Answer to A PERT network consists of the activities in the following list. Times are given in weeks. Activity a m b Б Predecessor..
Answer to A PERT network consists of the activities in the following list. Times are given in weeks. Activity a m b Б Predecessor..
Solutions
QUESTION
https://badassstudy.ml/answerK7C55WZ8CGFVBP9.html 1/3
10/5/21, 9:17 AM Eggy
A PERT network consists of the activities in the following list. Times are given in
weeks. Activity a m b Б Predecessor A 7 10 13 B 4 8 9 C 3 7 12 AB D 5 9 12 С E 8 11 15 C, D
a. What is the project length? [Select] b. What activities form the critical path? [Select] c.
What is the project standard deviation? 2.93 weeks < d. How much slack is in activity B?
[Select] e. What is the probability that the project will take 40 weeks or less? (Select] < f.
How many weeks would be required to be 99% sure of completion? [Select]
Show transcribed image text A PERT network consists of the activities in the following list.
Times are given in weeks. Activity a m b Б Predecessor A 7 10 13 B 4 8 9 C 3 7 12 AB D 5 9
12 С E 8 11 15 C, D a. What is the project length? [Select] b. What activities form the critical
path? [Select] c. What is the project standard deviation? 2.93 weeks
Comments
ANSWER
Thumbs Up : 1
Thumbs Down : 1
Answer:
Expected
Expected Variance,
Optimistic Pessimistic time=
Activity completion (sigma)^2=
time-a time-b (a+4*m+
time-m (b-a/6)^2
b)/6
A 7 10 13 10.00 1.00
B 4 8 9 7.50 0.69
C 3 7 12 7.17 2.25
D 5 9 12 8.83 1.36
E 8 11 15 11.17 1.36
Paths
c.
https://badassstudy.ml/answerK7C55WZ8CGFVBP9.html 2/3
10/5/21, 9:17 AM Eggy
https://badassstudy.ml/answerK7C55WZ8CGFVBP9.html 3/3