Productivity Rates: Sl. No. Description Manpower Equipment Unit Output Temporary Facilities

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

1 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


01 GENERAL REQUIREMENT
TEMPORARY FACILITIES

a. Watchman & Curing (Duration x 2H) Day ---


(Dhs.Contract Value/
b. Site Cleaning 50,000) Helper-Day Day 1
c. Fencing 1C + 2H + 1P Rm/Day 50
d. Fixing of Light Weight Scaffolding 1C + 1H m²/Day 70
02 SITE WORK
EARTH WORK
Excavation
a. Soft Soil (Hand Tools) 1H Hand Tools m³/Day 3
b. Hard Soil (Hand Tools) 1H Hand Tools m³/Day 1
c. Soft Soil --- Shovel m³/Hr 40
d. Hard Soil --- Shovel m³/Hr 25
e. Soft Soil --- JCB m³/Hr 20
f. Hard Soil --- JCB m³/Hr 10
Backfilling
a. Filling in foundation, plinth --- Shovel m³/Hr 30
b. Level, Compaction 1H Roller Compr. m²/Day 100
c. Spreading 200 mm layer (Subkha, Road Base) --- Shovel m³/Hr 100
d. Compaction 200 mm layer (Subkha, Road Base) 1H Roller Compr. m²/Day 200
PAVING & SURFACING
Interlock Paving
a. Compaction/ Levelling 2H Roller Compr. m²/Day 200
b. Spreading Sand and Brushing 2H m²/Day 200
c. Laying Tiles 1M + 2H m²/Day 60
d. Filling, Compaction 1H Plate Compr. m²/Day 150
Precast Kerb Stone
a. Excavation & Blinding for kerbstone 1H R.M/Day 10
b. Laying Kerbs 1M + 2H R.M/Day 35

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


2 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


c. Kerb stone on curved lines 1M + 1H R.M/Day 15
d. Hunching 1M + 1H R.M/Hr 20

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


3 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


03 CONCRETE
CONCRETE FORMWORK
Shuttering (with supports)
a. Shuttering Of Blinding 1C + 1H m²/Day 35
b. Shuttering Of Footing (Plywood) 1C + 1H m²/Day 15
c. Shuttering Of Footing (Plates) 1C + 1H m²/Day 20
d. Shuttering Of Stub Column 1C + 1H m²/Day 5
e. Shuttering Of Strap/ Tie Beam (Plywood) 1C + 1H m²/Day 12
f. Shuttering Of Strap/ Tie Beam (Plates) 1C + 1H m²/Day 20
g. Shuttering Of Wall 1C + 1H m²/Day 14
h. Shuttering Of Column 20 x 20 1C + 1H m²/Day 10
I. Shuttering Of Column 20 x 40 1C + 1H m²/Day 10
j. Shuttering Of Beam with support 1C + 1H m²/Day 12
k. Shuttering Of Roof Slab 1C + 2H m²/Day 10
l. Shuttering Of Lintel 1C + 1H m²/Day 6
m. Shuttering Of Copying beam 20 x 20 cm 1C + 1H m²/Day 6
n. Shuttering Of Parapet 1C + 1H m²/Day 12
o. Shuttering Of Arch Lintel 1C + 1H m²/Day 6
p. Expansion Joints/ Ground Slab 1C + 1H L.M/Day 70
q. Shuttering of beam& column for 8m to 12m high 1C + 1H m²/Day 8
r. Shuttering of staircase 1C + 1H m²/Day 12
s. De-shuttering works 20% of shuttering works
CONCRETE REINFORCEMENT
Reinforcement (Tightening for Cut & Bend Steel)
a. Reinforcement of Footing 1SF + 1H Kg/Day 400
b. Reinforcement of Stub Column 1SF + 1H Kg/Day 250
c. Reinforcement of Strap Beam 1SF + 1H Kg/Day 300
d. Reinforcement of Tie Beam 1SF + 1H Kg/Day 350
e. Reinforcement of Wall 1SF + 1H Kg/Day 400
f. Reinforcement of Column 1SF + 1H Kg/Day 300

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


4 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


g. Reinforcement of Beam 1SF + 1H Kg/Day 300
h. Reinforcement of Solid Slab 1SF + 1H Kg/Day 300
I. Reinforcement of Lintel 1SF + 1H Kg/Day 150
j. Reinforcement of Copying beam 20 x 20 cm 1SF + 1H Kg/Day 200
k. Reinforcement of Parapet 1SF + 1H Kg/Day 300
l. Reinforcement of Arch Lintel 1SF + 1H Kg/Day 150
m. Reinforcement of Staircase 1SF + 1H Kg/Day 250
Mesh Reinforcement
a. Mesh Reinforcement 1SF + 2H m²/Day 300

CAST IN PLACE CONCRETE


Casting Concreting (Readymix)
a. Cast. Blinding 5cm 1M + 2H m²/Day 30
b. Cast. Blinding 10cm 1M + 2H m²/Day 40
c. Cast. Blinding 5cm, 10cm 2M + 4H Pump m²/Day 250
d. Cast. Of Footing 2M + 4H m³/Day 40
e. Cast. Of Footing (Pump) 3M + 8H Pump m³/Day 120
f. Cast. Of Strap/ Tie Beam 1M + 6H m³/Day 20
g. Cast. Of Tie Beam (Pump) 2M + 6H Pump m³/Day 50
h. Cast. Of Ground Floor Slab 10cm 3M + 5H m³/Day 30
I. Cast. Of Ground Floor Slab 15cm 3M + 5H m³/Day 45
j. Cast. Of Ground Floor Slab 20cm 3M + 5H m³/Day 60
k. Cast. Of Wall 1M + 1C + 3H Pump m³/Day 40
l. Cast. Of Column 1M + 4H m³/Day 4
m. Cast. Of Beam of Slab 1M + 4H m³/Day 12
n. Cast. Of Roof Slab 2M + 2C + 5H Pump m³/Day 50
o. Cast. Of Lintel 1M + 2H Nos./Hour 4
p. Cast. Of Copying beam 20x20cm (upto 2.5m) 1C + 5H RM/Day 150
q. Cast. Of Copying beam 20x20cm (above 2.5m) 1C + 5H RM/Day 60
r. Cast. Of Parapet 1M + 1C + 4H Pump m³/Day 10

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


5 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


s. Cast. Of Arch Lintel 1M + 3H m³/Day 5
t. Cast. Of Neck Column 1M + 3H m³/Day 4
u. Cast. Of Staircase 1C + 1H m³/Day 12
04 MASONRY
BLOCK WORK
Solid Block
a. 200mm Solid Block upto 2.5m Height 1M + 2H Nos./Day 140

Hollow Block
a. 100mm Hollow Block upto 2.5m Height 1M + 1H Nos./Day 150
b. 100mm Hollow Block -2.5m to 6m Height 1m + 2H Nos./Day 140
c. 150mm Hollow Block - upto 2.5m Height 1M + 1H Nos./Day 150
d. 200mm Hollow Block - upto 2.5m Height 1M + 1H Nos./Day 180
e. 200mm Hollow Block - 2.5m to 6m Height 1M + 2H Nos./Day 140
f. 200mm Block Work above 6m Height 1M + 2H Nos./Day 100
g. 200mm Block Work including pointing 1M + 1H Nos./Day 120
Claustra Block
a. Claustra Block 200 x 200 1M + 1H m²/Day 10
b. Claustra Block 150 x 150 1M + 1H m²/Day 8
05 METALS
STRUCTURAL METAL FRAMING
Steel Structure
a. Painting of steel structure columns 1P + 1H m²/Day/Coat 50
b. Painting of steel structure rafters 1P + 1H m²/Day/Coat 40
Erection of steel structure main frame (Eave Height upto
c. 3E + 3H m²/Day 250
6m span upto 25m)
Erection of steel structure main frame (Eave Height more
d. 3E + 3H m²/Day 175
than 6m span upto 36m)
e. Fixing of Single Skin Sheet (Roof) 3E + 3H m²/Day 350
f. Fixing of single skin sheet (Walls) 3E + 3H m²/Day 150
g. Single skin with fibre glass insulation (Roof) 3E + 3H m²/Day 250

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


6 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


h. Single skin with fibre glass insulation (Wall) 3E + 3H m²/Day 100
I. Sandwich panels (Roof) 3E + 3H m²/Day 250
j. Sandwich panels (Wall) 3E + 3H m²/Day 150
k. Corner Flashing & Trims, etc 1E + 3H Rm/Day 80
l. 4m x 4m Double Sliding Door 1E + 3H Nos. 1
m. Wall or roof opening + frames (1.0m x 1.0m) 1E + 3H Nos. 8
n. Ridge Ventilator 1E + 3H Nos./Day 6
o. Gutter/ Down Spout 1E + 3H Rm/Day 70
07 MOISTURE THERMAL CONTROL
WATER PROOFING & DAMP PROOFING
Polythene Sheets
a. Polythene under footings 1C + 1H m²/Day 200
b. Polythene under slab 1C + 1H m²/Day 1000
c. Polythene under tie beam 1H Rm/Day 200

Bitumin Paint
a. Cold Bituminuous Painting 1H m²/Day/Coat 100
b. Hot Bituminous Painting 2H m²/Day/Coat 60
Bituminous Membrane
a. Bituminous Membrane + Protection Board 1C + 1H m²/Day 30

SEALERS
Construction Joint
a. Flexel Board 1C + 1H Rm/Hr 18
b. Sealant 1H Rm/Hr 7
09 FINISHES
PLASTER
Internal Plaster
a. Ceiling Plaster 1M + 1H m²/Day 10
b. Wall plaster upto 3m Height 1M + 1H m²/Day 20

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


7 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


c. Wall plaster 3m to 6m Height 1M + 2H m²/Day 17
d. Wall plaster above 6m Height 1M + 2H m²/Day 15
e. Fixing of Plaster Mesh 1C + 1H Rm/Day 90
f. Fixing of Corner beed 1M + 1H Rm 30
External Plaster
a. Wall plaster upto 3m Height 1M + 1H m²/Day 20
b. Wall plaster 3m to 6m Height 1M + 2H m²/Day 18
c. Wall plaster above 6m Height 1M + 2H m²/Day 15
TILES
Mosaic
a. Floor Mosaic Tiles 1M + 1H m²/Day 15
b. Mosaic Skirting 1M + 1H Rm/Day 40
c. Mosaic Steps (Riser & Tread) 1M + 1H Rm/Day 14
d. Mosaic Polishing 1Po + 1H m²/Day 100
Ceramic
a. Fixing of Ceramic Wall Tiles (Glue Type) 1M + 1H m²/Day 10
b. Grouting of Ceramic Wall Tiles 1M + 1H m²/Day 30
c. Fixing of Ceramic Wall Tiles (Cement Mortar Type) 1M + 1H m²/Day 8
d. Fixing of Ceramic Floor Tiles 20 x 20cm 1M + 1H m²/Day 12
e. Fixing of Ceramic Floor Tiles 30 x 30cm 1M + 1H m²/Day 15
f. Fixing of Ceramic Floor Tiles 50 x 50cm 1M + 1H m²/Day 20
g. Grouting of Ceramic Floor Tiles 1M + 1H m²/Day 40
h. Ceramic Skirting 1M + 1H Rm/Day 30
PVC Tiles
a. PVC Tiles 1M + 1H m²/Day 35
b. PVC Skirting 1M + 1H Lm/Day 40
Marble
a. Marble Wall 1M + 1H m²/Day 6
b. Marble Floor 1M + 1H m²/Day 15
c. Marble Skirting 1M + 1H Rm/Day 30

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


8 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


d. Marble Steps (Riser & Treads) 1M + 1H Rm/Day 10
Floor Screed (50mm)
a. Floor Screed (50mm) 1M + 1H m²/Day 50
b. Cement Skirting 1M + 1H Rm/Day 25
Wooden Skirting
a. Timber 1C + 1H Rm/Day 100

Threshold
a. Threshold 1M Rm/Day 10

False Ceiling
a. False Ceiling - Suspended Type 1C + 1H m²/Day 30

Dry Wall Partition


a. Dry wall Partition 1C + 1H m²/Day 20

PAINTING & WALL COVERINGS


Tyrolene (Cullamix)
a. Tyrolene over plastered surface 1M + 1H m²/Day/Coat 100
b. Tyrolene over block wall 1M + 1H m²/Day/Coat 100
Normal Paint (Emulsion/Oil)
a. Primer 1P m²/Day/Coat 200
b. Stucco (Putty) 1P m²/Day/Coat 80
c. Emulsion Paint 1P m²/Day/Coat 100
d. Oil Paint 1P m²/Day/Coat 60
Epoxy Painting
a. Epoxy Painting 1P + 1H m²/Day/Coat 50

10 MECHANICAL
PIPE & FITTINGS

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


9 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


Copper & PVC Pipes
a. ½" to 1" Copper Pipe (Hot Water) 1Pl + 1H Rm/Day 12
b. ½" to 1½" PVC Pipe 1Pl + 1H Rm/Day 20
c. 2" to 3" PVC Pipe 1Pl + 1H Rm/Day 75
d. 4" to 6" PVC Pipe 1Pl + 1H Rm/Day 60
PLUMBING FIXTURES
Plumbing Fixtures
a. Shower Tray 1Pl + 1H Nos/Day 2
b. Kitchen Sink 1Pl + 1H Nos/Day 2
c. Urinals + Partition 1Pl + 1H Nos/Day 3
d. Wash Basin 1Pl + 1H Nos/Day 2
e. W/C Asian 1Pl + 1H Nos/Day 2
f. W/C Western 1Pl + 1H Nos/Day 2
g. Bidet 1Pl + 1H Nos/Day 2
h. Booster Pump 1Pl Nos/Day 1
I. Manhole 60cm to 90cm 1M + 1H Nos/Day 2
PLUMBING APPLIANCES
Plumbing Appliances
a. Water Heater 1Pl + 1H Nos/Day 2

11 ELECTRICAL
RACE WAYS
Race Ways
a. Conduits 1El + 1H Rm/Day 50
b. Trunking 1El + 1H Rm/Day 50
CONDUCTORS & GROUNDING
Conductors & Grounding
a. Laying Cables 1El + 2H Rm/Day 150

WIRING

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.


10 of 10

PRODUCTIVITY RATES Issued 1-Sep-11

SL. NO. DESCRIPTION MANPOWER EQUIPMENT UNIT OUTPUT


Wiring
a. Wiring 1El + 1H Rm/Day 300

BOARDS
Boards
a. D.B's 1El + 1H Nos/Day 2
b. M.D.B's 1El + 1H Nos/Day 1

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber

- One Day is considered as 8 working hours.

You might also like