ABC Hospital - Solution
ABC Hospital - Solution
Project Operations
Agenda
Introduction
Characteristics of Project
Work Breakdown structure
Network Analyses
Critical Path Method (CPM)
Project Review & Evaluation Technique (PERT)
Network Representations
Activity on Node (AON diagram)
Activity on Arc (AOA diagram)
1
9/6/2021
2
9/6/2021
Characteristics of Project
Projects have specific life-cycle with a definite beginning and a
definite end called Project Duration.
Each Project consists of activities having inter-dependence. Some
activities cannot start till the predecessor activities are not
completed.
The requirements of resources are different during the progress of
the project and hence their assignment is a tricky business here.
Matrix form of organization is suitable when multiple projects are
being handled.
1 Project 1 Project 2
3
9/6/2021
4
9/6/2021
10
5
9/6/2021
11
12
6
9/6/2021
A,6 K,9
A,6 K,9
7
9/6/2021
15
A,6 K,9
[0, 6] [6, 8] [8, 17] [8, 12] [12, 22]
8
9/6/2021
18
9
9/6/2021
T = tA + tB + tC + tL + tM
T=6+4+7+3+5
T = 25 Weeks
20
10
9/6/2021
21
11
9/6/2021
Questions!
[email protected]
23
12