0% found this document useful (0 votes)
117 views11 pages

3 Work Accomplishment Report

The document summarizes the work accomplished by electronics engineering students from Bataan Heroes Memorial College during their internship at a hospital over multiple weeks in February through April. It describes tasks such as observing hospital operations and departments, researching how to improve cellular signal strength, assembling computers, gathering equipment IP addresses, assisting with the installation of biometrics systems to track employee attendance, and entering personnel information into biometrics and spreadsheet systems. The document is made up of weekly reports signed by student supervisors detailing the dates, tasks, and time spent on various projects during the internship.

Uploaded by

Sonic Hedgehog
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
117 views11 pages

3 Work Accomplishment Report

The document summarizes the work accomplished by electronics engineering students from Bataan Heroes Memorial College during their internship at a hospital over multiple weeks in February through April. It describes tasks such as observing hospital operations and departments, researching how to improve cellular signal strength, assembling computers, gathering equipment IP addresses, assisting with the installation of biometrics systems to track employee attendance, and entering personnel information into biometrics and spreadsheet systems. The document is made up of weekly reports signed by student supervisors detailing the dates, tasks, and time spent on various projects during the internship.

Uploaded by

Sonic Hedgehog
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Bataan Heroes Memorial College

Roman Super Hi-Way Balanga City, Bataan


Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: FEBRUARY
Week: 18 - 22

No of Hours
Day Date Work Accomplished
Worked
Monday

Tuesday

Wednesday 20 General orientation. 1:00 – 5:00PM

Introduction to the personnel/ 4 HOURS


employees of the company/ hospital

Thursday 21 Interview of expectation of the 8:00 – 5:00PM


Hospital operation in the field of
Electronics Engineering and how can 8 HOURS
we relate our course in the company.

Observation of the general operation


in the whole Hospital Operation
Management Program (IHOMP)
where we’re assigned.

Friday

Total Number of Hours: 12

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: FEBRUARY - MARCH


Week: Feb. 25 – Mar 1

No of
Day Date Work Accomplished Hours
Worked
Monday

Tuesday

Wednesday 27 The cellular signal in the lower ground 1:00 –


floor of the hospital. We were asked to 5:00PM
make a suggestion/ proposal on how to
increase the signal strength in the said 4 HOURS
area.

Layout the floor to where cellular was


weak.

Thursday 28 We do research on how increase the 8:00 –


signal strength for cellular phones. 5:00PM

8 HOURS

Friday March We do research on how increase the 8:00 –


1 signal strength for cellular phones. 5:00PM

8 HOURS

Total Number of Hours: 20

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: MARCH
Week: 4-8

No of
Day Date Work Accomplished Hours
Worked
Monday 4 Research on how increase the signal 8:00 –
strength for cellular phones. 5:00PM

8 HOURS

Tuesday

Wednesday 6 We presented our suggestion on how to 1:00 –


increase the signal strength of cellular 5:00PM
phones.
4 HOURS

Thursday

Friday

Total Number of Hours: 12

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: MARCH
Week: 11 - 15

No of
Day Date Work Accomplished Hours
Worked
Monday 11 We were stationed at the IT department. 8:00 –
Operation of the department was 5:00PM
discussed. We we’re to observe the
operation of the department 8 HOURS

Tuesday

Wednesday 13 We were assigned to assemble 1:00 –


computers in some offices 5:00PM

4 HOURS

Thursday 14 We were tasked to get all the IP 8:00 –


addresses of the equipment and 5:00PM
facilities in the hospital specifically the
IP addresses of CT Scan machine, 8 HOURS
Ultrasound etc. Also during the tasked,
technicians discussed the operation of
each equipment/ facility.

Friday

Total Number of Hours: 20

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: MARCH
Week: 18 – 22

No of
Day Date Work Accomplished Hours
Worked
Monday 18 Entry, lay outing and networking of 8:00 –
some computer systems. 5:00PM

8 HOURS

Tuesday

Wednesday 20 Observation and assist in the simulation 1:00 –


on the computer/ network system of the 5:00PM
hospital
4 HOURS

Thursday 21 Observation and assist in the simulation 8:00 –


on the computer/ network system of the 5:00PM
hospital
8 HOURS

Friday

Total Number of Hours: 20

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: MARCH
Week: 25 – 29

No of
Day Date Work Accomplished Hours
Worked
Monday 25 Assist in the installation of Biometrics 8:00 –
system. 5:00PM

Biometrics system was explained to us 8 HOURS


and how employee’s attendance would
be checked and recorded.

Tuesday

Wednesday 27 We were tasked to get all the basic 1:00 –


information of each personnel (including 5:00PM
their photo) in the company for profiling
and biometrics 4 HOURS

Thursday 28 Getting all basic information of each 8:00 –


personnel (including their photo) in the 5:00PM
company for profiling and biometrics
8 HOURS

Friday

Total Number of Hours: 20

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: APRIL
Week: 1–5

No of
Day Date Work Accomplished Hours
Worked
Monday 1 Getting all basic information of each 8:00 –
personnel (including their photo) in the 5:00PM
company for profiling and biometrics
8 HOURS

Tuesday

Wednesday 3 Entry of information of each personnel 1:00 –


in the Biometrics and in excel. 5:00PM

4 HOURS

Thursday 4 Entry of information of each personnel 8:00 –


in the Biometrics and in excel. 5:00PM

8 HOURS

Friday

Total Number of Hours: 20

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: APRIL
Week: 8 – 12

No of
Day Date Work Accomplished Hours
Worked
Monday 8 Checking of personnel’s data in the 8:00 –
system. 5:00PM

8 HOURS

Tuesday

Wednesday 10 Observation and assist in the simulation 1:00 –


on the computer/ network system of the 5:00PM
hospital
4 HOURS

Thursday 11 Observation and assist in the simulation 8:00 –


on the computer/ network system of the 5:00PM
hospital
8 HOURS

Friday

Total Number of Hours: 20

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: APRIL
Week: 22 – 26

No of
Day Date Work Accomplished Hours
Worked
Monday

Tuesday 23 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for Laboratory Department.
8 HOURS

Wednesday 24 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for Laboratory Department.
8 HOURS

Thursday 25 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for Emergency Department.
8 HOURS

Friday

Total Number of Hours: 24

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: MAY
Week: 7 – 10

No of
Day Date Work Accomplished Hours
Worked
Monday

Tuesday 7 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for Emergency Department.
8 HOURS

Wednesday 8 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for Emergency Department.
8 HOURS

Thursday 9 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for Radiology Department.
8 HOURS

Friday 10 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for HMO Department.
8 HOURS

Total Number of Hours: 32

_________________________________
Supervisor’s Signature over Printed Name
Bataan Heroes Memorial College
Roman Super Hi-Way Balanga City, Bataan
Engineering and Architecture Department
Electronics Engineering Program

WORK ACCOMPLISHMENT REPORT

Month: MAY
Week: 13 – 17

No of
Day Date Work Accomplished Hours
Worked
Monday 13 Photo editing and layout for the official 8:00 –
ID of the hospital’s personnel and 5:00PM
employees for Hemodialysis
Department. 8 HOURS

Tuesday 14 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for House and Linen.
8 HOURS

Wednesday 15 Photo editing and layout for the official 8:00 –


ID of the hospital’s personnel and 5:00PM
employees for Utility Department.
8 HOURS

Thursday 16 Compiling of all edited and layout ID per 8:00 –


department. 5:00PM

8 HOURS

Friday 17 General assessment of the course of 8:00 –


the OJT period. 5:00PM

8 HOURS

Total Number of Hours: 40