Control-System Engineering (Based On VDB R170C)

The document discusses requirements for technical specifications for distributed control systems and programmable logic controllers. It outlines what should be included in the specifications such as interface definitions, I/O requirements, and process control needs. It emphasizes creating clear, structured specifications according to standards like VGB R170C. The specifications should provide input for control engineering and support the project phases from engineering to commissioning.

Uploaded by

TD
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views14 pages

Control-System Engineering (Based On VDB R170C)

The document discusses requirements for technical specifications for distributed control systems and programmable logic controllers. It outlines what should be included in the specifications such as interface definitions, I/O requirements, and process control needs. It emphasizes creating clear, structured specifications according to standards like VGB R170C. The specifications should provide input for control engineering and support the project phases from engineering to commissioning.

Uploaded by

TD
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

FABRITIUS ENERGY CONSULTING

Control-system engineering
(based on VDB R170C)

Uwe Fabritius
FABRITIUS ENERGY CONSULTING

Contract Process

Tech. Spec. I&C&E


I&C&E request

Technical
Specification for DCS/PLC
FABRITIUS ENERGY CONSULTING

Techn. content of a specification:


• requirements based on the contract obligations (e.g. typ of DCS/PLC)
• add. requirements based on the process (e.g. special protections 2/3)
• interface definitions (e.g. limits of supply)

• amount I/O (necessary to define the hard-ware scope/supply


• basic process requests, amount of open/closed loop controls
• definition of alarm and visualisation requirements
• explicit inputs for process – control engineering
FABRITIUS ENERGY CONSULTING
I&C Limit of supply

Interfacedefinitions: S1 S2 S3 S4
local

Junction
Box

a) Typ of signal Analog


(4...20mA)

e.g. BI/AO/BO/AI Binary

Marshalling
Trunk Trunk
Signal
Cable Cable

Control System
Analog
(4...20mA)
Hea d
mounted Tx S1

T/C Cable
* Trunk
Cable

S2

*
Signal
conditioner
S5

Other

b) Interface location based Control


System
Serial link

on „limit of supply“ Proxi


mitor
Trunk
Cable TSI

Indicates I&C scope of supply

Indicated equipment is within scope of S1 and NOT S2


*
FABRITIUS ENERGY CONSULTING
DCS Field

Interface-definitions:

- based on typ of actuator


FABRITIUS ENERGY CONSULTING

Requirements based on VGB R170C:

1) Clear structure and breakdown


2) Function focused, in-depended of the used DCS/PLS

3) Reasonable economical effort for documentation

4) Usable for engineering, commissioning and operation

5) explicit input for process-control engineering and


operation philosophy
FABRITIUS ENERGY CONSULTING

Hierarchical
Structure:
FABRITIUS ENERGY CONSULTING

Schedule/Phasen:

P1 P2 P3 P4 P5
(part of DCS/PLS supplier)

P1 => basic process design and I&C&E engineering


P2 => basic hardware-engineering
P3 => software-engineering and factory acceptance test
P4 => site commissioning (operational handover client)
P5 => final documentation/Record issue
FABRITIUS ENERGY CONSULTING

Final documents after each phase:

P1 => basic process design and I&C engineering


• P&ID_Rev.0
• system description
• I/O or signal-list
• Drive Group list
• Specification for DCS/PLC supplier

P2 => basic hardware-engineering (hardware freeze)


• P&ID_Rev.A
• system description
• final I/O list or signal-list and instrument list
• Process-logic diagramm (based on VGB R170C)
FABRITIUS ENERGY CONSULTING

P3 => software-engineering and factory acceptance test

P4 => site commissioning (operational hand-over client)

P5 => Final documentation/Record issue


FABRITIUS ENERGY CONSULTING

Input documents for FUP engineering:

1) P&ID incl. a legend of P&ID


2) I/O - List, valve – list, Signal – list for subsystems

3) System description
4) FUP guideline
5) Abbreviation list
FABRITIUS ENERGY CONSULTING

Advantage of using FUPs:

1) Fup provides a better process-understanding than just a


description (if process-focused!!)
2) supports internal communication and process-understanding

3) clear guideline for DCS/PLC supplier

4) commissioning and operation support / needs to be


“recorded after comm.” => “lessons learned”

5) document used for “claim-negotiations”


FABRITIUS ENERGY CONSULTING

Different ways to match the VGB R170C requirements:


used tools are based on the requirements of:
⇒ frequence of need to draw FUP
⇒ requested or available interfaces to existing DBs
⇒ budget of the company and available peripheries
⇒ personal preferences

Recommended are tools with a comfortable drawing – surface


e.g. based on ACAD
FABRITIUS ENERGY CONSULTING

Special requirements: ex-protection based on ATEX or NFPA


ANSI/ISA-S84.01-1996 „Application of Safety Instrumented Systems“
IEC 61511 „Functional Safety for process industrial sector“

CE conformity declaration
….. intended to be incorporated in the supply according Order No.:...........

is in conformity with the provisions of the EC Machinery Directive (Ma-D) 89/392/EEC,


as amended by the Directives 91/44/EEC, 93/44/EEC, 93/68/EECand, in accordance with Article 8 Paragraph 5
of this Directive, is in conformity with the provisions of the following other EC-Directives:
Low Voltage Directive (LV-D) 73/23/EEC as amended by 93/68/EEC
Electromagnetic Compatibility Directive (EMC-D) 89/336/EEC as amended by 91/263/EEC, 92/31EEC, 93/68/EEC
Equipment and protective systems in potentially explosive atmospheres (Ex-D) 94/9/ EG
Simple pressure vessels (SPV-D) 87/404/EEC as amended by 90/488/EEC, 93/68/EEC
as well as in conformity with all other relevant EC Directives and Regulations, all of the above in their version
valid at the time the contract between XXXX and ourselves became valid, in particular concerning the affixing
of the CE marking, the furnishing of the EC Declaration of Conformity or the Manufacturer's Declaration of
Incorporation and the preparation of the required documentation.