A Simplified Two-Stage Method To Estimate The Settlement and Bending Moment of Upper Tunnel Considering The Interaction of Undercrossing Twin Tunnels
A Simplified Two-Stage Method To Estimate The Settlement and Bending Moment of Upper Tunnel Considering The Interaction of Undercrossing Twin Tunnels
A Simplified Two-Stage Method To Estimate The Settlement and Bending Moment of Upper Tunnel Considering The Interaction of Undercrossing Twin Tunnels
PII: S2214-3912(21)00048-9
DOI: https://doi.org/10.1016/j.trgeo.2021.100558
Reference: TRGEO 100558
Please cite this article as: Z. Liu, J. Xue, J. Ye, J. Qian, A simplified two-stage method to estimate the settlement
and bending moment of upper tunnel considering the interaction of undercrossing twin tunnels, Transportation
Geotechnics (2021), doi: https://doi.org/10.1016/j.trgeo.2021.100558
This is a PDF file of an article that has undergone enhancements after acceptance, such as the addition of a cover
page and metadata, and formatting for readability, but it is not yet the definitive version of record. This version
will undergo additional copyediting, typesetting and review before it is published in its final form, but we are
providing this version to give early visibility of the article. Please note that, during the production process, errors
may be discovered which could affect the content, and all legal disclaimers that apply to the journal pertain.
Authors: Zhiyong Liu 1,2, Jianfeng Xue1, Jianzhong Ye3, Jiangu Qian 4*
Affiliations: 1, School of Engineering and Information Technology, University of New South Wales,
Campbell, ACT, Australia
2, State Key Laboratory of Hydraulics and Mountain River Engineering, Sichuan University,
Chengdu, 610065, China
3, PSM Engineering Consultants, North Ryde, Sydney, NSW, Australia
4, Department of Geotechnical Engineering, Tongji University, Shanghai, China
Zhiyong Liu PhD candidate, School of Engineering and Information Technology, University of New South
Wales, Campbell, ACT, Australia
MSc graduate, State Key Laboratory of Hydraulics and Mountain River Engineering, Sichuan
University, Chengdu, 610065, China
Jianfeng Xue PhD, Senior Lecturer, School of Engineering and Information Technology, University of New
South Wales, Campbell, Australia
Jianzhong Ye PhD, Senior Engineer, PSM Engineering Consultants, North Ryde, NSW, Australia
Jiangu Qian PhD, Professor, Department of Geotechnical Engineering, Tongji University, Shanghai, China
1
Abstract:
With the expansion of existing networks of underground system, many metro tunnels are
excavated in a pair undercrossing existing tunnels. The new excavations will affect the stress
distribution and settlement behavior of the existing tunnels, particularly when the clearance is
small. Generally, the construction of the second undercrossing tunnel induces more settlement in
the upper tunnels compared to that caused by excavating the first one, due to the interaction
between the new excavations. The degree of interaction makes it difficult to predict the settlement
of existing tunnels. In this paper, a simplified two-stage analysis method considering the
interaction between the undercrossing twin tunnels is proposed to estimate the induced response
of existing upper tunnel. In the first stage, the greenfield settlement caused by the first excavation
is estimated using Peck’s empirical function, and that caused by the second excavation is modified
with a modification factor to consider the influence of the first tunnel. In the second stage, the
additional stress calculated using the greenfield displacement is imposed on the existing tunnel
resting on Pasternak foundation model. The calculated settlement profile and bending moment of
the existing tunnel using the two-stage analysis method is compared with those obtained from
finite element analysis and historical field monitored data. The effects of the characteristic
parameter of Pasternak foundation model, the spacing between the new twin tunnels, and the
modification factor of greenfield settlement, on the settlement profile and bending moment of the
Keywords: Undercrossing twin tunnels; Settlement and bending moment of existing tunnel;
2
1. Introduction
The rapid growing of traffic in big cities has led to traffic congestion on road. Developing
underground transportation systems is an effective approach to address this problem. Due to space
limitations, more and more tunnels are excavated in a pair undercrossing existing tunnels. New
excavation will affect the stress distribution and settlement behavior of existing tunnels,
particularly when those tunnels are too close. It is critical to accurately estimate the settlement and
bending moment of existing upper tunnels due to the excavation of undercrossing twin tunnels for
Unlike excavating one tunnel, twin tunnels interact significantly when excavated in a pair,
especially when they are excavated in sequence. Compared with that induced by excavating the
first tunnel, more settlement is anticipated in greenfield or upper tunnels due to the excavation of
the second tunnel. This phenomenon has been confirmed by numerical simulation [8,15], model
tests [6,10] and field monitoring data [7,9,17-19,28]. Therefore, while estimating the settlement of
existing tunnels, the interaction between undercrossing twin tunnels should be considered,
otherwise the settlement may be significantly underestimated. The settlement profile of existing
tunnels also differs to the greenfield subsurface settlement profile which can be described with a
Gaussian distribution curve [26]. If the existing tunnel is stiffer than the surrounding soil, the
settlement of existing tunnels is generally less and the settlement trough is wider than that of
Much research has been done to study settlement profile of surface and subsurface due to the
excavation of twin tunnels, and the interaction between twin tunnels. Fargnoli et al. [13] used the
empirical curves proposed by Peck [30] to predict greenfield settlement due to twin tunnels. The
3
final settlement was calculated using the superposition of the settlement induced by each tunnel.
For the settlement of existing tunnels, Fang et al. [12] used Gaussian distribution function and
superposition method to fit the settlement profile of existing tunnels induced by the construction
of undercrossing twin tunnels, using different values of volume loss and trough width for the
undercrossing twin tunnels. In the authors’ work, volume loss and trough width were determined
using monitored settlement of the existing tunnels. Lai et al. [21] classified the influence zones
caused by the construction of twin tunnels undercrossing an existing tunnel into strong, weak and
no influence zones. Based on the classification, the settlement of an existing tunnel can be
predicted using modified Gaussian distribution function. Ocak [28] introduced a coefficient
(1+d/D) to modify the settlement of greenfield induced by excavating the second tunnel to consider
When using empirical models to predict the settlement of existing tunnels, one keystone is to
determine the trough width. As discussed earlier, the settlement profile of existing tunnels is wider
than subsurface settlement of greenfield. Analytical solutions have also been proposed to predict
the settlement of existing tunnels due to underneath excavation. Liu et al. [25] investigated the
responses of an existing tunnel due to the excavation of a new tunnel by removing springs in
Winkler model. This method is limited to study the interactions between upper and lower tunnels
with zero clearance. The authors found that the extension of springs being deleted is the most
significant factor influencing the responses of existing tunnels. Vorster et al. [32] used an
equivalent linear approach with a closed form solution to analyze subsoil displacement, and the
bending moment of existing pipeline caused by single undercrossing tunnel. The method gives an
upper approximation of bending moment for pipes. Zhang et al. [39] proposed an infinitely long
beam model on Winkler foundation to determine the settlement and internal forces of existing
4
tunnel caused by single undercrossing tunnel. Among those studies, the subsoil is normally
simulated with Winkler foundation model. According to Tanahashi [31], however, Winkler
foundation model ignores the continuous deformation of the foundation and the accuracy of results
is scarified. To improve the accuracy, Zhang [37] used Pasternak foundation model, which
considers the interactions between the springs used in Winkler model, to predict the settlement and
bending moment of existing upper tunnels due to excavating twin new tunnels, but the interaction
This paper investigates the settlement and bending moment of existing upper tunnel due to new
undercrossing twin tunnels using a two-stage analysis method. The interaction of twin tunnels is
considered in calculating the settlement profile of greenfield subsurface, and the settlement of
subsoil is treated as loading acting on the existing tunnel. The settlement profile of existing tunnel
is calculated using Pasternak foundation model. The tunnel settlement and bending moment
calculated using the two-stage analysis method are compared with those obtained from Finite
Element Method (FEM) and field monitored data from historical projects. Parametric study is
performed to compare the results obtained from Pasternak and Winkler foundation model. The
dependence of the settlement and bending moment of existing tunnel on the shear modulus of the
shear layer in Pasternak model, the distance between the new twin tunnels (d'), and the
According to Hunt [15] and Divall et al. [11], due to the disturbance of surrounding soils during
the excavation of the first tunnel, the greenfield deformation and the reaction of upper tunnel
5
caused by the construction of the second tunnel would be different to those caused by the first
tunnel. This also has been confirmed with field observations, for example, the settlements of
Bayswater Road in London [34], Metro line 4 in Shenzhen [18], Metro line 2 in Changsha [7], and
Piccadilly Line tunnels in London [9] due to the excavation of new undercrossing twin tunnels, as
illustrated in Figure 1 and Table 1. In the table, Vl is the volume loss and i is the horizontal distance
from the centerline to the inflexion point of the settlement profile. The cases show that, as a
common phenomenon, the settlements of greenfield or the upper tunnels caused by the second
undercrossing tunnel differ to those caused by the first tunnel in three aspects: the second tunnel
induces more settlements than the first one; the settlement trough caused by the second tunnel may
not be symmetrical; and the maximum settlement caused by the second tunnel may not be along
the centerline of the second tunnel. Therefore, to predict the settlement profile caused by twin
tunnels, the interaction between the new twin tunnels should be considered, otherwise the
To obtain the subsurface settlement, a global coordinate system is defined in Figure 2 where the
centerlines of tunnel 1 and tunnel 2 are located at x1 and x2 respectively. The subsurface settlement
profile s1(x) of greenfield due to excavating tunnel l can be described using a Gaussian distribution
AVl x x1 2 (1)
s1 ( x) exp
i 2 2i 2
where A is the cross-section area of tunnel 1. According to Mair et al. [26], i can be written as:
where z0 is the depth of the tunnel, and z is the depth of subsurface as illustrated in Figure 2.
6
Because of the interaction between the two tunnels and the disturbance of soil due to the
construction of the first tunnel, the settlement profile of subsoil induced by excavating tunnel 2 is
different from that suggested in Eq. (1). Hunt [15] proposed a method to consider this effect. The
principle of the method shown in Figure 3 is to introduce a modification factor (M) to modify the
settlement due to excavating tunnel 2. M is the largest at the centerline of tunnel 1 where the
settlement due to excavating tunnel 1 has the largest value, and decreases to zero at the boundary
of the settlement profile due to tunnel 1. Therefore, the interaction has a linear relationship with
the settlement values caused by excavating tunnel 1. Beyond the settlement profile of tunnel 1, the
interaction is eliminated and the settlement profile due to excavating tunnel 2 is not influenced. As
recommended by Hunt [15], the settlement profile s2(x) due to excavating tunnel 2 can be
expressed as:
x x1 AVl x x2 2 (3)
s2 ( x) 1 M M exp
ni i 2 2i 2
where n is a multiplier to modify i with typically values ranging from 2.5 to 3.0. Take the value of
|𝑥 ― 𝑥1|
𝑛𝑖 as one if it is greater than one. Hunt [15] performed a series of numerical simulations and
found that M varies from 0.6 to 1.5 for London clay. The settlement profiles of greenfield due to
excavating tunnel 1 and tunnel 2 are revealed in Figure 4 with different M values. The figure shows
that, Eq. (3) well captures the characteristics of settlement profile due to excavating tunnel 2 in the
three aspects mentioned above: the increase of maximum settlement, the asymmetry of settlement
profile and the deviation of the location of the maximum settlement from the second tunnel’s
centerline.
The ground settlement due to excavating twin tunnels can be expressed in Eq. (4) using
superposition method:
7
S ( x) s1 ( x) s2 ( x) (4)
Equations (1) and (4) are used to calculate the settlement of subsurface soils in greenfield without
considering the effect of existing tunnels shown in Figure 2, therefore they cannot be used directly
to estimate the settlement of existing tunnels. The theory of beam resting on Winkler foundation
model has been widely used to estimate the settlement of existing tunnels as revealed in Figure
5(a) [20, 22, 25, 37, 39]. However, according to Tanahashi [31], Winkler foundation model
assumes that each spring behaves independently, which may not be the case in soils. To better
simulate the behavior of ground, Pasternak [29] introduced a shear layer to consider the interaction
between each spring, which is known as Pasternak foundation model. In this work, the existing
The governing equation for an infinite long beam resting on Pasternak foundation is:
d 4W ( x) d 2W ( x) (5)
EI kBW ( x ) G p B q( x) B
dx 4 dx 2
where EI is the bending stiffness of the beam; B is the cross-sectional width of the beam, or the
outer diameter of the existing tunnel; k is the coefficient of subgrade reaction; W(x) is the
deformation of the existing tunnel and q(x) is the loading acting on the tunnel; Gp is the shear
modulus of the shear layer. Note if Gp is set to zero, Eq. (5) becomes the governing equation of
Winkler foundation model. Eq. (5) is a fourth-order differential equation which can be solved using
8
Klar et al. [20] found that the coefficient of subgrade reaction, k, depends on the shape of the
6 Es (6)
k
i
Es H
Gp (7)
6 1
where, Es and υ are the elastic modulus and Poisson’s ratio of soil respectively; and H is the depth
of the elastic layer. According to Xu [35], for pipelines with a large length-width ratio, beyond the
depth of 6B the additional stress due to excavation becomes negligible. Therefore, in this paper H
Tanahashi [31] introduced a parameter to describe the relationship between the shear modulus
of the shear element, the bending stiffness of the beam and the coefficient of subgrade reaction:
Gp (8)
=
2 kEI B
Zhang and Zhang [36] introduced an analytical solution to Eq. (5) with a distributed load q(δ)
q ( ) Bd
dW ( x)
4 EI
2 2
e
x
cos x sin x (9)
where,
9
kB 4EI Gp B 4EI , kB 4EI Gp B 4EI (10)
Hence, the settlement of the existing tunnel under external loading can be expressed as:
q ( ) B
cos x sin x d
W ( x)
x
e (11)
4 EI
2 2
The solution of an infinite tunnel resting on Winkler foundation can be obtained if Gp is set to zero,
4 kB 4EI (12)
and
q( )
cos x sin x d
W ( x)
x
e (13)
2k
d 2W x
M b x EI (14)
dx 2
According to Zhang et al. [40], the additional stress exerted on twin tunnels resting on Pasternak
d 2 S ( x) d 2 s1 ( x) d 2 s2 ( x) (15)
q( x) kS ( x) Gp ks1 ( x) ks2 ( x) Gp
dx2 dx
2
dx2
Using equations 13 to 15, the deformation and bending moment of the upper tunnels due to
10
3 Application of the elastic two-stage analysis method
A three-dimensional finite element analysis was performed to investigate the response of an upper
tunnel to the excavation of undercrossing twin tunnels using Plaxis 3D [5]. As illustrated in Figure
7, the existing tunnel with the diameter of 6 m is at the depth of 12 m. The new twin tunnels are at
the depth of 23 m, with the diameter of 6 m. To better consider soil and tunnel interaction,
Hardening soil model with small-strain stiffness (HSS) is employed to simulate the behavior of
soil [14]. The existing tunnel is simulated using continuous elastic solid body with the elastic
modulus of 2.825 GPa, as used by Liang et al [23]. This gives a bending stiffness of 180 GPa.m4
for the existing tunnel. The tunnel boring machine (TBM) and the lining of the new tunnels are
simulated with 0.35 m thick plate elements. The input parameters for the finite element analysis
The excavation is simulated with step-by-step method [2,42]. In the procedure as illustrated in
Figure 8, soils and the existing tunnel are activated to reach the initial equilibrium. The first
calculation phase is to simulate the installation of the 12 m long TBM. After that, in each
consequential excavation, the soil in front of TBM is deactivated, the TBM segment and lining
segment are activated with assigned TBM material and lining material respectively, and both face
support and grouting pressure are activated. The face support and grouting pressure at the crown
of new tunnel are 200 kPa, and the value increases with depth at 14kPa/m. A contraction factor of
1.2% at the TBM facing with an increase of -0.1%/m along the alignment of TBM is employed to
simulate over-excavation. The TBM advances 2 m in each calculation phase and a total of 125
11
phases were performed. The construction of Tunnel 1 and tunnel 2 were simulated in the 2nd to the
After the installation of tunnel 1, the volume loss of 1.95% is achieved. The value of i is 8.2m
which is slightly larger than that determined with Eq. (2). Figure 9 illustrates the greenfield
settlement profiles due to new twin tunnel excavation. It is found that the greenfield settlement
due to excavating tunnel 2 is significantly larger than that due to excavating tunnel 1, as expected.
For M = 0.5, Eq. (4) well catches the behavior of greenfield settlement while compared with FEM.
Figure 10 compares the calculated results using the two-stage method and the results from FEM.
The input parameters of Pasternak foundation model are summarized in Table 3 as obtained from
finite element analysis. The k and Gp are calculated using Eqs. (6) and (7), where Es and υ are 10
ref
MPa and 0.2 respectively, which are the same with E50 and υur as shown in Table 2. It is found that
the calculated settlement and bending moment of existing tunnel agree well with those from FEM.
In addition, the comparison shows that the Pasternak foundation model and Winkler foundation
model produce almost similar predictions, which is consistent with the findings in Liang et al [24].
This is because the bending stiffness of existing tunnel is large but the elastic modulus of soil is
small, which leads to a small characteristic parameter ρ (0.05 for this case) as determined in
Equation 8. The effects of ρ values on the settlement and bending moment of existing tunnel will
be detailed later.
In this section, the predicted settlement profiles of existing tunnels using the proposed method are
compared with the field monitored data of Shenzhen metro line 4 [18] and Piccadilly Line tunnels
in London [9].
12
As revealed in Figure 11, the centerline of the Shenzhen Metro line 4 tunnels is at 12 m below
ground surface. The internal and external diameters of the tunnels are 5.4 m and 6.0 m respectively.
The centerline of the new tunnels is at the depth of 21 m, with the diameter of approximately 6.0
m. The tunnels are in gravelly clay and sandy soil. Piccadilly Line tunnels are in London clay. The
internal and external diameters of the existing Piccadilly Line tunnels are 3.8 m and 4.1 m
respectively at the depth of approximately 13 m. The diameter of the new tunnels is approximately
9.1 m at the depth of about 26 m. The tunnel linings are concrete for all the cases. The values of
M for the projects are estimated to be 1.5 based on the simulation results from Hunt [15]. The
typical cross-sections of the two projects and soil properties used in the analysis are summarized
in Figure 11. The elastic moduli of the soils in Shenzhen Metro Line 4 are estimated using Es=1.4N
MPa as recommended by Architectural Institute of Japan [1], where N is the SPT values shown in
Figure 11(a). Since the analytic solution assumes that the tunnel is resting on Pasternak foundation
which is semi-infinite, for multi-layered soil, an equivalent modulus may be obtained using weight
average method as proposed by Baguelin et al. [3]. For simplicity, the elastic modulus of the stratum
underlain the tunnel is used in Shenzhen Metro Line 4 as this layer is relatively deep. The elastic
modulus of London clay is from the work of Burland and Kalra [4] and shown in Figure 11(b).
The Poisson’s ratio of the soils is assumed to be 0.3 for both cases. The parameters used for
The settlement profiles determined with the proposed method are compared in Figure 12 with the
field monitored values. The comparison shows that the proposed method can well predict the total
settlement of the upper tunnels considering the interaction of the two undercrossing tunnels. The
comparison also shows that, though the solution is proposed for tunnels undercrossing existing
tunnels at 90 degrees, the method can well predict the settlement of tunnels that are not
13
undercrossing at 90 degrees. For example, in the case of Shenzhen Metro Line 4, the tunnels
intersect at 83 degrees, and for Piccadilly line tunnels in London, the tunnels intersect at about 69
degrees.
4 Parametric analysis
In this section, the dependence of settlement profile of the existing tunnel on input parameters of
the two-stage method, including the characteristic parameter of Pasternak foundation model (ρ),
the spacing between the new twin tunnels (d'), and the modification factor of greenfield settlement
(M), is analyzed. The parameters listed in Table 3 are used as the baseline.
The shear modulus (Gp) of shear layer strongly affects the value of characteristic parameter (ρ)
which distinguishes the Pasternak model with the Winkler model. The following shear moduli are
considered: 0 (Winkler foundation model), Gp, 4Gp, 7Gp, 10Gp (Gp is determined with Eq. (7) and
is 46.2 MPam from the finite element analysis), which gives ρ values of 0, 0.05, 0.2, 0.35 and 0.5
respectively.
The settlement profiles of the existing tunnel due to excavating tunnel 1 are given in Figure 13(a).
It is found that the deviation of Pasternak foundation model from Winkler foundation model (ρ
=0) increases with ρ as expected. Settlement profile becomes narrower and deeper as ρ increases.
greater than that in Winkler foundation model when ρ is set as 0.05, 0.2 and 0.5 respectively.
Figure 13(b) shows the bending moment of the existing tunnel with different ρ values. Similar with
settlement, the maximum bending moment obtained with Pasternak foundation model increases
14
with ρ, which is about 6%, 25% and 50 % greater than that from Winkler foundation model when
ρ is set be to 0.05, 0.2 and 0.5 respectively. Such phenomena suggest that only when ρ is small
Five spacings are considered: d'= 2D, 3D, 4D, 5D, 6D, to study the sensitivity of upper tunnel
settlement to the spacing between the undercrossing tunnels. The typical settlement profiles with
different d' values are given in Figure 14(a) which shows that with the increase of spacing, the
settlement curve of the upper tunnel changes from ‘V’ shape to ‘U’, then to ‘W’ shape. The
maximum settlements under those five scenarios are summarized in Figure 14(b). The result shows
that the maximum settlement of existing tunnel decreases with the spacing between the
undercrossing twin tunnels. When the spacing is greater than 6D, the interaction effect diminishes
and the settlement due to excavating tunnel 2 is not affected by that induced by excavating tunnel
1.
Figure 15(a) shows that the maximum bending moment in the upper tunnel does not always
increase as the new twin tunnels get closer. This can be better seen in Figure 15(b) where both the
positive and negative maximum bending moment are the largest when d' is 2D. The negative
bending moment almost halves when d'=4D compared with that at d'=2D, and the value increases
slightly as d' increases to 6D. This is similar to the positive bending moment which is the lowest
at d'=4~5D. The reason is explained in Figure 15(c), when d'=4D, the positive bending moment
induced by excavating tunnel 1 compensates the negative bending moment induced by excavating
tunnel 2. As a result, the final maximum bending moment due to excavating two tunnels is less
than that induced by single tunnel. This may suggest that d'=4D may be the optimum distance in
15
4.3 The modification factor (M)
The modification factor (M) determines the degree of interaction between the undercrossing twin
tunnels. Four different modification factors are considered: 0, 0.5, 1.0, 1.5. The settlement profiles
of the existing tunnel under different M values are illustrated in Figure 16(a). The maximum
settlement of each case is also summarized in Figure 16(b). These figures show that M greatly
affects the settlement profile of the existing tunnel, and the maximum settlement increases linearly
with M. When M increases from 0.5 to 1, the maximum settlement in the upper tunnel increases
gets larger, the location of the maximum settlement moves towards the centerline of tunnel 2.
Figure 17(a) and (b) illustrate the final bending moment and maximum bending moment under
different M values. Both the maximum positive and negative bending moment values increase
linearly with M.
5 Conclusion
A simplified two-stage analysis method is proposed to predict the settlement and bending moment
of existing upper tunnels due to excavation of undercrossing twin tunnels. The additional stresses
acting on existing tunnels are determined using superposition method considering the interaction
of the undercrossing twin tunnels. The settlement profile and bending moment of existing tunnels
are determined using Pasternak foundation model. The calculated results using the two-stage
analysis method are comparable with the results from finite element analysis and historical field
monitored data. In the method, the variation of water table is not considered, which needs to be
further investigated. The two-stage analysis method can be used to estimate the settlement and
16
bending moment of existing tunnels due to the excavation of undercrossing twin tunnels by
Parametric study shows that the settlement and bending moment of existing tunnels are affected
by the characteristic parameter of Pasternak foundation model (ρ), the distance of new twin tunnels
(d'), and the modification factors of greenfield settlement (M). Based on the limited number of
modelling, it was found that, the difference between the results obtained using Pasternak
foundation model and Winkler foundation model increases with ρ. Only when ρ is small would
Pasternak foundation model be replaced with Winkler foundation model. The interaction of the
twin tunnels decreases with the increase of d'. The shape of the final settlement profile of an
existing tunnel can be “V”, “U” or “W” shape, depending on d'. However, the maximum positive
and negative bending moments do not decrease monotonously with the increment of d', and the
values are the lowest when d'=4D based on the analyses performed. The modification factor has
great effect on the settlement profile and bending moment of existing tunnel. It was found from
one case that, when modification factor doubles (from 0.5 to 1), the maximum settlement of and
the maximum bending moment in the existing tunnel increase by approximate 30%. Yet more
Acknowledgement
The project is funded by the Zhejiang Institute of Transportation, the State Key Laboratory of
Hydraulics and Mountain River Engineering, China (SKHL1704), the National Natural Science
Foundation of China (Grant No.51578413) and the Fundamental Research Funds for the Central
Universities (Grant No. 22120190220). The first author received PhD scholarship from the
17
References
[2] Avgerinos V, Potts DM, Standing JR. Numerical investigation of the effects of tunnelling
https://doi.org/10.1680/jgeot.SiP17.P.103.
[3] Baguelin F, Jézequel JF, Shields DH. The pressuremeter and foundation engineering, series
[4] Burland JB, Kalra CJ. Queen Elizabeth II Conference Centre, Geotechnical Aspects. Proc
[5] Brinkgreve RBJ, Kumarswamy S, Swolfs WM, editors. (2017). Plaxis 3D 2017 tutorial
manual; 2017.
[6] Chapman DN, Ahn SK, Hunt DVL. Investigating ground movements caused by the
construction of multiple tunnels in soft ground using laboratory model tests. Can Geotech
J 2007;44(6):631-43. https://doi.org/10.1139/t07-018.
[7] Chen RP, Lin XT, Kang X, Zhong ZQ, Liu Y, Zhang P, Wu HN. Deformation and stress
[8] Chen SL, Gui MW, Yang MC. Applicability of the principle of superposition in estimating
ground surface settlement of twin- and quadruple-tube tunnels. Tunn Undergr Space
18
[9] Cooper ML, Chapman DN, Rogers CDF, Chan AHC. Movements in the Piccadilly Line
https://doi.org/10.1680/geot.2002.52.4.243.
[12] Fang Q, Zhang DL, Li QQ, Wong LNY. Effects of twin tunnels construction
beneath existing shield-driven twin tunnels. Tunn Undergr Space Technol 2015;45:128-
37. https://doi.org/10.1016/j.tust.2014.10.001.
[13] Fargnoli V, Boldini D, Amorosi A. Twin tunnel excavation in coarse grained soils:
Observations and numerical back-predictions under free field conditions and in presence
https://doi.org/10.1016/j.tust.2015.06.003.
https://doi.org/10.1007/s11440-008-0056-1.
[15] Hunt DVL. Predicting the ground movements above twin tunnels constructed in
[16] Jin DL, Yuan DJ, Li XG, Zheng HT. Analysis of the settlement of an existing tunnel
https://doi.org/10.1016/j.tust.2018.06.035.
19
[17] Jin DL, Yuan DJ, Li XG, Zheng HT. An in-tunnel grouting protection method for
excavating twin tunnels beneath an existing tunnel. Tunn Undergr Space Technol 2018b;
71:27-35. https://doi.org/10.1016/j.tust.2017.08.002.
[18] Jin DL. Research on mechanism and control of existing subway tunnel deformation
[19] Jin DL, Yuan DJ, Liu SY, Li XG, Luo WP. Performance of Existing Subway
Tunnels Undercrossed by Four Closely Spaced Shield Tunnels. J Perform Constr Facil
2019;33(1):04018099. https://doi.org/10.1061/(ASCE)CF.1943-5509.0001230.
[20] Klar A, Vorster TEB, Soga K, Mair RJ. Soil-pipe interaction due to tunnelling:
2005;55(6):461-6. https://doi.org/10.1680/geot.2005.55.6.461.
[21] Lai HP, Zhao X, Kang Z, Chen R. A new method for predicting ground settlement
2017;76:726. https://doi.org/10.1007/s12665-017-7079-6.
[22] Liang RZ, Xia TD, Hong Y, Yu F. Effects of above-crossing tunnelling on the
https://doi.org/10.1016/j.tust.2016.05.002.
[23] Liang RZ, Wu WB, Yu F, Jiang GS, Liu JW. Simplified method for evaluating
shield tunnel deformation due to adjacent excavation. Tunn Undergr Space Technol
2018;71:94-105. https://doi.org/10.1016/j.tust.2017.08.010.
20
[24] Liang RZ, Xia TD, Huang MS, Lin CG. Simplified analytical method for evaluating
the effects of adjacent excavation on shield tunnel considering the shearing effect. Comp
[25] Liu X, Fang Q, Zhang DL. Mechanical responses of existing tunnel due to new
https://doi.org/10.1016/j.tust.2018.06.001.
[26] Mair RJ, Taylor RN, Bracegirdle A. Subsurface Settlement Profiles above Tunnels
[27] Marshall AM, Klar A, Mair RJ. Tunneling beneath Buried Pipes: View of Soil
Strain and Its Effect on Pipeline Behavior. J Geotech Geoenviron Eng 2010;136(12):1664-
72. https://doi.org/10.1061/(ASCE)GT.1943-5606.0000390.
[28] Ocak I. A new approach for estimating the transverse surface settlement curve for
twin tunnels in shallow and soft soils. Environ Earth Sci 2014;72(7):2357-67.
https://doi.org/10.1007/s12665-014-3145-5.
[30] Peck RB. Deep excavations and tunneling in soft ground state of the art report. In:
7th International Conference on Soil Mechanics and Foundation Engineering, Mexico City;
1969.p. 225-90.
21
[32] Vorster TEB, Klar A, Soga K, Mair RJ. Estimating the effects of tunneling on
https://doi.org/10.1061/(ASCE)1090-0241(2005)131:11(1399).
[33] Wan JC, Zhang DL, Zhang CP, Fang Q, Su J, Du NX. Deformation characteristics
of existing tunnels induced by excavation of new shallow tunnel in Beijing. Chin J Rock
[34] Wan MSP, Standing JR, Potts DM, Burland JB. Measured short-term subsurface
2017;67(9):748-79. http://dx.doi.org/10.1680/jgeot.SIP17.P.148.
[35] Xu L. Study on the longitudinal settlement of shield tunnel in soft soil, PhD thesis.
[36] Zhang H, Zhang ZX. Vertical deflection of existing pipeline due to shield tunneling.
[37] Zhang QF. Field observation and theoretical study on an existing tunnel
https://doi.org/10.1155/2018/1598672.
[38] Zhang XM, Ou XF, Yang JS, Fu JY. Deformation Response of an Existing Tunnel
[39] Zhang ZG, Huang MS, Wang WD. Responses of existing tunnels induced by
adjacent excavation in soft soils. Rock Soil Mech 2009;30(5):1373-80. [in Chinese].
22
[40] Zhang ZG, Huang MS, Xu C, Jiang YJ, Wang WD. Simplified solution for tunnel-
2018;78:146-58. https://doi.org/10.1016/j.tust.2018.04.025.
[41] Zhang ZG, Huang MS, Zhang C P, Jiang KM, Lu MH. Time-domain analyses for
https://doi.org/10.1016/j.tust.2018.12.020.
[42] Zhao CY, Lavasan AA, Barciaga T, Zarev V, Datcheva M, Schanz T. Model
validation and calibration via back analysis for mechanized tunnel simulations - The
https://doi.org/10.1016/j.compgeo.2015.07.003
23
List of Tables
24
Table 1 The Gaussian fitting results of four undercrossing tunneling projects.
Vl due to i due to Vl due to i due to
Project excavating excavating excavating excavating
tunnel 1 (%) tunnel 1 (m) tunnel 2 (%) tunnel 2 (m)
Twin-tunneling beneath Bayswater
0.46 13.2 1.2 17.2
Road, London [34]
Metro line 4 in Shenzhen [18] 0.38 9.8 0.63 13.1
Metro line 2 in Changsha [7] 0.24 11.3 0.65 10.8
Piccadilly Line tunnels in London
1.2 10.5 1.8 12
[9]
25
Table 2 The input parameters of FEM.
26
Table 3 The input parameters of Pasternak foundation model.
z0 Z D A=πD2/4 Vl i EI d' k Gp
M
(m) (m) (m) (m2) (%) (m) (GPa·m4) (m) (MPa/m) (MP.m)
27
Table 4 The input parameters of the two projects.
z0 z D A=πD2/4 Vl EI d'
Projects M
(m) (m) (m) (m2) (%) (GPa.m4) (m)
Shenzhen metro line 4, the left
21 12 6 28.3 0.42 480 15.6 1.5
tunnel [18]
Shenzhen metro line 4, the
21 12 6 28.3 0.38 480 15.6 1.5
right tunnel [18]
Piccadilly Line tunnels in
26 13 9.1 65 1.2 80 23 1.5
London [9]
Note: The elastic modulus of lining is estimated to be 22 GPa. D is the outside diameter of new
twin tunnels.
28
List of figures:
Figure 1 (a): The measured settlement of Bayswater Road, London [33], (b): settlements of Metro
line 4 in Shenzhen [17], (c): Metro line 2 in Changsha [6], and (d): Piccadilly Line tunnels in
London (d) [8] due to excavating of new undercrossing twin tunnels. EX1: excavating tunnel
1, EX2: excavating tunnel 2 (same abbreviations are used in following figures).
Figure 2 The settlement of existing tunnel due to excavating new twin tunnels.
Figure 3 The surface/subsurface modification factor (after Hunt [14]).
Figure 4 The greenfield settlement due to excavating each tunnel with different M (data from Hunt
[14]).
Figure 5 Analytical model of excavating twin undercrossing tunnels using Winkler foundation
model (a) and Pasternak foundation model (b).
Figure 6 Deflection of Pasternak foundation model induced by external load.
Figure 7 Finite element model used to study the interaction between existing upper and
undercrossing tunnels.
Figure 8 The simulation of excavation process in finite element model.
Figure 9 The greenfield settlement caused by the exaction of twin tunnels.
Figure 10 Comparison between the settlement (a) and bending moment (b) of the existing tunnel
obtained using the two-stage method and FEM.
Figure 11 The typical cross-section of Shenzhen Metro Line 4 (a) (data from Jin et al. [17], N is
number of Standard Penetration Test), and Piccadilly line tunnels in London (b) (cross-section
modified after Cooper et al. [8] and the elastic modulus of soil from Burland and Kalra [3]).
Figure 12 The comparison of simulated settlement with field monitored data of, (a): the left tunnel,
and (b) the right tunnel of Shenzhen Metro Line 4 (monitored data from Jin et al. [17]), and
(c): Piccadilly Line tunnels (monitored data from Cooper et al. [8]).
Figure 13 The settlement (a) and bending moment (b) of existing tunnel due to the excavation of
tunnel 1.
Figure 14 The settlement profile (a) and maximum settlement (b) of the existing tunnel with
undercrossing twin tunnels at different spacings.
Figure 15 The bending moment profile (a), maximum bending moment (b) of the existing tunnel
with undercrossing twin tunnels at different spacings, and the bending moment profile due to
each tunnel excavation (c).
Figure 16 The settlement profile (a) and maximum settlement (b) of existing tunnel settlement
with different M values.
Figure 17 The bending moment profile (a) and maximum bending moment (b) of existing tunnel
with different M values.
29
Author Credit Statement
Jianfeng Xue: Supervision, Methodology, Writing - review & editing, Funding acquisition.
30
Dear Editor,
The authors declare that we do not have any commercial or associative interest that represents a conflict of
Best regards,
Jiangu Qian
31