Siwes Report For Building
Siwes Report For Building
Siwes Report For Building
STUDENT INDUSTRIAL
WORK EXPERIENCE
SCHEME (SIWES)
i
THE POLYTECHNIC, IBADAN
FACULTY OF ENVIRONMENTAL STUDIES
UNDERTAKEN AT:
UNIVERSITY OF LAGOS, WORKS AND PHYSICAL
PLANNING DEPARTMENT, AKOKA-YABA, LAGOS STATE.
PERIOD OF ATTACHMENT:
SUBMITTED TO:
THE DEPARTMENT OF BUILDING TECHNOLOGY
ii
CERTIFICATION
This is to certify that this report is original to the author, ADEMOLA TIMILEYIN JOSHUA
of the Department of Building Technology, faculty of Environmental Studies, The
Polytechnic, Ibadan and was supervised accordingly by;
Signature _________________
iii
ACKNOWLEDGEMENT
I am thankful to Almighty God for His inspiration, guidance and strength throughout the
course of this work.
I am very grateful to my beloved Parents Mr & Mrs. Ademola, my guardian Mrs. Atunde
and my Siblings for their dearest Love and Support in my course of study.
iv
ABSTRACT
I was attached to University Of Lagos, works and physical planning unit, which had
some ongoing maintenance works and supervision of some building constructions, such
as; the rehabilitation of the university buildings, reconstruction of fallen fences, repair of
roof leakages, This report is therefore an illustration of the nature of works and activities
carried out on the construction site and the nature of works done during the course of the
industrial programme. It also provides a detailed principle of building construction and
some aspects of Health and Safety Environment in reference to building technology and
how they are applied practically in the construction of buildings.
v
TABLE OF CONTENT
Title page i
Cover page ii
Certification iii
Acknowledgement iv
Abstract v
Table of contents vi
CHAPTER 1: INTRODUCTION
SIWES Background 1
1.1 Objectives of SIWES 1
1.2 Bodies involved in the management of SIWES 2
1.3 Background of Establishment. 3
CHAPTER 2:
2.0 Work experience during attachment 8
2.1 Introduction to construction materials,
equipments and machineries. 8
2.2 Foundation works.
2.3 Block work 16
2.5 Lintels 16
2.6 Ground beam
2.7 Maintenance and repair of roofs 17
CHAPTER 3
3.1 Problems encountered during period of attachment
vi
CHAPTER 4
4.0 conclusion 21
4.1 Recommendation 22
References 23
vii
viii
CHAPTER ONE
INTRODUCTION
1.1 OBJECTIVES
The Industrial Training Funds policy Document No. 1 of 1973 which
established SIWES outlined the objectives of the scheme. The objectives are
to:
3
efficient utilization of scarce land resources to meet the University's long
term aspirations.
With its professional staff, the Unit reviews University's building stock and
infrastructural facilities to determine performance. For future purposes and
development, the University had adopted two types of academic buildings.
They are the Arts-type building and the Science and Technology-type
buildings. The former accommodates faculties such as Arts, Social Science,
Business Administration, etc. while the latter is structured to meet the needs
of faculties such as Science, Environmental Sciences, Engineering, etc. This
is in cognizance of the 60:40 ratios for Science/Technology and Arts number
of students as recommended by NUC. The Unit is headed by a Director, who
is responsible to the Vice Chancellor.
4
CHAPTER TWO
MATERIALS
Example of materials used in building construction is as follows;
Cement: This is a powdered substance that develops strong adhesive
properties when mixed with water. It is used in Block work, Plastering,
Rendering and Concreting. The establishment of Cement is achieved by
burning a mixture of clay and chalk or limestone in a kiln. A proportion of
the raw materials in a definite proportion are converted into liquid state by
grinding, mixing and watering, termed Slurry. The slurry is then conveyed
5
through a set of pipes to rotary kiln which dry and burn the constituent in a
high temperature to form hard lumps.
This process changes the slurry to hard lumps called Clinker, which
afterwards pass on through a conveyor belt to the grinding mills for grinding
to a fine powder in its final process. During the final grinding, small quantity
of gypsum of between 2 and 5% of the whole materials is added to retard the
setting time. Tests are usually carried out on the finished product
occasionally to ensure high quality.
This process is mainly on Ordinary Portland Cement (OPC) used for general
purposes. There are other types of cement made for special purposes,
including Rapid Hardening Portland Cement (RHPC), Sulphate resisting
Portland cement and Low Heat Portland Cement, Water repellent Portland
Cement, and other varieties of cement such as; higher alumina cement, quick
setting cement, white cement and so on.
6
Fine Aggregate; this should be clean, sharp and passes through the sieve size
of 4.5mm.
EQUIPMENTS
The following are examples of various tools used in construction;
Trowel: This is a flat metal blade fixed to a short handle used for the
application, jointing, smoothing and shaping of mortar in masonry. It is also
used in the trimming of block/bricks. Trowel sizes ranges from 225-350mm
measuring from the blade.
Spirit Level: This is a Hand-tool used for indicating true horizontal and
vertical of a work, by means of an air bubble sealed in a marked, liquid-
filled glass tube mounted in a frame; the tube is horizontal when the bubble
7
is between two marks. Spirit levels are of various length ranging from about
225mm to 1.2m.
Straight Edge: The kind of straight edge that was used on the construction
site is an Aluminum frame of about 2m in length. The straight edge is used
to check the fairness of the newly laid piece of a wall and to ensure that all
the blocks are laid to the same level of each course.
MACHINERIES
The machineries that were used on site were brought
into considerations so as to promote high standards
required particularly in the context of structural
engineering works. Machineries are used on site to
eliminate heavy manual work thus reducing fatigue
and as a consequence increasing productivity. Such
machineries that were used include;
8
1. Maximum output required (m3/ hour).
2. Total output required (m3).
3. Type or method of transporting the mixed concrete.
4. Discharge height of mixer (compatibility with transporting method).
Poker Vibrator: This consist of a hollow steel tube casing in which is a rotating
impellor which generates vibrations as its head comes into contact with the casing.
It is immersed in fresh concrete to provide compaction through gentle agitation.
9
to induce the desired vibration to the mix placed in the mould in order to
enhance the strength of the blocks.
3.2 CONCRETING
10
1. Material Supply and Storage: This is the receiving on site of the basic
materials namely cement, fine aggregate and coarse aggregate and storing
them under satisfactory conditions.
After 21 days the formwork are removed completely to enhance the full
setting of the reinforced concrete floor.
Hence, concreting was carried out on almost all the construction work
during my period of attachment.
12
3.3 SETTING OUT
Refers to the act of measuring and marking out a full size plan of a building or element of
a building on site. This is accomplished by transferring the architectural details from
paper to the ground.
13
3.4 BLOCKWORK
The walling system was mostly carried out using sandcrete hollow blocks.
The sizes of blocks were used in respect to their functions. The 6 inches
blocks were used mostly for internal walls while the 9 inches blocks were
used in load bearing areas and external walling. The bonding process used in
the union of these block is Stretcher Bond; which is when the stretcher faces
of the blocks appear on the front or rear elevation of the wall.
3.5 LINTELS
16
4.0 PROBLEMS ENCOUNTERED DURING ATTACHMENT
1. Access Road: The access road to the site is extremely poor due to the lack of
drainages and constant passage of heavy vehicles such as trailer and Lorries.
2. Land Pollution: The soil and water of the land is polluted as a result of oil
spillage from trailers and lorries that where formerly abandoned on the land.
The borehole that was sunk by the company was producing water of brownish
color.
3. Nature of Soil: The area of the site appears to be water logged thereby
providing ponds of water in excavated trenches.
4.1 RECOMMENDATION
The following Recommendation is referred to the Establishment I undertook
my SIWES program, my college, Industrial Training Fund and the
Government; in order to improve and enhance the expected results of the
Student Industrial Work Experience Scheme;
1. The Federal Government should establish and promote laws and agencies
that regulate land use to prevent pollution.
17
3. The Federal Government should provide industries and organizations with
incentives to encourage and solicit for their cooperation and contribution to
the programme
4. The management of Fast Approach Konstruction Ltd can create and organise
a special forum for students on attachment, this will help in discovering
students’ potentials and to appropriately use them effectively.
REFERENCES.
18
Essential Elements of Block-work Construction by Udoh Christopher Timothy
(vol.1).
The Construction of Buildings by Barry R. vol.1 & 2 (1971).
Encyclopedia Britannica; Ultimate reference suite (2014).
Oxford English dictionary.
19