P&ID - Chemical Processes
P&ID - Chemical Processes
P&ID - Chemical Processes
S E C T I O N
1
Conceptualization
and Analysis of
Chemical Processes
The first section of this book consists of Chapters 1–4. Chapter 1 covers the im-
portant diagrams that are routinely used by chemical engineers to help design
and understand chemical processes. The book commences with this section and
chapter because nearly all the technical information that is presented in the re-
mainder of the book is, in some way, related to the three principal diagrams that
are presented in Chapter 1. These three diagrams are the block flow diagram
(BFD), process flow diagram (PFD), and the piping and instrument diagram
(P&ID). In addition, the three-dimensional representation of a process is intro-
duced, and some of the basic issues regarding equipment location are addressed.
In Chapter 2 the evolutionary process of design is investigated. The input-
output structure of a process is presented, and the basic building blocks that are
common to all processes are introduced. The different recycle structures of
processes are illustrated, and the rationale for adding inert material to the feed is
also explained.
In Chapter 3, methods for tracing chemical species through a process flow di-
agram are given. By following the paths of feed chemicals and reactants, it is pos-
sible to obtain a much clearer picture of what is happening in an existing process.
Finally, in Chapter 4, the conditions at which different equipment operate
are discussed and explained. The concept of conditions of special concern is ex-
plained, and examples of such conditions are identified and explained in the con-
text of the toluene hydrodealkylation process.
9
ch01.qxd 9/11/2002 11:40 AM Page 10
C H A P T E R
1
Diagrams
for Understanding
Chemical Processes
The chemical process industry (CPI) is involved in the production of a wide vari-
ety of products that improve the quality of our lives and generate income for the
companies and their stockholders. In general, chemical processes are complex,
and chemical engineers in industry encounter a variety of chemical process flow
diagrams. These processes often involve substances of high chemical reactivity,
high toxicity, and high corrosivity operating at high pressures and temperatures.
These characteristics can lead to a variety of potentially serious consequences, in-
cluding explosions, environmental damage, and threats to people’s health. It is
essential that errors or omissions resulting from missed communication between
persons and/or groups involved in the design and operation do not occur when
dealing with chemical processes. Visual information is the clearest way to present
material and is least likely to be misinterpreted. For these reasons, it is essential
that chemical engineers be able to formulate appropriate process diagrams and
be skilled in analyzing and interpreting diagrams prepared by others.
This chapter presents and discusses the more common flow diagrams en-
countered in the chemical process industry. These diagrams evolve from the time
a process is conceived in the laboratory through the design, construction, and the
many years of plant operation. The most important of these diagrams are de-
scribed and discussed in this chapter.
11
ch01.qxd 9/11/2002 11:40 AM Page 12
The research and development group at ABC Chemicals Company worked out a way
to produce alpha-beta souptol (ABS). Process engineers assigned to work with the de-
velopment group have pieced together a continuous process for making ABS in com-
mercial quantities and have tested key parts of it. This work involved hundreds of
block flow diagrams, some more complex than others. Based on information de-
rived from these block flow diagrams, a decision was made to proceed with
this process.
A process engineering team from ABC’s central office carries out the detailed
process calculations, material and energy balances, equipment sizing, etc. Working
with their drafting department, they produced a series of PFDs (Process Flow Dia-
grams) for the process. As problems arise and are solved, the team may revise and re-
draw the PFDs. Often the work requires several rounds of drawing, checking, and
revising.
Specialists in distillation, process control, kinetics, and heat transfer are
brought in to help the process team in key areas. Some are company employees and
others are consultants.
Since ABC is only a moderate-sized company, it does not have sufficient staff to
prepare the 120 P&IDs (Piping and Instrumentation Diagrams) needed for the
new ABS plant. ABC hires a well-known engineering and construction firm (E&C
Company), DEFCo, to do this work for them. The company assigns two of the ABC
process teams to work at DEFCo to coordinate the job. DEFCo’s process engineers,
specialists, and drafting department prepare the P&IDs. They do much of the detailed
engineering (pipe sizes, valve specifications, etc.) as well as the actual drawing. The
job may take two to six months. Every drawing is reviewed by DEFCo’s project team
and by ABC’s team. If there are disagreements, the engineers and specialists from the
companies must resolve them.
Finally, all the PFDs and the P&IDs are completed and approved. ABC can
now go ahead with the construction. They may extend their contract with DEFCo to
include this phase, or they may go out for construction bids from a number of sources.
associated with designing and building the plant. During this operating period,
many unforeseen changes are likely to take place. The quality of the raw materials
used by the plant may change, product specifications may be raised, production
rates may need to be increased, the equipment performance will decrease because
of wear, the development of new and better catalysts will occur, the costs of utili-
ties will change, new environmental regulations may be introduced, or improved
equipment may appear on the market.
As a result of these unplanned changes, plant operations must be modified.
Although the operating information on the original process diagrams remains in-
formative, the actual performance taken from the operating plant will be differ-
ent. The current operating conditions will appear on updated versions of the
various process diagrams, which will act as a primary basis for understanding
the changes taking place in the plant. These process diagrams are essential to an
engineer who has been asked to diagnose operating problems, to solve problems
in operations, to debottleneck systems for increased capacity, and to predict the
effects of making changes in operating conditions. All these activities are essen-
tial in order to maintain profitable plant operation.
In this chapter, we concentrate on three diagrams that are important to
chemical engineers: block flow, process flow, and piping and instrumentation
diagrams. Of these three diagrams, we will find that the most useful to chemical
engineers is the PFD. The understanding of the PFD represents a central goal of
this textbook.
The block flow diagram is introduced early in the education of chemical engi-
neers. In the first courses in material and energy balances, often the initial step
was to convert a word problem into a simple visual block flow diagram. This dia-
gram was a series of blocks connected with input and output flow streams. It
included operating conditions (temperature and pressure) and other important
information such as conversion and recovery, given in the problem statement. It
did not provide details regarding what was involved within the blocks, but con-
centrated on the main flow of streams through the process.
The block flow diagram can take one of two forms. First, a block flow dia-
gram may be drawn for a single process. Alternatively, a block flow diagram may
be drawn for a complete chemical complex involving many different chemical
processes. We differentiate between these two types of diagram by calling the
first a block flow process diagram and the second a block flow plant diagram.
Mixed Gas
(2,610 kg/h)
Toluene
(10,000 kg/h) Reactor Gas
Separator
Benzene
(8,210 kg/h)
Hydrogen
(820 kg/h) Conversion Mixed Liquids
75% Toluene Still
Toluene
Reaction : C 7 H8 + H 2 → C 6 H6 + C H4
Figure 1.1 Block Flow Process Diagram for the Production of Benzene
Toluene and hydrogen are converted in a reactor to produce benzene and methane. The
reaction does not go to completion, and excess toluene is required. The noncondensable
gases are separated and discharged. The benzene product and the unreacted toluene are
then separated by distillation. The toluene is then recycled back to the reactor and the
benzene removed in the product stream.
This block flow diagram gives a clear overview of the production of ben-
zene, unobstructed by the many details related to the process. Each block in the
diagram represents a process function and may, in reality, consist of several
pieces of equipment. The general format and conventions used in preparing
block flow process diagrams are presented in Table 1.1.
Although much information is missing from Figure 1.1, it is clear that such a
diagram is very useful for “getting a feel” for the process. Block flow process dia-
grams often form the starting point for developing a PFD. They are also very
helpful in conceptualizing new processes and explaining the main features of the
process without getting bogged down in the details.
Table 1.1 Conventions and Format Recommended for Laying Out a Block Flow
Process Diagram
1. Operations shown by blocks
2. Major flow lines shown with arrows giving direction of flow
3. Flow goes from left to right whenever possible
4. Light stream (gases) toward top with heavy stream (liquids and solids) toward
bottom
5. Critical information unique to process supplied
6. If lines cross, then the horizontal line is continuous and the vertical line is broken.
(hierarchy for all drawings in this book)
7. Simplified material balance provided
gram represents a complete chemical process (compressors and turbines are also
shown as trapezoids), and we could, if we wished, draw a block flow process dia-
gram for each block in Figure 1.2. The advantage of a diagram such as Figure 1.2
is that it allows us to get a complete picture of what this plant does and how all
the different processes interact. On the other hand, in order to keep the diagram
relatively uncluttered, only limited information is available about each process
unit. The conventions for drawing block flow plant diagrams are essentially the
same as given in Table 1.1.
Both types of block flow diagrams are useful for explaining the overall op-
eration of chemical plants. For example, consider that you have just joined a large
chemical manufacturing company that produces a wide range of chemical prod-
ucts from the site to which you have been assigned. You would most likely be
given a block flow plant diagram to orient you to the products and important areas
of operation. Once assigned to one of these areas, you would again likely be pro-
vided with a block flow process diagram describing the operations in your particular
area.
In addition to the orientation function described earlier, block flow dia-
grams are used to sketch out and screen potential process alternatives. Thus, they
are used to convey information necessary to make early comparisons and elimi-
nate competing alternatives without having to make detailed and costly com-
parisons.
16
water vent to
48 47
50 atmosphere
9/11/2002
air 41 42 45
COS Claus Beavon
39 hydrolysis plant plant water to sws
67 54
46 51 sulfur
25 38 23
11:40 AM
18
Sour Gas Rectisol 4 alcohol alcohol
mixed alcohols
Shift 22 synthesis separation
59 ww
63
17A water hydrocarbon
19 27 separation
20 8A 56B 56A
methanol 5 co2 57
make up 56
removal
purge
co2 purge
water 67
bfw
71 bfw 73
11 70 65
10 13
coal 75
coal Texaco syn. gas syn gas
limestone gas turbine
preparation Gasifier heat recov combust’n exhaust gases
12 water
2 33
2 8 37 slag product
34 9 74
water make-up water 68 76
slag
purge steam to sc
handling 36 steam
1 3 4 6 turbine nitrogen
air
1 cryogenic argon
1A
O2 plant
water
28 + CO2
Figure 1.2 Block Flow Plant Diagram of a Coal to Higher Alcohol Fuels Process
ch01.qxd 9/11/2002 11:40 AM Page 17
information than the PFD for the same process from another company. Having
made this point, it is fair to say that most PFDs convey very similar information.
A typical commercial PFD will contain the following information:
1. All the major pieces of equipment in the process will be represented on the
diagram along with a description of the equipment. Each piece of equip-
ment will have assigned a unique equipment number and a descriptive
name.
2. All process flow streams will be shown and identified by a number. A de-
scription of the process conditions and chemical composition of each stream
will be included. These data will be displayed either directly on the PFD or
included in an accompanying flow summary table.
3. All utility streams supplied to major equipment that provides a process
function will be shown.
4. Basic control loops, illustrating the control strategy used to operate the
process during normal operations, will be shown.
It is clear that the PFD is a complex diagram that requires a substantial ef-
fort to prepare. It is essential that to avoid errors in presentation and interpreta-
tion it should remain uncluttered and be easy to follow. Often PFDs are drawn on
large sheets of paper (Size D: 24” × 36”), and several connected sheets may be re-
quired for a complex process. Because of the page size limitations associated with
this text, complete PFDs cannot be presented here. Consequently, certain liberties
have been taken in the presentation of the PFDs in this text. Specifically, certain
information will be presented in accompanying tables and only the essential
process information will be included on the PFD. The resulting PFDs will retain
clarity of presentation, but the reader must refer to the flow summary and equip-
ment summary tables in order to extract all the required information about the
process.
Before we discuss the various aspects of the PFD, it should be noted that the
PFD and the process that we describe in this chapter will be used throughout the
book. The process is the hydrodealkylation of toluene to produce benzene. This is
a well-studied and well-understood commercial process that is still used today.
The PFD that we present in this chapter for this process is technically feasible but
is in no way optimized. In fact, there are many improvements to the process tech-
nology and economic performance that can be made. Many of these improve-
ments will become evident when the appropriate material is presented. This al-
lows the techniques provided throughout this text to be applied to identify both
technical and economic problems in the process and to make the necessary
process improvements. Therefore, as we proceed through the text, we will iden-
tify weak spots in the design, make improvements, and move toward an opti-
mized process flow diagram.
ch01.qxd 9/11/2002 11:40 AM Page 18
The basic information provided by a PFD can be categorized into one of the
following:
1. Process topology
2. Stream information
3. Equipment information
We will look at each aspect of the PFD separately. After we have addressed
each of the three topics, we will bring all the information together and present the
PFD for the benzene process.
E-101 E-102 V-102 V-103 E-103 E-106 T-101 E-104 V-104 P-102A/B E-105
9/11/2002
fuel gas
16
cw
E-101 combustion
Page 19
7 lps
V-102
P-102A/B
Hydrogen P-101A/B fuel cw
air 9 E-105
3 gas
R-101 cw 15
H-101 18
mps benzene
5
E-102
E-106
11
V-103
Figure 1.3 Skeleton Process Flow Diagram (PFD) for the Production of Benzene via the Hydrodealkylation of Toluene
19
ch01.qxd 9/11/2002 11:40 AM Page 20
HEAT EXCHANGERS
TOWERS
FIRED HEATER
VESSELS
STORAGE TANKS
REACTORS
The 100 area designation will be used for the benzene process throughout
this text. Other processes presented in the text will carry other area designations.
Along the top of the PFD, each piece of process equipment is assigned a descrip-
tive name. From Figure 1.3 it can be seen that Pump P-101 is called the “toluene
feed pump.” This name will be commonly used in discussions about the process
and is synonymous with P-101.
During the life of the plant, many modifications will be made to the process;
often it will be necessary to replace or eliminate process equipment. When a piece
of equipment wears out and is replaced by a new unit that provides essentially
the same process function as the old unit, then it is not uncommon for the new
piece of equipment to inherit the old equipment’s name and number (often an ad-
ditional letter suffix will be used, e.g., H-101 might become H-101A). On the other
hand, if a significant process modification takes place, then it is usual to use new
equipment numbers and names. The following example, taken from Figure 1.3, il-
lustrates this concept.
ch01.qxd 9/11/2002 11:40 AM Page 21
Example 1.1
Operators report frequent problems with E-102, which are to be investigated. The PFD for
the plant’s 100 area is reviewed, and E-102 is identified as the “Reactor Effluent Cooler.”
The process stream entering the cooler is a mixture of condensable and non-condensable
gases at 654°C that are partially condensed to form a two-phase mixture. The coolant is
water at 30°C. These conditions characterize a complex heat transfer problem. In addition,
operators have noticed that the pressure drop across E-102 fluctuates wildly at certain
times, making control of the process difficult. Because of the frequent problems with this
exchanger, it is recommended that E-102 be replaced by two separate heat exchangers. The
first exchanger cools the effluent gas and generates steam needed in the plant. The second
exchanger uses cooling water to reach the desired exit temperature of 38°C. These ex-
changers are to be designated as E-107 (reactor effluent boiler) and E-108 (reactor effluent
condenser).
The E-102 designation is retired and not reassigned to the new equipment. There
can be no mistake that E-107 and E-108 are new units in this process and that
E-102 no longer exists.
Referring back to Figure 1.3, it can be seen that each of the process streams
is identified by a number in a diamond box located on the stream. The direction
of the stream is identified by one or more arrowheads. The process stream num-
bers are used to identify streams on the PFD, and the type of information that is
typically given for each stream is discussed in the next section.
ch01.qxd 9/11/2002 11:40 AM Page 22
Also identified in Figure 1.3 are utility streams. Utilities are needed services
that are available at the plant. Chemical plants are provided with a range of cen-
tral utilities that include electricity, compressed air, cooling water, refrigerated
water, steam, condensate return, inert gas for blanketing, chemical sewer, waste
water treatment, and flares. A list of the common services is given in Table 1.3,
which also provides a guide for the identification of process streams.
Each utility is identified by the initials provided in Table 1.3. As an example,
let us locate E-102 in Figure 1.3. The notation, cw, associated with the nonprocess
stream flowing into E-102 indicates that cooling water is used as a coolant.
Electricity used to power motors and generators is an additional utility that
is not identified directly on the PFD or in Table 1.3 but is treated separately. Most
of the utilities shown are related to equipment that add or remove heat within the
Utility Streams
lps Low-pressure Steam: 3–5 barg (sat) ‡
mps Medium-pressure Steam: 10–15 barg (sat) ‡
hps High-pressure Steam: 40–50 barg (sat) ‡
htm Heat Transfer Media (Organic): to 400°C
cw Cooling Water: From cooling tower 30°C returned at less than 45°C†
wr River Water: From river 25°C returned at less than 35°C
rw Refrigerated Water: In at 5°C returned at less than 15°C
rb Refrigerated Brine: In at −45°C returned at less than 0°C
cs Chemical Waste Water with high COD
ss Sanitary Waste Water with high BOD, etc.
el Electric Heat (specify 220, 440, 660V service)
ng Natural Gas
fg Fuel Gas
fo Fuel Oil
fw Fire Water
‡
These pressures are set during the preliminary design stages and typical values vary within the
ranges shown.
†
Above 45°C, significant scaling occurs.
ch01.qxd 9/11/2002 11:40 AM Page 23
Optional Information
Component Mole Fractions
Component Mass Fractions
Individual Component Flowrates (kg/h)
Volumetric Flowrates (m3/h)
Significant Physical Properties
Density
Viscosity
Other
Thermodynamic Data
Heat Capacity
Stream Enthalpy
K-values
Stream Name
ch01.qxd 9/11/2002 11:40 AM Page 24
Table 1.5 Flow Summary Table for the Benzene Process Shown in Figure 1.3 (and Figure 1.5)
Stream Number 1 2 3 4 5 6 7 8
Temperature (°C) 25 59 25 225 41 600 41 38
Pressure (bar) 1.90 25.8 25.5 25.2 25.5 25.0 25.5 23.9
Vapor Fraction 0.0 0.0 1.00 1.0 1.0 1.0 1.0 1.0
Mass Flow (tonne/h) 10.0 13.3 0.82 20.5 6.41 20.5 0.36 9.2
Mole Flow (kmol/h) 108.7 144.2 301.0 1204.4 758.8 1204.4 42.6 1100.8
Component Mole Flow
(kmol/h)
Hydrogen 0.0 0.0 286.0 735.4 449.4 735.4 25.2 651.9
Methane 0.0 0.0 15.0 317.3 302.2 317.3 16.95 438.3
Benzene 0.0 1.0 0.0 7.6 6.6 7.6 0.37 9.55
Toluene 108.7 143.2 0.0 144.0 0.7 144.0 0.04 1.05
mary table for the benzene process, Figure 1.3, is given in Table 1.5 and contains
all the required information listed in Table 1.4.
With information from the PFD (Figure 1.3) and the flow summary table
(Table 1.5), problems regarding material balances and other problems are easily
analyzed. To start gaining experience in working with information from the PFD,
the following examples are provided.
Example 1.2
Check the overall material balance for the benzene process shown in Figure 1.3. From the
figure, we identify the input streams as Stream 1 (toluene feed) and Stream 3 (hydrogen
feed) and the output streams as Stream 15 (product benzene) and Stream 16 (fuel gas).
From the flow summary table, these flows are listed as (units are in (103 kg)/h):
Input: Output:
Stream 3 0.82 Stream 15 8.21
Stream 1 10.00 Stream 16 2.61
Total 10.82×103 kg/h Total 10.82×103 kg/h
Balance is achieved since Output = Input.
Example 1.3
Determine the conversion per pass of toluene to benzene in R-101 in Figure 1.3. Conver-
sion is defined as
9 10 11 12 13 14 15 16 17 18 19
654 90 147 112 112 112 38 38 38 38 112
24.0 2.6 2.8 3.3 2.5 3.3 2.3 2.5 2.8 2.9 2.5
1.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 1.0 0.0 1.0
20.9 11.6 3.27 14.0 22.7 22.7 8.21 2.61 0.07 11.5 0.01
1247.0 142.2 35.7 185.2 290.7 290.7 105.6 304.2 4.06 142.2 0.90
652.6 0.02 0.0 0.0 0.02 0.0 0.0 178.0 0.67 0.02 0.02
442.3 0.88 0.0 0.0 0.88 0.0 0.0 123.05 3.10 0.88 0.88
116.0 106.3 1.1 184.3 289.46 289.46 105.2 2.85 0.26 106.3 0.0
36.0 35.0 34.6 0.88 1.22 1.22 0.4 0.31 0.03 35.0 0.0
From the PFD, the input streams to R-101 are shown as Stream 6 (reactor feed) and Stream
7 (recycle gas quench), and the output stream is Stream 9 (reactor effluent stream). From
the information in Table 1.5 (units are kmol/h):
ε = 108.03/144.04 = 0.75
Towers
Size (height and diameter), Pressure, Temperature
Number and Type of Trays
Height and Type of Packing
Materials of Construction
Heat Exchangers
Type: Gas-Gas, Gas-Liquid, Liquid-Liquid, Condenser, Vaporizer
Process: Duty, Area, Temperature, and Pressure for both streams
No. of Shell and Tube Passes
Materials of Construction: Tubes and Shell
Tanks
See vessels
Vessels
Height, Diameter, Orientation, Pressure, Temperature, Materials of Construction
Pumps
Flow, Discharge Pressure, Temperature, P, Driver Type, Shaft Power, Materials of Construction
Compressors
Actual Inlet Flow Rate, Temperature, Pressure, Driver Type, Shaft Power,
Materials of Construction
Heaters (Fired)
Type, Tube Pressure, Tube Temperature, Duty, Fuel, Material of Construction
Others
Provide Critical Information
ch01.qxd 9/11/2002 11:40 AM Page 27
Shell
Temp. (°C) 225 654 160 112 112 185
Pres. (bar) 26 24 6 3 3 11
Phase Vap. Par. Cond. Cond. Cond. l Cond.
MOC 316SS 316SS CS CS CS CS
Tube
Temp. (°C) 258 40 90 40 40 147
Pres. (bar) 42 3 3 3 3 3
Phase Cond. l l l l Vap.
MOC 316SS 316SS CS CS CS CS
Vessels/Tower/
Reactors V-101 V-102 V-103 V-104 T-101 R-101
Temperature (°C) 55 38 38 112 147 660
Pressure (bar) 2.0 24 3.0 2.5 3.0 25
Orientation Horizn'l Vertical Vertical Horizn'l Vertical Vertical
MOC CS CS CS CS CS 316SS
Size
Height/Length (m) 5.9 3.5 3.5 3.9 29 14.2
Diameter (m) 1.9 1.1 1.1 1.3 1.5 2.3
Internals s.p. s.p. 42 sieve trays catalyst
316SS packed
bed-10m
(continued)
ch01.qxd 9/11/2002 11:40 AM Page 28
Example 1.4
We locate Stream 1 in Figure 1.5 and note that immediately following the stream identifi-
cation diamond a staff is affixed. This staff carries three flags containing the following
stream data:
ch01.qxd 9/11/2002 11:40 AM Page 29
1. Temperature of 25 °C
2. Pressure of 1.9 bar
3. Mass flow rate of 10.0 x 103 kg/h
The units for each process variable are indicated in the key provided at the left-hand
side of Figure 1.5.
With the addition of the process control loops and the information flags, the
PFD starts to become cluttered. Therefore, in order to preserve clarity, it is neces-
sary to limit what data are presented with these information flags. Fortunately,
flags on a PFD are easy to add, remove, and change, and even temporary flags
may be provided from time to time.
The information provided on the flags is also included in the flow summary
table. However, often it is far more convenient when analyzing the PFD to have
certain data directly on the diagram.
Not all process information is of equal importance. General guidelines for
what data should be included in information flags on the PFD are difficult to de-
fine. However, as a minimum, information critical to the safety and operation of
the plant should be given. This includes temperatures and pressures associated
with the reactor, flowrates of feed and product streams, and stream pressures
and temperatures that are substantially higher than the rest of the process. Addi-
tional needs are process specific. Some examples of where and why information
should be included directly on a PFD are given below.
Example 1.5
Acrylic acid is temperature sensitive and polymerizes at 90°C when present in high con-
centration. It is separated by distillation and leaves from the bottom of the tower. In this
case, a temperature and pressure flag would be provided for the stream leaving the re-
boiler.
Example 1.6
In the benzene process, the feed to the reactor is substantially hotter than the rest of the
process and is crucial to the operation of the process. In addition, the reaction is exother-
mic, and the reactor effluent temperature must be carefully monitored. For this reason
Stream 6 (entering) and Stream 9 (leaving) have temperature flags.
Example 1.7
The pressures of the streams to and from R-101 in the benzene process are also important.
The difference in pressure between the two streams gives the pressure drop across the re-
actor. This, in turn, gives an indication of any maldistribution of gas through the catalyst
beds. For this reason, pressure flags are also included on Streams 6 and 9.
ch01.qxd 9/11/2002 11:40 AM Page 30
toluene
V-101
hydrogen
Figure 1.5 Benzene Process Flow Diagram (PFD) for the Production of Benzene
via the Hydrodealkylation of Toluene
STREAM I.D.
TEMPERATURE
PRESSURE
LIQUID FLOWRATE
GAS FLOWRATE
MOLAR FLOWRATE
V-104
Of secondary importance is the fact that flags are useful in reducing the size
of the flow summary table. For pumps, compressors, and heat exchangers, the
mass flows are the same for the input and output streams, and complete entries
in the stream table are not necessary. If the input (or output) stream is included in
the stream table, and a flag is added to provide the temperature (in the case of a
heat exchanger) or the pressure (in the case of a pump) for the other stream, then
there is no need to present this stream in the flow summary table.
Example 1.8
Follow Stream 13 leaving the top of the benzene column in the benzene PFD given in Fig-
ure 1.5 and in Table 1.5. This stream passes through the benzene condenser, E-104, into the
reflux drum, V-102. The majority of this stream then flows into the reflux pump, P-102,
and leaves as Stream 14, while the remaining noncondensables leave the reflux drum in
Stream 19. The mass flowrate and component flowrates of all these streams are given in
Table 1.5. The stream leaving E-104 is not included in the stream table. Instead, a flag giv-
ing the temperature (112°C) was provided on the diagram (indicating condensation with-
out sub-cooling). An additional flag, showing the pressure following the pump, is also
shown. In this case the entry for Stream 14 could be omitted from the stream table, because
it is simply the sum of Streams 12 and 15, and no information would be lost.
More information could be included in Figure 1.5 had space for the dia-
gram not been limited by text format. It is most important that the PFD remains
ch01.qxd 9/11/2002 11:40 AM Page 32
For Piping—Include All Lines Including Drains, Sample Connections and Specify
Size (use standard sizes)
Schedule (thickness)
Materials of construction
Insulation (thickness and type)
For Instruments—Identify
Indicators
Recorders
Controllers
Show instrument lines
For Utilities—Identify
Entrance utilities
Exit utilities
Exit to waste treatment facilities
the larger-sized unit operations is reflected by the size of the symbol in the dia-
gram.
Utility connections are identified by a numbered box in the P&ID. The num-
ber within the box identifies the specific utility. The key identifying the utility
connections is shown in a table on the P&ID.
All process information that can be measured in the plant is shown on the
P&ID by circular flags. This includes the information to be recorded and used in
process control loops. The circular flags on the diagram indicate where the infor-
mation is obtained in the process and identifies the measurements taken and how
the information is dealt with. Table 1.10 summarizes the conventions used to
identify information related to instrumentation and control. The following exam-
ple illustrates the interpretation of instrumentation and control symbols.
Example 1.9
Consider the benzene product line leaving the right-hand side of the P&ID in Figure 1.7.
The flowrate of this stream is controlled by a control valve that receives a signal from a
level measuring element placed on V-104. The sequence of instrumentation is as follows:
ch01.qxd
34
9/11/2002
11:40 AM
Page 34
V-104
3
P-102B
TI
Figure 1.7 Piping and Instrumentation Diagram for Benzene Distillation (adapted from Kauffman, D, Flow Sheets and Diagrams,” AIChE Modular
Instruction, Series G: Design of Equipment, series editor J. Beckman, AIChE, New York, 1986, vol 1, Chapter G.1.5, AIChE copyright © 1986 AIChE, all
rights reserved)
ch01.qxd 9/11/2002 11:40 AM Page 35
Location of Instrumentation
A level sensing element (LE) is located on the reflux drum V-104. A level transmitter (LT)
also located on V-104 sends an electrical signal (designated by a dashed line) to a level in-
dicator and controller (LIC). This LIC is located in the control room on the control panel or
console (as indicated by the horizontal line under LIC) and can be observed by the opera-
tors. From the LIC, an electrical signal is sent to an instrument (LY) that computes the cor-
rect valve position and in turn sends a pneumatic signal (designated by a solid line with
cross hatching) to activate the control valve (LCV). In order to warn operators of potential
problems, two alarms are placed in the control room. These are a high-level alarm (LAH)
and a low-level alarm (LAL), and they receive the same signal from the level transmitter as
does the controller.
This control loop is also indicated on the PFD of Figure 1.5. However, the details of
all the instrumentation are condensed into a single symbol (LIC), which adequately de-
scribes the essential process control function being performed. The control action that
takes place is not described explicitly in either drawing. However, it is a simple matter to
infer that if there is an increase in the level of liquid in V-104, the control valve will open
slightly and the flow of benzene product will increase, tending to lower the level in V-104.
For a decrease in the level of liquid, the valve will close slightly.
The details of the other control loops in Figures 1.5 and 1.7 are left to problems at
the end of this chapter. It is worth mentioning that in virtually all cases of process
control in chemical processes, the final control element is a valve. Thus, all con-
trol logic is based on the effect that a change in a given flowrate has on a given
variable. The key to understanding the control logic is to identify which flowrate
is being manipulated to control which variable. Once this has been done, it is a
relatively simple matter to see in which direction the valve should change in
order to make the desired change in the control variable. The response time of the
system and type of control action used—for example, proportional, integral, or
differential—is left to the instrument engineers and is not covered in this text.
The P&ID is the last stage of process design and serves as a guide by those
who will be responsible for the final design and construction. Based on this
diagram:
1. Mechanical engineers and civil engineers will design and install pieces of
equipment.
2. Instrument engineers will specify, install, and check control systems.
3. Piping engineers will develop plant layout and elevation drawings.
4. Project engineers will develop plant and construction schedules.
ch01.qxd 9/11/2002 11:40 AM Page 37
Before final acceptance, the P&IDs serve as a checklist against which each
item in the plant is checked.
The P&ID is also used to train operators. Once the plant is built and is oper-
ational, there are limits to what operators can do. About all that can be done to
correct or alter performance of the plant is to open, close, or change the position
of a valve. Part of the training would pose situations and require the operators to
be able to describe what specific valve should be changed, how it should be
changed, and what to observe in order to monitor the effects of the change. Plant
simulators (similar to flight simulators) are sometimes involved in operator train-
ing. These programs are sophisticated, real-time process simulators that show a
trainee operator how quickly changes in controlled variables propagate through
the process. It is also possible for such programs to display scenarios of process
upsets so that operators can get training in recognizing and correcting such situa-
tions. These types of programs are very useful and cost-effective in initial opera-
tor training. However, the use of P&IDs is still very important in this regard.
The P&ID is particularly important for the development of start-up proce-
dures where the plant is not under the influence of the installed process control
systems.
Example 1.10
Consider the start-up of the distillation column shown in Figure 1.7. What sequence would
be followed? The procedure is beyond the scope of this text, but it would be developed
from a series of questions such as
These last three sections have followed the development of a process from a
simple BFD through the PFD and finally to the P&ID. Each step showed addi-
tional information. This can be seen by following the progress of the distillation
unit as it moves through the three diagrams described.
1. Block Flow Diagram (BFD) (see Figure 1.1): The column was shown as a
part of one of the three process blocks.
2. Process Flow Diagram (PFD) (see Figure 1.5): The column was shown as the
following set of individual equipment: a tower, condenser, reflux drum, re-
boiler, reflux pumps, and associated process controls.
3. Piping and Instrumentation Diagram (P&ID) (see Figure 1.7): The column
was shown as a comprehensive diagram that includes additional details
ch01.qxd 9/11/2002 11:40 AM Page 38
such as pipe sizes, utility streams, sample taps, numerous indicators, and so
on. It is the only unit operation on the diagram.
The value of these diagrams does not end with the start-up of the plant. The
design values on the diagram are changed to represent the actual values deter-
mined under normal operating conditions. These conditions form a “base case”
and are used to compare operations throughout the life of the plant.
During the planning and construction phases of a new project, many additional
diagrams are needed. Although these diagrams do not possess additional process
information, they are essential to the successful completion of the project. Com-
puters are being used more and more to do the tedious work associated with all
of these drawing details. The creative work comes in the development of the con-
cepts provided in the BFD and the process development required to produce the
PFD. The computer can help with the drawings but cannot create a new process.
Computers are valuable in many aspects of the design process where the size of
equipment to do a specific task is to be determined. Computers may also be used
when considering performance problems that deal with the operation of existing
equipment. However, they are severely limited in dealing with diagnostic prob-
lems that are required throughout the life of the plant.
The diagrams presented here are in both American Engineering and SI
units. The most noticeable exception is in the sizing of piping, where pipes are
specified in inches and pipe schedule. This remains the way they are produced
and purchased in the United States. A process engineer today must be comfort-
able with SI, conventional metric, and American (formerly British, who now use
SI exclusively) Engineering units.
We discuss these additional diagrams briefly below.
A utility flowsheet may be provided which shows all the headers for utility
inputs and outputs available along with the connections needed to the process. It
provides information on the flows and characteristics of the utilities used by the
plant.
Vessel sketches, logic ladder diagrams, wiring diagrams, site plans, struc-
tural support diagrams, and many other drawings are routinely used but add lit-
tle to our understanding of the basic chemical processes that take place.
Additional drawings are necessary to locate all of the equipment in the
plant. Plot plans and elevation diagrams are provided that locate the placement
and elevation of all of the major pieces of equipment such as towers, vessels,
pumps, heat exchangers, and so on. When constructing these drawings, it is nec-
essary to consider and to provide for access for repairing equipment, removing
ch01.qxd 9/11/2002 11:40 AM Page 39
tube bundles from heat exchangers, replacement of units, and so on. What re-
mains to be shown is the addition of the structural support and piping.
Piping isometrics are drawn for every piece of pipe required in the plant.
These drawings are 3-D sketches of the pipe run, indicating the elevations and
orientation of each section of pipe. In the past, it was also common for compre-
hensive plants to build a scale model so the system could be viewed in three di-
mensions and modified to remove any potential problems. Over the past twenty
years, scale models have been replaced by 3-dimensional computer aided design
(CAD) programs that are capable of representing the plant as-built in three di-
mensions. They provide an opportunity to view the local equipment topology
from any angle at any location inside the plant. One can actually “walk through”
the plant and preview what will be seen when the plant is built. The ability to
“view” the plant before construction will be made even more realistic with the
help of virtual reality software. With this new tool, it is possible not only to
“walk through” the plant but also to “touch” the equipment, turn valves, and
climb to the top of distillation columns, and so on. In the next section, the infor-
mation needed to complete a preliminary plant layout design is reviewed, and
the logic used to locate the process units in the plant and how the elevations of
different equipment are determined are briefly explained.
As mentioned earlier, the major design work products, both chemical and me-
chanical, are recorded on 2-dimensional diagrams (PFD, P&ID, etc.). However,
when it comes to the construction of the plant, there are many issues that require
a 3-dimensional representation of the process. For example, the location of shell
and tube exchangers must allow for tube bundle removal for cleaning and repair.
Locations of pumps must allow for access for maintenance and replacement. For
compressors, this access may also require that a crane be able to remove and re-
place a damaged drive. Control valves must be located at elevations that allow
operator access. Sample ports and instrumentation must also be located con-
veniently. For anyone who has toured a moderate-to-large chemical facility, the
complexity of the piping and equipment layout is immediately apparent. Even
for experienced engineers, the review of equipment and piping topology is far
easier to accomplish in 3-D than 2-D. Due to the rapid increase in computer
power and advanced software, such representations are now done routinely
using the computer. In order to “build” an electronic representation of the plant
in 3-D, all the information in the previously mentioned diagrams must be ac-
cessed and synthesized. This in itself is a daunting task, and a complete account-
ing of this process is well beyond the scope of this text. However, in order to give
the reader a flavor of what can now be accomplished using such software, a brief
review of the principles of plant layout design will be given. A more detailed
ch01.qxd 9/11/2002 11:40 AM Page 40
account involving a virtual plant tour of the dimethyl ether (DME) plant (Appen-
dix B.1) is given on the CD accompanying this book.
For a complete, detailed analysis of the plant layout, all equipment sizes,
piping sizes, PFDs, P&IDs, and all other information should be known. However,
for this description, a preliminary plant layout based on information given in the
PFD of Figure B.1 is considered. Using this figure and the accompanying stream
tables and equipment summary table (Tables B.1 and B.2), the following steps are
followed:
1. The PFD is divided into logical subsystems. For the DME process, there are
three logical subsections, namely, the feed and reactor section, the DME pu-
rification section, and the methanol separation and recycle section. These
sections are shown as dotted lines on Figure 1.8.
2. For each subsystem, a preliminary plot plan is created. The topology of the plot
plan depends on many factors, the most important of which are discussed
below.
In general, the layout of the plot plan can take one of two basic config-
urations: the grade-level, horizontal, in-line arrangement and the structure-
mounted vertical arrangement [5]. The grade-level, horizontal, in-line
arrangement will be used for the DME facility. In this arrangement, the
process equipment units are aligned on either side of a pipe rack that runs
through the middle of the process unit. The purpose of the pipe rack is to
carry piping for utilities, product, and feed to and from the process unit.
Equipment is located on either side of the pipe rack, which allows for easy
access. In addition, vertical mounting of equipment is usually limited to a
single level. This arrangement generally requires a larger “footprint” and,
hence, more land than does the structure-mounted vertical arrangement.
The general arrangement for these layout types is shown in Figure 1.9.
The minimum spacing between equipment should be set early on in
the design. These distances are set for safety purposes and should be set
with both local and national codes in mind. A comprehensive list of the rec-
ommended minimum distances between process equipment is given by
Bausbacher and Hunt [5]. The values for some basic process equipment are
listed in Table 1.11.
The sizing of process equipment should be completed and the approx-
imate location on the plot plan determined. Referring to Table B.1 for equip-
ment specifications gives some idea of key equipment sizes. For example,
the data given for the reflux drums V-202 and V-203, reactor R-201, and
towers T-201 and T-202 are sufficient to sketch these units on the plot plan.
However, pump sizes must be obtained from vendors or previous jobs, and
additional calculations for heat exchangers must be done to estimate their
required “footprint” on the plot plan.
ch01.qxd
P-201A/B V-201 E-201 R-201 E-202 E-203 T-201 E-204 E-205 V-202 P-202A/B E-206 T-202 E-207 V-203 P-203A/B E-208
Feed Pump Feed Methanol Reactor Reactor DME DME DME DME DME DME Reflux Methanol Methanol Methanol Methanol Methanol Wastewater
Vessel Preheater Cooler Cooler Tower Reboiler Condenser Reflux Pumps Reboiler Tower Condenser Reflux Pumps Cooler
Drum Drum
9/11/2002
DME
Methanol 10
11:40 AM
1 E-205
R-201
V-201 T-201
cw 13
1
Page 41
16 V-202
2
12
6 P-202A/B
9
P-201A/B
22
3 5 cw
T-202 E-207
1
mps
17 V-203
E-201
8
E-202
cw 11 14
mps 12
E-204 P-203A/B
4 7 26
E-203
DME Purification
cw Waste-
Feed and Reactor Subsystem Subsystem
water
mps 14 15
E-206
E-208
Methanol Separation
Subsystem
41
Figure 1.8 Subsystems for Preliminary Plan Layout for DME Process
ch01.qxd 9/11/2002 11:40 AM Page 42
(a)
(b)
Figure 1.9 Different Types of Plant Layout: (a) Grade-Mounted Horizontal Inline
Arrangement, and (b) Structure-Mounted Vertical Arrangement (Source: Process Plant Lay-
out and Piping Design, by E. Bausbacher and R. Hunt, © 1994, reprinted by permission of
Pearson Education, Inc. Upper Saddle River, NJ)
ch01.qxd 9/11/2002 11:40 AM Page 43
Table 1.11 Recommended Minimum Spacing (in feet) between Process Equipment
for Refinery, Chemical, and Petrochemical Plants
Example 1.11
Estimate the footprint for E-202 in the DME process.
From Table B.1 we have the following information:
Floating Head Shell-and-Tube design
Area = 171 m2
Hot Side—Temperatures: in at 364ºC and out at 281ºC
Cold Side—Temperatures: in at 154ºC and out at 250ºC
Choose a 2-shell pass and 4-tube pass exchanger
Area per shell = 171/2 = 85.5 m2
Using 12 ft, 1-inch OD tubes, 293 tubes per shell are needed
Assuming the tubes are laid out on a 11⁄4-inch square pitch, a 27-inch ID shell is required.
Assume that the front and rear heads (where the tube fluid turns at the end of the ex-
changer) are 30 inches in diameter and require 2 feet each (including flanges), and that the
two shells are stacked on top of each other. The footprint of the exchanger is given in Fig-
ure E1.11.
Next, the size of the major process lines must be determined. In order to es-
timate these pipe sizes, it is necessary to make use of some heuristics. A
heuristic is a simple algorithm or hint that allows an approximate answer to
be calculated. The preliminary design of a piece of equipment might well
use many such heuristics, and some of these might conflict with each other.
Like any simplifying procedure, the result from a heuristic must be re-
viewed carefully. For preliminary purposes, the heuristics from Chapter 9
can be used to estimate approximate pipe sizes.
ch01.qxd 9/11/2002 11:40 AM Page 44
2 ft 6 in
Plot plan view (from above looking down) showing approximate size of footprint
2 feet 6 inches
(30 inches)
16 feet
Example 1.12
Consider the suction line to P-202 A/B, what should be the pipe diameter?
From Table 9.8, 1(b) for liquid pump suction, the recommended liquid velocity and pipe
diameter are related by u = (1.3 + D (inch)/6) ft/s.
From Table B.2, the mass flowrate of the stream entering P-202, ṁ = Stream 16 + Stream 10
= 2170 + 5970 = 8140 kg/h and the density is found to be 800 kg/m3.
The volumetric flowrate is = 8140/800 = 10.2 m3/h = 0.00283 m3/s= 0.0998 ft3/s
The procedure is to calculate the velocity in the suction line and compare it to the heuristic.
Using this approach, the following table is constructed:
Therefore, the pipe diameter that satisfies both the heuristic and the continuity equation
lies between 3 and 4 inches. Taking a conservative estimate, a 4-inch suction line is chosen
for P-202.
The next step to consider is the placement of equipment within the plot
plan. This placement must be made considering the required access for
maintenance of the equipment and also the initial installation. Although this
step may seem elementary, there are many cases [5] where the incorrect
placement of equipment subsequently led to considerable cost overruns and
major problems both during the construction of the plant and during main-
tenance operations. Consider the example shown in Figure 1.10(a) where
two vessels, a tower, and a heat exchanger are shown in the plot plan.
Clearly, V-1 blocks the access to the exchanger’s tube bundle, which often
requires removal to change leaking tubes or to remove scale on the outside
of the tubes. With this arrangement, the exchanger would have to be lifted
Crane
Road Road
Rearrangement of equipment makes
tube bundle removal easy
V-2 V-2
E-1 V-1
T-1 T-1
V-1 E-1
Pipe Rack
Pipe Rack
(a) (b)
Figure 1.10 The Effect of Equipment Location on the Ease of Access for Maintenance, Installation
and Removal
ch01.qxd 9/11/2002 11:40 AM Page 46
Pipe Rack
P-201A
P-201B
E-201
E-202
V-201
R-201
24 ft
36 ft
gas is poisonous). For this reason, towers are generally elevated between
3 to 5 m (10 and 15 feet) above ground level by using a “skirt.” This is illus-
trated in Figure 1.12. Another reason for elevating a distillation column is
also illustrated in Figure 1.12. Often a thermosiphon reboiler is used. These
reboilers use the difference in density between the liquid fed to the reboiler
and the two-phase mixture (saturated liquid-vapor) that leaves the reboiler
to “drive” the circulation of bottoms liquid through the reboiler. In order to
obtain an acceptable driving force for this circulation, the static head of the
liquid must be substantial, and a 3–5 m height differential between the liq-
uid level in the column and the liquid inlet to the reboiler is typically suf-
ficient. Examples of when equipment elevation is required are given in
Table 1.12.
4. Major process and utility piping are sketched in. The final step in this prelimi-
nary plant layout is to sketch in where the major process (and utility) pipes
(lines) go. Again, there are no set rules to do this. However, the most direct
route between equipment that avoids clashes with other equipment and
piping is usually desirable. It should be noted that utility lines originate and
usually terminate in headers located on the pipe rack. When process piping
must be run from one side to the process to another, it may be convenient to
run the pipe on the pipe rack. All control valves, sampling ports, and major
Distillation Tower
Grade
Horizontal (or Vertical)
Thermosiphon Reboiler Column Skirt
The best way to see how all the above elements fit together is to view the
Virtual_Plant_Tour.AVI file on the CD that accompanies this text. The quality
and level of detail that 3-D software is capable of giving depends on the system
used and the level of detailed engineering that is used to produce the model. Fig-
ures 1.13–1.15 were generated for the DME facility using the PDMS software
package from Cadcentre, Inc. (These figures and the Virtual_Plant_Tour.AVI file
are presented here with permission of Cadcentre, Inc.) In Figure 1.13, an isomet-
ric view of the DME facility is shown. All major process equipment, major
process and utility piping, and basic steel structures are shown. The pipe rack is
shown running through the center of the process, and steel platforms are shown
where support of elevated process equipment is required. The distillation sec-
tions are shown to the rear of the figure on the far side of the pipe rack. The reac-
ch01.qxd 9/11/2002 11:40 AM Page 49
tor and feed section is shown on the near side of the pipe rack. The elevation of
the process equipment is better illustrated in Figure 1.14, where the piping and
structural steel have been removed. The only elevated equipment apparent from
this figure are the overhead condensers and reflux drums for the distillation
columns. The overhead condensers are located vertically above their respective
reflux drums to allow for the gravity flow of condensate from the exchangers to
the drums. Figure 1.15 shows the arrangement of process equipment and piping
for the feed and reactor sections. The layout of equipment corresponds to that
shown in Figure 1.11. It should be noted that the control valve on the discharge of
the methanol feed pumps is located close to grade level for easy access.
1.7 SUMMARY
In this chapter, you have learned that the three principal types of diagrams used
to describe the flow of chemical streams through a process are the block flow dia-
gram (BFD), the process flow diagram (PFD), and the piping and instrumentation
diagram (P&ID). These diagrams describe a process in increasing detail.
ch01.qxd 9/11/2002 11:40 AM Page 50
Figure 1.15 3-D Representation of the Reactor and Feed Sections of the DME Process
Model (Reproduced by Permission of Cadcentre, an Aveva Group Company, from their
Vantage/PDMS Software)
50
ch01.qxd 9/11/2002 11:40 AM Page 51
Each diagram serves a different purpose. The block flow diagram is useful
in conceptualizing a process or a number of processes in a large complex. Little
stream information is given, but a clear overview of the process is presented. The
process flow diagram contains all the necessary information to complete material
and energy balances on the process. In addition, important information such as
stream pressures, equipment sizes, and major control loops are included. Finally,
the piping and instrumentation diagram contains all the process information nec-
essary for the construction of the plant. These data include pipe sizes and the lo-
cation of all instrumentation for both the process and utility streams.
In addition to the three diagrams, there are a number of other diagrams
used in the construction and engineering phase of a project. However, these dia-
grams contain little additional information about the process.
Finally, the logic for equipment placement and layout within the process
was discussed. The reasons for elevating equipment and providing access were
discussed, and the 3-D representation of the plant was presented.
The PFD is the single most important diagram for the chemical/process en-
gineer and will form the basis of much of the discussion covered in this book.
REFERENCES
1. Kauffman, D., “Flow Sheets and Diagrams,” AIChE Modular Instruction, Se-
ries G: Design of Equipment, series editor J. Beckman, American Institute of
Chemical Engineers, New York, 1986, vol. 1, Chapter G.1.5. Reproduced by
permission of the American Institute of Chemical Engineers, AIChE copy-
right 1986, all rights reserved.
2. Graphical Symbols for Process Flow Diagrams, ASA Y32.11 (New York: Ameri-
can Society of Mechanical Engineers, 1961).
3. Austin, D. G. Chemical Engineering Drawing Symbols (London: George
Godwin, 1979).
4. Instrument Symbols and Identification Research Triangle Park, NC: Instrument
Society of America, Standard ISA-S5-1, 1975.
5. Bausbacher, E. and R. Hunt, Process Plant Layout and Piping Design (Upper
Saddle River, NJ: Prentice Hall PTR, 1998).
PROBLEMS
Note: Problems 1–9 are from Kauffman [1] and are reproduced by permission of
the American Institute of Chemical Engineers, AIChE copyright © 1986, all rights
reserved.
1. What are the three principal types of flowsheets used in the chemical process
industries?
ch01.qxd 9/11/2002 11:40 AM Page 52
2. Which of the three principal types of flowsheets would one use to:
a. give a group of visiting chemical engineering students an overview of a
plant’s process?
b. make a preliminary capital cost estimate?
c. trace down a fault in a control loop?
3. In what type of flowsheet could one expect to find pipe diameters and mate-
rials of construction?
4. To what extent are instruments and controls indicated in each of the three
types of flowsheets?
5. On which of the three principal types of flowsheets would one expect to find:
a. relief valves?
b. which pipe lines need insulation?
c. which control loops are needed for normal operation?
d. rectangles shown, rather than symbols, that resemble pieces of equipment?
e. whether a controller is to be located in the control room or in the plant?
6. Would you expect the process design to include more PFDs or P&IDs?
7. Prepare the simplest principal type of flowsheet for the following process,
and indicate the flowrates of the principal chemical components:
A refinery stream containing paraffins and a mixture of aromatics (benzene,
toluene, xylene, and heavier aromatics) is extracted with a liquid solvent to re-
cover the aromatics. The solvent and aromatics are separated by distillation, with
the solvent recycled to the extraction column. The aromatics are separated in
three columns, recovering benzene, toluene, and mixed xylenes, in that order.
The feed stream consists of the following:
LAH
V-101
FY FRC FT
FE
TCV
4" Sch 40
8" Sch 40
LI
LI
Chemical Chemical
Sewer Sewer
The overhead vapor stream from the column is totally condensed in a water-
cooled heat exchanger prior to being fed to an overhead reflux drum. The
liquid product from the drum is sent to the reflux pump (which has a spare),
and the discharge from the pump is split into two streams. One of these
streams is the overhead reflux to the column and is fed back to the column on
Tray 1. The second liquid stream from the pump discharge is the overhead
product and is sent to storage.
The bottom of the distillation column is used to store the liquid leaving the
bottom plate. From the bottom of the column a liquid stream leaves and is
immediately split into two. One stream is the bottom product, which is sent
for further processing in Unit 400. The other stream is sent to a ther-
mosyphon reboiler where a portion of the stream is vaporized by condensing
low pressure steam on the other side of the exchanger. The partially vapor-
ized stream from the reboiler is returned to the column just below the
twenty-fourth tray. The two-phase mixture separates, with the vapor portion
passing upward through the bottom plate to provide the vapor flow in the
column. The liquid portion returns to the liquid accumulated at the bottom
of the column.
For the process described above, draw a PFD. You may assume that the
process is Unit 200, and you should identify and number all the equipment
appropriately.
11. For the process described in Problem 10, the following control scheme has
been suggested for the overhead portion of the column:
The flow of overhead product going to storage is controlled by a signal
from the liquid level indicator on the reflux drum, which is used to control
ch01.qxd 9/11/2002 11:40 AM Page 54
the position of a pneumatic control valve in the product line (pipe). The flow
of reflux back to the column is also regulated by a pneumatic control valve,
which uses the signal (electrical) from a flow indicator on the overhead prod-
uct line to adjust the valve such that the flow of reflux is always in a certain
proportion to the product flow.
On the PFD developed in Problem 10, add the controls to give the desired
control action described above.
Bonus Points: Can you describe how the control scheme should operate,
that is, what valve opens or closes, and so on, when the level of liquid rises
above or falls below its set-point value?
12. For the process described in Problem 10, the flow of bottom product sent to
Unit 400 is controlled by a pneumatic valve that receives a signal from a liquid
level indicator that senses the level of accumulated liquid in the bottom of the
column. Add this control loop to the PFD developed in Problem 10.
13. For the process described in Problem 10, it is desired to control the purity of
the top product. If we assume that the pressure of the column does not vary
(not necessarily a good assumption), we may infer the product purity from
the temperature of the top tray. Devise a control scheme to implement a feed-
back loop to control the top product purity. Draw this control loop on the
PFD for Problem 10.
14. Drying oil (DO) is produced by thermally decomposing acetylated castor oil
(ACO) according to the following reaction:
ACO1l2 340°C
: DO1l2 + CH3COOH1g2
heat
For the process described above, draw a PFD showing the following
details:
Equipment numbers and description
Basic control loops
Temperature and pressure flags
15. A preliminary plant layout (plot plan) for a new process is shown in Figure
P1.15. List and explain all the potential problems with the equipment layout
that you can find.
Road
P-1A/B
R-1
Elevations
R-1 bottom at grade +15 ft
T-1 bottom at grade
Pipe Rack
16. The elevation of equipment above ground level is expensive because addi-
tional structural steel is required. However, it is normal practice in chemical
plants to elevate the bottom of a distillation column by 10 to 15 feet, using a
metal “skirt.” Why is such extra expense justified?
17. What are the advantages and disadvantages of placing a pump in a pit below
ground level?
18. A compressor, reactor, tower, condenser, and overhead reflux drum and re-
flux pump must be added to an existing process. The plot plan of the existing
process and the available space for the new equipment is shown in Figure
ch01.qxd 9/11/2002 11:40 AM Page 56
Road
R-301
Battery limits of existing process unit
Existing equipment
R-302
Road
T-301
6 ft
Pipe Rack
Battery limits of new process unit
Elevations Dimensions
C-305 at grade C-305 L = 10 ft, W = 6 ft
R-307 bottom at grade R-307 L = 35 ft, Diam = 5 ft
T-311 bottom at grade T-311 L = 80 ft, Diam = 4 ft
V-317 bottom at grade +30 ft V-317 L = 6 ft, Diam = 3 ft
E-323 bottom at grade +41 ft E-323 L = 18 ft, Diam = 4 ft
P-322A&B at grade P-322 A&B L = 5 ft. W = 2.5 ft
Figure P1.18 Plot Plan for Problem 1.18 (Data for New Equipment
Given in Table)