Chapter 1. Introduction: 1.1. Background
Chapter 1. Introduction: 1.1. Background
Chapter 1. Introduction: 1.1. Background
CHAPTER 1. INTRODUCTION
1.1. BACKGROUND
By implementing lean practices in the process industry, which has been making
automobile tyre valves for decades, this project explains how performance can be
improved. Throughout the world, Lean Manufacturing has been a concern and issue for many
manufacturing companies. The processes leading up to lean manufacturing have greatly
influenced this, such as interchangeable parts, just-in-time production, the Assembly line, and
the Toyota Production System.
Eli Whitney, the inventor of interchangeable parts, is regarded as the originator of the
early lean concepts. Henry Ford introduced the assembly line in the 1900s, which allowed
rapid production of automobiles. Technology has advanced since then, which has led to faster
production times and a reduction of ineffective materials. Since Eli Whitney created
replaceable parts, lean manufacturing has grown as shown in the chronology below, after
World War II in the 1930s Japanese automobile companies were facing shortages of material,
financial, and manpower leads the formulation of lean concepts. Toyota's Toyota Production
System was invented by Eiji Toyoda and Taiichi Ohno after learning Ford's flow of
production concept. As a result of this new system, the focus has shifted from the use and
utilization of individual machines to the workflow in the overall process. Since then to meet
customer needs, Toyota aims to reduce production costs, improve product quality, and speed
up the production cycle to reduce costs and increase quality. In its design, the process
includes the following steps: sizing of the machines to cater to the required volume,
incorporation of self-regulating features so that quality can be enhanced, sequencing the
machines according to the process, creating quick steps so that multiple parts can be
manufactured incomparably small quantities, and communicating the requirements of the
parts between the steps.
major milestone in the implementation of Lean was the TPS. "Lean Thinking: Banish Waste
and Create Wealth in Your Corporation", by James P. Womack and Daniel T. Jones, lays out
the fundamentals of the Lean Philosophy in ways that can be understood (Cholewicka-
Godzik K, 2001) is the early theoretical works about lean. Traditionally, Lean Manufacturing
is considered the successor to Total Quality Management. Previously, Toyota developed
these instruments, the company has also been assigned five principles for better functioning
by establishing patterns for the company. Moreover, five principles have been added to
establish the patterns for the company's better functioning (Lukasz Dekier, 2012). These five
principles were aimed to determine the product's value from a client's perspective. Identifying
and clarifying the product value stream. Providing an uninterrupted value stream. Clients
being able to identify the value a producer can provide, and Aiming for excellence.
The company requires a support system to cope with increased production requirements.
Aside from the newly adopted digital kanban system, the company seeks an integrated
solution to reduce inventory, increase material tracking and visibility, as well as eliminate
paper-based processes.
Improving the operations by reducing lead times and automating manual processes.
Tracking materials during processing operation to ensure better visibility, the material
Bar-coding and eKanban systems facilitate the process.
Using the Kanban principle to reduce overall inventory and an electronic Kanban system
to manage inventory and drive procurement.
Make it easier for parts to be located in multiple locations.
Improve the flow of products by redesigning the current layout structure.
Install a proactive alert system for nonconforming part numbers and products.
Identifying and grouping elements to determine distribution frequency, as well as It is
necessary to make arrangements with suppliers.
Link information with barcodes to improve material management directly to the
enterprise resource planning (ERP).
Remove no longer required materials from the site.
mapping is first used to map the current process, states to determine which ones need to be
modified using lean principles. Waste is then identified and reduced using lean tools. Lean
tools are applied to all of these systems to develop future state maps. In addition to reducing
production lead times, transportation, inventory, and prices, changes in production result in
improved space utilization, increased labour productivity, and increased production.
and other areas of the firm, as well as factors external to the company(3). Adopting lean
manufacturing as an integrated concept involves several factors or key areas.
Manufacturing in India has become a favourite destination on the global
stage(4). Having become an international manufacturing hub has not only opened up many
opportunities but also forced Indian process industries to face heightened competition, both
local and global. Several challenges must be met by these industries if they are to remain
competitive in the global marketplace. In manufacturing, two prominent challenges are
improving efficiency and improving performance in the supply chain. Another challenge is
improving quality. Furthermore, (5) the inventory turns in Indian process industries are low,
resulting in tied-up working capital for a longer period. Indian process industries also have
problems related to equipment, including a high number of rework and rejections, frequent
breakdowns, and high accident rates. Process industries consume a high amount of energy
due to their inherent characteristics(6).
In addition, India's high energy costs exacerbate the problem. Thus, process
industries are securing methods to reduce their energy consumption. For the Indian process
industry to remain globally competitive and to increase profitability and productivity, it must
achieve operational excellence and restructure its operations. As a result, the need to supplant
antiquated production methods with 21st-century manufacturing methodologies, such as lean,
has been argued for and is being observed in process industries (7). (8) emphasize that lean
aims to reduce production costs by eliminating non-value-adding activities. Lean is useful for
improving both processes and customer services. Lean manufacturing ranks high in the
manufacturing management literature as one of the most effective modern management tools
for dealing with contemporary competitive challenges. (9) demonstrate that lean adoption can
enhance operational, financial, and environmental performance. Several reports suggest that
lean practices have been adopted in the Indian process Nevertheless, lean adoption is not
encouraging. Several published papers describing the benefits of lean have presented
conflicting information on adopting it as a process in Indian process industries.
Second, case studies dominate the literature on lean implementation in process
industries. It is rare to find empirical studies that examine the implementation of lean in
process industries (10). Similarly, although there are prior published case studies on the
implementation of lean in Indian process industries, their scope is confined to a particular
firm or a particular type of process (11) (12). Therefore, their results cannot be generalized.
Additionally, process industries often have different characteristics than discrete industries,
Dept. of I & P Engg NIE, Mysore 8
Enhancing Quality and Productivity through Lean Strategies in the Automobile Industry with
the Help of Value Stream Mapping 2020-21
making the adoption of lean thinking more difficult (13). (14) it is important to carry out lean
practices carefully in each distinctive industry setting. Due to the inseparable nature of the
product, many of the lean practices such as kanban, pull systems, and cellular manufacturing
are challenging to implement and can be unproductive in the process. (15) observed that
national cultures can contribute to the successful implementation of new manufacturing
techniques. National culture can also influence the adoption of lean practices.
Using selected performance improvement metrics from Indian process industries, this
study attempts to quantify the impact of lean practices. To investigate the causal relationships
between performance improvement and the adoption of lean practices, a multivariate
statistical analysis is used. Through exploratory factor analysis, the lean practices are grouped
into higher-level, lean constructs. A similar clubbing is found with performance measures. To
develop statistical models for analysing the causal relationship between lean constructs and
performance improvement, multiple linear regression analysis is conducted between lean
constructs and performance constructs. An in-depth analysis of the results, as well as insights
regarding the implications of the research for theory and management, is presented.
Reference
(1) Shah and Ward, 2003 “Lean manufacturing: context, practice bundles, and performance”,
Journal of Operations Management”, 21, pp. 129-149.
(1) Sanchez and Perez, 2001; Karlsson and Ahlstrom, 1996 “Assessing changes towards lean
production”, International Journal of Operations & Production Management”, 16, pp. 24-41.
(3) Womack, J.P., and D. T. Jones. 1996. “Lean Thinking: Banish Waste and Create Wealth
in Your Corporation. New York: Simon and Schuster”, 48, pp. 1-8.
(4) Panizzolo, R., Garengo, P., Sharma., M.K., and A. Gore. 2012. “Lean manufacturing
in developing countries: evidence from Indian SMEs.” Production Planning & Control,
23(10-11), pp.769-788.
(5) Dogra, M., Sharma, V.S., Sachdeva, A., and J.S. Dureja. 2011. “TPM-a key strategy
for productivity improvement in the process industry.” Journal of Engineering Science and
Technology, 6(1), pp. 1-6.
(6) Wesseling, J.H., Lechtenböhmer, S., Åhman, M., Nilsson, L.J., Worrell, E. and
Coenen, L., 2017. The transition of energy-intensive processing industries towards deep
decarbonization: characteristics and implications for future research. Renewable and
Sustainable Energy Reviews, 79, pp.1303-1313.
(7) Mathur, A., Mittal, M.L., and G.S. Dangayach.2012. “Improving productivity in
Indian SMEs.” Production Planning & Control, 23(10-11), pp. 754-768.
(8) Doolen, T.L. and Hacker, M.E., 2005. “A review of lean assessment in organizations: an
exploratory study of lean practices by electronics manufacturers”, Journal of Manufacturing
Systems, 24, pp. 55-67.
(9) Gupta, V., Acharya, P., and M.. Patwardhan. 2013. “A strategic and operational
approach to assess the lean performance in radial tire manufacturing in India: A case-based
study”. International Journal of Productivity and Performance Management, 62(6), pp. 634-
651.
(10) Ghosh, M. 2012. “Lean manufacturing performance in Indian manufacturing plants.”
Journal of Manufacturing Technology Management, 24(1), pp.113-122.
(11) Roy, R.N., and K.K. Guin. 1999.“A proposed model of JIT purchasing in an integrated
steel plant.”International Journal of Production Economics,59(1), pp.179-187.
(12) Gupta, V., Acharya, P., and M.Patwardhan. 2013.“A strategic & operational
approach to assess the lean performance in radial tire manufacturing in India: A case-based
study”. International Journal of Productivity and Performance Management, 62(6), pp.634-
651.
(13) Panwar, A., Jain, R., and A.P.S. Rathore.2015b. “Lean implementation in Indian
process industries- some empirical evidence.”Journal of Manufacturing Technology
Management, 26(1), pp. 131-160.
(14) Panwar, A., Nepal, B.P., Jain, R., and A.P.S. Rathore. 2015. “On the adoption of lean
manufacturing principles in process industries.”Production Planning & Control, 26(7),
pp.564-587.
(15) Cagliano, R., Caniato, F., Golini, R., Longoni, A. and Micelotta, E. 2011. "The
impact of country culture on the adoption of new forms of work organization". International
Journal of Operations & Production Management, 31(3), pp. 297-323.
(16) Rao, P.(2013). "The role of national culture on “best” practices in India: a multiple case
study approach." Journal of Indian Business Research, 5(2), pp.122-143.
(17) Panwar, A., Jain, R., and A.P.S. Rathore.2015b. “Lean implementation in Indian
process industries- some empirical evidence.”Journal of Manufacturing Technology
Management, 26(1), pp. 131-160.
all focused on achieving a particular target, such as waste elimination, quality control,
demand management, or cost reduction. Lean manufacturing is defined by Shah and Ward
(2003) as 22 lean practices. The authors identified several significant lean practices such as
set-up reduction, quick changeover techniques, statistical process control, kanban, supplier
partnership, quality management, total productive maintenance (TPM), fool proof systems,
standard operating procedures, and mixed model production. As described by the author,
Lean practices are divided into four categories: Total Productive Maintenance (TPM), Total
Quality Management (TQM), Human Resource Management (HRM), and Just-in-Time (JIT).
Among the lean practices, 5S and Kaizen should be noted as efforts that provide
general fitness such as agility, resilience, and the ability to deal with changes in an
organization. Based on these lean practices, more technical lean practices can be adapted to
focus on a particular type of performance contribution, such as (Bortolotti et al. 2015). The
data are from (Bortolotti et al. 2015). In Shah and Ward's (2003) lean bundles, HRM and
TPM contain general lean practices aimed at laying a firm foundation for TQM, as well as
JIT practices related to specific types of performance. Furthermore, Bamford et al. (2015)
conclude that not all of the six lean tools must be employed to achieve
improvements. Contrarily, an application of lean philosophy partially within certain operating
constraints can yield dramatic results in terms of operational performance as well.
ultimately reduce the cost of goods and services, therefore resulting in higher profits.
According to Lean theory, wastes should be eliminated or reduced (or "Muda", the
Japanese word for waste) along with the use of activities that add customer value. A
customer's opinion of value is the price he or she is willing to pay for a product or service.
The goal of lean manufacturing is to eliminate waste. The following are some instances of
how industrial companies might use them (Womack et al., 1990; Ohno, 1997; Monden, 1998;
Shingo, 1997; Mid-America Manufacturing Technology Centre, 2000) Materials.
All raw materials must be converted into finished products. Scraps and excess raw materials
should be avoided.
The sources of waste are all interconnected, so getting rid of one can either reduce or
eliminate the sources of waste for others. Time and inventory are likely to be the leading
sources of waste. It is advisable to eliminate or reduce the extent to which finished parts
inventory and work-in-process inventory are held. Inventory reduction leads to the detection
of hidden problems, so immediate action can be taken. A reduction in the production lot size
is one way to reduce inventory.
Preventive maintenance can accomplish this is obvious that inventory reduction reduces
other sources of waste as well. As an example, space that used to be used for inventory can be
used for other purposes, such as increasing the capacity of the facility. Decreased setup times
as a means of reducing inventory also reduces time as a wasteful activity. Another source of
waste is transportation time. It does not add value to a product to move parts from one side of
a facility to the other. The manufacturing process should be streamlined to reduce
transportation times. Utilizing a cellular manufacturing layout is one way to ensure
continuous product flow. Energy waste can also be eliminated in this way.
Cellular organization minimizes non-productive operations by allowing a group of people
to fully devote their time to each cell, thus avoiding excessive human utilization. In addition
to defects, scraps are another source of waste. Eliminating defects and scrap is one way to
improve productivity. Making parts that are fault-free from the start has profound
implications for productivity (Hayes and Clark1966).
3.2.3. JIT-PILLAR
Japanese management philosophy for manufacturing is called Just-in-Time
manufacturing (JIT). Capital, equipment, and labour can be optimized by Just in Time (JIT).
In this approach, production rates are precisely aligned with market demand and the Takt
time to ensure that only the necessary units are manufactured at the appropriate time. As a
result of using smaller buffers (which remove the SafetyNet), problems such as quality
defects become more evident. For production to resume, workers are required to solve the
problem immediately.
3.2.3.1. PRINCIPLES OF JIT-SYSTEM
1- Continuous flow
The primary goal of lean manufacturing is to eliminate bottlenecks, interruptions,
detours, backflows, and waits from the manufacturing process. If this is effectively
implemented, it is possible to shorten the production cycle time by as much as 90%.
2- Pull-production
Just-in-Time (JIT) production, also known as pull production, strives to produce only
what is required at the time it is required. Workstations can only produce what is demanded
by workstations downstream.
3- Production levelling
The levelling procedure entails repeatedly arranging orders and smoothing out the daily
operations. the day-to-day order changes, long-term demand is taken into account.
occurring in the first place; Jidoka is in charge of stopping production. When an abnormal
condition occurs, a machine or operator can be warned promptly. Operations may increase
quality at every level by separating machines and humans for more efficient functioning.
3.2.4.1 PRINCIPLES OF JIDOKA
1- Andon lights& signal quality problems.
A process abnormality is a defect, error, or failure of the machine. Using an Andon, In
a production context, problems are graphically communicated to teams as soon as they occur.
When an irregularity is found, a process should come to a halt. As a result, there will be
fewer flaws.
Figure3.4: Andon
Light
Poka-Yoke refers to methods for verifying quality in-line (rather than merely visual
examination) to ensure that no defective materials make it to the next stage of production. If a
machine generates a defect, production is halted until the problem is resolved. Defective
goods will not make their way downstream and cause bigger problems, maintaining a zero-
tolerance culture for flaws. Any employee, for example, can shut down the Toyota production
line. This holds upstream workers accountable as well.
The addition of value to a product or service is any activity that makes the client feel
better about it.
Storage
Transportation
Excess processing etc.
It indicates that this activity cannot be redesigned, reduced, or eliminated without affecting
the quantity, responsiveness, or quality of the output required by the customer or the
organization. It takes little time to process and add value. The 95% of activities that do not
contribute to the final product should be identified and the time and resources should be
reduced.
Rather than being delivered individually, customer value is generated from the full
package. The matter is complicated, yet ignoring it could result in disgruntled customers and
a loss of brand equity. The value equation is crucial because customers desire value in
addition to the price they are ready to pay.
When processes are mapped, determining which actions provide value to the result is
relatively simple. Products are converted from their raw condition to their final state in the
shortest time and at the lowest cost possible as a result of value-added activities. For an
action to be called value-adding, it must meet three criteria: By moving it downstream, the
product is one step closer to completion.
Taiichi Ohno has spent his career working to eliminate waste from manufacturing
operations (Muda). That's most likely how he discovered he might add value to the
customer's experience. Ohno was able to discover some activities in various work processes
that can be removed. If they are both removed, the company's overall economic performance
may improve.
Fishbone diagrams (Ishikawa) can be used to identify the root causes of these wastes.
Using them can identify the root causes of wastes that appear in a particular value stream, so
you can then apply the appropriate methodology or tool to resolve them.
3.5.1. OVER-PRODUCTION
Overproduction is the production of materials that are no longer needed. Almost
always, large batches are produced faster than their consumption rate (and final shipping
rate). A job shop completes a piece of work that was previously unused since it won't be
needed for the next step in the process. As a result, the product will either sit in a queue
waiting to be finished, or it will sit in a finished goods stock that is not required at present.
There are many reasons for overproduction, such as long setups, poor quality, unreliable
machines, avoiding setups to make performance measures look better, or the desire to keep an
expensive resource available.
Inventory is considered the greatest threat to success, whether in the form of finished
goods or work in progress (WIP). As long as the materials are always available, no focus is
placed on the process, quality, or rate of work. As a result, inventory conceals problems
within the production system. The waste associated with over-production leads to extra
storage space, time spent controlling inventory, spending on goods, the possibility of
damages and obsolescence that prevent these products from being used, and the lengthening
of delivery lead times, to name just a few of the direct costs. Further, having more than is
needed causes indirect waste due to inventory. When processes are not kept in mind,
inventories accumulate. Therefore, process cycling times are well outside of the average.
When inventory is buffered, even great differences in cycle times cannot be noticed until a
continuous line or cell is introduced. To balance the flow with the rate of pulling customers,
equipment must be replaced or great effort must be made. With a large inventory, the
reliability of the machine may also be neglected. If the inventory is low, reliability becomes
extremely important, or everything will come to a screeching halt. In lean factories, 100%
uptime is achieved by implementing 5S, maintaining simple machines, and performing
proper maintenance. The same applies to quality. The source cannot be controlled 100% (as
Shingo explains in Zero Defects), therefore mistakes will always occur. The use of simple,
capable machines and a quick response to problems (at the machine) are also important for
100% defect-free production. A standard work process is essential for smooth operations and
a minimum amount of inventory.
3.5.4. TRANSPORTATION
An operation requires the movement of inventory between operations when the
facility layout is extended over a large area. Therefore, it is another result of overproduction.
In addition, it is caused by arranging production equipment according to its purpose. For a
variety of reasons, primarily to do with the ability to specialize, each type of machine
(stampeding presses, welding machines, injection molding machines, etc.) is placed in its
own "department". Usually, this results in overproduction. An unobstructed flow of
production is impossible with a functional layout. Manufacturers keep all their equipment in a
concentrated factory and using cellular layouts.
Using this method, one operation can be balanced with another, one can provide feedback
to the next about quality, the number of operators can be balanced with the production
demands, and customer service is emphasized. Setting up a focused factory (a small location
with all the equipment required to make the product family), or setting up a cell (a group of
Dept. of I & P Engg NIE, Mysore 25
Enhancing Quality and Productivity through Lean Strategies in the Automobile Industry with
the Help of Value Stream Mapping 2020-21
machines that are laid out in a U-shape) causes overprocessing since the equipment isn’t
matched in output
speed. Aside from reducing facility damage and WIP, eliminating large material handling
equipment offers the option to use narrower aisles, improved safety, and lower costs. The
implementation of Visual Control is much easier, as well, in a focused environment.
3.5.5. Motion
Moving equipment and operators is a waste of time. Operator waste motion includes
bending, walking to pick up or place parts, lifting, and taking multiple steps to reach a
machine interface. During setups, this may include moving around the machine repeatedly to
perform the changeover steps in an unplanned manner. Balance is needed between cells and
focused factories to account for movement, which can significantly increase cycle time.
Using ergonomics, work planning, standardization of work, and 5S, as well as smaller
containers, we can reduce motion waste. When it comes to machinery, wasted motion is
associated with long strokes, "circuits" and other errors that prevent parts from performing
their functions. Often, machines are designed to be versatile. It is associated with functional
layouts to produce batches. A general-purpose machine may work with a wide range of tools.
When viewed from the perspective of continuous flow, waste results.
3.5.6. Scrap
Wasteful activities include scrapping and reworking. Because more material is always
available, and the run can be extended for a short period to produce the quantity required,
scrap is scarce in batch production. Scrap is a serious problem in continuous flow machines
since each rejecting piece means losing a cycle. Hence, a shipment is missed when
production is aligned with the customer's takt. A 100% source inspection is required when
perfect quality is required. In Shingo's example, mistake-proofing is achieved through poka-
yoke (error-proofing). In addition, it relies on maintaining and improving equipment to
become more reliable, as well as simplifying machinery. As well as reducing mistakes and
defects, 5S (especially cleaning and checking) and standardization of work are also
important. It is also possible to reduce scrap and rework by designing for manufacturing and
simplifying the processing. A serious issue is a rework, which has the same impact as scrap.
3.5.7. Waiting
Waiting can take many forms. It is typical for operators to wait for a machine to
complete its cycle or for materials to arrive before they can work on it. Operators, as well as
machines, must load and unload production material. Waiting in batch production facilities is
different from waiting in continuous flow systems, where waiting is wasteful. Batch systems
ensure that the equipment is always operational. All inventories of machines should be
buffered. By assigning operators to specific machines, operators are kept busy. As single-
piece flow progresses, not all machines will be kept busy (equipment is a sunk cost).
It is considered wrong to use a machine that is capable of more. Machines that are kept
running produce too much. Operators should not be left idle, even though keeping them
occupied is important. Each operation is performed by different operators. As you complete
the required work at one station, you move on to the next station after completing the desired
work (for example, within a day or a few weeks). In constructing cells, an operator can
balance the volume of work required with the number of operators, reducing setup time and
improving reliability. It would only take a little effort to operate each machine (e.g., one or
two tiny objects). Extra 5S operations and continuous improvement activities should be
performed with spare time.
what consumers want, how they want their products or services delivered, and the price they
can afford.
5. PURSUE PERFECTION
Wastes are prevented through the achievement of the first four steps: 1) identifying
value, 2) mapping value stream, 3) creating flow, and 4) adopting a pull system. However,
the fifth step of pursuing perfection is the most important among them all. It embeds Lean
thinking and continuous process improvement into the culture of the company. While
delivering products based on consumer needs, every employee should aim for perfection. The
corporation should be a learning organization that is continually looking for ways to improve.
The five Lean principles are used to build an efficient and successful organization.
Lean can help managers identify waste in their firms and give better value to their customers.
Work processes can be improved and a continuous improvement culture formed by adhering
to the concepts.
To decrease or eliminate the waste listed above, lean practitioners employ a set of
tools known as Lean Building Blocks. Although many applications can be utilized on their
own, the majority of them have minimal impact when used alone. Incorrect implementation
might have a negative impact on the total impact. Some of the most common construction
blocks are listed here. The majority of them are equally applicable to service businesses.
The five lean principles listed above should be followed when implementing any lean
tools and techniques.
PDCA is often overlooked as one of the most vital steps. Did implemented solution
work? This is a very serious question, in most cases, it does not, or at least not well enough.
3.7.1.4 ACT
Acts determine what should be done next. A check will determine this. The reason for
a project's failure to achieve targets must be determined. What caused the solution to failing
to work as expected? This will result in another PDCA cycle with a plan to develop a better
or more efficient solution to your problem.
3.7.2. 5s
It is 5S, which is a foundation for an effective lean company, that is known as one of
the most effective tools for continuous improvement. 5S is the first, modular step toward
Dept. of I & P Engg NIE, Mysore 30
Enhancing Quality and Productivity through Lean Strategies in the Automobile Industry with
the Help of Value Stream Mapping 2020-21
serious waste reduction. 5S consists of the Japanese words Seiri (Sort), Seiton (Straighten),
Seiso (Sweep and Clean), Seiketsu(Systemize), and Shitsuke (Standardize). The underlying
concept behind 5S is to look for waste and then try to eliminate it.
A major advantage of organizing items in this manner (i.e. making them readily
accessible) is increased productivity. Diversion of production workers to look for tools,
gauges, production paperwork, fasteners, and so on is the most frustrating form of lost time in
any plant. Hirano's businesses employ a standardized strategy to ensure that things are
prepared in the most convenient position and returned to their proper spot after each use. This
is an important part of Hirano's management style. Workers are accountable for taking care of
their plant components and keeping them clean and neat as part of the Hirano improvement
program. They can also spot possible issues before they have an impact on performance.
3.7.2.1. PHASES OF 5 S
Five major five steps in 5S are: sorting, adjusting, reorganizing, and standardizing. In
addition to these two phases, there are sometimes three others: safety, security, and
satisfaction.
Examine all tools, materials, and other items in the work area and factory. It's a good
idea to keep only the necessities and to get rid of the rest; the process should prioritize objects
based on their needs and put them where they're easy to find. Everything else is stored and
discarded.
3.7.2.1.2. STABILIZING OR STRAIGHTENING OUT (SEITON)
It is essential for everything to have a place and to be in its place. Each item should be
labelled with its proper location. The most often used equipment should be the most
accessible when arranging objects, allowing for optimal productivity.
Workers should not have to bend over and over to get to materials workers should not
have to bend over and over to get to materials. Straightening the flow channel means keeping
tools, parts, supplies, and equipment close to where they'll be used. The notion of seitan
distinguishes 5S from "normal clean-up." This stage is also known as "simplifying."
Ensure that the workspace and all of the process equipment are clean, tidy, and well-
organized. Ensure that the work environment is cleaned and everything is placed back in its
proper position at the end of each shift. Keeping things arranged in this way makes it easier to
maintain things in their proper places. Spills, leaks, and other messes may signal that
equipment or process stages require attention.
Standards must be maintained and reviewed. The previous 4 s's become the new way
of doing things once they've been established. Be careful not to go back into old habits as you
continue to accept this new attitude. Also, consider different options while learning about the
new way. Consider alternate choices as the project investigates the new method. A change in
working style, a new tool, or a new output need can all be detected. Examine the first 4 s's
and make any necessary changes.
3.7.2.1.6. SAFETY
Sometimes a sixth phase, "safety," is added. There is a dispute about whether
inserting this sixth "s" improves safety by openly declaring this objective, or whether
relegating a full safety program to a single item in an efficiency-focused business model
undermines it.
3.7.2.1.7. SECURITY
A seventh phase, security, could be added. The seventh "s" intends to use security as
an investment rather than an expense by identifying and resolving security risks to important
business categories. Fixed assets, materials, human capital, brand equity, intellectual
property, information technology, and assets in transit are all examples of these.
3.7.2.1.8. SATISFACTION
Employee satisfaction, in the eighth place, is responsible for ensuring the long-term
viability of continuous improvement projects. Non-Utilized Intellect, Talent, and Resources
— the eighth waste – can be the most harmful of all.
As a result of line balancing, mass production processes become more productive and
cost-effective. It is recommended that a product be produced within an optimal timeframe. To
ensure that each operation in the line happens within the specified time frame, workers and
workstations are divided equally among them.
A balanced assembly line consists of assigning workers and machines to individual segments
appropriately. Productivity can be increased by reducing idle time.
3.7.2.2.1 STEPS IN ASSEMBLY LINE BALANCING
In this example, line balancing software that uses P-graph algorithms frequently
produces more accurate results. Several factors are considered, including the performance of
machines and employees over several periods. To calculate manually, use this formula:
4. Start assigning tasks to the workstations until the process times are equal
Rearrange tasks with the team to remove excess capacity and bottlenecks. This entails
redistributing workers from workstations with light workloads to workstations with heavy
workloads. As a result, overcrowding at the stations is minimized. Divide the amount of
labour logically across all the operators on a line to maximize equipment use. Takt time
calculations will be required to help you determine workload distribution for optimum
efficiency in meeting customer demand.
Takt time is estimated by comparing the time it takes a skilled worker to complete a
task to the time it takes unmanned machinery. If you execute keg line balance after takt time,
you risk overproduction and waste. When takt time is not fulfilled, however, the effect can be
client frustration and delays.
It's possible to alter the settings connected with machine times, takt time, and set up time if
more balance is required. By modernizing machinery on a balanced basis and training staff,
the cycle time can be greatly shortened. Lean manufacturing also entails reducing overall
labour time and reducing the number of workstations in each division.
When the production process moves one unit at a time at a rate determined by customer
needs, it is known as one-piece flow. Mass production with batches and queues is the
opposite of one-piece flow. Rather than focusing on resource efficiency, one-piece flow
focuses on flow efficiency. With one-piece flow, it is possible to:
Arrange equipment and workstations closer together to reduce travel distance. It must
be close to the end of the process that the process begins. Each step and cycle should be as
short as possible.
HOW TO DESIGN CELLS FOR CELLULAR MANUFACTURING
What will happen next? Wouldn't it be great if everyone was responsible for the upkeep
and maintenance of the production equipment, not just the maintenance crew? Could
maintenance teams focus on more critical projects if operators were trained to perform simple
preventive maintenance activities on their equipment? What if engineers and original
equipment manufacturers (OEMs) modified their designs to make them easier to use and
maintain? These questions led to the invention of the concept of total productive
maintenance.
Reduced production costs; greater output quantity; and shorter lead times are the
primary advantages of Lean manufacturing. In Lean Manufacturing, the following goals are
pursued:
1. Defects and wastage - Reduce defects and unnecessary physical wastage, including
excessive use of raw material inputs, preventable defects, costs associated with reprocessing
defective items, and unnecessary product characteristics that are not required by customers.
2. Cycle Times - Reduce manufacturing lead times and production cycle times by reducing
waiting times between processing stages, as well as process preparation times and
product/model conversion times.
3. Inventory levels - Minimize inventory levels at all stages of production, particularly works-
in-progress between production stages. Lower inventories also mean lower working capital
requirements.
4. labour productivity - Improve labour productivity, both by reducing the idle time of
workers and ensuring that when workers are working, they are using their effort as
productively as possible (including not doing unnecessary tasks or unnecessary motions).
5. Utilization of equipment and space - Use equipment and manufacturing space more
efficiently by eliminating bottlenecks and maximizing the rate of production through existing
equipment, while minimizing machine downtime.
6. Flexibility - Can produce a more flexible range of products with minimum changeover
costs and change over time
4.1. INTRODUCTION
Value Stream Mapping (VSM), also known as Material and Information Flow
Mapping, is a lean manufacturing methodology used to analyse the flow of materials and
information necessary to develop a product or service for a consumer (Wikipedia
contributors). Despite its origins in the TPS, it can also be used in industries where there are
service-related needs, such as logistics, supply chain, software development, and product
development. Waste (any activity that does not contribute to the value of the final product) is
used primarily to identify, demonstrate, and decrease waste. It also creates flows in the
manufacturing process (Value stream mapping - waste visualization). As a result of the value,
VSM can provide companies, it is not only a communication tool but also a strategic planning
tool and a change management tool.
VSMs can be created by simply using paper and pencil; however, more complex maps
are created using computer software such as Microsoft Visio or Microsoft Excel. VSM maps
look somewhat like flow charts and an example of what one looks like can be seen below:
The VSM method visually maps materials and information flow from the time
products arrive as raw materials, through each step of manufacturing, and finally off the
loading dock as finished products. Each step in VSM is broken down into a few steps:
To identify the product, the first step is to choose which product the VSM will focus
on. A VSM, also called a Current State Map (CSM), is drawn after a product has been
decided on. Each step and its parameters are included in this CSM. Cycle times, TAKT time,
Work-In-Progress (WIP), production rate, number of operators, and waiting time are among
the parameters considered. Once all the necessary data has been compiled in the CSM, the
team will assess the current state of affairs. Value Stream Mapping identifies where added
value is created in a manufacturing process, and where non-value-added steps are involved.
The next step is to determine where non-value-added steps or wastes can be eliminated after
assessing current conditions and identifying non-value-added steps. Once these methods are
developed, the Future State Map (FSM), which is a final version of a VSM, can be drawn
without these wastes. To follow the drawn FSM as closely as possible, the last task is to
implement the changes. As a result, lean manufacturing processes will become more efficient
(Emerald Full-Text article: The seven value stream mapping tools.).
In this study, I analysed the flow of valves from order to delivery, and I also examined
waste from previous orders. By making the system more efficient and reducing waste, I
employed lean manufacturing techniques.
A process is the transformation of raw materials into completed items (what is known
as the internal value stream). An operation is an interaction between an operator, a machine,
and materials; a process is an interaction between an operator, a machine, and materials. The
majority of members of an organization are involved in one or more activities. As a result,
many efforts are directed toward improving operations. Rather than optimizing operations
alone, Shingo realized that process improvement could improve the process more. For
example, he said it is better to eliminate transportation than find ways to speed up the flow of
materials. Thus, all operational improvements must be integrated into a larger picture of how
the process should be. Shinzo may not have gotten it quite right. Operators, materials, and
machines interact not only with each other but also with each other to carry out an
operation. While evaluating the process, it is, therefore, crucial to examine the role
information plays in the internal value stream. Customer needs form the basis for product
specifications, manufacturing schedules, pull signals, and delivery instructions.
To increase the efficiency (and profitability) of the value stream, you must understand
the internal value stream. To understand how raw materials are transformed into finished
products, value stream mapping is used, which describes the process using symbols and
numbers.
For most of the time that industry has operated across a broad scale, materials have
been pushed through a series of activities. It is almost as if it is a natural rule of how things
are formed that large quantities have been produced. In their quest for excellence, pride, and
customer service, Shingo and Ohno wanted to bring back the pride, quality, and service of
late 19th-century craftsmanship. Neither the craftsman nor the client knew what they wanted
until it was time for them to create it.
Value streams go to a specific destination as the name implies. Value streams' clients
specify the criteria of this end. Value streams need to be upgraded if they are unable to meet
the needs they were created for. Customers base their purchasing decisions on three simple
criteria: price, quality, and delivery. High quality and a competitive price are essentials in
today's market.
applying Lean tools and practices increases a business' ability to maintain fundamental
operational change. Value Stream Managers provide this leadership.
To effectively manage value streams, one needs to step back and view the entire
process with a broader perspective. Understanding value from the perspective of the
customer, rather than from the perspective of an organization or department. By eliminating
waste throughout the value chain, a Value Stream Manager enhances the ratio of value to
non-value by breaking free of traditional buyer/supplier roles and meeting customer
expectations.
As a result of the Current State Map, each business process and the related queue will
be connected starting with the supplier and ending with the customer. A fundamental rule to
remember is that the entire group should participate in creating the map. Participation by all
participants in the drawing, the debate, and inquiries about "what happens" result in a better
understanding than when only one or two people participate. If there are any existing process
flow charts, they should be ignored and information from the walkthrough should be relied
upon.
To create current and future state maps, data must be of high quality. Gathering good,
actionable data is not always easy. This might take a long time if everything needs to be
measured for the first time. In addition, if no consistent measures are taken, it will be
necessary to gather information from individuals directly associated with the operation,
which is typically unreliable. Be aware that many of the standards and ERP systems are either
out of date or are based on guesses.
When the target state maps are drawn to get an idea about the current state, drawn and
tested, many team members would ask: "Why do we do it that way?"?" and "Isn't it better to
do it another way?" There are numerous options for improvement at this point in the process,
as well as for including a diverse group of people in improvement (kaizen) projects. The fact
that a fully-fledged pull system, designed to meet customer takt time, can be developed at this
point, does not entail that this is necessarily the right step to take next. There are numerous
causes to seek a better version of what now exists but falls short of the ultimate future state.
For starters, an organization may lack the funds, time, or expertise necessary to achieve the
desired future state in a single step. Getting operators to work in cells with new cross-trained
abilities or reducing setup time to less than 10 minutes may be too costly or time-
consuming. More essential, improvement efforts should not obstruct immediate client
service. Getting there in phases is usually the greatest option for businesses. With the
capacity to build and get performance data on any value stream, as stated above, it is possible
to test out improvement ideas that the organization is comfortable with, as well as those that
are both inexpensive and achievable Map’s target maps.
Value stream mapping is a method for reducing lead times, improving product flow,
and eliminating waste (non-value-added procedures or activities) to satisfy customer demand
at the lowest possible cost and with the greatest possible quality. Overproduction,
overprocessing, inventory, motion, scrap, waiting, and transportation are the "seven wastes"
that Lean thinking focuses on. Target maps show which of these wastes can be eliminated
right now and where they can be eliminated. It is simple to circumvent the typical difficulty
of removing waste in an operation where there is no net gain using simulation. This is
because the performance of the redesigned system may be compared to the current state to
determine the impact of the proposed changes. The reduction of WIP and batch sizes will
slowly reveal the problems hidden by a high inventory level. With traditional production
planning and traditional management, companies are rarely able to achieve the levels of
organization and standardization needed for one-piece flow. Before constructing a future state
map of the problems in the current process is identified, the appropriate waste reduction
techniques are to be used to get good results mapped in the future state of the process.
The process boxes that are immediately upstream and downstream of a value stream
should be connected by a process box. A one-piece flow is ideal. A one-piece flow process
can be formed by integrating processes so that a workpiece flows from one process to the
next with no interruptions and no WIP; however, this can only be done for highly
reliable/repeatable processes that can be scaled to run at takt time. A pull system must be
utilized to connect the flow in operations that do not lend themselves to one-piece flow.
Shiingo and Ohno attributed their success in developing TPS to their ability to
reliably reduce changeover times (good part to good part) to an insignificant amount of time.
Shingo called it the "single minute exchange of die", meaning it aimed to reduce the time for
the changeover on large stamping presses used for producing car side panels. The concept
was that in calculating the economic order quantity for a production run, a changeover of
fewer than ten minutes (thus a single minute, or several minutes expressible with a single-
digit) was unimportant. This meant that only what was needed could be produced at a
reasonable cost, regardless of the setup time.
(2) Constant equipment improvement to reduce design and material flaws, and
(3) Preventive and predictive maintenance are used to guarantee that equipment is running at
its best at all times.
4.7.7 SUPPLIERS.
After considering the above concepts for establishing a flow system, the next step is
to figure out how to put them into practice. It has already been established that by choosing a
planning period, each action in the value stream is immediately subjected to lead time
reduction criteria properly execute these concepts, process improvements such as improving
process yield, lowering defects, improving uptime, minimizing change over time, and
eliminating wasted time/motion within processes are necessary.
The next step after analysing the aforementioned notions for creating a flow system is
to figure out how to put them into practice. It has already been shown that selecting a
planning period subjects each step in the value stream to lead time reduction criteria right
away.
Blanking the rods into pieces of the desired length and mixing raw rubber with a
measured amount of chemicals
Extruding the rubber to required dimensions
Machining the core elements
Machining the stem part of the valves
Chemical treatment
Molding the stems with a rubber base or rubber cover
Pickling and buffing
Assembly
Packing
Storage
The next step is to obtain all of the necessary information about the current process
such as routings of parts and subassemblies, demand, set-up time and processing time for
each operation, travel time and material handling costs, labour and machine hour rates,
inventory, etc. Motion time study is used to achieve this. The goal of time and motion study
is to determine more efficient methods of production and to set time standards for specific
operations.
precision of 0.01 minutes using a simple stopwatch. Stopwatch, recording board, observation
sheet, and pencil comprise the observation equipment. Such a study involves the following
steps:
Observe the elements of the job while they are being performed and record the time
Record the time for each element after repeating the measurements a sufficient number
of times.
It also involves determining how many processes there are (which boxes are assigned to
each)
Filling out data boxes, drawing inventory triangles, and tracking inventory
The analysis is depicted in figure 4.2, figure4.5, figure4.6, figure 4.11, figure 4.14, figure
4.16
To identify process inaccuracies, production per shift is compared with full efficiency
of production (calculated for each machine cell based on the cycle time) to determine the
impact of the process inaccuracies. Therefore, by identifying the difference between the
amount of processable and processing parts in a particular machine cell, flaws in the process
can be identified and eliminated.
The parts produced here are small in size, having less cycle time and there are dedicated
numbers of machines to produce each type of valve part, so according to the cycle time
of each machine, the production capacity (no of units produced) per shift /day is
calculated. here the production capacity is considered as units per minute or production
per day.
½ hours for preparation for work (raw material storage, machine cleaning and
preparation)
24000
¿ =4sec/unit
6500
¿ 15units/minutes for peterman Bush
When calculated for each machine the total production is 1735000 units per day
The available time per shift is 450 minutes, no of rods processed 20/shift, the time
required to process each rod 20 minutes, amount of time utilized is = no. of rod
processed * time required process each rod = 20*20= 400 minute, so the total waiting
time of each machine is =available time –time utilized =450-400=50 minutes/shift,150
minutes/day.
The daily production target (shown in table 5.2) is not been achieved as per planning
because process inaccuracies are as follows.
One operator has to run more than one machine in each machine cell, so machines need to
wait for 5-10 minutes whenever materials need to be loaded, so the downtime of each
machine increases.
Intermittent inspection is being done by the machine operator himself so after processing
machines sometimes stay in waiting for material to be loaded till the operator finishes
inspection.
Few machines go idle either because of repair or shortage of operator
Nonrelated workstation between the process limiting the process efficiency
Most of the machines used here are conventional needs more manpower and space
Improper machine cell layout, leading to inaccurate flow and mixing of materials.
Disrupts the ease of material transport and comfort during the work process by having
non-working assets in between each machine cell.
Stocking of raw materials and processed parts unnecessarily results in additional
inventory.
The non-effective layout leaves more space unused.
PROPOSED LAYOUT FOR SOLUTION: The new layout that shows improved machine
cell design and flow is shown below using the sketch up a design tool
Each machine cell is equipped with stage inspection rather than inspecting parts from all
machine cells simultaneously in one stage inspection to avoid mixing, in turn prevents
miss processing, improves quality.
Each work cell is equipped with stage inspection, buffer storage, and separate raw
inventory storage. As a result, poke yoke is installed efficiently to eliminate either
processing of the wrong material or the processing of the material with the wrong process
steps.
PROPOSED SOLUTION: The waiting time of the machines can be reduced if simple line
balancing is adopted.
A machine operator who has to operate six machines simultaneously feeds raw material
one by one while loading one machine with raw material, the other machines then have to
wait for between 5 and 15minutes. Therefore, all the machines wait for 1:30 hours a day
without working.
A B C D E F
By using the Kanban system for the identification, each machine should name and coded
with color, so it's easy to collect the processed part separately without mixing and find
defects in the machine.
If the operator feeds each machine considering the cycle time in ascending order, the
machines with less cycle time will not spend a lot of time waiting, so when the machine
with less cycle time which spends less time in waiting is more productive.
It has conventional, automated, and semiautomated modes of machines that process all
types of parts. Machine cells ( combination of set of machines involves in the production
of a part or product) have to be able to combine all the modes of machines for the
production of each part , it could be possible to combine all modes of machine considering
their cycle time meet annual demand of each part . So, the production efficiency increases
furthermore by the utilization of every machine available.
5.2.2.4. RESULT
A single workstation is designated for inspection and grinding of raw materials, and both
processes are reduced to one. Thus, the processing time is reduced from 4 hours to 2
hours and manpower is reduced from 3 to 2.
To prevent mixing and improving the quality of products, the use of the Kanban
(Naming and color coding) system identifies machines and the material they process.
Improved plant layout and new processing methods increase process efficiency
25000
Revised cycle time ¿
6890
¿3.6sec/unit
¿17.5 units/ minute for peterman Bush
When calculated for each machine total production is 1869000units /day
The available time per shift is 450 minutes, no of rods processed 22/shift, the time
required to process each rod 20 minutes, amount of time utilized is 22*20= 440 minute,
so the total waiting time of each machine is =available time –time utilized =450-440=10
minutes/shift,30 minutes/day. Time utilization increased from 85 to 97 %.
The impact of value stream mapping and other lean tools in the improvement of the process is
proposed with The comparison of the current state map with the future state map as shown in
table 5.3
The core assembly has conventional, automated machines, each of which has a different
cycle time, makes it impossible to achieve the production that planned because there is an
unbalanced flow of materials and processes.
The machine arrangement is not an effective method for achieving the intended result,
requiring more manpower and takes more time in inventory and transport.
Mixing parts results in a failed assembly and wasted product.
There is no one-piece flow between assembly, testing, and packing, which is the main
cause of wastes.
Operators would be able to add more value to the process if machines could be improved
for other operations, such as automated loading and collecting parts.
5.3.1.3. DAILY PRODUCTION DATA UNIT 1(CORE ASSEMBLY AND TUBELESS VALVE ASSEMBLY ) MONTHLY
FORECAST
Types of Available Targe Production Achieve Balance in lakhs Achievable
components machine t in /day d in after
lakhs lakhs implementation
of lean
Remainin achievable In lakhs
g
Regular core 05 60.00 2.07 41.17 18.83 56.85 58.52
The present machine center layout has no one-piece flow its most important way of the
efficient assembly process. Here one operator is operating 3 machines in a conventional
blitz machine cell. as shown bellow
3.Bush&washer assembly
A-L represents the machine name whereas 1,2,3,4 represent the assembly sequence of the
core of the valve but in this case, the machine not being arranged in the sequence is the
main issue, where every time operator has to walk from machine to machine in different
locations is the main source of non-value adding activity.
The poor machining sequence causes mixing.
Needs more operators than required.
Here the materials spend much of their time in inventory and transport, as shown in the
figure below. Assembly, packing, and testing are all performed in different process cells.
There is no one-piece flow, increasing waiting times.
Uncontrollable production due to mixed production.
Within this core assembly, the assembly sequence is 1. pin with a washer, 2. bush with a
washer, 3. bush, and washer assembly with a spring. All of the three previous assemblies
come together to form one at the last assembly.
A combination of all assembly machines is used to create the three machine groups to
provide the one-piece flow of parts. as shown in table 5.5
The combination of four assembly machines is made according to their cycle time to give
balanced production from each three machine cell is shown above is represented as.
OUTCOME:
The layout proposed below is simplified the process by eliminating unwanted workspace.
Machine cell is created for product family to provide one piece flow of the parts hence
travel time of the inventory reduced.
The machines are positioned so that assembly, testing, and packing can be done at one
work cell, resulting in improved productivity and reduced inventory.
The machining center is set up in a way that the operator can operate two or more
machines without spending a lot of time walking between them. So eliminates machine
waiting time.
OUTCOME:
5.3.3.4. RESULT
The impact of value stream mapping and other lean tools in the improvement of the
process is proposed with The comparison of the current state map with the future state map as
shown in table 5.6
The overall efficiency of the process is increased with good results such as
productivity, flexibility to interchange the product, ease of inventory flow, avoid mixing,
reduced waiting time, balanced production, reduction in nonvalue adding activity.
No of operators 35 34 -1
Hereafter the moulding of the valve stem with the base rubber part of the valve has to
go through the surface property enhancement by a chemical treatment process called
pickling. The process inaccuracies are found in the area of picking, buffing, and packing.
The current process flow is not so efficient because of ineffective material transportation,
overprocessing, inaccurate production planning.
Inefficient plant management leading to parts missing and mixing.
Non ergonomically designed work table reducing the productivity of the worker.
Bad material handling results in damage and rejection of valves
Disturbed information flow between the work cell resulting misunderstand and miss
processing
Consuming more manpower than required due to non-productive production methods
such as manual material handling, manual loading, and unloading
The following table shows the production parameters of each machine cell.
The machine cell constructed in the present plant has many flaws causing bottlenecks
in each process.
The non-related work cell (slug rubber processing area) installed between the process
leads to disturbance in the process, material flow, and missing parts.
No effective workflow between machining and inspection due to inefficient
workspace design.
Due to poor visibility, the worker has to spend more time looking for parts in the
inventory store.
No dedicated inventory and sufficient space for each part being processed, causing
parts to mix.
From molding to pickling, there is no direct path for materials to be transferred. They
must transit a long path, which consumes more time of the workers.
Slug rubber processing area installed between pickling and buffing area is disturbing
both processes.
Nonworking inventory consumes a large portion of the space needed for working
inventory.
After plotting the current state map on unit 2, it was discovered that the same
processes like CV and SV buffing inspection, packing were being performed in
different processing stations at two different locations, thereby causing less flexibility
for interconnections and changes.
In addition, the study found that compact workstations lead to quality problems and
less flexibility to change due to lack of kanbanization.
Mixing of products in the in-stock inventory makes it difficult to achieve first-in-first-
out (FIFO).
PROPOSED SOLUTION: By eliminating the flaws in the process outlined above, the
revised layout has been created.
The time and space required to move the valve are reduced, as a result, more space is
saved and operation time is shortened.
Eliminates the mixing of different components.
After installing a new layout as proposed, the space that is freed up is used to store valves
for buffing and inspection, and to pack them up.
There needs to be a storage space adjacent to each machine. To allocate parts easily in
less time, the material transporter should be aware of each machine and part it processes.
So, it’s easy to store the part from previous process avoids mixing and eliminates time
required in finding of the parts at storage and easy achieve FIFO
For identifying the destination machine for each part, a Kanban system of color coding
should be used, as well as the traveling job card of each part should be written with color-
coding of each machine where the part going to be machined.
Outcome:
No need to spend much time in search of material
Avoid mixing of component
Easy to achieve the first in first out (FIFO)
Avoid miss processing
Reduces manpower
Automation of the buffing machine for automatic loading and unloading to the inspection
table with a conveyor system makes the process more productive for the worker.
Outcome:
Operators do not need to spend more time loading and unloading parts. As a result,
inspections are also performed more efficiently because the workers operating time
saved can be used for inspection.
The working table must be ergonomically designed to separate the accepted and rejected
parts at a distance that is reachable from the worker's left or right rather than the top of
the table to facilitate inspection and packing.
Outcome: Increase the workability of the worker, Reduces the damage.
Figure 5.16:
Future State Map
Unit 2
With processing time reduced from 3days to 2&1/2 days. for night shift only 6 hours of 12
hours is considered since the man power is half compared to day shifts
=70000+(49*60*6)
=87000 units/day
SV buffing and inspection =252000+(175*60*6)
=315000units/day
5.3.3.4. RESULT
The impact of value stream mapping and other lean tools in the improvement of the
process is proposed with The comparison of the current state map with the future state map as
shown in table 5.8
No of operators 59 57 -1
Wait time of each machine 1.5hrs 30 min -33.33%
This study indicates that lean approaches have a considerable impact on operational
performance, including inventory management, on-time delivery, waste reduction, demand
management, cost reduction, and productivity enhancement. More crucially, this study backs
up prior findings that lean approaches boost operational performance in process sectors. As a
result, this research clears up any uncertainty.
For each processing plant, the current state map is created, which helped to identify
problems with the process such as lack of one-piece flow, flaws in layouts, and lack of lean
practices in an industry where lean has already been practiced. It is concluded that VSM does
not only help to improve processes but also identifies potential problems in the process
methods practiced today.
In the current operational scenario, the processing is based on the process family
where every product must pass through each processing unit in the plant. The product spends
a lot of time in traveling between the processing unit and being inventoried, resulting in
misprocessing, missing products, and reduced production efficiency. The future of the project
is to break the plant into many processing cells, in which every processing machine the
family goes through is integrated into one cell to implement a one-piece flow process. In the
dedicated processing cell, the raw material is processed from raw to ready-to-use in one flow
without travelling to different processing unit , which would result in increasing production
efficiency and flexibility to demand fluctuation.
BIBLIOGRAPHY
[1] Abdulmalek, F.A. and Rajgopal, J., 2007. “Analysing the benefits of lean
manufacturing and value stream mapping via simulation: a process sector
case study”, International Journal of Production Economics, 107, pp. 223-
236.
[2] Acosta, C., Leon, V. J., Conrad, C., Gonzalez, R., and C. O. Malave. 2004.
“Case study on culture and the implementation of manufacturing strategy in
Mexico.”Journal of manufacturing systems, 23(3), pp. 204-214.
[3] Aggarwal, A. 2002. “Liberalisation, multinational enterprises and export
performance: evidence from Indian manufacturing.” Journal of Development
Studies, 38(3). pp119-137.
[4] Armstrong, J. S., and T. S. Overton.1977. “Estimating non-response bias in
mail surveys. Journal of marketing research, 1, pp.396-402.
[5] Åhlström, P., 1998. “Sequences in the implementation of lean production”,
European Management Journal, 16, pp. 327-334.
[6] Bamford, D., Forrester, P., Dehe, B., and R. G. Leese.2015. “Partial and
iterative Lean implementation: two case studies.” International Journal of
Operations & Production Management,35(5), pp. 702-727.
[7] Ballard, G. and G. A. Howell (2003). "Lean project management." Building
Research and Information, 31(2), pp. 119-133.
[8] Billesbach, T. J. (1994). Applying lean production principles to a process
facility. Production and Inventory Management Journal, 35(3), 40.
[9] Cagliano, R., Caniato, F., Golini, R., Longoni, A. and Micelotta, E. 2011.
"The impact of country culture on the adoption of new forms of work
organization". International Journal of Operations & Production Management,
31(3), pp.297-323.
[10] Cholewicka-Goździk, K. (2001). Metoda LEAN-doskonalenie procesów i
produktów: wokół książki Jamesa P. Womack'a i Daniela T. Jones'a. Problemy
jakości, (1), 21-25.
[11] Cook, R.C., and R.A. Rogowski, “Applying JIT principles to continuous
process
manufacturing supply chains,” Production and Inventory Management Journal,
First Quarter, 1996, PP. 12-16
[12] Danese, P., Romano, P., and. Bortolotti. 2012.“JIT production, JIT supply, and
performance: investigating the moderating effects.” Industrial Management &
Data Systems112(3):441-465.
[13] Dogra, M., Sharma, V.S., Sachdeva, A., and J.S. Dureja. 2011. “TPM-a key
strategy for productivity improvement in the process industry.” Journal of
Engineering Science and Technology 6(1):1-6.
[14] Doolen, T. L., and M. E. Hacker.2005. “A review of lean assessment in
organizations: an exploratory study of lean practices by electronics
manufacturers.”Journal of Manufacturing Systems 24(1):55-67.
[15] Doolen, T.L. and Hacker, M.E., 2005. “A review of lean assessment in
organizations: an exploratory study of lean practices by electronics
manufacturers”, Journal of Manufacturing Systems 24, pp. 55-67.
[16] Flynn, B. B., Schroeder, R. G, and S. Sakakibara.1994. “A framework for
Dept. of I & P Engg NIE, Mysore 88
Enhancing Quality and Productivity through Lean Strategies in the Automobile Industry with
the Help of Value Stream Mapping 2020-21
[29] Hays, R.H., and K.B. Clark, “Why some factories are more productive than
others,” Harvard Business Review, September-October 1986, PP. 66-73
[30] Jaiganesh, V., and J.C. Sudhahar.2013. “Sketching out the hidden lean
management principles in the pharmaceutical manufacturing.”International
Journal of Scientific and Research Publications3(2):1-2.
[31] Karlsson, C. and Åhlström, P., 1996. “Assessing changes towards lean