Answer to A PERT network consists of the activities in the following list. Times are given in weeks. Activity a m b Б Predecessor..

A PERT network consists of 5 activities (A, B, C, D, E) with expected durations provided. The critical path is A-C-D-E with a total project length of 37.17 weeks. Activity B has 2.5 weeks of slack. The standard deviation of the project duration is calculated to be 2.44 weeks.

Uploaded by

vinayak kapoor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
96 views3 pages

Answer to A PERT network consists of the activities in the following list. Times are given in weeks. Activity a m b Б Predecessor..

A PERT network consists of 5 activities (A, B, C, D, E) with expected durations provided. The critical path is A-C-D-E with a total project length of 37.17 weeks. Activity B has 2.5 weeks of slack. The standard deviation of the project duration is calculated to be 2.44 weeks.

Uploaded by

vinayak kapoor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

10/5/21, 9:17 AM Eggy

Solutions

QUESTION

Question: Answer to A PERT network


consists of the activities in the following list.
Times are given in weeks. Activity a m b Б
Predecessor...

https://badassstudy.ml/answerK7C55WZ8CGFVBP9.html 1/3
10/5/21, 9:17 AM Eggy

A PERT network consists of the activities in the following list. Times are given in
weeks. Activity a m b Б Predecessor A 7 10 13 B 4 8 9 C 3 7 12 AB D 5 9 12 С E 8 11 15 C, D
a. What is the project length? [Select] b. What activities form the critical path? [Select] c.
What is the project standard deviation? 2.93 weeks < d. How much slack is in activity B?
[Select] e. What is the probability that the project will take 40 weeks or less? (Select] < f.
How many weeks would be required to be 99% sure of completion? [Select]
Show transcribed image text A PERT network consists of the activities in the following list.
Times are given in weeks. Activity a m b Б Predecessor A 7 10 13 B 4 8 9 C 3 7 12 AB D 5 9
12 С E 8 11 15 C, D a. What is the project length? [Select] b. What activities form the critical
path? [Select] c. What is the project standard deviation? 2.93 weeks
Comments

ANSWER
Thumbs Up : 1

Thumbs Down : 1

Answer:

Expected
Expected Variance,
Optimistic Pessimistic time=
Activity completion (sigma)^2=
time-a time-b (a+4*m+
time-m (b-a/6)^2
b)/6
A 7 10 13 10.00 1.00
B 4 8 9 7.50 0.69
C 3 7 12 7.17 2.25
D 5 9 12 8.83 1.36
E 8 11 15 11.17 1.36
Paths

Paths Duration Variance


ACDE 37.17 5.97
ACE 28.33
BCDE 34.67
BCE 25.83
The longest path is the critical path

a. Project length= 37.17

b. Critical path activities are A-C-D-E

c.

https://badassstudy.ml/answerK7C55WZ8CGFVBP9.html 2/3
10/5/21, 9:17 AM Eggy

variance along the critical


path 5.97
standard deviation=
sqrt(variance)=   2.44
d. Slack in activity B will be equal to the difference
in activity times of A and B= 2.5
weeks (because the
activity after B is the critical path activity)