Cover Block Method Sta

This document provides a methodology for making concrete cover blocks for reinforced concrete structures. It outlines the scope, references, roles and responsibilities of project members, required materials, tools, equipment, and work method and control steps for producing the concrete cover blocks.

Uploaded by

Ravi kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views1 page

Cover Block Method Sta

This document provides a methodology for making concrete cover blocks for reinforced concrete structures. It outlines the scope, references, roles and responsibilities of project members, required materials, tools, equipment, and work method and control steps for producing the concrete cover blocks.

Uploaded by

Ravi kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

METHODOLOGY FOR

CONCRETE COVER BLOCK FOR RCC SRTUCTURE

SCOPE
This Methodology describes a proper work procedure shall be carried out during the making cover
blocks work.
.
REFERENCES
 Project Specification
 Site Drawing
 General Notes

ROLE & RESPONSIBILITIES:


 Project Manager: He shall be responsible to guide and give direction to the entire site team to
execute the job as mentioned in this Methodology.
 Site Engineer: He shall be responsible for control, supervision and implementation of this
Methodology at project site.
 QA/QC Engineer: He shall be responsible to carry out material approval/field
inspection/checking.
 Site Supervisor: He shall be responsible to carry out the work as per drawing, specification.

MATERIAL, TOOLS AND EQUIPMENTS

 Steel Wire Brush


 Trowel
 Kany/Patra
 Mould
 Raw Material & Cement water.
 Mixer Machine.

WORK METHOD AND CONTROL

 Identify the areas where is block making


 Prepare the Area and apply the shuttering oil properly.
 The ratio of concrete block same as concrete of strength as per requirement.
 Mix the material in the concrete mixture as per grade of concrete.
 Making the cover with size mould.
 Cure in surface minimum for 7 days