Chapter 19 Piping Handbook-Done
Chapter 19 Piping Handbook-Done
The hydrostatic and pneumatic tests are pressure tests that challenge the
system above the design pressure. But they do not replace pressure design of pip-
ing or components. The pipe size, fitting and component rating must still be sized
in accordance with the design rules or qualified by proof testing to a pressure
higher than the system hydrostatic or pneumatic test pressure.
In the oil and gas pipeline industries, hydrostatic testing is used to assess the
fitness-for-service of a pipeline, based on fracture mechanics analysis. The logic
being that if a pipeline can withstand a certain hydrostatic pressure it can be con-
cluded that it does not contain flaws larger than a certain size. In Chapter 21 we
will see that a pipeline tested at a hoop stress of 100% its specified minimum yield
stress (SMYS) will not contain a flaw longer or deeper than the limits of ASME
B31G, otherwise the line would have failed at these flaws during hydrotest.
There are several methods for leak and pressure testing a piping system.
ASME B&PV Code, Section V Article 10, provides a good reference for leak
testing techniques. Following are the most common leak test methods used for
industrial piping systems and pipelines.
Bubble test (ASME B&PV Section V Article 10, Appendix I): air or an inert
gas is introduced in the pipe, at a relatively low pressure, in the order of 15 psig. A
bubble solution is applied at welds and joints. The joints are then visually in-
spected for signs of bubbles, which would indicate a leak. The bubble solution
may contain inhibitors to avoid corrosion. The sensitivity of the method is in the
order of 10"4 to 10"5 std. cc/sec.
Vacuum box (ASME B&PV Section V Article 10, Appendix II): a bubble
forming solution is applied at welds and joints. The weld or joint is then covered
with a sealed box with transparent windows, as shown in Figure 19-1. A slight
vacuum of about - 2 psid is drawn into the box and held for a short time, typically
less than a minute. The joints in the vacuum box are then visually inspected for
signs of bubbles, which would indicate a leak. The method is particularly well
suited for the leak testing girth welds in pipes. The sensitivity of the method is in
the order of 1 to 10"2 std. cc/sec.
Sensitive leak test (ASME B&PV Section V Article 10, Appendix IV and
V): the sensitive leak test technique consists in detecting leakage of a tracer gas,
such as Helium or SF6, into or out of the tested system [ASTM E 432]. There are
four sensitive leak test methods, illustrated in Figure 19-2. Either a gas is intro-
duced inside the component and the air is sampled around it for traces of gas
(sniffing probe or bell jar), or the component is immersed in gas or joints are
sprayed with gas, and the air inside the component or system is sampled for traces
of gas (hood or tracer spray). A detector probe is used to detect small amounts of
leakage by ionization and magnetic field deflection of the tracer gas. The sensitiv-
The correction Stest / Sdesign has an important practical consequence when hy-
drostatically testing piping systems in the field: the leakage of valve packing dur-
ing hydrotest. Indeed, take for example a carbon steel system with a design tem-
perature of 650°F. The correction factor is 20 ksi / 17 ksi = 1.18. The piping sys-
tem will be tested at a pressure of 1.5 x 1.18 x Pdesign. Yet, the vendor has only
tested the valve at 1.5 times its rated pressure [ASME B16.34]. Therefore, if the
system design pressure is equal to the valve pressure rating, the valve will be ex-
posed for the first time to a pressure 1.5 x 1.18 x Prated, in this case the field hy-
Up to the 1950's, many gas transmission pipelines were tested with air or
gas slightly above maximum operating pressure. As a result of failures, operating
and insurance companies and regulators imposed a hydrostatic test at 1.1 to 1 .4
times the maximum allowable operating pressure (MAOP) depending on the loca-
tion class (population density) [ASME B31.8, 49CFR192].
A pig is inserted in front of the hydrostatic water to sweep all the air out of
the line through open-air vent valves at high points. This will insure that the pipe-
line is full of liquid, with no trapped air pockets. There are three reasons why air
has to be removed when hydrotesting a pipeline: (1) to reduce the energy trapped
in the line, so that a leak will not turn into a large rupture (Chapter 4), (2) to avoid
pressure fluctuations caused by pumping water against trapped air bubbles
(Chapter 9), (3) to maintain the siphon effect to balance static heads caused by ups
and downs in elevation. A pipeline can be tested in sections, to reuse the test wa-
ter.
itae = 0.0408 d2 L
Vtes, = volume of test water to fill and pressurize the line, gallons
Vpipe = pipe volume, gallons
FWP = correction factor for water compressibility
Fpp = correction factor pipe volume increase with pressure
FpT = correction factor for pipe and water temperature change
D = pipe inner diameter, in
L = pipe length, ft
P = test pressure, psi
D = pipe outside diameter, in
T = pipe temperature, °F
FWT = factor 1.0 at 60°F [McAllister]
Pneumatic test: the piping system is filled with air or gas, and slowly pres-
surized to a pressure specified by the construction code, such as 110% of the de-
sign pressure for ASME B31.3 pneumatic tests. An arrangement of the test assem-
bly is shown in Figure 19-3, at bottom. Note the pressure regulator, the isolation
valve, the mandatory safety valve, the easily visible pressure gages, and the barrier
or rope placed as a safety precaution. Joints are inspected for evidence of leaks,
either using bubble solution or by monitoring the pressure drop.
Pressure change test (ASME B&PV Section V Article 10, Appendix VI):
this pressure testing technique is also referred to as pressure decay (rate of fall)
test. The system is pressurized, typically with water, and sealed. The pressure is
monitored at least every hour for large systems, during a sufficiently long period
of time to detect any pressure drop that would indicate leakage. For testing small
volumes (such as a small vessel) 15 minutes may be sufficient. The sensitivity of a
rate of fall test is 1 to 10"2 std. cc/sec. Note that the rate of fall has to be corrected
because the pressure in the sealed system will increase if the ambient temperature
increases and vice-versa. The increase in pressure due to a temperature rise AT of
a trapped liquid can be obtained by solving the following set of algebraic equa-
tions [Mohitpour, McAllister]
A-BC+D=0
A = d2 L F AT
For vacuum systems, the test is reversed, and the pressure increase (rate of
rise) would be measured to detect in-leakage. The sensitivity of a rate of rise test is
in the range of 1 to 10~5 std. cc/sec.
In-service leak test: the in-service leak test is a visual inspection of pipe
joints during system startup, at normal operating pressure.
Neither the constructor nor the owner has much latitude when it comes to
leak or pressure testing. The type of test and the test pressure are typically speci-
fied by the construction code, federal, state or local regulations. In the construction
of pressure vessels or piping systems, pressure testing is typically a hold point
witnessed by the owner's inspector, or a third party inspector. Leak testing must
include all the new joints of a piping system. Even if new piping subassemblies
are tested in the pipe shop, the field joints between these subassemblies must be
tested in the field.
hi power and chemical process plant piping, the leak test is a pressure test
typically a hydrostatic test at 150% of the design pressure. For systems with low
design pressure, typically below 150 psi, and non-flammable, non-toxic fluids, the
pressure test may be replaced by an in-service leak test during system startup, if
permitted by the construction code or the applicable regulation. For example, an
in-service leak test is typical for building services and in non-critical process sys-
tems operating below 150 psi and 366°F. In industrial process plants, for piping
Leak testing of gas pipelines and distribution systems depends on the loca-
tion of the pipeline and the operating hoop stress. For a hoop stress below 100 psi,
an in-service soap bubble leak test is often sufficient. For hoop stresses above 30%
of yield, the pipeline is hydrostatically tested at pressures ranging from 110% to
140% of design pressure, depending on the pipeline location [49 CFR 192, ASME
B31.8].
Keep in mind that the hydrostatic test pressure is the minimum pressure to
be achieved in the system, therefore, because of elevation heads, low points will
see a pressure in excess of the hydrostatic test pressure. But in no case should the
hydrostatic hoop stress in the pipe exceed its yield stress or, preferably, 90% of the
yield stress, except when the hydrotest is used as a means to check for flaws in
pipelines (Chapter 21).
Table 19-1 Dew Point in Air (°F), given Ambient Temperature and Humidity
Humidity % 30°F 50°F 70°F 80°F
90% 28 47 67 87
70% 22 40 60 78
50% 15 31 50 67
40% 11 26 43 61
30% 4 20 36 52
19.5 ISOLATION
High-pressure pipe stoppers, discs or pistons with neoprene seal, have been
used to isolate sections for test pressures as high as 5000 psi, Figure 19-4. Line
stops, Figure 19-4 bottom, can be inserted using hot taps (Chapter 23). They have
been used to isolate pipelines with diameter as high as 36" and pressures as high
as 1000 psi. Plugs with inflatable seals have been used in subsea pipelines [Far-
que].
'^ f
\
. , . v, . K ~ ~~
ZZJjZA
; ; ! L!
Small digs can be made to locally expose the pipe, or manholes used to
place listening devices to detect sound that will indicate leaks. To isolate the leak
in a buried line, it may be necessary dig and cut the line at mid-point, and hy-
drostatically test each half of the line. A leaking half would in turn be divided in
two halves and the procedure is repeated until the leaking area is isolated. Alter-
natively, a freeze plug may be used, as described section 19.5, to isolate pipe sec-
tions.
19.7 REFERENCES
49CFR192, Transportation of Natural and Other Gas by Pipeline: Minimum Federal Safety,
Code of federal Regulations, Washington, DC.
API 598, Valve Inspection and Testing, American Petroleum Institute, Washington, D.C.
API 1110, Pressure Testing of Liquid Petroleum Pipelines, American Petroleum Institute,
Washington, DC.
ASME B31.4, Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liq-
uids, American Society of Mechanical Engineers, New York, NY.
ASME B31.8, Gas Transmission and Distribution Piping Systems, American Society of
Mechanical Engineers, New York, NY.
ASME B16.34, Valves - Flanged, Threaded, and Welding End, American Society of Me-
chanical Engineers, New York.
ASME Boiler and Pressure Vessel Code, Section V, Article 10 Leak testing, ASME, New
York.
ASTM E 432, Standard Recommended Guide for the Selection of a Leak testing Method,
American Society for Testing and Materials, West Conshohocken, PA.
ASTM E 479, Recommended Guide for Preparation of a Leak testing Specification, Ameri-
can Society for Testing and Materials, West Conshohocken, PA.
Bowen, R.J., et. al., Pipe Freezing Operations Offshore - Some Safety Considerations, Off-
shore Marine and Arctic Engineering Symposium, Volume V Pipeline Technology, ASME,
1996.
Bryce, P.W., et. al., Leak-Detection System to Catch Slow Leaks in Offshore Alaska Line,
Oil & Gas Journal, December 9, 2002.
EPRI, Freeze Sealing (Ice Plugging) of Piping, report TR-016384R1, Electric Power Re-
search Institute, November, 1997.
Farque, J.A., Remotely Operated Hydroplug Keeps Vital Pipeline Online, Pipeline & Gas
Journal, February, 1999.
FCI, Flow Control Institute, Control Valve Seat Leakage, ANSI/FCI 70-2, Cleveland, Ohio.
Howard, G.J., The Ice-O-Lator: A Proven Way to Determine Pipeline Leaks, OCG Journal,
April 19, 1987.
McAllister, E.W. editor, Pipelines Rule of Thumb Handbook, Gulf Publishing, Third Edi-
tion.
Mohitpour, M, Golshan, H., and Murray A., Pipeline Design and Construction A Practical
Approach, ASME Press, New York.
Ziu, C.G., Handbook of Double Containment Piping Systems, McGraw Hill, New York.