All materials and equipment shall be inspected by Quality Control Department prior to shifting to work
site.
The latest revision of the Approved Shop Drawing should be available at the installation area.
Project Engineer / Supervisor will ensure that safety requirements have been complied with and are in
place.
Project Engineer / Supervisor will orient and familiarize all the workers and assistants involved in the
installation regarding relevant approved drawings, technical submittals, installation procedures and
details, acceptance criteria.
Install fire protection systems in accordance with NFPA rulings,listings and manufacturers
recommendations.
Thoroughly clean the pipe surfaces with damp cloth and let dry the surface. In case, if any foreign
materials remain on the surface, which cannot be cleaned by damp cloth, then use a mild wire brush to
remove the same. If pipe surface is contaminated with oily material, then use a washing solvent. Avoid
scratching and damaging the galvanized surfaces
For pipe sizes of 2” and below, thread the pipe end using the standard threading machine having BSPT
dies. The threading machine will be inspected daily before starting the work. Scale, slag, dirt, and debris
will be removed from the pipe and fittings before machining process.
The pipes will be cut to the actual required length and threaded from both sides. The pipe will be tapered
and the threads will be cleaned using steel brush and file. All threading residuals will be removed to
restore full inside diameter.
Pipe Jointing
The joint compound will be applied on the ale portion of the thread for fitting assembly. The branches will
be either assembled at the fabrication workshop or on installation spot. The pipes will be hanged to the
proper level and will be connected to the cross-main. Pipe work will be protected from foreign matters.
The branch lines will be hanged to the proper level and will be connected to the cross main. Where piping
is embedded or passing through masonry or concrete, sleeves will be provided as per specification mostly
of GI material.
Clean internally the pipes during construction and installation.
Provide clearance for access to valves.
Anchors, expansion joints, swing joints and/or expansion loops shall be provided so that piping may
expand and contract without damage to itself, equipment or the building. Expansion / Contraction joints
will be provided wherever is applicable as per the approved shop drawings.
Apply the PTFE tape only to the male portion of the sprinkler and install the upright sprinkler head using
the wrench provided by the manufacturer, and in such a way that the arms are parallel to the branch
pipe. Maintain a clearance of 1” between the deflector of upright sprinkler and ceiling. Ensure that
sprinkler heads have the correct finish and temperature rating.
Fix the sprinkler floor control valve as per the approved shop drawing. Ensure that valves are located at
an accessible location. Ensure that the arrow of the water flow detector switch points to the direction of
the water flow.
Ensure that the sight glass of the test / drain valve is free of damage.
Ensure that test / drain valves are provided as shown on the drawings.
Attach the pressure pump to the desired location through an isolation valve, by pass valve and calibrated
pressure gauge to indicate the pressure on the pipe work.
The drain point will be plugged and the highest point of the system will be considered as the water supply
point for pressure testing. The selected supply point will be provided with an isolation valve, calibrated
pressure gauge and manual water pump.
Fill the pipe with water and connect the test pump to the pipe work at the filling location, bleed all air
from the pipe work.
Connect a calibrated and approved pressure gauge and fix an isolation valve just below the pressure
gauge.
Apply pressure gradually until it reaches the test pressure. The test pressure will be as per agreed terms
and as per Civil Defence requirements.
Hold the piping under pressure for duration of 2hours and observe for any leakage or pressure drop, if
the pressure gauge shows a steady reading after 2 hours; notify the client/consultant and get the test
witnessed by the consulting engineer.