Group Assignment Three

This document provides instructions for Group Assignment Three which involves developing an AON network diagram to calculate project durations and floats for questions from the textbook. Students are asked to find the early start, early finish, late start, and late finish in Day 1 format for questions 13 and 14, and calculate the project floats if management allows only 20 working days for each. The assignment submission must include all diagrams and answers for each question, along with the names and student numbers of participating students on the title page.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views1 page

Group Assignment Three

This document provides instructions for Group Assignment Three which involves developing an AON network diagram to calculate project durations and floats for questions from the textbook. Students are asked to find the early start, early finish, late start, and late finish in Day 1 format for questions 13 and 14, and calculate the project floats if management allows only 20 working days for each. The assignment submission must include all diagrams and answers for each question, along with the names and student numbers of participating students on the title page.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Group Assignment Three

Project Duration Estimates


• Develop an AON network diagram with legend and using
proper unidirectional relationship arrows and calculate the
project duration for the following questions
• Use Day₀ format first, then covert to Day₁ format for your
answer.
• Question 11 on page 199
• Find the project float for question 11, if the management only
gives 110 days to work.
• Questions 13 and 14 on pages 200
• In addition, find ES, EF, LS, and LF in Day 1 format
• Find the project floats for questions 13 & 14 if the management
only allows 20 working days for each project.
Submission including all the necessary diagrams and answers for each
question
Include all the participated student names and student numbers on
your title page