DRM450 Installation

This document provides installation instructions for a DRM450 crane in 7 stages: 1) Perform safety precautions like using PPE and qualified technicians. 2) Assemble the rear and top counterweights to the chassis. 3) Attach the boom and lift cylinders to the chassis and secure with pins and bolts. 4) Install the spreader by hinging it to the boom and attach the damping cylinder. 5) Connect the hydraulic hoses from the cylinders to the proper ports in the specified sequence.

Uploaded by

chandu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
161 views34 pages

DRM450 Installation

This document provides installation instructions for a DRM450 crane in 7 stages: 1) Perform safety precautions like using PPE and qualified technicians. 2) Assemble the rear and top counterweights to the chassis. 3) Attach the boom and lift cylinders to the chassis and secure with pins and bolts. 4) Install the spreader by hinging it to the boom and attach the damping cylinder. 5) Connect the hydraulic hoses from the cylinders to the proper ports in the specified sequence.

Uploaded by

chandu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 34

DRM450-Installation

Safety
1)Use face mask, hand gloves and keep social distancing when ever
possible
2)Wear Safety PPE
3)Use Fork lift with man gauge for working in height
4)Wear Safety harness while working in height
5)Deploy qualified supervisor, Crane operator and technicians for
assembling
6)Use proper lifting chains(slings) and shackles for lifting heavy objects
7)Use correct handling capacity cranes for assembling spreader, boom
counter weight and Lift cylinder
8)For Electrical Installation deploy qualified electrician
9)If any clarification required ,contact Cargotec service personal or MAU
1)Park the machine in the level surface
2)Before starting the assembly, make sure the parking brake is switch on
Stage I-Rear Counter weight Assembly
Stage I-Rear Counter weight Assembly
Stage I-Rear Counter weight Assembly

1)Align the counterweight with Chassis rear plate


2)Use M36X130 Length bolt with washer for Rear Counter weight mounting
3)Properly Tight the bolts (Tightening Torque 1400Nm)
Stage II-Top Counter weight Assembly
Stage II-Top Counter weight Assembly

Chassis Bracket Fender Mountings

1)Align the counterweight with Chassis Bracket, Mud guard(Fender) and rear counterweight
2)Use M36X80 Length bolt with washer for Rear Counter weight mounting
3)Properly Tight the bolts (Tightening Torque 1400Nm)
Stage III-Boom and Lift Cylinder Assembly

1)Clean and apply a new grease in chassis hinge bore and Boom
bushings
2)Make sure ,rear part of the boom is slightly down as comparing the
front side .for that use lengthy chain or slings in rear side
Stage III-Boom and Lift Cylinder Assembly
Stage III-Boom and Lift Cylinder Assembly

Before inserting the pin Align all the chassis and boom bore
in Inline
Stage III-Boom and Lift Cylinder Assembly

1)Secure the pin with M20X55 length bolt with washer


2)Hold the boom with cranes until lift cylinder mounting
Stage III-Boom and Lift Cylinder Assembly

1)Secure the pin with M20X55 length bolt with washer


2)Hold the boom with cranes until lift cylinder mounting
Stage III-Boom and Lift Cylinder Assembly

LEFT & RIGHT MARKINGS ARE THERE ON THE


CYLINDERS…FIX ACCORDINGLY
Stage III-Boom and Lift Cylinder Assembly

Valve is facing
towards inside

Align the cylinder bottom bore with Chassis bracket. ensure both lift
cylinder valve is facing towards inside
Stage III-Boom and Lift Cylinder Assembly

Mount the pin and secured with Lock plate and Bolts(M20X55
and washer)
Stage III-Boom and Lift Cylinder Assembly

Align the boom bracket and Lift cylinder by adjusting both the cranes(Crane
holding with Cylinder and Crane holding with boom. During this time cylinder is
very close with cabin. Take extra care for Cabin
Stage III-Boom and Lift Cylinder Assembly

Mount the pin and secured with Lock plate and


Bolts(M20X55 and washer)
Stage III-Boom and Lift Cylinder Assembly

Do the same in LH side


Stage III-Boom and Lift Cylinder Assembly

Check all Pin mountings and Lock plate tightness. Release both the
cranes.
Stage IV-Spreader Installation
Stage IV-Spreader Installation

Lifting Hook
Stage IV-Spreader Installation
Stage IV-Spreader Installation

Align the Boom and Spreader hinge bores in inline


Stage IV-Spreader Installation
Stage IV-Spreader Installation

Insert the pin and secured with Bolt and Lock nut
Stage IV-Spreader Installation

1)Align the damping cylinder and mount the pins


2)Secured with Bolt and washer
3)
Stage IV-Spreader Installation

Release the chains or slings after Damping Cylinder Mounting


Stage V-Hydraulic Connections

Connect the hoses as per the sequence marked. All the


hoses and fittings having face seals. Take care during
hose tightness
Stage V-Hydraulic Connections

Connect the hoses as per the sequence marked


Stage V-Hydraulic Connections

RH Cylinder
connections

Connect the hoses as per the sequence marked


Stage V-Hydraulic Connections

LH Cylinder
connections

Connect the hoses as per the sequence marked


Stage V-Hydraulic Connections

Damping
Cylinder
connections

Connect the hoses as per the sequence marked