Plan Schedule TB. CAMAR 20

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 20

TB.

Jeneponto
PT. PELAYARAN PELANGI SINDU MULIA
OS Hartono 2-Jul 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Pimpro
Mukhlis Hidayat Daily '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
31-Dec 7/2/2021 7/3/2021 7/4/2021 7/5/2021 7/6/2021 7/7/2021 7/8/2021 7/9/2021 7/10/2021 7/11/2021 7/12/2021 7/13/2021 7/14/2021 7/15/2021 7/16/2021 7/17/2021 7/18/2021 7/19/2021 7/20/2021 7/21/2021 7/22/2021

'21

'21

'21

'21

'21
Jul
'21

Jul
'21

'21

Jul
'21
Jul
'21
Jul
'21

'21

'21

Jul
'21
Jul
'21
Jul
'21

'21

Jul

Jul
'21
Jul
'21
Jul
'21

'21
Jul

Jul

Jul

Jul

Jul

Jul

Jul

Jul

Jul
13

14

15

18

19

20

21
10

11

12

16

17

22
100.00%

9
ASSIGNED
WBS TASK DESCRIPTION
TO
Weight Prosentase START FINISH Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

1.1 kapal datang sampai delivery PAMI 100% 2-Jul 22-Jul 21 Plan
actual

RESUME PROJECT ( S curve , detail Project , Etc )


plan 7.73% average plan 1.44% 2.38% 5.13% 7.97% 6.80% 8.63% 7.38% 6.63% 5.51% 4.88% 2.38% 1.84% 1.97% 0.88% 1.63% 1.00% 2.50% 3.33% 0.83% 0.83% 2.50%
progress pekerjaan sesuai repair list awal Wednesday, October 27, 2021
46.37% cum Plan 1.44% 3.82% 8.96% 16.92% 23.72% 32.36% 39.74% 46.37% 51.88% 56.76% 59.15% 60.99% 62.96% 63.84% 65.47% 66.47% 68.97% 72.31% 73.14% 73.97% 76.47%
plan Actual
progress pekerjaan sesuai Aktual di Lapangan Wednesday, October 27, 2021
53.08% -38.65% deviasi Cum actual
Deviasi -1.44%

progress pekerjaan sesuai repair list awal progress pekerjaan pekerjaan tambahan
PLAN ACTUAL DEVIASI
110.00%
15
90.00%
70.00% 10
50.00% 5
30.00%
0
10.00% 1 2 3 4 5 6 7 8 9 10
-10.00% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A Before Docking PIC 5.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
'21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
A1 kapal sandar di jetty PAMI 1.25% 0.00% belum finish 22-Jan 30-Jan 9 Plan 0.14%
0.00% actual
A2 persiapan lahan PAMI 1.25% 0.00% belum finish 28-Jan 30-Jan 3 Plan 0.42%
0.00% actual
A3 start docking sampai duduk PAMI 1.50% 0.00% belum finish 1-Jul 2-Jul 2 Plan 0.75% 0.75%
0.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
B During Docking ( pelayanan umum ) 5.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
B1 pelayanan umum 2.00% 0.00% belum finish 30-Jan 13-Feb 15 Plan '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21 '21 '21 '21 '21 '21
docking report ( 4 rangkap ) 0.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
C Propulsion 25.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
C1 Ukur clearance poros baling-baling pintle terhadap bantalannya( in & out board) 1.00% 100.00% finish 2-Jul 3-Jul 2 Plan '21 '21
0.50% '21
0.50% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
1.00% actual 1.00%
C2 Lepas rudder blade, Rudder Stock, propeller & shaft Propeller 3.00% 166.67% belum finish 2-Jul 3-Jul 2 Plan 1.50% 1.50%
5.00% actual 2.50% 0.50% 1.00% 1.00%
C3 Cek Kelurusan shaft di meja bubut 2.00% 100.00% belum finish 3-Feb 4-Feb 2 Plan 1.00% 1.00%

C4 Repair shaft PS & SB 8.00% belum finish

C5 lepas & pasang cutless bearing 2.00% finish


2.00% actual 1.00% 1.00%
C6 Test Penetrant Shaft pada Cone dan Spi 1.00% 100.00% finish 4-Feb 5-Feb 2 Plan 0.50% 0.50%
1.00% actual 1.00%
C7 Penambahan bracket daun kemudi & tambah daging pintle 2.00% 0.00% belum finish 5-Feb 7-Feb 3 Plan 0.67% 0.67% 0.67%
2.00%
C8 Final check kelurusan shaft PS & SB 2.00% belum finish
actual 1.00% 1.00% 1.00% 1.00% 1.00%
C9 Penetrant Test 1.00% 100.00% finish 4-Feb 5-Feb 2 Plan 0.50% 0.50%
1.00% actual 1.00%
C10 Pasang rudder stock, rudder blade, propeller & shaft Propeller 3.00% 66.67% belum finish 7-Feb 8-Feb 2 Plan 1.50% 1.50%
2.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 2.00%
17 18 19 20 21 22
D Pekerjaan Sand Blast dan Coating 10.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Full Sand Blasting Hull 3.00% 0.00% belum finish 1-Feb 4-Feb 4 Plan '21 '21 '21
0.75% '21
0.75% '21
0.75% '21
0.75% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
0.00% actual
Full Sand Blasting Underwater 4.00% 25.00% belum finish 2-Feb 5-Feb 4 Plan 1.00% 1.00% 1.00% 1.00%
1.00% actual 0.50% 0.50%
full Sand Blasting External Bulwark 3.00% 0.00% belum finish 4-Feb 6-Feb 3 Plan 1.00% 1.00% 1.00%
0.00% actual
Coating Hull (3 Layers) 1.50% 0.00% belum finish 3-Feb 5-Feb 3 Plan 0.50% 0.50% 0.50%
0.00% actual
Coating Underwater (2 Layers) 1.50% 33.33% belum finish 4-Feb 6-Feb 3 Plan 0.50% 0.50% 0.50%
0.50% 0.25% actual 0.25% 0.25%
Coating External Bulwark (2 Layers) 1.50% 0.00% belum finish 6-Feb 7-Feb 2 Plan 0.75% 0.75%
0.00% actual
Coating chain anchor (2 ls) 1.50% 33.33% belum finish 8-Feb 11-Feb 4 Plan 0.38% 0.38% 0.38% 0.38%
0.50% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 0.50%
19 20 21 22
E Pekerjaan Steel Work 20.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Replatinig Bulwark (Top, penambahan Pipa, Cropping stanchion, Slanting) 5.00% 100.00% finish 2-Feb 6-Feb 5 Plan '21 '21 '21 '21
1.00% '21
1.00% '21
1.00% '21
1.00% '21
1.00% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21

Penggantian fender

Pembuatan dudukan towing hook

5.00% actual 2 3 4 5 6 2.00%


7 8 9 10 1.00%
11 2.00%
12 13 14 15 16 17 18 19 20 21 22
D Outfitting 10.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Roller Guard for Towing equipment (PS & SB) 1.00% 100.00% finish 4-Feb 6-Feb 3 Plan '21 '21 '21 '21 '21 '21
0.33% '21
0.33% '21
0.33% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
1.00% actual 0.66% 0.34%
Repair tangga gangway (PS & SB) dan tangga Haluan 1.00% 100.00% finish 5-Feb 8-Feb 4 Plan 0.25% 0.25% 0.25% 0.25%
1.00% actual 1.00%
Perbaikan Pintu steering gear room (PS & SB) 0.50% 100.00% finish 7-Feb 10-Feb 4 Plan 0.13% 0.13% 0.13% 0.13%
0.50% actual 0.25% 0.25%
Perbaikan pintu emergency exit engine room (Lock handle) 0.50% 100.00% finish 9-Feb 11-Feb 3 Plan 0.17% 0.17% 0.17%
0.50% actual 0.50%
Pembuatan drainase PS & SB 1.00% 100.00% finish 11-Feb 14-Feb 4 Plan 0.25% 0.25% 0.25% 0.25%
1.00% actual 0.50% 0.50%
Penggantian tanda selar 0.50% 100.00% finish 7-Feb 9-Feb 3 Plan 0.17% 0.17% 0.17%
0.50% actual 0.50%
Repair tannga bulwark 1.00% 100.00% finish 2-Feb 4-Feb 3 Plan 0.33% 0.33% 0.33%
1.00% actual 0.66% 0.34%
Penggantian zinc anode 1.00% 50.00% belum finish 9-Feb 10-Feb 2 Plan 0.50% 0.50%
0.50% actual 0.50%
Penggantian kupingan daprah 0.50% 100.00% finish 5-Feb 8-Feb 4 Plan 0.13% 0.13% 0.13% 0.13%

Page 1 552511416.xls
0.50% actual 0.50%
Penggantian ban daprah 1.50% 0.00% belum finish 13-Feb 14-Feb 2 Plan 0.75% 0.75%
0.00% actual

Page 2 552511416.xls
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
E Pekerjaan Mooring Equipments 5.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
E1 Pengukuran dan kalibrasi rantai jangkar 1.00% 0.00% belum finish 31-Jan 31-Jan 1 Plan '21 '21
1.00% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
mp and motor , electrical 0.00% actual
E2 Perawatan jangkar dan rantai jangkar 3.00% 0.00% belum finish 6-Feb 8-Feb 3 Plan 1.00% 1.00% 1.00%
mp and motor , electrical 0.00% actual
E3 Pembuatan cover lubang urloop 1.00% 100.00% finish 2-Feb 3-Feb 2 Plan 0.50% 0.50%
1.00% actual 2 3 4 0.50%
5 0.50%
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
F Pekerjaan Pipa, Valve, Pump, Vent head 5.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
F1 Penggantian pipa inlet mesin M/E 0.50% 50.00% belum finish 5-Feb 8-Feb 4 Plan '21 '21 '21 '21 '21 '21 '21
0.13% '21
0.13% '21
0.13% '21
0.13% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
0.25% actual 0.25%
F2 Perbaikan pipa filling, vent, sounding Tangki PS & SB 1.00% 100.00% finish 8-Feb 9-Feb 2 Plan 0.50% 0.50%
1.00% actual 0.50% 0.50%
Perbaikan pipa pendingin shaft PS & SB 0.50% 100.00% finish 2-Feb 3-Feb 2 Plan 0.25% 0.25%
0.50% actual 0.25% 0.25%
Penambahan rakor 0.25% 100.00% finish 7-Feb 9-Feb 3 Plan 0.08% 0.08% 0.08%
0.25% actual 0.12% 0.13%
Perbaikan pipa Wastafel 0.25% 100.00% finish 7-Feb 9-Feb 3 Plan 0.08% 0.08% 0.08%
0.25% actual 0.12% 0.13%
F3 Penggantian pipa inlet cooling ME dan hose pipe ME (PS & SB) 1.00% 100.00% finish 2-Feb 5-Feb 4 Plan 0.25% 0.25% 0.25% 0.25%
1.00% actual 0.25% 0.25% 0.25% 0.25%
Penggantian inlet dan outlet Cooling pipe (PS & SB) 1.00% 100.00% finish 3-Feb 6-Feb 4 Plan 0.25% 0.25% 0.25% 0.25%
1.00% actual 0.25% 0.25% 0.25% 0.25%
Perbaikan shaft cooling pipe (PS & SB) 0.25% 100.00% finish 5-Feb 7-Feb 3 Plan 0.08% 0.08% 0.08%
0.25% actual 0.25%
Perbaikan cooling pipe gear box (PS & SB) 1.00% 100.00% finish 6-Feb 8-Feb 3 Plan 0.33% 0.33% 0.33%
1.00% actual 1.00%
Service seachest box dan grating 0.75% 100.00% finish 10-Feb 11-Feb 2 Plan 0.38% 0.38%
0.75% actual 0.38% 0.37%
Service gate valve PS & SB (hidro test dan ganti packing) 0.75% 100.00% finish 1-Feb 3-Feb 3 Plan 0.25% 0.25% 0.25%
0.75% actual 0.37% 0.38%
Service sea strainer PS & SB (ganti packing) 0.25% 100.00% finish 3-Feb 5-Feb 3 Plan 0.08% 0.08% 0.08%
0.25% actual 0.25%
Service tank emergency valve (hidro test dan ganti packing) 0.25% 48.00% belum finish 5-Feb 7-Feb 3 Plan 0.08% 0.08% 0.08%
0.12% actual 0.12%
Service hand pump chain locker (ganti packing) 0.25% 100.00% finish 7-Feb 9-Feb 3 Plan 0.08% 0.08%
0.25% actual 0.12% 0.13%
Service strainer AE PS & SB 0.50% 100.00% finish 9-Feb 11-Feb 3 Plan 0.17% 0.17% 0.17%
0.50% actual 0.50%
Perbaikan Flexible joint exhaust Main Engine (PS & SB) 0.50% 100.00% finish 11-Feb 13-Feb 3 Plan 0.17% 0.17% 0.17%
0.50% actual 0.17% 0.17% 0.16%
Perbaikan ciylincer muffler (PS) 1.00% 100.00% finish 11-Feb 13-Feb 3 Plan 0.33% 0.33% 0.33%
1.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 0.33%
15 0.33%
16 17 18 19 20 0.34%
21 22
G Pekerjaan interior 3.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
G1 Penggantian tempat duduk salon room dan anjungan 2.00% 75.00% belum finish 1-Feb 4-Feb 4 Plan '21 '21 '21
0.50% '21
0.50% '21
0.50% '21
0.50% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
1.50% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1.50%
18 19 20 21 22
H Pekerjaan Cleaning & Others 2.00% remark START FINISH Days P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
H1 Chain Locker 3.00% 66.67% belum finish 1-Feb 2-Feb 2 Plan '21 '21 '21
1.50% '21
1.50% '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
2.00% 1.50% actual 2 3 4 5 1.50%
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 0.50%
21 22
I Undocking 5.00% P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Undocking 5.00% 0.00% belum finish 15-Feb 16-Feb 2 Plan '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
2.50% '21
2.50% '21 '21 '21
0.00% actual 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
J Pekerjaan After Docking 5.00% P/A Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul Jul
Last touch 2.50% 0.00% belum finish 16-Feb 18-Feb 3 Plan '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
0.83% '21
0.83% '21
0.83% '21
0.00% actual
Delivery 2.50% 0.00% belum finish 19-Feb 19-Feb 1 Plan 2.50%
0.00% actual

0.04166667

Additional Job from klass 100.00% 1


Jul 2
Jul 3
Jul 4
Jul 5
Jul 6
Jul 7
Jul 8
Jul 9
Jul 10
Jul 11
Jul 12
Jul 13
Jul 14
Jul 15
Jul 16
Jul
Y remark START FINISH Days '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21 '21
Y1 replating haluan 4.17% 100.00% finish 21-Jul 26-Jul 6 Plan 0.70% 0.70% 0.70% 0.70% 0.70% 0.70%
4.17% 21-Jul 26-Jul 6 actual 0.50% 0.50% 0.00% 1.00% 1.00% 1.17%
Y2 pemasangan push area di haluan dan pasang daprah besar 4.17% 14.39% belum finish 24-Jul 30-Jul 7 Plan 0.60% 0.60% 0.60% 0.60% 0.60% 0.60% 0.60%
0.60% actual 0.60%
Y4 penggantian sirip kemudi 4.17% 89.93% belum finish 21-Jul 26-Jul 6 Plan 0.70% 0.70% 0.70% 0.70% 0.70% 0.70%
3.75% 21-Jul 27-Oct 464.2507 actual 0.70% 0.70% 0.70% 0.70% 0.70% 0.00% 0.25%
Y5 penggantian pipa fender yang penyok 4.17% 19.90% belum finish 27-Jul 31-Jul 5 Plan 0.83% 0.83% 0.83% 0.83% 0.83%
0.83% 27-Jul 27-Oct 458.2507 actual 0.83%
Y6 Perbaikan pintu dan gawangan kamar mandi 4.17% 59.95% belum finish 25-Jul 31-Jul 7 Plan 0.60% 0.60% 0.60% 0.60% 0.60% 0.60% 0.60%
2.50% 24-Jul 27-Oct 461.2507 actual 1.00% 0.50% 0.50% 0.50%
Y7 Pembuatan & Pemasangan kursi kemudi (spt Brahma 15) 4.17% 43.17% belum finish 25-Jul 31-Jul 7 Plan 0.60% 0.60% 0.60% 0.60% 0.60% 0.60% 0.60%
1.80% 25-Jul 27-Oct 460.2507 actual 0.60% 0.60% 0.60%
Y8 Perbaikan sofa mess room 4.17% 43.17% belum finish 25-Jul 31-Jul 7 Plan 0.60% 0.60% 0.60% 0.60% 0.60% 0.60% 0.60%
1.80% 25-Jul 27-Oct 460.2507 actual 0.60% 0.60% 0.60%
Y9 Penggantian handle pintu bagian dalam (semua pintu) 4.17% 0.00% belum finish 25-Jul 31-Jul 7 Plan 0.60% 0.60% 0.60% 0.60% 0.60% 0.60% 0.60%
0.00% actual
Y10 Perbaikan penutup shore connection emergency 4.17% 0.00% belum finish 26-Jul 27-Jul 2 Plan 2.09% 2.09%
0.00% actual
Y11 Penggantian penutup soundingan BBM 1C 4.17% 0.00% belum finish 28-Jul 29-Jul 2 Plan 2.09% 2.09%
0.00% actual
Y12 Pemasangan penutup tanki airtawar ukuran 2 hid (2 pcs) 4.17% 0.00% belum finish 27-Jul 28-Jul 2 Plan 2.09% 2.09%
0.00% actual
Y13 Pemasangan dudukan smoke signal direling anjungan (kiri/kanan) 4.17% 0.00% belum finish 26-Jul 27-Jul 2 Plan 2.09% 2.09%
0.00% actual
Y14 Pemasangan kupingan tali jernuran ditengah panel cerobong (kiri/kanan} 4.17% 0.00% belum finish 26-Jul 27-Jul 2 Plan 2.09% 2.09%
0.00% actual
Y15 Niple jangkar,hook,handle pintu (70 pcs) (8 pcs kunci 14 dan 62 pcs·kunci 11) 4.17% 0.00% belum finish 26-Jul 27-Jul 2 Plan 2.09% 2.09%
0.00% actual
Y16 Penggantian kampas rem jangkar (kiri/kanan) 4.17% 0.00% belum finish 25-Jul 28-Jul 4 Plan 1.04% 1.04% 1.04% 1.04%
0.00% actual
Y17 Pembuatan Cover hidrolis dan motor hidrolis jangkar (di beri pintu) 4.17% 0.00% belum finish 30-Jul 3-Aug 5 Plan 0.83% 0.83% 0.83%
0.00% actual
Y18 Pergantian pipa dan hose hidrolikjangkar (1 set) 4.16% 0.00% belum finish 24-Jul 26-Jul 3 Plan 1.39% 1.39% 1.39%
0.00% actual
Y19 Pergantian switch control remote winch jangkar (4 Tombol) 4.16% 0.00% belum finish 2-Aug 4-Aug 3 Plan
0.00% actual
Y20 Penggantian lapisan penutup main hole daily tank fresh water cabin crew 4.16% 0.00% belum finish 1-Aug 2-Aug 2 Plan 2.08%
0.00% actual
Y21 Pembuatan lubang pembuangan air storage towing hook (kiri/kanan) 4.16% 0.00% belum finish 27-Jul 27-Jul 1 Plan 4.16%
0.00% actual
Y22 Penggantian roundbar bolard belakang sebelah kanan 4.16% 0.00% belum finish 26-Jul 27-Jul 2 Plan 2.08% 2.08%
0.00% actual
Y23 Penggantian ring manhole beserta bolt/nut stainless tanki BBM ic dengan stainless 4.16% 0.00% belum finish 29-Jul 31-Jul 3 Plan 1.39% 1.39% 1.39%

0.00% actual
Y24 Modifikasi jalur pembuangan di bawah wastafel 4.16% 0.00% belum finish 31-Jul 1-Aug 2 Plan 2.08% 2.08%
0.00% actual
Y25 Pemasangan flange pipa pembuangan air wastafel dapur (y strainer baru) 4.16% 0.00% belum finish 1-Aug 2-Aug 2 Plan 2.08%
0.00% actual
66.35%

Page 3 552511416.xls
No Description Qty Item Required date
Unit
1 cat 4 pcs
2 zinc anode 2 pcs
3 cutless bearing 2 pcs
4 ban daprah uk 10
5 rantai daprah 5/8
6 sackhle 5/8
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31

32
Project No PR Status
No Tanggal
1

7
Plan
contact fit flange shaft ( kanan , 50 % ok )
balancing propeller kanan dan kiri
cleaning strainer mainline port and starboard
modifikasi strainer AE 1 pcs sebelah kiri
pemasangan valve bunker 1 pcs
pemasangan valve got 3 pcs
pemasangan pipa gear box kanan saja dan AE inlet port and starboard side
pemasangan quick closing valve 1 pcs
ach ( % ) plan awal estimasi plan revisi
problem identification remark
jumlah MP
Tanggal Nama pekerja List pekerjaan plan Actual
17 juni 2020 bambang fore peak tank fit up 7 3
17 juni 2020 wahyudi helper bambang fore peak tank fit up
17 juni 2020 ijai cutting and fitting fin stabilizer
17 juni 2020 dani cutting and fitting fin stabilizer
Remark
lembur sampai jam 22:00 ( hari pertama lembur )
lembur sampai jam 22:00 ( hari pertama lembur )
lembur sampai jam 22:00 ( hari pertama lembur )
lembur sampai jam 22:00 ( hari pertama lembur )
NO Hari ke - tanggal pekerjaan material preparation ( PAMI )
cutting
proses Plan Actual
fit up full welding inspecting Pimpro inspecting QC inspecting OS start finish start finish
Remarks Nama Manpower Subkon Remark
PIPING + OUTFITTING

NO tanggal pekerjaan
1 pipa pendingin ME
3 pipa pernapasan
5 pipa pernapasan
6
7
9
10
11
12
13
14

VALVE

NO tanggal pekerjaan

1
2
3
4
5
6
7
8
9
10
11
12
job desc
material preparation ( PAMI )
sub/internal cutting fit up

material preparation ( PAMI ) dismant


assy
le
proses Plan Actual
full welding inspecting Pimpro inspecting QC inspecting OS start finish start finish

Process Plan Actual

assy on
inspecting Pimpro inspecting QC inspecting OS start finish start finish
board
Remarks Nama Manpower Subkon

Remarks Nama Manpower Subkon


Remark

Remark