Project Plan and Timeline - Rempoa House Renovation
Project Plan and Timeline - Rempoa House Renovation
Project Plan and Timeline - Rempoa House Renovation
uration Start Finish Resource Feb 25, '18 Mar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18Jun 10, '18 Jul 1, '18 Jul 22, '18 Aug 12, '18 S
Names F S S M T W T F S S M T W T F S S M T W T F S S
0 Rempoa House Renovation 1,746 hrs 150 days Mon 2/26/18 Thu 8/30/18
1 Project Initiated 0 hrs 0 days Mon 2/26/18 Mon 2/26/18 2/26
2 PHASE: PLANNING 104 hrs 20.75 days Tue 2/27/18 Fri 3/23/18
3 DELIVERABLE: Design & Architectural Drawing Document 104 hrs 20.75 days Tue 2/27/18 Fri 3/23/18
4 Requirement Gathering 24 hrs 4 days Tue 2/27/18 Fri 3/2/18 Inal[75%] Inal[75%]
5 Design and Architectural Drawing Development 40 hrs 11 days Mon 3/5/18 Fri 3/16/18 GDR Architects[90%] GDR Architects[90%]
6 Review and Finalize Architecthural Design & Drawing 24 hrs 5 days Mon 3/19/18 Fri 3/23/18 GDR Architects[90%] GDR Architects[90%]
7 Permit Submission to Kelurahan (IMB) 16 hrs 10 days Mon 3/12/18 Thu 3/22/18 Inal[15%] Inal[15%]
8 Design and Architecthural Drawing Completed 0 hrs 0 days Fri 3/23/18 Fri 3/23/18 3/23
9 PHASE: PRE-DEVELOPMENT 150 hrs 17.38 days Fri 3/23/18 Fri 4/13/18
10 DELIVERABLE: Land and As Building Readiness 150 hrs 17.38 days Fri 3/23/18 Fri 4/13/18
11 Consctuction (New Stucture) 60 hrs 7.5 days Fri 3/23/18 Tue 4/3/18 Contractor Contractor
12 Current Stucture Destruction (Wall, Roof, Land and Other) 60 hrs 7.5 days Thu 4/5/18 Fri 4/13/18 Contractor Contractor
13 Other Preparation 30 hrs 3.75 days Mon 4/9/18 Thu 4/12/18 Contractor Contractor
14 Land and As Is Building Ready to Build 0 hrs 0 days Fri 4/13/18 Fri 4/13/18 4/13
15 PHASE: DEVELOPMENT 972 hrs 95.75 days Mon 4/16/18 Mon 8/13/18
16 DELIVERABLE: Main Structure of A New Building 120 hrs 15 days Mon 4/16/18 Thu 5/3/18
17 2nd Level Floor Construction 60 hrs 7.5 days Mon 4/16/18 Tue 4/24/18 Contractor Contractor
18 Wall Construction 60 hrs 7.5 days Tue 4/24/18 Thu 5/3/18 Contractor Contractor
19 Build a new stcuture completed 0 hrs 0 days Thu 5/3/18 Thu 5/3/18 5/3
20 DELIVERABLE: Roof Construction & Wall Finishing 120 hrs 15 days Thu 5/3/18 Tue 5/22/18
21 Roof Construction 60 hrs 7.5 days Thu 5/3/18 Fri 5/11/18 Contractor Contractor
22 Finisihing Wall 60 hrs 7.5 days Mon 5/14/18 Tue 5/22/18 Contractor Contractor
23 Roof Construction Completed 0 hrs 0 days Tue 5/22/18 Tue 5/22/18 5/22
24 DELIVERABLE: Plumbing and Electrical Installed 180 hrs 15 days Tue 5/22/18 Fri 6/8/18
25 Electrical Line Installation 60 hrs 7.5 days Tue 5/22/18 Thu 5/31/18 Contractor Contractor
26 Plumbing Installation 60 hrs 7.5 days Tue 5/22/18 Thu 5/31/18 Contractor Contractor
27 Other (ventilation, etc.) 60 hrs 7.5 days Thu 5/31/18 Fri 6/8/18 Contractor Contractor
28 Electrical and Plumbing Installation Completed 0 hrs 0 days Fri 6/8/18 Fri 6/8/18 6/8
29 DELIVERABLE: Floor, Ceiling and Bathroom 180 hrs 15 days Mon 6/18/18 Thu 7/5/18
30 Ceiling Installation 60 hrs 7.5 days Mon 6/18/18 Tue 6/26/18 Contractor Contractor
31 Floor Installation 60 hrs 7.5 days Tue 6/26/18 Thu 7/5/18 Contractor Contractor
32 Batchroom Installation 60 hrs 7.5 days Tue 6/26/18 Thu 7/5/18 Contractor Contractor
33 Floor, Ceiling and Bathrom Completed 0 hrs 0 days Thu 7/5/18 Thu 7/5/18 Contractor 7/5
34 DELIVERABLE: Door and Window Installed 60 hrs 7.5 days Thu 7/5/18 Mon 7/16/18
35 Door and Window Installation 60 hrs 7.5 days Thu 7/5/18 Mon 7/16/18 Contractor Contractor
36 Door and Window Completed 0 hrs 0 days Mon 7/16/18 Mon 7/16/18 7/16
37 DELIVERABLE: Wall Painted & All Finished 120 hrs 15 days Mon 7/16/18 Thu 8/2/18
38 Painting Wall 60 hrs 7.5 days Mon 7/16/18 Tue 7/24/18 Contractor Contractor
Page 1
ID Task Name Work Duration Start Finish Resource Feb 25, '18 Mar 18, '18 Apr 8, '18 Apr 29, '18 May 20, '18Jun 10, '18 Jul 1, '18 Jul 22, '18 Aug 12, '18 S
Names F S S M T W T F S S M T W T F S S M T W T F S S
39 Other Finishing 60 hrs 7.5 days Tue 7/24/18 Thu 8/2/18 Contractor Contractor
40 Wall Paint and All Part Completed 0 hrs 0 days Thu 8/2/18 Thu 8/2/18 8/2
41 DELIVERABLE: Interior Design Installed Properly 60 hrs 7.5 days Thu 8/2/18 Mon 8/13/18
42 Interior Design Installation 60 hrs 7.5 days Thu 8/2/18 Mon 8/13/18 Contractor Contractor
43 Interior Design Application Completed 0 hrs 0 days Mon 8/13/18 Mon 8/13/18 Contractor 8/13
44 DELIVERABLE: Railing and Outdoors 132 hrs 7.5 days Thu 8/2/18 Mon 8/13/18
45 Carport Floor Installation 60 hrs 7.5 days Thu 8/2/18 Mon 8/13/18 Contractor Contractor
46 Railing Installation 24 hrs 3 days Thu 8/2/18 Tue 8/7/18 Contractor Contractor
47 Terrace floor 24 hrs 3 days Thu 8/2/18 Tue 8/7/18 Contractor Contractor
48 Canopy Installation 24 hrs 3 days Thu 8/2/18 Tue 8/7/18 Contractor Contractor
49 Railing and Outdoor Completed 0 hrs 0 days Mon 8/13/18 Mon 8/13/18 8/13
50 Development A New House Completed 0 hrs 0 days Mon 8/13/18 Mon 8/13/18 8/13
51 PHASE: COMMISSIONING AND HAND OVER 270 hrs 13.45 days Mon 8/13/18 Wed 8/29/18
52 DELIVERABLE: Cheklist and Fixing Items 150 hrs 4.29 days Mon 8/13/18 Thu 8/16/18
53 Architectural Review 60 hrs 4.29 days Mon 8/13/18 Thu 8/16/18 Inal,Contractor Inal,Con
54 Functional Review 60 hrs 4.29 days Mon 8/13/18 Thu 8/16/18 Inal,Contractor Inal,Con
55 Aesthetics Review 30 hrs 3.33 days Mon 8/13/18 Thu 8/16/18 Inal[75%],Contractor[75%] Inal[75%]
56 Validation and Checklist Completed 0 hrs 0 days Thu 8/16/18 Thu 8/16/18 8/16
57 DELIVERABLE: All Fixing Items Addressed 120 hrs 9.17 days Thu 8/16/18 Wed 8/29/18
58 Addressing Fixing Items 60 hrs 7.5 days Thu 8/16/18 Mon 8/27/18 Contractor Co
59 Review and Handover 60 hrs 1.67 days Mon 8/27/18 Wed 8/29/18 Inal[75%],Contractor[75%] Ina
60 Addressing Validation and Checklist Completed 0 hrs 0 days Wed 8/29/18 Wed 8/29/18 8
61 PHASE: PROJECT MANAGEMENT 250 hrs 150 days Mon 2/26/18 Thu 8/30/18
62 DELIVERABLE: Manage, Supervise and Quality Control 250 hrs 150 days Mon 2/26/18 Thu 8/30/18
63 Supervise Task, Quality Control and Time keeper 200 hrs 150 days Mon 2/26/18 Thu 8/30/18 Chief Contractor C
64 Project Management and Cost Control 50 hrs 150 days Mon 2/26/18 Thu 8/30/18 Inal In
65 Project Completed 0 hrs 0 days Wed 8/29/18 Wed 8/29/18 8