Basharat Ali

From: Ajaz Ali <[email protected]>


Sent: Sunday, September 29, 2019 1:21 PM
To: 'Basharat Ali'
Subject: FW: Modify Piping to close the WDR-M-2500

fyi

From: Patricio Bueno Velazquez [mailto:[email protected]]


Sent: Saturday, September 28, 2019 5:07 PM
To: Karray, Moaez (GE Power, Non-GE) <[email protected]>; 'Zubair Ahmed' <[email protected]>
Cc: Ajaz Ali <[email protected]>; 'Waqar Ali' <[email protected]>; Jose Antonio Rosa Carrasco <[email protected]>; Pelser, Barend (GE Power, consultant)
<[email protected]>
Subject: Re: Modify Piping to close the WDR-M-2500

I think this is not extra work, as per the contract all the drains and vents must be addressed to a safety area….
Please change and included in welding book….

Patricio Bueno Velázquez- Mechanical Manager


ABENGOA
Waad Al Shamal ISCC Power Plant.
Phone: ES 0034603711837 ARAB +966 0550805583
[email protected]
P Eco-Tip: Printing e-mails is usually a waste.

De: "Karray, Moaez (GE Power, Non-GE)" <[email protected]>


Fecha: sábado, 28 de septiembre de 2019, 12:50
Para: 'Zubair Ahmed' <[email protected]>
CC: Ajaz Ali <[email protected]>, 'Waqar Ali' <[email protected]>, Jose Antonio Rosa Carrasco <[email protected]>, "Pelser, Barend (GE
Power, consultant)" <[email protected]>, Patricio Bueno Velazquez <[email protected]>, "Karray, Moaez (GE Power, Non-GE)"
<[email protected]>
Asunto: Modify Piping to close the WDR-M-2500

Caution:This email has been originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.

1
Dear Zubair,

Could you please send us your estimation to close the WDR-M-2500 by rotating the outlet of the pipe, place it parallel to the engine and add an extra elbow pointing to the
ground as per below sketch.

Thank you
Regards,
Moez