A Report On A Deteriorated Building: Group 1
A Report On A Deteriorated Building: Group 1
GROUP 1
1. KUSORO DANIEL O. N/BT/19/3244
2. IDOWU OPEYEMI E. N/BT/19/3247
3. ONI NIMOTALAHI A. N/BT/19/3255
4. TIJANI MUSTAPHA O. N/BT/19/3269
5. ODESESAN GBEMILEKE O. N/BT/19/3246
6. AKINTUNDE STEPHEN A. N/BT/19/3252
7. ODUNIYI TENIOLA O. N/BT/19/3298
8. OLOWOYO TOLUWANI T. N/BT/19/3267
9. ALOWOLODU SHAMSUDEEN O. N/BT/19/3303
10. ADEGBE QUAREEB O. N/BT/19/3268
11. ADEBESIN OLAWALE O. N/BT/19/3292
12. MUSTAPHA YUSUF O. N/BT/19/3295
BUILDING TECHNOLOGY
SCHOOL OF ENVIRONMENTAL STUDIES
THE FEDERAL POLYTECHNIC, ILARO
OGUN STATE
BLDR. ADENAIYA
INTRODUCTION
Building Maintenance
Building Maintenance Technology essentially deals with the study of the occurrence of building
defects and the remedies which such defects would require. The maintenance of the built
environment affects everyone continually, for it is on the state of our homes, offices and
factories that we depend not only for our comfort, but for our economic survival. Maintenance
starts the day the Builder leaves the site. Design, materials, workmanship, function, use and
their interrelationship, will determine the amount of maintenance required during the lifetime of
the building. Effective building maintenance requires the correct diagnosis of defects, and
implementation of the correct remedial measures, all based on sound technical knowledge. It is
highly desirable but hardly feasible to produce buildings that are maintenance free, although
much can be done at design stage to reduce the amount of subsequent maintenance work.
BS3811 defines maintenance as work undertaken in order to keep or restore every facility i.e.
every part of the site, building and contents to an acceptable standard. It went further to define it
as the combination of all technical and associated administrative actions intended to retain an
item in, or restore it to, a state in which it can perform its required function.
The aim of this investigation was to evaluate and identify the building defect on the selected
case study building and also to study the methods of minimizing the construction defects in
construction project. In order to achieve the aim of this research, the objectives were as listed
below;
1. To identify the type of building defects that occurred in the selected building.
2. To access the causes and effect of the building defect on the selected building.
A residential building of six rooms which is located at 26, Olorunsogo, Sabo, Ilaro, Ogun State.
The building was built over the years with the approved plan date 29 th, July, 1996, owned by a
retired Nigerian army officer in the person of Mr. Lamidi Yusuf. The building was said to be
constructed with blocks fabricated manually producing 36 blocks per cement bag as stipulated
in BS regulation body. The room consists of six rooms of dimension 3600mm x 3000mm per
room. The height of the building from normal ground level is exceeded 3m, this emanate due to
sloppy condition of the land before the erection of the building. At the front view of the
building, there is a provision of five steps stair case to gain entrance with ease into the terrace of
the building. The building was provided with two external doors (front and back) as the main
entrance to the passage whereby other doors are accessed made of timber.
BUILDING PLAN
DEFECT OF THE BUILDING
1. FOUNDATION DEFECT
The foundation of the building is the hope of the building which all loads of the building
returned back too. Defects of the foundation can leads to crack in the floor and walls etc
Causes
Soil erosion due to improper drainage: Inadequate drainage around the building leads
to over saturation of the soil and it expose the beneath of the foundation.
Remedy
2. DAMPNESS
Dampness can be a genuine matter, especially to structures situated close to water sources. It
breaks down building structures as well as harms to decorations. The primary driver of
clamminess is water been depicted on the building. Water infiltration happens usually through
dividers presented to winning wet, wind or rain. With the presence of gravity rainfall, water can
escape into the walls of the building which can reduce the life structure of the building. In most
cases, dampness can occur through the toilet drainage when it is water sealed. Water can also
escape into the building through the foundation when there is absent of DPC (Damp Proof
Cause) and DPM (Damp proof Membrane). The action of moisture on the different portion of
the structure in this decay and disintegration of materials stone, steel, timber etc as the
Rain penetration: This is the most highly natural occurrence cause of dampness on
building which emanate due to exposure of the building to heavy rainfall. Similarly the
leaking roof also contributes to this cause. Dampness cannot be fully eradicated but can
Remedy
The recommended solution to rain penetration are grunting and pressure grouting, the
former refers to the process of spraying a layer of concrete mixtures, making it water
proof while the later is the process of applying a mixture of cements and sand with a jet
Rising of moisture from the ground: The sub soil moisture, present below the ground
level rises through the foundation beds due to capillary action. Creating a down-proof
barrier by introducing DPC, this is one of the most important elements of the structure.
The DPC protect structures against moisture rising from the ground to repel water from
the ground.
Roof leakage: In the case of flat roof, inadequate roof slopes, improper rain water pipe
connection and defective junction between roof slab and parapet wall contributed to the
building dampness.
Remedy
Check for missing or cracked tiles and also were the roof met the wall of a chimney, also
could potentially damage the fabric of the building if allowed to continue. In addition, if
mould starts to grow, this can even affects the health of the occupant.
Remedy
Consider adding more ventilation to the building is the solution to this cause.
3. CRACKING OF WALLS
Cracks are signs of structural movement during and after construction, it is a universal problem
encountered all over the world. Building components develop cracks whenever stress in the
components exceeds its strength. Stress in the building components could be cause by externally
applied forces such as dead, live, wind, foundation settlement, and chemical action. Crack affect
the buildings artistic look and it destroy the word integrity, affect the safety of the structure and
even reduces the durability of the structure. The cracks on this building were based on structural
Faulty design: This is a deficiency or error in the design structure, which leads to
building defect stated above. In view of the architectural plan released, there was no
provision for adequate structural elements such as pillars, beams, columns etc, which is
Remedy
Introduction of beams across the openings of the building, pillars to the edges of the
building, which will be casted in situ in order to support the strength of the building.
Remedy
Cracking due to vegetation: Existence of vegetation may be the cause of crack of walls
due to expansive action of roots growing under the foundation or in brick masonry. The
soil under the foundation of the building is shrinkage clay which can also be the cause
of the cracks.
Remedy
Other than being one of the principle structures in a building, roof top may go about as a climate
shield, offering assurance to clients to tenants from rain and sun. The roof of the building is in
bad condition due to the age of the building and the type of the roofing sheet. There is
possibility of water entering into the building through the opened part of the roof.
Causes and remedy of room defect
Types of the building roof: The roof is the main shield for the building and the tenants.
The roof is the most exposed part of the building providing protection against rain,
snow, sunlight, extreme temperature and wind. The said building was roofed with pan or
metal, which does not possess high resistance to withstand weather and climate
Remedy
The old sheet to be removed and replace with modern sheet e.g aluminum or jerad.
Weak fascia board: The building fascia boards were not in a good condition in terms of
the exposure to weather climates and termites, which decrease shorten the life span of
the woods.
Remedy
The fascia board needs to be replaced and also applying anti-termites solution on the
5. WINDOW/DOOR DEFECT
Window is part of the building or an opening in the wall of the building fitted with timber for
daytime illumination and also serves as passage for fresh air into the rooms while the door gives
Decay of timber: The window of the building which were erected at the external part of
the building with the height of 900mm from the ground are exposed to weather and
climate e,g rain, sun and moreover, the timber was affected by termites which also
Remedy
Fumigation of the window with anti-termites solution and also replacement of the
6. RENDERING DEFECT
Rendering of the external wall of the building serves as the finishes for the wall which is
applied in layers with the mixture of sand, cement and water for the capability of achieving a
smooth surface.
Causes and remedy of rendering defect
Plaster De-bonding: separation of plaster from the building wall was caused by
excessive thickness of the plaster layer, inadequate substrate preparation or may be due
Remedy
- Remove dust and oil from the surface of the wall before applying another plaster.
Electricity in construction means the installation of lightings and power sockets for illumination
and to control electrical devices. It is a network of conductors and equipment designed to carry,
Insecure wiring: The connection of the service wire from the pole to the main building
was highly terrible, it was observed that the service wire was sagging and requires urgent
attention.
Remedy
Disconnect the wire from the pole and re-connect to the standard height.
Bad Illumination: On the cause of inspection, the building was obvious to possess little
or no illumination.
Remedy
The defective lighting fittings and bulbs needs to be replaced for better illumination.
CONCLUSION
In conclusion, it can be deduced that the highlighted deformity of the said building was as a
result of poor supervision during construction, lack of building expatriate, inferior materials and
RECOMMENDATION
On the