Productivity Rates: Sl. No. Description Manpower Equipment Unit Output Temporary Facilities
Productivity Rates: Sl. No. Description Manpower Equipment Unit Output Temporary Facilities
Productivity Rates: Sl. No. Description Manpower Equipment Unit Output Temporary Facilities
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
Hollow Block
a. 100mm Hollow Block upto 2.5m Height 1M + 1H Nos./Day 150
b. 100mm Hollow Block -2.5m to 6m Height 1m + 2H Nos./Day 140
c. 150mm Hollow Block - upto 2.5m Height 1M + 1H Nos./Day 150
d. 200mm Hollow Block - upto 2.5m Height 1M + 1H Nos./Day 180
e. 200mm Hollow Block - 2.5m to 6m Height 1M + 2H Nos./Day 140
f. 200mm Block Work above 6m Height 1M + 2H Nos./Day 100
g. 200mm Block Work including pointing 1M + 1H Nos./Day 120
Claustra Block
a. Claustra Block 200 x 200 1M + 1H m²/Day 10
b. Claustra Block 150 x 150 1M + 1H m²/Day 8
05 METALS
STRUCTURAL METAL FRAMING
Steel Structure
a. Painting of steel structure columns 1P + 1H m²/Day/Coat 50
b. Painting of steel structure rafters 1P + 1H m²/Day/Coat 40
Erection of steel structure main frame (Eave Height upto
c. 3E + 3H m²/Day 250
6m span upto 25m)
Erection of steel structure main frame (Eave Height more
d. 3E + 3H m²/Day 175
than 6m span upto 36m)
e. Fixing of Single Skin Sheet (Roof) 3E + 3H m²/Day 350
f. Fixing of single skin sheet (Walls) 3E + 3H m²/Day 150
g. Single skin with fibre glass insulation (Roof) 3E + 3H m²/Day 250
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
Bitumin Paint
a. Cold Bituminuous Painting 1H m²/Day/Coat 100
b. Hot Bituminous Painting 2H m²/Day/Coat 60
Bituminous Membrane
a. Bituminous Membrane + Protection Board 1C + 1H m²/Day 30
SEALERS
Construction Joint
a. Flexel Board 1C + 1H Rm/Hr 18
b. Sealant 1H Rm/Hr 7
09 FINISHES
PLASTER
Internal Plaster
a. Ceiling Plaster 1M + 1H m²/Day 10
b. Wall plaster upto 3m Height 1M + 1H m²/Day 20
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
Threshold
a. Threshold 1M Rm/Day 10
False Ceiling
a. False Ceiling - Suspended Type 1C + 1H m²/Day 30
10 MECHANICAL
PIPE & FITTINGS
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
11 ELECTRICAL
RACE WAYS
Race Ways
a. Conduits 1El + 1H Rm/Day 50
b. Trunking 1El + 1H Rm/Day 50
CONDUCTORS & GROUNDING
Conductors & Grounding
a. Laying Cables 1El + 2H Rm/Day 150
WIRING
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
BOARDS
Boards
a. D.B's 1El + 1H Nos/Day 2
b. M.D.B's 1El + 1H Nos/Day 1
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber