7364M Main Propeller Installation Manual 2019 09-11-040022
7364M Main Propeller Installation Manual 2019 09-11-040022
7364M Main Propeller Installation Manual 2019 09-11-040022
5 Technical Data
6 Accessories
7 Alarm System
8 Appendix – Drawings
10 Appendix – Pre-commissioning
Report
TABLE OF CONTENTS
1. RECEIPT AND STORAGE
1.1. INTRODUCTION
1.2. SAFETY
1.3. GENERAL HAZARD INFORMATION
1.4. PRESSURIZED AIR AND WATER
1.5. FLUID PENETRATION
1.6. CONTAINING FLUID SPILLAGE
1.7. LINES, TUBES AND HOSES
1.8. ASBESTOS INFORMATION
1.9. DISPOSE OF WASTE PROPERLY
1.10. BURN PREVENTION
1.11. OILS
1.12. BATTERIES
1.13. FIRE PREVENTION AND EXPLOSION PREVENTION
1.14. FIRE EXTINGUISHER
1.15. LINES, TUBES, AND HOSES
1.16. CRUSHING PREVENTION AND CUTTING PREVENTION
1.17. MOUNTING AND DISMOUNTING
1.18. BEFORE STARTING THE PROPULSION EQUIPMENT
1.19. STARTING THE PROPULSION EQUIPMENT
1.20. STOPPING THE PROPULSION EQUIPMENT
1.21. ELECTRICAL SYSTEM
1.22. GROUNDING PRACTICES
1.23. PRESERVATION BY THE VENDOR
1.24. CONSIGNEE'S/SHIPYARD'S QUALITY PROTECTION
1.25. CORROSION PROTECTION
1.26. PROPELLER VS HULL – NOBLE POTENTIAL AND CORROSION
1.26.1. SHAFT GROUNDING TO PROTECT AGAINST STRAY CURRENT CORROSION
1.27. MAINTENANCE OF PROPELLER SYSTEMS TAKEN OUT OF OPERATION
1.28. LIST OF INSTALLATION RESPONSIBILITIES
1.29. NAMES AND LABELS IN DRAWINGS
1.30. RULES FOR THE CONSIGNEE/SHIPYARD
1.31. SEALING COMPOUND
1.32. PREPARATIONS FOR TECHNICAL TEST RUN
1.33. PRE-COMMISSIONING ACTIVITIES - YARD
1.33.1. BEFORE THE VESSEL IS LAUNCHED
1.33.2. ANY TIME BEFORE THE FIRST SERVICE ENGINEER VISIT
1.34. PRE-COMMISSIONING ACTIVITIES TO BE PERFORMED UNDER THE SUPERVISION
OF A CATERPILLAR SERVICE ENGINEER
1.34.1. BEFORE SYSTEM STARTUP
1.34.2. AT QUAY
1.34.3. AT SEA TRIAL
1.35. LAY-UP REQUIREMENTS
2. MAIN UNIT
2.1. GENERAL
2.2. MPP PROPULSION SYSTEM OVERVIEW
2.3. TYPE OF DELIVERY
2.4. DISMOUNTING
2.5. GENERAL TORQUE DATA
2.6. LIFTING THE PROPELLER AND SHAFT
2.6.1. PREPARATIONS
2.6.2. LIFTING PROCEDURE
2.7. PROPELLER BLADES AND SHAFTS
2.7.1. LIFTING A BLADE
2.7.2. INSTALLING THE BLADES
8.1. MECHANICS
8.2. HYDRAULICS
8.3. REMOTE CONTROL SYSTEM
8.4. MECHANICAL DRAWINGS
9. APPENDIX – MPP OIL REQUIREMENTS
9.1. GENERAL INFORMATION
9.2. OIL REQUIREMENTS, MINERAL OIL
10. APPENDIX – PRE-COMMISSIONING REPORT
10.1. PRE-COMMISSIONING CHECK LIST
1.2. SAFETY
The equipment to which this manual applies must only be used for the purpose for which it was
designed. Improper use or maintenance may cause damage to the equipment and/or injury to
personnel. The user must be familiar with the contents of the appropriate manual before attempting to
operate or work on the equipment.
The user is responsible for ensuring that proper actions, in accordance with the relevant statutory,
legal, and industry requirements, are taken to protect against risks to personal health and safety in
relation to the work described in this manual. Neither this manual, nor its use, in any way absolves the
users from their responsibility to ensure that such proper actions and precautions are taken.
Caterpillar disclaims any responsibility for damages or injury caused by improper installation,
use or maintenance of the equipment.
Unless other instructions are provided, perform the maintenance under the following conditions:
• The engine is stopped. Ensure that the engine cannot be started.
• The protective locks or the controls are in the applied position.
• Disconnect the batteries (if applicable) and power supply, when maintenance is performed or
when the electrical system is serviced. Disconnect the battery ground leads (if applicable). Tape
the leads to help prevent sparks.
• Do not attempt any repairs that are not understood. Use the proper tools. Replace any equipment
that is damaged or repair the equipment.
• Power supplies switch off and locked.
Ensure that all the clamps, the guards, and the heat shields are installed correctly. Correct installation
of these components will help to prevent these effects: vibration, rubbing against other parts and
excessive heat during operation.
1.11. OILS
Hot oil and hot lubricating components can cause personal injury. Do not allow hot oil to contact the
skin. Also, do not allow hot components to contact the skin.
1.12. BATTERIES
Electrolyte is an acid. Electrolyte can cause personal injury. Do not allow electrolyte to contact the skin
or the eyes. Always wear protective glasses for servicing batteries. Wash hands after touching the
batteries and connectors. Use of gloves is recommended.
Improper jumper cable connections can cause an explosion that can result in injury. Refer to your
battery manual for specific instructions.
Do not charge a frozen battery. Charging a frozen battery may result in an explosion.
The batteries must be kept clean. The covers (if equipped) must be kept on the cells. Use the
recommended cables, connections, and battery box covers when the propulsion equipment or battery
is operated.
Do not stand on components which cannot support your weight. Use an adequate ladder or use a
work platform. Secure the climbing equipment so that the equipment will not move.
Do not carry tools or supplies when you mount the propulsion equipment or when you dismount the
propulsion equipment. Use a hand line to raise and lower tools or supplies.
Blades Time for first corrosion protection refill Subsequent corrosion protection refills
After >12 months on land Every 24 months
Blades mounted
After >2 months in water Every 12 months
Blades not After >6 months on land Every 6 months
mounted*
*Wooden covers are mounted in the hub.
The volume of the static part is specified in the hub assembly drawing:
Figure 5. The arrow points at the volume of the static part of the hub. (Example drawing)
Fill the corrosion protection in the plug hole in the static part of the hub:
This means that the hull must be properly protected using paint and anodes. Also, a shaft grounding
device is required.
To protect the propeller system against such damage, Caterpillar strongly recommends that a
propeller shaft grounding system (5) is installed.
However, if welding is done on a vessel using land-based current and a ground fault occurs, a shaft
grounding system will not prevent against stray current corrosion. The same applies if the vessel is
connected to a source of power supply on shore that is badly grounded, or if a neighboring vessel is
badly grounded.
…………………………..
Signature:
…………………………..
Mount the stern tube Yard No
seals according to the
Company:
seal manufacturer’s
manual.
…………………………..
Fill out the protocols
from the manufacturer
and present them to
Caterpillar’s service Name:
engineer.
. …………………………..
Signature:
…………………………..
Insert the propeller shaft Yard No
according to chapter 2
Company:
in the Installation
Manual and the
SHAFTING …………………………..
ARRANGEMENT
drawing.
Name:
…………………………..
Signature:
…………………………..
…………………………..
Signature:
…………………………..
Mount the intermediate Yard No
shafts according to
Company:
chapter 2 in the
Installation Manual and
the SHAFTING …………………………..
ARRANGEMENT
drawing.
Name:
…………………………..
Signature:
…………………………..
Mount the propeller Yard If requested
blades according to
Company:
chapter 2 in the
Installation Manual.
…………………………..
Name:
…………………………..
Signature:
…………………………..
Name:
…………………………..
Signature:
…………………………..
Align the shafts Yard No
according to the gap
Company:
and sag calculations.
…………………………..
Name:
…………………………..
Signature:
…………………………..
Permanently mount the Caterpillar Yes
OD box according to
Company:
chapter 2 in the
Installation Manual and
the OD BOX drawing. …………………………..
Measure run-out and
note it in the service
report. Name:
…………………………..
Signature:
…………………………..
…………………………..
Signature:
…………………………..
Install the hydraulic Yard No
power unit according to
Company:
chapter 3 in the
Installation Manual and
the HYDRAULIC …………………………..
ARRANGEMENT and
HYDRAULIC SYSTEM
drawings. Name:
…………………………..
Signature:
…………………………..
Complete all piping Yard No
according to the
Company:
HYDRAULIC
ARRANGEMENT and
LUBRICATION …………………………..
SYSTEM drawings.
Name:
…………………………..
Signature:
…………………………..
…………………………..
Fill the system with oil Yard No
according to the oil
Company:
recommendations
appendix in the
Installation Manual. …………………………..
Name:
…………………………..
Signature:
…………………………..
a) Central unit
(CENTRAL UNIT …………………………..
drawing)
b) Local unit (LOCAL Name:
CONTROL CABINET
drawing)
…………………………..
Signature:
…………………………..
…………………………..
Signature:
…………………………..
Install the frames for the Yard No
control panels according
Company:
to the CONTROL
PANEL drawing.
…………………………..
Name:
…………………………..
Signature:
…………………………..
Fill out the pre- Yard No
commissioning check list
Company:
at the end of this manual
and send it to the
Caterpillar contract …………………………..
engineer.
Name:
…………………………..
Signature:
…………………………..
Project Manager
Name:
……………………………………………………………………………………………………………
Signature:
……………………………………………………………………………………………………………
Date:
……………………………………………………………………………………………………………
PART 2
It is the responsibility of the project manager at the shipyard to ensure that this form is filled out. When
the sea trial is completed, the list is handed over to Caterpillar’s service engineer.
INSTALLATION PERFORMED RESPONSIBILITY CATERPILLAR
PROCEDURE SERVICE
ENGINEER
ATTENDING
Install the control panels Caterpillar Yes
according to the
Company:
CONTROL PANEL
drawing.
…………………………..
Name:
…………………………..
Signature:
…………………………..
Start-up Caterpillar Yes
Company:
…………………………..
Name:
…………………………..
Signature:
…………………………..
Sea trial Yard/Caterpillar Yes
Company:
…………………………..
Name:
…………………………..
Signature:
…………………………..
Project Manager
Name:
……………………………………………………………………………………………………………
Signature:
……………………………………………………………………………………………………………
Date:
……………………………………………………………………………………………………………
STORAGE
The Caterpillar products must be stored under protective conditions.
The equipment should be stored indoors under dry conditions. When storing outdoors, use applicable
waterproof covering, protecting against direct sunlight too, and keep the humidity at the lowest
possible level.
All hydraulic equipment must be stored indoors under dry conditions. This applies to the remote
control system as well.
INSTALLATION
All products must be protected during the installation period. The following rules apply:
• The equipment must be carefully protected against sand, dust, and damaging moisture.
• Control panels and indicators shall be protected against impact after installation in the vessel.
1.34.2. AT QUAY
• Check for any external leakage.
• Check pressures and temperatures.
• Adjust the zero pitch position.
• Adjust full pitch and engine load.
• Test the functions of the remote control system and make the necessary adjustments.
• Fill out the Caterpillar sea trial report.
2. MAIN UNIT
2.1. GENERAL
This manual describes how to install a Caterpillar MPP propeller with an HDX type Oil Distribution Box
(OD box).
14 HDX gear mounted OD box Distributes the hydraulic oil, enabling rotating shaft pitch setting. It also works as a
feedback unit. The actual pitch position is sent to the remote control system, but is
also visually displayed on a mechanical scale.
2.4. DISMOUNTING
To dismount the unit, you generally perform the mounting steps in reverse order. However, if there are
necessary deviations from the direct reverse procedure, a note indicates the exception.See example
below.
M6 9.8 9.3
M8 24 22
M10 47 44
M12 81 76
M16 197 187
M20 385 364
M24 665 629
M30 1310 1240
M36 2280 2160
M39 2930 2770
M42 3640 -
M48 5450 -
Table 1. General torque data.
Nominal mounting torque expressed in Nm for steel screws for rough, greased steel screw joint
reinforcement. 1Nm = 0.737 foot pounds.
2.6.1. PREPARATIONS
Thoroughly clean the tail shaft and stern tube, and carry out a complete inspection for any damage
that might have occurred during transportation.
Use soft slings to protect the bearing surfaces. Ensure that the lifting equipment is approved for lifting
the stated weight.
Lubricate and protect all parts using grease or thick oil in preparation for installation.
Note: Care must be taken not to damage the surfaces during lifting
operations.
Mount the outer (aft) stern tube seal on the shaft in accordance with the instructions from the
manufacturer.
When freely lifting the propeller with the propeller shaft, position the lifting points symmetrically around
the center of gravity, and along the shaft. See the image below as to the proportions:
Note: Weld two lifting eyes to the hull if this hasn’t already been done.
Also, some yards may provide a cart to roll in the shaft.
Furthermore, if the stern tube stretches a long distance into the hull, you
have to lift and push simultaneously from inside the hull. This not to scratch
the stern tube bearings.
In analogy with mounting, dismount in accordance with the schematic figure below:
General
The following procedure applies if the blades have been delivered unmounted.
Ref. Description
1 Punched blade identifier.
2 Punched hub identifier.
2. Check that the dowel (#1 in Figure 13) is inserted into the unthreaded hole in the blade mount:
Ref. Description
1 Dowel
2 Blade seal
3 Bolts with O-rings
Note! If the blade seal is lubricated incorrectly, that is too much grease
and/or unevenly applied, the seal may be damaged thus requiring
mandatory replacement.
5. Attach the blade seal (#2 in Figure 13) in the groove in the hub body.
6. Fasten the blade to the blade mount. Ensure that each screw has an O-ring correctly positioned in
its groove (#3 in Figure 13).
7. Tighten all bolts in accordance with the main drawing. Use rotation measurement described in
section 2.7.6.
8. Weld-lock the screws on the side of the head. The locks must be placed along the periphery of the
screws (not towards the bottom of the screw head):
Note: When welding, be very careful not to damage the O-ring under each
bolt head.
Note: After the final tightening of the blade bolts, the hub must be tested,
using low pressure air for example, to ensure that there is no leakage at
blade bolts, blade seals and oil plugs. Please refer to section 2.7.8 below.
WARNING: The main engine must be shut down and all pumps must be
shut off before dismounting the blade. Place warning signs wherever
necessary to ensure that the engine and pumps are not started before
finishing the blade dismounting/mounting.
Figure 16. Apply four hoisting belts around the blade flange.
WARNING: The main engine must be shut down and all pumps must be
shut off before mounting the blade. Place warning signs wherever
necessary to ensure that the engine and pumps are not started before
finishing the blade dismounting/mounting.
4. Apply four hoisting belts around the blade flange and fasten them to the welded lifting eyes in the
hull.
5. From aft, position the blade just under the opening:
Figure 18. From aft, position the hoisted blade under the hub opening.
6. Insert a wedge under the blade and secure the blade so that it does not turn over when the
hoisting belts are removed in the next step.
7. Remove the hoisting belts.
8. Fasten the blade bolts in accordance with chapter 2.7.2.
General
In the factory, OKS530 dry lubricant and OKS 250 all-round paste are applied on bolts. This should be
done at the yard as well. However, to obtain a correct tightening that is not affected by such factors the
method below should be used:
3. Mark the position of the screw head at a suitable point (#1 in Figure 20) on the outer diameter of
the screw.
4. Mark the tightening chord distance on the protective guard in accordance with the PROPELLER
HUB ASSEMBLY drawing (#2 in Figure 20) +- 5%.
5. Tighten the bolt to the prescribed torque in the PROPELLER HUB ASSEMBLY drawing.
6. Perform the steps above for the other outer bolts (#1 in Figure 21) on each side of the blade. After
that, check that the two contact surfaces are perfectly tight using a 0.05 mm feeler gauge in the
remaining two center holes (#2 in Figure 21).
Figure 21. Outer bolts (1) and holes for measuring tightness (2).
7. Perform steps 1 - 5 for the remaining two center bolts in the empty holes.
To mount the net cutters on the rope guard, perform the following steps:
1. Mark the position of the net cutter hole in relation to the protection cover:
2. With the rope guard separated from the hub, cut out the hole (the hole is best made a bit extra
long).
3. Ensure that the distance between the knife and the protection cover (1 in Figure 23) is correct in
accordance with the CUTTER GROUP drawing:
Ref. Description
1 Knife position
2 Sides for welding
3 Bracket
4 Knife
4. On three sides (2, dotted line in Figure 23), weld the bracket (3 in Figure 23) in the hole.
5. Using the screws and washers, adjust and fasten the knife (4 in Figure 23) to the bracket.
Cover
Mount the cover at the end of the shaft, using the O-ring and screws:
Hub
Pressurize to 1 bar. Use the air pressure tool assembly when you test the hub for leakage (1):
When testing the hub for leakage, the air leakage tool must be mounted and all connections must be
plugged. (The tool is delivered with quick-couplings that are automatically leak-proof when the male
end is not connected.) Use leak detection spray when testing and ensure that the manometer still
shows 1 bar after 30 minutes of pressurizing.
Note: Please note that the images above are for illustration purposes only.
The blade bolts are weld-locked in the image to the left. Normally, this step
occurs later in the procedure.
If the hub and the propeller shaft are delivered separated, test points #3 (plug in the hub) and #4 (seal
between the hub and protective guard ) are added.
Also, beware of the fact the hole for the tool and the cover at the end of the shaft are potential leakage
points. Therefore, carefully check the plug and seals for this hole to ensure that they are not damaged.
General
The pressure test equipment is delivered together with the OD box equipment. The pressure is
generated using the Caterpillar pumps and tanks included in the system.
Test Equipment
• 1 blind plug
• 1 adapter with blind plug and manometer
Ref. Description
1 Blind plug
2 Adapter with blind plug and manometer
Test Procedure
There is full pressure in the manometer until the piston reaches the surface of the hub. After that, the
leakage in the OD box makes the pressure peter out in the B channel, which can be observed on the
temporarily mounted manometer. However, the standard manometer of the system shows full
pressure.
3. Mount the outer stern tube seal on the shaft in accordance with the manufacturer’s instructions.
4. Insert the tail shaft into the stern tube.
5. Mount a fixture unit (a clamp, for example, fixed to the hull) between the forward shaft seal and the
shaft coupling to prevent it from sliding aft:
10. Check that the shaft has not moved during launching. Use the reference point you marked in step
number 5.
Note: The vessel can be launched before filling the hub with oil.
For information on filling hydraulic and lubrication oil, please refer to the Operation and Maintenance
Manual, chapter 4 - Hydraulics. The oil can be filled when the coupling, intermediate shaft (if fitted),
gear and OD box have been mounted.
Note: For compliance with ABS Class rules, the nuts must be locked using high
strength chemical threadlocker suitable for large threads, Loctite 275 or
equivalent.
The ABS surveyor must be informed prior to locking the nuts in question. The
surveyor must witness that the procedure stipulated by the threadlocking
adhesive manufacturer is strictly followed.
General
The Caterpillar OMC Coupling (Oil-Mounted Coupling) is a hydraulic-mounted Flange Coupling with
tapered inside diameter which is mounted on the tapered shaft end.
When mounting the Caterpillar OMC Coupling, it is slid onto the tapered shaft. Ordinary mineral oil is
then injected between the coupling and the shaft. A built-in hydraulic jack drives the coupling up the
taper on the shaft. When the coupling has reached its final position, an interference fit is created. For a
detailed instruction, please refer to section 0.
At the shop test, the coupling is mounted on the actual shaft. When the correct drive up is reached, a
line is marked 20 mm from aft end of the coupling. For information, a calculated drive up length is
stamped on the aft end of coupling.
Ref. Description
1 Two injectors
2 One hydraulic pump
5. Connect the injectors as displayed in Figure 35 and start injecting oil until it emerges all around
the periphery at the aft end of the coupling.
6. After injecting oil with both injectors for a couple of minutes, start the hydraulic pump, thus driving
up the coupling on the shaft. The injection of oil between the coupling and the shaft should be
continued during the entire drive-up process in order to maintain the oil film.
The drive-up is completed when the aft end of the coupling is 20 mm from the marking line on the
shaft (please refer to the PROPELLER SHAFT ASSEMBLY drawing). At this position, the diameter of
the coupling in point “B” has increased by the dimension stated on the assembly drawing. The drive-up
length stated on the drawing is the calculated drive-up length
Note: If the injector pressure is lost during the operation, the drive-up must
be stopped until pressure is regained.
7. Open the pressure reduction valve (see Figure 37) on the injectors to release the oil between the
coupling and the shaft. This takes about 5 minutes. The pressure in the hydraulic hand pump must
remain unchanged for about 20 minutes to prevent slide back and possible damage to the
coupling.
8. Disconnect the injector and the pump, but let the oil remain in the hydraulic unit. Seal the oil ducts
with the appropriate plugs.
2.8.1. GENERAL
General
The pipe assembly in the shaft comprises four channels. Channel A (pitch ahead) is the center pipe.
Channel B (pitch astern) runs in the shaft itself. The four peripheral pipes handle lubrication in and out,
L & D.
The outside of the pipe assembly and inside of the propeller shaft is the inlet lubrication flow and
reverse flow line for the lubrication oil displaced during pitch setting.
Ref. Description
A Pitch ahead
B Pitch astern
L Lubrication in
D Lubrication out
Note: If the pipe in the shaft is disconnected, the square in the piping must
be engaged with the square in the piston rod. See image below.
General
After contact is made between the coupling male end and the female end of the pipe assembly, the
male end must be tightened as specified in the Pipe Tightening Guide below. The same procedure
applies when connecting two pipe assemblies. Note where threadlocker must and must NOT be used.
Note: Threadlocker must be MEDIUM strength, Loctite 243 or equivalent.
B Intermediate shaft pipes are connected to the next shaft pipe with a threaded coupling. These Yard
must ALWAYS be secured using threadlocker.
C The extension pipe located furthest astern is connected to the next shaft pipe (if more than Caterpillar Certified
one) with a threaded coupling, which MUST NOT be secured using threadlocker. Service Engineer
The oil distributor pipe is connected to the extension pipe furthest ahead (more than one
extension pipe possible) with a threaded coupling. This connection MUST be secured using
threadlocker.
Ref. Description
D Distance to tighten (mm)
The OD box shaft (together with the connected chain of extension pipes) must be turned to be
connected to the propeller shaft pipe at the front
Figure 45. Insert the propeller shaft into the stern tube.
2. Insert the shaft pipe into the propeller shaft and gently tighten it without damaging the outer pipes:
2.9. OD BOX
General
The following instruction gives information on how to do a temporary mounting of the outer parts of the
OD box so that the yard can prepare all pipe and hose connections before a Caterpillar representative
does a permanent installation and test runs the system.
Mount the connection flange (#1 in Figure 48) on the gearbox (#2) and then mount the outer rings
(#3), excluding the feedback unit, on the connection flange
3. HYDRAULIC SYSTEM
3.1. INTRODUCTION
In order to ensure the correct function, maximum efficiency and durability of the propulsion system it is
essential that the following basic principles are observed during the design and installation of the
hydraulic tank and piping system.
The hydraulic system provides servo pressure for changing the pitch and hub lubrication. The pitch
control unit consists of two main parts: the oil distributor and the cylinder.
The oil distributor is mounted on the forward end of the reduction gear box and connected to the
gearbox secondary shaft. The cylinder is an integral part of the propeller hub.
The hydraulic system is pressurized with a header tank, which in turn can be air-pressurized.
3.2. INSTALLATION
1. The header tank must be placed so that the nominal oil level in the header tank is 4-7 meters
above the nominal oil level in the hydraulic tank (#1 in the above figure). This is to achieve the
drive of the oil circulation.
2. If possible, the nominal oil level in the header tank should be at a height above the shaft center
line (#2) approximately 1.3 x the (H) distance between the shaft center line and the max load
water line. This is to ensure the pressure balance in the hub and to compensate for the difference
in density between water and oil.
3. The nominal oil level in hydraulic tank must be 0.5-6 meters above the shaft center line (#3). This
is to avoid too much pressure on the OD box seals so that they don’t wear in advance.
4. The recommended minimum distance between the bottom of the OD box and the top of the sump
tank (#4) is 0.5 m, however at least 0.25 m.
5. The nominal oil level in the hydraulic tank must be above the shaft center line for the system to be
to self-bleeding.
6. The header and hydraulic tanks must be placed to enable easy access for maintenance and
adjustment. Also, it must not be exposed to open atmosphere where it can be damaged by rain or
dust.
Ensure the pump housing is filled with hydraulic fluid before the pump is
set into operation.
4. Start the pump and then check for the correct rotation. Check the pressure setting, (see technical
specification for standard factory setting).
5. Check the hydraulic tank level and fill to the correct level.
6. Test the sensors.
If the working pressure is increased, you have to ensure that the working pressure is 10 bar lower than
the relief valve pressure.
Note: Ensure that the plug, rod and sealing washer are made of stainless
steel.
Note: New oils often contain impurities. For this reason, the filter must be
checked and cleaned if necessary at the first convenient opportunity after
an oil change or top-up.
To guarantee reliable function of the system, the cleanliness must be maintained at least according to
ISO 4406, 20/18/15 (equivalent to NAS grade 9).
4.1. GENERAL
The system should be installed and wired according to the layout drawing. The wire requirements
should be met or exceeded. External connections to other systems should be isolated on the output
side. For example, the digital outputs have relay contacts in the Caterpillar MPC800 system, the digital
inputs should have potential free connections to other systems.
The units are not to be installed in heavily vibrating locations, such as directly on an engine. The
central unit must be installed in an air-conditioned room. If it is installed in the engine room,
appropriate ventilation must be provided.
The units withstand temperatures up to 70 degrees Celsius, but high temperatures for prolonged
periods of time will affect the lifetime of the system. It is recommended that the ambient temperature
normally does not exceed 35 degrees Celsius. The panels are mounted in frames. On installation, first
the naked frames should be mounted, and then the panel parts could be fitted into the frames. This
facilitates the panel installation and also makes it possible to protect the panels from dents and
scratches.
5. TECHNICAL DATA
5.1. OVERVIEW
MAIN UNIT
Caterpillar Order 7364M
Type MPP620
Propeller Quantity Twin
Hub Type MPP620
Propeller Diameter 2500
Material Bronze
No. of Blades 4
Rotation, seen from aft Outwards turning (over the top)
Classification BV
Ice Class No Ice
Rated Power 1520 kW
Propeller Speed 215 RPM
HYDRAULIC SYSTEM
Pump Type AXIAL PISTON PUMP
Motor Type 3 PH, 4 POLE
System Pressure 50 BAR
6. ACCESSORIES
Table of Contents
General and Safety ......................................................................................................................................... 3
Intended use ................................................................................................................................................... 3
Information regarding the Installation Guidelines ................................................................................ 3
Special notation used............................................................................................................................. 3
Liability and warranty ........................................................................................................................... 3
Copyright protection ............................................................................................................................. 4
Delivery................................................................................................................................................. 4
Disposal................................................................................................................................................. 4
Safety .................................................................................................................................................... 4
Contents of the Installation Guidelines ................................................................................................. 5
Changes and conversions to the equipment .......................................................................................... 5
Responsibility of the customer .............................................................................................................. 5
Requirements of the personnel .............................................................................................................. 5
Work Safety .......................................................................................................................................... 6
Personal protective gear ........................................................................................................................ 6
Order Specification ........................................................................................................................................ 7
Preparation before the installation of the Stern Tube ..................................................................................... 7
Unpacking ............................................................................................................................................. 7
Visual check .......................................................................................................................................... 8
Disassembly .......................................................................................................................................... 8
Cleaning ................................................................................................................................................ 9
Installation ................................................................................................................................................... 10
Mounting of the Stern Tube ................................................................................................................ 10
Mounting of the Adapter Ring ............................................................................................................ 10
Final alignment of the Stern Tube................................................................................................................ 11
Fixing of the Welding and mounting of the Cover Ring ..................................................................... 11
Pressure test before the epoxy resin filling ......................................................................................... 11
Filling of the epoxy resin ............................................................................................................................. 12
Final assembly ............................................................................................................................................. 13
Bolts at the AFT Flange ...................................................................................................................... 13
Temperature sensor connection box .................................................................................................... 13
Protection of the installed Stern Tube ................................................................................................. 13
Screw tightening torque table ...................................................................................................................... 13
Stern Tube handling for avoiding problems during operation ..................................................................... 14
Intended use
The Svenska Bearing Stern Tube supplied (also referred to as "Stern Tube" in the following) is to be used
exclusively for the bearing of a rotating ship tail shaft in a tube housing between the AFT boss and the bulkhead.
The texts and illustrations do not necessarily correspond to the scope of delivery. The drawings and graphics do
not correspond to a ratio of 1:1
Copyright protection
The Installation Guidelines must be treated as confidential. It is determined exclusively for those persons
working on and with the equipment.
All content-related information, texts, drawings, pictures and other representations are protected as defined by
copyright protection law and are subject to other industrial property rights. Any improper utilization is liable to
prosecution.
It is not permitted to pass on the Installation Guidelines to third parties, to make reproductions in whatever type
or form - even extracts - or to recycle and/or communicate the contents without written permission by
SVENSKA BEARING (manufacturer). Violations incur the obligation to pay compensation. All other rights
reserved.
We reserve the right to exercise industrial property rights.
Delivery
Examine the delivery on receipt for transport damage.
Report any damage immediately to the carrier and make a note of it on the delivery note.
Check the scope of delivery immediately for completeness.
Contact the manufacturer as soon as possible if any parts are missing.
Disposal
If no agreement has been made regarding return or disposal, dismantled components are to be recycled
following appropriate dismantling:
• Scrap metal material remains
• Take plastic elements to plastics recycling
• Dispose of remaining components that are sorted according to material composition
Safety
At the time of its development and manufacture, the equipment was built according to applicable, recognized
rules of technology and is considered to be safe to operate.
However, risks can arise from this equipment if it is not used by appropriately trained personnel, or if it is
operated incorrectly or not according to the intended use.
The Chapter "Safety" gives an overview of all-important safety aspects for the optimum protection of persons
and the safe, trouble-free operation of the equipment.
In addition to this, the other chapters in this Installation Guidelines contain concrete safety notes identified by
symbols to avert danger. Furthermore, pictogram, signs and labels located on the equipment must be observed.
This means that they may not be removed and must be kept in a good, legible condition.
Operational safety is only guaranteed if the equipment is used according to the intended use.
Expert personnel are defined as whoever can assess the work allocated to him and recognize potential dangers
based on his expert training, knowledge and experience, as well as his knowledge of pertinent conditions.
If personnel do not have the necessary knowledge, they must be trained.
Responsibilities for work on and with the equipment (installation, operation, servicing and maintenance) must
be clearly determined and adhered to, so that there is no unclear distribution of competency with regard to
safety.
Only those persons who can be expected to work reliably may work on and with the equipment. Avoid any
mode of operation that impairs the safety of persons, the environment or the equipment.
Persons who are under the influence of drugs, alcohol or reaction-impairing medication must never work on or
with the equipment.
When selecting personnel, the age- and profession-related regulations applicable at the place where the
equipment is being used are to be observed.
The customer must also make sure that non-authorized persons are kept a sufficiently safe distance away from
the equipment.
Personnel are obliged to report to the customer immediately about any changes to the equipment that impair
safety.
Work Safety
Personal injuries and material damage during work with and on the equipment can be avoided by following the
safety notes and instructions stated in this Installation Guidelines.
Non-compliance with these notes can lead to persons being endangered and damage to or destruction of the
equipment.
If the safety notes and instructions stated in this Installation Guidelines and the accident prevention guidelines
applicable for the place of use and general safety conditions are not complied with, then all liability obligations
and claims for damage compensation against the manufacturer or his representatives are excluded.
Order Specification
CLASSIFICAION SOCIETY: BV
Unpacking
After the Factory Acceptance Test (FAT) the stern tube is packed and delivered in packed condition. If or when
the packing is broken the customer has to ensure that the corrosion protection and the cleanliness of the stern
tube is guaranteed.
All single part materials are packed in named bags and boxes.
For storage of the Stern Tube the following requirements must be followed:
• Store the Stern Tube in dry and moderately heated rooms only.
• Make sure that the Stern Tube is stored on the packing foundation.
• Make sure that the stern tube rests immovably.
The end covers of the Stern tube packing are equipped with
inspection holes for enabling the yard to do inspections during the storage
time.
Unpack the Stern Tube nearby to the assembly place to avoid damage during internal transport. For lifting use
only textile straps, no steel ropes, to avoid damage to the Stern Tube.
Lift, transport and unpack the stern tube as shown in the lifting note on the packing.
Marked on the Stern tube are the prescribed lifting points, as indicated on the above picture. The stern tube must
be lifted with two (2) approved and adequate textile stripes/slings one at each indicated lifting area.
When lifting the Stern tube, make sure that the handling element do not cause damaged to the goods.
Visual check
Check the received Stern Tube items against the delivery notes to ensure that nothing has been damaged during
transport and that no items are missing.
Disassembly
The Adapter Ring (5) must be disassembled from the Stern Tube:
Loosen the Screws (34) and dismount the Adapter Ring (5).
NOTE!
There are numbers of O-Rings (11) and (35) which are used to seal off the Adapter Ring.
These sealing must be handled with care.
NOTE!
Take care that none of the O-Rings (35) gets lost. A missing O-Ring will cause leakages.
Cleaning
The anti-corrosion preservation on all mechanically machined surfaces must be removed carefully and all
surfaces must be cleaned.
Installation
General mounting sequence:
The Stern Tube itself consist of two main parts, the Stern Tube (1) including the AFT (2) and the FWD Stern
Tube Bush (3) and the Adapter Ring (5). All further parts are used for fixing these parts, to ensure the function
of the Stern Tube Bushes and for checking the operating data.
The Stern Tube can be installed using different methods. The shipyard can choose the method most suitable for
them. The commonly used method used is to insert the Stern Tube from the AFT side using chain blocks or
pushing it in a short distance and then pulling it from the inside of the ship, also using chain blocks.
NOTE!
All parts are marked with “TOP”. Make sure that these marks are in “TOP” position,
to avoid problems during the installation
NOTE!
Check that the O-Ring (11) is in position. A damage can cause leakages.
NOTE!
Check that the O-Rings (35) are in position and that no O-Ring gets lost. A damage can
cause leakages. A missing O-Ring will cause leakages.
Insert and tighten the Screws (34) and secure them with LOCTITE.
NOTE!
The O-Rings (11) and (35) are used to seal off the Adapter Ring. These sealing
must be handled with care.
NOTE!
Make sure that the holders (40) do not cover the Adjustment Screws (33).
Press the Stern Tube with the horizontal Alignment Screws (41) against the stern boss. Move the Stern Tube
with the radial Alignment Screws (47) to the given centre line.
The combination of the Adjustment Screws (33) and the Alignment Screws (41) allows to move the Stern Tube
FWD end into position. Loosening the Adjustment Screws on one side and tightening the Alignment Screws at
the same side will move the Stern Tube to the other side. Similarly, the alignment works in vertical direction.
For helping to align the stern tube FWD end additionally two Holders (40) and Alignment Screws (41) and (47)
at the FWD end, see View B. These are keeping the Stern Tube FWD in position or can move it radially.
The Stern Tube is machined with a high level of accuracy. See also the transmitted dimension sheets. The yards
target during the installation should be to reach this level.
The recommended alignment deviance, when using laser equipment, is, due to the high accurate pre-alignment,
0.02 mm / m i.e. 0.1 mm / 5 m. The shipyard must approve the alignment in writing!
After the Stern Tube is aligned to its final position it must be fixed until the epoxy resin filling is completed.
NOTE!
Make sure that the O-Ring (12) gets no heat during the welding.
A damage can cause leakages.
Move the O-Rings (12) and the Covering Ring towards the Welding Ring (6). Insert and tighten the Screws (27)
and secure them with LOCTITE.
NOTE!
The app. resin filling amounts are shown on the order cover page. When the resin
filling amount comes close to these values the pumping speed should be reduced.
In case the resin reaches the venting opening, the inner pressure increases
immediately, and resin leakages may occur at the resin space seals
Final assembly
The Stern Tube AFT Flange is pre-drilled with a remaining wall thickness of app. 3mm for avoiding a resin
leakage during the filling process.
After the resin is hardened the yard must drill through the remaining wall thickness and the resin. Then the
threads for the fixing bolts (22) must be drilled and cut into the AFT boss.
NOTE!
Svenska Bearing recommends the use of high-speed steel tools for this installation step.
I. Drill and tap the holes for the screws M16x80 (22) at the AFT Stern Tube Flange.
II. Insert the screws M16x80 (22), including the rubber-steel washer (23), tighten them and secure them
with LOCTITE.
NOTE!
The rubber-steel washers do have sealing function!
Make sure that all rubber -steel washers are in position. The loss of one rubber-steel washer
may cause leakages.
Mount the temperature sensor connection boxes where it is convenient at the engine room bulkhead.
After the Stern Tube is completely mounted it is very important to protect the White Metal surface of the Stern
Tube bushes. A useful protection would be for example plywood covers at both ends of the Stern Tube.
Yard TBA
POLIGONO INDUSTRIAL SETE PIAS Existing law protects Svenska Bearing's right of possession to this
PARCELA 34 document. The design or the document must not, without
36634- CAMBADOS permission of the company , be published, copied, reproduced,
PONTREVEDRA / SPAIN manufactured or exploited in any other unauthorized way
TEL.: +34 986520909
PARTS LIST
DRAWING-No.: PAGE 1 OF 2
STERN TUBE 3-100-2060-000-I 2019-06-20
MC6S M16x80
22 6 SCREW
A4-70 ISO 4762
M10x50
27 8 SCREW
8.8 ISO4017
POLIGONO INDUSTRIAL SETE PIAS Existing law protects Svenska Bearing's right of possession to this
PARCELA 34 document. The design or the document must not, without
36634- CAMBADOS permission of the company , be published, copied, reproduced,
PONTREVEDRA / SPAIN manufactured or exploited in any other unauthorized way
TEL.: +34 986520909
PARTS LIST
DRAWING-No.: PAGE 2 OF 2
STERN TUBE 3-100-2060-000-I 2019-06-20
M10x60
34 6 SCREW
A4-70 ISO 4762
M16x80
41 6 ALIGNMENT SCREW
8.8 ISO4017
46 1 TURN BUCKLE
M16x80
47 6 ALIGNMENT SCREW
8.8 ISO4017
M8X25
52 12 SCREW
A2-70 ISO 4762
M12X35
54 8 SCREW
A4-70 ISO4017
POLIGONO INDUSTRIAL SETE PIAS Existing law protects Svenska Bearing's right of possession to this
PARCELA 34 document. The design or the document must not, without
36634- CAMBADOS permission of the company , be published, copied, reproduced,
PONTREVEDRA / SPAIN manufactured or exploited in any other unauthorized way
TEL.: +34 986520909
STERN TUBE LENGTH =4600
SHAFT DIA
SHAFT DIA
( Ø 569 )
Ø 225 h7
Ø 545
Ø 540
Ø 358
Ø 398
Ø 564
Ø 538
Ø 398
Ø 358
F
FWD SEAL
225 120 MAPROM M225
45 F 114,5 D ISM225SS0
196 490
TO BE WELDED
BY YARD
196
E G1/2 RESIN VENTING
CONNECTION G1 STERN TUBE
VENTING CONNECTION
H-H MIRRORED IN THE BOTTOM
FOR WATER FILLING
M16, DEPTH 35/45 35
TO BE CUT BY YARD
AFTER STERN TUBE
ALIGNMENT AND RESIN
HARDENING ACCORDING
TO CHAPTER 8 OF THE
INSTALLATION
GUIDELINES.
Ø 400
( Ø 569 )
( Ø 545 +5 )
( Ø 540 )
+0,2
Ø 279,25 +0,1
10
( 225 ) ( 120 )
( 45 )
D
C
F-F
WEIGHT:
STERN TUBE COMPL. APP. 998 kg
STEEL BOOSES APP. 1115 kg
CONTRACT No.
A
(AFT END) G1/2 RESIN B G1/2 RESIN
VENTING
H CONNECTION
(FWD END) VENTING
CONNECTION
G1 WATER
G VENTING
CONNECTION
45
°(
8x
)
)
(6x
60°
45°
G
35°
H
,5
22,5°
±0
40
Ø3
PS I STB PS
STB
35°
I
35°
M16, DEPTH 37/46
33
Ø 470
CONTRACT No.
BY WELD SPOT OR LOCTITE
ITEM QTY. DRAWING
ALL DIMENSIONAL INFORMATION IS BASED ON A MACHINING TEMPERATURE DESCRIPTION MATERIAL REMARKS
NO. NUMBER
OF 21 C, UNLESS STATED OTHERWISE. MACHINE GROOVES ONLY WHERE SHOWN
1 1 BEARING THORDON COMPAC TG-
60°
(TYP)
30(KEY)
40+0.25
0 82±0.13
299
B.C. 241.42
5 X 82 = 410
(INSTALLED I.D.)
281
263(REF)
317 263 (HOUSING I.D.)
19 (REF) 13(KEY)
75±0.13 35.50+0.25
0
2 X 75 = 150 226.36
(INSTALLED I.D.)
246 264H7
(REF) (HOUSING I.D.)
AXIAL RETENTION
REQUIRED
MARINE GROWTH
Marine growth on the shaft liner will prematurely wear a bearing. These deposits, including
calcium carbonate deposits will disrupt the hydrodynamic film and create an abrasive
environment for the bearing.
Preventative Measures
• Turn the shaft 2.5 revolutions every 2-3 days while alongside or at anchor to help
reduce marine growth build up.
• Fresh water pumped into stern tube when the ship is idle will inhibit marine growth in the
strut and stern tube bearings. A flow of 1x the water volume in the stern tube per day
should be sufficient but can be adjusted for local environmental conditions.
• Active cathodic protection systems which are not operated properly and maintained can
lead to material plating out on the shaft liner, leading to abrasive wear
WATER FLOW
Insufficient water supply or poor quality water can lead to bearing failure. Common design and
installation mistakes include:
• Orifice plates placed in water supply line by others restricting the flow of water to the
stern tube. In one application the seal manufacturer had placed an orifice plate in the
water flow line because he felt there was too much water going to the stern tube.
• Bearing lubrication supply line valves are closed. After the bearing failure the valves
should be re-opened.
• A single cooling water line feeding multiple systems and the stern tube supply is at the
end of line. If other items divert the water supply, there may be insufficient water flow to
the bearing. One solution is to place a flow meter (with alarm) to monitor flow
under varying ship operational conditions.
• Corrosion in supply pipe. There have been occasions where a mild steel pipe was
substituted for the normal Copper-Nickel piping. The steel pipe corroded on the pipe
ID enough to restrict water flow to the stern tube.
• Sufficient opening between streaming cap (fairwater) and the propeller shaft to ensure
adequate water flow to the bearing. As a general rule the opening between the shaft
and streaming cap should be 20x the cross sectional area of the sum of all bearing
grooves.
Note: Future marine growth will reduce this opening and should be kept to a minimum.
• Sufficient holes should be placed in the rope guard to prevent a blockage of water
exiting the bearing. As a general rule, the area of the holes should be 20x cross
sectional area of the sum of all bearing grooves.
• Flow meter with alarm should be used to indicate water flow to the bearings. You can
have sufficient pressure or a pressure gauge but no water flow.
• Bearing cooling should be from a sole raw water cooling source and NOT post cooling.
A common problem is when engine cooling water is used to lubricate the bearings.
• A dedicated pump should be used for bearing lubrication and not an engine driven
pump.
For further information, please contact your local Thordon Distributor or Thordon Bearings.
3225 Mainway, Burlington, Ontario L7M 1A6 Canada Tel: +1.905.335.1440 Fax: +1.905.335.4033 www.ThordonBearings.com
Ch. 1 PROPELLER SHAFT BEARINGS
1.5 LUBRICATION source of clean water for bearing lubrication. A strainer or
cyclone separator system can be used. Thordon Bearings
1.5.1 SEAWATER
manufactures a self contained Water Quality Package to
Water is the most common lubricant used with Thordon ensure an adequate supply of clean water is consistently
propeller shaft bearings. Water serves three purposes in being delivered to both the forward seal and the bearings
the operation of the bearing. First, it forms a thin layer of – see Figure 10. The life of the bearings will be extended
hydrodynamic film between the shaft and bearing which if clean lubricating water is supplied to the bearings.
reduces wear. Second, a flow of water removes heat
generated during rotation of the shaft. Third, the water Figure 10: Thordon Water Quality Package
flow facilitates the removal of abrasive particles which can
accelerate bearing wear. In order to accomplish this, a
positive flow of cooling water from a pump source is
recommended. The minimum flow rate required is 0.15
litres per minute per mm (1 U.S. gallon per minute per
inch) of shaft diameter. The water pressure should be
sufficient to overcome hydrostatic pressure from the
draught of the vessel and flow losses, and to ensure
positive flow at the aft end of the stern tube when the
vessel is fully loaded. If vessel has two stern tubes, two
water supply pipes are preferable to one large supply pipe
that is split. The cooling water should be as close as
possible to the temperature of the water in which the
vessel is operating. Water which has already been used to
cool the main engine, gear box or other machinery before
it reaches the bearings may not be suitable. Water over
40°C (104°F) should not be used as it may have a
detrimental effect on the Thordon bearing.
10
DIA. 540 TO BE MACHINED
BEFORE SAW CUT.
SAW CUT 2-4 SUFFICIENT
45
°(
8x
)
Ø1
4
45°
22,5°
45°
MOVED INTO
NET CUTTER
CUTTING AREA
46,6
( Ø 569 )
Ø 545 +5
12
88
196 -3
12
CONTRACT No.
ISO 128
60
DRAWING No.
33
16
Ø 532 +3 (AFTER WELDING)
( 53 )
59
Ø 564 +5
Ø 398 ±1
Ø 458
( 40 )
59
Ø 538 +5
Ø 398 +5
Ø 458
DELLNER BRAKES AB Vikavägen 144 SE-791 95 FALUN SWEDEN Phone: +46 (0)23-78 30 50 Fax: +46 (0)23-77 06 90
[email protected] www.dellner-brakes.com Org.nr/F-skatt: 556553-1299 VAT-no: SE556553129901
Table of contents
Table of contents
1. INTRODUCTION ....................................................................................................................................... 3
1.1 THE DELLNER BRAKES STOPPING, TURNING AND LOCKING SYSTEM .......................................................................... 3
1.2 READING THIS MANUAL ................................................................................................................................... 3
1.3 SAFETY ........................................................................................................................................................ 4
1.4 OVERALL SYSTEM GUIDE AND TECHNICAL DATA .................................................................................................... 5
1.5 LIFTING ........................................................................................................................................................ 6
1.6 HYDRAULIC OIL .............................................................................................................................................. 7
2. INSTALLATION ......................................................................................................................................... 8
2.1 MECHANICAL ................................................................................................................................................ 8
2.2 HYDRAULIC ................................................................................................................................................... 9
2.3 ELECTRICAL................................................................................................................................................... 9
3. MAINTENANCE ...................................................................................................................................... 10
3.1 GENERAL.................................................................................................................................................... 10
3.2 MAINTENANCE SCHEDULE ............................................................................................................................. 10
3.3 PREVENTIVE MAINTENANCE ........................................................................................................................... 11
3.4 CORRECTIVE MAINTENANCE ........................................................................................................................... 11
4. RECOMMENDED SPARE PARTS.............................................................................................................. 12
4.1 STOPPING UNIT ........................................................................................................................................... 12
4.2 COMPACTUS UNIT ........................................................................................................................................ 12
5. APPENDIX ............................................................................................................................................. 13
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 2 Stopping system 322493.
Introduction
1. Introduction
Stopping Dellner Brakes hydraulic disc brakes handle the stopping operation.
The brake system and hydraulic cylinders, integrated into a mechanical linkage,
are used to index turning the shaft. The brake disc is finally positioned
Turning manually or together with an intelligent PLC based control system.
The turning system is used to positioning one of the brake discs outer
peripheral slots to align with the locking device and the tapered pawl is
Locking inserted (manually, hydraulically or electrically) to mechanically lock the shaft
in place.
The STL- systems are modular which means that they are based on modules that allow the
user to choose the function(s) and capacity needed. All from single S, T or L functions,
combined dual functions in terms of SL, ST or TL to a complete STL system can be selected.
Operation and Maintenance instructions are intended for personnel with experience of
similar activities. The manual doesn’t contain detailed instructions to guide inexperienced
personnel through the operation and maintenance procedures. Please consult Dellner
Brakes AB (DBAB) before proceeding if personnel are uncertain in how to follow the
instructions.
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 3 Stopping system 322493.
Introduction
1.3 Safety
Safety precautions concerns Your safety as well as safety of others and undertaking could
also result in serious damage to the equipment if, for example, the warning text is ignored.
The manual describes which safety precautions to take when working with the Stopping
system in general.
The warning sign indicates that there is great risk of personal injury as well
Warning: as serious damage to product if the warning text is ignored.
The caution sign indicates that minor personal injury as well as damage to
the product or major operating faults can occur if the caution text is ignored.
Caution:
The note text draws attention to important information which facilitates the
Note: reading of the instruction.
Properly warning and/or caution and/or note texts are mentioned in associated description
and shall be read very carefully.
Undertaking work may either directly, or indirectly, create risks to safety and health. It is the
user’s responsibility to ensure that appropriate controls and precautions are identified and
applied as well as making all relevant hazard identifications and risk assessments of all
activities associated with the use of this manual. It is also the user’s responsibility to design
and implement safety systems of work and to supply safety equipment and training to
anyone using this manual to work on products to which it relates.
Neither this manual or its use in any way absolves the user from their
responsibility to identify controls, precautions, hazards and risks of all
Note: activates described in this manual are implemented.
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 4 Stopping system 322493.
Introduction
1.4 Overall system guide and technical data
Items delivered from Dellner Brakes AB are listed in Table 1.1 and shown in drawing
3224931. It is defined that one Stopping system consists of two Stopping units (one disc
brake SKD 65 with support) designed to operate with two 25 mm thick brake discs (not
supplied by DBAB) and one Compactus unit.
1
See appendix 1
2
See appendix 1.1
3
See appendix 1.2
4
E.g. a Ø1000 mm brake disc would give the following braking torque: (0,5-0,045) x 100 x 273 = 12500 Nm.
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 5 Stopping system 322493.
Introduction
1.5 Lifting
5
See appendix 1.2
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 6 Stopping system 322493.
Introduction
1.6 Hydraulic oil
Figure 1.1 shows the average viscosity versus temperature curves for the most commonly
used oils subdivided in three groups, each one with a different viscosity. Manufacturers of
hydraulic pumps and motors find their best operating conditions with oil having a viscosity
around 30 cSt at operating temperature. Since the average operational temperature of
hydraulic circuits is about 50C, the oil often used is the oil corresponding to curve B.
We, Dellner Brakes AB, recommend a conventional hydraulic fluid based on mineral oil,
which shall be compatible with nitrile rubber and polyurethane (used materials in seals). The
oil shall at least fulfil ”Vickers M-2950-S (mobile hydraulic systems)” and at least have a
purity 20/17 according to ISO 4406.
Hydraulic oil shall be chosen so that viscosity at working temperature in your system is 30
cSt.
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 7 Stopping system 322493.
Installation
2. Installation
2.1 Mechanical
Exposed mounting surfaces are corrosion protected with DINITROL 77B or equal at delivery.
Assure to clean these surfaces with a solvent prior to installation.
6
See appendix 1, 1.1, 1.1.1 and 2
7
See appendix 1.2 and 5
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 8 Stopping system 322493.
Installation
2.2 Hydraulic
The hydraulic tubing shall be connected according to the hydraulic circuit diagram (drawing
no. 319596-0C8). All connections points are of type 12L and fits with the above hydraulic
tube recommendation.
2.3 Electrical
Use the electrical terminal boxes (see drawing no. 3224939) and connect according to the
electrical circuit diagram (drawing no. 145210).
8
See appendix 1 and 3
9
See appendix 1
10
See appendix 7
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 9 Stopping system 322493.
Maintenance
3. Maintenance
3.1 General
Ensure to have the vicinity clean and free from dirt and the hydraulic system depressurised
prior to removal of any hydraulic system component. Protect the Compactus Unit and the
electrical items by keeping the cabinet doors closed. Be extra careful at oil filling since dirt in
the oil will damage the hydraulic system.
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 10 Stopping system 322493.
Maintenance
3.3 Preventive maintenance
The preventive maintenance recommended in Table 3.1 ensures reliability and function of
the S system throughout its service life.
At normal circumstances, Dellner Brakes AB recommends replacing the air filter twice per
year. If your air is much polluted, more frequently replacements are recommended.
Every ten years we recommend a major overhaul of the S system as described in Table 3.1.
Use test connectors and measure the pressure with a pressure gauge to
Caution: ensure that the hydraulic system is depressurised prior to removal of any
hydraulic system component.
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 11 Stopping system 322493.
Recommended spare parts
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 12 Stopping system 322493.
Appendix
5. Appendix
Table 5.1 (Appendix list)
Appendix no. Document ID. Type Name Pages
1 322493 rev 1 Drawing Stopping system 1
Document ID: M0325 Dellner Brakes AB, 2016. All rights reserved.
Issue: 2 The manufacturer reserves the right to modification without special notice.
Page: 13 Stopping system 322493.
3
5
755 400
PI
600
B1
B2
DR1
PORT STARBOARD
25 Represents hydraulic tubing (customer supply).
700 4 Recommended hydraulic tube dimension: 12x1,5 according to DIN 2391/C.
Connections: 12L .
Stopping system E
2 3
157,5 0,5
140
315
(315)
4
140
7
8 11
25
315
~193
Datum/Date
*) 2mm air gap between brake housing/pad and brake disc SKD 65 2016-02-05
Ritn. nr
Draw. no. 322494 Sheet 1 /1
(on both sides of the disc) if the disc brake is installed Denna handling r upphovsr ttsligt skyddad och f r inte, utan This document is copyright legislationed protected and must
according to nominal axial installing dimension (see dim. A). tillst nd fr n Dellner Brakes AB, delges eller verl mnas till
utomst ende. vertr delse medf r ansvar.
not, without permission from Dellner Brakes AB, be given or
handed over to any outsider. Trespass give rise to responsibi-
lity.
No. Change. Date. Intr. Appr.
1 Pos. 1 updated, now 6x M10 threads, O 2014-11-11 TL MA
39343
43
15 6 14 7
~154
40
141
10 5
95
Outer diameter
Rec. tightening torque: 3 of brake disc
81Nm
12 13 11
A 104 + b
Rec. tightening torque:
197Nm
143
163
B
6x M10 15
1
8 2 5755065000 Wiper DK 65 0
7 2 5703014000 Bonded seal G 1/4" 0
Warning! 6 2 216290 Bleeder 0
Manual for this brake must be read 5 4 215531 Return spring screw 0
before installation. For installation, 4 2 204548 Piston 0,9
operation and maintenance, request 3 4 215530 Guide pin 0,1
manual from Dellner Brakes AB. 2 2 215527-A Brake pad 1,5
1 2 215271 Brake housing 5,5
Det. nr. Antal Artikelnummer Ben mning Vikt [kg]
Assembly instruction: Det. no. Number Article number Name
Material Dimension Weight
All parts to be cleaned thoroughly before Konstr./Des. Ritad Kontr. Skala Vikt/Weight Ers tter/Replaces Ersatt av/Replaced by
1 2 85
A (2:1)
155
Detail view A shows recommended air gap 3
between proximity switch and brake pad
back plate at released condition. The air
gap might need to be finally adjusted at
commissioning.
Proximity switch shall indicate (lose
signal) when the disc brake is applied
(before 2 mm back plate travel from
released condition).
20
26
4
1V3
1V4 PI
1Z6
15
16
17 B1 B2
600
560
16 2
17
1P1
1V1
1V2
22
1Z1
1Z2 DR1
1Z3
1Z4
1Z5
9 4x n8,5
10 10 5 21 29 30 31 6 7 8 Hydraulic outlet ports Drainage port
Max. oulet pressure: See below *)
11 Product specification: 319596-0
31 4 000125084000 Washer BRB 8.8 FZB 8,4x16x1,5
1V5 12 18 19 20 30 4 006924008000 Nut M6M locking 8.8 FZB M8
(to be sealed at assembly) 29 2 319287 Threaded bar 8.8 FZB M8x270
M1 28 4 00012564000 Washer BRB 8.8 FZB 6.4x12x1.5
M2 27 4 006924006000 Nut M6M locking 8.8 FZB M6
26 4 000931006014 Screw M6S 8.8 FZB M6x14
Note: 25 2 000125125000 Washer BRB 8.8 FZB 12,5x35x3
Cabinet door not shown in upper left view. 24 2 006924012000 Nut M6M locking 8.8 FZB M12
Trap door / 10x Mounting screws, 23 2 319183 Eye bolt FZB M12
22 0,9 m 7284012015 Hydraulic tubes GK ø12x1,5
could be opened at service *) Pressure step up ratio: 44.
21 0,45 m 7284008010 Hydraulic tubes GK ø8x1
Max. hydraulic outlet pressure is specific for Your installation,
20 2 8303-00-12 Test connector DKLO 12L, M16x2
see product specification or contact Dellner Brakes AB. 19 2 6035-12-12 Fitting DKLO 12L
18 2 6043-12-12 Fitting T 12L
**) Plus max. 5 l hydraulic fluid. 17 3 5601-02-18 Bonded seal M18
16 3 6045-12-12 Fitting SV 12L
15 1 6089-12-06 Fitting EVGE 12L, G/ED 3/8"
14 1 6042-12-12 Fitting W 12L
13 1 6009-12-06 Fitting GE 12L, G/ED 3/8"
12 3 6009-12-04 Fitting GE 12L, G/ED 1/4"
11 1 6130-00-08 Plug 8L
10 2 5703014000 Bonded seal G 1/4"
9 1 6045-08-08 Fitting SV 8L
8 1 5703012000 Bonded seal G 1/8"
7 1 6050-08-08 Fitting EVW 8L
6 1 6003-08-02 Fitting GE 8L, GB 1/8"
5 1 534-421-003-0 Safety valve G 1/4" (2-6 bar)
4 1 319275 Air processing unit
2 1 319597 Pneumatic/Hydraulic Power Pack
File: PRODUCTS\HYDRAULICS\COMPACTUS\319596-0.idw
C:\AutodeskVaultWork\DESIGNS\ARTICLES AND
1 1 AS06064 Cabinet 600x600x400
Det. nr Antal Artikelnummer Benämning Vikt [kg]
Det. no. Number Art.no. Name Material Dimension Weight
Konstr./Des. Ritad Kontr. Skala Vikt Ersätter/Replace Ers.av/Replaced by
Cabinet door - Left hanged A2 PMi Drawn
PMi Control
MO Scale
1:5
Weight
43 **)
Datum/Date
(BWN 1 L-NN-1-1-G24) Ritn. nr
2013-02-12 Draw. no. 319596-0
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
lity.
Installation, Operation and
Maintenance
Manual
from Dellner Brakes AB
Hydraulically activated disc brakes
type SKD 35, 50, 65, 80
Manual no: M0011‐8
Customer:
Customer order
no:
DBAB order no:
Published by:
DELLNER BRAKES AB
Vikavägen 144
SE‐791 95 FALUN
SWEDEN
Telephone: + 46 (0)23 – 78 30 50
Telefax: + 46 (0)23 – 77 06 90
Internet address: www.dellner‐brakes.com
E‐mail: info@dellner‐brakes.com
1. TABLE OF CONTENTS
TABLE OF CONTENTS ______________________________________________ 2
A. Technical description disc brake SKD ________________________________ 3
B. Assembly instructions disc brake type SKD ___________________________ 5
C. Maintenance instruction disc brake SKD _____________________________ 6
D. Hydraulic oil ___________________________________________________ 7
E. Part list and drawing SKD 35 ______________________________________ 8
F. Part list and drawing SKD 50 _____________________________________ 10
G. Spare parts and drawing SKD 65 __________________________________ 12
H. Spare parts and drawing SKD 80 __________________________________ 14
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
2
2. A. Technical description disc brake SKD
2.1 General description:
Disc brakes of type SKD are direct acting and are activated by hydraulic‐ or air pressure. The
braking power achieved is directly proportional to the applied pressure. The brake consists
of two symmetrical brake halves and is designed for a brake disc thickness of 12 mm. Should
a thicker brake disc be required, the brakes can be supplied with a spacer. Each brake half is
supplied with two cylindrical guiding pins which transmit the tangential braking force from
the brake pads to the brakes. This means that the brake piston is not subjected to any radial
energy and as a result, contributes to a longer life for the brakes. Each brake half is supplied
with two retracting springs, which pull the brake pad back at brake release. The brake pad
wear is automatically compensated through increased stroke by the piston.
When the brakes are used with air activation it is preferred to remove the return spring
screws.
2.2 Technical data:
Table 1
Type Tangential brake force* Air gap brake pad / brake disc
SKD 35 8000 N 2 x 2.0 mm
SKD 50 16200 N 2 x 2.0 mm
SKD 65 27300 N 2 x 2.0 mm
SKD 80 41400 N 2 x 2.0 mm
* Valid at 100 bar hydraulic pressure. External losses not accounted for.
Values are calculated with μ=0,42.
Max. hydraulic pressure = 100 bar
2.3 Friction material
The standard friction material used on the brake pads is a non‐asbestos organic material.
Max. continuous rubbing speed is 21 m/s and max. continuous temperature is 300 oC. Other
materials are available for more demanding applications.
2.4 Seal material
Nitrile is used as a standard material in seals. If chosen hydraulic oil is not suitable together
with nitrile, EPDM is available. If the operational oil temperature is over 100 oC, viton is
available.
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
3
2.5 Corrosion protection
The standard Dellner brakes are protected against corrosion due to following:
• Return spring material are stainless steel
• All bolts are electrically galvanized
• The brakes are painted with a two pack epoxy paint
2.6 Options
Indicators: Indicators can be used as options for this brake, indicating on/off and brake pad
wear. Versions with a micro switch and with a proximity switch are available for selected
brakes. Please contact DBAB for information.
Spacer: Is used between the caliper halves when the brake disc is thicker then 12 mm.
Thickness of spacer = brake disc thickness ‐ 12 mm.
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
4
3. Assembly instructions disc brake type SKD
Install the brake with the air bleeder screws as high as possible.
The brake unit should be installed and adjusted parallel with the brake disc, installing
tolerance +/‐0.5 mm.
Before finally tightening of the mounting screws, apply the brake, tighten the screws, release
the brake and check the installing tolerance again.
Bleed any air from the brake.
Check that the discs angular throw in relation to the support does not exceed the
permissible values, see below.
The hydraulic tubes which are to be connected to the disc brake have to be seamless steel
tubes according to DIN 2391 / c, (St. 35) (dim. see table).
The tubes have to be cleaned internally by compressed air before assembly.
Before the brake is taken into operation the friction material on the brake pads have to be
bedded in. Use the brake to brake the machine down to stop a couple of times. Do not
overheat the brake pads. Max. recommended temperature on the brake disc surface is 200°
C. The brake pads are ready for operation when the entire surface colour have turned into
black from the brand new grey colour.
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
5
4. Maintenance instruction disc brake SKD
4.1 Deaeration procedure
1. Pressurize the brake.
2. Mount a draining hose on the air bleeder nipple and open it carefully and keep it open
until all air is exhausted.
3. Close the deaeration nipple.
4. Repeat 1‐3 on all brake cylinders.
NOTE: The brake pads will loose friction if they are contaminated with oil or grease. The
brake pads should be replaced if the friction material has absorbed oil or grease.
4.2 Replacement of brake pads procedure
The brake pads are to be replaced when 2 mm friction material is left.
1. Depressurize the brake.
2. Remove the guide pins and the return spring screws.
3. Slide brake pad up and out.
4. Slide new brake pad in.
5. Install guide pins and return spring screws.
6. Tighten the screws due to the tightening table on the general drawing.
NOTE: New brake pads have to be bedded in before full friction is achieved (see above,
chapter B).
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
6
5. Hydraulic oil
5.1 Recommended oil
Diagram below show the average curves viscosity versus temperature for the most
commonly used oils subdivided in three groups each one with a different viscosity.
Manufactures of hydraulic pumps and motors find their best operating conditions with an oil
having a viscosity around 30 cSt at the operating temperature. Since the average operation
temperature of hydraulic circuits is about 50°C, the oil mostly used is that corresponding to
curve B.
Hydraulic oil shall be chosen so that viscosity at working temperature in your system is 30
cSt.
Table 2
Curve ISO‐VG standard
A 32
B 46
C 68
5.2 Oil volume SKD brakes
Table 3
Type Volume 1 Volume 2 Connection pipe ∅ x t
SKD 35 15.2 cm3 6 cm3 8x1,0
SKD 50 31.2 cm3 18 cm3 8x1,0
SKD 65 52.8 cm3 43 cm3 10x1,0
SKD 80 80 cm3 62 cm3 10x1,0
Volume 1: Max. working oil volume in the brake with worn out brake pads.
Volume 2: Oil volume in released brake.
Recommended oil viscosity at working temperature, approx. 30 cSt.
NOTE: Standard material in rubber seals is nitrile. Check that used oil is applicable with
nitrile rubber.
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
7
6. Part list and drawing SKD 35
6.1 Part list
Det. no. Quantity Description Art. no.
1 2 Caliper half 215269
2 2 Brake pad 215508‐A
3 4 Guide pin 215511
4 2 Piston 215512
5 4 Return spring screw 212207
6 2 Bleeder 216290
7 2 Seal TT G 1/8” 5703012000
8 2 Stripper 5755035000
9 2 O‐ring 5725342030
10 4 Return spring 215830
11 2 Screw M6S 10x120 8.8 000931010120
12 2 Nut locking M10 8.8 006924010000
13 4 Washer BRB 17x30x3 000125105000
14 2 Nipple G 1/8” 215333
15 2 Plug 215543
16 2 Wear indicator, option 215514‐A
‐ 1 Spacer, option 217627‐xx*
* Depending on the spacer thickness.
6.2 Recommended spare parts
Description Art. no. Material remark Remark
Brake pad 215508‐A Organic (standard) 2 pcs / brake
Brake pad 215508‐B Low friction 2 pcs / brake
Brake pad 217871 Semi metal 2 pcs / brake
Brake pad 218049 Sinter metal 2 pcs / brake
Seal kit 216863‐1 Nitril rubber (standard) 1 pcs / brake
Seal kit 216863‐2 EPDM rubber 1 pcs / brake
Seal kit 216863‐3 Viton rubber 1 pcs / brake
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
8
7. F. Part list and drawing SKD 50
7.1 Part list
Det. no. Quantity Description Art. no.
1 2 Caliper half 215270
2 2 Brake pad 215519‐A
3 4 Guide pin 215522
4 2 Piston 215523
5 4 Return spring screw 216011‐1
6 2 Bleeder 216290
7 2 Seal TT G 1/8” 5703012000
8 2 Stripper 5755050000
9 2 U‐ring 5773050007
10 4 Return spring 215826‐1
11 3 Screw M6S 12x120 8.8 000931012120
12 3 Nut locking M12 8.8 006924012000
13 6 Washer BRB 13x42x2 000125130000
14 2 Nipple G 1/8” 215333
15 2 Plug 215543
16 2 Wear indicator, option 215524‐A
‐ 1 Spacer, option 217628‐xx*
* Depending on the spacer thickness.
7.2 Recommended spare parts
Description Art. no. Material remark Remark
Brake pad 215519‐A Organic (standard) 2 pcs / brake
Brake pad 215519‐2 Low friction 2 pcs / brake
Brake pad 215521‐1 Semi metal 2 pcs / brake
Brake pad 217574 Sinter metal 2 pcs / brake
Seal kit 216864‐1 Nitril rubber (standard) 1 pcs / brake
Seal kit 216864‐2 EPDM rubber 1 pcs / brake
Seal kit 216864‐3 Viton rubber 1 pcs / brake
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
10
8. Spare parts and drawing SKD 65
8.1 Recommended spare parts
Description Art. no. Material remark Remark
Brake pad 215527‐A Organic (standard) 2 pcs / brake
Brake pad 215527‐AL Low friction 2 pcs / brake
Brake pad 218050 Semi metal 2 pcs / brake
Brake pad 217680 Sinter metal 2 pcs / brake
Seal kit 216865‐1 Nitril rubber (standard) 1 pcs / brake
Seal kit 216865‐2 EPDM rubber 1 pcs / brake
Seal kit 216865‐3 Viton rubber 1 pcs / brake
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
12
No. Change. Date. Intr. Appr.
6x M10 was 4x M10, drawing updated. CO
1 2014-12-17 TL PMi
39343
A-A ( 1 : 2 )
~163
Rec. tightening torque:
~143 197Nm
45 45 104 + b
12 13 11
30
81Nm 3 Outer diameter
of brake disc
10 5
~141
40
7 14 6 15
9. Spare parts and drawing SKD 80
9.1 Recommended spare parts
Description Art. no. Material remark Remark
Brake pad 215536‐A Organic (standard) 2 pcs / brake
Brake pad 215536‐L Low friction 2 pcs / brake
Brake pad 217703 Semi metal 2 pcs / brake
Brake pad 217857 Sinter metal 2 pcs / brake
Seal kit 216866‐1 Nitril rubber (standard) 1 pcs / brake
Seal kit 216866‐2 EPDM rubber 1 pcs / brake
Seal kit 216866‐3 Viton rubber 1 pcs / brake
Return spring screw 215603 4 pcs / brake
Return spring 216076 Stainless steel 4 pcs / brake
© Copyright Dellner Brakes AB, 2002. All rights reserved
The manufacturer reserves the right to modification without special notice
Manual for SKD 35, 50, 65, 80.
14
No. Change. Date. Intr. Appr.
1 Pos. 1 updated, was 4x M16. CO 39267. 2014-12-17 TL MA
2 Drawing updated.CO: 43826. 2015-01-19 OK TL
b
6 7 14 15 To be secured with Loc-Tite 2 2 2 8
9 4
243 or equivalent. 1
A
10 5
55
110
43
182
Outer diameter
122
of brake disc
B(1:2) 1
6x M16 30
Record of changes:
Revision Date Description of change Signature Approved
1 2016-11-14 Safety valve setting changed. PSI-value for pressure regulator updated. OK PMi
Manual
with spare parts lists
From Dellner Brakes AB
Compactus unit
Published by:
1. Introduction _________________________________________________________ 3
1.1 General description _________________________________________________________ 3
1.2 Pneumatically operated Hydraulic Power Pack (PHPP) _____________________________ 4
1.3 Technical data _____________________________________________________________ 4
2. Installation instructions ________________________________________________ 5
2.1 Lifting ___________________________________________________________________ 5
2.2 Mechanical _______________________________________________________________ 5
2.3 Hydraulic and pneumatic_____________________________________________________ 6
2.4 Electrical _________________________________________________________________ 6
3. Operation instructions _________________________________________________ 7
4. Maintenance instructions ______________________________________________ 8
4.1 General __________________________________________________________________ 8
4.2 Oil level inspection and refilling/changing _______________________________________ 8
5. Hydraulic oil _________________________________________________________ 9
6. Recommended spare parts ____________________________________________ 10
7. Part lists and drawings _______________________________________________ 11
7.1 Compactus units with one hydraulic outlet port __________________________________ 11
7.1.1 Compactus unit without pressure switch - Art. no. 319535 __________________________________ 11-15
7.1.2 Compactus unit with pressure switch - Art. no. 319535-1 ___________________________________ 16-20
7.1.3 Pneumatically operated Hydraulic Power Pack (PHPP) - Art. no. 319555________________________ 21
7.2 Compactus units with two hydraulic outlet ports _________________________________ 22
7.2.1 Compactus unit without pressure switches - Art. no. 319596 _________________________________ 22-26
7.2.2 Compactus unit with pressure switches - Art. no. 319596-1 _________________________________ 27-31
7.2.3 Pneumatically operated Hydraulic Power Pack (PHPP) - Art. no. 319597________________________ 32
7.3 Compactus units with three hydraulic outlet ports ________________________________ 33
7.3.1 Compactus unit without pressure switches - Art. no. 321121 _________________________________ 33-37
7.3.2 Compactus unit with pressure switches - Art. no. 321121-1 _________________________________ 38-42
7.3.3 Pneumatically operated Hydraulic Power Pack (PHPP) - Art. no. 321133________________________ 43
8. Appendix list ________________________________________________________ 44
2
1. Introduction
1.1 General description
Figure 1.1.1 (Closed Compactus unit) Figure 1.1.2 (Open Compactus unit)
The PHPP and the air processing unit are assembled inside the lockable cabinet,
which keeps the equipment clean and free from dirt. The Compactus unit is also
equipped with external fittings (combined with rubber bonded seal washers) for
pneumatic connection, hydraulic connection and oil drainage. The PHPP shall be
supplied with pneumatic pressure through the air processing unit consisting of a shut
off valve, a pressure regulator with filter and pressure gauge and a safety valve. The
regulator and safety valve are adjusted before delivery and the safety valve is also
secured with a lock wire.
The lockable electrical connection box is assembled on the right side of the cabinet.
The connection box shall be considered as interface between the hydraulic system
and an external control system. The connection box shall be supplied with control
power through conduits which are located on the bottom side of the box.
Dellner Brakes AB, 2012. All rights reserved.
The manufacturer reserves the right to modification without special notice.
Manual for Compactus unit
3
The cabinet and the electrical connection box are delivered painted in grey shade
(RAL 7032).
Figure 1.1.2 shows a Compactus unit with one hydraulic outlet port, but models are
available where it is possible to control a number of hydraulic outlet ports
individually and/or simultaneously by adding solenoid valves to the PHPP. Models
where each hydraulic outlet port is equipped with a pressure switch for hydraulic
pressure ON/OFF detection are also available (adjusted and secured with a lock wire
before delivery).
4
2. Installation instructions
The below installation instructions are general for all Compactus models and
therefore it is important that the correct reference drawings valid for your installation
are used during the installation (see chapter 7).
When complete installation has been carried out, it is important that the operation
instructions according to chapter 3 are followed.
2.1 Lifting
2.2 Mechanical
The back side of the cabinet shall be considered as primary mounting surface (4x
mounting holes, Ø8,5).
The Compactus unit shall be mounted in the vicinity of the hydraulic consumer
device e.g. disc brake. If not possible, please contact Dellner Brake AB if the height
difference is more than 10 meter.
5
2.3 Hydraulic and pneumatic
Hydraulic tubes shall be connected from the hydraulic outlet port(s) to the hydraulic
consumer device e.g. disc brake.
Hydraulic tubes shall be connected from the pneumatic inlet port to the pneumatic
pressure source.
2.4 Electrical
Use the electrical connection box and connect the Compactus unit to the electric
control system according to the electric wiring diagram for the Compactus unit valid
for your installation.
6
3. Operation instructions
The below operation instructions are general for all Compactus models and therefore
it is important that the correct reference drawings valid for your installation are used
during the operation (see chapter 7).
Prior to the first actuation of Compactus unit, i.e. solenoid valve(s) energized and
hydraulic outlet port(s) pressurized, the following shall be checked:
1. Oil has been filled into the tank (pos. 1Z1). If not, see chapter 4.2.
2. The shut of valve (included in the air processing unit, det. no. 4) is in open
position. If not, open it.
3. The pressure gauge (included in the air processing unit and assembled to the
pressure regulator) shows a permissible value valid for your installation. If not,
correct the pressure with the regulator.
To pressurize the hydraulic outlet port(s) the solenoid valve(s) shall be energized.
If the Compactus unit has more than one hydraulic outlet port, the ports can be
pressurized individually and/or simultaneously e.g:
When the solenoid valve(s) is energized the PHPP will start and pump oil to fulfil
pistons strokes and finally pressurize the hydraulic outlet port(s) with the correct
operating pressure.
To depressurize the hydraulic outlet port(s) respectively solenoid valve shall simply
be de energized.
NOTE: The pressurizing sequence is not important. Each hydraulic outlet port can
be pressurized and depressurized without affecting the remaining hydraulic
outlet ports.
7
4. Maintenance instructions
The below maintenance instructions are general for all Compactus models and
therefore it is important that the correct reference drawings valid for your installation
are used during the maintenance (see chapter 7).
4.1 General
Ensure to have the vicinity of the Compactus unit clean and free from dirt prior to
removal of any hydraulic system component. Protect the hydraulic, pneumatic and
electrical components by keeping the cabinet doors closed. Be extra careful at oil
filling since dirt in the oil will damage the hydraulic system.
NOTE: It is recommended to turn the shut off valve (included in the air processing
unit, det. no. 4) into closed/vented position prior to any major maintenance
tasks (e.g. removing system components), but do NOT forget to restore its
position afterwards.
The oil should be inspected ones a year. If it has turned black, change it. Use new
clean oil according to chapter 5. The changing interval is specific for Your
installation, please contact Dellner Brakes AB for further recommendation.
NOTE: Oil level inspection shall be done when hydraulic system is depressurized.
8
5. Hydraulic oil
Figure 5.1 shows the average viscosity versus temperature curves for the most
commonly used oils subdivided in three groups, each one with a different viscosity.
Manufacturers of hydraulic pumps and motors find their best operating conditions
with oil having a viscosity around 30 cSt at operating temperature. Since the average
operational temperature of hydraulic circuits is about 50°C, the oil often used is the
oil corresponding to curve B.
We, Dellner Brakes AB, recommend a conventional hydraulic fluid based on mineral
oil, which shall be compatible with nitrile rubber (used materials in seals). The oil
shall at least fulfil ”Vickers M-2950-S (mobile hydraulic systems)” and at least have
a purity 20/17 according to ISO 4406.
Hydraulic oil shall be chosen so that viscosity at working temperature in your system
is 30 cSt.
9
6. Recommended spare parts
The below spare part list (table 6.1) is general for all Compactus models and
therefore it is important that the correct reference drawings valid for your installation
are used when choosing spare parts (see chapter 7).
Check that the Compactus unit valid for your installation is equipped with
pressure switch(es) before ordering.
10
Document name Head line Date Page no.
COMPACTUS UNIT
PRODUCT SPECIFICATION LP80-12/B4 K1 (BWN 1 L-N-1-1-G24) 2006-10-18 1 (of 1)
Issuer Approved by Contract / Order no. Contract name Document ID Revision
Pär Mikaelsson Peter Mikaelsson -/- - 319535 2
Product no. Assembly drawing Assembly drawing, PHPP Hydraulic circuit diagram Assemly / test instruction
319535 319535 319555 319535C -
Record of changes:
Revision Date Description of change Signature Approved
1 2007-06-12 Art. no. for pos. 1V1 corrected, was 200-35-225 PMi PM
Art. no. for pos. 1P1 added
2 2012-03-14 Art. no. for pos. 1V1 corrected, was 200-35-120 PMi PM
20
26
4
1V2
200
1V3 PI
1Z5
15
16
3
17 B1
600
560
16 2
17
1P1
1V1
1Z1
22 1Z2
1Z3 DR1
1Z4
9 4x n8,5
10 10 5 21 29 30 31 6 7 8 Hydraulic outlet port Drainage port
1 Max. oulet pressure: See below *) Product specification: 319535
11
31 4 000125084000 Washer BRB 8.8 FZB 8,4x16x1,5
30 4 006924008000 Nut M6M locking 8.8 FZB M8
1V4 12 18 19 20 Cable gland for electric control supply
29 2 319287 Threaded bar 8.8 FZB M8x270
(to be sealed at assembly) Grip range: 11 -17 mm
28 4 00012564000 Washer BRB 8.8 FZB 6.4x12x1.5
M1 27 4 006924006000 Nut M6M locking 8.8 FZB M6
26 4 000931006014 Screw M6S 8.8 FZB M6x14
25 2 000125125000 Washer BRB 8.8 FZB 12,5x35x3
Note: 24 2 006924012000 Nut M6M locking 8.8 FZB M12
Cabinet door not shown in upper left view. 23 2 319183 Eye bolt FZB M12
Trap door / 10x Mounting screws, 22 0,65 m 7284012015 Hydraulic tubes GK ø12x1,5
21 0,45 m 7284008010 Hydraulic tubes GK ø8x1
could be opened at service *) Pressure step up ratio: 44.
20 1 8303-00-12 Test connector DKLO 12L, M16x2
Max. hydraulic outlet pressure is specific for Your installation,
19 1 6035-12-12 Fitting DKLO 12L
see product specification or contact Dellner Brakes AB. 18 1 6043-12-12 Fitting T 12L
17 2 5601-02-18 Bonded seal M18
**) Plus max. 5 l hydraulic fluid. 16 2 6045-12-12 Fitting SV 12L
15 1 6089-12-06 Fitting EVGE 12L, G/ED 3/8"
14 1 6042-12-12 Fitting W 12L
13 1 6009-12-06 Fitting GE 12L, G/ED 3/8"
12 2 6009-12-04 Fitting GE 12L, G/ED 1/4"
11 1 6130-00-08 Plug 8L
10 2 5703014000 Bonded seal G 1/4"
9 1 6045-08-08 Fitting SV 8L
8 1 5703012000 Bonded seal G 1/8"
7 1 6050-08-08 Fitting EVW 8L
200
Datum/Date
(BWN 1 L-N-1-1-G24) Ritn. nr
2006-10-18 Draw. no. 319535
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
lity.
Document name Head line Date Page no.
COMPACTUS UNIT WITH PRESSURE SWITCH
PRODUCT SPECIFICATION LP80-12/B4 K1 (BWN 1 L-N-1-1-G24) 2008-04-30 1 (of 1)
Issuer Approved by Contract / Order no. Contract name Document ID Revision
Pär Mikaelsson Peter Mikaelsson -/- - 319535-1 1
Product no. Assembly drawing Assembly drawing, PHPP Hydraulic circuit diagram Assemly / test instruction
319535-1 319535-1 319555 319535-1C -
Record of changes:
Revision Date Description of change Signature Approved
Art. no. for pos. 1P1 added
1 2012-03-14 Art. no. for pos. 1V1 corrected, was 200-35-120 PMi PM
20
29
4
1V2
200
1V3 PI
1Z5
17
18
3
19 B1
600
560
18 2
19
1P1
1V1
1Z1
25 1Z2
1Z3 DR1
1Z4
11
34 4 000125084000 Washer BRB 8.8 FZB 8,4x16x1,5
12 12 5 24 32 33 34 8 9 10 Hydraulic outlet port Drainage port
33 4 006924008000 Nut M6M locking 8.8 FZB M8
Max. oulet pressure: See below *) 32 2 319287 Threaded bar 8.8 FZB M8x270
13
1S1 31 4 00012564000 Washer BRB 8.8 FZB 6.4x12x1.5
(to be sealed at assembly) 2x Cable gland for electric control supply 30 4 006924006000 Nut M6M locking 8.8 FZB M6
1V4 6 7
(to be sealed at assembly) Grip range: 11 -17 mm 29 4 000931006014 Screw M6S 8.8 FZB M6x14
28 2 000125125000 Washer BRB 8.8 FZB 12,5x35x3
27 2 006924012000 Nut M6M locking 8.8 FZB M12
14 20 21 22 23 26 2 319183 Eye bolt FZB M12
Note: 25 0,65 m 7284012015 Hydraulic tubes GK ø12x1,5
M1 Cabinet door not shown in upper left view. 24 0,45 m 7284008010 Hydraulic tubes GK ø8x1
Setting pressure for pressure switch (1S1): See product specification. 23 1 6107-12-08 Fitting KOR 12/8L
22 1 8303-00-12 Test connector DKLO 12L, M16x2
21 1 6035-12-12 Fitting DKLO 12L
*) Pressure step up ratio: 44.
Trap door / 10x Mounting screws, 20 1 6044-12-12 Fitting K 12L
Max. hydraulic outlet pressure is specific for Your installation,
could be opened at service 19 2 5601-02-18 Bonded seal M18
see product specification or contact Dellner Brakes AB. 18 2 6045-12-12 Fitting SV 12L
17 1 6089-12-06 Fitting EVGE 12L, G/ED 3/8"
**) Plus max. 5 l hydraulic fluid. 16 1 6042-12-12 Fitting W 12L
15 1 6009-12-06 Fitting GE 12L, G/ED 3/8"
14 2 6009-12-04 Fitting GE 12L, G/ED 1/4"
13 1 6130-00-08 Plug 8L
12 2 5703014000 Bonded seal G 1/4"
11 1 6045-08-08 Fitting SV 8L
10 1 5703012000 Bonded seal G 1/8"
9 1 6050-08-08 Fitting EVW 8L
8 1 6003-08-02 Fitting GE 8L, GB 1/8"
7 1 200-90-509 Adapter DG3-Y8 8L
6 1 200-90-510 Pressure switch DG36 4-12 bar
5 1 534-421-003-0 Safety valve G 1/4" (2-6 bar)
200
Datum/Date
(BWN 1 L-N-1-1-G24) PS Ritn. nr
2008-04-30 Draw. no. 319535-1
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
Product specification: 319535-1 lity.
Nr. Ändring Datum Inf. Godk.
No. Change Date Intr. Appr.
1P1 1V1
1Z2
A
~364
1Z3
1Z1
242,5
200 200
Drainage port DR (G 1/8")
255
B (1:2)
225 A (1:2)
B
4x n9
130
1Z4
Datum/Date
LP 80-12/B4 K1 (BWN 1 L-N-1-1-G24) Ritn. nr
2006-11-02 Draw. no. 319555
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
lity.
Document name Head line Date Page no.
COMPACTUS UNIT
PRODUCT SPECIFICATION LP80-12/B4 K1 (BWN 1 L-NN-1-1-G24) 2006-12-07 1 (of 1)
Issuer Approved by Contract / Order no. Contract name Document ID Revision
Pär Mikaelsson Peter Mikaelsson -/- - 319596 2
Product no. Assembly drawing Assembly drawing, PHPP Hydraulic circuit diagram Assemly / test instruction
319596 319596 319597 319596C -
Record of changes:
Revision Date Description of change Signature Approved
1 2007-06-12 Art. no. for pos. 1V1 and 1V2 corrected, was 200-35-225 PMi PM
Art. no. for pos. 1P1 added
2 2012-03-14 Art. no. for pos. 1V1 and 1V2 corrected, was 200-35-120 PMi PM
20
26
4
1V3
200
1V4 PI
1Z6
15
16
3
17 B1 B2
600
560
16 2
17
1P1
1V1
1V2
22 1Z1
1Z2 DR1
1Z3
1Z4
1Z5
9 4x n8,5
10 10 5 21 29 30 31 6 7 8 Hydraulic outlet ports Drainage port
1 Max. oulet pressure: See below *) Product specification: 319596
11
31 4 000125084000 Washer BRB 8.8 FZB 8,4x16x1,5
Cable gland for electric control supply 30 4 006924008000 Nut M6M locking 8.8 FZB M8
1V5 12 18 19 20 29 2 319287 Threaded bar 8.8 FZB M8x270
(to be sealed at assembly) Grip range: 11 -17 mm
28 4 00012564000 Washer BRB 8.8 FZB 6.4x12x1.5
M1 27 4 006924006000 Nut M6M locking 8.8 FZB M6
M2 26 4 000931006014 Screw M6S 8.8 FZB M6x14
25 2 000125125000 Washer BRB 8.8 FZB 12,5x35x3
Note: 24 2 006924012000 Nut M6M locking 8.8 FZB M12
Cabinet door not shown in upper left view. 23 2 319183 Eye bolt FZB M12
Trap door / 10x Mounting screws, 22 0,9 m 7284012015 Hydraulic tubes GK ø12x1,5
21 0,45 m 7284008010 Hydraulic tubes GK ø8x1
could be opened at service *) Pressure step up ratio: 44.
20 2 8303-00-12 Test connector DKLO 12L, M16x2
Max. hydraulic outlet pressure is specific for Your installation,
19 2 6035-12-12 Fitting DKLO 12L
see product specification or contact Dellner Brakes AB. 18 2 6043-12-12 Fitting T 12L
17 3 5601-02-18 Bonded seal M18
**) Plus max. 5 l hydraulic fluid. 16 3 6045-12-12 Fitting SV 12L
15 1 6089-12-06 Fitting EVGE 12L, G/ED 3/8"
14 1 6042-12-12 Fitting W 12L
13 1 6009-12-06 Fitting GE 12L, G/ED 3/8"
12 3 6009-12-04 Fitting GE 12L, G/ED 1/4"
11 1 6130-00-08 Plug 8L
10 2 5703014000 Bonded seal G 1/4"
9 1 6045-08-08 Fitting SV 8L
8 1 5703012000 Bonded seal G 1/8"
7 1 6050-08-08 Fitting EVW 8L
200
Datum/Date
(BWN 1 L-NN-1-1-G24) Ritn. nr
2006-12-07 Draw. no. 319596
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
lity.
Document name Head line Date Page no.
COMPACTUS UNIT WITH PRESSURE SWITCHES
PRODUCT SPECIFICATION LP80-12/B4 K1 (BWN 1 L-NN-1-1-G24) 2007-11-02 1 (of 1)
Issuer Approved by Contract / Order no. Contract name Document ID Revision
Pär Mikaelsson Peter Mikaelsson -/- - 319596-1 1
Product no. Assembly drawing Assembly drawing, PHPP Hydraulic circuit diagram Assemly / test instruction
319596-1 319596-1 319597 319596-1C -
Record of changes:
Revision Date Description of change Signature Approved
Art. no. for pos. 1P1 added
1 2012-03-14 Art. no. for pos. 1V1 and 1V2 corrected, was 200-35-120 PMi PM
20
29
4
1V3
200
1V4 PI
1Z6
17
18
3
19 B1 B2
600
560
18 2
19
1P1
1V1
1V2
25 1Z1
1Z2 DR1
1Z3
1Z4
1Z5
11
34 4 000125084000 Washer BRB 8.8 FZB 8,4x16x1,5
12 12 5 24 32 33 34 8 9 10 Hydraulic outlet ports Drainage port
33 4 006924008000 Nut M6M locking 8.8 FZB M8
Max. oulet pressure: See below *)
13 32 2 319287 Threaded bar 8.8 FZB M8x270
1S1 31 4 00012564000 Washer BRB 8.8 FZB 6.4x12x1.5
1V5 1S2 2x Cable gland for electric control supply 30 4 006924006000 Nut M6M locking 8.8 FZB M6
6 7 (to be sealed at assembly) Grip range: 11 -17 mm 29 4 000931006014 Screw M6S 8.8 FZB M6x14
(to be sealed at assembly)
28 2 000125125000 Washer BRB 8.8 FZB 12,5x35x3
27 2 006924012000 Nut M6M locking 8.8 FZB M12
14 20 21 22 23 26 2 319183 Eye bolt FZB M12
Note: 25 0,9 m 7284012015 Hydraulic tubes GK ø12x1,5
M1 Cabinet door not shown in upper left view. 24 0,45 m 7284008010 Hydraulic tubes GK ø8x1
M2 Setting pressure for pressure switches (1S1 & 1S2): See product specification. 23 2 6107-12-08 Fitting KOR 12/8L
22 2 8303-00-12 Test connector DKLO 12L, M16x2
21 2 6035-12-12 Fitting DKLO 12L
*) Pressure step up ratio: 44.
Trap door / 10x Mounting screws, 20 2 6044-12-12 Fitting K 12L
Max. hydraulic outlet pressure is specific for Your installation,
could be opened at service 19 3 5601-02-18 Bonded seal M18
see product specification or contact Dellner Brakes AB. 18 3 6045-12-12 Fitting SV 12L
17 1 6089-12-06 Fitting EVGE 12L, G/ED 3/8"
**) Plus max. 5 l hydraulic fluid. 16 1 6042-12-12 Fitting W 12L
15 1 6009-12-06 Fitting GE 12L, G/ED 3/8"
14 3 6009-12-04 Fitting GE 12L, G/ED 1/4"
13 1 6130-00-08 Plug 8L
12 2 5703014000 Bonded seal G 1/4"
11 1 6045-08-08 Fitting SV 8L
10 1 5703012000 Bonded seal G 1/8"
9 1 6050-08-08 Fitting EVW 8L
8 1 6003-08-02 Fitting GE 8L, GB 1/8"
7 2 200-90-509 Adapter DG3-Y8 8L
6 2 200-90-510 Pressure switch DG36 4-12 bar
5 1 534-421-003-0 Safety valve G 1/4" (2-6 bar)
200
Datum/Date
(BWN 1 L-NN-1-1-G24) PS Ritn. nr
2007-11-02 Draw. no. 319596-1
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
Product specification: 319596-1 lity.
Nr. Ändring Datum Inf. Godk.
No. Change Date Intr. Appr.
1Z2
A
~364
1Z3
1Z1
242,5
200 200
Drainage port DR (G 1/8")
255
B (1:2)
225
A (1:2)
1Z4 1Z5
B
4x n9
130
Pneumatic inlet port (G 1/4") Hydraulic outlet port Hydraulic outlet port
PH1 (G 1/4") PH2 (G 1/4")
Datum/Date
LP 80-12/B4 K1 (BWN 1 L-NN-1-1-G24) Ritn. nr
2006-12-07 Draw. no. 319597
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
lity.
Document name Head line Date Page no.
COMPACTUS UNIT
PRODUCT SPECIFICATION LP80-12/B4 K1 (BWN 1 L-NNN-1-1-G24) 2012-01-23 1 (of 1)
Issuer Approved by Contract / Order no. Contract name Document ID Revision
Pär Mikaelsson Peter Mikaelsson -/- - 321121 1
Product no. Assembly drawing Assembly drawing, PHPP Hydraulic circuit diagram Assemly / test instruction
321121 321121 321133 321121C -
Record of changes:
Revision Date Description of change Signature Approved
Art. no. for pos. 1P1 added
1 2012-03-14 Art. no. for pos. 1V1, 1V2 and 1V3 corrected, was 200-35-120 PMi PM
20
26
4
1V4
200
1V5 PI
1Z7
15
16
3
17 B1 B2 B3
600
560
2
16
1P1
17 1V1
1V2
1V3
1Z1
22 1Z2
1Z3 DR1
1Z4
1Z5
9 1Z6 4x n8,5
10 10 5 21 29 30 31 6 7 8 Hydraulic outlet ports Drainage port
Max. oulet pressure: See below *) Product specification: 321121
11
31 4 000125084000 Washer BRB 8.8 FZB 8,4x16x1,5
Cable gland for electric control supply 30 4 006924008000 Nut M6M locking 8.8 FZB M8
1V6 12 18 19 20 29 2 319287 Threaded bar 8.8 FZB M8x270
(to be sealed at assembly) Grip range: 11 -17 mm
28 4 00012564000 Washer BRB 8.8 FZB 6.4x12x1.5
M1 27 4 006924006000 Nut M6M locking 8.8 FZB M6
M2 26 4 000931006014 Screw M6S 8.8 FZB M6x14
M3 25 2 000125125000 Washer BRB 8.8 FZB 12,5x35x3
Note: 24 2 006924012000 Nut M6M locking 8.8 FZB M12
Cabinet door not shown in upper left view. 23 2 319183 Eye bolt FZB M12
Trap door / 10x Mounting screws, 22 1,1 m 7284012015 Hydraulic tubes GK ø12x1,5
21 0,45 m 7284008010 Hydraulic tubes GK ø8x1
could be opened at service *) Pressure step up ratio: 44.
20 3 8303-00-12 Test connector DKLO 12L, M16x2
Max. hydraulic outlet pressure is specific for Your installation,
19 3 6035-12-12 Fitting DKLO 12L
see product specification or contact Dellner Brakes AB. 18 3 6043-12-12 Fitting T 12L
17 4 5601-02-18 Bonded seal M18
**) Plus max. 5 l hydraulic fluid. 16 4 6045-12-12 Fitting SV 12L
15 1 6089-12-06 Fitting EVGE 12L, G/ED 3/8"
14 1 6042-12-12 Fitting W 12L
13 1 6009-12-06 Fitting GE 12L, G/ED 3/8"
12 4 6009-12-04 Fitting GE 12L, G/ED 1/4"
11 1 6130-00-08 Plug 8L
10 2 5703014000 Bonded seal G 1/4"
9 1 6045-08-08 Fitting SV 8L
8 1 5703012000 Bonded seal G 1/8"
7 1 6050-08-08 Fitting EVW 8L
200
C:\AutodeskVaultWork\DESIGNS\ARTICLES AND
File: PRODUCTS\HYDRAULICS\COMPACTUS\321121.idw
1 1 AS06064 Cabinet 600x600x400
Det. nr Antal Artikelnummer Benämning Vikt [kg]
Det. no. Number Art.no. Name Material Dimension Weight
Konstr./Des. Ritad Kontr. Skala Vikt Ersätter/Replace Ers.av/Replaced by
Cabinet door - Left hanged Electric connection box door - Screwed A2 PMi Drawn
PMi Control
PM Scale
1:5
Weight
47 **)
Datum/Date
(BWN 1 L-NNN-1-1-G24) Ritn. nr
2012-01-23 Draw. no. 321121
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
lity.
0 1 2 3 4 5 6 7 8 9
CONNECTION BOX
200x200x80MM
QTY. POS. DESCRIPTION MANUFACTURE
X1
CONDUIT
1xM25
2
Date 23.Jan.2012 =
CONN. BOX 321122
Desig. FNE
LAYOUT 06116-4 +
23.Jan.2012
COMPACTUS UNIT p. 1
Rev.date Verif.
Revision Norm
DELLNER BRAKES 2 p.
0 1 2 3 4 5 6 7 8 9
BRAKE (VALVE 2)
BRAKE (VALVE 3)
BRAKE (VALVE 1)
CONTROLSIGNAL
CONTROLSIGNAL
CONTROLSIGNAL
0V SPARE
SKD
SKD
SKD
1 2 3 4 5 6 7 8 9 10
BLACK
BLACK
BLACK
BLUE
BLUE
BLUE
1 2 3
1 2 1 2 1 2
1
Date 23.Jan.2012 =
CONN. BOX 321122
Desig. FNE
FIELD WIRING 06116-4 +
23.Jan.2012
COMPACTUS UNIT p. 2
Rev.date Verif.
Revision Norm
DELLNER BRAKES 2 p.
Document name Head line Date Page no.
COMPACTUS UNIT WITH PRESSURE SWITCHES
PRODUCT SPECIFICATION LP80-12/B4 K1 (BWN 1 L-NNN-1-1-G24) 2012-01-23 1 (of 1)
Issuer Approved by Contract / Order no. Contract name Document ID Revision
Pär Mikaelsson Peter Mikaelsson -/- - 321121-1 1
Product no. Assembly drawing Assembly drawing, PHPP Hydraulic circuit diagram Assemly / test instruction
321121-1 321121-1 321133 321121-1C -
Record of changes:
Revision Date Description of change Signature Approved
Art. no. for pos. 1P1 added
1 2012-03-14 Art. no. for pos. 1V1, 1V2 and 1V3 corrected, was 200-35-120 PMi PM
20
29
4
1V4
200
1V5 PI
1Z7
17
18
3
19 B1 B2 B3
600
560
2
18 1P1
19 1V1
1V2
1V3
1Z1
25 1Z2
1Z3 DR1
1Z4
1Z5
11 1Z6
34 4 000125084000 Washer BRB 8.8 FZB 8,4x16x1,5
12 12 5 24 32 33 34 8 9 10 Hydraulic outlet ports Drainage port
33 4 006924008000 Nut M6M locking 8.8 FZB M8
Max. oulet pressure: See below *)
13 32 2 319287 Threaded bar 8.8 FZB M8x270
1S1 31 4 00012564000 Washer BRB 8.8 FZB 6.4x12x1.5
1V6 1S2 2x Cable gland for electric control supply 30 4 006924006000 Nut M6M locking 8.8 FZB M6
6 7 1S3 Grip range: 11 -17 mm 29 4 000931006014 Screw M6S 8.8 FZB M6x14
(to be sealed at assembly)
(to be sealed at assembly) 28 2 000125125000 Washer BRB 8.8 FZB 12,5x35x3
27 2 006924012000 Nut M6M locking 8.8 FZB M12
14 20 21 22 23 26 2 319183 Eye bolt FZB M12
Note: 25 1,1 m 7284012015 Hydraulic tubes GK ø12x1,5
M1 Cabinet door not shown in upper left view. 24 0,45 m 7284008010 Hydraulic tubes GK ø8x1
M2 Setting pressure for pressure switches (1S1, 1S2 & 1S3): See product specification. 23 3 6107-12-08 Fitting KOR 12/8L
M3 22 3 8303-00-12 Test connector DKLO 12L, M16x2
21 3 6035-12-12 Fitting DKLO 12L
*) Pressure step up ratio: 44.
Trap door / 10x Mounting screws, 20 3 6044-12-12 Fitting K 12L
Max. hydraulic outlet pressure is specific for Your installation,
could be opened at service 19 4 5601-02-18 Bonded seal M18
see product specification or contact Dellner Brakes AB. 18 4 6045-12-12 Fitting SV 12L
17 1 6089-12-06 Fitting EVGE 12L, G/ED 3/8"
**) Plus max. 5 l hydraulic fluid. 16 1 6042-12-12 Fitting W 12L
15 1 6009-12-06 Fitting GE 12L, G/ED 3/8"
14 4 6009-12-04 Fitting GE 12L, G/ED 1/4"
13 1 6130-00-08 Plug 8L
12 2 5703014000 Bonded seal G 1/4"
11 1 6045-08-08 Fitting SV 8L
10 1 5703012000 Bonded seal G 1/8"
9 1 6050-08-08 Fitting EVW 8L
8 1 6003-08-02 Fitting GE 8L, GB 1/8"
7 3 200-90-509 Adapter DG3-Y8 8L
6 3 200-90-510 Pressure switch DG36 4-12 bar
5 1 534-421-003-0 Safety valve G 1/4" (2-6 bar)
200
File: PRODUCTS\HYDRAULICS\COMPACTUS\321121-1.idw
C:\AutodeskVaultWork\DESIGNS\ARTICLES AND
1 1 AS06064 Cabinet 600x600x400
Det. nr Antal Artikelnummer Benämning Vikt [kg]
Det. no. Number Art.no. Name Material Dimension Weight
Konstr./Des. Ritad Kontr. Skala Vikt Ersätter/Replace Ers.av/Replaced by
A2 PMi Drawn
PMi Control
PM Scale
1:5
Weight
47 **)
Cabinet door - Left hanged Electric connection box door - Screwed
Machinery plate Compactus unit LP80-12/B4 K1 E
Datum/Date
(BWN 1 L-NNN-1-1-G24) PS Ritn. nr
2012-01-23 Draw. no. 321121-1
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
Product specification: 321121-1 lity.
0 1 2 3 4 5 6 7 8 9
CONNECTION BOX
200x200x80MM
QTY. POS. DESCRIPTION MANUFACTURE
X1 PE
EARTH LINE
1 PE MALMBERGS
2099062
CONDUIT
2xM25
2
Date 23.Jan.2012 =
CONN. BOX 321123
Desig. FNE
LAYOUT 0852-2 +
23.Jan.2012
COMPACTUS UNIT p. 1
Rev.date Verif.
Revision Norm
DELLNER BRAKES 2 p.
0 1 2 3 4 5 6 7 8 9
BRAKE (VALVE 1)
BRAKE (VALVE 2)
BRAKE (VALVE 3)
CONTROLSIGNAL
CONTROLSIGNAL
CONTROLSIGNAL
0V
BRAKE STATUS
BRAKE STATUS
BRAKE STATUS
B1 ON/OFF
B2 ON/OFF
B3 ON/OFF
SKD
SKD
SKD
1 2 3 4 5 6 7 8 9 8 9 10 11 12 13 14 - 18
BLACK
BLACK
BLACK
BLACK
BROWN
BLACK
BROWN
BLACK
BROWN
BLUE
BLUE
BLUE
BLUE
BLUE
BLUE
SPARE
1 2 3 4 5 6
1 2 3 1 2 3 1 2 3
1 2 1 2 1 2
1
Date 23.Jan.2012 =
CONN. BOX 321123
Desig. FNE
FIELD WIRING 0852-2 +
23.Jan.2012
COMPACTUS UNIT p. 2
Rev.date Verif.
Revision Norm
DELLNER BRAKES 2 p.
Nr. Ändring Datum Inf. Godk.
No. Change Date Intr. Appr.
1V2
~201
1Z2
~364
1Z3
1Z1
242,5
200 200
Drainage port DR (G 1/8")
255
A (1:2)
B (1:2) 1Z5
225
1Z4 1Z6
130
Hydraulic outlet port
PH2 (G 1/4")
Pneumatic inlet port (G 1/4")
Hydraulic outlet port
PH3 (G 1/4")
File: PRODUCTS\HYDRAULICS\COMPACTUS\321133.idw
C:\AutodeskVaultWork\DESIGNS\ARTICLES AND
Det. nr Antal Artikelnummer Benämning Vikt [kg]
Det. no. Number Art.no. Name Material Dimension Weight
Konstr./Des. Ritad Kontr. Skala Vikt Ersätter/Replace Ers.av/Replaced by
A3 PMi Drawn
PMi Control
PM Scale
1:5
Weight
Datum/Date
LP 80-12/B4 K1 (BWN 1 L-NNN-1-1-G24) Ritn. nr
2012-02-01 Draw. no. 321133
Denna handling är upphovsrättsligt skyddad och får inte, utan This document is copyright legislationed protected and must
tillstånd från Dellner Brakes AB, delges eller överlämnas till not, without permission from Dellner Brakes AB, be given or
utomstående. Överträdelse medför ansvar. handed over to any outsider. Trespass give rise to responsibi-
lity.
8. Appendix list
44
Brief operation manual
for pneumatically operated hydraulic pump type LP
acc to D 7280 and D 7280 H
Maintenance unit Commercially available maintenance devices, consisting of air filter (filter cartridge approx. 5µm) with
water separator, pressure control valve (press, reducer), oiler and manometer are required for perfect
preparation of compressed air and safe functioning of the pumps (see sect. 4)
2.1. Size LP 80
Standstill pressure
su ing
L 6
L 7
Hydraulic operating pressures pHy (bar)
ba 8 700 7.1
n
io
r
pt
LP80- 10 630
m
su
1)
on
12 430 10
rc
Ai
16 240
pL = ppneum.
November 2001-02
B 7280 page 2
Standstill pressures
Op ess
1)
type
pr
r
er ure
Standstill Corresp. pneum.
ba
at
L6
ing p L
pressure (bar) pressure (bar)
p
Hydraulic operating pressures pHy (bar)
at
air 7 ba
n
8 700/(1500) 2) 2.9/ (6.2) 2)
io
pt
m
10 700/(1500) 2) 4.5/ (9.7) 2)
r
1)
rc
Ai
LP125-16 600
18 470
1)
20 380 10
25 240
30 160
pL = ppneum.
Standstill pressures
r
ba
ing p L
L6
air 7 ba
p
at
em
1) 12 4
rd
Ai
pL = ppneum.
3. Mounting instruction
Installation position like illustrated in the dimensional drawings (i.e. suction ports down, pressure ports and muffler up) as this
eases automatic bleeding of the hydraulic pump elements. A lateral or downward orientation is also possible, see sect. 3.2.2).
Volume superseding:
Tank bottom LP 80.. appox. 0.9 l with fluid level distance h , 15 - 20 mm to the mounting area
LP 125.. appox. 2.2 l with fluid level distance h , 20 - 25 mm to the mounting area
LP 160.. appox. 3.1 l with fluid level distance h , 25 - 30 mm to the mounting area
Hanging position, using fastening thread B 1; Side position, using fastening thread B 2
note torque (sect. 3.2.3)
Spacers between
tank and pump
Return pipe
Two suc-
tion pipes Example:
Suction pipes made from pre-
cision pipes, connected with
Tubing pipe fittings
Dirt strainer. e.g. wire grating with
mesh size approx. 0.6 ... 0.8 mm
B 7280 page 4
While taking into consideration the best position for the suction pipes, or in special operating circumstances as in sect. 5, the pump
cylinders can be turned by 90° in to different positions after loosening the screws b .
Restriction for LP 80: The pump can only be installed laterally like in illustration a) as complete unit (state of delivery). It is not pos-
sible to rotate the hydraulic cylinders in relation to the pneumatic cylinder. The other installations like illustration b or below are not
possible due to design reasons.
Pump position with horizontal suction connection Pump position with suction connection
a) Pump, as assembled by HAWE entering vertically from bottom to top
Pump mounted with cylinders turned by 180°
Distance
plates for wall
spacing
Two suc-
tion pipes
Spacers between
tank and pump
1. Set the pressure reducing valve on the maintenance unit to the lowest supply air pressure (approx. 1.5 bar). The air start valve
should be on stop.
2. Loosen the pressure pipe at the consumer sufficiently so that enclosed air can escape. Open the air start valve and wait for the
oil to come.
3. Air start valve on stop. Tighten the pressure pipe, and after starting the pump again, pressurize the unloaded consumer several
times and move it to and fro. Then turn the pressure reducing valve up as in 1 to required supply air pressure (step by step if
necessary), unit the desired end pressure, e.g. standstill pressure, is shown on the manometer of the pressure pipe to the
hydraulic consumer.
The maintenance unit in the compressed air supply pipe is obligatory, since it alone ensures smooth operation by filtering, moisture
separation and oil ing (= preperation of compressed air). It has a pressure reducing valve to limit the air pressure, which is
necessary on the hydraulic side to fix the standstill pressure.
Attention: Observe the max. air pressure rating for air pumps piped by HAWE!
A pressure reducing valve has to be used when the pump is supplied via compressed air cylinders. The pumps type LP do not fea-
ture any pressure valve on the pneumatic side !
Any industrial standard hydraulic oil (ISO VG 10) or spindle oil (ISO
VG 5 to 10) may be used in the pneumatic maintenance unit. The dy-
namic seals of piloting and main plunger of the reversal control valve
should be lubed regularily when connected to oil-free pneumatics
and frequent every-day use is intended. Suited are longterm lubes
e.g. Autol TOP 2000 from Co. Autol, Paradiesstraße 14, D-97080
4
1 Würzburg.
3 The maintenance intervalls depend on the indivdual operation con-
ditions e.g. a 3-4 month interval for 3-shift permanent operation.
See also notes in sect. 5
2
1
3
4
6
3 Reinstall the cover plate including O-rings. 1) Industrial standard pneumatic reducers
4 Remove the tapped plugs including the copper seal rings. can be installed at port L, if the thread of
port A at the pneumatic directional valve
5 Push the piloting plunger (any side) out of the housing. and port L at the air driven pump type LP
Lube the visible sections of the O-rings. are differing. The largest possible diameter
Reinstall the plunger in the housing. for the air line should be used always.
6 Reinstall the tapped plugs including the copper seal rings.
B 7280 page 6
1 4 4 1
Union pipe
2
3
Drain line to the tank
2
2 Hose 6020 077 a
1 Hose clamp T-PK-4 (FESTO)
3
1 3 Seal ring A 6x10x1 DIN 7603-Cu
4
4
0 1 2 3 4 5 6 7 8 9
WUPE001E 01.03.1994
JL AUTOMATIK AB
Tel: 0243-219900
Fax: 0243-219901
e-post: [email protected]
Electrical Drawings
Highest 0-number :
Not used 0-number :
Remarks:
2
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE 1452 +
23.Dec.2014
S-SYSTEM p. 1
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
Table of content Column x: created autom. but modified manually WUPJ005 22.04.96
1 23.Okt.2013 FNE
1 3
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
TABLE OF CONTENT 1452 +
23.Dec.2014
S-SYSTEM p. 2
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
K102
K103
K104
2919602
CONDUITS
2xM25
3xM20
2 4
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
LAYOUT 1452 +
23.Dec.2014
S-SYSTEM COMPACTUS p. 3
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
CONNECTION BOX
80x125x57MM
S-UNIT
PORT SIDE
QTY. POS. DESCRIPTION MANUFACTURE
X2
2 CABINET KLIPPON 9529150000 WEIDMULLER
1xM25
CONDUIT M16 RUTAB
2xM16 4
1476112
CONNECTION BOX
80x125x57MM
S-UNIT
STBD SIDE
X3
CONDUITS
1xM25
2xM16
3 5
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
LAYOUT 1452 +
23.Dec.2014
S-SYSTEM S-UNITS p. 4
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
+24VDC /6.0
0V /6.0
X1 3 5
CUSTOMER
X1 4 6
X1 7 9
1 1
1V1 1V2
2 2
BRAKE BRAKE
VALVE VALVE
X1 8 10
X1 1 2
ON/OFF ON/OFF
0V
4 6
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
BRAKE VALVES 1452 +
23.Dec.2014
S-SYSTEM p. 5
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
X1 11 12 15 16
S-UNIT S-UNIT
PORT SIDE STBD SIDE
X2 1 2 X3 1 2
X2 3 4 X3 3 4
X1 13 14 17 18
A1 A1 A1 A1
11 14 11 14 11 14 11 14
7.1 7.2 6.2 6.3
11 12 11 12 11 12 11 12
7.2 7.2 7.6 7.6
5 7
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
S-UNITS 1452 +
23.Dec.2014
S-SYSTEM PORT & STBD SIDE p. 6
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
11 11
K103 K104
11 11
K101 K102 6.6
12
6.6
12
6.1 6.2
12 12
21 22
X1 19 20
6 8
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
CUSTOMER SIGNALS 1452 +
23.Dec.2014
S-SYSTEM p. 7
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
X1 1 2 3 4 5 6 7 8 9 10
+24VDC
BLACK
BLACK
0V
REMOTE ACTIVATE
PORT BRAKES
REMOTE ACTIVATE
STBD BRAKES
BLUE
BLUE
POWER
SUPPLY
1 2
1 2 1 2
VALVE VALVE
Pos.1V1 Pos.1V2
7 9
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
FIELD WIRING 1452 +
23.Dec.2014
S-SYSTEM COMPACTUS p. 8
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
X1 11 12 13 14 15 16 17 18 X2 1 2 3 1 2 4 X3 1 2 3 1 2 4
1 2 3 4 1 2 3 4 1 2 3 1 2 3 1 2 3 1 2 3
5 6 7 8 9 10
1 2 3 1 2 3 1 2 3 1 2 3
1 2 3 4 1 2 3 4
+ - N0 + - N0 + - N0 + - N0
X2 1 2 3 4 X3 1 2 3 4
8 10
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
FIELD WIRING 1452 +
23.Dec.2014
S-SYSTEM p. 9
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
0 1 2 3 4 5 6 7 8 9
X1 19 20 21 22
9
Date 08.Maj.2014 =
CATERPILLAR PROP.
Desig. FNE
FIELD WIRING 1452 +
23.Dec.2014
S-SYSTEM CUSTOMER SIGNALS p. 10
Rev.date Verif.
Revision Norm
DELLNER BRAKES 10 p.
1(2)
BEDDING‐IN PROCEDURE FOR DELLNER DISC BRAKES
General
In order to achieve the optimum performance from Dellner disc brakes for a particular
application, it is important that the interface between the brake pads and the disc be
properly bedded or burnished.
The bedding‐in of the pads with the disc is generally a two step process. The first step is to
get the entire surface of the brake pads in full contact with the disc. Next is to generate
more and more heat between the pads and disc to burn off loose particles of friction
material and remove high spots from the pad surface.
Preparations
Before starting the process, check to be sure that the brake pads and the disc are clean and
dry. If the pads are contaminated with oil, it may be necessary to replace them. Oil soaked
pads will not provide the rated capacity of the brake. If the disc is dirty with grease or oil,
clean the surface with a solvent that leaves no residue. If the braking area of the disc is rusty,
clean it with a fine grade of abrasive paper and remove the dust with a clean cloth and
solvent.
Process time
The time required for the bedding process will vary depending of the severity of the required
braking duty. This can best be determined on the job site based on the observed
performance of the brake pads during the conditioning process.
Brakes that will be engaged frequently under dynamic conditions must first be worked lightly
to insure that the high spots are removed from the pads and that full contact with the disc is
achieved.
Pressure applied brakes
For pressure applied brakes, first apply 10% to 15% of the full pressure and allow the unit to
slip against the rotating disc until the surface reaches approximately 100° C. Stop and allow
the disc to cool. Slowly increase the pressure and slipping time until the disc surface reaches
approximately 200° ‐ 250° C. (For the maximum continuous operating temperature for the
friction material being used ‐ see Dellner Brakes Technical Specification manual TS0001.)
Allow the disc to cool to near ambient and repeat the process until full rating of the brake is
achieved.
AI04-011E-03
If the disc surface starts to glaze showing shiny deposits of friction material on the disc
surface, reduce the pressure and/or disc speed and progress more slowly to full brake
capacity. Remove any glazing from the disc surface with a fine grade of abrasive paper.
DELLNER BRAKES AB Tel: Fax: Org.nr/VAT no: Internet / e‐mail:
Vikavägen 144 023‐78 30 50 023‐77 06 90 556553‐1299 www.dellner‐brakes.com
SE ‐ 791 95 FALUN +46 23 78 30 50 +46 23 77 06 90 SE556553129901 info@dellner‐brakes.com
SWEDEN
2(2)
Spring applied, pressure released brakes
Spring applied, pressure released brakes require the same conditioning, but pressure on the
brake pads is increased by slowly reducing the applied pressure (back pressure) until the
maximum run‐in temperature and design capacity of the brake is reached.
Brakes used in light duty service may provide sufficient capacity without the run‐in
procedure. This can be determined on the job site before the units are put into full service.
After the run‐in procedure, adjust the air gap for spring applied brakes to the recommended
minimum, inspect and clean the units and they are ready to be put into service.
AI04-011E-03
Table of contents
1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.1 Field of application and purposes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.2 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.2.1 Personnel qualification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.2.2 Safely lifting the gearbox . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1
BV2122
Introduction
1 Introduction
1.1 Field of application and purposes
This operation description applies to heavy marine gearboxes with rigid fasten-
ing, metal seat chocks and longitudinal mounting arrangement. It does not apply
to light marine gearboxes in accordance with BV2378.
1.2 Safety
2
BV2122
Introduction
WARNING!
The gearbox can fall over if it is transported inappropriately or with unsuit-
able transport aids, lifting equipment and/or slings.
Persons hit by the gearbox can suffer life-threatening injuries and can be killed.
Make sure that transport is carried out only by persons competent in the use
of transport aids and lifting equipment.
Before every transport of the gearbox, make sure that nobody is in the gear-
boxʼs hazardous area.
Use only transport aids, lifting equipment, and slings that are approved for
the anticipated load and in perfect technical condition. The gearbox weight
(without operating oil but including special accessories) is stamped on the
type plate.
Transport aids and lifting equipment must be designed to be able to safely
hoist the load, hold it and set it down again.
Observe the regulations and instructions provided by the manufacturer of the
transport aids, lifting equipment, and slings.
Use only the lifting eyes intended for lifting the gearbox. The lifting eyes are
marked with signs and are indicated in the drawing of installation. Lifting eyes
on components, e.g. motor, are only intended for lifting these components
and not for lifting the whole gearbox.
Secure slings to all of the eyebolts intended for this purpose using shackles.
Never put slings around shaft ends, pipes, or other externally mounted parts.
Make sure that the sling angle does not exceed 45° from the perpendicular.
Use a traversing bridge if necessary.
NOTICE
Danger of damage to the gearbox!
When transporting the gearbox, make sure that you do not damage its
packaging, if further storage is intended afterward.
Avoid slings pressing against pipes or externally mounted parts. Use a tra-
versing bridge if necessary.
3
BV2122
Installation and alignment
2.2 Preparations
WARNING!
Observe the warnings in chapter 1.2.2 Safely lifting the gearbox.
Installation location
There must be enough space for the installation personnel in the working area.
Consider free spaces as indicated in the drawing of installation. The foundation
must be designed to absorb the gearbox weight and working loads.
Consider sufficient space for disassembling housing and shafts during later
maintenance work.
Work steps
1. Before setting up the gearbox, make sure that you have these documents:
a. operating manual
b. drawing of installation
c. supervision plan
d. alignment calculation (optional)
2. Make sure that you have fully read and understood all information concerning
alignment.
3. Place the gearbox on the foundation in the intended position.
4. Secure the gearbox against shifting on the foundation until it has been
aligned and permanently fastened.
5. Protect the gearbox from corrosion, contamination and damage.
The drawing of installation represents the basis for installation and alignment of
the gearbox. This drawing includes all dimensions and values relevant for instal-
lation and alignment of the gearbox. You will find the applicable drawing number
for your gearbox on the order confirmation.
You can obtain the drawing of installation from REINTJES by providing the gear-
boxʼs serial number.
REINTJES service
E-mail: [email protected] or
on working days: phone +49 5151 104 0
in emergencies and on weekends: phone +49 5151 104 237
4
BV2122
Installation and alignment
2.4 Alignment
5
BV2122
Installation and alignment
The process of alignment is basically identical for rigid and resilient fastening.
The difference is that with a rigid fastening the gearbox foot is fixed permanently
to the gearbox housing. With a resilient fastening the gearbox can be removed
from the base plate. It is possible to remove the gearbox from the base plate even
after the base plate is aligned and fixed with cast resin. The gearbox can then be
put back without another alignment.
For connecting the propeller shaft line with the gearbox, the propeller shaft and/
or the intermediate shaft must be in the static operating position.
That means:
the propeller shaft and the intermediate shaft are in their bearings
the propeller is mounted
the intermediate shaft flanges are connected (if present)
the flange facing the gearbox is in the alignment position (if necessary)
6
BV2122
Installation and alignment
Work steps:
1. Screw the alignment screws into the gearbox foot.
2. Fix the alignment screws for horizontal alignment to the foundation.
3. With the alignment screws, align the gearbox vertically and horizontally in
longitudinal and transverse directions with the propeller flange, according to
the specified data.
With a resilient fastening ensure that there is no distortion in the elastic elements
during the horizontal alignment. The base plates must be evenly displaced on
both sides of the gearbox.
4. Align the gearbox in accordance with the required GAP and SAG values.
5. With approved methods (gauges, laser), measure the vertical and horizontal
GAP value 4 as well as the vertical and horizontal SAG value 3 between the
gearbox flange 2 and the counter flange on the propeller side 1.
7
BV2122
Installation and alignment
2.4.3 Foundation
8
BV2122
Installation and alignment
Fig. 2-3: Metal seat chocks with four fitting bolts, through bolts and collision chocks for
propeller thrust AHEAD and ASTERN
Fig. 2-4: Metal seat chocks with through bolts and collision chocks for propeller thrust and
lateral fixation
9
BV2122
Installation and alignment
Fig. 2-5: Metal seat chocks with four fitting stud bolts, through stud bolts and collision
chocks for propeller thrust AHEAD and ASTERN
Fig. 2-6: Metal seat chocks with through stud bolts and collision chocks for propeller thrust
and lateral fixation
10
BV2122
Installation and alignment
Fig. 2-7: Metal seat chocks with fitting bolts and through bolts without collision chocks
11
BV2122
Installation and alignment
12
BV2122
Installation and alignment
General information
The gearbox foundation bolts are fitting bolts and/or through bolts.
Observe the following requirements:
1. Calculate the foundation bolts according to the state of the art. Under all op-
erating conditions, the preload of the bolts must be higher than the workload.
2. Consider for the bolt elongation that the connection cannot be loosened by
settlement effects. We recommend an elongation of the screws of > 0.17 mm
for cast resin seat chocks and of > 0.25 mm for metal seat chocks.
3. Any lifting of the gearbox under dynamic stress must be excluded.
4. Contact REINTJES service for information on the working forces. When cal-
culating the bolts, also consider external forces e.g. added by mounted com-
ponents that have an impact on the gearbox.
5. Secure all screw joints against loosening.
6. The seats of bolt heads and nuts have to be plane-parallel. Ensure that the
seat under the bolt head and nut is sufficiently dimensioned in order not to
exceed the permissible surface pressure.
13
BV2122
Installation and alignment
Fitting bolts
The fitting bolts fix the gearbox on the foundation.
Observe the following requirements:
1. The geometry of the fitting bolts must be designed such that at least 50 % of
the height of the gearbox foot and 50 % of the height of the top plate are cov-
ered by each shaft.
2. Only use fitting bolts with a tensile strength of at least 8.8 in accordance with
ISO 898. The fitting bolt bores are predrilled.
When using metal seat chocks and a sufficient number of fitting bolts, the propel-
ler thrust can be transmitted through the fitting bolts into the foundation. In this
case, check the fitting bolts for bolt bearing pressure and shear. Position the fit-
ting bolts in the direct vicinity of the thrust bearing.
14
BV2122
Installation and alignment
Through bolts
Only use through bolts with a tensile strength of at least 8.8 in accordance with
ISO 898.
The through bolts must comply with application-specific requirements and be
tightened to the specified torque.
15
BV2122
Installation and alignment
16
BV2122
Installation and alignment
Work steps:
1. With the alignment screws, align the engine horizontally in longitudinal and
transverse directions and vertically in front of the gearbox input flange, ac-
cording to the specified data.
2. With approved methods (gauges, laser), measure the vertical and horizontal
GAP value as well as the vertical and horizontal SAG value.
3. Observe the permissible tolerances:
SAG: Radial misalignment 0.05 mm (centreline run-out 0.025 mm)
GAP: Angular misalignment 0.1 mm/m
4. Document the GAP and SAG values.
17
BV2122
Installation and alignment
FR = Δ r x Cr dyn
Δ r = radial shaft misalignment
Cr dyn = radial stiffness of the flexible coupling
A = engine side gearbox flange
B = engine flywheel
6. Determine the corresponding bending moment MB.
MB = 0.5 x Cax x D x X1
Cax = axial stiffness of the flexible coupling
D = diameter of the connection between flange and flexible coupling
X1 = measured angular misalignment (GAP value)
7. Inform REINTJES of the reaction force FR, the bending moment MB and the
distance L for approval.
L = S + X = distance from application point FR to big cone diameter of gear-
box input shaft
8. During all operations, observe the instructions of the engine and coupling
manufacturers.
9. Check the GAP and SAG values.
10. Fix the engine to the foundation.
11. Connect gearbox and engine with the flexible coupling.
18
BV2122
Installation and alignment
Work steps:
1. Align the auxiliary unit that is driven by the PTO or driving the PTI with the
alignment screws, horizontally in longitudinal and transverse directions, and
vertically in front of the PTO or PTI shaft of the gearbox, according to the
specified data.
2. With approved methods (gauges, laser), measure the vertical and horizontal
GAP value as well as the vertical and horizontal SAG value.
3. Observe the permissible tolerances:
SAG: Radial misalignment 0.05 mm (centreline run-out 0.025 mm)
GAP: Angular misalignment 0.1 mm/m
4. Document the GAP and SAG values.
5. Consider the maximum permissible reaction forces exerted by the flexible
coupling on the gearbox PTO or PTI shaft.
6. During all operations, observe the instructions of the auxiliary unit and cou-
pling manufacturers.
7. Fix the auxiliary unit to the foundation.
8. Determine the reaction forces of the flexible coupling, see chapter 2.4.4 Con-
nection to engine.
9. Connect PTO or PTI and auxiliary unit with the flexible coupling.
19
BV2122
Installation and alignment
20
BV2122
Installation and alignment
21
BV2122
Installation and alignment
DANGER!
The electric stand-by pump is a live component.
Danger of death due to electric shock!
Have all work on the electric stand-by pump only be carried out by qualified
electricians.
Before carrying out any work on the electric stand-by pump, shut down power
supply and secure against unintentional restart.
WARNING!
If the pump operates in the wrong direction, excessive pressure could
build up. Pipes can burst and lubricants can escape.
Danger of severe injuries!
Check the rotation direction of the pump when installing the electric circuits
for the pump motor.
22
BV2123 Installation and alignment
Table of contents
1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.1 Field of application and purposes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.2 Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.2.1 Personnel qualification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.2.2 Safely lifting the gearbox . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1
BV2123
Introduction
1 Introduction
1.1 Field of application and purposes
This operation description applies to heavy marine gearboxes with rigid or resil-
ient fastening, cast resin seat chocks and longitudinal mounting arrangement. It
does not apply to light marine gearboxes in accordance with BV2378.
1.2 Safety
2
BV2123
Introduction
WARNING!
The gearbox can fall over if it is transported inappropriately or with unsuit-
able transport aids, lifting equipment and/or slings.
Persons hit by the gearbox can suffer life-threatening injuries and can be killed.
Make sure that transport is carried out only by persons competent in the use
of transport aids and lifting equipment.
Before every transport of the gearbox, make sure that nobody is in the gear-
boxʼs hazardous area.
Use only transport aids, lifting equipment, and slings that are approved for
the anticipated load and in perfect technical condition. The gearbox weight
(without operating oil but including special accessories) is stamped on the
type plate.
Transport aids and lifting equipment must be designed to be able to safely
hoist the load, hold it and set it down again.
Observe the regulations and instructions provided by the manufacturer of the
transport aids, lifting equipment, and slings.
Use only the lifting eyes intended for lifting the gearbox. The lifting eyes are
marked with signs and are indicated in the drawing of installation. Lifting eyes
on components, e.g. motor, are only intended for lifting these components
and not for lifting the whole gearbox.
Secure slings to all of the eyebolts intended for this purpose using shackles.
Never put slings around shaft ends, pipes, or other externally mounted parts.
Make sure that the sling angle does not exceed 45° from the perpendicular.
Use a traversing bridge if necessary.
NOTICE
Danger of damage to the gearbox!
When transporting the gearbox, make sure that you do not damage its
packaging, if further storage is intended afterward.
Avoid slings pressing against pipes or externally mounted parts. Use a tra-
versing bridge if necessary.
3
BV2123
Installation and alignment
2.2 Preparations
WARNING!
Observe the warnings in chapter 1.2.2 Safely lifting the gearbox.
Installation location
There must be enough space for the installation personnel in the working area.
Consider free spaces as indicated in the drawing of installation. The foundation
must be designed to absorb the gearbox weight and working loads.
Consider sufficient space for disassembling housing and shafts during later
maintenance work.
Work steps
1. Before setting up the gearbox, make sure that you have these documents:
a. operating manual
b. drawing of installation
c. supervision plan
d. alignment calculation (optional)
2. Make sure that you have fully read and understood all information concerning
alignment.
3. Place the gearbox on the foundation in the intended position.
4. Secure the gearbox against shifting on the foundation until it has been
aligned and permanently fastened.
5. Protect the gearbox from corrosion, contamination and damage.
The drawing of installation represents the basis for installation and alignment of
the gearbox. This drawing includes all dimensions and values relevant for instal-
lation and alignment of the gearbox. You will find the applicable drawing number
for your gearbox on the order confirmation.
You can obtain the drawing of installation from REINTJES by providing the gear-
boxʼs serial number.
REINTJES service
E-mail: [email protected] or
on working days: phone +49 5151 104 0
in emergencies and on weekends: phone +49 5151 104 237
4
BV2123
Installation and alignment
2.4 Alignment
5
BV2123
Installation and alignment
The process of alignment is basically identical for rigid and resilient fastening.
The difference is that with a rigid fastening the gearbox foot is fixed permanently
to the gearbox housing. With a resilient fastening the gearbox can be removed
from the base plate. It is possible to remove the gearbox from the base plate even
after the base plate is aligned and fixed with cast resin. The gearbox can then be
put back without another alignment.
For connecting the propeller shaft line with the gearbox, the propeller shaft and/
or the intermediate shaft must be in the static operating position.
That means:
the propeller shaft and the intermediate shaft are in their bearings
the propeller is mounted
the intermediate shaft flanges are connected (if present)
the flange facing the gearbox is in the alignment position (if necessary)
6
BV2123
Installation and alignment
Work steps:
1. Screw the alignment screws into the gearbox foot.
2. Fix the alignment screws for horizontal alignment to the foundation.
3. With the alignment screws, align the gearbox vertically and horizontally in
longitudinal and transverse directions with the propeller flange, according to
the specified data.
With a resilient fastening ensure that there is no distortion in the elastic elements
during the horizontal alignment. The base plates must be evenly displaced on
both sides of the gearbox.
4. Align the gearbox in accordance with the required GAP and SAG values.
5. With approved methods (gauges, laser), measure the vertical and horizontal
GAP value 4 as well as the vertical and horizontal SAG value 3 between the
gearbox flange 2 and the counter flange on the propeller side 1.
7
BV2123
Installation and alignment
2.4.3 Foundation
8
BV2123
Installation and alignment
Fig. 2-3: Cast resin seat chocks with four fitting bolts, through bolts and collision chocks
for propeller thrust AHEAD and ASTERN
Fig. 2-4: Cast resin seat chocks with through bolts and collision chocks for propeller thrust
and lateral fixation
9
BV2123
Installation and alignment
Fig. 2-5: Cast resin seat chocks with four fitting stud bolts, through stud bolts and collision
chocks for propeller thrust AHEAD and ASTERN
Fig. 2-6: Cast resin seat chocks with through stud bolts and collision chocks for propeller
thrust and lateral fixation
10
BV2123
Installation and alignment
Fig. 2-7: Cast resin seat chocks with four fitting bolts, through bolts and collision chocks
for propeller thrust AHEAD and ASTERN
Fig. 2-8: Cast resin seat chocks with four fitting stud bolts, through stud bolts and collision
chocks for propeller thrust AHEAD and ASTERN
11
BV2123
Installation and alignment
12
BV2123
Installation and alignment
General information
The gearbox foundation bolts are fitting bolts and/or through bolts.
Observe the following requirements:
1. Calculate the foundation bolts according to the state of the art. Under all op-
erating conditions, the preload of the bolts must be higher than the workload.
2. Consider for the bolt elongation that the connection cannot be loosened by
settlement effects. We recommend an elongation of the screws of > 0.17 mm
for cast resin seat chocks and of > 0.25 mm for metal seat chocks.
3. Any lifting of the gearbox under dynamic stress must be excluded.
4. Contact REINTJES service for information on the working forces. When cal-
culating the bolts, also consider external forces e.g. added by mounted com-
ponents that have an impact on the gearbox.
5. Secure all screw joints against loosening.
6. The seats of bolt heads and nuts have to be plane-parallel. Ensure that the
seat under the bolt head and nut is sufficiently dimensioned in order not to
exceed the permissible surface pressure.
13
BV2123
Installation and alignment
Fitting bolts
The fitting bolts fix the gearbox on the foundation.
Observe the following requirements:
1. The geometry of the fitting bolts must be designed such that at least 50 % of
the height of the gearbox foot and 50 % of the height of the top plate are cov-
ered by each shaft.
2. Only use fitting bolts with a tensile strength of at least 8.8 in accordance with
ISO 898. The fitting bolt bores are predrilled.
When using cast resin seat chocks the propeller thrust must not be transmitted
through the fitting bolts.
14
BV2123
Installation and alignment
Through bolts
Only use through bolts with a tensile strength of at least 8.8 in accordance with
ISO 898.
The through bolts must comply with application-specific requirements and be
tightened to the specified torque.
15
BV2123
Installation and alignment
Fig. 2-12: Fitting stud bolts with cast resin seat chocks
16
BV2123
Installation and alignment
Fig. 2-13: Through stud bolts with cast resin seat chocks
17
BV2123
Installation and alignment
We recommend the following thicknesses for the cast resin seat chocks and the
top plate:
Tolerances of the thicknesses of cast resin seat chocks and top plate of up to
40 mm can be compensated for by machining the bush.
18
BV2123
Installation and alignment
Work steps:
1. With the alignment screws, align the engine horizontally in longitudinal and
transverse directions and vertically in front of the gearbox input flange, ac-
cording to the specified data.
2. With approved methods (gauges, laser), measure the vertical and horizontal
GAP value as well as the vertical and horizontal SAG value.
3. Observe the permissible tolerances:
SAG: Radial misalignment 0.05 mm (centreline run-out 0.025 mm)
GAP: Angular misalignment 0.1 mm/m
4. Document the GAP and SAG values.
5. Consider the maximum permissible reaction forces exerted by the flexible
coupling on the gearbox input shaft.
FR = Δ r x Cr dyn
Δ r = radial shaft misalignment
Cr dyn = radial stiffness of the flexible coupling
A = engine side gearbox flange
B = engine flywheel
19
BV2123
Installation and alignment
Work steps:
1. Align the auxiliary unit that is driven by the PTO or driving the PTI with the
alignment screws, horizontally in longitudinal and transverse directions, and
vertically in front of the PTO or PTI shaft of the gearbox, according to the
specified data.
2. With approved methods (gauges, laser), measure the vertical and horizontal
GAP value as well as the vertical and horizontal SAG value.
3. Observe the permissible tolerances:
SAG: Radial misalignment 0.05 mm (centreline run-out 0.025 mm)
GAP: Angular misalignment 0.1 mm/m
4. Document the GAP and SAG values.
5. Consider the maximum permissible reaction forces exerted by the flexible
coupling on the gearbox PTO or PTI shaft.
6. During all operations, observe the instructions of the auxiliary unit and cou-
pling manufacturers.
7. Fix the auxiliary unit to the foundation.
8. Determine the reaction forces of the flexible coupling, see chapter 2.4.4 Con-
nection to engine.
9. Connect PTO or PTI and auxiliary unit with the flexible coupling.
20
BV2123
Installation and alignment
21
BV2123
Installation and alignment
22
BV2123
Installation and alignment
DANGER!
The electric stand-by pump is a live component.
Danger of death due to electric shock!
Have all work on the electric stand-by pump only be carried out by qualified
electricians.
Before carrying out any work on the electric stand-by pump, shut down power
supply and secure against unintentional restart.
WARNING!
If the pump operates in the wrong direction, excessive pressure could
build up. Pipes can burst and lubricants can escape.
Danger of severe injuries!
Check the rotation direction of the pump when installing the electric circuits
for the pump motor.
23
CONFIRMATION OF GEAR SHAFT INTERFACE DIMENSIONS
2 l 3 6 7 I 8 l 9 10 l 11 l 12
00.04 I C-13
771
[Q10.21
5
///// © 100.5
./
-----,,-..
b%' 7
I
- ____---
..e ,p,
.
.,
14
r.
C.,
CD CD
cS
C,
/SI o -31
' ' w...,,
25
iiìt .....
0.5 , • ..`G-
, ....
0 2x G1/4
fur Hydrculidencnt age tipfnU P
FOR hYDRALSALLY
0,05 A-B C,.SMANTLING
til0=14 tief/D
0,07 I A-B
TOLERANCED LIMITS
DIMENSION OF SIZE
.0,025
37 H7 0
r7-15 Li! 0.05 A-B
76 H7
.0,030
C,C:5 710 / 0
.0,040
,.••••
160 117 0
-0,017
OZ.• A-B 290 g6 -0,049
740
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
Gearbox LAF 873 HL-HR
Classification BV MMS
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Cover sheet
0-211- 120947 -
=
+
Page
F1
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
Table of contents
Page Page description supplementary page field
1 Cover sheet
2 Table of contents
3 Hydraulic diagram
4 Pressure switches
5 Pressure switches / Pressure transmitter
6 Temperature sensor - Temperature after oil cooler
7 Control valve - Main clutch
8 Terminal diagram =+-X000
9 Measuring points list
10 Monitor list
11 Terminal box
12 Pressure test valve
13 Grounding -Gearbox housing / Terminal box
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Table of contents
0-211- 120947 -
=
+
Page
F2
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
/4.8
-A74
P
-A128
/12.3 /4.0 /4.6 /12.4
-A35 -A103 -A125
P P
-A113
/12.2
MA MB
A B Main clutch
A B
/7.3
-V1
MP
MP
MP
-V1-a -V1-b
/7.4 /7.5
MP
P T
/6.3
-A55 -A480
MPS
Oil cooler T
P
/5.6
-A465
L T PS
Oil filter
P
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
-A43.1 P P -A43.2 -A128
/5.0 Δ Δ /5.2 /12.4
Gearbox pump
-A10
Dipstick
Lubrication oil
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Hydraulic diagram
0-211- 120947 -
=
+
Page
F3
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
Pressure switches
1-2 Pressure low
1-3 Pressure high
R = Resistor
delivery by
engine manufacturer
Feedback
Oil pressure too low - Alarm Main engine shut down
- Main clutch engaged
1 2 3 1 2 3 1 2 3
R
1 2 3 1 2 3 1 2 3
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
-X000 1 2 3 -X000 4 5 6 -X000 7 8 9 -X000 10 11 12 -X000 13 14 15
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Pressure switches
0-211- 120947 -
=
+
Page
F4
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
-A43.1 -A43.2
/3.1 /3.2 -A465
P P /12.5 P
Δ Δ /3.7
1 2 3 1 2 3 I
0-6 Bar / 4..20 mA
1 2 3 1 2 3 1+ 2
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
-X000 16 17 18 -X000 19 20 21 -X000 22 23 -X000 24 25 -X000 26 27 28
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Pressure switches /
Pressure transmitter
0-211- 120947 -
=
+
Page
F5
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
-A480.1
-A480.2
2L / 2x Pt100
Pt100
Pt100
1 3 2 4
Shield
-W480 BN BU WH BK
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
-X000 29 30 -X000 31 32 33 34 -X000 35 36
wiring by yard
-AS -MES
Alarm system Main engine system
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Temperature sensor
- Temperature after oil cooler
0-211- 120947 -
=
+
Page
F6
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
1+ U 2- 1+ U 2-
Plug
Plug
- -
+ +
Shield Shield
-W_V1.A 1 2 -W_V1.B 1 2
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
-X000 37 38 39 40
wiring by yard
-RC
Remote control system
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Control valve - Main clutch
0-211- 120947 -
=
+
Page
F7
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
Terminal diagram
-W103
-W125
-W74
-W43.1
-W43.2
-W465
-W480
-W_V1.A
-W_V1.B
Strip
Cable name
Cable name
=+-X000
C MC 2x0.75
ÖLFLEX HEAT
C MC 2x0.75
ÖLFLEX HEAT
C MC 3x0.75
ÖLFLEX HEAT
C MC 3x0.75
ÖLFLEX HEAT
C MC 3x0.75
ÖLFLEX HEAT
C MC 2x0.75
ÖLFLEX HEAT
C MC 2x0.75
ÖLFLEX HEAT 125
C MC 2x0.75
ÖLFLEX HEAT 125
Page / column
Connection
Connection
cable type
cable type
terminal
jumper
point
point
125
125
125
125
125
125
Function text Target designation Target designation
Oil pressure too low - Alarm -AS 1 -A103 1 1 /4.1
= -AS 2 -A103 3 2 /4.1
3 /4.1
4 /4.2
5 /4.3
6 /4.3
7 /4.4
8 /4.5
9 /4.5
Main engine shut down -MES 10 -A125 1 1 /4.6
= -MES 11 -A125 2 2 /4.6
12 /4.7
Feedback - Main clutch (com) -RC 13 -A74 1 1 /4.8
Feedback - Main clutch disengaged -RC 14 -A74 2 2 /4.8
Feedback - Main clutch engaged -RC 15 -A74 3 3 /4.9
Filter element 1 - (com) -AS 16 -A43.1 1 1 /5.1
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
Filter element 1 - ready -AS 17 -A43.1 2 2 /5.1
Filter element 1 - contaminated -AS 18 -A43.1 3 3 /5.1
Filter element 2 - (com) -AS 19 -A43.2 1 1 /5.2
Filter element 2 - ready -AS 20 -A43.2 2 2 /5.3
Filter element 2 - contaminated -AS 21 -A43.2 3 3 /5.3
22 /5.4
23 /5.5
Transmitter - Lubrication oil pressure -AS 24 -A465 1+ 1 /5.6
= -AS 25 -A465 2 2 /5.6
26 /5.8
27 /5.8
28 /5.9
29 /6.2
30 /6.2
Oil temperature - Alarm (Pt100) -AS 31 -A480 1 BN /6.3
= -AS 32 -A480 3 BU /6.4
Oil temperature - Engine slow down (Pt100) -MES 33 -A480 2 WH /6.5
= -MES 34 -A480 4 BK /6.5
35 /6.7
36 /6.7
Control valve - Main clutch engaged -RC 37 -zV1.1 1 /7.3
= -RC 38 -zV1.1 2 /7.4
Control valve - Main clutch disengaged -RC 39 -zV1.2 1 /7.5
= -RC 40 -zV1.2 2 /7.5
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Terminal diagram =+-X000
0-211- 120947 -
=
+
Page
F8
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
Measuring points list Note: XX - sequence alarm *Note: Time delay / Alarm suppression by customer
Pos. Measuring point Abbre. Responding value Function Function Function Alarm value Time delay Comment Function text
Low High Alarm slow down shut down
-A10 Pressure suction pipe P Connection point for gauge
-A35 Operating oil pressure P Visual indication at gearbox 0...40bar Manometer - Operating oil pressure
-A43.1 Filter difference pressure PDAH X X DP > 5bar Filter element 1 - contaminated
-A43.2 Filter difference pressure PDAH X X DP > 5bar Filter element 2 - contaminated
-A55 Oil temperature T Visual indication at gearbox 0...120°C / 32...248°F Temperature after oil cooler
-A74 Clutch oil pressure P X P > 17bar Feedback - Main clutch engaged
-A103 Operating oil pressure PAL X X P < 17bar *10sec - (Customer) Only during engagement of the clutch Oil pressure too low - Alarm
-A125 Operating oil pressure PALL X X X P < 15bar *10sec - (Customer) Only during engagement of the clutch Main engine shut down
-A465 Lube oil pressure PAL X X P < 0.2bar=4.53mA *Suppress below 70% of main engine max. rpm Transmitter_Lube oil pressure
-A480-A480.1 Oil temperature TAH X X T > 65°C Oil temperature - Alarm
-A480-A480.2 Oil temperature TAHH X X T > 70°C Oil temperature - Engine slow down
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Measuring points list
0-211- 120947 -
=
+
Page
F9
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
Monitor list
Pos. Manufacturer Designation Type number Measuring range Degree of protection
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Monitor list
0-211- 120947 -
=
+
Page
F
10
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
360 mm
160 mm
Cover
Cable glands
-A120
91 mm
-A21
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
Box
-A119
Cable glands
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Terminal box
0-211- 120947 -
=
+
Page
F
11
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
-A113 -A128
/3.3 /3.7
/3.7
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Pressure test valve
0-211- 120947 -
=
+
Page
F
12
Modification Date Name Original Replaced by Replaced by Supervision Page 13
0 1 2 3 4 5 6 7 8 9
Terminal box
PE
Grounding point
Box
-W_GRD.1
Grounding cable
wiring by Reintjes
1x16mm² / gn-ye
"Schutzvermerk nach DIN 34 beachten" copyright: REINTJES GmbH, Eugen - Reintjes - Strasse 7, D-31785 Hameln
Gearbox housing -
central grounding point
Safety note:
Gearbox housing has to be grounded by shipyard.
Ed.
Appr
VOI
KLA
18.06.2019 Gearbox
Commission
LAF 873 HL-HR Grounding -
Gearbox housing / Terminal box
0-211- 120947 -
=
+
Page
F
13
Modification Date Name Original Replaced by Replaced by Supervision Page 13
INSTALLATION MANUAL
MPP HDX
-1-
K.C. LTD. SHAFT EARTHING
DOCUMENT
REV(H) : 29/06/09
1. Introduction
A turning propeller shaft on a ship becomes electrically insulated from the hull by the
lubricating oil film in the bearings and by the use of non-metallic bearing materials in
the tail shaft. When the shaft is insulated in this way an electrical potential can be
measured between the shaft and the hull and this can accelerate corrosion in the ship.
If the ship has a system of cathodic protection, whether it is sacrificial anode or an
impressed current system, the shaft insulation will prevent the propeller and the boss
from receiving protection.
The electrical potential between the shaft and the hull can also cause a heavy current
to flow in bearings when the oil film breaks down or is contaminated with seawater.
This current can cause deep pitting of the bearing surface. Excessive wear on the shaft
bearings can often be traced to this cause.
Now in addition it’s necessary to reduce the spark erosion causing the excessive wear
on main engine metal bearings and this shaft earthing is the most appropriate method.
All the troubles can be avoided and cathodic protection can be extended to the
propeller if the shaft is properly earthed with a propeller shaft slip ring. The
effectiveness of the shaft earthing system should ensure a maximum contact resistance
of no greater than 0.001 ohms for a water filled bearing and 0.01 ohms for an oil filled
bearing.
Our own tests indicate that high silver content brushes running on a silver track have
repeatable low conductivity that can maintain these limits and ensure a low resistance
contact is maintained even under dirty conditions.
The shaft earthing assembly comprises a pair of high silver content / graphite
compound brushes mounted in balanced brush holder, running on a silver alloy slip
ring.
Each brush holder has a adjustable spring tensioner which is supplied preset to the
minimum and results in a pressure of 225g/cm2.
At this pressure the expected life of the brush is in excess of one year.
-2-
K.C. LTD. SHAFT EARTHING
DOCUMENT
REV(H) : 29/06/09
3. Installation
CAUTION : It is strictly required to install slip ring correctly according to following procedure
for the good performance of shaft earthing and longer life time of brushes.
3.1.1. Make clean the area where slip ring is positioned.
The area should be cleaned and prepared for a bright bare steel.
KEEP CLEAN
SHAFT
Approx.130mm
SHAFT
KEEP CLEAN
3.1.3. Put the slip ring around the shaft and mark the overlapped part.
Cut the overlapped part at an angle of 45 O carefully, which is very important job.
MARK FOR CUT
SHAFT
SLIP RING
-3-
K.C. LTD. SHAFT EARTHING
DOCUMENT
REV(H) : 29/06/09
- After cutting properly rub the both edges of inner surface of slip ring with a fine-mesh file or
sand paper as below. Then secure slip ring very tightness around shaft;
SLIP RING
SLIP RING
45
45
°
°
SHAFT
SECURE SLIP RING
VERY TIGHTNESS
AROUND SHAFT.
FINE-MESH
FILE OR
SAND PAPER
CORRECT INSTALLATION
FILE INNER SURFACE OF SLIP RING
3.1.4. Fasten the slip ring around the shaft by the tightening stainless steel band (B).
SHAFT
3.1.5. Fasten the both edges of slip ring with 3/4” pressure tape for a preparation of tight
fastening of stainless steel band.
Apply the tape to the slip ring five times at the opposite direction of the shaft rotation.
SHAFT
PRESSURE TAPE
(5 TIMES)
-4-
K.C. LTD. SHAFT EARTHING
DOCUMENT
REV(H) : 29/06/09
3.1.6. Fasten the stainless steel band(A) over the pressure tape tightly by tightening fixing bolt
around the edge of slip ring.
BAND (A) BAND (B)
SHAFT
3.1.7. Fasten the stainless steel band(B) over the pressure tape tightly by tightening fixing bolt
around the edge of slip ring.
After tightening bands (A, B), bend the end part of band to the opposite direction to
prevent loosening during the shaft rotates.
SHAFT
BAND
3.1.8. Apply 2” tape over both stainless steel bands (A & B) at the opposite direction of the shaft
rotation finally.
2" TAPE
SAHFT
MIN.30
WIDTH OF SLIP RING
AFTER FINAL INSTALLATION
WHERE BRUSHES RUN.
-5-
K.C. LTD. SHAFT EARTHING
DOCUMENT
REV(H) : 29/06/09
3.2.1. Carefully study the drawing for correct installation and keep the distance of 3mm
between bottom of brush holder and slip ring surface.
3.2.2. Fit the brush holder to the support bar and align the assembly so that the brushes
are able to run centrally on the slip ring, and the brush holders assembly is to be
clear of the slip ring securing brackets when the shaft rotates.
Secure the assembly in this position by tightening the hexagon headed bolt at the
top of the brush holder body.
3.2.3. Do not adjust the tension of spring without approval from K.C.Ltd.
3.3.1. The system comprises a bulkhead mounted panel that incorporates terminals and
a display meter. The system is self contained and requires no external power
supply.
4. Operation
4.2 Reading of below 80mV when shaft is turning at sea indicate proper grounding.
If readings are above 80mV, clean the faces of slip ring and brush with a clean
cloth.
4.3 The millivolt meter will read '0' when shaft is at rest because of the current
entering the propeller will return to the hull through main engine bearings and
engine foundation.
4.4 Check according to troubleshooting in case the millivolt meter reading is '0' when
shaft is turning at sea.
-6-
K.C. LTD. SHAFT EARTHING
DOCUMENT
REV(H) : 29/06/09
5.1 This grounding assembly should be checked at least twice a week for cleanliness.
5.2 If there has been a build-up of oil, dirt, scale and rust on the slip ring face or
between slip ring and shaft, this should be removed with a degreaser, emery paper
and clean cloth.
5.3 Inspect and clean the brushes and brush holder to prevent their moving due to dirt
build-up. Inspect the brush copper leads (pig tails) to ensure they have not
become loose or corroded. The brush wear-down should be noted.
5.4 At the time of every dry dock, disassemble the slip ring and clean the surface of
the shaft right thereunder.
6.1 The brushes are getting worn out by metal touch with slip ring.
Therefore it’s strictly required to keep clean and smooth surface of slip ring, also to
carry out proper installation / alignment of brush holders as per our manual and
drawing. Otherwise it’s very hard to obtain the proper earthing and the proper life
time of brushes.
6.2 The brushes are consumable parts with wearing ratio approximately 2~3mm per 1,000
hours shaft rotation under proper installation.
The replacement time is shown by engraving the line (15mm from the top) on the
brushes.
Customer is requested to replace brushes with spares when the time comes.
6.3 Brushes are consumable parts as stated above and they are often consumed earlier but
it’s not a matter of guarantee claim for supplying extra brushes.
6.4 Use only our genuine silver graphite brushes for longer life and higher earthing
efficiency.
Contact K.C. LTD. for purchasing and indicate part number.
CAUTION
Customers are recommended for the purchase of genuine spare parts as imitated
parts make the system get fatally wrong.
Of course a quick technical support and maintenance services are guaranteed
with only our genuine parts.
-7-
K.C. LTD. Shaft Earthing Device
REV(D)18/06/09
From the above check you can find the reading above 1mV with brush(es) removed
from double brush holder and also 0mV with double brushes fitted, which means
present 0mV reading proves good shaft grounding.
So don't worry about "0" reading at the present.
-8-
K.C. LTD. Shaft Earthing Device
REV(D)18/06/09
03 The millivolt 1) The edge of slip ring is not 1) Make smooth edge preparation
value is smooth. by sand(emery) paper.
varied 2) The edge of slip ring is found 2) Dismantle and tightly install
widely. gap. again to remove the gap. When
the slip ring is tightly installed no
overlapped part or gap is found.
In case there happens
with overlapped part smoothly
rub the overlapped part with sand
(emery) paper.
3) The surface of slip ring got 3) Replace the old slip ring with
damaged. new one.
-9-
INSTALLATION MANUAL
MPP HDX
10x45° M5
20
10x45°
B R22
115
B B
84.9
84.9
B
68
B
51
B
third party nor be used for any unauthorized purpose. Contravention will be prosecuted in accordance with Swedish law.
This document must not be copied without our written permission, and the contents thereof must not be imparted to a
35
10
20 2x 9 10
A
Note:
MATERIAL:
1.4436, X4CrNiMo17-13-3
according to EN10250-4
(SS 2343)
ALTERNATIVE MATERIAL:
316L
according to AISI
Drawn Checked Approved E Previous dwg. Tot.weight
NC MN 16539 0.22
Sheet of Date
40467
Revis.
B
INSTALLATION MANUAL
MPP HDX
7. ALARM SYSTEM
TRUE Oil Pressure Pitch Pump 2 Low On/Off Pressure Switch NC <10 bar 8 Autostart Pitch Pump 1
TRUE Oil Pressure Pitch Pump 1 Low On/Off Pressure Switch NC <10 bar 8 Autostart Pitch Pump 2
TRUE Oil Pressure Pitch System Low On/Off Pressure Switch NC <6 bar 5
TRUE Oil Temperature Pitch High On/Off Temp. Switch NC >60°C 5
TRUE Oil Level Pitch Low On/Off Level Switch NC <70% 4
TRUE Oil Pressure Pitch High On/Off Pressure Switch NC >55 bar 5
TRUE Oil Filter Pitch Blocked On/Off Pressure Switch NC >5 bar 10 Differential pressure
TRUE Oil Filter Lubrication Blocked On/Off Pressure Switch NC >2 bar 10 Differential pressure
TRUE Pump Started (103-105 Closed) On/Off P.F. Contact <10 bar Delay set in starter
TRUE Phase Fault Alarm & Voltage Alarm On/Off P.F. Contact 20V Treshold Voltage Window +/-20V
TRUE Pump Started (103-105 Closed) On/Off P.F. Contact <10 bar Delay set in starter
TRUE Phase Fault Alarm & Voltage Alarm On/Off P.F. Contact 20V Treshold Voltage Window +/-20V
8. APPENDIX - DRAWINGS
8.1. MECHANICS
8.2. HYDRAULICS
See the hydraulic installation manual.
TO BE LOCKED IN BLADE ROOT TIGHTENING TORQUE: 910 Nm Basic size Tolerances Basic size Tolerances
WITH LOCTITE 242 OR EQUIVALENT OVERRULED BY TIGHTENING ANGLE, SEE SKETCH (0,5)- 3 ±0,1 (1000)- 2000 ±1,2
30 TIGHTENING TORQUE: 550 Nm (3)-
(6)- 30
6 ±0,1
±0,2
(2000)- 4000
(4000) 8000
±2
±3
OVERRULED BY TIGHTENING ANGLE, SEE SKETCH (30)- 120 ±0,3 (8000)-12000 ±4
(120)- 400 ±0,5 (12000)-16000 ±5
(400)-1000 ±0,8 (16000)-20000 ±6
16 9 7 48
28 8 47
21
a3 2x10 A
LOCTITE 243
26° a3 2x20
37 38 35
12
11,
20% OF TIGHTENING TORQUE 9
FULL TIGHTENING 29
°
7 11
,4
20% OF TIGHTENING TORQUE 11
,3
D (1.3 : 1)
8 FULL TIGHTENING
53
C (1.3 : 1) TORQUE:
60 SEE EXPANSION 45
B DOWEL DRAWING
187 Nm 10 45 1 54 12 49 5
A
18 A 36 31 32
17 B-B (1 : 4)
540
BLADE SEAL
52 OIL TYPE PART No.
MINERAL TO4480
EAL TO4480-V
The copying, distribution and utilization of this document as well as the communication of its contents to other without expressed authorization is prohibited. Offenders will be held liable for the payment of damages.
TO2795
70 AHEAD 52 1 O-RING TO2772
99 51 1 O-RING 89,5x3 SMS 1586/87
TO2289
126 A 50
D 49 4 O-RING TO2249
C 48
47
24 O-RING
16 O-RING
TO1139
TO1136
E 46 1 O-RING TO2219
45 4 BLADE SEAL SEE TABLE
All rights reserved in the event of the grant of a patent, utility model or ornamental design registration. Caterpillar: Yellow Confidential ® Caterpillar Propulsion AB
TX4680
35 2 GUIDE RING LX4465
51930
425 E (1 : 1.5)
A-A A
Dev. Order Deviation comprises Date Sign Check. Appr. Surface texture ISO/R 1302 Ra µm
When not otherwise stated :
Angle dimension tolerance shall comply with SS-ISO 2768-1 middle column.
Linear dimension tolerance shall comply with SS-ISO 2768-1 middle column. (See the table below)
6680
8
ADD CORTEC VPCI-368 OR SIMILAR
A FROM RECESS TO CLADDED SURFACE
11 10
B
The copying, distribution and utilization of this document as well as the communication of its contents to other without expressed authorization is prohibited. Offenders will be held liable for the payment of damages.
K=15
16
1457 Nm
6 7
9
All rights reserved in the event of the grant of a patent, utility model or ornamental design registration. Caterpillar: Yellow Confidential ® Caterpillar Propulsion AB
A
4 1 2 3
99 L = 229
A-A (1 : 5)
16 1 O-RING TO2760
15 1 O-RING TO2324
14 15 5 12 13 14 1 O-RING TO2736
13 8 LOCKING WASHER BL3010
12 8 BOLT MC6S SM6822
11 4 LOCKING WASHER BL3016
10 4 BOLT M6S SM1532
9 8 CYLINDRICAL PIN 70431 CP70431
8 1 DISC-BRAKE 70337 AB70337
7 12 NUT MM2036
6 12 BOLT-FLANGE 53829 SE53829
5 1 RING-SEALING 70322 TR70322
4 1 GUARD-PROTECTIVE 70323 SK70323
3 1 OMC ASSEMBLY 70354 AK70354
2 1 PIPE GP-PROP 70429 AR70429
1 1 SHAFT-PROP 70311 AP70311
Item No. No.of Description Reference Material Part No.
THE CORRECT DRIVE UP LENGTH IS REACHED
WHEN THE AFT END OF THE COUPLING IS Drawn Checked Approved E Previous dwg. Tot.weight
70312 -
Dev. Order Deviation comprises Date Sign Check. Appr. Rev. Revision comprises Date Sign. Check. Appr.
Surface texture ISO/R 1302 Ra µm
When not otherwise stated :
Angle dimension tolerance shall comply with SS-ISO 2768-1 middle column.
Linear dimension tolerance shall comply with SS-ISO 2768-1 middle column. (See the table below)
35
D=30
4
The copying, distribution and utilization of this document as well as the communication of its contents to other without expressed authorization is prohibited. Offenders will be held liable for the payment of damages.
6 3 5
7 2 1
47 Nm
SCALE 1 : 2.5
8x 11
190
160 h11
P.C.D.
7 1 POTENTIOMETER EP3271
6 1 O-RING TO2680
5 8 BOLT MC6S SM2626
4 1 EXTENSION PIPE 54698 AR54698
3 1 FLANGE–CONNECTION 56955 AF56955
2 1 PCU ELECTRICAL 61396 HD61396
1 1 PCU MECHANICAL 50381 HD50381
Item No. No.of Description Reference Material Part No.
Drawn Checked Approved E Previous dwg. Tot.weight
AE 95
Sheet of Date
70421 -
Dev. Order Deviation comprises Date Sign Check. Appr. Revis. Revision comprises Date Sign. Check. Appr.
Surface texture ISO/R 1302 Ra µm
When not otherwise stated :
Angle dimension tolerance shall comply with SS-ISO 2768-1 middle column.
Linear dimension tolerance shall comply with SS-ISO 2768-1 middle column. (See the table below)
58 3 2 26 45 59 8 7 9 55 59 10 12 59 18 11
24 Nm
46 32
0
25 28
C 33
13
1 4 32 34
57
56
301
25 24 Nm
28 C (2 : 1.5)
B 15
5 47 33 17 33 32 31 6 35
48
LOCTITE 638
50
LOCTITE 638
NOTE!
AT FINAL ASSEMBLY-YARD INSTALLATION
TO BE LOCKED WITH LOCTITE 243
(MEDIUM STRENGTH) OR EQUIVALENT.
14
24 Nm
19 49 LOCTITE 638
LOCTITE 243
A 0,05 A 0,05 A B (2 : 1.5)
65
REPLACE WITH 15 TO MOVE CONNECTION FOR "L"
16 ALL EXTERNAL STEEL SURFACES TO BE PAINTED
0-PITCH
The copying, distribution and utilization of this document as well as the communication of its contents to other without expressed authorization is prohibited. Offenders will be held liable for the payment of damages.
59 3 O-RING TO2654
Max. ASTERN 69 Max. AHEAD 204 58 1 O-RING TO2620
57 1 O-RING TO2315
56 3 O-RING TO2308
55 4 O-RING TO2294
50 2 WASHER BG1513
49 2 WASHER BG1007
A 48 2 PLUG SR4064
47 1 GUIDE RING LX7033
239
46 1 RADIAL SEAL TM2138
45 2 RADIAL SEAL TM2142
A
All rights reserved in the event of the grant of a patent, utility model or ornamental design registration. Caterpillar: Yellow Confidential ® Caterpillar Propulsion AB
50361 -
Dev. Order Deviation comprises Date Sign Check. Appr. Revis. Revision comprises Date Sign. Check. Appr.
Surface texture ISO/R 1302 Ra µm
- See Sheet1 - - - - When not otherwise stated :
Angle dimension tolerance shall comply with SS-ISO 2768-1 middle column.
Linear dimension tolerance shall comply with SS-ISO 2768-1 middle column. (See the table below)
209,2
"D"
"A" 205,6
185,4
0-PITCH=719
D-D
"A"
"D" "B"
The copying, distribution and utilization of this document as well as the communication of its contents to other without expressed authorization is prohibited. Offenders will be held liable for the payment of damages.
D
All rights reserved in the event of the grant of a patent, utility model or ornamental design registration. Caterpillar: Yellow Confidential ® Caterpillar Propulsion AB
"L"
"L"
"B"
E-E "B"
Drawn Checked Approved E Previous dwg. Tot.weight
Amm BW JG 56
Sheet of Date
50361 -
Dev. Order Deviation comprises Date Sign Check. Appr. Revis. Revision comprises Date Sign. Check. Appr.
Surface texture ISO/R 1302 Ra µm
When not otherwise stated :
Angle dimension tolerance shall comply with SS-ISO 2768-1 middle column.
Linear dimension tolerance shall comply with SS-ISO 2768-1 middle column. (See the table below)
6 (3)-
(6)- 30
6 ±0,1
±0,2
(2000)- 4000
(4000) 8000
±2
±3
(30)- 120 ±0,3 (8000)-12000 ±4
(120)- 400 ±0,5 (12000)-16000 ±5
(400)-1000 ±0,8 (16000)-20000 ±6
50
7 D A B L
A
CONNECTION FLANGE
SEE PCU ASSEMBLY
5
D
4
LENGTH OF HOSES, 1m
B
5
3 L
The copying, distribution and utilization of this document as well as the communication of its contents to other without expressed authorization is prohibited. Offenders will be held liable for the payment of damages.
~280
50 65
504
660
All rights reserved in the event of the grant of a patent, utility model or ornamental design registration. Caterpillar: Yellow Confidential ® Caterpillar Propulsion AB
25
°
E
26
Amm BW JG 97
19
Sheet of Date
CAN BE ROTATED IN STEPS OF 45° PCU MECHANICAL 1 1 08 Apr 2015
TO SUIT PIPING AND VISIBILITY. CAN BE ROTATED IN STEPS OF 90°. Part No. Scale
50381 -
Dev. Order Deviation comprises Date Sign Check. Appr. Revis. Revision comprises Date Sign. Check. Appr.
Surface texture ISO/R 1302 Ra µm
When not otherwise stated :
Angle dimension tolerance shall comply with SS-ISO 2768-1 middle column.
Linear dimension tolerance shall comply with SS-ISO 2768-1 middle column. (See the table below)
24,5
(120)- 400 ±0,5 (12000)-16000 ±5
20
12,5 (400)-1000 ±0,8 (16000)-20000 ±6
A
The copying, distribution and utilization of this document as well as the communication of its contents to other without expressed authorization is prohibited. Offenders will be held liable for the payment of damages.
700
All rights reserved in the event of the grant of a patent, utility model or ornamental design registration. Caterpillar: Yellow Confidential ® Caterpillar Propulsion AB
25
NOTE: BRAKE DISC IS NON-SPLIT VERSION
OMC200
70337 A
INSTALLATION MANUAL
MPP HDX
Important!
Failure to follow the oil requirements can shorten the service life of the
propulsion equipment.
GENERAL
Yard no.:
Shipyard: Detroit Brasil
ELECTRONICS Yes No
1. Electronic equipment installed:
a) Central unit
b) Local unit
d) ECR interface plate
e) Bridge interface plate
f) All panel frames mounted
2. All external cables terminated
3. All power supplies to Caterpillar System rdy to power "on"
STARTUP Yes No
M/E, G/B ready for interface check
Joystick/DP ready for interface check