0% found this document useful (0 votes)
261 views4 pages

Job Order Cost Sheet

The document contains cost summaries for 4 jobs from BSU Manufacturing Company to produce chairs, tables, doors, and cabinets. It lists material costs, direct labor costs, and factory overhead for each job, as well as total costs, markups, and selling prices. The chair order for ABC was completed with a total cost of $34,000 and selling price of $44,200 after a 10% markup. The table order for DEF had total costs of $32,000 but was not yet sold.

Uploaded by

Jasmine Acta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
261 views4 pages

Job Order Cost Sheet

The document contains cost summaries for 4 jobs from BSU Manufacturing Company to produce chairs, tables, doors, and cabinets. It lists material costs, direct labor costs, and factory overhead for each job, as well as total costs, markups, and selling prices. The chair order for ABC was completed with a total cost of $34,000 and selling price of $44,200 after a 10% markup. The table order for DEF had total costs of $32,000 but was not yet sold.

Uploaded by

Jasmine Acta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

BSU Manufacturing Company

For: ABC Job Order No.


Product: chairs Specification:
Quantity: 250 pcs

Material Costs Direct Labor Costs Factory Overhead


Date Amount Date Amount Date
Beginning 9,000.00 Beginning 6,000.00 October
October 2,500.00 October 3,000.00

Cost Summary:
Material Costs ₱ 11,500.00 Cost per unit
Direct Labor Costs: ₱ 9,000.00 Selling price per uni
Factory Overhead: ₱ 13,500.00 Sales
Total Costs ₱ 34,000.00
Add: Mark up ₱ 10,200.00
Selling Price ₱ 44,200.00

BSU Manufacturing Company

For: DEF Job Order No.


Product: tables Specification:
Quantity: 50 pcs

Material Costs Direct Labor Costs Factory Overhead


Date Amount Date Amount Date
October 12,000.00 October 8,000.00 October

Cost Summary:
Material Costs ₱ 12,000.00 Cost per unit
Direct Labor Costs: ₱ 8,000.00 Selling price per uni
Factory Overhead: ₱ 12,000.00 Sales
Total Costs ₱ 32,000.00
Add: Mark up ₱ 9,600.00
Selling Price Not yet sold

BSU Manufacturing Company

For: GHI Job Order No.


Product: doors Specification:
Quantity: 21 pcs

Material Costs Direct Labor Costs Factory Overhead


Date Amount Date Amount Date
October 25,000.00 October 10,000.00 October

Cost Summary:
Material Costs ₱ 25,000.00 Cost per unit
Direct Labor Costs: ₱ 10,000.00 Selling price per uni
Factory Overhead: ₱ 15,000.00 Sales
Total Costs ₱ 50,000.00
Add: Mark up
Sales Not yet sold

BSU Manufacturing Company

For: JKL Job Order No.


Product: cabinets Specification:
Quantity: 50pcs

Material Costs Direct Labor Costs Factory Overhead


Date Amount Date Amount Date
October 18,000.00 October 5,000.00

Cost Summary:
Material Costs ₱ 18,000.00 Cost per unit
Direct Labor Costs: ₱ 5,000.00 Selling price per uni
Factory Overhead: Not yet completed Sales
Total Costs Not yet completed
Add: Mark up
Selling Price Not yet sold
A15
Wood

Factory Overhead
Amount
13,500.00

136.00
176.80
44,200.00

B18
Wood

Factory Overhead
Amount
12,000.00

1,523.81
Not yet sold
Not yet sold

B19
Wood
Factory Overhead
Amount
15,000.00

2,380.95
Not yet sold
Not yet sold

C11
Wood

Factory Overhead
Amount

Not yet completed


Not yet sold
Not yet sold

You might also like