Technical Specification For 11 KV Packaged Substation
Technical Specification For 11 KV Packaged Substation
Page 1 of 77
SP-PSSC-38-R7
Index
1.0 Scope .................................................................................................................. 7
2.0 Codes & standards.............................................................................................. 7
3.0 Electrical Distribution System Data ..................................................................... 8
4.0 PSS Configuration............................................................................................... 9
5.0 11 kV Ring Main Unit ........................................................................................ 11
6.0 11KV XLPE Cable & termination kit .................................................................. 21
7.0 Oil Type Sealed Distribution Transformer ......................................................... 22
8.0 Dry Type Transformer (1000KVA/ 630KVA/ 400KVA/250 KVA) ....................... 31
9.0 Low Voltage Bus bar system ............................................................................. 39
10.0 Low voltage switchgear, ACB, MCCB & Fuses ................................................. 39
11.0 Automatic Power Factor Correction system ...................................................... 41
12.0 Energy Meter Box ............................................................................................. 43
13.0 Enclosure for packaged substation ................................................................... 44
14.0 Other Provisions: Earthing, Illumination, Hooter & Smoke Detector.................. 46
15.0 Labels & painting............................................................................................... 46
16.0 Approved makes ............................................................................................... 47
17.0 Quality assurance ............................................................................................. 48
18.0 Inspection & testing ........................................................................................... 48
19.0 Shipping, Handling and Site support ................................................................. 51
20.0 Deviations ......................................................................................................... 52
21.0 Drawings Submission ........................................................................................ 52
Annexure A Service Conditions ......................................................................................... 53
Annexure B Technical Specification for transformer oil ..................................................... 54
Annexure C Guaranteed Technical Particulars (Data by Supplier) ..................................... 55
Annexure D CRGO & Testing Points [R7] .......................................................................... 75
Annexure E Recommended spares (Data by supplier) ....................................................... 76
Annexure F BOM for 250 kVA PSS [R7]............................................................................. 77
Page 2 of 77
SP-PSSC-38-R7
Record of Revision
Revision Item / clause Approved
Nature of Change/Clause Descriptions
No no. By
R3 4.2.13, 14.24 Added- 02 no’s Smoke detectors for each compartment DS
R3 5.3.9 LBS short time withstand capacity revised to 20kA for 3 sec DS
Page 3 of 77
SP-PSSC-38-R7
R3 4.2.2, 5.1.1 Requirement of 4 way RMU has been added for PSS type – I DS
7.2.5.1 & Total losses at 50% & 100% load updated as per IS
R4 KKA
7.2.5.2 1180(2014)
Flux density at 10% over excitation changed to 12.5% over
R4 7.2.8 KKA
excitation
Page 4 of 77
SP-PSSC-38-R7
10.2.2 &
R6 MCCB Specifications revised AT/VP
10.2.10-13
R7 9.0 Low Voltage Bus bar system-Bus bar rating of PSS-IV added AT/KS
R7
5.13.0 Special Technical requirement-added AT/KS
Page 5 of 77
SP-PSSC-38-R7
R7 AT/KS
7.2.4 Impedance at 75 deg C for 250 KVA added
R7 AT/KS
7.2.5 Losses at 75 deg C updated and 250 KVA added
R7 AT/KS
7.2.8 Flux density at rated conditions
R7 7.3.5.3 AT/KS
Core Design Features-Type of core added
8.3.1.6
R7 AT/KS
7.3.6.5 Winding Design features-Type of windind added
R7 7.3.10.7 AT/KS
CT ratio for 250 KVA added
8.3.5.6
R7 AT/KS
7.3.11.4 Rated Current for tap Switch for 250 KVA added
R7 8.1.13 AT/KS
8.1.14 E2C2F1 Certification for dry Type DT added
8.1.15
R7 AT/KS
8.2.5 Temperature for losses revised and 250 KVA added
R7 8.2.7 AT/KS
Flux density-maximum value at overfluxing revised
8.3.1.5
R7 AT/KS
8.3.1.4 Design Flux Density at rated conditions at principal tap
R7 AT/KS
18.1 Type test and special test details for transformer added
R7 AT/KS
18.3.2.2 IR value revised
Page 6 of 77
SP-PSSC-38-R7
1.0 Scope
i. Design, manufacture, testing at manufacturer works before dispatch, packing, and delivery
of Packaged Substation (PSS) as per this specification and supply of commissioning
spares.
ii. Supply of all installation/commissioning accessories for PSS.
iii. Submission of documentation of PSS.
iv. Supervision of testing & commissioning of PSS at site.
Materials, equipment and methods used in the manufacture of 11kV Packaged Substation
shall conform to the latest edition of following –
Standard Title
Indian Electricity Rules With latest amendments
Indian electricity act IE act 2003
CBIP manual on transformers
IEC 60076 Power transformers
IEC:60616 Terminal and Tapping Markings for Power Transformers
IEC:60726 Dry-Type Power Transformers
IEC: 60529 Degrees of Protection Provided by Enclosures (IP Code).
IEC:60905 Loading Guide for Dry-Type Power Transformers
IEC 60694 Specification for high voltage switchgear
IEC 60439-1 Low voltage switchgear & control gear assemblies
IEC 60529 Degree of enclosures provided by enclosures
IEC 60664-1 Insulation coordination for low voltage systems
Degree of protection provided by enclosure against mechanical
IEC 62262
shocks
IEC 62271-202 High voltage switchgear & control gear - prefabricated substation
IEC 60044 Instrument transformers - Current & voltage transformers
IEC 60225 Electrical relays
IEC 60625 High voltage switches
IEC 60502 Power cables
IEC 60947-2 Low-voltage switchgear and control gear : Circuit-breakers
Outdoor Type Oil Immersed Distribution Transformers Up to
IS 1180
and Including 2500 kVA, 33kVSpecification [R4]
IS 2026 Power transformers
IS 11171 Dry type transformers
Page 7 of 77
SP-PSSC-38-R7
In the event of direct conflict between various order documents, the precedence of authority of
documents shall be as follows -
i. Guaranteed Technical Particulars (GTP)
ii. Specification including applicable codes & standards
iii. Approved Vendor Drawings
iv. Other documents
Page 8 of 77
SP-PSSC-38-R7
4.2.4 Low voltage bus bar system Insulated /sleeved with epoxy insulators
Page 9 of 77
SP-PSSC-38-R7
Low voltage system 1600A ACB incomer and 07 nos. 400A MCCB
4.2.5
configuration for PSS type-I (utilization category- B) as outgoing.
1600A ACB incomer and 05 nos. 400A MCCB
Low voltage system (utilization category- B) as outgoing. Provisions shall
4.2.6
configuration for PSS type-II also be made in LT panel to increase LT outgoing by
02 no’s by adding MCCB’s in future.
1250A ACB incomer and 03 nos. 400A MCCB
Low voltage system (utilization category- B) as outgoing. Provisions shall
4.2.7
configuration for PSS type-III also be made in LT panel to increase LT outgoing by
02 no’s by adding MCCB’s in future.
Low voltage system 400A ACB incomer and 02 nos. 250A MCCB
4.2.8
configuration for PSS type-IV (utilization category- B) as outgoing. [R7]
Page 10 of 77
SP-PSSC-38-R7
Page 11 of 77
SP-PSSC-38-R7
Page 12 of 77
SP-PSSC-38-R7
5.2.13 Earth bus bar Tinned Copper sized for rated fault duty for 3 sec [R7]
Earth bus internal connection
By 2.5 sq mm copper flexible green PVC wire, Earth
to all
5.2.13.1 connection point maximum 1 meter away from cable
noncurrent carrying metal
test facility
parts
Earth bus external Studs on both sides with holes and with M10 bolt +
5.2.13.2 connection to hardware to readily receive purchaser earth
owners earth connection
5.2.14 Cooling arrangement By natural air without fan
Multi strand flexible color coded PVC insulated Cu
wire 1 sq mm (SCADA) / 2.5 sq mm (for CT’s) 1100
volt grade (R phase - Red, Y phase – Yellow, B phase
5.2.15 Panel internal wiring – Blue, AC- black, DC – grey, Earth – green) with
ferrules at both ends.
All the internal control / auxiliary wiring shall be routed
through proper conduit. [R3]
Hardware (Nut, bolts & Stainless steel (Except termination nut-bolts-washers-
5.2.16
handle) reducer which are Brass / Tinned Copper) [R7]
5.2.17 Gasket Neoprene rubber
1 Sq mm, Nylon 66 material, screw type + 20% spare
5.2.18 Marshalling terminal blocks
in each row of TB.
5.2.19 Panel cover fixing bolts Allen head 6mm with hexagonal slot
5.2.20 Padlock facility Required for all earth switches & all handles
Page 13 of 77
SP-PSSC-38-R7
Arc interruption in
5.3.2 SF6 or Vacuum
dielectric medium
Operating mechanism for
5.3.3 Manual as per enquiry.
close / open
5.3.4 Addition / removal of motor Without overhaul of operating mechanism [R7]
Complete with power & control wiring so that only motor
5.3.5 RMU without motor
can be added at later date
5.3.6 Motor rated voltage NA
5.3.7 Battery type & size a) NA
5.3.8 Continuous rating of LBS 630 Amp at design 40 deg C ambient
5.3.9 Short time withstand capacity 20 KA for 3 sec [R3]
5.3.10 Fault making capacity 50 kA peak [R3]
Minimum number of
Mechanical Endurance – Class M1( 1000 operations)
5.3.11 operations at rated current (as
Electrical Endurance – Class E3 (100 operations) [R3]
per IEC 62271-102)
Minimum number of
operations at rated fault
5.3.12 Class E3 (Min 10 operations) [R3]
current (as per IEC IEC
62271-102 )
Fault passage indicator (FPI) To be provided on incommer side of one LBS for panel
5.3.13 (For both Earth fault and Over type 1CB + 2 LBS. For all other configuration of RMU,
Current Protection) {R7} FPI to be provided on all LBS.
CBCT – Split open type suitable for mounting without
5.3.14 Earth Fault Indicator
disconnection of cable.
Cable connection of FPI with CBCT shall be of pre
5.3.15 Connection of CBCT with FPI moulded type on the CBCT side. Cable shall be 2.5
sq.mm cu PVC insulated cable only. {R7}
Digital type and shall operate as the current exceeds
the set value. Flash indication for identifying faults with
red LED with one flash for every one sec. Test & rest
Fault Passage Indicator
button 1 NO + 1 NC potential free contact for remote
5.3.16 (For both Earth Fault and
indication FPI power supply unit shall use lithium battery
Over Current Protection)
with minimum life of 1000 blinking hours , so that FPI
shall continue to function even after main feeder has
tripped. [R7]
5.3.17 Data by Purchaser [R7]
5.3.17.1 System Fault Level 2kA – 8.75kA
5.3.17.2 Type of Grounding Solidly Grounded
5.3.17.3 Fault clearing time 100ms
Page 14 of 77
SP-PSSC-38-R7
5.3.17.4 Cable Type PILC / XLPE , 11Kv, 3CX150 sq.mm to 400 sq.mm
5.3.18 Earth Fault Indicator
5.3.18.1 Sensing Current 100 to 400A
5.3.18.2 Sensing Time 30 to 100 ms in steps of 10ms.
5.3.18.3 Reset Time 0.5 -1-2-3-4 hr
a) Self rest after reset time
b) Self rest after restoration of voltage
5.3.18.4 Resetting Facility
c) Manual
d) Remote resetting
5.3.18.5 Contact Rating 1A at 230 V
5.3.18.6 Degree of Protection IP 54
5.3.18.7 Mounting Arrangement Surface or Flush Mounting
5.3.18.8 Ambient Temperature -0 to 50 Deg C
5.4.0 Circuit breaker [R7]
Three pole, operated simultaneously by a common
5.4.1 Type
shaft
Transformer circuit breaker -
5.4.2 For controlling transformer, manual operation only
TCB
For controlling cable feeder, manual operation.
5.4.3 Feeder circuit breaker - FCB
Remote trip operation by SCADA possible
Arc interruption in dielectric
5.4.4 Vacuum Bottle
medium
5.4.5 Operating mechanism - TCB Manual spring charged stored energy type
Manual spring charged stored energy type, remote
5.4.6 Operating mechanism - FCB
electrical close / open operation possible.
Emergency trip / open push On panel front with Protective flap to prevent any
5.4.7
button accidental tripping of breaker.
Continuous rating at design
5.4.8 630amp
40 deg C ambient
5.4.9 Short time withstand capacity 20 KA for 3 sec
Minimum number of
Mechanical Endurance – Class M1( 2000 operations)
5.4.10 operations at rated current
Electrical Endurance – Class E2
(as per IEC 62271-100)
5.4.11 Fault making capacity 50 KA peak
5.4.12 Fault breaking capacity a) 20 KA Minimum
Maximum number of
Electrical Endurance – Class E2 . To be guaranteed
5.4.13 operations at rated Fault
by manufacturer with authorized lab test reports
current (as per IEC 62271-
Page 15 of 77
SP-PSSC-38-R7
100)
Breaker status auxiliary
5.4.14 2NO + 2NC wired to terminal block
contact
b) 75-400 / 1 amp for TCB/ FCB.
c) Considering three core cable terminations,
mounting flexibility shall be provided for CT’s
(in horizontal & vertical direction both).
Additionally, CAUTION marking (by sticker/
5.4.15 Current transformer paint) shall be provided to avoid CT’s
installation above the screen of cable. (I.e.
earth potential point.)
d) Position of CTs inside compartment shall be
adjustable in vertical and horizontal direction
Page 16 of 77
SP-PSSC-38-R7
Page 17 of 77
SP-PSSC-38-R7
Page 18 of 77
SP-PSSC-38-R7
Page 19 of 77
SP-PSSC-38-R7
Page 20 of 77
SP-PSSC-38-R7
The 11kV XLPE cable connection from RMU to distribution transformer shall be conforming
to IS 7098 and shall have all the following features -
Page 21 of 77
SP-PSSC-38-R7
box
Page 22 of 77
SP-PSSC-38-R7
Page 23 of 77
SP-PSSC-38-R7
Page 24 of 77
SP-PSSC-38-R7
Page 25 of 77
SP-PSSC-38-R7
Page 26 of 77
SP-PSSC-38-R7
Page 27 of 77
SP-PSSC-38-R7
Page 28 of 77
SP-PSSC-38-R7
Page 29 of 77
SP-PSSC-38-R7
Page 30 of 77
SP-PSSC-38-R7
Page 31 of 77
SP-PSSC-38-R7
8.2.6 Temperature rise winding Outside PSS without Inside PSS max.
Page 32 of 77
SP-PSSC-38-R7
enclosure
80°C 90°C
Maximum flux density at 10 % over excitation
8.2.7 Flux density
/overfluxing-1.73 Tesla [R7] maximum
Off Circuit taps on HV winding , + / - 5 % in steps of 2.5
8.2.8 Tapping on HV winding
% , change of taps by link
8.2.9 Design Clearances Phase – phase Phase - earth
11KV system 180mm 120mm
415V system 25mm 25mm
415V system 25mm 25mm
8.3 Construction & Design
8.3.1 Core
High grade , non ageing, low loss, high permeability,
8.3.1.1 Material
grain oriented, cold rolled silicon steel lamination
8.3.1.2 Grade Premium grade minimum M3 or better [R4]
8.3.1.3 Lamination thickness 0.23mm (Max) [R4]
Design Flux Density at
8.3.1.4 rated conditions at 1.6 Tesla [R7]
principal tap
Maximum Flux Density at
8.3.1.5 10 % over excitation / over 1.73 Tesla [R7] maximum allowed
fluxing
a. All steel sections used for supporting the core shall
be thoroughly sand blasted after cutting, drilling,
welding.
8.3.1.6 Core Design Features b. Core shall be in the form of step and stack in three
limb format [R7].
Note: No wound core shall be acceptable
c. Provision of lifting lugs for core coil assembly
8.3.2 Winding
8.3.2.1 Material Electrolytic Aluminum [R4]
Maximum Current Density
8.3.2.2 Maximum allowed 1.5 A per sqmm [R4]
allowed
Class F minimum, free from compounds liable to ooze
Winding Insulating out, shrink or collapse. Uniform insulation shall be
8.3.2.3
material applied to the windings and overall winding shall be
epoxy cast resin
Off Circuit taps on HV winding , + / - 5 % in steps of 2.5
8.3.2.4 Tapping
% , change of taps by link
Essential provision for tap Shall be shrouded with cover made from insulating
8.3.2.5
links material. To prevent deposit of dust.
Page 33 of 77
SP-PSSC-38-R7
Page 34 of 77
SP-PSSC-38-R7
Page 35 of 77
SP-PSSC-38-R7
Nominal Discharge
8.8.1.6 5
Current, kA peak
Energy Absorption
8.8.1.7 Greater than 2.5
Capability, kJ/kV
8.8.1.8 Creepage factor 31 mm /kV
8.8.1.9 Reference std IS 3070 part 3 and IEC 99-4
Winding Temperature
8.8.2 Required
scanner
Five (Three for windings, one for enclosure & one shall
be spare) RTD for enclosure temperature monitoring
8.8.2.1 No of RTD inputs shall be fixed at enclosure Top from inside to give max
enclosure temp reading & shall be wired up to temp.
scanner to indicate the reading
At location of winding where maximum temperature is
8.8.2.1.1 Location of winding RTD
expected.
No of potential free trip
8.8.2.2 Two
contacts
No of potential free Alarm
8.8.2.3 Two
contacts
240 V AC, 1 phase, 50 Hz. Tapped from LV side busbar
8.8.2.4 Auxiliary supply
through a MCB located inside box
Winding Temperature
8.8.2.5 Required
Scanner terminal Box
8.8.2.5.1 Size As per Manufacturer’s Standard
Fixing of instrument within
8.8.2.5.2 On base plate
box
Fixing of terminals within
8.8.2.5.3 On C channel available with the terminals
the box
8.9 Fitting and accessories
8.9.1 Rating & Diagram plate Required
8.9.1.1 Material Anodized aluminum 16SWG
8.9.1.2 Background SATIN SILVER
8.9.1.3 Letters, diagram & border Black
8.9.1.4 Process Etching
Following details shall be provided on rating and diagram
plate as a minimum
a) Type of transformer i.e cast resin or VPI etc. With
winding material
b) IS / IEC [R3] standard to which it is manufactured
8.9.1.5 Name plate details c) Manufacturer's name;
d) Transformer serial number;
e) Month and year of manufacture
f) Rated frequency in HZ
g) Rated voltages in KV
h) Number of phases
Page 36 of 77
SP-PSSC-38-R7
Page 37 of 77
SP-PSSC-38-R7
Page 38 of 77
SP-PSSC-38-R7
8.9.17 Copper earthing link Across all gasketted joints in the enclosure body.
Page 39 of 77
SP-PSSC-38-R7
Page 40 of 77
SP-PSSC-38-R7
Page 41 of 77
SP-PSSC-38-R7
Page 42 of 77
SP-PSSC-38-R7
Page 43 of 77
SP-PSSC-38-R7
12.3 Energy meter box Size 650 mm height x 450 mm width x 275 mm depth.
With antitheft hinge, padlock facility, door fixed by
12.4 Box door design
stainless steel Allen screw M6 size.
On slotted horizontal channel 40 x 12 mm size,
Fixing of energy meter
12.5 channel shall be movable on vertical slotted angle 40
within box
x 40 mm size at two ends.
Front door shall be with acrylic sheet for viewing the
12.6 Meter reading window
energy meter.
02 no’s sealing arrangement shall be provided on
12.7 Sealing arrangement meter box’s door.
Slot shall be provided on door of meter box for fixing 9
12.8 Data downloading port pin DB connector (RS232 serial port).
12.9 Test Terminal Block No Test terminal block shall be provided.
PVC insulated, extruded PVC inner sheathed,
armored, extruded PVC outer sheathed 1100 V grade
12.10 Cables and wires control cable as per latest edition of IS 1554 part 1
minimum 2.5 sq mm for PT and 4 sq mm for CT with
multi strand copper conductor.
Nickel plated brass double compression weatherproof
12.11 Cable Glands
cable gland.
To be fixed on the back of door along with CT spec.
12.12 Wiring diagram
etched on Anodised Aluminium plate fixed by rivet.
All CT and PT’s Secondary wires shall be routed
CT / PT Secondary through metallic conduit. All secondary wires shall be
12.13
wires bunched and kept for termination without any terminal/
TTB in between.
Page 44 of 77
SP-PSSC-38-R7
Page 45 of 77
SP-PSSC-38-R7
Transformer)
14.0 Other Provisions: Earthing, Illumination, Hooter & Smoke Detector
Page 46 of 77
SP-PSSC-38-R7
a) 02 no’s
b) HV and LV side of PSS enclosure.
c) Shall be etched on anodized aluminium
15.5 BSES Insignia
16SWG / SS plate.
d) Details shall be finalized during drawing
approval.
Enclosure painting surface
15.6 Shot blasting or 7 tank chemical process
preparation
Enclosure painting external finish Hot dip galvanizing – 80 micron thick grade A,
15.7 Powder coated epoxy polyester shade - RAL 7032, uniform thickness 60 micron
base minimum .
Powder coated epoxy polyester base grade A,
15.8 Enclosure painting internal finish shade -white, uniform thickness 80 micron
minimum
Page 47 of 77
SP-PSSC-38-R7
Page 48 of 77
SP-PSSC-38-R7
Page 49 of 77
SP-PSSC-38-R7
Page 50 of 77
SP-PSSC-38-R7
Page 51 of 77
SP-PSSC-38-R7
20.0 Deviations
Deviations from this Specification shall be stated in writing with the tender by
reference to the Specification clause/GTP/Drawing and a description of the alternative
20.1
offer. In absence of such a statement, it will be assumed that the bidder complies fully
with this specification.
Page 52 of 77
SP-PSSC-38-R7
information)
Operation & maintenance manual for all items in Packaged substation. (for
21.3.13
information)
21.3.14 Transport / Shipping dimensions with weights, wheel base details, un tanking height
21.4 Submittals required prior to dispatch
21.4.1 As built Drawings
21.4.2 Inspection and test reports, carried out in manufacturer’s works
21.4.3 Test certificates of all bought out items
21.4.4 Operation and maintenance Instruction as well as trouble shooting charts/ manuals
21.5 Drawing and document sizes Standard size paper A3, A4
Number of Documents required at 4 hard copies + 2 soft copies in CD
21.6
different stages Format at each stage
Duly signed & stamped copies of the drawings / documentation are required to be
Note :
submitted to BSES for approval.
The package substation shall be designed & tested to operate satisfactorily under following
conditions -
Sr No Description Data by purchaser
1. Location Delhi
2. Reference design ambient temperature 40°C for Delhi
3. Maximum ambient temperature 50°C for Delhi
4. Relative humidity 85% for Delhi
5. Seismic zone Zone IV for Delhi
Page 53 of 77
SP-PSSC-38-R7
1.1 Properties
The insulating oil shall have following features [R7]:
S.No. Item description Specification requirement
2.1 Appearance of oil Clear, free from sediment and suspended matter
Viscosity Max. 15 mm2 /s at 40°C
2.2
1800 mm2 /s at 0°C
2.3 Pour Point, Max -10°C
2.4 Water content, Max 30 mg/Kg
2.5 Breakdown voltage
i) New unfiltered oil. Min. 30 kV
ii) After filtration Min. 70 kV
2.6 Density Max. 0.895 g/ml at 20°C
2.7 Dielectric dissipation factor Max 0.005 at 90 °C,
2.8 Particle Content Value to be provided by the vendor
2.9 Acidity Max 0.01 mg KOH/g
2.10 Interfacial tension at 27°C Min 40 mN/m
2.11 Total sulphur content Value to be provided by the vendor
2.12 Corrosive sulfur Not-corrosive
2.13 Potentially Corrosive sulfur Not-corrosive
2.14 DBDS Not detectable (<5 mg/kg)
2.15 Inhibitor Not detectable (<0.01%)
2.16 Metal Passivator Not detectable (<5 mg/kg)
2.17 Other addivites Type and concentration of additives to
Page 54 of 77
SP-PSSC-38-R7
Page 55 of 77
SP-PSSC-38-R7
Page 56 of 77
SP-PSSC-38-R7
15.7 No of LBS close & open operation cycles 25% rated current -
guaranteed at 50% rated current -
Page 57 of 77
SP-PSSC-38-R7
Page 58 of 77
SP-PSSC-38-R7
Instantaneous O/C-
Instantaneous E/F-
Over Current – Curves
22.3 Operating Time
Instantaneous
22.4 Pick up Current
22.5 Resetting Current
22.6 Relay Burden
22.7 Time Accuracy
22.8 Tripping Coil O/P – type & duration
22.9 Fault Current Display
No of Fault Current Latching with time
22.10
stamping
22.11 Display Facility / Type
22.12 Operational Indicators
22.13 Potential Free Output Contacts
22.14 Thermal Withstand Capacity of Relay
23 Fault Passage Indicator Over Current and Earth Fault
23.1 CBCT
a Type
b Mounting Arrangement
c CT to indicator connection
d ID of sensor
23.2 Earth Fault Indicator
a Sensing Current
b Sensing Time
c Indication
d Reset Time
e Resetting Facility
f Output Contact
g Contact Rating
h Aux Power Supply
i Degree of Protection
j Mounting Arrangement
k Ambient Temperature
24 Current Transformer- Make
24.1 Ratio
24.2 Burden
Page 59 of 77
SP-PSSC-38-R7
HV winding LV winding
Transformer continuous rating when placed
7.3.0
in package substation enclosure
KVA KVA
HV winding LV winding
7.4.0 Rated voltage ( kV )
11 KV 0.433 KV
HV winding LV winding
7.5.0 Rated current
Amps Amps
7.6.0 Transformer vector group – Dyn11 Yes / No
250KVA/400KVA & 630KVA -
Impedance at principal tap rated current and
7.7.0 4.5.0 % & 1000KVA-5% with IS
frequency, ohm @75 °C
tolerance [R4]
7.7.1 Impedance at lowest tap Ω
7.7.2 Impedance at highest tap Ω
HV winding LV winding
7.8.0 Resistance of the winding at 75°C in ohm
Ω Ω
HV winding LV winding
7.9.0 Zero sequence impedance in ohm
Ω Ω
Guaranteed maximum losses at principal tap
7.10.0 full load and 75°C without any positive
tolerance, kW
7.10.1 No load losses (max.) KW
Page 60 of 77
SP-PSSC-38-R7
Page 61 of 77
SP-PSSC-38-R7
Page 62 of 77
SP-PSSC-38-R7
Page 63 of 77
SP-PSSC-38-R7
neutral
7.29.1 Phase to phase clearance, 25 mm minimum
7.29.2 Phase to earth clearance , 25 mm minimum
7.30.0 Current Transformer on LV phases
7.30.1 Type
7.30.2 Make
7.30.3 Reference Standard
7.30.4 CT Ratio
7.30.5 Burden, VA
7.30.6 Class of Accuracy / ISF
7.30.7 CT terminal box size
7.31.0 Pressure release device on tank - make
Minimum pressure the device is set to
7.31.2
rupture
Fittings Accessories Each Transformer
7.32.0 Yes/No
furnished as per Clause 7.3.0
Painting: as per clause for the transformer,
7.33.0 Yes/No
cable boxes, Marshalling box
7.34.0 Over all transformer dimensions
7.34.1 Length mm
7.34.2 Breadth mm
7.34.2 Height Mm
7.35.0 Weight data
7.35.1 Core KG
7.35.2 Winding KG
7.35.3 Frame KG
7.35.4 Tank KG
7.35.5 Weight of oil in Tank KG
7.35.6 Total Transport weight of the transformer KG
7.36.0 Transformer total oil volume liters
250/400/630/1000KVA Cast Resin
8.0.0
Transformer
8.1.0 Make
8.2.0 Type- Cast Resin Dry Type Yes / No
HV winding LV winding
Transformer continuous rating when placed
8.3.0
in package substation enclosure KVA KVA
HV winding LV winding
8.4.0 Rated voltage ( kV )
11 KV 0.433 KV
8.5.0 Rated current HV winding LV winding
Page 64 of 77
SP-PSSC-38-R7
Amps Amps
8.6.0 Transformer vector group – Dyn11 Yes / No
Impedance at principal tap rated current and
8.7.0 5.0 % with IS tolerance
frequency, ohm @130°C
8.7.1 Impedance at lowest tap Ω
8.7.2 Impedance at highest tap Ω
HV winding LV winding
8.8.0 Resistance of the winding at 130°C in ohm
Ω Ω
HV winding LV winding
8.9.0 Zero sequence impedance in ohm
Ω Ω
Guaranteed maximum losses at principal tap
8.10.0 full load and 130°C without any positive
tolerance, kW
8.10.1 No load losses (max.) KW
8.10.2 Load losses (max.) KW
8.10.2 Total losses (max.), KW
No load loss at maximum permissible
8.10.4 KW
voltage and frequency (approx.),
8.10.5 Total stray loses @ 130° C
8.11.0 Temperature rise over reference ambient
Winding by resistance: Outside the
8.11.1 PSS enclosure / inside the PSS 80°C/ 90°C
enclosure 0 C
Maximum hot spot temperature, Deg.
8.11.2 °C
C
8.12.0 Efficiency at 130°C and unity power factor
8.12.1 at 110% load %
8.12.2 at 100% load %
8.12.2 at 80% load %
8.12.3 at 60% load %
8.12.4 at 40% load %
8.12.5 at 20% load
Maximum hot spot temperature, Deg. at 130°C and 0.8 power factor
8.13.0
C lag
8.13.1 Efficiency %
8.13.2 at 110% load %
8.13.3 at 100% load %
8.13.4 at 80% load %
Page 65 of 77
SP-PSSC-38-R7
Page 66 of 77
SP-PSSC-38-R7
Page 67 of 77
SP-PSSC-38-R7
Page 68 of 77
SP-PSSC-38-R7
rms
8.34.6 Nominal Discharge Current, kA peak
8.34.7 Energy Absorption Capability, kJ/kV
8.34.8 Creepage factor
8.34.9 Reference std
8.35.0 WTI Scanner Details
8.35.1 Make
8.35.2 Model no.
8.35.3 No of Channel / Input
8.35.4 Manual submitted
To connect transformer LV side
9.0.0 Low voltage bus bar system
to ACB & to MCCB
9.1.0 Bus bar material tinned copper Yes / No
9.2.0 Bus bar size sqmm
9.3.0 Bus bar continuous current rating Amp
9.4.0 Bus bar insulator voltage class kV
9.5.0 Bus bar droppers size from ACB to MCCB
(40x6 tinned copper)
9.6.0 Maximum bus bar temperature rise
10.0.0 ACB, MCCB As per IS 13947
10.1.0 ACB make
10.1.1 ACB rated voltage 415v +/- 10%
10.1.2[R7] ACB 4 pole Yes / No
10.1.3 ACB continuous current capacity at 415v
amp
50Hz, at 50 deg C
10.1.4 ACB short circuit breaking capacity Ics =Icu
kA
= 50kA minimum
10.1.5 ACB SC making current capacity 100kAp kA peak
10.1.6 ACB short time current withstand capacity
kA
for 1 sec (Icw= 50kA)
ACB rated impulse withstand voltage for
10.1.7
main & aux circuit in kv
10.1.8 ACB closing time in ms
10.1.9 ACB opening time in ms
Guaranteed number of close & open
10.1.10
operations at no load
10.1.11 Guaranteed number of close & open
operations at rated load
10.1.12 ACB dimensions
10.1.13 ACB operating mechanism -Trip free, anti
Yes / No
pumping type, manual as well as motor
Page 69 of 77
SP-PSSC-38-R7
Page 70 of 77
SP-PSSC-38-R7
Page 71 of 77
SP-PSSC-38-R7
Page 72 of 77
SP-PSSC-38-R7
Page 73 of 77
SP-PSSC-38-R7
Page 74 of 77
SP-PSSC-38-R7
Page 75 of 77
SP-PSSC-38-R7
CRGO with M3 Grade or better with max thickness of 0.23mm and with max core loss
of 1 W/Kg, perfectly insulated and clamped to minimize noise and vibrations.
2 Following stage inspections will be carried out by purchaser or by third party engineers
appointed by BSES :
2.1 Verification & inspection of the mother coil at port & putting stamp & seal may be
inspected by BSES.
2.2 Reconciliation of mother coil by checking stamp & seal at factory before slitting. One
sample of CRGO to be sealed for testing at ERDA/CPRI. Following Tests shall be
conducted on the sample:
1) Specific core loss measurement
2) Magnetic polarization
3) Magnetic permeability
4) Specific core loss measurement after accelerated ageing test
5) Surface insulation resistivity
6) Electrical resistivity measurement
7) Stacking factor
8) Ductility(Bend test)
9) Lamination thickness
10) Magnetization characteristics (B-H curve)
2.3 Bidder should have in house core cutting facility for proper monitoring & control on
quality.
In case it is done outside cutting shall be done in presence of BSES.
2.4 Following documents to be submitted during the stage inspection :
2.4.1 Invoice of supplier
2.4.2 Mills test certificates
2.4.3 Packing list
2.4.4 Bill of lading
2.4.5 Bill of entry certificates by customs
2.4.6 Core material shall be directly procured either from the BSES approved manufacturer
or through their authorized service centre/distributor and not through any contractor.
2.5 Bidder should have hydraulic core lifting facility to avoid any jerk at the time of core
building.
2.6 BSES may appoint recognized testing authority like CPRI /ERDA with their
instruments & engineer’s team and measure no load loss, load loss and percentage
impedance of the transformer at supplier’s works at our own cost. Bidder shall agree
and give them full cooperation during their stay & testing at shop floor. The losses &
impedance values so obtained will be considered as final.
2.7 Bidder should have in-house NABL accredited testing facility.
Page 76 of 77
SP-PSSC-38-R7
4
5
6
7
300 mm above
E Height of all equipment (RMU,LT panel & DT) from FGL from FGL
F No foundation requirement , base frame / Pad mounted Req.
G Smoke detector with flag type auxiliary relay Req.
Other material like (MFM, Fire Ball, Cable sealing compound, Space for
H DT meter Installation, etc.) As per Spec
Page 77 of 77
SP-ERMUX-15-R9
A.C. Metal Enclosed Switchgear and Control gear for Rated Voltages
IS 3427
Above 1 Kv
IS 9920 part 1,3 & 4 High voltage switches above rated voltage 1kv
IS 13118 General requirements of circuit breakers above rated voltage 1kv
IS 3231 Electric Relays for Power System Protection
IEC 60265 part 1 High voltage switches
IEC 60056 High voltage alternating current circuit breakers
IEC 60059 Preferred current ratings of high voltage switchgear
IEC 60185 Current transformers
IEC 60694 Specification for high voltage switchgear
IEC 60298 AC metal enclosed switchgear
IEC 60129 Ac disconnector and earth switches
IEC 60529 Classification of degrees of protection provided by enclosures
IEC 60255 Electrical relays
In the event of direct conflict between various order documents, the precedence of authority of
documents shall be as follows -
i. Guaranteed Technical Particulars (GTP)
ii. Specification including applicable codes & standards
iii. Approved Vendor Drawings
iv. Other documents
3.0 Electrical Distribution System Data
3.1 Supply 3 phase AC, 3 wire
3.2 Voltage 11000 volt ±10%
Page 6 of 49
SP-ERMUX-15-R9
3.3 Frequency 50 Hz ± 5%
3.4 System neutral Earthed at upstream 11kv source
4.4.2 Breakers SF6 gas or Vacuum type (with disconnector & earth switch)
4.4.3 Load break switches SF6 gas or Vacuum type (With Earth Switch)
i) Separate for each breaker
Arc interruption
4.5 ii) Arc interruption chamber of breakers shall be separate
chamber for breaker
from the main insulated tank. (Desirable feature)
Maximum dimensions
4.6 for a 3 way panel (1 CB
+ 2 LBS)
Width (measured from
4.6.1 1250 mm
front)
4.6.2 Depth 800 mm
4.6.3 height 2000 mm
Page 7 of 49
SP-ERMUX-15-R9
Terminals for 11kv Suitable for Ring Type Bimetallic lug as per annexure F
5.13
cable termination [R5]
5.13.1 Right angled boots Single piece cold shrink type per bushing
Page 8 of 49
SP-ERMUX-15-R9
5.15 Earth bus bar Tinned Copper flat sized for rated fault duty for 3 sec {R9}
Earth bus internal
connection to all By 2.5 sq mm copper flexible wire, Earth connection point
5.16
non current carrying maximum 1 meter away from cable test facility
metal parts
Earth bus external
Studs on both sides with holes for M10 bolt + hardware to
5.17 connection to
readily receive purchaser earth connection
owners earth
5.23 Panel cover fixing bolts Allen head 6mm with hexagonal slot
5.24 Padlock facility Required for all earth switches & all handles
Page 9 of 49
SP-ERMUX-15-R9
Page 10 of 49
SP-ERMUX-15-R9
Digital type and shall operate as the current exceeds the set
value. Flash indication for identifying faults with red LED with
Fault Passage Indicator
one flash for every one sec. Test & rest button 1 NO + 1 NC
(For both Earth Fault
6.10.3 potential free contact for remote indication FPI power supply
and Over Current
unit shall use lithium battery with minimum life of 1000 blinking
Protection) [R8]
hours , so that FPI shall continue to function even after main
feeder has tripped.
Page 11 of 49
SP-ERMUX-15-R9
ambient {R9}
Short time withstand
7.5.2 20 KA for 3 sec (R5)
capacity
Minimum number of
operations at rated Mechanical Endurance – Class M1( 2000 operations)
7.6
current (as per IEC Electrical Endurance – Class E2 ( R5)
62271-100)
7.7 Fault making capacity 50 KA peak (R5)
7.8 Fault breaking capacity 20 KA Minimum (R5)
Maximum number of
operations at rated Electrical Endurance – Class E2 . To be guaranteed by
7.9
Fault current (as per manufacturer with authorized lab test reports (R5)
IEC 62271-100)
Breaker status auxiliary
7.10 2NO + 2NC wired to terminal block
contact
1. 75-400 / 1 amp for TCB/ FCB. {R9}
2. Considering three core cable terminations, mounting
flexibility shall be provided for CT’s (in horizontal &
vertical direction both). Additionally, CAUTION
marking (by sticker/ paint) shall be provided to avoid
7.11 Current transformer
CT’s installation above the screen of cable. (I.e.
earth potential point.)
3. Position of CTs inside compartment shall be
adjustable in vertical and horizontal direction {R9}
Page 12 of 49
SP-ERMUX-15-R9
Page 13 of 49
SP-ERMUX-15-R9
Page 14 of 49
SP-ERMUX-15-R9
Page 15 of 49
SP-ERMUX-15-R9
Page 16 of 49
SP-ERMUX-15-R9
16.0 Deviations
a) Deviations from this specification shall be listed separately by bidder clause wise
(format given below) along with optional offer and has to submit the list along with
bid/quotation. BRPL will review the deviations and if BRPL is agreed with the
deviation, seller has to take written confirmation from BRPL on deviation during tender
evaluation.
b) In the absence of any separate list of deviations from the bidders with bid as well as
16.1
written confirmation from BRPL on deviations, it will be assumed by the Buyer that the
Seller complies with the Specification fully.
c) Any deviations mentioned in any other submitted bid documents (i.e.in filled GTP,
Catalog, BRPL old approval, buyer’s/seller’s standards etc) by seller without separate
deviation sheets will not consider as a deviation from this tech spec at any stage of
contract.
Page 17 of 49
SP-ERMUX-15-R9
17.1 To be submitted along with bid The seller has to submit following:
17.1.1 GA / cross sectional drawing of product showing all the views / sections
Detailed reference list of customers using the offered product during the last 5 years
17.1.2 with similar design and rating
17.1.3 Completely filled GTP
17.1.4 Manufacturer's quality assurance plan and certification for quality standards
17.1.5 Type test reports for the type, size & rating of product / equipment offered
17.1.6 Complete product catalogue and Manual.
Recommended spare parts and consumable items for five years of operation and
17.1 spare parts catalogue with price list
17.2 All documents as per clause 13 of this specification
After award of contract, Seller has to submit following drawings for buyer’s Approval
17.3 (A) / Reference (R)
17.3.1 Program for production and testing (A)
17.3.2 Guaranteed Technical Particulars (A)
17.3.3 GA drawing
17.3.4 Schematic and wiring drawings for all components
17.3.5 Terminal arrangement & cable box details including gland plate arrangement etc
17.3.6 Bill of material
17.3.7 Detailed loading drawing to enable the buyer to design and construct foundations
17.3.8 Transport / Shipping dimensions with weights, wheel base details, un tanking height
17.3.9 detailed installation and commissioning instructions
17.3.10 quality plan
17.4 Submittals required prior to dispatch
-Inspection and test reports, carried out in manufacturer’s works
-Test certificates of all bought out items
-Operation and maintenance Instruction as well as trouble shooting charts/ manuals
Page 18 of 49
SP-ERMUX-15-R9
Page 19 of 49
SP-ERMUX-15-R9
maintenance trouble shooting of mechanism, FPI and all other components. This
shall be carried out within 1 week from date of 1st shipment/ dispatch. Supplier shall
also provide training for Self Powered relay at respective manufacturer’ factory for 12
engineers/ technicians in 2 batches. [R5].All the trainings shall be applicable for each
P.O.
1.8 Unit price for Conversion kit should be offered separately for converting the RMU
from single cable termination design to double cable termination design, at site.
1.9 BOQ as following –
Page 20 of 49
SP-ERMUX-15-R9
Page 21 of 49
SP-ERMUX-15-R9
28kv min
13 Bus bar
13.1 Material & grade
13.2 Bus bar cross section area in sq mm
Bus bar rated current in amp
i) at designed 50 deg.C ambient
13.3
{R9}
ii) at 50 deg.C ambient
Max temperature rise above reference
13.4
ambient of 40 deg C
Short time current withstand capacity for
13.5
3 seconds (in KA)
13.6 Bus bar clearances in mm P-P / P-E
13.7 Bus bar with insulation sleeve / barriers
13.8 Bus bar support insulator type
13.9 Bus bar support insulator voltage class
Bus bar support insulator minimum
13.10
creepage distance / mm
13.11 Earth bus bar material
13.12 Earth bus bar size
14 Circuit breaker type – SF6 or VCB
14.1 Rated voltage & frequency
14.2 Rated current in amp
Rated breaking current – KA rms
14.3
symmetrical
Short time withstand capacity in KA for 3
14.4
sec
14.5 Rated making current - KA peak
Breaker total opening time at rated
14.6
breaking capacity (in milliseconds)
14.7 Number of breaks per pole
Page 22 of 49
SP-ERMUX-15-R9
Page 23 of 49
SP-ERMUX-15-R9
Page 24 of 49
SP-ERMUX-15-R9
22.1 CT Input
Overcurrent-
Earth Fault-
IDMT Setting Range 4 element – Over
22.2 Instantaneous O/C-
Current & Earth fault & steps
Instantaneous E/F-
Over Current – Curves
22.3 Operating Time
Instantaneous
22.4 Pick up Current
22.5 Resetting Current
22.6 Relay Burden
22.7 Time Accuracy
22.8 Tripping Coil O/P – type & duration
22.9 Fault Current Display
No of Fault Current Latching with time
22.10
stamping
22.11 Display Facility / Type
22.12 Operational Indicators
22.13 Potential Free Output Contacts
22.14 Thermal Withstand Capacity of Relay
23 Fault Passage Indicator Over Current and Earth Fault
23.1 CBCT
a Type
b Mounting Arrangement
c CT to indicator connection
Page 25 of 49
SP-ERMUX-15-R9
d ID of sensor
23.2 Earth Fault Indicator Make / Model as per Annexure-I
a Sensing Current
b Sensing Time
c Indication
d Reset Time
e Resetting Facility
f Output Contact
g Contact Rating
h Aux Power Supply
i Degree of Protection
j Mounting Arrangement
k Ambient Temperature
24 Current Transformer- Make As per Annexure-I
24.1 Ratio
24.2 Burden
24.3 Accuracy Class
25 Voltage Presence Indicator
Make As per Annexure-I
Rating
Model No
Terminal Blocks, Disconnecting type
26.8
fuses make
Page 26 of 49
SP-ERMUX-15-R9
a) 11kv RMU shall have Transformer circuit breakers (TCB) with Load break switches (LBS) or Feeder
circuit breakers (FCB) as per configuration defined in Purchase Requisition.c) TCB shall be operated
Page 27 of 49
SP-ERMUX-15-R9
d) 11kv RMU shall be suitable for extension on sides for addition of LBS, TCB or FCB.
e) Fault passage indicator (For Both Earth Fault and Over Current Protection) including associated CT &
f) RMU Configuration-
Page 28 of 49
SP-ERMUX-15-R9
INDEX
1.0 Purpose …………………………………………………………………………………………..3
2.0 Applicability ……………………………………………………………………………………..3
3.0 Priority ……………………………………………………………………………………………..3
4.0 Liability …………………………………………………………………………………………....3
5.0 Warranty Requirements …………………………………………………………………..3
6.0 Process Requirements ………………………………………………………………………4
7.0 Documents/records/report submission …………………………………………….7
8.0 Qualification requirement for service engineers ……………………………….8
9.0 Safety ……………………………………………………………………………………………....8
10.0 Communication …………………………………………………………………………………8
11.0 Changes/revision management ………………………………………………………...8
Page 29 of 49
SP-ERMUX-15-R9
1. Purpose
This document is prepared to specify the servicing requirement and Warranty /
Guarantee handling procedure in case of difficulty that arises in the supplied equipment
within the useful service life of the equipment being procured by BSES Rajdhani Power
Limited.
2. Applicability
It is applicable to any equipment supplied directly or indirectly for installation / use in
BSES Rajdhani Power Limited.
3. Priority
i) Supplier shall be liable to arrange OEM qualified service engineers as and when
required by BSES Rajdhani Power Limited to attend defects, trouble shooting to
restore equipment health to ensure 100 % capacity availability.
ii) OEM shall be liable to provide essential spares at reasonable price for entire
lifespan of the equipment.
iii) Service call shall be attended within reasonable time frame as mentioned in this
document.
iv) Service cannot be denied by supplier/OEM till completion of useful life of the
equipment.
v) The commercial liability shall be restricted to supply/service contract provision.
It will be liability of manufacturer /vendor tie up with accessories / component
manufacturer to full fill requirement stipulated this document.
5. Warranty Requirements
Page 30 of 49
SP-ERMUX-15-R9
i) The equipment failed / malfunctioned within stipulated warranty period shall
be attended free of cost for the reasons not attributed to BSES Rajdhani
Power Limited.
ii) The cost incurred for service, spares, transportation, consumable and
manpower / labour shall be borne by supplier.
iii) OEM is bound to send service engineer to site on request for troubleshooting
promptly.
iv) There is no cap on number of visit or spare replacement required to repair /
trouble soot the problem in the equipment during warranty period.
v) Each break down / problem reported shall be analysed scientifically to
establish the root cause of breakdown.
vi) In case it is established that any component or accessories is not performing
satisfactorily or causing repeated failure due to poor performance,
manufacturing mistakes, design mistakes or not suitable to our environment
condition applicable to NCR region, the OEM shall be liable to rectify or
replace the same in all equipment supplied to BRPL irrespective of warranty
period.
vii) In case if RMU supplier is not OEM of the equipment / accessories, the
supplier will be liable to tie up with OEM to provide service / spares to meet
warranty / servicing requirement stipulated in this documents.
viii) Irrespective of onsite or workshop repairing, it will be responsibility of OEM
to maintain work quality to ensure no compromise on performance and
useful life of the equipment.
6. Process requirements
6.1 Complain Registration.
i) Supplier to provide communication details for complaint registration in O&M
Manual, on website as well as shall be printed on the equipment. In case of
changes, same shall be communicated to BRPL.
ii) BRPL will register complain through a e‐mail / telephonic call to the call
centre / service centre
Page 31 of 49
SP-ERMUX-15-R9
6.2 Confirmation and Service time Schedule.
i) All timing will be counted from date of call registration by BRPL till
restoration of equipment health at respective site in operation condition
satisfactory of BRPL engineer.
ii) Service call confirmation & service engineer visit schedule shall be provided
within two hour for working hour call (09:00AM to 06:00PM, Monday to
Saturday) and before 10 AM next working day for off working hour calls.
iii) Emergency trouble shooting calls ‐ within 12 Hrs including spare
arrangements.
iv) Normal trouble shooting call ‐ within 48 Hrs.
v) On site repairing / component replacement ‐ within 7 days.
vi) OEM workshop repairing ‐ within 30 days including returning to BRPL stores.
vii) Replacement of complete RMU ‐ within 45 days.
viii) The service engineer shall intimate necessary requirement to attend call
along with confirmations
6.3 Site visit & Investigation.
i) The OEM shall depute qualified and experienced engineer to carryout trouble
shoot as well as testing and collecting necessary data / details essential for
root cause analysis.
ii) The service engineer shall collect preliminary details to understand and
estimate the spare requirement, shutdown time requirement from our
respective area engineer whose details will be provided along with service
call.
iii) The necessary tools shall be carried by service engineer attending calls.
iv) Service engineer to get call attendance certificate from respective area BRPL
engineers.
Page 32 of 49
SP-ERMUX-15-R9
vi) Detailed technical report (root cause analysis) to be submitted to CES Team
for records and analysis against each call.
6.4 Recommendation.
i) Shall be based on scientific study / test results only.
ii) Shall cover root cause analysis for failure.
iii) Shall cover spares / component list for repairing.
iv) Shall cover time requirement.
v) Shall cover site preparation / condition requirement.
vi) Other critical measures essential for quality work.
6.5 On Site Repairing.
i) All site repairing shall be under supervision of OEM engineer and shall meet
all OEM recommendation to ensure quality of work.
ii) All spares arrangement shall be carried out well in advance to minimize
outage time. The list must be shared with CES team
iii) Necessary repairing process to be intimated to CES team in advance. It shall
include in process & final quality and performance checks / test.
iv) The repairing process shall be certified by OEM design / quality expert.
v) Detailed time schedule and spares arrangement details shall be submitted to
CES team for necessary planning.
vi) The repairing work shall be witness by BRPL CES engineer, who may insist in
process / performance checks / test in addition to above if felt essential.
vii) If BRPL engineer observed any quality problem / skill problem, may insist for
repairing at OEM facility.
6.6 Repairing at OEM facility.
Following requirement shall be fulfilled during OEM workshop repairing work: ‐
Page 33 of 49
SP-ERMUX-15-R9
i) During site inspection, if service engineer felt necessary to send equipment to
OEM facility, the same shall be organized by OEM.
ii) In case if BRPL felt that site repairing is not up to the required quality or felt
necessary to analyze cause of failure, the same shall be organized by OEM.
iii) Equipment unpacking, testing and opening for analysis inspection shall be
carried out in presence of BRPL engineer. It shall be intimated to BRPL at least
3 days in advance for necessary travel arrangement.
iv) If cause of failure observed due to design mistake / manufacturing mistakes,
the same shall be rectified in all other similar design equipments without any
cost to BRPL.
v) OEM to intimate the final testing for inspection. BRPL may depute engineer
or third party representative to carryout inspection / testing before dispatch.
vi) Dispatch shall be carried out only after BRPL clearance.
vii) Necessary lifting, shifting, loading / unloading & transportation arrangement
shall be in the scope of OEM / supplier.
viii) A document required essential for lifting and shifting of equipment will be
intimated at least two days in advance.
6.6 Witness / Inspection stages.
Even though OEM is liable for overall quality of work, BRPL may witness / Inspection
following activity:‐
i) On site inspection, repairing/replacement work.
ii) Testing / inspection equipments / any accessories / component to establish the
cause of failure.
iii) Opening of equipment for internal part inspection.
iv) Final testing/inspection before despatch.
v) Testing / checking of the evidence causing failure / problem.
Page 34 of 49
SP-ERMUX-15-R9
Note: It will be responsibility of OEM / Supplier to establish with facts, figure,
photographs, and evidence to prove that cause of failure not attributed to design.
7 .0 Documents / records / report submission
The following be recorded and provided to BRPL by OEM against each call / repairing /
rectification works for BRPL clearance and future reference:‐
i) Root cause analysis report.
ii) All test report.
iii) Minutes of meeting.
iv) Spares / accessories test report / calibration certificates.
v) Proof of expenditure for cost incurred to BRPL.
vi) Copy of transportation documents.
vii) All technical details of parts / accessories being replaced.
8.0 Qualification requirements for service engineers
i) All work must be carried out by only qualified, experience engineer certified by OEM.
BRPL may request qualification and experience details if felt necessary.
9.0 Safety.
i) All necessary personal protective equipments requirement for the personal and
labour will be in the scope of OEM / supplier.
ii) It will be liability of OEM / Supplier to meet the necessary safety norms , standards,
rules & regulation .
iii) BRPL may audit the same during on site work.
10.0 Communications.
For better coordination, single channel communication must be followed. BRPL and
OEM / Supplied to communicate to each other their team for communication time to
time in case of any changes.
At present, all warranty related communication is to be done with CES team.
Page 35 of 49
SP-ERMUX-15-R9
11.0 Changes / revision management.
Necessary approval of O&M analytic cell is essential for changes in this document.
In case if any stack holders do not agree or wish to amend its content may send request
to BRPL O&M analytic cell for approval.
The request will be in effect only on consideration and authorized release of revision in
document by O&M analytic cell.
IP 54 Minimum
Overall Enclosure
4 (Complete unit i.e. RMU coupled to Metering unit shall be
Protection
IP54)
Page 36 of 49
SP-ERMUX-15-R9
Page 37 of 49
SP-ERMUX-15-R9
1. Bottom
2. Gland plate - 3mm metallic, removable & split type in two
10.1 Cable Entry
parts, with 1no. 90 mm diameter knocks out punch/hole in
the centre. Approval should be taken for the same during
drawing submission
Page 38 of 49
SP-ERMUX-15-R9
1. Secondary wiring of CTs and PTs shall be done with 2.5 sq.
mm PVC insulated cables with stranded copper conductor.
Page 39 of 49
SP-ERMUX-15-R9
Page 40 of 49
SP-ERMUX-15-R9
1. BRPL Property
2. Supplier’s name
3. P.O. No. & Year of manufacturing
4. Sr. No. of metering cubicle
5. Particulars of CT’s such as ratio, VA burden, accuracy
class, SC rating, BIL.
2.6 Name plate details
6. Particulars of PT’s such as ratio, accuracy class, VA
burden, BIL.
a) 01 no’s
2.9 BSES Insignia
b) Shall be etched on anodized aluminium 16SWG / SS
Page 41 of 49
SP-ERMUX-15-R9
plate.
Enclosure painting
internal/ external finish Hot dip galvanizing – 80 micron thick grade A, shade - RAL
2.11
Powder coated epoxy 7032, uniform thickness 60 micron minimum.
polyester base
Page 42 of 49
SP-ERMUX-15-R9
On primary winding KV rms 28KV (rms) for 1 minute 28KV (rms) for 1 minute for 11
13.1 On secondary winding KV for 11 KV class 3KV (rms) KV class 3KV (rms) for 1
rms for 1 minute minute
Page 43 of 49
SP-ERMUX-15-R9
1 Name of Manufacturer
5 Frequency 50Hz
6 Insulation Class
Page 44 of 49
SP-ERMUX-15-R9
Page 45 of 49
SP-ERMUX-15-R9
Clearances a. Phase to
13 phase clearance b. Phase
to earth clearance
Dimensions of complete
Metering cubicle a. Height
17
(mm) b. Breadth (mm) c.
Length (mm)
18 Meter compartment
Dimensions of meter
compartment with double
door (minimum sheet
18.1
thickness 2mm) a. Height
(mm) b. Breadth (mm) c.
Length (mm)
Provision of mounting
18.6 metering reading port on
door.
Page 46 of 49
SP-ERMUX-15-R9
Annexure ‘I’ Make list
Sl. No Descriptions
1 Animated video for ETC guide of RMU shall be submitted to BRPL before
delivery of first lot
2 Relay Protection setting (min 10%)
3 All the communicable accessories shall have Latch contact
4 NO/NC contact for manometer shall be provided
Page 47 of 49
SP-ERMUX-15-R9
Sl. No Descriptions
--Bidders shall have additional RMU readily available of each type to replace
under warranty faulty RMU in case it is repairable at OEM factory
--In case of under warranty failure and if the faulty RMU is repairable only at
OEM factory, bidder has to replace the faulty RMU during lifting with new/
operatable same type of RMU within the time period mentioned in the tech spec
5
warranty clauses.
--BRPL shall not issue any RMU from their assets for replacement activity. In
case of delay, penalty shall be imposed as per this corrigendum sl no 9
--After Warranty period completion (5 years), these clause shall not be
applicable to OEM
6 Sample RMU
Page 48 of 49
SP-ERMUX-15-R9
Sl. No Descriptions
along with drawing
Page 49 of 49
GN101-03-SP-06-03
Index
Page 2 of 44
GN101-03-SP-06-R
General Specification
1.0 Codes & standards
Materials, equipment and methods used in the Laying of 11/33/66KV Cable shall conform to the
latest edition of following –
2.0 Design guidelines and Parameter for cable laying‐
Page 3 of 44
GN101-03-SP-06-R3
• The excavated earth shall be so stored at site, that it shall
not cause trouble to running traffic
• All excavated earth shall be stored within the barricaded
area.
•
c) Full height fence, barriers, barricades etc. shall be erected
around the site in order to prevent the working area from the
risk of accidents due to speedy vehicular movement. Same the
way barricades protect the road users from the danger due to
construction equipment and temporary structures.
d) The structure dimensions of the barricades , material and
composition, its colour scheme, BSES logo and details shall be in
accordance with specification and drawing laid down in the
tender documents.
e) All the barricades shall be erected as per the design
requirements of employer, numbered painted and maintained in
good condition and also barricade in charge maintain a barricade
register at site.
f) All barricades shall be conspicuously seen in the dark/night time
by the road users so that no vehicle hits the barricades.
Conspicuity shall be ensured by affixing retro reflective strips of
required size and shape at appropriate angle at bottom and
middle portion of the barricades at a minimum gap of 1000 mm.
In addition minimum one red light /red blinker and red beacon
light should be placed at the top of each barricade.
g) PPP to be provided by vendor to all workers and engineers.
h) Also refer Annexure‐ 7: Barricading and Safety
2.3 Clearance The desired minimum clearances are as follows –
‐ Power cable to power cable – A minimum clearance equal to diameter
shall be maintained. Trench drawings shall be referred to for guidance.
‐ Power Cable to control cables – 0.2 M
‐ Power cable to communication cable – 0.3M
‐ Power cable to gas/water main – 0.3 M
2.4 Depth of Cable The desired minimum depth of laying from ground surface to the top of
Laying cable shall be:
650 / 1100V grade XLPE Cables – 75 cm
6.35 / 11KV grade XLPE Cables – 90 cm
Low voltage and Control cable ‐ 75 cm
19 / 33KV grade XLPE Cables ‐ 1.2 M
38 / 66KV grade XLPE Cables ‐ 1.5 M
Cables at Road crossing ‐ 1.0 M (min.)
Cables at railways level crossings (measured from bottom of sleepers to
the top of Pipe) ‐ 1.0 M (min.)
Whenever there is any obstacle at the laying depth, the cable should be
lowered/ raised to cross the obstacle. However variation in the depth is
to be approved by BSES. The Contractor shall provide the same in
deviation report.
2.5 Width of Cable The width and depth of Cable Trenches shall depend upon number of
Page 4 of 44
GN101-03-SP-06-R3
trenches circuits and Voltage Grade. Annexure # 3 and drawings of this
specification shall be followed.
2.6 Bending Radius While pulling of the Cable from the drum or during laying
of Cables following minimum bending radius shall be maintained so that
the cable, in particular the insulation does not get damaged –
A) Single Core Cables ( PVC & XLPE)
Upto 1.1KV grade – 15 X D
Above 11KV grade ‐ 20 X D
B) Multi Core Cables ( PVC & XLPE)
Upto 1.1KV grade ‐ 12 X D
Above 1.1KV grade – 15 X D
Where ‘D’ is overall diameter of the cable.
2.7 Maximum For cables pulled with Stocking
permissible PVC and XLPE SWA Armoured cables P = 30 X D
Tensile PVC and XLPE AWA Armoured cables P = 20 X D
Strength for Where P= pulling force in Kgrm, D= Diameter of Cable in mm
Cables
For Cables pulled by Cable eyes
Aluminium conductor – 30 N/mm2 = 3 Kg/sq. mm
Copper conductors ‐ 50N/mm2 = 5 Kg/sq. mm
Permissible force is calculated by multiplying the above values by cross
sectional area (CSA) of conductor of each core and then number of cores.
2.8 Methods of a) Cables shall be laid in direct in ground, in trenches excavated
Laying therein and shall be protected with covers as given in the
drawing. Cables shall also be drawn into pipes of ducts or laid in
the formed trenches or troughs or on racks or supported in trays
or cleats as required by the site exigencies. Where the cables are
laid in the formed trenches, the installation shall include removal
and replacement of the trench covers and the provision of
temporary protective covers on the trenches where they cross
the access ways.
b) HDPE (PN6,PE80) or RCC ducts shall be used where cable cross
roads and railways tracks. Spare ducts for future extensions
should be provided. Spare duct should be sealed off. Buried
ducts or ducting blocks shall project into footpath or upto the
edge of road, where there is no footpath, to permit smooth entry
of cable without undue bending. The diameter of the cable
conduit or pipe or duct should be at least 1.5 times the outer
diameter of the cable. Angular alignment of the duct across road
crossings shall be predetermined to maintain safe bending radius
when direction of cable trench changes before or after the road.
c) The contractor shall lay cable by Horizontal direct drilling (HDD)
in main roads and highway with heavy traffic, passage to public
property where excavation is not possible. Contractor shall take
approval for laying of cable by means of HDD wherever required
from the supervising engineer. The cable laid by HDD shall be
Page 5 of 44
GN101-03-SP-06-R3
minimized so that it doesn’t exceed by 12% of total route length.
This is to avoid De‐rating of Cables.
d) Unless approved by BSES, the contractor shall lay the cables,
direct in ground, in single layer. The cables shall be laid with the
pre‐determined and approved cable route.
e) Spacing shall be maintained uniformly between the cables all
along the length including the bends, as approved by BSES. To
maintain the spacing, suitable non‐metallic formers shall be
placed uniformly with spacing not exceeding 5 meters. Every
bend shall have at least one spacer.
f) 75 mm of the sand bed shall be placed at the bottom of cable
trench.
g) After the cables have been laid the trench shall be filled with the
sand and shall be well rammed to a level not less than 75 mm
above the top of the cables all throughout the route.
h) To protect the cables against external mechanical damage, which
may be caused by other agencies, the cable shall be protected by
suitable cover. (for drawing of RCC cable cover refer annexure
VI).
i) The type of the covers shall be as under
‐ 1.1KV Cables – Single layer of brick thickness not less than
75 mm ( 3 inch)
‐ 11KV Cables – sand stone of thickness not less than 75mm (
3 inch).
‐ 33KV Cables shall be protected by reinforced concrete cover of
width 300 mm as per attached drawing with thickness not less
than 50mm.
‐ 66KV Cables shall be protected by reinforced concrete cover as
per attached drawing with thickness not less than 50mm.
The RCC cable cover shall be embossed as “BSES EHV
CABLE”.
j) Back fill to be filled up to 75mm and the warning tape shall be
installed continuously. The tape shall be yellow in colour with
Black / Red lettering of minimum 20mm height. The approved
warning message shall be written in English and Hindi/ local
language. The minimum thickness and width of the tape should
be 300 microns and 150 mm respectively.
k) The trench shall be filled‐up by loose soft soil (300mm) and
Excavated soil as indicated in drawings.
2.9 Cable over On Bridges the cables are generally supported on wooden cleats and
Page 6 of 44
GN101-03-SP-06-R3
Bridges clamped on steel supports at regular intervals. The cables laid on bridges
shall be provided with Sun shield.
Approval from appropriate authorities (PWD/railways) as applicable shall
be taken by contractor.
2.10 Laying of Single a) The single core cables shall be laid in trefoil formation. Single
Core Cables core cables can be laid individually in HDPE pipe in case
of HDD only. (Details of HDPE Pipe as per Annexure-9)
b) For single core cables laid in trefoil formation, plastic cable ties
shall be used at interval of 1.0 (one) meter throughout the cable
length to maintain the trefoil arrangement.
c) To balance the inductance, the phase sequence in trefoil format
shall be maintained by vendor ( for double circuit)
d) To prevent magnetic losses (eddy current and hysteresis losses),
the base plate of the panels or the terminal box of the
equipments, shall have aluminium plate. In case the entry into
the building is through GI pipe, a “slit” in the GI pipe shall be
necessary. Alternatively GI pipes may altogether be avoided and
non‐metallic pipes such as PVC or HDPE pipe shall be used.
Concrete pipes having steel reinforcement (RCC pipe) are not to
be used.
2.11 Earthing of a) Single point bonded earthing shall be employed to prevent flow
Single Core of induced circulating current in the armour and screen and
Cables consequential de‐rating of cables for feeder less than 2.0 KM.
b) For feeder length more than 2 KM, mid point earthing shall be
provided.
2.12 Violation of On violation of barricading guideline and safety norms, a fine of Rs.5000
barricading /day shall be imposed.
guideline and BRPL inspector/engineer in‐charge shall be empowered to impose the
safety norms above penalty.
3.0 General guidelines for Laying Cables
Page 7 of 44
GN101-03-SP-06-R3
showing the entire route, road crossings, location of joints and
also the arrangement of cables to be laid. In case due to site
exigencies, cables have to cross over within the trench, the same
shall be shown in the drawing. For each and every job, these
drawings shall be approved by BSES, prior to commencement of
work.
d) BSES shall arrange for all the material and manpower required
for jointing and end termination. The Contractor shall provide
pit, carry out excavation for creation of working space required
for jointing by the jointer. All civil works, structural work,
clamping and earthing shall be carried out by the contractor, so
that the cables and accessories perform satisfactorily during the
entire life time.
e) The entry and exit of the cables into the building shall be through
RCC or GI pipe except for single core cables, which shall be
properly sealed and shall be duly supported as per the method
and technique approved by BSES, so that the outer sheath of the
cable does not get damaged at the entry and exit points. The
sealing should be of adequate length so that it minimizes the risk
of spreading of fire or ingress of water.
3.2 Handling and a) The cable drums shall be transported upright, so that the weight
Storage of is distributed on both the flanges. Under no circumstances the
Cable drums (All cable drum may be laid on its side. During transportation the
empty drums are drums must be properly secured. The cable drums should never
returnable) be dropped from Lorry or a trailer, so as to prevent damage to
the cable drum and also to the cable. Ramp may be used for
unloading. The drums may be rolled over short distance,
provided the correct direction of rolling as provided on the drum
is observed. Alternatively, a mobile crane should be used for
lifting and lowering the drum. A chain‐pulley arrangement may
also be used to lift the drums and deposit the same on ground if
required.
b) In case the drums are to be stored prior to cable laying, they
should be arranged in such a way to leave some space between
them for air circulation. It is desirable that the drums stand on
battens placed directly under the flanges. Overhead covering is
not essential except in heavy rainfall areas or during monsoon.
Cable should however be protected from direct rays of sun by
leaving the battens on or by providing some form of sunshade. In
no case the drums shall be stored in a flat position with flanges
horizontal.
c) For transportation of the cable drums from storage site to work
site, the drum should be mounted on a trailer or an open lorry
and unloaded by mobile cranes.
d) After cable laying, empty cable drums shall be taken return back
by vendor from site at their own risk and cost. Cost of empty
drums shall be deducted from vendor account during final
settlement.
3.3 Cable Laying a) The ground over which the drum is positioned at site should be
Page 8 of 44
GN101-03-SP-06-R3
properly consolidated and jacks placed on both sizes of the drum
to make the pay‐off arrangement stable. Suitable arrangement
be made to stop the drum rotation, during cable laying
preferably by square wooden poles kept temporarily pivoted
over cable roller under the flanges which when required can be
applied on the flange as a brake by personnel manning the drum.
b) The cable should always be paved off from the top of the drum.
The drum must be positioned in such a way that the arrow on
the drum points opposite to the direction of rotation marked on
the drum.
c) It must be ensured that the cable is not dragged over sharp
object or on the road surface, so as to avoid damage to the outer
sheath of the cable.
d) The pulling method to be used shall be approved by BSES. Cable
supplier’s recommended maximum pulling tension shall not be
exceeded.
e) Rollers shall be placed at intervals and the cable shall be pulled
over the rollers. The rollers shall be kept lubricated so that they
rotate freely, minimize friction to the cable in motion. Rollers
shall be positioned at the bends to minimize side wall friction.
The contractor shall ensure that PVC/HDPE sheath of cable is
free from damage due to abrasion.
f) The cable should not be pulled out from the drum by lifting of
the coil while the drum is lying flat on the flange. This leads to
twisting of the armour and cores resulting in permanent damage
to the cable.
g) To avoid ingress of moisture, it must be observed that the end
capping of the cables is not damaged. Cut pieces of the cables
must be capped immediately, before laying of the same is taken‐
up.
3.4 Excavation of a) The excavation of the trenches shall be commenced, with proper
the Trenches co‐ordination with BSES, so that all the necessary clearances for
the route are already obtained from the competent authorities,
well in time.
b) Before opening of the section of the trench, the contractor shall
satisfy himself that the line of the trench is clear of underground
obstructions, by taking out trial pits on the line of the trench.
c) The exact location of each trench shall be approved on site by
BSES. The trenches shall be kept as straight as possible and each
trench shall be excavated to approved formation and
dimensions. If necessary, the trenches shall be adequate shored
by wooden planks and bracing to avoid trench cave‐ins which
would cause injury to the persons and also damage the cables
laid.
d) The bottom of each trench shall be firm and of smooth contour.
The contractor shall take reasonable precautions to prevent
damage to the highway or ground surface from a slip or breaking
away of the sides of the trench.
e) The trench excavation and filling in shall be so executed that all
Page 9 of 44
GN101-03-SP-06-R3
walls, roads, sewers, drains, pipes, cables, structures, places and
things shall be reasonably secured against risk of subsidence or
injury and shall be carried out to the satisfaction of the
authorities concerned. Should, however, a damage to an existing
or other services be made, the Contractor will arrange and pay
for any necessary repair, to make good the damages.
f) Where trenches pass from a footway to a roadway or at other
positions where a change of level is necessary, the bottom of the
trench shall rise or fall gradually. The rate of rise or fall shall be
approved by BSES.
g) Contractor shall ensure that during excavation and until
restoration has been completed, for reasonable access of
persons and vehicles to property or places adjacent to the route.
h) When the excavation of the trenches has been accurately
executed, the contractor shall inform BSES for approval. Laying
of cables or building of structure shall not be started until the
contractor has been advised by BSES to proceed with the work.
3.5 Excavated a) The materials excavated from each trench shall be placed so as
material to prevent nuisance or damage to adjacent ditches, drains
fences, gateways and other property or things. Excavated
material shall be stacked so as to avoid undue interference with
traffic.
b) Where, owing to traffic or for reasons of safety or other
considerations, this is not permissible, the excavated material
shall be removed from the site and returned for refilling the
trench on completion of laying; surplus material shall be
disposed off by the contractor at his own cost.
3.6 Pipes and a) Care shall be taken to make the bend of the pipes or duct lines as
Ducts easy as practicable and in no case of radius less than 3 meters.
Where approved, split pipes may be used on bends, the pipes
being fitted round the cable after laying.
b) All road crossings shall be ducted. This applies to present and
future roads as indicated on the route plans. The pipes and the
ducts shall be laid in an approved manner and shall be
surrounded by 150 mm of PCC (1:2:4)
c) Ducts under the road shall be provided by the contractor, by
non‐disruptive method, if road cutting is not permitted by the
concerned authorities Cable laying shall be done by Horizontal
Direct drilling method (HDD).
d) The cables shall be suitably protected at entry and exit from the
pipes, so that the outer sheath does not come in contact with
the edges of the pipes / ducts. The pipes and ducts shall have
slope so that the seepage water can drain through the small
opening provided on the lower side of the pipe sealing.
e) The pipes and ducts shall be secured to the base at both ends
and at regular interval, throughout the length, so that at no point
the ducts or pipes get suspended over the threaded cable, and
damage the same, thus defeating the very purpose of providing
the pipe / duct.
Page 10 of 44
GN101-03-SP-06-R3
f) At all road crossings at least one spare duct / pipe shall be
provided for future use. The pipe shall be thoroughly cleaned of
obstructions. A draw wire or rope shall be left in each pipe to
facilitate the drawing in of the cables. The duct end shall be
sealed temporarily to prevent the entry of foreign matter. End
caps and permanent markers shall be placed flush with footpath
/ roadways at both the ends. The pipes and ducts shall be
cleaned again immediately before the cables are drawn in.
g) The internal diameter of the pipe / duct should be such that the
cables occupy only 40% of the area of the pipe / duct to avoid
de‐rating.
3.7 Joint Bays The contractor shall provide all help so as to enable jointers to carry out
their work efficiently and expeditiously. The method of securing and
supporting cable joints and cables also the bonding and earthing thereof,
shall be detailed on the drawing. The details shall be approved by BSES
prior to commencement or work. The joint position should be staggered.
3.8 Back filling of a) Filling in of trenches shall not be commenced until BSES has
trenches inspected and approved the cables and accessories at site. The
inspection should be got done on daily basis so that the trenches
do not remain open unnecessarily, to avoid inconvenience to
public.
b) The trench shall be backfilled after putting all protections for
cables.
c) Soft soil shall be backfilled for 300 mm above the cable
protection cover.
d) Caution Tape shall be laid all along the cable route above the soft
soil filling.
e) Complete backfilling shall be done above the caution tape.
3.9 temporary a) Where cables routes are in public highways, footpaths, gardens
Reinstatement etc., the method of reinstatement will be subject to approval by
MCD. All costs incurred will be at the contractor’s expenses.
b) The contractor shall be responsible for proper permanent
reinstatement of the upper levels, which shall be carried out to
the satisfaction of BSES and the MCD authorities concerned.
c) Before finally leaving site, permanent reinstatement shall be
executed by the contractor to the approval of MCD and the
property owners and all costs incurred shall be to the
contractor’s account.
3.10 Permanent a) In public roads and footways the surfaces and foundations shall
Reinstatement be temporarily reinstated by the contractor. After settlement,
of Public Road, temporary reinstatement material shall be removed as necessary
and the permanent reinstatement shall be carried out to the
approval of the appropriate highway authority / MCD. Stone and
pre‐cast concrete paving kerbs and channels shall also be finally
reinstated by the contractor.
b) Temporary reinstatement shall be maintained by the contractor
until commencement of final reinstatement to ensure that the
surface is always safe for the passage of pedestrians and
vehicular traffic.
Page 11 of 44
GN101-03-SP-06-R3
Page 12 of 44
GN101-03-SP-06-R3
Page 13 of 44
GN101-03-SP-06-R3
and asphalted road)
The drawing are shown in annexure IV
The guidelines for road restoration for various type of roads
and surfaces are indicated in annexure V as :‐
‐ Bituminous road Type I (category I & II)
‐ Bituminous road Type II (category III)
‐ Cement concrete road
‐ Kota/Rajasthan stone Road
‐ Brick Road
‐ Interlocking paving tiles.
‐ Agra stone road
‐ Chequered tiles road
‐ Asphalted road
4.0 Testing
Page 14 of 44
GN101-03-SP-06-R3
clearance Road cutting permission shall be taken from competent authority by
vendor. How ever official fees shall be paid by BRPL.
b) Electrical inspector clearance
Electrical Inspector clearance shall be in vendor scope. How ever
official fees shall be paid by BRPL.
5.0 Progress Reporting:
Page 15 of 44
GN101-03-SP-06-R3
7.0.0 Deviations
Deviations from this Specification shall be stated in writing by the contractor. Written approval shall
be obtained from BSES by the contractor. In absence of such a statement, it will be assumed by BSES
that the Contractor complies fully with this specification during execution of the job.
Deviation mentioned in any other submitted tender docs like in GTP, QAP, Old PO, old WO, BRPL
Standard, vendor standards etc. shall not be considered as a deviation at any stage of contract.
The format for approval of deviation attached in annexure # 1
Annexure # 1 – DEVIATION REPORT FORMAT
S. Clause No. of Details about Reason for Approved by (Sign &
NO. Specification deviation deviation Name)
Annexure # 2 – DC HIGH VOLTAGE TEST
Rated Voltage Test Voltage Between Duration in Min.
of cable in KV
Any conductor and Conductor to
metallic sheath / conductor (for
Screen / armour unscreened Cables)
0.65 / 1.1 3 3 15 Min
6.35 / 11 18 30
19 / 33 60 ‐‐‐‐
38 / 66 90 ‐‐‐‐
Reference value for DC High voltage Test.
Page 16 of 44
GN101-03-SP-06-R3
Annexure # 3 – CABLE TRENCH DETAILS
S. No. Cable Size Trench Cable Trench drawing
reference
Width (mm) Depth (mm)
1 1.1 kV LT Cables
a 3.5Cx150 mm2 ‐ Single 400 875 A – 1 (Drg. # 9)
Circuit
b 3.5Cx150 mm2 ‐ Double 400 875 A – 1 (Drg. # 9)
Circuit
c 3.5Cx150 mm2 ‐ Triple 400 875 A – 1 (Drg. # 9)
Circuit
d 3.5Cx300 mm2 ‐ Single 400 875 A – 1 (Drg. # 8)
Circuit
e 3.5Cx300 mm2 ‐ Double 400 875 A – 1 (Drg. # 8)
Circuit
f 3.5Cx300 mm2 ‐ Triple 400 875 A – 1 (Drg. # 8)
Circuit
2 11 KV Cables
a 3Cx150 / 300 mm2 ‐ Single 400 1055 A – 2 (Drg. # 6)
Circuit
b 3Cx150 / 300 mm2 ‐Double 650 1055 B – 1 (Drg. # 7)
Circuit
3 33 kV Cables
a 3Cx400 mm2 ‐ Single Circuit 400 1235 A – 3 (Drg. # 3)
b 3Cx400 mm2 ‐ Double 650 1235 B – 2 (Drg. # 4)
Circuit
c 3Cx400 mm2 ‐ Quadruple 650 1235 B – 2 (Drg. # 5A)
Circuit
d 3Cx400 mm2 ‐ Quadruple 650 1545 B – 3 (Drg. # 5B)
Circuit
e 3Cx400 mm2 ‐ Quadruple 1200 1235 C – 1 (Drg. # 5C)
Circuit
4 66 kV Cables
a 1Cx630/1000 mm2 ‐ Single 650 1445 B – 4 ( Drg. # 1)
Circuit
b 1Cx630/1000 mm2 ‐ Double 1200 1445 C – 2 (Drg. # 2)
circuit
c 3Cx300 mm2 ‐ Double circuit 1200 1445 C – 2 (Drg. # 2A)
Page 17 of 44
GN101-03-SP-06-R3
Annexure # 4 – Standard Road Profile
Page 18 of 44
GN101-03-SP-06-R3
Page 19 of 44
GN101-03-SP-06-R3
Annexure # 5 – Road Restoration Sectional Drawing
Page 20 of 44
GN101-03-SP-06-R2
Page 21 of 44
GN101-03-SP-06-R3
Page 22 of 44
GN101-03-SP-06-R3
Page 23 of 44
Page 24 of 44
Page 25 of 44
Page 26 of 44
Page 27 of 44
Page 28 of 44
Page 29 of 44
Page 30 of 44
Page 31 of 44
Page 32 of 44
Page 33 of 44
Page 34 of 44
Page 35 of 44
Page 36 of 44
Page 37 of 44
GN101-03-SP-06-03
• Helmets
Page 38 of 44
GN101-03-SP-06-03
• Mask
• Jacket
• Shoes
• First Aid Box etc.
Shall be available at site 24x7. Zero tolerance on absence of PPEs to the
working personnel. No excuse shall be acceptable in this regards.
19. GPR/Scanning shall be done by vendor of whole the route and same shall be
submitted to BRPL. This work shall be done by vendor before execution of
job.
20. Jointing TAT- Jointing to start within 48 hrs. and shall be completed by 96
hrs.+1 day.
21. Lifting of cable drums with hydraulic machine, pulling of cable from top end
of drum with pulling machine (hydraulic winch) is mandatory.
22. Violation on barricading guideline and safety norms, a fine of Rs.5000 /day
shall be imposed. BRPL inspector/engineer in-charge shall be empowered to
impose the above penalty.
Page 39 of 44
GN101-03-SP-06-03
Page 40 of 44
Page 41 of 44
Page 42 of 44
Annexure#9-Note for HDPE Pipe Diameter in Cable Laying
1) Primarily our intent for laying cable will be through open trench only.
2) Trench dimensions shall be as per the standards which mentioned as below
table
3) QC team will do stage inspection after completion of digging to validate the depth
of trench and will give approval for issuing of cable.
4) Execution in charge to ensure the cable laying work.
5) QC team will also inspection the laying work to validate the laying as per
standards before back filling.
6) In case of site constraints, trench less cable laying shall be allowed as per the
followings-
a) Cable laying up to 50 mtr through trenchless will be allowed with approval of
circle head (O&M) for road crossing or site constraints. Site photos of
constraints shall be reviewed before approval by circle head.
b) Absence of permission for digging- written disapproval by road owing agency
and appropriate approval by circle head (for O&M Jobs), by O&M head (for
11kV, P&C job) and by EHV head (for EHV Jobs)
c) The size of HDPE (PN6, PE80) pipe shall be as per the guidelines of IS-1255,
1983, clause no-6.3.4.3. Details mentioned below in below table-
Page 43 of 44
d) In-case of using lower size of HDPE pipe due to site conditions, the deviation
for using lower HDPE pipe from above table, written approval must be taken
through technical committee. Photos of the challenges while apparently the
same will be reviewed by technical committee.
(However, HDPE pipe size with less than 1.5XOD of cable shall not be
allowed at any stage)
Page 44 of 44
Technical Specification for
Specification no – GN101-03-SP-18-01
___________________________________________________________________________________________
Page 1 of 25
GN101-03-SP-17-01
Index
List of Annexure……………………………………………………………………..……..10
___________________________________________________________________________________________
Page 2 of 25
GN101-03-SP-17-01
1. Scope of supply
The equipment shall confirm to this specification and latest revision of following codes
with all amendments:-
3. Service Conditions
The feeder pillar panel shall be designed to work satisfactorily under following service
conditions:-
Title Indian Standard
3.1 Supply Voltage 3 phase neutral, AC 433Volt +/-10%
3.2 Supply Frequency 50 Hz +/- 5%
3.3 Location of panel Outdoor, on foot path or roadside
3.4 Pollution Heavily Polluted and Dry
3.5 Humidity 90% maximum
3.6 Ambient Temperature Average 40 Deg C, Maximum 50 Deg C
3.7 Incoming supply to feeder From distribution transformer or Main feeder
pillar panel pillar panel
3.8 Seismic Zone 4
___________________________________________________________________________________________
Page 3 of 25
GN101-03-SP-17-01
4.0 Feeder Pillar Type Incoming feeder ( Circuit Outgoing feeder ( Circuit
ways ) & Cable size ways ) & Cable size
4.1 A-1 , 8-Way 2 X 400A TP fuse / cable 6 X 250A TP fuse / cable
size 4CX300Sqmm size 4CX150Sqmm
5. Panel Construction
5.0 Panel Construction Free Standing floor mounted with steel frame,
5.4 Base frame for 8 Way 3mm MS Channel 50mm height painted in Black
& 7 way panel Color
5.5 Bottom holes on four Oval Shape, for grouting bolts
Sides
5.6 Pedestal for 5 way Of height 400mm with side covers of FRP or
Galvanized MS painted in black
___________________________________________________________________________________________
Page 4 of 25
GN101-03-SP-17-01
5.10 Door type for front & Centre Opening double leaf with insulating rubber grip
rear access handle
5.11 Double leaf doors Right hand side leaf can be opened only after left
hand side leaf
5.14 Padlocking facility For Front and Rear door by total 4 nos L- drop
arrangement. 2 nos front door and 2 nos rear door.
5.21 Bus for 8 – Way Bolted type removable link to be provided at middle of
all the phases and neutral bus bar to adapt two
incomers from separate source.
5.22 Earth Bus at panel 25X6mm Aluminum
bottom
5.23 Bus bar arrangement Horizontal, with R phase bus at top
5.24 Neutral bus bar With holes for connection incoming and outgoing
cables up to 300Sqmm
5.25 Bus Bar support SMC / DMC, 1100v Grade
insulators
___________________________________________________________________________________________
Page 5 of 25
GN101-03-SP-17-01
5.35 Gland plate at panel Galvanized MS, 3mm thick for multi core cable
bottom
___________________________________________________________________________________________
Page 6 of 25
GN101-03-SP-17-01
6. Fuse Base
7. Operational requirements
8.4 Marking for panel earth stud Green letter ‘E’, on riveted AL label
8.5 Danger board in English and local Red color background with black
language, riveted on doors lettering on 1.6mm thick Al plate
9.1 Door type for front access Centre Opening double leaf with
insulating rubber grip handle only front
side.
9.2 Rear side No door at read side. Panel to be
access only from front.
9.3 All other constructions shall be as per above mentioned construction
9.4 Use of compacted feeder pillars Where sufficient space at rear side is
not available due to space constraints
at site.
___________________________________________________________________________________________
Page 8 of 25
GN101-03-SP-17-01
10.2.9 No negative tolerance on bus bar dimensions and bus bar clearances
12. Deviation
___________________________________________________________________________________________
Page 9 of 25
GN101-03-SP-17-01
List of Annexure
___________________________________________________________________________________________
Page 10 of 25
GN101-03-SP-17-01
Bidder to submit hard copy duly filled and signed along with techno commercial offer.
Bidder to submit separate GTP for each type of feeder pillar panel
S. BRPL / BYPL
Particulars Vendor Data
No Requirement
Name
1 Manufacturer Address
Contact no.
Quantity
Rating in amp
4 No. of Incoming feeders
Quantity
Rating in amp
5 No. of Outgoing feeders
___________________________________________________________________________________________
Page 11 of 25
GN101-03-SP-17-01
Phase= 50X6MM
5 Way
Neutral= 50X6MM
___________________________________________________________________________________________
Page 12 of 25
GN101-03-SP-17-01
___________________________________________________________________________________________
Page 13 of 25
GN101-03-SP-17-01
Continuous rated
40 433volt +/- 10%
operating voltage
High voltage withstand
41 2000V at 50Hz for 1 min.
capacity
___________________________________________________________________________________________
Page 14 of 25
GN101‐03‐SP‐80‐00
TECHNICAL SPECIFICATION OF NUT, BOLTS & WASHERS
INDEX
4. TESTS 3
5. INSPECTION 4
8. MARKING 4
9. PACKING 4
Page 2 of 9
GN101‐03‐SP‐80‐00
TECHNICAL SPECIFICATION OF NUT, BOLTS & WASHERS
1. SCOPE OF SUPPLY
The specification covers the manufacturing, testing and inspection of Nut, Bolts & Washers.
2. CLIMATIC CONDITION
The material to be supplied against this specification shall be suitable for satisfactory
operation under following climatic condition
Location At various location in the Delhi
Maximum ambient temperature (⁰C) 50
Minimum ambient temperature (⁰C) 0
Maximum altitude above mean sea level 1000
(m)
Relative Humidity (%) 100
Rainy month June to October
Maximum Rainfall (mm) 1450
Wind Pressure (Kg/Sq.m) 195
Seismic Zone Zone IV as per IS : 1893
3. CODES & STANDARDS
The Nut & bolt shall be designed, manufactured and tested in Accordance with the following
Indian standards.
IS‐ 12427 Specification for Transmission Tower Bolts
IS‐4072 Steel for Spring Washer
IS‐3063 Single Coil Rectangular section Spring Washer for bolt, nut & Screw
IS‐1586 Methods for Rockwell Hardness test for steel
IS‐2016 Plain Washer
ISO 898/1‐1988 Metric Bolts, Screws and Studs
IS‐2633 Methods of testing of uniformity of coating of zinc coated articles
IS‐6745 Method of determining of mass zinc coating on zinc coated iron &
steel articles
IS‐1363 (All parts) Hexagonal bolts & nuts
IS‐1367 (Part‐iii) Technical supply condition for threaded steel Fastner
IS‐4759 Hot dip Zinc coating on structural Steel & other allied Products
DIN 127 A Spring Lock Washers
4. TESTS
All types of test including routine test shall be carried out according to IS : 1367‐1967 or its latest
amendment.
Page 3 of 9
GN101‐03‐SP‐80‐00
TECHNICAL SPECIFICATION OF NUT, BOLTS & WASHERS
5. INSPECTION:
The material shall be inspected and tested before dispatch by an authorized representative of
the BSES in respect of quality. In case the supplier is not in position to get these tests carried out
at his work, such test may get be carried out by hum at any NABL accredited lab at his own
expenses.
6. TEST CERTIFICATES:
The supplier shall supply one set of test certificates from any NABL accredited lab in respect of
quality as per IS: 1363‐1967 with latest amendment for approval of the purchaser.
7. INSPECTION AFTER RECEIPT AT STORE:
BSES inspector will inspect the material received at BSES Store and shall have right to reject if
found different from the reports of pre‐dispatch inspection.
8. MARKING:
The material shall be marked with the ISI certification mark.
I. Manufacture’s name or trade mark.
II. Place of manufacturers.
III. The name & designation of consignee
IV. Ultimate destination as required by the purchaser.
V. Net weight with description of material.
VI. The marking shall be stencilled in delible link on gunny bag.
VII. The manufacturer's identification symbol.
VIII. The hexagonal head bolts shall be marked with the following symbols on the top surface
of the bolt head either embossed or identified as given below. The manufacturer's
identification symbol.
IX. Minimum height of marking shall be 3.0 mm. When embossed, marking shall project not
less than 0.3 mm above the surface of the head and total head height (Head plus
marking) shall not exceed the specified maximum head height plus 0.4 mm.
9. PACKING:
The supplier shall be responsible for suitable packing of all the material and marking on the
consignment, so as to avoid any damage during transport and storage and to ensure correct dispatch
Page 4 of 9
GN101‐03‐SP‐80‐00
TECHNICAL SPECIFICATION OF NUT, BOLTS & WASHERS
to the destination. The packing shall be conforming to the requirement laid down in IS : 3256‐1965
or its latest amendment.
Electro galvanized spring washers shall be packed in cartons of 500 or 1000 numbers.
Each carton containing the spring washers shall be marked with the manufacturer's name
Or trade mark, type, nominal size and quantity of the washers.
.
10. GTP FOR NUT, BOLTS & WASHERS :
S.
Technical particular Hot Dip galvanized Hexagonal bolt
No.
Mechanical Properties/ particular to which the
Bolt will confirm IS 1367 (Part ‐2)‐1979
1 product grade –C
i Tensile Strength N/mm2 (Strength under wedge loading)
ii Rockwell hardness HRB
iii Yield Stress N/mm2
Iv Stress under proof load N/mm2
v Strength under wedge loading Kg/mm2
vi Wt of Zinc Coating g/mm2
vii Shear strength N/mm2
2. Specification & standards for M.S. Bolts & As per IS 1363(part 1 & 3) IS: 1367( part 3 & 6) IS: 1367
Nuts(Black) (part 17) & other Relevant standards with latest
amendments
3. Property class:
a. Bolts a. I) M10 to M16, length 40 mm to 80 mm
min HT 4.8 grade
ii)For others min 4.6 grade
b. Nuts b. Min 5
4. Size Assorted size
5. Tolerance As per IS
6. Raw material:
a) Grade As per IS :2062
b) Type of steel used
Low Carbon Steel(Grade C) as per IS : 2062
Page 5 of 9
GN101‐03‐SP‐80‐00
TECHNICAL SPECIFICATION OF NUT, BOLTS & WASHERS
7. Chemical composition (%)
a) For Hexagonal bolts:
i) Carbon (Max.)
ii) Phosphorous (Maxm.)
0.55%
iii) Sulphur (Maxm.) 0.05%
b) For Hexagonal nuts: 0.06%
i) Carbon (Maxm.) 0.50%
ii) Phosphorous(Maxm.) 0.06%
iii) Sulphur (Maxm.) 0.15%
8 Mechanical properties: i) For Hexagonal bolts: As per IS: 1367( Pt. 3) 400 225 114 Min. to 258 Maxm.
a) Tensile strength N/mm Sq. Minm. b) Stress 67 Min. to 99.5 Max. 120 Min. to 250 Maxm. 22% 400
under proof load N/mm Sq.Minm. c) Brinell No Fracture As per IS: 1367 (Pt.6) 610 130 Min. to 302
Hardness HB d) Rockwell Hard HRB e) Vickers Max.
Hardness HV f) Elongation after fracture g)
Strength under wedg. Loading N/mm
Sq.Minm. h) Head soundness ii) For Hexagonal
nuts a) Proof stress N/mm Sq.min. b) Vicker
Hardness HV‐HV‐Minm/Maxm
9 Sampling procedure As per IS :2614/1969 with latest amendments.
10 Packing details Material to be supplied in double gunny bag of 50Kg
PLAIN WASHERS:
The plain washers shall be Hot dip Galvanized in accordance with the requirements of lS:4759‐1984
"Specification for Hot‐Dip Zinc coating on structural steel and other allied products" (Second‐revision) except
that the minimum value of the average mass of coating shall be 300 g/m2,shall be conforming to lS: 1363-
1967. Plain washers shall be conforming to lS: 2016-1967.
SPRING WASHERS:
Page 6 of 9
GN101‐03‐SP‐80‐00
TECHNICAL SPECIFICATION OF NUT, BOLTS & WASHERS
11. INSPECTION TESTING CRITERIA :
Sr Testing Lot Size
Requirement Product BSES lot Size
No. Standards (Manufacturers)
Chemical Every 20th
1 NBW IS : 228 Each Consignment
Composition Consignment
NBW Every 20th
2 Dimension IS : 2141 ‐ 2000 Each Consignment
Consignment l
NBW As per relevant Every Fifth Every 20th
3 Tensile Strength
IS Consignment Consignment
NBW Every Fifth Every 20th
4 Proof load Test IS : 898‐2 1992
Consignment Consignment
NBW
5 Coating Test
NBW Every Fifth Every Fifth
5.1 Wt of of Zinc Coating IS : 6745 ‐ 1972
Consignment Consignment
Uniformity of Zinc NBW Every Fifth Every Fifth
5.2 IS : 2633 ‐ 1986
Coating Consignment Consignment
Adhesion of Zinc NBW Every Fifth Every Fifth
5.3 IS : 4826 ‐ 1979
Coating Consignment Consignment
Page 7 of 9
GN101‐03‐SP‐80‐00
TECHNICAL SPECIFICATION OF NUT, BOLTS & WASHERS
Note: ‐
• Corrosion Protection (all items shall be hot‐dip galvanised in accordance with AS 4680 or
AS1214)
• Hot dip Galvanized Bolt with one Nut, two Plain Washer and one Spring Washer which is electro
galvanised
• Nickel chromium plated bolts with one Nut, two Plain Washer and one Spring Washer which is
electro galvanised
• Full threading is required for bolts sizes up to length 100mm and minimum thread length of
38mm for bolts sizes having length more than 100mm
• All electrical connection hardware ( M10 to M16, length 40 mm to 80 mm) shall be minimum HT
4.8 grade for other size 4.6 grade.
S.No Description
Bolt (G.I)
1 BLT,HEX,M16X150MM;GI
2 BLT,HEX,M16;175MM;GI
3 BLT,HEX,M16;225MM;GI
4 BLT,HEX,M16;250MM;GI
5 BLT,HEX,M16X300MM;GI
6 BLT,HEX,M16;350MM;GI
7 BLT,HEX,M16;125MM;GI
8 BLT,HEX,M10;40MM;GI;4.8
9 BLT,HEX,M12X40MM;GR 4.8
10 BLT,HEX,M16;100MM;GI
11 BLT,HEX,M16;75MM;GI GR 4.8
12 BLT,HEX,M6X20MM;GI
13 BLT,HEX,M16;200MM;GI
14 BLT,HEX,M16;400MM;GI
15 BLT,HEX,M16;25MM;GI GR 4.8
16 BLT,HEX,M12X60MM;GI;FULL THRD GR 4.8
17 BLT,HEX,M16X40MM;GI GR 4.8
18 BLT,HEX,M8X130MM;GI;MET
19 BLT,HEX,M12;60MM;GI; GR 4.8
20 BLT,HEX,M6X35MM;GI;GR 4.6;FULL THRD
Bolt (Nickel Chromium)
21 BLT,HEX,M16X100MM;NKL CHROMIUM
22 BLT,HEX,M12X50MM;NKL CHROMIUM GR 4.8
23 BLT,HEX,M16X 50MM;NKL CHROMIUM GR 4.8
24 BLT,HEX,M10X75MM;NKL CHROMIUM GR 4.8
25 BLT,HEX,M12X75 MM;NKL CHROMIUM GR 4.8
26 BLT,HEX,M16X75MM;NKL CHROMIUM GR 4.8
Bolt (MS)
27 BLT,HEX,M16MM;80MM;MS; GR 4.8 MET
Page 8 of 9
GN101‐03‐SP‐80‐00
TECHNICAL SPECIFICATION OF NUT, BOLTS & WASHERS
28 NUT,HEX,M10X40MM;MS;NUT BLT WSHR
29 BLT HEX MS ‐‐ MC 150MM M16
30 NUT,HEX,M10X40MM;MS;NUT BLT WSHR
31 BLT,HEX,M8X75MM;GALVANIZED ZN COATED MS
Eye Bolt
32 BLT,EYE,25MM;240MM;M12
33 OEM,EYE BLT OPERTG RD;1HYN400075P1
Washer (Spring)
34 WSHR,SPRNG,21MM;13MM;2.5MM;GALVANIZED MS
35 WSHR,SPRNG,11MM;17MM;2.5MM;GALVANIZED MS
Washer (Flat)
36 WSHR,FLT,37MM;13MM;3MM;NKL CHROMIUM
37 WSHR,FLT,50MM;17MM;3MM;NKL CHROMIUM
38 WSHR,FLT,24MM;13MM;2MM;GALVANIZED MS
39 WSHR,FLT,21MM;11MM;2.35MM;GALVANIZED MS
40 WSHR,FLT,30MM;10.5MM;2.5MM;NKL CHROMIUM
41 WSHR,FLT,23.8MM;8.4MM;2MM;NI CHROMIUM
Washer (Sling)
42 WSHR,SLNG,NEOPRENE;FOR M12STM
43 WSHR,SLNG,NEOPRENE;10MM;14MM;2MM
Washer (Teflon)
44 WSHR,TEFLON;22X32X5MM
45 WSHR,TEFLON;12X20X5MM
46 WSHR,TEFLON;18X22X5MM
47 WSHR,TEFLON;15X30X5MM
48 WSHR,TEFLON;20X30X5MM
49 WSHR,TEFLON;35X22X5MM
50 WSHR,TEFLON;46X32X5MM
51 WSHR,TEFLON;25X15X5MM
Washer (Brass)
52 WSHR,BRASS;LV FOR 990KVA XMER
53 WSHR,HEX;LV BRASS;FOR 630KVA TRAFO
54 WSHR,PLN;LV BRASS WSHR FOR 100KVA XMER
55 WSHR,CLAMPING MEMBER;AL;FOR HV BSHG
56 WSHR,BRASS;FOR HV SIDE TRNSF
Hex Nut (MS)
57 NUT,HEX,M10X40MM;MS;NUT BLT WSHR
58 NUT,LOCK,SHEARING;M6X25MM;5;SHEA;MS;A
59 NUT,HEX,M16;GALVANIZED MS
Page 9 of 9
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
INDEX
1. SCOPE OF SUPPLY 3
2. CLIMATIC CONDITION 3
3. CODES & STANDARDS 3
4. TESTS 4
5. INSPECTION: 4
6. TEST CERTIFICATES: 4
7. INSPECTION AFTER RECEIPT AT STORE: 4
8. MARKING: 4
9. PACKING: 4
10. GTP FOR G.I. PIPE (40 MM): 5
11. GTP FOR G.I. PIPE (20 MM / 32 MM) : 6
12. GTP FOR G.I. PIPE (100 MM) : 7
Page 2 of 2
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
1. SCOPE OF SUPPLY
The specification covers the manufacturing, testing and inspection of G.I Conduit & Earthing Pipe
2. CLIMATIC CONDITION
The material to be supplied against this specification shall be suitable for satisfactory operation
under following climatic condition
Location : At various location in the Delhi
Maximum ambient temperature (⁰C) 50
Minimum ambient temperature (⁰C) 0
Maximum altitude above mean sea level (m) 1000
Relative Humidity (%) 100
Rainy month June to October
Maximum Rainfall (mm) 1450
Wind Pressure (Kg/Sq.m) 195
Seismic Zone Zone IV as per IS : 1893
3. CODES & STANDARDS
The G.I. Conduit Pipe shall be designed, manufactured and tested in Accordance with the
following Indian standards.
IS :1239 Part (1) Steel Tubes, Tubular And Other Wrought Steel Fittings ‐
Specification
IS: 2633/72 & IS: For galvanising testing
6745/72
IS 1161 : 1998 Steel Tubes for Structural Purposes
IS 1387: 1993 General requirements for the supply of metallurgical
materials
IS 228 :1987 Methods of chemical analysis of steels
IS 1161 : 1998 Steel Tubes for Structural Purposes
IS 2629 : 1985 Recommended Practice’ for Hot‐Dip Galvanizing of Iron and Steel
IS 2633 : 1986 Methods for testing uniformity of coating of zinc coated articles
IS
IS 2629 : 1985 Recommended Practice for Hot‐Dip Galvanizing of Iron and Steel
IS 2500 :2000 Sampling of lot by lot
Page 3 of 3
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
4. TESTS
All types of test including routine test shall be carried out according to IS: 1239‐1 or its latest
amendment.
5. INSPECTION:
The material shall be inspected and tested before dispatch by an authorized representative of
the BSES in respect of quality. In case the supplier is not in position to get these tests carried out
at his work, such test may get be carried out by hum at any NABL accredited lab at his own
expenses.
6. TEST CERTIFICATES:
The supplier shall supply one set of test certificates from any NABL accredited lab in respect of
quality as per IS: 1239‐1 with latest amendment for approval of the purchaser.
7. INSPECTION AFTER RECEIPT AT STORE:
BSES inspector will inspect the material received at BSES Store and shall have right to reject if
found different from the reports of pre‐dispatch inspection.
8. MARKING:
The material shall be marked with the ISI certification mark.
I. Manufacture’s name or trade mark
II. ISI mark with CML No.
III. Purchase no. shall be stencilled indelible link
IV. The manufacturer's identification symbol
V. Hot marking at every running meter Name/logo of manufacturer, ISI, class of tube i.e. L
for Light colour of Band
9. PACKING:
The supplier shall be responsible for suitable packing of all the material and marking on the
consignment, so as to avoid any damage during transport and storage and to ensure correct dispatch
to the destination.
Page 4 of 4
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
10. GTP FOR G.I. PIPE (40 MM):
S.
Technical particular Unit BSES Requirement Vendor Data
No.
1 Name of the manufacturer
2 Ref IS No. IS: 1239(Part‐1) 2004
3 Type(Light , Medium, Heavy) Light
4 Ends (Plain/ Screwed) Plain
5 Size mm 40mm NB
6 Thickness mm 2.90mm
7 Max & Min outside diameter mm 48.4 (Max), 47.8 (Min)
8 Length of pipe mm 06 Mtrs. (±2%)
9 Mass of tube Kg/m 3.23
10 Tolerance on thickness % (+) Not limited, (‐) 8%
11 Tolerance on Mass % +10 %, ‐8%
12 Galvanizing thickness Gm/m2 360gm/m2 (Min.)
13 Tensile strength N/mm2 320 N/mm2 (Min.)
14 Elongation percent % 20% (Min.)
15 Embossing details Hot marking on every Name/logo of
metre Name/ logo of manufacturer,
manufacturer, IS No., PO
Class, ISI monogram No,ISI,Class of
tube i.e L for
light,Colour of
Band (PO no
provided in
stencil)
16 Color Coding Yellow color band
17 Make of steel Tata/SAIL/Reputed
make
18 Chemical composition certificate As per Table 1 of
IS:1239 (Pt‐I)‐2004
19 Max. permissible variation of chemical As per Table 2 of
composition IS:1239 (Pt‐I)‐2004
20 Leak proof test 5MPA for atleast 3
sec.
21 Tests
21.1 Test of tensile strength As per IS:1239 (Pt‐I)‐
2004
21.2 Bend test As per IS:1239 (Pt‐I)‐
2004
Page 5 of 5
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
11. GTP FOR G.I. PIPE (20 MM / 32 MM) :
S.
Technical particular Unit BSES Requirement Vendor Data
No.
1 Name of the manufacturer
2 Ref IS No. IS: 1239(Part‐1) 2004
3 Type(Light , Medium, Heavy) Light
4 Ends (Plain/ Screwed) Plain
5 Size mm 20mm NB/ 32 mm NB
6 Thickness mm 2.30mm/2.60mm
26.9 (Max), 26.4 (Min) for 20mm
&42.5 (Max), 41.9 (Min) for
7 Max & Min outside diameter mm 32mm
8 Length of pipe mm 06 Mtrs. (±2%)
9 Mass of tube Kg/m 1.38 for 20 mm & 2.54 for32 mm
10 Tolerance on thickness % (+) Not limited, (‐) 8%
11 Tolerance on Mass % +10 %, ‐8%
12 Galvanizing thickness Gm/m2 360gm/m2 (Min.)
13 Tensile strength N/mm2 320 N/mm2 (Min.)
14 Elongation percent % 12% (Min.)
15 Embossing details Hot marking on every metre Name/logo of
Name/ logo of manufacturer, IS manufacturer, PO
No., Class, ISI monogram No,ISI,Class of
tube i.e L for
light,Colour of
Band (PO no
provided in stencil)
16 Color Coding Yellow color band
17 Make of steel Tata/SAIL/ESSAR
18 Chemical composition As per Table 1 of IS:1239 (Pt‐I)‐
certificate 2004
19 Max. permissible variation of As per Table 2 of IS:1239 (Pt‐I)‐
chemical composition 2004
20 Leak proof test 5MPA for atleast 3 sec.
21 Tests
21.1 Test of tensile strength As per IS:1239 (Pt‐I)‐2004
21.2 Bend test As per IS:1239 (Pt‐I)‐2004
Page 6 of 6
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
12. GTP FOR G.I. PIPE (100 MM) :
S.
Technical particular Unit BSES Requirement Vendor Data
No.
1 Name of the manufacturer
IS: 1239(Part‐1)
2 Ref IS No. 2004
3 Type(Light , Medium, Heavy) Light
4 Ends (Plain/ Screwed) Plain
5 Size mm 100mm NB
6 Thickness mm 3.60 mm
113.9 (Max), 113.0
7 Max & Min outside diameter mm (Min)
8 Length of pipe mm 06 Mtrs. (±2%)
9 Mass of tube Kg/m 9.75
10 Tolerance on thickness (+) Not limited, (‐)
% 8%
11 Tolerance on Mass % +10 %, ‐8%
12 Galvanizing thickness Gm/m2 360gm/m2 (Min.)
13 Tensile strength N/mm2 320 N/mm2 (Min.)
14 Elongation percent % 20% (Min.)
15 Embossing details Hot marking on Name/logo of
every metre manufacturer, PO
Name/ logo of No,ISI,Class of
manufacturer, IS tube i.e L for
No., Class, ISI light,Colour of
monogram Band (PO no
provided in
stencil)
16 Color Coding Yellow color band
17 Make of steel Tata/SAIL/Reputed
make
18 Chemical composition certificate As per Table 1 of
IS:1239 (Pt‐I)‐2004
19 Max. permissible variation of chemical As per Table 2 of
composition IS:1239 (Pt‐I)‐2004
20 Leak proof test 5MPA for atleast 3
sec.
21 Tests
21.1 Test of tensile strength As per IS:1239 (Pt‐
I)‐2004
21.2 Bend test As per IS:1239 (Pt‐
I)‐2004
Page 7 of 7
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
13.0 GTP FOR GI EARTHING PIPE DIA 40 MM X 2.50 MTR CLASS B:
*Pipe may be perforated or non‐perforated, BRPL may ask as per requirement. Bidder has to
provide the same.
Page 8 of 8
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
Fig. 1 G.I. EARTHING PIPE DIA 40 MM X 2.50 MTR CLASS B
Page 9 of 9
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
13. INSPECTION TESTING CRITERIA:
Page 10 of 10
GN101‐03‐SP‐97‐00
TECHNICAL SPECIFICATION OF G.I. CONDUIT PIPES & EARTHING PIPE
Note: ‐
• GI Earthing pipe : Hot marking on every meter Name/logo of manufacturer, ISI monogram,
Color of band (Blue Color)
• GI conduit pipe : Hot marking on every meter Name/logo of manufacturer, ISI monogram,
Color of band (Yellow Color)
Page 11 of 11