Commissioning Services Department Commissioning Manual Factory Type and Routine Tests
Commissioning Services Department Commissioning Manual Factory Type and Routine Tests
COMMISSIONING MANUAL
FACTORY TYPE AND ROUTINE TESTS
Section B - Page 1 of 19
INTRODUCTION:
Purpose of this document is to verify that the factory tests being performed by the
manufacturers on the contractual electrical equipment are in line with latest IEC standards read
with SEC specifications. It is also a guideline for SEC inspectors to check and approve the factory
procedures submitted prior to the tests executions. Factory Inspection is carried out to ensure that
various equipments ordered are manufactured/assembled with good engineering work meeting
contract specifications and design and all related tests prior to shipment are performed.
It is full responsibility of manufacturer to deliver zero defect equipment. This also needs to be
supported by all documentation which includes ‘Factory Test Records’.
SEC exercises right to do factory inspection & witness the tests and ask to fulfill deficiencies
pointed out prior to shipment of equipments. This inspection may be by SEC engineers or their
appointed Consultants/Inspecting agency.
PURPOSE:
The purpose of this section is to specify the guidelines for witnessing of factory routine, special
and type tests on the new equipments used in Saudi Electricity Company transmission network.
NOTE:
1 TEST GUIDELINES
REFERENCE
EQUIPMENT TEST CHECKS, TEST LEVELS AND STANDARD AND
NO
DESCRIPTION ACCEPTANCE CRITERIAS REMARKS
IEC 60076-1
IEC 60076-2
1.0 POWER TRANSFORMERS IEC 60076-3
IEC 60076-4
IEC 60076-5
1.1 ROUTINE TESTS
Quality of paint and welding, serial
Visual inspection and no, hight, width, wheels, name plate
1.1.1
dimensional checks. data, fans radiators, valves open
close positions, etc.
Measurements by 5kv megger
between phase-ground and phase-
phase with guard used.
Measurement of insulation
PI = insulation resistance (IR) at ten
resistance (IR) and
1.1.2 minutes value / one minute value.PI
polarization index (PI) tests.
should be greater than 1.1and IR at
10 minutes value not less than 1000
mega ohms at room temperature.
1.1.19 Core ad clamp megger test by IR value shall be more than 10 mega
2kv megger. ohms.
33/8.8 KV Power Transformers
Test voltage for 8.8kv winding at
1.1.20 Separate source voltage
38kv for one minute.
withstand test.
Test voltage for 33kv windings at
75kv for one minute.
ACSD test performed by balanced
Short duration ac withstand three phase injection on LV side and
voltage test (ACSD) as per voltage raised, and not exceed
1.1.21 clause 7.2.1- IEC-60076-3- double the phase-phase voltage on
(2000) to the uniformly line (66kv for 33kv windings and
insulated HV windings 27.5kv for 8.8kv windings). No pd
measurements required normally.
1.1.22 Capacitance and power factor Pf < 0.5%
test on windings and bushings.
COMMISSIONING SERVICES DEPARTMENT
COMMISSIONING MANUAL
FACTORY TYPE AND ROUTINE TESTS
Section B - Page 5 of 19
132-115-110/33KV/8.8 KV Power
Transformer
Test sequence (um = 145kv)
raise from zero to
1.1um/√3=92kv for 5 minutes
u2 = 1.5um/√3= 125kv 5 minutes
u1=1.75um/√3=253kv 5 sec
u2 = 1.5um/√3= 125kv 60minutes
pd at 1.1um/√3 (92kv-5minutes) <
500pc
COMMISSIONING SERVICES DEPARTMENT
COMMISSIONING MANUAL
FACTORY TYPE AND ROUTINE TESTS
Section B - Page 6 of 19
132-115-110/33KV/8.8 KV Power
Transformer
Test sequence (um = 420kv)
Long duration induced ac raise from zero to
voltage test (ACLD) with partial 1.1um/√3=266kv for 5 minutes
discharge measurements as per u2 = 1.5um/√3= 364kv 5 minutes
IEC-60076-3 (2000) clause 7.4. u1=1.75um/√3=420kv 36 sec
measure pd level at u2 = 1.5um/√3=
364kv- 5minutes,
1.1um/√3 =266kv-5minutes
lower voltage and switch off
Measurement of harmonics on
1.3.4 the no load current.
Measurement of cooling
1.3.6 equipment power consumption.
2.0
COMMISSIONING SERVICES DEPARTMENT
COMMISSIONING MANUAL
FACTORY TYPE AND ROUTINE TESTS
Section B - Page 7 of 19
IEC-60840
3.0 132KV XLPE POWER CABLES 1999
3.1
ROUTINE TESTS
3.1.1 Partial discharge test 1.5uo with Pd less than 10 pc
prestress voltage 1.75uo-10sec
3.1.2 Power frequency voltage test at Test level = 190kv ac
tests voltage 2.5uo-30 mints
3.1.3 25 kv dc withstand test on sheath No break down
insulation
3.3
COMMISSIONING SERVICES DEPARTMENT
COMMISSIONING MANUAL
FACTORY TYPE AND ROUTINE TESTS
Section B - Page 10 of 19
TYPE TESTS
Dielectric loss
4.1.1 angle/temperature test
(Clause 17 IEC 141-1 ).
4.1.2 Dielectric security test(clause
18 IEC 141-1).
4.1.3 Lightening impulse voltage test
(clause 19 IEC 141-1)
4.1.4 Ac voltage test after impulse
test.
4.2
ROUTINE TEST ON CABLES
4.2.1 Conductor resistance test.
4.2.2 Capacitance test.
4.2.3 Dielectric loss angle test.
IEC 51-2
IEC 517
5.0 132KV & 380KV GAS INSULATED SWITCHGEARS (GIS) IEC 694
Type tests
5.2 As per clause 6.1 to 6.109 of
IEC 517.
5.2.3 Power frequency high voltage Power frequency withstand test for
test with pd measurements. 380 kv = 550kv ac ad for 132kv =
275kvac one minute.
Short circuit making and
5.2.4 breaking tests for circuit
breakers.
COMMISSIONING SERVICES DEPARTMENT
COMMISSIONING MANUAL
FACTORY TYPE AND ROUTINE TESTS
Section B - Page 13 of 19
5.2.7
AC POWER FREQUENCY VOLTAGE WITHSTAND LEVELS
5.2.8
5.2.9
REQUIREMENTS OF NEW SF6 GAS
SF6 which is delivered in cylinders in liquid phase, contains impurities with in the limits imposed by IEC
376 as under.
IMPURITIES MAX LIMIT
Carbon Tetra fluoride (Cf4) 0.03%
Oxygen + Nitrogen (Air) 0.03%
Water 15ppmM
Carbon dioxide (Co2) TRACES
HF 0.3ppmM
SF6 should be 99.9% pure
IEC-186
COMMISSIONING SERVICES DEPARTMENT
COMMISSIONING MANUAL
FACTORY TYPE AND ROUTINE TESTS
Section B - Page 16 of 19
6.2
TYPE TESTS
6.2.1 Temperature rise test
6.2.2 Ferro-resonance tests
6.2.3 Transient response test
6.2.4 Tests for accuracy
SPECIAL TESTS
6.3 SEC-SPECIAL
REQUIREMENTS
6.3.1 Windings resistance
6.3.2 Megger test
Vt primary isolation
6.3.3
device operational tests
Verification of primary
isolation gap to withstand
6.3.4 rated power frequency high
voltage withstands tests.
7.0
132KV & 380KV CAPACITOR VOLTAGE TRANSFORMERS IEC-186
COMMISSIONING SERVICES DEPARTMENT
COMMISSIONING MANUAL
FACTORY TYPE AND ROUTINE TESTS
Section B - Page 17 of 19
IEC 44-4
7.2
TYPE TESTS
7.2.1 Temperature rise test
7.2.2 Ferro-resonance tests
7.2.3 Transient response test
7.2.4 Tests for accuracy
9.0 OIL/SF6 TRANSFORMER AND OIL IMPREGNATED PAPER HIGH IEC 137
VOLTAGE BUSHINGS
9.1 TIGHTNESS TEST