Comparison Fidic Red Book & Iem
Comparison Fidic Red Book & Iem
Comparison Fidic Red Book & Iem
3
Plant, Materials and Workmanship
Setting Out
FIDIC RED BOOK IEM
Clause 4.7 Clause 13
If the Contractor suffers delay or incurs cost If any time during the progress of the works
from executing work which was necessitated any error shall appear in the position, levels,
by an error in this item, the contractor could alignment of any part of the works, the
not reasonably have discovered such error Contractor on being required so to do by the
and avoided this delay. The contractor shall Engineer or the Engineer’s Representative
give notice to the Engineer and shall be shall at his own cost unless such error based
entitled subject to Sub Clause 20.1: on incorrect data supplied.
An extension of time for any such
delay.
Payment of any such Cost plus
reasonable profit, which shall include
in the Contract Price.
4
considers himself to make an extension of there are any requests from the contractor,
time. Besides that, they need to follow the sub-contractor or nominated sub-contractor
decision and the Contractor. Before the followed with the reason which affects their
Contractor wants to entitle the Time for work that has been stating in the contract
completion the contractor must give notice .Moreover, in IEM Engineer will estimate the
to the engineer. delay of the extension of time and also
engineer will issue the condition.
Insurance of Work
FIDIC RED BOOK IEM
Clause 18.2 Clause 33 and 34
In FIDIC, insurance of work and contractor It has a bit similar with the IEM in clause 34
equipment clause 18.2 said that insurance Insurance of work, which all the production
that is provided by the contractor must be of the insurance policy with or without an
agreed with the general term by the excess clause needs to be effected with an
employed. insurance that has been agreed with by the
employer. But for IEM all of the production
In FIDIC all the insurances need to include all must be approved by the engineer and
the detail followed with particular condition contractor.
such as the tenderer will estimate the
insurance followed with their wish for their In IEM for personal injuries and damage
protection. Besides that, the employer property clause 33, they are cover any
should find the most difficult that can be respect personal injuries or dead arriving out
effected the insurance. For example the or if there are any reason of the execution of
contractor equipment and also the the works. The contractor will arrange such
subcontractor equipment. insurance to incorporate such as damage by
the contractor or subcontractor to the
property. Moreover, the insurance is also
cover the architect, surveyor, engineer and
also the third parties. This insurance will only
cover for the whole construction period. For
the insurance of works, the insurance cover
the damage such as the storm, flood lighting,
explosion, fire and all the series services.
Arbitration
5
commercial which has a lot of advantage shall arise. Besides that, the Engineer needs
with their litigation in national court. to give a decision in writing that have been
Moreover, the arbitration is compatible with issued or with any subject that is binding on
all of the provision in clause 20 with an all the parties until all the work is complete. In
the rule are from the International Chamber addition, if the engineer fails to do that in 48
of Commerce the (ICC)which all of that are days the entire request will be dissatisfied.
base at 38 courses, Albert, Ler , 75008 Paris, All the arbitration should be conduct under
France. In addition, there is no standard the provision of the clause accordance with
form of multi-party arbitration clause for the Rule for arbitration of the institution of
international use. Engineer Malaysia. Finally, all the award of
the arbitration shall be fine between the
parties.
Payment
6
Prime Cost and Provisional Cost
7
Variation and Adjustment
Fluctuation of Price
8
Completion of Work
FIDIC RED BOOK IEM
Clause 8.2 Clause 39
The clause stated that the obligation of the The Contractor shall complete the whole
Contractor to complete the whole of the work as agreed in the contract before or on
works, within the Time of Completion Date of Completion, If any extended time
measured from the Commencement Date. needed, refer Clause 43. As the project is
complete, there will be Defect Liability
Period. Hence, the Engineer fully satisfied
with the project then the Engineer will issue
Certificate Practical Completion.
Day Work
FIDIC RED BOOK IEM
Clause 13.6 Clause 17
Day work cannot be measured because we The labour will not working on the following
cannot predict what will happen in the days:
future. The work shall be evaluated Once a week for rest day
according to the Day work Schedule. The Any public holiday according to the State
Schedule is not in the Tender Document. Between the hours of five in the evening and
Hence, the Contract must include the Day eight in the morning
work Schedule in his own proposal. The
objective Day work Schedule is to keep
records to support his claims when the work
is done. So that the Contractor entitled to
receive payment of cost.