inside the sump + haunches 1 4 50.00 - 3.75
750.00 Sqm 1638.34 10 Sqm 122876.00 472.50 23/Dec/17 62.81 6.28% 1.28% -27.00 -4.00 -31.00 0.00 0.00 -3.72
1/20/2018 25 1 2 40.00 - 3.75
300.00 Sqm 1638.34 10 Sqm 49150.00 189.00 23/Dec/17 62.81 6.28% 1.28% -11.00 -1.00 -12.00 0.00 0.00 -1.44
1/20/2018 25 Suction Pit 1 2 16.00 - 2.0064.00 Sqm 1638.34 10 Sqm 10485.00 40.32 23/Dec/17 62.81 6.28% 1.28% -2.00 0.00 -2.00 0.00 0.00 -0.24
1/20/2018 25 1 4 2.83 - 2.0022.64 Sqm 1638.34 10 Sqm 3709.00 14.26 23/Dec/17 62.81 6.28% 1.28% -1.00 0.00 -1.00 0.00 0.00 -0.12
1/20/2018 25 Bottom of the sump 1 1 50.00 40.00 - 2000.00 Sqm 1638.34 10 Sqm 327668.00 1260.00 23/Dec/17 62.81 6.28% 1.28% -71.00 -10.00 -81.00 0.00 0.00 -9.72
1/20/2018 25 Column 1 88 1.20 - 3.45 364.32 Sqm 1638.34 10 Sqm 59688.00 229.52 23/Dec/17 62.81 6.28% 1.28% -13.00 -2.00 -15.00 0.00 0.00 -1.80
1/20/2018 25 Deduction for Columns 1 88 0.30 0.30 -7.92 Sqm 1638.34 10 Sqm -1298.00 -4.99 23/Dec/17 62.81 6.28% 1.28% 0.00 0.00 0.00 0.00 0.00 0.00
1/20/2018 25 Stair case bottom 1 2 3.50 1.00 - 7.00 Sqm 1638.34 10 Sqm 1147.00 4.41 23/Dec/17 62.81 6.28% 1.28% 0.00 0.00 0.00 0.00 0.00 0.00
Page 218 of 230
POL Taxes on POL
Sl. Date of Page Description No. L B D Qty. Rate per Amount Seinorages POL Add CP Total POL
record No. Charages Dt-28 Revised Diff Operati Amount @13.61 Amount VAT 5% GST 18%
GST18%
12%
Rate (Rs) % ve %
(Rs) 5% (Rs)
QVP NO: 28, 29
Epoxy protective coating with procoat SNF (item 279 SSR) paint 3 coat over
8 water proof plastering .including conveyance of all m/labour charges etc.,
complete
24-01-2018 28 Inside the sump + haunches 4 50.00 3.75 750.00 Sqm 331.81 1 Sqm 248859.00 0.00 #VALUE! 62.81 6.28% 1.28% -48.00 -7.00 -55.00 0.00 0.00 -6.60
24-01-2018 28 2 40.00 3.75 300.00 Sqm 331.81 1 Sqm 99544.00 0.00 #VALUE! 62.81 6.28% 1.28% -19.00 -3.00 -22.00 0.00 0.00 -2.64
24-01-2018 28 Suction Pit 1 2 16.00 2.00 64.00 Sqm 331.81 1 Sqm 21236.00 0.00 #VALUE! 62.81 6.28% 1.28% -4.00 -1.00 -5.00 0.00 0.00 -0.60
24-01-2018 28 1 4 2.83 2.00 22.64 Sqm 331.81 1 Sqm 7512.00 0.00 #VALUE! 62.81 6.28% 1.28% -1.00 0.00 -1.00 0.00 0.00 -0.12
24-01-2018 28 Bottom of the sump 1 50.00 40.00 2000.00 Sqm 331.81 1 Sqm 663625.00 0.00 #VALUE! 62.81 6.28% 1.28% -127.00 -17.00 -144.00 0.00 0.00 -17.28
24-01-2018 28 Stair case bottom 1 2 3.25 1.00 - 6.50 Sqm 331.81 1 Sqm 2157.00 0.00 #VALUE! 62.81 6.28% 1.28% 0.00 0.00 0.00 0.00 0.00 0.00
24-01-2018 28 Landing slab bottom 2 2 4.30 1.23 21.16 Sqm 331.81 1 Sqm 7021.00 0.00 #VALUE! 62.81 6.28% 1.28% -1.00 0.00 -1.00 0.00 0.00 -0.12
24-01-2018 29 Landing slab beam bottom 2 2 2.30 0.45 4.14 Sqm 331.81 1 Sqm 1374.00 0.00 #VALUE! 62.81 6.28% 1.28% 0.00 0.00 0.00 0.00 0.00 0.00
24-01-2018 29 Column 1 88 1.20 3.45 364.32 Sqm 331.81 1 Sqm 120886.00 0.00 #VALUE! 62.81 6.28% 1.28% -23.00 -3.00 -26.00 0.00 0.00 -3.12
1/24/2018 29 Deduction for Columns 1 88 0.30 0.30 -7.92 Sqm 331.81 1 Sqm -2628.00 0.00 27/Dec/17 62.81 6.28% 1.28% 1.00 0.00 1.00 0.00 0.00 0.12
1/20/2018 26 Head room out side 1 2 5.10 - 2.93 29.84 Sqm 2204.00 10 Sqm 6577.00 26.26 23/Dec/17 62.81 6.28% 1.28% -14.00 -2.00 -16.00 0.00 0.00 -1.92
1/20/2018 26 0 1 2 4.90 - 2.93 28.67 Sqm 2204.00 10 Sqm 6319.00 25.23 23/Dec/17 62.81 6.28% 1.28% -13.00 -2.00 -15.00 0.00 0.00 -1.80
1/20/2018 26 Inner side 1 2 4.30 - 2.50 21.50 Sqm 2204.00 10 Sqm 4739.00 18.92 23/Dec/17 62.81 6.28% 1.28% -10.00 -1.00 -11.00 0.00 0.00 -1.32
1/20/2018 26 0 1 4 4.30 - 2.50 43.00 Sqm 2204.00 10 Sqm 9477.00 37.84 23/Dec/17 62.81 6.28% 1.28% -20.00 -3.00 -23.00 0.00 0.00 -2.76
1/20/2018 26 Less for Door 2 2 1.00 - 2.20 -8.80 Sqm 2204.00 10 Sqm -1940.00 -7.74 23/Dec/17 62.81 6.28% 1.28% 4.00 1.00 5.00 0.00 0.00 0.60
1/20/2018 26 0 1 2 6.40 - 0.25 3.20 Sqm 2204.00 10 Sqm 705.00 2.82 23/Dec/17 62.81 6.28% 1.28% -2.00 0.00 -2.00 0.00 0.00 -0.24
1/20/2018 26 Less for ventilator 2 4 1.20 - 0.60 -5.76 Sqm 2204.00 10 Sqm -1270.00 -5.07 23/Dec/17 62.81 6.28% 1.28% 3.00 0.00 3.00 0.00 0.00 0.36
Painting with Snowcem paint 2 coats over a primary coat including cost and
9
conveyance of all materials and labour charges, etc., complete
1/28/2018 30 Slab bottom 1 1 50.00 40.00 - 2000.00 Sqm 1029.90 10 Sqm 205980.00 0.00 31/Dec/17 62.81 6.28% 1.28% -474.00 -65.00 -539.00 0.00 0.00 -64.68
1/28/2018 30 Beam side 12 8 3.86 - 0.30 111.17 Sqm 1029.90 10 Sqm 11449.00 0.00 31/Dec/17 62.81 6.28% 1.28% -26.00 -4.00 -30.00 0.00 0.00 -3.60
1/28/2018 30 Beam side 10 11 3.70 - 0.30 122.10 Sqm 1029.90 10 Sqm 12575.00 0.00 31/Dec/17 62.81 6.28% 1.28% -29.00 -4.00 -33.00 0.00 0.00 -3.96
1/28/2018 30 Deduct for vent opening 1 60 0.90 0.90 - -48.60 Sqm 1029.90 10 Sqm -5005.00 0.00 31/Dec/17 62.81 6.28% 1.28% 12.00 2.00 14.00 0.00 0.00 1.68
1/28/2018 30 Head room out side 1 2 5.10 - 2.93 29.84 Sqm 1029.90 10 Sqm 3073.00 0.00 31/Dec/17 62.81 6.28% 1.28% -7.00 -1.00 -8.00 0.00 0.00 -0.96
1/28/2018 30 1 2 4.90 - 2.93 28.67 Sqm 1029.90 10 Sqm 2953.00 0.00 31/Dec/17 62.81 6.28% 1.28% -7.00 -1.00 -8.00 0.00 0.00 -0.96
1/28/2018 30 Inner side 1 2 4.50 - 2.50 22.50 Sqm 1029.90 10 Sqm 2317.00 0.00 31/Dec/17 62.81 6.28% 1.28% -5.00 -1.00 -6.00 0.00 0.00 -0.72
1/28/2018 30 1 4 4.30 - 2.50 43.00 Sqm 1029.90 10 Sqm 4429.00 0.00 31/Dec/17 62.81 6.28% 1.28% -10.00 -1.00 -11.00 0.00 0.00 -1.32
1/28/2018 31 Slab Bottom 1 1 4.50 4.30 - 19.35 Sqm 1029.90 10 Sqm 1993.00 0.00 31/Dec/17 62.81 6.28% 1.28% -5.00 -1.00 -6.00 0.00 0.00 -0.72
1/28/2018 31 Beam side 1 2 4.50 - 0.30 2.70 Sqm 1029.90 10 Sqm 278.00 0.00 31/Dec/17 62.81 6.28% 1.28% -1.00 0.00 -1.00 0.00 0.00 -0.12
1/28/2018 31 1 2 4.30 - 0.30 2.58 Sqm 1029.90 10 Sqm 266.00 0.00 31/Dec/17 62.81 6.28% 1.28% -1.00 0.00 -1.00 0.00 0.00 -0.12
1/28/2018 31 Parapit wall Inner side 1 1 19.08 - 0.30 5.72 Sqm 1029.90 10 Sqm 589.00 0.00 31/Dec/17 62.81 6.28% 1.28% -1.00 0.00 -1.00 0.00 0.00 -0.12
Cost of steel and Fabrication charges of steel including cutting bending and
10 binding the steel with contractors binding wire with placing in position for
premeasurements etc complete
9/26/2016 a As per Annexure VAT @5% 126.73 MT 51392.60 1 MT 6512894.00 0.00 29/Aug/16 53.21 -9.97% -4.97% -2138.00 -291.00 -2429.00 -121.45 0.00 0.00
As per Annexure GST @18% 0.00 MT 51392.60 1 MT 0.00 0.00
1/12/2018 b As per Annexure GST @12% 2.01 MT 51392.60 1 MT 103489.00 0.00 15/Dec/17 62.95 6.52% 1.52% -24.00 -3.00 -27.00 0.00 0.00 -3.24
Supply, fabrication and erection of SS hand rail of 1mt height (40mm dia)
vertical for every 1mt spacing and 2 rows 25mm dia horizontal in between of
SS - 304 grade, 40S. As per the standard spectification including cost and
conveyance of all materials completed for finished item of work
3/1/2018 39 RC 1 1 13.25 - - 13.25 3100.00 1 Rmt 41075.00 0.00 1/Feb/18 66.68 12.83% 7.83% -49.00 -7.00 -56.00 0.00 0.00 -6.72
3/1/2018 39 LC 1 1 13.25 - - 13.25 3100.00 1 Rmt 41075.00 0.00 1/Feb/18 66.68 12.83% 7.83% -49.00 -7.00 -56.00 0.00 0.00 -6.72
3/1/2018 39 Over Top Side 1 1 184.1 - - 184.10 3100.00 1 Rmt 570710.00 0.00 1/Feb/18 66.68 12.83% 7.83% -682.00 -93.00 -775.00 0.00 0.00 -93.00
3/1/2018 39 Door outer frame 1 2 0.75 - 2 3.00 Sqm 6285.37 1 Sqm 18856.10 0.00 1/Feb/18 66.68 12.83% 7.83% -24.00 -3.00 -27.00 0.00 0.00 -3.24
3/1/2018 39 Ventilator 1 4 1.20 - 0.6 2.88 Sqm 3134.54 1 Sqm 9027.49 0.00 1/Feb/18 66.68 12.83% 7.83% -11.00 -1.00 -12.00 0.00 0.00 -1.44
2/28/2018 38 Phenial Openings 60 4 0.9 - 0.8 172.80 Sqm 3134.54 1 Sqm 541649.20 0.00 31/Jan/18 65.41 10.68% 5.68% -498.00 -68.00 -566.00 0.00 0.00 -67.92
Rs. Total Rs. 29639694.78 181132.72 5607.33 -3406.00 -167.00 0.00 -8.00
Lakhs 296.40 6866.64
Asst. Executive Engineer Dy. Executive Engineer Executive Engineer Superintending Engineer
MB Grid SD Bhainsa MB Grid SD Bhainsa MB Grid SD Bhainsa MB, Circle- Adilabad
Total in MT 198.59
0.581
Total in MT 128.74
Measurements Amount
Sl.No. Description No. Qty. Rate (Rs) per
L B D (Rs)
RCC M30 Grade Concrete using 20 mm HBG matal including cost and conveyance of all
1
materials and labour charges etc., complete
Ventilator Openings
Pedestal Columns Pi/4X4 0.1 0.1 1.2 0.038 11113.71 1 Cum 419
Cover slab over phenial
openings 1X1 1.2 1.2 0.15 0.216 10152.71 1 Cum 2193
Brick Masonry in CM (1:6) using Second class bricks including cost and conveyance of all
2
materials and labour charges etc., complete
1x4 0.90 0.23 0.110 0.09 5234.78 1 Cum 477
Plastering with 12mm thick with sponge finish first coat in CM(1:5) Prop 8mm thick and second
3 coat in CM(1:3) prop 4mm thick including cost and conveyance of all materials and labour
charges etc., complete for sump well
Ventilator Openings
To brickwork
Outside 1x4 0.90 - 0.110 0.40
Inside 1x4 0.90 - 0.260 0.94
Top 1x4 0.90 0.23 - 0.83
To Pedestal columns Pix4 0.1 1.2 1.51
To cover slab top 1X1 1.2 1.2 1.44
Sides 1X4 1.2 0.15 0.72
5.83 3,029.33 1765
Oil Bound washable Distemper with 2 coats over a primary coat including cost and
4 conveyance of all materials and labour charges etc., complete as per standard
specifications
Ventilator Openings
To brickwork
Outside 1x4 0.90 - 0.110 0.40
Inside 1x4 0.90 - 0.260 0.94
Top 1x4 0.90 0.23 - 0.83
To Pedestal columns Pix4 0.1 1.2 1.51
To cover slab top 1X1 1.2 1.2 1.44
Sides 1X4 1.2 0.15 0.72
5.83 1249.53 10 Sqmt. 728
Supply, fabrication and fixing of aluminium section of 25x12 mm and
powder coated aluminium alloy mesh in 14x14x.38 PVCL rubber beeding
5
including cost and conveyance of all materials and labour charges etc.,
complete. As per standard specification
To phenials 1X4 0.9 1.1 3.96 1614.58 1 Sqmt. 6394
Supply and placing of the HYSD bars, fabrication including cost and
6
conveyance of all the materials etc complete.
0.031 51392.61 1 MT 1593
Total Amount 15896