Plan Schedule TB. CAMAR 20
Plan Schedule TB. CAMAR 20
Plan Schedule TB. CAMAR 20
Jeneponto
PT. PELAYARAN PELANGI SINDU MULIA
OS Hartono 2-Jul 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Pimpro
Mukhlis Hidayat Daily '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
31-Dec 7/2/2021 7/3/2021 7/4/2021 7/5/2021 7/6/2021 7/7/2021 7/8/2021 7/9/2021 7/10/2021 7/11/2021 7/12/2021 7/13/2021 7/14/2021 7/15/2021 7/16/2021 7/17/2021 7/18/2021 7/19/2021 7/20/2021 7/21/2021 7/22/2021
'21
'21
'21
'21
'21
Jul
'21
Jul
'21
'21
Jul
'21
Jul
'21
Jul
'21
'21
'21
Jul
'21
Jul
'21
Jul
'21
'21
Jul
Jul
'21
Jul
'21
Jul
'21
'21
Jul
Jul
Jul
Jul
Jul
Jul
Jul
Jul
Jul
13
14
15
18
19
20
21
10
11
12
16
17
22
100.00%
9
ASSIGNED
WBS TASK DESCRIPTION
TO
Weight Prosentase START FINISH Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1.1 kapal datang sampai delivery PAMI 100% 2-Jul 22-Jul 21 Plan
actual
progress pekerjaan sesuai repair list awal progress pekerjaan pekerjaan tambahan
PLAN ACTUAL DEVIASI
110.00%
15
90.00%
70.00% 10
50.00% 5
30.00%
0
10.00% 1 2 3 4 5 6 7 8 9 10
-10.00% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A Before Docking PIC 5.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
'21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
A1 kapal sandar di jetty PAMI 1.25% 0.00% belum finish 22-Jan 30-Jan 9 Plan 0.14%
0.00% actual
A2 persiapan lahan PAMI 1.25% 0.00% belum finish 28-Jan 30-Jan 3 Plan 0.42%
0.00% actual
A3 start docking sampai duduk PAMI 1.50% 0.00% belum finish 1-Jul 2-Jul 2 Plan 0.75% 0.75%
0.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
B During Docking ( pelayanan umum ) 5.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
B1 pelayanan umum 2.00% 0.00% belum finish 30-Jan 13-Feb 15 Plan '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21 '21 '21 '21 '21 '21
docking report ( 4 rangkap ) 0.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
C Propulsion 25.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
C1 Ukur clearance poros baling-baling pintle terhadap bantalannya( in & out board) 1.00% 100.00% finish 2-Jul 3-Jul 2 Plan '21 '21
0.50% '21
0.50% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
1.00% actual 1.00%
C2 Lepas rudder blade, Rudder Stock, propeller & shaft Propeller 3.00% 166.67% belum finish 2-Jul 3-Jul 2 Plan 1.50% 1.50%
5.00% actual 2.50% 0.50% 1.00% 1.00%
C3 Cek Kelurusan shaft di meja bubut 2.00% 100.00% belum finish 3-Feb 4-Feb 2 Plan 1.00% 1.00%
Penggantian fender
Page 1 552511416.xls
0.50% actual 0.50%
Penggantian ban daprah 1.50% 0.00% belum finish 13-Feb 14-Feb 2 Plan 0.75% 0.75%
0.00% actual
Page 2 552511416.xls
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
E Pekerjaan Mooring Equipments 5.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
E1 Pengukuran dan kalibrasi rantai jangkar 1.00% 0.00% belum finish 31-Jan 31-Jan 1 Plan '21 '21
1.00% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
mp and motor , electrical 0.00% actual
E2 Perawatan jangkar dan rantai jangkar 3.00% 0.00% belum finish 6-Feb 8-Feb 3 Plan 1.00% 1.00% 1.00%
mp and motor , electrical 0.00% actual
E3 Pembuatan cover lubang urloop 1.00% 100.00% finish 2-Feb 3-Feb 2 Plan 0.50% 0.50%
1.00% actual 2 3 4 0.50%
5 0.50%
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
F Pekerjaan Pipa, Valve, Pump, Vent head 5.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
F1 Penggantian pipa inlet mesin M/E 0.50% 50.00% belum finish 5-Feb 8-Feb 4 Plan '21 '21 '21 '21 '21 '21 '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
0.25% actual 0.25%
F2 Perbaikan pipa filling, vent, sounding Tangki PS & SB 1.00% 100.00% finish 8-Feb 9-Feb 2 Plan 0.50% 0.50%
1.00% actual 0.50% 0.50%
Perbaikan pipa pendingin shaft PS & SB 0.50% 100.00% finish 2-Feb 3-Feb 2 Plan 0.25% 0.25%
0.50% actual 0.25% 0.25%
Penambahan rakor 0.25% 100.00% finish 7-Feb 9-Feb 3 Plan 0.08% 0.08% 0.08%
0.25% actual 0.12% 0.13%
Perbaikan pipa Wastafel 0.25% 100.00% finish 7-Feb 9-Feb 3 Plan 0.08% 0.08% 0.08%
0.25% actual 0.12% 0.13%
F3 Penggantian pipa inlet cooling ME dan hose pipe ME (PS & SB) 1.00% 100.00% finish 2-Feb 5-Feb 4 Plan 0.25% 0.25% 0.25% 0.25%
1.00% actual 0.25% 0.25% 0.25% 0.25%
Penggantian inlet dan outlet Cooling pipe (PS & SB) 1.00% 100.00% finish 3-Feb 6-Feb 4 Plan 0.25% 0.25% 0.25% 0.25%
1.00% actual 0.25% 0.25% 0.25% 0.25%
Perbaikan shaft cooling pipe (PS & SB) 0.25% 100.00% finish 5-Feb 7-Feb 3 Plan 0.08% 0.08% 0.08%
0.25% actual 0.25%
Perbaikan cooling pipe gear box (PS & SB) 1.00% 100.00% finish 6-Feb 8-Feb 3 Plan 0.33% 0.33% 0.33%
1.00% actual 1.00%
Service seachest box dan grating 0.75% 100.00% finish 10-Feb 11-Feb 2 Plan 0.38% 0.38%
0.75% actual 0.38% 0.37%
Service gate valve PS & SB (hidro test dan ganti packing) 0.75% 100.00% finish 1-Feb 3-Feb 3 Plan 0.25% 0.25% 0.25%
0.75% actual 0.37% 0.38%
Service sea strainer PS & SB (ganti packing) 0.25% 100.00% finish 3-Feb 5-Feb 3 Plan 0.08% 0.08% 0.08%
0.25% actual 0.25%
Service tank emergency valve (hidro test dan ganti packing) 0.25% 48.00% belum finish 5-Feb 7-Feb 3 Plan 0.08% 0.08% 0.08%
0.12% actual 0.12%
Service hand pump chain locker (ganti packing) 0.25% 100.00% finish 7-Feb 9-Feb 3 Plan 0.08% 0.08%
0.25% actual 0.12% 0.13%
Service strainer AE PS & SB 0.50% 100.00% finish 9-Feb 11-Feb 3 Plan 0.17% 0.17% 0.17%
0.50% actual 0.50%
Perbaikan Flexible joint exhaust Main Engine (PS & SB) 0.50% 100.00% finish 11-Feb 13-Feb 3 Plan 0.17% 0.17% 0.17%
0.50% actual 0.17% 0.17% 0.16%
Perbaikan ciylincer muffler (PS) 1.00% 100.00% finish 11-Feb 13-Feb 3 Plan 0.33% 0.33% 0.33%
1.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 0.33%
15 0.33%
16 17 18 19 20 0.34%
21 22
G Pekerjaan interior 3.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
G1 Penggantian tempat duduk salon room dan anjungan 2.00% 75.00% belum finish 1-Feb 4-Feb 4 Plan '21 '21 '21
0.50% '21
0.50% '21
0.50% '21
0.50% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
1.50% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1.50%
18 19 20 21 22
H Pekerjaan Cleaning & Others 2.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
H1 Chain Locker 3.00% 66.67% belum finish 1-Feb 2-Feb 2 Plan '21 '21 '21
1.50% '21
1.50% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
2.00% 1.50% actual 2 3 4 5 1.50%
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 0.50%
21 22
I Undocking 5.00% P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Undocking 5.00% 0.00% belum finish 15-Feb 16-Feb 2 Plan '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
2.50% '21
2.50% '21 '21 '21
0.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
J Pekerjaan After Docking 5.00% P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Last touch 2.50% 0.00% belum finish 16-Feb 18-Feb 3 Plan '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
0.83% '21
0.83% '21
0.83% '21
0.00% actual
Delivery 2.50% 0.00% belum finish 19-Feb 19-Feb 1 Plan 2.50%
0.00% actual
0.04166667
0.00% actual
Y24 Modifikasi jalur pembuangan di bawah wastafel 4.16% 0.00% belum finish 31-Jul 1-Aug 2 Plan 2.08% 2.08%
0.00% actual
Y25 Pemasangan flange pipa pembuangan air wastafel dapur (y strainer baru) 4.16% 0.00% belum finish 1-Aug 2-Aug 2 Plan 2.08%
0.00% actual
66.35%
Page 3 552511416.xls
No Description Qty Item Required date
Unit
1 cat 4 pcs
2 zinc anode 2 pcs
3 cutless bearing 2 pcs
4 ban daprah uk 10
5 rantai daprah 5/8
6 sackhle 5/8
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
Project No PR Status
No Tanggal
1
7
Plan
contact fit flange shaft ( kanan , 50 % ok )
balancing propeller kanan dan kiri
cleaning strainer mainline port and starboard
modifikasi strainer AE 1 pcs sebelah kiri
pemasangan valve bunker 1 pcs
pemasangan valve got 3 pcs
pemasangan pipa gear box kanan saja dan AE inlet port and starboard side
pemasangan quick closing valve 1 pcs
ach ( % ) plan awal estimasi plan revisi
problem identification remark
jumlah MP
Tanggal Nama pekerja List pekerjaan plan Actual
17 juni 2020 bambang fore peak tank fit up 7 3
17 juni 2020 wahyudi helper bambang fore peak tank fit up
17 juni 2020 ijai cutting and fitting fin stabilizer
17 juni 2020 dani cutting and fitting fin stabilizer
Remark
lembur sampai jam 22:00 ( hari pertama lembur )
lembur sampai jam 22:00 ( hari pertama lembur )
lembur sampai jam 22:00 ( hari pertama lembur )
lembur sampai jam 22:00 ( hari pertama lembur )
NO Hari ke - tanggal pekerjaan material preparation ( PAMI )
cutting
proses Plan Actual
fit up full welding inspecting Pimpro inspecting QC inspecting OS start finish start finish
Remarks Nama Manpower Subkon Remark
PIPING + OUTFITTING
NO tanggal pekerjaan
1 pipa pendingin ME
3 pipa pernapasan
5 pipa pernapasan
6
7
9
10
11
12
13
14
VALVE
NO tanggal pekerjaan
1
2
3
4
5
6
7
8
9
10
11
12
job desc
material preparation ( PAMI )
sub/internal cutting fit up
assy on
inspecting Pimpro inspecting QC inspecting OS start finish start finish
board
Remarks Nama Manpower Subkon
Remark