f1. Emergency Response Plan - Englsih
f1. Emergency Response Plan - Englsih
f1. Emergency Response Plan - Englsih
Revisionsheet: Version R3
Organization Validator Dated Visa
EPC
Partner
SUMMARY
LIST OF TABLES........................................................................................................... 5
FIGURES… ..................................................................................................................... 6
ACRONYMS AND DEFINITIONS ............................................................................... 6
1. INTRODUCTION .................................................................................................. 8
1.1. Context ........................................................................................................ 8
1.1.1. Project display ............................................................................................. 8
1.1.2. Scope of this management plan .................................................................. 9
1.2. Terminology used ...................................................................................... 10
1.3. Approach and objectives of the INTERVENTION plan ......................... 10
2. HEALTH AND SAFETY EMERGENCIES ....................................................... 11
2.1. Generalities ............................................................................................... 11
2.1.1. Goals .......................................................................................................... 11
2.1.2. Measures.................................................................................................... 11
2.2. inteverners ................................................................................................. 12
2.3. Health and safety risks .............................................................................. 12
2.4. Definitions ................................................................................................. 13
2.5. Means of preparation ................................................................................ 13
2.6. Means of intervention ............................................................................... 14
2.6.1. Means of taking care of an injured person .............................................. 14
2.6.1.1.Human resources ...................................................................................... 14
2.6.1.2.Technical means ....................................................................................... 14
2.6.2. Fire fighting means ................................................................................... 15
2.6.2.1.Fire extinguishers ..................................................................................... 15
2.6.2.2.Water extinguishing ................................................................................. 16
2.6.3. General alarms .......................................................................................... 16
2.6.4. Means of communication and transmissions ........................................... 17
2.6.5. Emergency resources ................................................................................ 17
2.6.6. Variousmaterials ....................................................................................... 18
2.7. Organization of intervention areas ........................................................... 19
2.7.1. Command centers ..................................................................................... 19
2.7.2. Medicalposts .............................................................................................. 20
2.8. Roles and responsibilities .......................................................................... 20
2.8.1. Responsibilities of the Principal Controller ............................................. 20
2.8.2. Responsibility of the Communications Coordinator ............................... 20
2|P a ge
2.8.3. Responsibilities of the Incident Controller............................................... 21
2.8.4. Responsibility of Incident Response Team Members .............................. 21
2.8.5. Responsibility of Site Supervisors ............................................................ 22
2.8.6. Site personnel ............................................................................................ 22
2.8.7. First aid, firefighters and police ............................................................... 22
2.8.8. Subcontractors .......................................................................................... 23
2.9. Emergency response procedures .............................................................. 23
2.9.1. Emergency signalingflowchart ................................................................. 25
2.9.2. Fire ............................................................................................................ 26
2.9.2.1.Emergency response plan for a minor fire .............................................. 26
2.9.2.2.Action plan for a Major fire ..................................................................... 26
2.9.2.3.Fire emergency procedures ...................................................................... 27
2.9.2.4.Special case of firefollowing an explosion ................................................ 28
2.9.3. Personal accidents involving machinery or vehicles ................................ 30
2.9.4. Collapse of building, hangars and structures etc. .................................... 31
2.9.5. Gas leak ..................................................................................................... 32
2.9.6. Natural disasters (storm, earthquake, lightning, etc.) ............................. 33
2.9.6.1.General guidelines .................................................................................... 33
2.9.6.2.Storm procedure ....................................................................................... 33
2.9.6.3.Lightning strike procedure ...................................................................... 34
2.9.6.4.Procedureduring an earthquake .............................................................. 34
2.9.7. Response plan in the event of a fall from a height / serious injury ......... 35
2.9.8. Civil unrest / Violence ............................................................................... 35
2.9.9. Snake, scorpion or insectinjury ................................................................ 36
2.9.10. "Missing person" ...................................................................................... 37
2.9.11. Crisis management methods with internal / external interference ......... 40
2.9.11.1. Serious injury of a local resident ......................................................... 40
2.9.11.2. Case of a fire generated on the site that could impact resident soutside
the site 40
2.9.11.3. Case of an event outside the site thatcould impact the personnel inside
the site 40
2.10. Description and location of routes and meeting point ............................. 42
2.11. Control List ............................................................................................... 43
2.12. Training and retraining ............................................................................ 43
2.12.1. Emergency situations training .................................................................. 43
3|P a ge
2.12.2. Exercises .................................................................................................... 43
2.13. Maintenance and resumption of activities and emergency plans ............ 44
3. ENVIRONMENTAL EMERGENCIES .............................................................. 45
3.1. Generalities ............................................................................................... 45
3.1.1. Goals .......................................................................................................... 45
3.1.2. Measures.................................................................................................... 45
3.2. Speakers .................................................................................................... 46
3.3. Environmental risks .................................................................................. 47
3.4. Definitions ................................................................................................. 47
3.5. Means of preparation ................................................................................ 48
3.5.1. Classification of spills ................................................................................ 48
3.5.2. Preparation of resources ........................................................................... 48
3.6. Means of intervention ............................................................................... 49
3.6.1. Human resources ...................................................................................... 49
3.6.2. Technicalmeans ......................................................................................... 50
3.6.2.1.Anti-spill kit .............................................................................................. 50
3.6.2.2.Personal Protective Equipment (PPE) ..................................................... 51
3.6.2.3.Otherequipment ....................................................................................... 51
3.6.3. Means of communication and transmissions ........................................... 52
3.6.4. Emergency resources ................................................................................ 53
3.6.5. Variousmaterials ....................................................................................... 53
3.7. Organization of intervention areas ........................................................... 54
3.7.1. Command centers ..................................................................................... 54
3.7.2. Waste storage areas .................................................................................. 55
3.7.3. Medical posts ............................................................................................. 55
3.8. Roles and responsibilities .......................................................................... 55
3.8.1. Responsibilities of the Principal Controller (Project Manager) .............. 55
3.8.2. Responsibility of the Communications Coordinator ............................... 56
3.8.3. Responsibilities of the Incident Controller............................................... 56
3.8.4. Responsibility of Incident Response Team Members .............................. 57
3.8.5. HSE Director ............................................................................................. 57
3.8.6. HSE / Environment Engineer ................................................................... 58
3.8.7. Responsibility of Site Supervisors ............................................................ 58
3.8.8. Site personnel (all employees) ................................................................... 58
3.8.9. First aid, firefighters and police ............................................................... 59
4|P a ge
3.8.10. Subcontractors .......................................................................................... 59
3.9. Emergency response procedures .............................................................. 60
3.9.1. Procedure in the event of a productspill .................................................. 60
3.9.2. Emergency signalingflowchart ................................................................. 62
3.9.3. Chemical and oilspill ................................................................................. 63
3.10. Training and retraining ............................................................................ 64
3.10.1. Training in environmental emergency management ............................... 64
3.10.2. Exercises .................................................................................................... 64
3.11. Maintenance and resumption of activities and emergency plans ............ 65
4. INCIDENT MANAGEMENT PROCEDURE .................................................... 66
4.1. Incident declaration (with location) ......................................................... 66
4.2. Monitoring the effects of the incident....................................................... 66
4.2.1. Monitoring the effects of a fire ................................................................. 66
4.2.2. Monitoring the effects of an accident on an employee ............................. 66
4.2.3. Monitoring the effects of a conflict with local residents .......................... 66
4.2.4. Monitoring the effects of an environmental incident ............................... 66
4.3. Proposal of a remediation plan and modification of processes if necessary
................................................................................................................... 67
4.4. Monitoring of the implementation of the remediation plan .................... 67
4.5. Closure of the incident .............................................................................. 67
5. COMMUNICATION WITH LOCAL ADMINISTRATIVE AUTHORITIES . 67
5.1. Communication with the media ............................................................... 68
5.2. Communication with the public ............................................................... 68
APPENDICES ............................................................................................................... 69
Annex 1 -Declaration and follow-up of a health and safety emergency ............................ 70
Annex 2 -Improvement of the Emergency Plan ................................................................ 73
Annex 3 -Forms following a simulation exercise ............................................................. 75
Annex 4 -List of minimum stocks of PPE in the event of a spill ....................................... 80
Annex 5 -Immediate spill declaration form ...................................................................... 82
Annex 6 -Spill Prevention and Response Training Form Immediate Spill Declaration ..... 87
LIST OF TABLES
FIGURES
The meaning of the acronyms and the definition of certain formulas used in the plan are detailed in
the table below.
6|P a ge
IFC International finance corporation
SGES Environmental and Social Management System
ST Subcontractor
7|P a ge
1. INTRODUCTION
1.1. CONTEXT
The SAG consortium, formed by Meridiam and GSEZ (ARISE) has been requested by the
Gabonese government to implement the project to redevelop and operate the so-called
Transgabonaiseeconomic road, linking Libreville to Franceville. The Transgabonaiseis Gabon's
major road axis, approximately 828 km long, itfollows the national roads RN1, RN2, RN3 and
RN4.
Meridiam and GSEZ (ARISE) both have experience in structuring and delivering large projects in
the country. The projectisdevelopedwithin the framework of a 30-year public-private partnership
contract by which the State grants the Partner the design, redevelopment, financing, maintenance,
operation and maintenance of the Transgabonaise.
Between Libreville and Franceville, the projectisdividedintothree stages, shown on the mapbelow:
1. Stage 1: Libreville - Alembé;
2. Stage 2:Alembé - Mikouyi;
3. Stage 3:Mikouyi - Franceville.
Within Stage 1 of the project, the EPC will be in charge of the contract for the design and
redevelopment / construction of PK24 to PK105 of the N1 national road, connectingNkok to
Kango, passing throughNtoum, Kougouleou and Ndouaniang.
This management plan covers the activitiesrelating to the redevelopment / construction
workscorresponding to this segment rangingfrom PK24 to PK105, illustrated on the mapbelow.
The works consist of the repair or improvement of the roadway, hydraulicworks (drainage, etc.), the
installation of safety and signaling equipment.
The EPC will design, build, test and complete all installations and systemsnecessary to carry out the
work.
The redevelopment and improvementworks, as specified, will be carried out within the framework
of the existing right-of-way, avoiding the acquisition of land, except for places where the wid this
insufficient and where provisions for correcting the route, d Improvement of intersections /
geometriccharacteristics of the road are considerednecessary, feasible and affordable. This is the
case, for example, of the doubling of lanesplannedbetween PK24 and PK40.
9|P a ge
1.2. TERMINOLOGY USED
Throughout the document, the following terminology isused with the following meaning:
The Project:Redevelopment of the section from PK24 to PK105 of the Route Nationale
Transgabonaise;
The Partner: Société Autoroutière du Gabon (SAG);
EPC: Afcons Infrastructure Limited.
The implementation of this plan is part of the Environmental and Social Management System
(ESMS) of the EPC. This plan aims to allow the EPC to identify potential emergency situations,
with a view to planning in advance the development of organizational and technical lmeasures to
ensure a rapid and effective response to an emergency situation on the safety or environmental plan.
10 | P a g e
2. HEALTH AND SAFETY EMERGENCIES
2.1. GENERALITIES
2.1.1. Goals
This chapter aims to implement the necessary measures in order to anticipate all the situations
which would cause an emergency situation such as an explosion or even a fire in construction areas
or parking or guard areas.
These chapters will provide adequate human and material resources in order to reduce the response
time and thuslimit the accident to the smallest possible area. This chapter helps to limit indirect
impacts on the human and natural environment, in particular impacts on health.
2.1.2. Measures
Train operators in case of emergency response. These trainings will giverise to special
training sessions;
Identify on a map the locations of hazardous materials and the activities in which they are
used for rescue operations;
Certify the availability of Personal Protective Equipment and the necessary equipment in the
event of an intervention in an emergency situation;
Describe the planned organization in the event of an intervention (internal and external
notification procedures, responsibilities, decision-making process, emergency exits and
post-accident operations);
Describe the coordination of planning with a view to informing the public, response
organizations, indicating first aid and emergency medical treatment, and finally reviewing
and updating the response plan in the event of an emergency regularly to take in to account
all the realities on the ground. Ensure that this information is communicated to employees;
11 | P a g e
2.2. INTEVERNERS
The main stakeholders for the management of emergency situations within the emergency response
team willbe:
The Principal Controller is responsible for all aspects of emergency preparedness and
response during operations.
The Communications Coordinatoris the only official spokes person authorized to deal with
external gencies.
Site Supervisors.
Site personnel.
Senior Officials, the Safety and Security Service, any local and administrative authority
involved or not at different levels of information depending on the nature of the emergency
to be managed.
Intervention and rescue services (external firefighters), depending on the nature of the
emergency to be managed.
The main crisis situations identified during the construction phase likely to impact the health and
safety of people, and requiring the implementation of intervention and emergency procedures are
listed below:
12 | P a g e
2.4. DEFINITIONS
The technical means internal to the projectdirectlyinvolved in the care of a serious injury generated
by the activities of the site are listed in the following tables:
14 | P a g e
Table5 – Technical resources internal to the project for wounded relief
Type Location
First aid kit Offices/Warehouse/Vehicle/
oil Station/Power
Plant/Workshop/Kitchen/
Hotmix and bayching plant
Warm blanket or silver rescue sheet Warehouse/Clinic
Rescue harness Hotmix and batching
plant/Workshop
Fireextinguishers of the correct type and in correct working condition are the first line of
defenseagainst a fire. Knowing the location of extinguishers and the type of firethey are intended to
extinguishis essential.
15 | P a g e
Fire extinguishers deployed on the project
The extinguishers available on the site will be:
Provided in sufficient numbers.
Arranged appropriately.
It will be guaranteed that the extinguishers will not be blocked and will be certified annually
by an external company. Monthly fire extinguisher inspection should be performed and
documented
Table7 – Fire extinguishers available on site
Breakdown Type of
by Type of Number extinguishing Capacity Precise locations on the
geographic extinguisher agent (L) site
area
10 Offices/ Warehouse
3 /Vehicle/oil Station/Power
AB portable Liquid
6 Plant/Workshop/Kitchen/
Hotmix and bayching plant
Mobile AB 0
Construction Portable 8 Wharehouse/Kitchen/Hotmix
site Powder 9
powder and Batching plat/ Workshop
Powder 0
mobile
3 Oil Station
CO2 CO2 2
A overhead water tank is present at the PK 50 and 95 base camps for fire fighting purposes.
In certain cases, a generalalarmwill have to betriggered to warn all the personnel of a site and / or to
warn the neighboringresidents by the emergency situation.
This plan shouldbeupdated if thereis a change in any of the contact persons / contact number.
Table10 - Name and contact number of the on-site emergency response team
Last name Designation Roleduring the emergency Contact no.
Mr. Sujit Kumar Jha Project Manager Main Controller 06 01 83 319/06
10 05 400
Mr. Agnelo Pereira Head of Communications Coordinator 06 10 05 406
Administration
Mr. AneeshKumar.S Head of HSE Fire zone accesscontroller 06 10 05 417
Mr. Nishant Kumar Plant Manager Installation of facilities and equipment 06 10 05 412
Mr. Jerome Security agent Unauthorized entry control and 06 64 32 658
17 | P a g e
barricades.
Mr. NdongBitome First aid First aid 07 75 79 264/06
Lucien 64 44 995
Contact details of externalagency in Gabon
Police 177
Firefighters 18
Ambulance 177
Medical services
Army Instruction Hospital Military Hospital, PK-9, Libreville +241 11 79 00 00
2.6.6. Variousmaterials
18 | P a g e
2.7. ORGANIZATION OF INTERVENTION AREAS
The Meeting Room has been identified as the Emergency Control Room.
The following items are provided in the Incident Control Center:
01. Site plan showingevacuation routes and assembly point and access routes.
02. List of emergency contacts, numbers of key project personnel and other external agencies
such as the Gabon Fire Department, Ambulance, etc.
03. List of safetyequipment applicable on the site and theirstorage locations.
04. Details of the fire station.
05. Emergency power ON / OFF.
06. Hand lamps / emergency torches, Hand alarms.
07. Details of the surroundingcommunity, including the telephonenumbers of village and
township chiefs.
The location of the EPC Project Manager's office isindicated on the plan of the base-camp located
at PK-50.
19 | P a g e
2.7.2. Medicalposts
The roles and responsibilities of the emergency response team are outlined below.
Control and lead the overall situation from the incident control center
Inform the Partner of the changeover of the project in a crisis management situation
Ensurethatoutsidefirefighters are called (if necessary). This can be done using either the
front desk phone or the mobile phone clearly indicating the NAME AND ADDRESS OF
THE SITE LOCATION and the NATURE OF THE EMERGENCY (Fire, Chemical Spill,
etc.).
If the phone lines do not work, send the companyvehicle to notify the FireDepartment.
20 | P a g e
If the vehicle, machinery, etc. are not available, seek help from neighboring businesses.
Maintain contact with the Emergency Coordinator and the Fire and Safety Coordinator for
the requirement of Ambulance Services or company vehicles needed to sendinjured people
to the doctor.
Meet the firefighters on theirarrival and informthem of the state of evacuation of the Site
and of the location and type of emergency.
Set up communication between the incident scene and the incident control center.
Keep in touch with the Communications Coordinator for the requirement of Ambulance
Services or other transportation.
The role of the operational teams is to implement the technical means necessary to control the
emergency situation.
Fightfires and control spills
Shut down plant and energized equipment, isolate materials and move equipment
Manage assembly points and emergency exits, and instruct staff to assemble there.
21 | P a g e
2.8.5. Responsibility of Site Supervisors
Stop operations in a safemanner after consulting the Principal Incident Controller and
attempting to control the emergency.
Direct the firefighting team to the causes of the fire and to areas where water
cannotbeapplied.
Check the direction of the wind and whetherthereis a danger to others; inform the Incident
Controller and others.
Keep control of the situation until the arrival of Senior Officials. Submit a detailed report to
them.
When witnessing an event, each person present on the site will be responsible for:
Without putting your own safety at stake, intervene on a flame start using the extinguishers
available;
Without jeopardizing your own safety, secure the accident area where the injured persons
located.
First aid, firefighters and the police can intervene in the event of a major disaster on construction
sites, such as extinguishing a fully developed fire, helping victims, or, for the police, apprehending
possible intruders who may represent a threat. They also act on the external consequences to protect
residents from the current incident.
22 | P a g e
2.8.8. Subcontractors
Subcontractors and theirsupervisors are assimilated to EPC site personnel. Theirrole in providing
information and responding to emergency situations isidentical to everyone in the project.
The following emergencies have been identified as potential emergencies at the site during
construction.
Fire& Explosion.
Accidents related to the Installation / Machines / Vehicle.
Collapse of Structures.
Gas leak.
Spill of Chemicals.
Natural calamities (Storm, Earthquake, Lightning, etc.).
Fallfrom a Height.
Civil unrest.
Medical Evacuation.
Missing Person.
General guidelines
1. Do not panic.
2. Do not approach the incident site as a spectator. However, stay at home,
unlessotherwisespecified.
3. Do not engage in communication channels / phones except to deal with the emergency.
4. Don't move unnecessarily.
5. Keep your guests / visitors away from the site.
23 | P a g e
24 | P a g e
2.9.1. Emergency signalingflowchart
Emergency situation
1. Fire& Explosion
2. Incidents related to the Installation / Machines / Vehicles
3. Collapse of Structures.
4. Gas Leak.
5. Spill of Chemicals.
6. Natural Calamities.
7. Fallfrom a Height.
8. Civil unrest
9. Medical Evacuation
Inform relatives of
the injured
25 | P a g e
2.9.2. Fire
Minor : A minor fireis a small, localized fire that can beeasily and safely extinguished using
portable firefighting equipment.
Major : A major fireis a firewhichcannotbeeasilycontrolled by the use of portable extinguishers
and whichrequiresthat an emergency bedeclared.
People not involved in firefightingshouldreach the assembly point closest to the area
wherethey are.
26 | P a g e
2.9.2.3. Fire emergency procedures
27 | P a g e
General standard fire evacuation procedures
The guidelines for personnel during evacuation in the event of a minor or major fire are as follows:
I. Remember the actions to be performed seen in training and exercises.
II. Intervene quickly without haste or sudden gestures.
III. Recognize hand signals / messages.
In the event of a fire due to the explosion of highlyflammablematerialssuch as gasoline, LPG, etc.,
the followingproceduresshouldbefollowed:
Anyone who has witnessed the incident should immediately report the situation to the
Designated / Alternate Person (see Annex III: Emergency Reporting Flow chart) regarding
the extent of the fire and the exact location of the accident.
The designate / deputy immediately takes charge of the situation and informs the
othermembers of the central command team. The Central Command, in turn, willinform the
administrative office, first aid, fire brigade, hospital, police, etc., and alsoimmediatelynotify
the internalauthority and the team to take charge of the situation.
Members of the incident response team immediately rush to the location. Devices required
by the initial team such as high powered torches whistles and helmets with identifying
marks must beavailable in the administrative office and they must bebrought to the site and
provided to the members.
All fuel lines feeding the fire or endangered must beisolated. If possible, all combustible
materials in the vicinity of the fire location should be removed. People around a fire should
also be moved to a safe distance (200 meters). The area will be cordoned off for the moment
and handed over to the experts (firefighters) after their arrival.
Clear the approach road for the Rescuer, the Fire Department and the Ambulance to access
the location to rescue and protect the injured. Immediately send the seriously injured to
hospitals and the remaining injured will be taken to the first aid center for initial treatment
and advised for further treatment in hospitals, if necessary. The Rescuer will provide CPR if
the victim is unconscious.
28 | P a g e
Once the fire is completely extinguished, the visual inspection should be performed by the
security service.
At the end of the formalities, workers and machines must be organized to remove debris and
restart work.
29 | P a g e
2.9.3. Personal accidents involving machinery or vehicles
If the incident is major, the Principal Controller (Project Manager) will declare it as an emergency
and the EPC emergency response system will act respectively.
EMERGENCY ACTION
1. Go quickly to the emergency site hearing the alarm and / or the emergency message.
2. In the event of a lifting devicecollapsing, anyonewho has witnessedit must immediately
report the situation to theirsupervisor on the extent of the incident and the location of the
accident.
3. The supervisorwillinform the othermembers of the central command team.
4. The central command team shouldalsoinform the administrative office, first aid, fire brigade,
hospital, police, etc. to take charge of the situation.
5. Clear the approach road for the Rescuer, Fire Truck and Ambulance to access the location to
rescue and protectinjured people.
6. Immediately takes seriously injured people to hospitals and others injured will be taken to
the first aid center for initial treatment and advised for furthertreatment in hospitals, if
necessary. The rescuer will provide CPR if the victimis unconscious.
7. If necessary, use a crane, etc. to immediately remove aging material if someone is trapped
underneath.
8. The EPC security service must attend the scene of the incident, cordon off the area and
preventunauthorized entry by others.
30 | P a g e
2.9.4. Collapse of building, hangars and structures etc.
Guidelines for the person who is locked inside the collapsed building
1. Position your self immediately under tables, desks or other items that will provide protection
from shards of glass and debris. If you are in a building that is experiencing full or partial
collapse, use your best judgment to determine whether it is safer to evacuate the building
immediately or to take cover and stay in the building.
2. If you are in an affected building and itissafer to evacuate, immediately evacuate the
building, advising others to do so when you leave. Evacuate in the direction as close to the
affected area as possible. Do not use the elevators. Help injured people as long as you are
able to do so. Once outside, go to an area at least 300 meters from the building.
3. If a bombmay have caused the explosion during the collapse (there may have been an
anonymous call, priorthreats, a context of litigation with malicious groups, etc.), do not
activate the alarms / siren. Fire because it could detonate other bombs.
4. Do not block accessroads or parking lots adjacent to the building, as emergency personnel
may need them.
5. Whenyou are able to do sosafely, call the Main Controller and the Incident Controller.
6. Do not enter the affected building untilyou are instructed to do so.
If the incident is major, the Principal Controller (Project Manager) will declareit as an
emergency
and the EPC emergency response system willactrespectively.
Emergency response
I. Immediatelyinform the nearestfire station and police department.
II. Clear the access for the free flow of rescue vehicles.
III. The rescuer must also rush to the scene and immediatelysend the seriously injured to hospital.
The other injured will be taken to the first aid center for initial treatment and advised for
further treatment in hospitals, if necessary.
IV. The rescuer will provide CPR if the victimisunconscious.
V. Use an emergency vehicle and any other vehicle available for hospitalization of injured
persons.
VI. Use all our devices / vehicles / EDM for rescue imprisoned staff.
31 | P a g e
2.9.5. Gas leak
A minor gas leakis a small volume leakthat can be easily contained, affecting only a small area. For
gas cutting, the EPC will use an LPG cylinder. Gas escaping from the LPG cylinder poses an
explosion hazard.
32 | P a g e
2.9.6. Natural disasters (storm, earthquake, lightning, etc.)
Go quickly to the emergency site upon hearing the alarm and / or the emergency message.
Set up work teams with available people, made up of fire fighters, security guards. The work
team should perform the following tasks:
1. Clear the approach road for the fire department and ambulance.
2. Evacuate injured people for medical treatment.
3. Control traffic around the emergency site.
4. Organize to save people, property and materials.
5. Ensure the availability of an adequate water supply at the incident site. Disconnect
electrical power to the emergency site, if necessary in consultation with the Incident
Controller.
Site manager / engineer will take the following actions in the event of a storm:
Obtain the regular weather forecast report from the relevant authority
All height related work should be stopped if the wind speed is 32 km / h or 20 MPH or
greater.
If he receives a warning in the event of a strong wind, then he must ask a special team to
secure the loose objects.
Ensures that buckets, ladders, maintenance materials and the like are to bekept in a safe
place.
Factories should be shut down and equipment should be placed in safe positions / locations.
Work at height must be suspended and all workers must be placed in a safe place.
All building materials i.e. beams, pipes, electrical equipment, etc. which cannot be moved to
a safe place, must be secured in the best possible way.
33 | P a g e
2.9.6.3. Lightning strike procedure
In the event of storm activity generating lightning in the local area, the following work activities
should be stopped immediately:
Work at height
Look for low ground and avoid high or open areas. If you are on high or open ground,
crouch close to the ground with your feet close together.
Avoid touching or staying near any metallic object such as mobile installation, towers and
power lines / poles).
Storms are fast approaching; distances can be estimated using 0.62 miles (1 kilometer) at 3
seconds between lightning and thunder.
After an earthquake, a visual inspection of the structures should be performed to assess any
material damage.
34 | P a g e
If you are in a car:
Do not attempt to get out of your vehicle if electrical wires have fallen on it. Wait for help.
2.9.7. Response plan in the event of a fall from a height / serious injury
The affected person must not be moved in the event of a fall from a height and suspected of
having a back injury.
First aid (ABC approach) for anyother injuries sustained should be provided at the site.
The injured can only be moved by members of the emergency response team if thereis a risk
of an accident on the victim.
She will be made comfortable by removing her shoes, loosening her clothes and giving her
water to drink.
A vehicle will immediately be called and the stretcher gently lifted and placedinside the
vehicle.
At the same time, the doctor with whom the on-site visit was made, the permanent
arrangements should be discussed over the phone and he should be informed of the patient's
condition and should be ready to receive the patient.
A responsible person must accompany the patient to the hospital. Remember, too many
people don't help and are more of a nuisance.
The work must bestopped; all personnel must collect and receive a toolboxhighlighting the
reasons for the accident, the failures that have occurred and the corrective actions to
betaken.
If there are persons in or near company property with suspected intent to cause property damage,
injury to project personnel, disruption of normal operations, etc. The information will be
communicated to the SAG community liaison officer and to the security company responsible for
securing the site and the equipment. The following steps will be taken:
35 | P a g e
In the event of an attack on the site / camp, do not assemble at the assembly point, try to stay
hidden wherever you are, awayfrom a window (under your bed in your room, turn off the
light and do not make noise)
The site / camp must be kept secure at all times and access by unauthorized personnel is
prohibited.
The security shift supervisor will be responsible for providing related details and law
enforcement will be notified by the communications coordinator, if necessary.
The security shift supervisorwillordersecurity to close and lock all entrance doors to the site.
The security shift supervisor will order security to close and lock all entrance doors to the
site. It will be guaranteed that no unauthorized person is authorized to access the site without
positive identification by the security personnel of the door and according to the instructions
given by the Head of Administration / Head of Security.
The medical emergency response team and the fire and security team willbealerted.
Wash the wound and keep the area lowerthan the heart, calm the victim and takethem to the
hospitalimmediately.
Loosen tight clothing, minimize use of infected end. Do not try to remove their clothes
because by moving to do so, it will cause the movement of the venom along the blood
stream. Use a gutter if necessary to immobilize it.
Lightly compress the bandage at the end above the wound. The bandage should be very
tight.
Clean itwith a sponge and save the sponge for later testing.
36 | P a g e
Dress the wound.
A person is considered missing when they are absent fromwheretheyshouldbe and no one
knowswherethey are.
Check the person's support plan, area newspaper, or other relevant sources to see if the
personis at a pre-arranged meeting or appointment.
Askother people during the day or residential service if the person has toldanyonewherethey
are going.
If this information is not recorded, inform the HR manager of the day or his assistant,
whothenbecomes the researchcoordinator.
A persondisappearsduring an outing
Ask the spectators and guardian for help if the personis in danger if they are alone
Notify the manager and staff of the day as well as their parents / guardians.
37 | P a g e
Contact the person's place of residence to find out wherethey are
If thereis no response, contact their usual means of transport to find out if the person has
been picked up or dropped off.
If the missed person is not found and no explanation is forth coming, the person is confirmed as
"missing"
The Research Coordinator coordinates with the members of the research team and
designates the areas to be researched.
The Research Coordinator must remain in place during the day or in the residential area and
remain reachable by telephone
Depending on individual circumstances, the research team may require some or all of the
following:
o A fully charged flashlight in the case of a missing person after dark.
o Warm blanket or silver rescue sheet
o Potable water
The manager (also the ResearchCoordinator) of the day or residence service must inform the
parents / guardians of the person.
If the missing person is not found after the search, immediately notify the nearest police
station.
38 | P a g e
o The Manager, the Hierarchical Executive
The person should be medically examined by the rescuer on duty and a doctor if necessary.
If a new medical referral or hospital transfer is indicated, this should be arranged and the
person'sfamily / guardian should be informed.
39 | P a g e
2.9.11. Crisis management methods with internal / external interference
A local resident can beinjuredduring contact with the site, for example:
By collision with a light or construction vehiclenear the site or in the event of an intrusion;
By collision withan out of control construction machine;
By a projection towards the outside of the site;
By the effects of an uncontrolledfire.
In the event of a medical emergency involving a local resident, take the person out of danger and
first inform the person in charge of the emergency medical team. The first aid attendant available on
site will assist the injuredperson (s) and provide first aid, in accordance with the definedprocedure.
If an emergency ambulance isrequired, call the nearest SAMU or hospital,
2.9.11.2. Case of a fire generated on the site that could impact resident soutside the
site
By site wemean:
The construction site of the Transgabonaise.
The life bases located at PK-50 and PK-95.
A fire occurring on the construction site or on one of the life bases can, if itis not controlled,
generate dangerous effects on the population. To prevent this risk, in order to protect populations as
quickly as possible, the following measures will be deployed:
A security perimeter will be set up around the site;
The nature and extent of the perimeter will be worked out by the operational fire
intervention team, with regard to the location and size of the fire;
EPC people will be placed around this perimeter to preventany local residents from entering
the perimeter.
2.9.11.3. Case of an event outside the site thatcould impact the personnel inside the
site
A procedure will be established between each site of the construction site (the road, life bases, etc.)
and the administrative point of attachment with the local authorities.
This procedure will be the object of defining the modalities according to which the sites will be
warned in the event of external events which could impact the site (for example a fire outside the
site, the appearance of civil disturbances…).
Communication will be by landline or mobile phone between the local authorities and the EPC
manager of the place concerned.
40 | P a g e
Procedure in case of COVID positive workers 19 :
A worker presenting the symptoms of COVID 19 (fever, cough, headache, sore throat and
respiratory discomfort) coming for a consultation in our infirmary;
A curative treatment is prescribed to him and he follows it from his quarantine area;
Access to the premises is forbidden to unauthorized persons during the entire quarantine
period;
The person concerned is provided with a sufficient quantity of masks, a hand washing
device, sanitary control including coughing/sneezing, temperature, etc. ;
In any case, the premises will only be used again after this disinfection.
41 | P a g e
2.10. DESCRIPTION AND LOCATION OF ROUTES AND MEETING POINT
One or more assembly points will be defined for each construction site. The chosen location (s)
must meet the following criteria:
Provide enough space to accommodate all workers;
Stay away from any source of danger (aggravation of the fire, traffic outside the site, etc.);
Access must be easy, secure and free of all obstacles at all times.
Meeting points will be identified on the project site and clearly marked with signage.
Signswillbeplaced to indicate the direction to the assembly point from different work areas.
The assembly point on the PK-50 life base isindicated on the ground plan below:
Assembly point 2
Assembly point 1
42 | P a g e
2.11. CONTROL LIST
A list of the safetye quipment applicable on the site and their storage locations is provided in the
Emergency Control Room (cabin / project manager's office).
The intervention equipment must be operational at all times. To keep the equipment in good
workingorder, regular checks must be carried out. The material to be checked is that shown in the
following tables:
Technical resources internal to the project for the rescue of the wounded (2.6.1.2. )
In the event of an anomaly, the equipment concerned will be immediately repaired or replaced.
Defective material will be immediately disposed of in the garbage so that it is not used by mistake.
The EPC will conduct regular prevention trainings sothat all staff and workers are aware of
emergency situations and the procedures to befollowed, in order to minimize the impact on staff and
communities.
Employee emergency response training will cover the following topics:
The function and elements of the emergency response plan.
Emergency responseprocedures.
2.12.2. Exercises
The human and material resources necessary to resolve the emergency are available in
sufficient number and in the right place;
If the exercise was carried out jointly with the emergency services and the public
authorities:thereis good coordination between internal and external actors;
44 | P a g e
3. ENVIRONMENTAL EMERGENCIES
3.1. GENERALITIES
3.1.1. Goals
This plan aims to implement the necessary measures in order to anticipate all the situations that
would cause an emergency situation such as an accidental spill of hazardous materials or wasteinto
the environment at the level of work sites or work areas. parking or guarding.
This plan will make it possible to have adequate human and material resources in order to reduce
the intervention time and thus limit the accident to the smallest possible area. This plan helps to
limit the impacts on the biophysical environment and to limit the indirect impacts on the natural
environment, in particular the impacts on health and on ecosystems.
3.1.2. Measures
Train operators in case of emergency response. These trainings will giverise to special
training sessions;
Describe the pollution control equipment that will be put in place by companies at
storagesites: anti-pollution kits, safety data sheet, etc. ;
Describe the planned organization in the event of an intervention (internal and external
notification procedures, responsibilities, decision-making process, emergency exits and
post-accident operations);
45 | P a g e
In case of contamination:
Identify the source, carry out tests, analyze the results and deduce whether any measures
need to be taken (exceeding thresholds, etc.);
Implement measures to reduce, eliminate or limit one or all three risk factors (contaminants,
receptors and routes of contamination)
Raise awareness and protect personnel who will work near contaminated areas.
3.2. SPEAKERS
The main stakeholders for the management of emergency situations within the emergency response
team are:
The Principal Controller (Project Manager) is responsible for all aspects of emergency
preparedness and response during operations;
The Communications Coordinatoris the only official spokes person authorized to deal with
external agencies;
On-Site Supervisors;
Senior Officials, the Safety and Security Service, any local and administrative authority
involved or not at different levels of information depending on the nature of the emergency
to be managed;
Intervention and rescue services (external fire fighters), depending on the nature of the
emergency to be managed.
46 | P a g e
3.3. ENVIRONMENTAL RISKS
The main crisis situations identifiedduring the construction phase likely to impact the environment
and requiring the implementation of intervention and emergency procedures is listedbelow:
3.4. DEFINITIONS
Internalresources: resources made available by the EPC within the framework of the project.
Externalmeans: publicmeans.
Danger: Source likely to cause injury and healthproblems.
Hazardouschemical: Chemical productthat has propertiesthatmayharmhuman or animal health, the
environment, or that can damage property.
HazardousMaterial : Any item or agent (biological, chemical, radiological and / or physical)
thatmay cause harm to humans, animals or the environment, either by itself or by interaction
withotherfactors.
Impact: The activities of road projectswill have environmental and social impacts, suchas:
atmospheric pollution, soil contamination, concentration and sedimentation of suspendedsediments,
loss of habitat, increasedrisksassociatedwith road traffic, job opportunities.
Incident: Event occurring as a result of or in the course of workwhichcould or doesresult in
pollution, injuries and illhealth.
Spill: Dropping or dropping (something), sinking or going over the edge of a container,
usuallyaccidentally.
47 | P a g e
3.5. MEANS OF PREPARATION
Means of Permanentlycharged
communication Available in sufficientnumbers
Staff Trained and regularlytrained
Weather data Daily monitoring of weather data and storm warning
48 | P a g e
3.6. MEANS OF INTERVENTION
49 | P a g e
3.6.2. Technicalmeans
The technical means internal to the project directly involved in handling a spill generated by site
activities are listed in the following tables:
Table16 – Technical resources internal to the project for the rescue of the wounded
Type Number Location
Oil Station/Hot mix
and batching
Anti-spill kit 10 plant/Workshop
50 reflectivevests
25 bluesafetyvests
18 orangesafetyvests
Personal Protective Equipment (PPE) 15 bluehelmets
Oil Station/Hot mix
(pants and jacket clothes, mask, glasses, 75 yellowhelmets and batching
gloves, boots, etc.) 20 greenhelmets plant/Workshop
350 pairs of gloves
150 safetyshoes Fuel
Station/Power
Plant/Workshop
0
Mobile pumps
Small spills will be cleaned up using the availables pill prevention kits. Used spill kits and
associated bags and PPE should then be disposed of in the appropriate garbage cans (thesewastes
are generally hazardous).
To eliminate soil pollution, priority will be given to the part of the soil where the greatest amount of
chemicalsisfound. Thus, the first few centimeters or evenmeters of soilmayneed to beexcavated, and
the pollutedsoil must thenbetreated as hazardouswaste.
Spill kits willbe made available to all locations wherehazardousmaterials are used and
storedsothatthey can beeasilydeployed in the event of a spill. Having clean-up kits in high-risk areas
givesworkers the toolstheyneed to containspillsquickly, reducingwaste and improving clean-up
time.
The spill kit willcontain at least:
50 | P a g e
Absorbent materials (papertowels, cleaning pads, cleaningsocks)
Waste container
Personal protective equipment, including clothing, should be provided to enable workers to safely
mop up spills. The extent of this PPE must beadapted to the spillslikely to been countered. Personal
protective equipment will be at a minimum:
A protective mask for the forehead,
Waterproof glasses;
Gloves resistant to chemical attack (corrosive);
Boots;
Respiratory mask (corrosive, toxic);
Clothing, jacket, coveralls and / or pants resistant to chemicalattacks (corrosive, toxic);
Self-containedbreathingapparatus (ARI).
Emergency equipmentrequired, with the exception of spill response kits and PPE, mayinclude, but
are not limited to, first aid kits, pictorialsigns and stickers, hand tools. hand, pumps, etc.
A check list of minimum stocks of PPE to be supplied by the employer is provided in the Annex.
3.6.2.3. Otherequipment
Mobile pumps
Mobile pumps will be available to collect any liquid contained in the secondary containment, to
allow evacuation and proper treatment of the pumped liquid.
Manual equipment
Manual equipmentshouldbeavailable to pick up the spill and pollutedsoil:
Handlebrush;
51 | P a g e
Shovel ;
Polyethylene bag.
52 | P a g e
3.6.4. Emergency resources
This plan should be updated if thereis a change in any of the contact persons / contact number.
Table18 - Name and contact number of the on-site emergency response team
Last name Designation Roleduring the emergency Contact no.
Mr. Sujit Kumar Jha Project Manager Main Controller 06 01 83 319/06
10 05 400
Mr. Agnelo Pereira Head of Communications Coordinator 06 10 05 406
Administration
Mr. AneeshKumar.S Head of HSE Fire zone accesscontroller 06 10 05 417
Mr. AangeEngonga Environment Environmental engineer
Manager
Mr. Vasudevan T. N Plant Manager Installation of facilities and equipment 06 10 05 412
Mr. Jerome Security agent Unauthorized entry control and 06 64 32 658
barricades.
Mr. NdongBitome First aid First aid 07 75 79 264/06
Lucien 64 44 995
Contact details of externalagency in Gabon.
Police 177
Firefighters 18
Ambulance 177
Medical services
Army Instruction Hospital Military Hospital, PK-9, Libreville +241 11 79 00 00
3.6.5. Variousmaterials
53 | P a g e
Means Number Characteristics Location
160 KVA
415 Volts Hot mix plan / Pont
Generator 2
bascule
Brand Stamford
Emergency lighting 0
The Emergency Control Room of an emergency situation depends on the importance of the level of
emergency triggered.
The project meeting room has been identified as an Emergency Control Room.
The following items are provided in the Spill Control Center:
01. Site plan showingevacuation routes and assembly point and access routes.
02. List of emergency contacts, numbers of key project personnel and other external agencies
such as the Gabon Fire Department, Ambulance, etc.
03. List of safetye quipment applicable on the site and their storage locations.
04. Details of the fire station.
05. Emergency power ON / OFF.
06. Hand lamps / emergency torches, Hand alarms.
07. Details of the surroundingcommunity, including the telephone numbers of village and
township chiefs.
The location of the office of the EPC Project Manager is indicated on the plan of the base-camp
located at PK-50.
54 | P a g e
Emergency Control Room
(Meeting Room)
The residues collected following the spreading recovery operations will be stored in a predefined
area on the site, and evacuated as waste.
Non-hazardous waste will be collected in designated bins and handed over to an external body
authorized to dispose of it.
For hazardous waste, an authorized external company will then be hired for treatment and disposal.
Thoseinjured as a result of a spill will be taken to the first aid center for initial treatment and
advised for further treatment in hospitals, if necessary. As soon as the necessary first aid means
prove to bein sufficient, the person will be redirected to hospitals.
The roles and responsibilities of the emergency response team are outlined below.
55 | P a g e
Control and lead the overall situation from the incident control center
Inform the Partner of the changeover of the project in a crisis management situation
Ensure tha toutside fire fighters are called (if necessary). This can be done using either the
front desk phone or the mobile phone clearly indicating the NAME AND ADDRESS OF
THE SITE LOCATION and the NATURE OF THE EMERGENCY (Fire, Chemical Spill,
etc.).
If the phone lines do not work, send the company vehicle to notify the Fire Department.
If the vehicle, machinery, etc. are not available, seek help from neighboring businesses.
Maintain contact with the Emergency Coordinator and the Fire and Safety Coordinator for
the requirement of Ambulance Services or company vehicles needed to send injured people
to the doctor.
Meet the fire fighters on their arrival on site and informthem of the evacuation status of the
Site and the location and type of emergency.
56 | P a g e
Evaluate the level of intervention required.
Call the Senior Manager, if applicable, who will become the Principal Controller.
Set up communication between the incident scene and the incident control center.
The role of the operational teams is to implement the technicalmeansnecessary to control the
emergency situation.
Fightfires and control spills
Manage assembly points and emergency exits, and instruct staff to assemble there.
Developrules and best practices for the project in order to avoidspillsduring construction
work and monitor itsimplementation and compliance
Review the spill risk assessment and suggest improvements that should be incorporated into
the assessment
Manage and control situations arising during a spill emergency. Continuously review and
update the spill response procedure
Maintain all records and reports relating to spill incidents and responses.
57 | P a g e
3.8.6. HSE / Environment Engineer
Maintain all records and reports relating to spill incidents and responses.
Train staff, including subcontractor personnel, on appropriate emergency and spill response
procedures;
Establishment of spill control kits and their maintenance as well as PPE and hand
toolsnecessary to control, contain, absorb and dispose of materials associated with spill
response.
Immediate notification (verbal and written letter) to the customer of any spill that has
occurred on the site.
Stop operations in a safe manner after consulting the Principal Incident Controller and
attempting to control the emergency.
Direct the fire fighting team to the causes of the fire and to areas where water cannot be
applied.
Check the direction of the wind and whetherthereis a danger to others; inform the Incident
Controller and others.
Keep control of the situation until the arrival of Senior Officials. Submit a detailed report to
them.
When witnessing an event, each person present on the site will be responsible for:
58 | P a g e
Be able to correctly use the spill control kits, which will be made available in sufficient
quantity at strategic locations.
Report to the controller any unsafe or unhealthy conditions or any defect in the installations
or equipment.
First aid, fire fighters and the police can intervene in the event of a major disaster on construction
sites, such as extinguishing a fully developed fire, helping victims, or, for the police, apprehending
possible intruders who may represent a threat. They also act on the external consequences to protect
residents from the current incident.
3.8.10. Subcontractors
Subcontractors and theirsupervisors are assimilated to EPC site personnel. Their role in providing
information and responding to environmental emergencies is identical to everyone in the project.
59 | P a g e
3.9. EMERGENCY RESPONSE PROCEDURES
A spillis an accidental release of chemicals or grease into the surrounding environment (ground,
parking lot, construction site, water, etc.). In situations where it is not possible to contain a spil
limmediately, and in a safe manner, itis the responsibility of responders to clean up and report any
spill.
Spill prevention will be the first line of defense to prevent releases to the environment. Many of the
identified mitigation measures will be covered by standard professional working procedures or good
practices. The main sources of spills identified during the construction phases are:
Waste disposal.
The following emergencies have been identified as potential emergencies at the site during
construction.
Spill of Chemicals
60 | P a g e
Spill of
Chemical product
Can the
quantityreleasedgen
erate
a danger ?
The substance
isitverytoxic?
(eg Mercury)
SpillMAJOR
MINOR spill
Emergency situation
1. Spill of Chemicals.
Inform relatives of
the injured
62 | P a g e
3.9.3. Chemical and oilspill
A spillis the accidental release of a chemical / oil (hydrocarbons) into the surrounding environment
(ground, parking lot, workshop, body of water, etc.). A spill should be cleaned up using this
procedure in cases whereit cannot be safely and immediately contained, or if any material enters the
drain, enters the ground, or mayevaporate. In the event of an oil spill in the water body,
immediately start the gully suction cup and move the flexible hose over the spill in the water body.
It is the responsibility of incident response teams to clean up and report anyspills.
In the event of a chemical / petroleum spill in / or outsideour site or in the water body, the site
emergency response team will be alerted to handle the situation in a safe and legal manner. You
willneed to consult the manufacturer's instructions and refer to the safety data sheet
63 | P a g e
Action taken at the on-site diesel tank :
Ensure that all applicable regulations or guidelines regarding the storage of petroleum products are
followed.
At the time of installation, we will take the following measures:
- The tank implementation area must be easily accessible by vehicles (transporters, firefighters) to
facilitate product ingress and egress and response
- Avoid flood plains and areas with a shallow water table.
- Consider soils with a high rate of water infiltration that present a significantly increased risk of
groundwater contamination.
- Place the tank on an impermeable platform that can contain the volume of the tank to compensate
for any failure, it includes a channeling of river water that transits to a tank de-oiling;
- Equip the diesel storage site with two spill kits, fire extinguishers and sand trays
- Train site operators on the use of spill kits and fire extinguishers
- Post safety instructions and guidelines for all persons on the storage site
The EPC will conduct regular prevention training so that all staff and workers are aware of
emergency situations and the procedures to be followed, in order to minimize the impact on the
environment.
Employee emergency response training will cover the following topics:
Intervention training to stop a leak in progress.
3.10.2. Exercises
Although the exercises are used for training purposes, their primary function is to test the adequacy
of the plan, available resources, equipment and the readiness of personnel. Exercises are a very
effective way to check the effectiveness of training and to make improvements by correcting
deficiencies found during practice.
64 | P a g e
Regular exercises must be carried out in order to involve as many people as possible, in various
situations. Before the exercises, briefings could be organized in order to recall the main principles
and to highlight the last modifications. Below are examples of exercises to organize:
Situation of loss of confinement.
Grouping exercise.
Functional exercise.
Evacuation drill.
Complete exercise.
An exercise report is provided in the appendix.
For these exercises, different types of scenarios will be considered in particular:
Small hazardous chemical spill (<10 L);
Large spill of hazardouschemicals (> 10 L);
Spillsgreaterthan or equal to 200 L;
Spills in the terrestrialenvironment;
Spill on a watercourse.
Response personnel will respect the following response priority:
Environmental Protection ;
Preservation of humanlife;
Preservation of property.
Immediately after each exercise, a meeting isorganized to analyze and highlight all the positive and
negative points, to establish an action plan and to define any updates to the ERP.
The HSE director is responsible for:
Exercise reports and organization of debriefing sessions;
During the emergency, the activity on the site concerned may be fully or partially maintained, or it
must be completely interrupted.
The decision rests with the management of the EPC, depending on the level of emergency.
65 | P a g e
At the end of the emergency situation, in the event of a partial or total interruption, the total activity
can only resume when the conditions defined in chapter Error! Reference source not found.Will
be verified.
At the end of the emergency, a form will be used for the declaration of emergency situations. An
example of incident reporting and monitoring is given in the Appendix.
Following a fire, it is necessary to check whether structures have not been damaged, so that their
stability would be likely to compromise the safety of workers.
Depending on the case, in-depthstudies carried out by a specialistwillbe carried out for a more
detailed expertise.
Following an accident involving an employee, it is necessary to check the health of this person after
returning to the site, if necessary after a period of sick leave. A suitable medical follow-up can be
set up on thisperson, carried out by a doctor.
The objectis to check that this person is recovering well following their accident, and to avoid a
relapse.
Following a conflictual relationship between a site and the residents, mediation will be set up in
order to maintain a regular dialogue, in order to ensurethat all the subjects of tension are well dealt
with in the short, medium and long terms.
This mediation unit willinclude at least:
The EPC crisis management unit;
A representative of the residents;
66 | P a g e
The district chiefconcerned.
This mediation unit will be maintained as long as necessary.
As soon as the emergency situation isfullyunder control, priorityisgiven to identifying the causes
and determining corrective measuresfor:
Prevent the same situation from happening again;
Improve the procedures for managing emergency situations.
This remediation plan willthenbeimplemented (Annex 2).
A report must bewritten by the EPC in order to take stock of the root causes thatled to the incident
occurring.
67 | P a g e
A remediation plan has been determined and isbeingimplemented.
An incident isclosedwhen the remediation plan isfullyimplemented.
Good communication, in particularwith the media (in the event of a major accident), makesit
possible to control the information provided to the public. Indeed, when the media have confidence
in the information theyreceive, the reports and articles about the incident are generally more
accurate.
In the first hours of the emergency situation, communication revolvesaround 3 main topics:
The eventsthat have occurred;
Actions initiated.
Subsequently, itendeavors to respond in anticipation to the questions and expectations of the media
and the public. A question / answer document must bedrawn up and kept up to date in this regard.
The information shouldbeneithertooalarmingnor excessive.
In times of crisis, communication with the media is the responsibility of the Communication
Manager.
It is important that the public, during an emergency, beinformed in the mostprecise and
regularmanner of the evolution of the situation.
To avoid confusion and misunderstanding, youshould:
That thereisonly one spokespersonwhowillbe the Head of ExternalCommunication;
APPENDICES
69 | P a g e
ANNEX 1 -DECLARATION AND FOLLOW-UP
OF A HEALTH AND SAFETY EMERGENCY
70 | P a g e
CONDUCT OF THE EMERGENCY SITUATION
Message
Hour Message details / Events Comments
From: AT :
EDITOR: _______________________
MEANS / DOCUMENTS
MISSIONS CONTACT PERSONS
REQUIRED
5 / Preparation of Communication
EQUIPMENT INVOLVED:
PLACE OF INCIDENT:
SCENARIO: _________________________________
DATED: _____ / _____ / _____
Serial
DESCRIPTION STATUS NOTES
No.
Serial
DESCRIPTION STATUS NOTES
No.
21 Number of missingpersons
SIMULATION EXERCISE ANALYSIS REPORT
SCENARIO: _________________________________
DATED: _____ / _____ / _____
Summarysummary:
ANNEX 4 -LIST OF MINIMUM STOCKS OF
PPE IN THE EVENT OF A SPILL
List of minimum stocks of Personal Protective Equipment (PPE) in the event of a spill
2 Safety glasses
4 Pair of cottongloves
5 Pair of rubbergloves
6 Pair of leathergloves
10
11
Last name
Dated
Signature
ANNEX 5 -IMMEDIATE SPILL DECLARATION
FORM
Immediatespilldeclarationform
Name of contractor: Report date: (DD / MM / YY) Report time (24 hourclock): (HH /
MM)
Name of the Signature: Date: (DD / MM /
individualdepositreport: YY)
Reception report Signature: Date: (DD / MM /
categoryname: YY)
Spills:
NB:Anyspillinto a body of water must berecorded and reported to the operator.
NB:Spillsgreaterthan or equal to 200 liters must bereported to the section Responsibilities of the
Mauritaniangovernment for spillresponse.
Brief description of the spill incident, how ithappened, the source of the spill, etc. (25 words or less)
Hydrocarbon solvent
Solid chemicals
Lubricants
Dangerous waste
Other substances
Spilled volume
Volume recovered (liters)
(liters)
Detailed description of the
Includedetails of the location, cause and duration of the spill, response actions
spill incident and response
taken, types of wastegeneratedduringspillresponse and cleanup, how and
/ clean-up measures (use
wherespillresponse and cleanupwastescleaning have been eliminated, new
additional pages if
preventivemeasures, etc.)
necessary)
Seeattached
Parties notified
about the spill
List all parties otherthan the operatorwho have been informed of the spill (eg local
(useadditional communities and governmentofficials). pleasecomplete all fields
pages if
necessary)
- Use of PPE
- Recognizepictograms
- Using the spill kits
- ...
Training subject:
__________________________________________________________________
PARTICIPANTS
10
11
12
13
14
15