JURNAL
JURNAL
JURNAL
1
Mahasiswa Teknik Sipil, Fakultas Teknik Sipil dan Perencanaan, Universitas Islam Indonesia
Email: [email protected]
2
Staf Pengajar Program Studi Teknik Sipil, Fakultas Teknik Sipil dan Perencanaan, Universitas
Islam Indonesia
Email: [email protected]
Abstract: In building a project, project management is one of the things that must be
considered. There are three things that affect the success of a project, namely quality, time, and
cost. So that planning a project can be better designed and implementation can be more easily
controlled. Quality and time are considered not only during implementation but during
planning. There are a number of things that need to be considered in estimating costs and time
during planning. One of them is by determining what method or software to use. This research
began by collecting data on the KUA development project in Kotagede, Yogyakarta in the form
of a budget and scheduling plan. The data that has been obtained is recalculated using the
iBuild application. The total RAB results in iBuild are compared with project data. The total
budget plan for iBuild is 0.03% greater than project data. The calculation of the cost budget
plan in the project document amounted to Rp 1,098,692,000 then after calculating the iBuild,
the total budget plan was Rp. 1,099,773,000. The difference occurs due to some errors in the
project data when designing using Ms.Excel. In designing Rab's calculations and scheduling an
estimator need to consider time and cost. The estimator can consider the cost and time of
planning by choosing or using the right method for planning, especially in calculating RAB and
scheduling. In the work of designing the right method selection can minimize the
implementation costs and the length of work.
Keywords: cost estimation, time estimation, iBuild, ms.excel