AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
This document or /and his attachments are subjected to revisions / modifications. Before using this document,
please verify to have the updated document.
Whoever comes in possession of this edition, is obliged to cancel or destroy any previous copies in his hands or
duplicates submitted of with he must have evidence tracking
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
SECTIONS REVISION
STATUS
SECTION DESCRIPTION
0 0 0 0 0 0 0
0 1 2 3 4 5 6
PREFACE X X
PART – I
QUALITY MANAGEMENT SYSTEM
1 GENERAL X X
2 PROJECT ORGANIZATION X X
2.1 GENERAL
2.2 APPENDIX
3.1 GENERAL
4.1 GENERAL
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
SECTIONS REVISION
STATUS
SECTION DESCRIPTION
0 0 0 0 0 0 0
0 1 2 3 4 5 6
4.2 RESPOSIBILITIES
4.3 METHODOLOGY
5.1 SCOPE
5.2 GENERAL
5.4 CHANGES
5.5 RECEIPT
5.6 DISTRIBUTION
5.11 APPENDICES
6.1 SCOPE
6.2 REPONSIBILITIES
SECTIONS REVISION
STATUS
SECTION DESCRIPTION
0 0 0 0 0 0 0
0 1 2 3 4 5 6
6.7 APPENDICES
7.1 SCOPE
7.2 RESPONSIBILITIES
7.4 PROCEDURES
7.5 APPENDICES
8.1 GENERAL
SECTIONS REVISION
STATUS
SECTION DESCRIPTION
0 0 0 0 0 0 0
0 1 2 3 4 5 6
8.11 APPENDIX
9.1 GENERAL
9.5 NON-CONFORMITIES
9.9 APPENDICES
10.1 SCOPE
10.2 OBJECTIVE
10.3 REFERENCE
10.4 RESPONSIBILITIES
10.5 PROCEDURES
10.6 APPENDICES
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
SECTIONS REVISION
STATUS
SECTION DESCRIPTION
0 0 0 0 0 0 0
0 1 2 3 4 5 6
PART – II
QUALITY PLAN FOR PROCUREMENT &
MATERIALS MANAGEMENT
11 PROCUREMENT PLAN X X
11.2 REFERENCE
11.4 RESPONSIBILITIES
11.6 APPENDICES
11A.3 RESPONSIBILITIES
11A.6 STORAGE
SECTIONS REVISION
STATUS
SECTION DESCRIPTION
0 0 0 0 0 0 0
0 1 2 3 4 5 6
11A.11 APPENDICES
PART – III
QUALITY PLAN FOR CONSTRUCTION & X X
PRE-COMMISSIONING PLAN
12.2 REFERENCE
12.3 RESPONSIBILITY
PREFACE
This Project Quality Plan shall be used as reference during the implementation of
Contractor’s contract scope with SAUDI ARAMCO, Project Requisition No. 3000613310
referred herein as “AL-JANADRIYAH EXHIBITION FACILITY AR-RIYADH”.
The preparation of this Project Quality Plan is correlated with ETE established Company
Quality Manual and its Operating Procedures, which describes the Management Policies
and commitment of its resources to support the effectiveness of the Quality system
implementation in all of its business operations.
This Project Quality Plan is subdivided into three (3) parts, i.e.:
Describes the Quality Control Activities during the Procurement Phase and Material
Management at Site to assure the procurement of Equipments, Materials &
Services conforms to the contract requirements.
______________________
Engr.Sinan Bu-Khamseen
General Manager
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
Eastern Trading & Contracting. Est. (ETE) is committed in maintaining its proven,
reliable performance with the Company for the Contract Job Execution of the project, AL-
JANADRIYAH EXHIBITION FACILITY AR-RIYADH, in achieving the objectives of the
Contract.
______________________
Engr.Sinan Bu-Khamseen
General Manager
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
5 Management Responsibility
5.4 Planning
6 Resource Management
7 Product Realization
7.4 Purchasing
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
8.3 Control of non conforming product Section 9 under 9.5 & 9.6
8.5 Improvement
1. GENERAL
The Exhibition Building is situated within an approximately 13,000 sq. m. site. The
building composes of 3 major parts & pavillion, namely:
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
a) Part 1: Main Exhibit Hall A one and half story circular building which
houses artwork and various events. It has a
lower & Main Upper levels for various functions.
b) Part 2: Atrium (Pre-function) Serves as a “nodes” between two-major parts of
this building, it connects the Main Exhibit Hall &
the Auditorium Building.
c) Part 3: Auditorium Building A single-storey structure with permanent stage
and supporting back stage areas, to serve as
the main lecture and presentation hall for the
entire complex.
d) Porte-cochere/Pavilion A permanent structure located at the VIP drop-
off area constructed with the same main
building construction.
1.4 EXCLUSIONS
Engineering including all detailed drawings, Layout Drawings
HOLD (H) : Means the Hold (H) point/s during the stage of
POINT/S Inspection/Test activities whereby Contractor Inspector
cannot proceed with the inspection or test without the
presence of CLIENT Inspector. Notification to the CLIENT
shall be carried out through written "Request for Inspection
(RFI)".
WITNESS (W) : Means the witnessing (W) points during the stage of
POINT/S Inspection/Test activities whereby Contractor Inspector may
proceed with the scheduled inspection and/or test after
notifying the CLIENT through written Request for Inspection
(RFI).
2. PROJECT ORGANIZATION
2.1 GENERAL
The Project Organization to be adopted in this contract job is shown on the
appendix of this Section. The Project team is linked to the Head Office of
CONTRACTOR in Dammam to provide technical and functional supportive roles
to the project needs.
At the CONTRACTOR’s Dammam Head Office, the Key Personnel to provide
authoritative and supportive roles for this contract job are as follows:
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
All work on this Project shall be completed in accordance with the latest issue of
Saudi Aramco Standard Specifications as applicable, upon award of the project
including but not limited to the above documents cross-referenced therein.
The work Quality Control Procedures (QCPs) or Method of statements which are part
of Quality Procedures Deliverables are summarized as appended in Section 12 of
this PQP.
4.2 RESPONSIBILITIES
CONTRACTOR Site Planning and Scheduling Unit shall be responsible for planning
and scheduling of work activities and required resources in the construction execution
and mechanical completion of the contract activities based on main Contractor’s
Project Critical Milestone Dates as shown in Contract Requirements. The
CONTRACTOR Planner or Scheduling Engineer shall coordinate with Main Contractor
for any changes on schedules in the work phases and shall make adjustment/updating
on the current project situation. He shall also be responsible for periodical progress
reporting, schedule updating and to include delay analysis if setbacks on schedules
are encountered during the contract execution. Any revisions to the Project Schedule
shall be subject to approval by the CLIENT.
4.3 METHODOLOGY
For an effective control of project activities, the Planning and Scheduling Unit will be
using the aid of MICROSOFT EXCEL or PRIMAVERA PROJECT PLANNER
SOFTWARE for the preparation of computer operated CPM and BAR Chart Schedules
as time saving and useful tool in Project Management. The planning phase involves
the listing of tasks of job, which must be performed to bring about the completion of the
project milestones. Resource requirements for materials, equipment and manpower
are determined in this phase and duration for each is made. Scheduling is done by
interconnecting of all the necessary activities of the project in the logical order as input
to the Computer Software Program with its corresponding early and late occurrences
of start and finish dates and the computer handles processing of the data. Control is a
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
function, which is a periodical review of the difference between schedule and the actual
performance as the aspect of review and evaluation and pursuing corrective actions to
prevent overall delay impact to Project Target Critical Milestone Dates.
5 DOCUMENT CONTROL
5.1 SCOPE
This section describes the management system to be adopted for project documents
and records control covering Construction Drawings, Specifications, other relevant
project technical documents and QA/QC records to include all submittals directed to
the CLIENT.
A close coordination between CONTRACTOR Home Office and Site Office shall be
observed on issuance and receipts of approved and latest documents.
5.2 GENERAL
In general, field documents and record management shall be governed and be handled
according to the requirements of the following:
Contract Schedules Provisions
Project Records
Security Control of the CLIENT Engineering Data outside of Saudi Aramco
This Project Quality Plan
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
5.4 CHANGES
5.4.1 The changes to the documents shall be carried out by the functional
unit/discipline that originally prepared, approved, and authorized the
documents unless specifically designated otherwise. The designated
functions shall be given access to pertinent background information.
5.4.2 The nature of amendment/reason (description) in brief shall be mentioned in
the ‘Status’ column of the cover sheet of the concerned document(s).
5.4.3 The amendment incorporated shall be identified by double vertical lines on
right side of the amended line, paragraph or page
5.4.4 When a paragraph is completely deleted, the number of the paragraph shall
be retained and the word ‘deleted’ shall appear in its front and in addition to
the double lines on the right hand side of the number.
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
5.5 RECEIPT
5.5.1 Initially, the CONTRACTOR Engineering Manager (Home Office) is
responsible for receiving and controlling of the Initial issue of the Issued For
Construction Drawings and Specifications and all other documents from the
CLIENT.
5.5.2 Subsequent receipt from the CLIENT is the responsibility of the Site Project
Manager through the Site Technical Support Supervisor.
5.5.3 All incoming documents/drawing transmittals for this project are to be
addressed to the Site Manager, as the CONTRACTOR field representative.
The document transmittal notes shall be date-stamped on the date received
and registered in Log Register Book. Distribution of receipt documents is
controlled by the Document Controller for established distribution schedule
under the directional responsibility of the Site Manager. In particular, the
following shall be observed in receiving documents/drawings:
a) Check the contents of the document transmittal to confirm:
That all drawings/documents as stated were matching
That the drawing numbers, sheet numbers and revisions match
those given in the document transmitted
b) Log in all received drawings onto the computer, to include
Drawing title for all new drawings
Date of the revision
Revision Number
Document transmittal reference
The document Log is interactive (both historical and live reference). No
document shall be deleted or deleted from the Log. When any drawing is
superseded, it shall be noted in the Log.
5.5.4 Once the drawings/documents are registered, the Drawing/Document Central
File shall be provided a copy as the “Master Copy”, to replace superseded
revision of the previous “Master Copy” (applies to reused drawings).
5.5.5 One copy stamped ‘Superseded’ is retained in a file for all superseded
documents and maintained by Site QA/QC Unit/Document Controller as
applicable.
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
5.6 DISTRIBUTION
5.6.1 At the start of site activities, the Document Controller shall establish the
document distribution schedule (Form No: Q-014) and classify it by type and
mainly divides to internal and external to CONTRACTOR in order to ensure
that the current issues of all documents are available at the pertinent
locations. This will be discussed and cleared with the CONTRACTOR Site
Manager and other project key staff members to include Secretary/
Administrative Assistant, Construction Superintendents, P&S Engineer,
QA/QC Engineer, Safety Supervisor, etc.
5.6.2 A copy of the document transmittal shall be circulated to each concerned
Engineer/Supervisor and initialed by them to indicate their awareness of the
new/revised drawing.
5.6.3 The Document Controller shall do distribution of the drawing/documents as
per the Distribution Schedule as “Controlled Copy”.
5.6.4 The Controlled copy holders shall destroy the superseded documents when
the revised documents are issued to them.
5.6.5 Documents shall be distributed to all concerned through “Document
Transmittal”
5.6.6 The document controller shall maintain both the electronic version and hard
copy of the drawing register at the same status at all times.
6.2 RESPONSIBILITIES
This preparation of Work Quality Plan and its management during implementation is
vested primarily under the functional responsibility of CONTRACTOR QA/QC
Department and Project Site’s QA/QC Unit. They have the full authorities and
responsibilities to perform generally the following:
Prepares QC Plan and Procedures for each Production Units or phases of
activity
Initiate action to prevent the occurrence of non-conformity during the job
execution
Identify and Record any quality problems during Procurement and
Construction phases or all work phases.
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
- Applicable Test Record Sheet approved for use during Test Operations for In-
process and Final Test.
- Identification of test instruments to be used correctly calibrated and set.
- After construction or installation, the work shall be subjected to all final and
inspection required by the Saudi Aramco Standard Specifications.
7.3 PROCEDURES
7.3.1 Shop Drawings Preparation and As-Built Drawings Management
a) Shop drawing preparation required only to facilitate fabrication and
construction activities shall include title block indicating shop drawing nos.,
reference drawing / documents, description, revision no., date and approving
internal authorities. All shop drawings prepared by the responsible draftsman
shall be checked by Supervisor and reviewed by the Site Manager for
endorsement to main Contractor for final review & approval (only on cases if
ever warrants.)
Note: All shop Drawings shall be controlled in a log sheet Register for
monitoring of subsequent changes/revisions.
b) All drawings listed in the drawing control document shall be included in the
“as-built” set. Drawings shall be marked in red for additions or changes, and
green for deletions. All as-built drawings shall be in accordance with the
CLIENT drafting manual and Project Specification.
c) The assigned draftsman responsible for the maintenance of required sets of
IFC drawings for mark-ups and current as-built conditions ensures that;
The Drawing Control Index List is updated to the latest revisions.
Mark-ups on a live set of IFC drawings, MTOs and data sheets are on
latest revised issues to include those instructions from the CLIENT
covering field modification/changes and/or actual conditions.
As-built mark-ups also include those revisions initiated by CONTRACTOR and its
Vendors and/or with official concurrence from the CLIENT.
d) Upon completion of the contract job and prior to issuance of Mechanical
Completion Certificate (MCC), CONTRACTOR shall submit this live set of the
marked-up as-built drawings, MTOs and data sheets to the CLIENT for
review/comments and corrections needed.
e) Any corrections/comments raised by the CLIENT are incorporated in the final
reproduction of as-built mark-up drawings.
f) After initiation of changes, all As-built drawings shall be submitted to the
CLIENT for Final Approval.
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
g) The As-built drawings shall incorporate and mark the location of under-ground
obstructions, existing pipelines, and power cables in the vicinity work sites
encountered.
b) Procedure of Endorsement
A Standard “Site Technical Query” Form (Q-007) is prepared (see Appendix) to be
filled-up by the Originating CONTRACTOR Discipline Engineer/Supervisor for
submission to the CLIENT through CONTRACTOR Technical Support Services
Unit.
The Query’s portion covers the following:
The Query’s Brief Subject item
Brief description of the item as the subject of the query, example:
“Relocating of Lighting Post at the Sidewalk”.
Referenced Contract Document/Dwg. No.
The referenced document number where the subject of query is
encountered.
Site Location/Unit System
The statement of place where the problem is encountered.
Statement of Query
A complete description of the case situation, and can be appended by
an attached sketch drawing and technical narration.
Impact to other Discipline
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
b) Procedure of Endorsement
A standard Form for “Request for Waiver of the CLIENT Standards or
Specification Requirements” is prepared (see Appendix to this section) to be
filled-up by the originating CONTRACTOR QA/QC Supervisor and approval
endorsement of its Construction Site Manager.
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
CONTRACTOR shall ensure that all necessary resources and quality control initiatives
are made available and/or performed based on the Work QCPs and ITPs.
b) Inspection and Test Activity Planning, Scheduling and Implementation, and QC
Reports and Coding
The detailed procedure is comprehensively explained in this Project Quality Plan
Section 6, Preparation and Management of Construction Work Quality Plan specifically
under Paragraph 6.4 and 6.5.
8.8.3 Procedure
a) Compilation of Quality Records, Storage and Retention
a-1. During Procurement Stage
All inspection and test records conducted at Vendor's source by the CONTRACTOR
assigned QC Inspector shall be compiled by the respective QC Inspector and
submitted to the CONTRACTOR Procurement QC Supervisor who is responsible for
consolidation and filing to its respective Inspection Record Book.
a-2. During In-Process Construction / Installation
All inspection and test reports / records and relevant document being used while in
the process of job construction and installation are compiled in provisional book files
per job work disciplines and work areas in accordance with the Inspection and Test
Plan as prepared for the specific project. These will be the sourced back-up quality
record documents to be used for the next milestone phase of the project when it
reached the Plant System Testing and Pre-Commissioning stage prior to Mechanical
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
Completion. These quality records are filed with proper book identification and safely
stored in shelves / cabinets for easy retrievable or traceability. Original copies of
these quality records shall be filed in their assigned book files.
a-3. During Plant System Testing and Pre-Commissioning Prior to Mechanical
Completion.
All plant system test and pre-commissioning quality records shall be organized in
accordance with the Plant Facility / System Mechanical Completion Checklist
Packages which will form part of the whole project’s Pre-Commissioning Plan.
Relevant in-process installation quality checks and test records required to form part
of the Mechanical Completion Checklist Package per Plant System shall be in the
form of “migrated photo copies” in order to retain the original copies intended for
Project Inspection Record Books on a separate indexed form & filing.
a-4. Pre-Commissioning / Commissioning Inspection Record Book (Project Quality
Records)
The final Quality Record documents are packaged based on agreed indexing and
book packaging to be agreed later with the CLIENT.
Work
procedure Qualification Personal
Approval (A) Procedure Qualification
Code Special Process
or Review Approval Approval
(R) Required Required`
Required
Concrete Installation R No No
Structural Bolt R No No
Tensioning
Coatings A No No
9.1 GENERAL
CONTRACTOR Corporate QA/QC Manager and Project QA/QC Manager shall
monitor its Quality System Management by the following QA activities:
- Document Review
- Quality Audits and Quality Surveillance
- Non Conformity Management
- Corrective / Preventive Action(s)
chaired by either the Vice President and/or General Manager which also highlights
the results of the Internal Quality Audits conducted at the project. The Corporate
QA/QC Manager prepares the agenda & outcome of the Management Review
Meeting covering the necessary action plans for quality system improvements.
The project internal audit report is the source information and/or part of the
Management Review results and recommended actions to be presented / submitted
to the CLIENT within 14 days after the actual review date.
9.5 NON-CONFORMITIES
For CONTRACTOR’s Non-Conformities Management of its construction activities, refer
to Section 10 of this Project Quality Plan, which describes comprehensively how non-
Conformances are identified, reported, and the manner of documenting its clearances
and closures. CONTRACTOR’s QA/QC Manager is responsible for the non-
conformities management in this contract job.
NCR issued by the CLIENT shall be resolved by CONTRACTOR following the
procedure. Refer to Section 10 par. 10.5, how external sourced NCRs are resolved
and cleared by CONTRACTOR.
9.7.3 Training
The CONTRACTOR Corp. QA/QC Manager and/or his delegated Site QA/QC
Manager shall indoctrinate their QC Inspectors and other concerned personnel to
ensure their clearer understanding on the following:
Job Specification
Briefings on the CLIENT Standard Documentation
List of the applicable specifications
Inspection / Monitoring
Inspection according to QCP/ITP
RFI/ QMIS issue
Witness/Hold points
Continuous monitoring based on the applicable relevant CLIENT
Specifications.
Material Identification
Surveillance of material identification
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
are taken during interim period and/or after completion of each project. Performances
of the CONTRACTOR services are evaluated using ratios, i.e.:
Man-hours expended per unit of Work or each Equipment Installed.
Average actual Revenue yielded per expended Direct Man-hour.
Actual ratio between total Expended Indirect Man-hour vs. Direct Man-hour
Optional only if possible to account specifically for Major activities that will influence
significant cost deviation to budget.
The above useful data is gathered and acquiring by the cost control unit during the
contract life deviation.
Statistical data is generated from the following:
Numbers of Punch list and NCRs issued by the CLIENT as indication of quality
performance.
Safety Statistics record as reported monthly based on OSHA requirements.
10.4 RESPONSIBILITIES
a) Project QA/QC Manager (Home Office)
Participates on advisory functions covering the investigation of identified non-
conformities and complaints through Non-Conformance Reports (NCRs), or
Corrective Action Requests (CARs) raised by the Originators and seeks/
oversees appropriate resolutions by the concerned action persons for its
remedial actions and closure.
b) Site QC Manager / QC Inspectors
As part of their primary functions, are authorized persons for raising Non-
Conformance Reports (NCRs) to the concerned responsible person of a
production or functional unit/area where the non-conformities/complaints are
identified, and required from them to monitor actions needed for its
resolutions.
The CONTRACTOR QC Manager at Site is the representative of the
CONTRACTOR’s Corporate QA/QC Manager at Site to implement this
procedure at site on proper documentation and reporting required covering
encountered non-conformities at the project site.
c) CONTRACTOR’s Construction Site Manager/
Superintendents/ Supervisors
Are responsible for entertaining identified Non-Conformance items under their
respective areas and pursuing corrective and preventive actions, based on
agreed or appropriate resolutions in order to clear and close those issued
NCRs.
d) Internal Quality Auditors
All pre-selected company’s employees who are trained as internal quality
auditors whose ad-hoc responsibility is to conduct quality management
system auditing to company’s various functional support and production
areas. They are authorized by the management to issue Corrective Action
Requests (CARs) to audited areas where non-compliance to company’s
quality policies and procedures are identified. They are qualified as per the
requirement of Contract Provisions for Quality System Auditors.
10.5 PROCEDURES
10.5.1 Identification of Non-Conformance
In accordance with Contract Requirements, the CONTRACTOR shall exercise
proper control and disposition of identification and documentation of non-
conformances, corrective actions and waivers of contract requirements. These
non-conformances possible occurrences are inadvertent use of design
documents, materials, parts, components, services or workmanship not
conforming to the requirements of the contract.
Source and/or areas where non-conformities are identified from the materials
and/or services supplied by the Vendors/ Subcontractors and the
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
c) The person responsible for the area is responsible for analysis of the root
cause of problem in co-ordination with the person responsible /
knowledgeable on the nature of Problem.
d) Collection of data and statistical analysis shall be done where feasible.
e) The results of this investigation shall be recorded in the “brief statement of
Non-conformance” space provided in the NCR Form. A copy of each NCR
shall be submitted to the CLIENT within 48 hours.
11 PROCUREMENT PLAN
Refer to JEF-DOC-003/PrP “Procurement Plan
SAUDI ARAMCO Southern Area Projects Department Document No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-001/PQP
AR-RIYADH Revision: 01
EASTERN TRADING & CONT. EST. Date: 18 May 2015
PROJECT QUALITY PLAN
Contract No. 3000613310
12.2 References
Defines all relevant document i.e. codes, standards, specifications, etc. to be referred
with for the correct execution of the job to conform with the contract technical
requirements for the specific work item covered by the construction work quality plan
as basis of criteria of acceptance.
- Sec. 3.0 of this PQP
- Sub-Contract Agreement
- Contract Documents, Specifications & Drawings
12.3 Responsibility
Defines the performing units/persons responsible for the correct execution of the job
and required interfaces of Inspection Units/Persons to control and ensure attainment of
the required Quality Standards.
Inspection and Test Plans is the quality plan for each construction work phase
discipline showing in details the methods and timing for examinations, measurement or
tests to assure compliance with contract job requirements. In a matrix presentation, the
ITP shows the following:
Task descriptions
Acceptance criteria (Checked per applicable Specifications, Codes, Standards,
Procedures or IFC Drawing etc.)
Verifying Documents (Referenced Submittals, Test and Inspection Reports,
Certificates, etc.)
Quality Control Activity (Inspection and Test Activity)
Established WITNESS and HOLD point intervention of Clients Inspection from
the planned Inspection and Test activities.
The ITP are supported by suitable and approved certification forms to document all
the test and inspection to be performed during the process of the work. Checklist
and Test Record Sheets shall be the verifying acceptance of each accomplished
tasks as shown in the ITP.
END DOCUMENT