Estimate Ilaya FC

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 12

LEGACY CONSTRUCTION CORPORATION /

EMQ DESIGN & CONSTRUCTION JOINT VENTURE


Calasiao, Pangasinan

SUMMARY OF MATERIALS
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

SUMMARY OF QUANTITIES

ITEM NO. DESCRIPTION UNIT QTY UNIT COST AMOUNT


PART A FACILITIES FOR THE ENGINEER
Provision of Combined Field Office, Laboratory and Living Quartes
A.1.1(6) building for the engineers (Rental Basis) mos. 10.67 ₱ 16,499.70 ₱ 176,051.80

A.1.1(11) Provision of Furnitures/Fixtures, Equipment and Appliances for the


Field Office for the Engineer ls 1.00 ₱ 226,891.50 ₱ 226,891.50

Sub-Total ₱ 402,943.30

PART B OTHER GENERAL REQUIREMENTS


B.4(1) Construction Survey and Staking km. 0.91 ₱ 109,998.00 ₱ 100,098.18
B.5 Project Billboard/Signboard each 2.00 ₱ 4,195.82 ₱ 8,391.64
B.7(1) Occupational Safety Health Program mos. 10.67 ₱ 32,034.17 ₱ 341,804.59
B.9 Mobilization/Demobilization ls 1.00 ₱ 400,761.64 ₱ 400,761.64
B.13 Additional Geotechnical Investigation ls 1.00 ₱ 109,998.00 ₱ 109,998.00
Sub-Total ₱ 961,054.05

PART C EARTHWORKS
101(6) Removal of Structure and Obstruction (Concrete) cu.m. 252.35 ₱ 1,406.18 ₱ 354,849.52
Sub-Total ₱ 354,849.52

PART I-A EARTHWORKS


1701(1) Unsuitable Excavation cu.m. 1,183.00 ₱ 290.85 ₱ 344,075.55
1702(1)a Structure Excavation cu.m. 3,402.00 ₱ 280.26 ₱ 953,444.52
1704(1)b Embankment from Borrow cu.m. 2,522.50 ₱ 1,163.36 ₱ 2,934,575.60
Sub-Total ₱ 4,232,095.67

PART I-B BANKS AND SLOPE PROTECTION WORKS


1710(2)a Grouted Riprap (Class A) cu.m. 1,008.16 ₱ 3,190.16 ₱ 3,216,191.71
1713(1) Rubble Concrete cu.m. 1,729.00 ₱ 3,792.55 ₱ 6,557,318.95
1714(2) Mattresses cu.m. 3,402.00 ₱ 2,991.06 ₱ 10,175,586.12
1717(2)a1 Sheet Piles, Steel (Slope Protection) m. 4,000.00 ₱ 4,514.56 ₱ 18,058,240.00
Sub-Total ₱ 38,007,336.78

PART F BRIDGE CONSTRUCTION


404(1)a Reinforcing Steel, Grade 40 kg 3,334.74 ₱ 56.86 ₱ 189,613.32
405(1)a2 Structural Concrete Class A (20.68 MPa) cu.m. 110.00 ₱ 7,846.18 ₱ 863,079.80
Sub-Total ₱ 1,052,693.12

TOTAL ESTIMATED AMOUNT ₱ 45,010,972.44

Submitted by:

ALEX H. ABELIDO
Authorized Managing Officer
LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

PART I - FACILITIES FOR THE ENGINEER


A.1.1(6) - Provision of Combined Field Office, Laboratory and Living Quartes building for the engineers (Rental Basis)
Qty: 10.67 mos.
C. Materials
Project/Materials Engineers lumpsum x 1 x ₱ 155,248.50 = ₱ 155,248.50
Facilities and Laboratory ₱ 155,248.50

Direct Cost ₱ 155,248.50


OCM ₱ 0.00
Profit ₱ 12,419.88
VAT/Taxes ₱ 8,383.42
TOTAL ITEM COST ₱ 176,051.80

UNIT COST ₱ 16,499.70

A.1.1(11) - Provision of Furnitures/Fixtures, Equipment and Appliances for the Field Office for the Engineer
Qty: 1.00 ls
C. Materials
Lumpsum ₱ 200,080.68 = ₱ 200,080.68
₱ 200,080.68

Direct Cost ₱ 200,080.68


OCM ₱ 0.00
Profit ₱ 16,006.46
VAT/Taxes ₱ 10,804.36
TOTAL ITEM COST ₱ 226,891.50

UNIT COST ₱ 226,891.50


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

PART II - OTHER GENERAL REQUIREMENTS


B.4(1) - Construction Survey and Staking
Qty: 0.91 km.
C. Materials
Lumpsum ₱ 88,270.00 = ₱ 88,270.00
₱ 88,270.00

Direct Cost ₱ 88,270.00


OCM ₱ 0.00
Profit ₱ 7,061.60
VAT/Taxes ₱ 4,766.58
TOTAL ITEM COST ₱ 100,098.18

UNIT COST ₱ 109,998.00

B.5 - Project Billboard/Signboard


Qty: 2.00 each
C. Materials
Warning Signs each x 2 x ₱ 3,700.02 = ₱ 7,400.04
₱ 7,400.04

Direct Cost ₱ 7,400.04


OCM ₱ 0.00
Profit ₱ 592.00
VAT/Taxes ₱ 399.60
TOTAL ITEM COST ₱ 8,391.64

UNIT COST ₱ 4,195.82


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

B.7(1) - Occupational Safety Health Program


Qty: 10.67 mos.
A. Labor
Safety Officer 1 x 2,183.40 x ₱ 65.12 = ₱ 142,183.01
First Aider 1 x 2,560.00 x ₱ 51.51 = ₱ 131,865.60
₱ 274,048.61

C. Materials
Safety helmet man-days x 2,560.00 x ₱ 0.25 = ₱ 640.00
Safety globes man-days x 2,560.00 x ₱ 2.77 = ₱ 7,091.20
Safety shoes man-days x 2,560.00 x ₱ 7.67 = ₱ 19,635.20
₱ 27,366.40

Direct Cost ₱ 301,415.01


OCM ₱ 0.00
Profit ₱ 24,113.17
VAT/Taxes ₱ 16,276.41
TOTAL ITEM COST ₱ 341,804.59

UNIT COST ₱ 32,034.17

B.9 - Mobilization/Demobilization
Qty: 1.00 ls
C. Materials
Mobilization/Demobilization Lumpsum = ₱ 381,677.75
₱ 381,677.75

Direct Cost ₱ 381,677.75


OCM ₱ 0.00
Profit ₱ 0.00
VAT/Taxes ₱ 19,083.89
TOTAL ITEM COST ₱ 400,761.64

UNIT COST ₱ 400,761.64


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

B.13 - Additional Geotechnical Investigation


Qty: 1.00 ls
B. Equipment
Lumpsum = ₱ 97,000.00
₱ 97,000.00

Direct Cost ₱ 97,000.00


OCM ₱ 0.00
Profit ₱ 7,760.00
VAT/Taxes ₱ 5,238.00
TOTAL ITEM COST ₱ 109,998.00

UNIT COST ₱ 109,998.00

PART C - EARTHWORKS
101(6) - Removal of Structure and Obstruction (Concrete)
Qty: 252.35 cu.m.
A. Labor
Foreman 1 x 47.46 x ₱ 71.02 = ₱ 3,370.61
Laborer 3 x 47.46 x ₱ 39.73 = ₱ 5,656.76
₱ 9,027.37

B. Equipment
Dump Truck 2 x 47.46 x ₱ 1,337.50 = ₱ 126,955.50
Backhoe w/ Breaker 1 x 47.46 x ₱ 1,481.25 = ₱ 70,300.13
Pay Loader 1 x 47.46 x ₱ 1,587.50 = ₱ 75,342.75
₱ 272,598.38

Direct Cost ₱ 281,625.75


OCM ₱ 33,796.09
Profit ₱ 22,530.08
VAT/Taxes ₱ 16,897.60
TOTAL ITEM COST ₱ 354,849.52

UNIT COST ₱ 1,406.18


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

PART I-A - EARTHWORKS


1701(1) - Unsuitable Excavation
Qty: 1,183.00 cu.m.
A. Labor
Foreman 1 x 63.19 x ₱ 71.02 = ₱ 4,487.75
Laborer 3 x 63.19 x ₱ 39.73 = ₱ 7,531.62
₱ 12,019.37

B. Equipment
Dump Truck 2 x 63.19 x ₱ 1,337.50 = ₱ 169,033.25
Backhoe 1 x 63.19 x ₱ 1,456.25 = ₱ 92,020.44
₱ 261,053.69

Direct Cost ₱ 273,073.06


OCM ₱ 32,771.59
Profit ₱ 21,846.35
VAT/Taxes ₱ 16,384.55
TOTAL ITEM COST ₱ 344,075.55

UNIT COST ₱ 290.85

1702(1)a - Structure Excavation


Qty: 3,402.00 cu.m.
A. Labor
Foreman 1 x 171.94 x ₱ 71.02 = ₱ 12,211.18
Laborer 5 x 171.94 x ₱ 39.73 = ₱ 34,155.88
₱ 46,367.06

B. Equipment
Dump Truck 2 x 171.94 x ₱ 1,337.50 = ₱ 459,939.50
Backhoe 1 x 171.94 x ₱ 1,456.25 = ₱ 250,387.63
₱ 710,327.13

Direct Cost ₱ 756,694.18


OCM ₱ 90,808.30
Profit ₱ 60,540.03
VAT/Taxes ₱ 45,402.00
TOTAL ITEM COST ₱ 953,444.52

UNIT COST ₱ 280.26


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

1704(1)b - Embankment from Borrow


Qty: 2,522.50 cu.m.
A. Labor
Foreman 1 x 161.01 x ₱ 71.02 = ₱ 11,434.93
Laborer 8 x 161.01 x ₱ 39.73 = ₱ 51,175.42
₱ 62,610.35

B. Equipment
Dump Truck 2 x 161.01 x ₱ 1,337.50 = ₱ 430,701.75
Backhoe 1 x 161.01 x ₱ 1,456.25 = ₱ 234,470.81
Water Truck 1 x 161.01 x ₱ 1,012.50 = ₱ 163,022.63
Plate Compactor 1 x 161.01 x ₱ 120.00 = ₱ 19,321.20
₱ 847,516.39

C. Materials
Embankment Materials
(25% shrinkage Factor) cu.m. x 3,153.13 x ₱ 450.00 = ₱ 1,418,906.25
₱ 1,418,906.25

Direct Cost ₱ 2,329,032.99


OCM ₱ 279,478.96
Profit ₱ 186,322.64
VAT/Taxes ₱ 139,741.02
TOTAL ITEM COST ₱ 2,934,575.60

UNIT COST ₱ 1,163.36


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

PART I-B - BANKS AND SLOPE PROTECTION WORKS


1710(2)a - Grouted Riprap (Class A)
Qty: 1,008.16 cu.m.
A. Labor
Foreman 1 x 537.66 x ₱ 71.02 = ₱ 38,184.61
Skilled Worker 2 x 537.66 x ₱ 51.51 = ₱ 55,389.73
Laborer 10 x 537.66 x ₱ 39.73 = ₱ 213,612.32
₱ 307,186.66

B. Equipment
One Bagger Mixer 1 x 537.66 x ₱ 156.25 = ₱ 84,009.38
Water Truck 1 x 190.00 x ₱ 1,012.50 = ₱ 192,375.00
₱ 276,384.38

C. Materials
Cement bags x 2,521.00 x ₱ 260.00 = ₱ 655,460.00
Sand cu.m. x 480.00 x ₱ 700.00 = ₱ 336,000.00
Gravel cu.m. x 75.00 x ₱ 800.00 = ₱ 60,000.00
Weep Holes (PVC) ln.m. x 600.00 x ₱ 150.00 = ₱ 90,000.00
Filter Cloth sq.m. x 80.00 x ₱ 290.00 = ₱ 23,200.00
Boulders cu.m. x 1,058.30 x ₱ 760.00 = ₱ 804,308.00
₱ 1,968,968.00

Direct Cost ₱ 2,552,539.04


OCM ₱ 306,300.68
Profit ₱ 204,203.13
VAT/Taxes ₱ 153,148.86
TOTAL ITEM COST ₱ 3,216,191.71

UNIT COST ₱ 3,190.16


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

1713(1) - Rubble Concrete


Qty: 1,729.00 cu.m.
A. Labor
Foreman 1 x 800.00 x ₱ 71.02 = ₱ 56,816.00
Skilled Worker 2 x 800.00 x ₱ 51.51 = ₱ 82,416.00
Laborer 10 x 800.00 x ₱ 39.73 = ₱ 317,840.00
₱ 457,072.00

B. Equipment
One Bagger Mixer 1 x 800.00 x ₱ 156.25 = ₱ 125,000.00
Water Truck 1 x 250.00 x ₱ 1,012.50 = ₱ 253,125.00
Backhoe Wheel Type 1 x 250.00 x ₱ 937.50 = ₱ 234,375.00
₱ 612,500.00

C. Materials
Cement bags x 5,187.00 x ₱ 260.00 = ₱ 1,348,620.00
Sand cu.m. x 805.00 x ₱ 700.00 = ₱ 563,500.00
Gravel cu.m. x 590.00 x ₱ 800.00 = ₱ 472,000.00
Weep Holes (PVC) ln.m. x 856.00 x ₱ 150.00 = ₱ 128,400.00
Filter Cloth sq.m. x 250.00 x ₱ 290.00 = ₱ 72,500.00
Boulders cu.m. x 2,038.98 x ₱ 760.00 = ₱ 1,549,624.80
₱ 4,134,644.80

Direct Cost ₱ 5,204,216.80


OCM ₱ 624,510.52
Profit ₱ 416,337.34
VAT/Taxes ₱ 312,254.29
TOTAL ITEM COST ₱ 6,557,318.95

UNIT COST ₱ 3,792.55


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

1714(2)- Mattresses
Qty: 3,402.00 cu.m.
A. Labor
Foreman 1 x 757.76 x ₱ 71.02 = ₱ 53,816.12
Skilled Laborer 2 x 757.76 x ₱ 51.51 = ₱ 78,064.44
Laborer 6 x 757.76 x ₱ 39.73 = ₱ 180,634.83
₱ 312,515.38
C. Materials
Mattresses (6m x 2m x 0.3m) pc x 958.00 x ₱ 5,000.00 = ₱ 4,790,000.00
Boulders cu.m. x 3,912.30 x ₱ 760.00 = ₱ 2,973,348.00
₱ 7,763,348.00

Direct Cost ₱ 8,075,863.38


OCM ₱ 969,102.61
Profit ₱ 646,069.07
VAT/Taxes ₱ 484,551.06
TOTAL ITEM COST ₱ 10,175,586.12

UNIT COST ₱ 2,991.06

1717(2)a1 - Sheet Piles, Steel (Slope Protection)


Qty: 4,000.00 m.
A. Labor
Foreman 1 x 360.00 x ₱ 71.02 = ₱ 25,567.20
Skilled Laborer 2 x 360.00 x ₱ 51.51 = ₱ 37,087.20
Laborer 4 x 360.00 x ₱ 39.73 = ₱ 57,211.20
₱ 119,865.60

B. Equipment
Crawler Crane 1 x 360.00 x ₱ 1,500.00 = ₱ 540,000.00
Vibro Hammer (Hydraulic Operated) 1 x 360.00 x ₱ 2,087.50 = ₱ 751,500.00
Welding Machine 1 x 133.45 x ₱ 318.75 = ₱ 42,537.19
Cutting Outfit 1 x 133.45 x ₱ 375.00 = ₱ 50,043.75
₱ 1,384,080.94
C. Materials
Steel Sheet Pile lumpsum = ₱ 12,828,000.00
₱ 12,828,000.00

Direct Cost ₱ 14,331,946.54


OCM ₱ 1,719,822.58
Profit ₱ 1,146,555.72
VAT/Taxes ₱ 859,915.15
TOTAL ITEM COST ₱ 18,058,240.00

UNIT COST ₱ 4,514.56


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

PART F - BRIDGE CONSTRUCTION


404(1)a - Reinforcing Steel, Grade 40
Qty: 3,334.74 kg
A. Labor
Foreman 1 x 23.80 x ₱ 71.02 = ₱ 1,690.28
Skilled Laborer 2 x 23.80 x ₱ 51.51 = ₱ 2,451.88
Laborer 4 x 23.80 x ₱ 39.73 = ₱ 3,782.30
₱ 7,924.45

B. Equipment
Bar Cutter 1 x 8.00 x ₱ 193.75 = ₱ 1,550.00
Bar Bender 1 x 8.00 x ₱ 306.25 = ₱ 2,450.00
Cargo Truck 1 x 8.00 x ₱ 1,187.50 = ₱ 9,500.00
₱ 13,500.00

C. Materials
Reinforcing Steel Bar (Grade 40) kgs x 3,334.74 x ₱ 37.00 = ₱ 123,385.38
Tie Wire cu.m. x 81.00 x ₱ 70.00 = ₱ 5,670.00
₱ 129,055.38

Direct Cost ₱ 150,479.83


OCM ₱ 18,065.58
Profit ₱ 12,038.39
VAT/Taxes ₱ 9,029.53
TOTAL ITEM COST ₱ 189,613.32

UNIT COST ₱ 56.86


LEGACY CONSTRUCTION CORPORATION /
EMQ DESIGN & CONSTRUCTION JOINT VENTURE
Calasiao, Pangasinan

DETAILED ESTIMATE
FOR
Construction of Ilaya Flood Control Structure, Sta. Maria, Romblon
Tablas Island Romblon

405(1)a2 - Structural Concrete Class A (20.68 MPa)


Qty: 110.00 cu.m.
A. Labor
Foreman 1 x 88.00 x ₱ 71.02 = ₱ 6,249.76
Skilled Laborer 2 x 88.00 x ₱ 51.51 = ₱ 9,065.76
Laborer 3 x 88.00 x ₱ 39.73 = ₱ 10,488.72
₱ 25,804.24

B. Equipment
One Bagger Mixer 1 x 88.00 x ₱ 156.25 = ₱ 13,750.00
Concrete Vibrator 1 x 88.00 x ₱ 37.50 = ₱ 3,300.00
Water Truck 1 x 24.00 x ₱ 1,012.50 = ₱ 24,300.00
₱ 41,350.00

C. Materials
Good Lumber bd.ft. x 1,030.00 x ₱ 45.00 = ₱ 46,350.00
Marine Plywood (1/2" x 4' x 8') pcs x 350.00 x ₱ 810.00 = ₱ 283,496.50
Assorted CWN kgs x 70.00 x ₱ 75.00 = ₱ 5,250.00
Cement bags x 749.00 x ₱ 260.00 = ₱ 194,736.50
Sand cu.m. x 40.00 x ₱ 700.00 = ₱ 27,996.50
Gravel(Crushed) cu.m. x 75.00 x ₱ 800.00 = ₱ 60,000.00
₱ 617,829.50

Direct Cost ₱ 684,983.74


OCM ₱ 82,198.05
Profit ₱ 54,798.70
VAT/Taxes ₱ 41,099.31
TOTAL ITEM COST ₱ 863,079.80

UNIT COST ₱ 7,846.18

TOTAL ESTIMATED AMOUNT ₱ 45,010,972.44

Submitted by:

ALEX H. ABELIDO
Authorized Managing Officer