F0810 - Pre-Post Rig Move Meetings Forms
F0810 - Pre-Post Rig Move Meetings Forms
F0810 - Pre-Post Rig Move Meetings Forms
1. Overview
General Information
Move Days
Standard rig move
7.59 DAY KPI Targeted Rig Move Days 6.9 DAYS
days (per matrix)
Move Distance
Rig Route distance Distance from Base Legal or Non Legal
2 KM 75-80 KM LEGAL
between locations Camp to old location move
Moving Loads Site Survey
Rig Site Number of Loads 164 Site Survey Completed Date 27-Dec-20
F0810 Page 1 of 18
2. Key Personnel
Superintendent 1
Rig Manger 1
Truck Pusher 2
Rigger 1 2
EMS technician 0
Additional Medic 0
Additional welders 0
2
Solas Techician
1
EPOCH Technician
Carpenters 0
Plumbers 0
AC Techician 0
Helper Electrician 1
Helper Mechanic 1
0
Electrician Sr. Technician
F0810 Page 2 of 18
3. Planned Maintenance Projects Scheduled during Rig Move
F0810 Page 3 of 18
4. Equipment List
Number
Standard Number
Equipment Number
Required
Committed ** Comments
*
Winch Truck 8 8 7
Super Truck 2 2 2
Forklift 2 2 2
Cranes 4 4 5
Highboy 6 6 6
Spreader Bars 0 0 0
Derrick dolly 1 1 1
Security 2 2 2
Thuraya 2 2 2
Additional ambulance 0 0 0
Coaster bus 1 1 1
Genie manlift 1 1 1
F0810 Page 4 of 18
Rig move - start date: 2-Jan-21
Number
Standard Number
Equipment Number
Required
Committed ** Comments
*
Winch Truck 8 8 7
Super Truck 2 2 2
Forklift 2 2 2
Cranes 4 4 5
Highboy 6 6 6
Spreader Bars 0 0 0
Derrick dolly 1 1 1
Security 2 2 2
Thuraya 2 2 2
Additional ambulance 0 0 0
Coaster bus 1 1 1
Genie manlift 1 1 1
F0810 Page 5 of 18
Post move - start date:
Number
Standard Number
Equipment Number
Required
Committed ** Comments
*
Winch Truck 8 8 6
Super Truck 2 2 1
Forklift 2 2 1
Cranes 4 4 3
Highboy 6 6 4
Spreader Bars 0 0 0
Derrick dolly 1 1 0
Security 2 2 0
Thuraya 2 2 2
Additional ambulance 0 0 0
Coaster bus 1 1 1
Genie manlift 1 1 1
F0810 Page 6 of 18
5. Other
6. Approvals
OTHER INFORMATION
F0810 Page 7 of 18
Additional information:
Any load that will be transported to Location# xxx should be documented in a cargo manifest and make sure that the load is
secured and measure height of each load before departing.
• PPE is mandatory for all Drivers.
• Reflective vest must be worn by all supervisors.
• Rig signs to be placed out
• Daily rig move planning and coordinate with Operations Supt, Rig Manager, and DRT Truck Pusher. Safety meeting to be
documented and share with Aramco Foreman.
• Daily report by rig superintendent to management.
• Ensure communication is available at all times.
• Ensure sufficient light towers are available for different work areas
• Rigger one must physically witness all critical lifting operations. Also to review the critical lifting plans prior to any lift.
• Safety Officer and Truck pusher will ensure all shackle & slings used are within valid inspection certificates / colour code
• All heavy equipment & operator must carry valid government & Saudi Aramco certificates.
• NO night driving unless it is very emergency.
• Ensure the rig Ambulance is standby with full tank fuel & all required medical equipment.
• Plan everything in advanced.
• Make sure we have qualified & experienced Driver for Rig move ( Nabors & Third Party)
• All trucks must be thoroughly checked before the rig move.
• Ensure all rental trucks drivers and truck pushers to attend the daily rig move safety meetings
• Follow rig move procedures.
Reference:
RMS – 09 Rig Move Manual
F0544 – Rig Load Analysis time plan
F0542 – Rig Move Plan Cover Sheet
F0543 – Rig Load Analysis Worksheet
F0538 – Rig Move Plan & Status report
F0726 – Daily Rig Move Planning & Safety Meeting
F0782 – Job Safety Analysis
RMS – Permit to Work System
F0813 Site Survey Checklist
F0810 Page 8 of 18
POST RIG MOVE MEETING
1. Overview
Following forms are available for review on post move meeting:
Pre move meeting F0810 Rig move plan Rig move plan cover sheet F0542
Rig load analysis F0543 Rig load analysis time plan F0544 Rig move plan and status report (daily)
General Information
Rig number 785, Rig release date and time 1-JAN-2021 0800HRS
Previous location QTIF 856 Spud in date and time 11-JAN-2021 1200HRS
Move Days
Standard rig move 7.59 DAY KPI Targeted Rig Move Days 6.9 DAYS
days (per matrix)
Move Distance
Rig Route distance Distance from Base Legal or Non Legal
2 KM 75-80 KM LEGAL
between locations Camp to old location move
Moving Loads
F0810 Page 9 of 18
2. Previous Rig Moves
2. Additional personnel
Superintendent 1 1
Rig Manger 1 1
Truck Pusher 2 2
Rigger 1 2 2
EMS technician 1
Additional Medic 0
Additional welders 0
Solas Techician 1 2
EPOCH Technician 1 1
Carpenters 1 2
Plumbers 1 2
AC Techician 0
Helper Electrician 1
Helper Mechanic 1
F0810 Page 10 of 18
4. Planned Maintenance Projects Scheduled during Rig Move
F0810 Page 11 of 18
5. Unplanned Maintenance during rig move
F0810 Page 12 of 18
6. Equipment List
Number
Standard Number
Equipment Number
Required
Committed ** Comments
*
Winch Truck 8 8
Super Truck 2 2
Forklift 2 2
Cranes 4 4
Highboy 6 6
Spreader Bars 0
Derrick dolly 1 1
Security 2 2
Thuraya 2 2
Additional ambulance 0
Coaster bus 1 1
Genie manlift 1 1
F0810 Page 13 of 18
Rig move - start date: 30-Dec-20
Number
Standard Number
Equipment Number
Required
Committed ** Comments
*
Winch Truck
8 8
Super Truck
2 2
Forklift
2 2
Cranes
4 4
Highboy
6 6
Spreader Bars
Derrick dolly
1 1
Security
2 2
Thuraya
2 2
Additional ambulance
Coaster bus
1 1
Genie manlift
1 1
F0810 Page 14 of 18
Post move - start date: 11-Jan-21
Number
Standard Number
Equipment Number
Required
Committed ** Comments
*
Winch Truck
8 8 0
Super Truck
2 2 0
Forklift
2 2 1
Cranes
4 4 1
Highboy
6 6 0
0
Bolster Beam / Derrick
0
Spreader Bars
Derrick dolly
1 1 0
Security
2 2 0
Thuraya
2 2 0
0
Additional ambulance
Coaster bus
1 1 0
Genie manlift
1 1 0
F0810 Page 15 of 18
7. Improvements and issues observed during rig move
Delay due to waiting on equipment or personnel (Nabors and 3rd party, provide MOL for 3rd
party):
Other:
F0810 Page 16 of 18
8.Action items to improve next rigmove (Lessons learned)
F0810 Page 17 of 18
F0810 Page 18 of 18