Architecture GATE Solution Calculating Decadal Growth Rate
Architecture GATE Solution Calculating Decadal Growth Rate
Projected Growth
If you wish to calculate projected growth to some point in the future, first calculate the
Annual Growth Rate (R) with Equation #3 and then calculate the Projected Growth (Pf) with
Equation #4.
Example 1:
Suppose your average attendance in 2003 is 400 and your average attendance in 1993
was 175. What is your decadal growth rate?
The data is ten years apart (2003 – 1993 = 10) so use Formula #1
Pn = Population now = 400
Po = Population originally = 175
𝑃𝑛 − 𝑃𝑜
𝐷𝐺𝑅 = ( ) × 100
𝑃𝑜
400 − 175
𝐷𝐺𝑅 = ( ) × 100
175
225
𝐷𝐺𝑅 = ( ) × 100
175
(DGR is usually reported in whole numbers so round up to the nearest whole number)
Example 2:
Suppose your average attendance in 2003 is 850 and your average attendance in 1998
was 500. What is your decadal growth rate?
𝐷𝐺𝑅a = 189%
Example #3:
Suppose your average attendance in 1998 was 500 and your average attendance in 2003
is 850. If you continue to grow at the same rate, what would your average attendance
be in 2010?
𝑅 = {0.112} × 100
𝑅 = 11.2%
Continue by using the decimal form of this rate (0.112) and calculate projected growth with Equation #4.
𝑃𝑓 = 𝑃𝑛 (1 + 𝑟)N
𝑃𝑓 = 850 X (1 + 0.112)7
𝑃𝑓 = 850 X (1.112)7
𝑃𝑓 = 850 X (2.103)
𝑃𝑓 = 1785
Example #4:
A town of 2,25,000 population in 1981 has exhibited a decadal growth ratio of 25% and
30% during 1991 and 2001 respectively. Estimate the population in 2011 having 40%
decadal growth rate:
(1) 3,50,000
(2) 6,14,250
(3) 5,11,875
(4) 4,50,000
Solution :
Pf = Population in the future
Pn = Population now = 2,25,000
N = Interval between Pn and Pf = 1
Note : Population in the future for year 2001 = Population now for year2011
Terms
The laws
1d
Where E is illuminance 2d
3d
I is Luminous intensity
d is distance
Example 1 - The illuminance on a surface directly below a point source is 400 lux. If
the distance between the light source and the surface is 2m, what is the intensity of the
light source?
Solution :-
The solution assumes that the lamp is a filament or energy saver type.
A long fluorescent type does not use this law
I
E lux
d2
I Ed2
I 400 4 I 1600cd
I 100 d 1.58m
d d
E 40
Cosine Law
This method allows us to calculate the illuminance with one or more lamps or with
reflection from surroundings. b
c
I
E cos
d2 ?
I
Point a E In this case d = h h = 3m
d
d2
I 400
E E 44.4lx
h2 9
a 4m b
I I
Point b E cos E 0.6
d2 d2
400
E 0.6 E = 9.6 lx
25
Q.55 If utilization factor is 0.5, at a working height of 90 cm above the floor level, the
illumination in lux would be
(A) 100 (B) 200
(C) 500 (D) 1000
Answer (A)
Explanation:-
We know that
Work area = A = 100 m2
Number of lamps = N = 10 lamps
Required Illumination = E
Lumen output of lamp = O
Coefficient of utilization = cu
Maintenance factor = mf ( Not given)
Q.55 If utilization factor is 0.5, at a working height of 90 cm above the floor level, the
illumination in lux would be
N cu O 10 0.5 (40 50)
E E 100lm
A 100
Site planning
Principles
1. Keeping in view the purpose of building
2. Fast developing, social and friendly neighborhood
3. Where community services, utilities, amenities, means of transport are
available
4. With in the limits of area, building byelaws
5. With possibilities of future extension
6. Situation on elevated place, with uniform slopes
7. Good soil surface for foundation
8. Naturally beautiful and man made environment
9. Good landscape and away from quarries, kilns, factories
10. Consider legal, financial aspects. (ownership rights)
Area of plot
Less than 200 SQm 60%
200 – 500 50%
500 – 1000 40%
More than 1000 33.33%
-1-
PERT/CPM
PERT – Program Evaluation & Review Technique – It is generally used for those projects where time required
to complete various activities are not known as a priori. It is probabilistic model & is primarily concerned for
evaluation of time. It is event oriented.
CPM – Critical Path Analysis – It is a commonly used for those projects which are repetitive in nature & where
one has prior experience of handling similar projects. It is a deterministic model & places emphasis on time & cost
for activities of a project.
• A project can be defined as a set of large number of activities or jobs (with each activity consuming
time & resources) that are performed in a certain sequence determined.
• A network is a graphical representation of a project, depicting the flow as well as the sequence of well-
defined activities & events.
• An activity (Also known as task & job) is any portion of a project which consumes time or resources
and has definable beginning & ending.
• Event (Also known as node & connector) is the beginning & ending points of an activity or a group
of activities.
Network Representation:
Each activity of the project is represented by arrow pointing in direction of progress of project. The events of the
network establish the precedence relationship among different activities.
Three rules are available for constructing the network.
Rule 2. Each activity must be identified by two distinct events & No two or more activities can have the same tail
and head events.
Following figure shows how a dummy activity can be used to represent two concurrent activities, A & B. By
definition, a dummy activity, which normally is depicted by a dashed arrow, consumes no time or resources.
Dummy activity is a hypothetical activity which takes no resource or time to complete. It is represented by broken
arrowed line & is used for either distinguishing activities having common starting & finishing events or to identify &
maintain proper precedence relationship between activities that are not connected by events.
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
-2-
Inserting dummy activity in one four ways in the figure, we maintain the concurrence of A & B, and provide unique
end events for the two activities (to satisfy Rule 2).
Rule 3. To maintain correct precedence relationship, the following questions must be answered as each activity is
added to the network:
(a) What activities must be immediately precede the current activity?
(b) What activities must follow the current activity?
(c) What activities must occur concurrently with the current activity?
The answers to these questions may require the use of dummy activities to ensure correct precedences among
the activities. For example, consider the following segment of a project:
1. Activity C starts immediately after A and B have been completed.
2. Activity E starts only after B has been completed.
Part (a) of the figure above, shows the incorrect representation of the precedence relationship because it requires
both A & B to be completed before E can start. In part (b) the use of dummy rectifies situation.
Question 1: What do you mean by a dummy activity? Why it is used in networking? (4 Marks) May/08
Question 2: Depict the following dependency relationships by means of network diagrams.(The Alphabets stands
for activities)
1. A and B control F; B and C control G.
2. A and B control F; B controls G while C controls G and H.
3. A controls F and G; B controls G while C controls G and H.
4. A controls F and G; B and C control G with H depending upon C.
5. F and G are controlled by A, G and H are controlled by B with H controlled by B and C.
6. A controls F, G and H; B controls G and H with H controlled by C.
Question 3: Develop a network based on the following information;
Activity Immediate predecessors
A -
B -
C A
D B
E C,D
F D
G E
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
-3-
H F
Question 4: Construct the project network comprised of activities A to L with the following precedence
relationships:
(a) A,B and C, the first activities of the project can be executed concurrently
(b) A & B precede D
(c) B precedes E,F,H
(d) F and C precede G
(e) E and H precede I & J
(f) C,D,F and J precede K
(g) K precede L
(h) I, G, and L are terminal activities of the project.
Question 5: Construct the project network comprised of activities A to P that satisfies the following precedence
relationships:
(a) A,B and C, the first activities of the project can be executed concurrently
(b) D,E and F follow A
(c) I and G follow both B and D
(d) H follows both C & G
(e) K and L follow I
(f) J succeeds both E and H
(g) M and N succeed F, but cannot start until both E and H are completed.
(h) O succeeds both M and I
(i) P succeeds J,L and O
(j) K,N and P are the terminal activities of the project.
Question 6: A publisher has a contract with an author to publish a textbook. The simplified (activities) associated
with the production of the textbook are given below. The author is required to submit to the publisher a hard copy
and a computer file of the manuscript. Develop the associated network for the project.
Question 7: A project consists of a series of tasks labeled A, B, …., H, I with the following relationships (W<X, Y
means X and Y cannot start until W is completed; X, Y<W means W cannot start until both X and Y are
completed). With this notation construct the network diagram having the following constraints:
A<D, E; B,D <F; C<G; B<H; F,G<I
Question 8 (Concurrent Activities): The footing of a building can be completed in four consecutive sections.
The activities for each section include (1) digging, (2) placing steel, and (3) pouring concrete. The digging of one
section cannot start until that of the preceding section has been completed. The same restriction applies placing
steel & pouring concrete. Develop the project network.
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
-4-
In PERT analysis, there is always a great deal of uncertainty associated with the activity durations of any project.
Therefore, te estimated time is better described by a probability distribution than by a single estimate. Three time
estimates (from beta probability distribution) are made as follows:
1) The Optimistic Time Estimate (to): Shortest possible time in which an activity can be completed in ideal
conditions. No provisions are made for delays or setbacks while estimating this time.
2) The Most Likely Time (tm): It assumes that things go in normal way with few setbacks.
3) The Pessimistic Time (tp): The max. possible time if everything go wrong & abnormal situations prevailed.
However, major catastrophes such as earthquakes, labour troubles, etc. are not taken into account.
The expected time (mean time) for each activity can be approximated using the weighted average i.e.
Forward Pass Computation: It is the process of tracing the network from START to END. It gives the earliest start
& finish times for each activity.
Earliest event time (Ej): The time that event j will occur if the preceding activities are started as early as possible.
Ej is the max. of the sums Ei + tij involving each immediately precedent event i & intervening event ij.
Backward Pass Computation: It is the process of tracing the network starting from LAST node & moving
backward.
Latest event time (Lj): The latest time that event i can occur without delaying completion of beyond its earliest
time. Li is the min. of the differences Li - tij involving each immediately precedent event j & intervening event ij.
E.g. of Earliest event time & Latest event time:
Activity: 1-2 1-3 2-3 2-5 3-4 3-6 4-5 4-6 5-6 6-7
Duration: 15 15 3 5 8 12 1 14 3 14
(Weeks)
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
-5-
• In accordance with Zero Slack Convention, if no schedule date for completion of the project is
specified, then we take L=E for the terminal event of the project.
• It is a convention to keep the earliest allowance time of the START event as zero.
• Flexibility of non critical in case of event is known as slack & in case of activity is term as
float.(Though some writers have used these terms interchangeably).
The critical path can be identified by determining the following four parameters for each activity:
• EST - earliest start time: the earliest time at which the activity can start given that all its precedent
activities must be completed first = Ei
• EFT - earliest finish time, equal to the earliest start time for the activity plus the time required to complete
the activity = EST(i-j) + tij
• LFT - latest finish time: the latest time at which the activity can be completed without delaying (beyond its
targeted completion time) the project = Lj
• LST - latest start time, equal to the latest finish time minus the time required to complete the activity =
LFT(i-j) - tij
CRITICAL PATH: The critical path is the path through the project network in which none of the activities have
float (total float is zero) i.e. A critical path satisfies following 3 conditions:
• EST =LST
• EFT=LFT
• Ej – Ei = Lj – Li = tij
The duration of project is fixed by the time taken to complete the path through the network with the greatest total
duration. This path is known as critical path & activities on it are known as critical activities. A delay in the critical
path delays the project. Similarly, to accelerate the project it is necessary to reduce the total time required for the
activities in the critical path.
Dummy Activity may or may not lie on critical path.
Question 9 (Critical Path): Tasks A, B, C,….., H, I constitute a project. The precedence relationships are
A<D; A<E; B<F; D<F; C<G; C<H; F<I; G<I
Draw a network to represent the project and find the minimum time of completion of the project when time, in
days, of each task is as follows:
Task: A B C D E F G H I
Time: 8 10 8 10 16 17 18 14 9
Also identify the critical path.
[Ans.: Critical path is 1-2-4-5-6 with 44 days]
Question 10: A project consists of seven activities for which relevant data are given below:
(i) Draw the network (5 Marks)
(ii) Name and highlight the critical path.
Activity Preceding activity Activity duration (days)
A 4
B 7
C 6
D A, B 5
E A, B 7
F C, D, E 6
G C, D, E 5 (1Mark)Nov2006
[Ans.: B. E,F = 20 days]
Question 11 (Forward and Backward Pass): A project schedule has the following characteristics:
Activity Time (weeks) Activity Times (week)
1-2 4 5-6 4
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
-6-
1-3 1 5-7 8
2-4 1 6-8 1
3-4 1 7-8 2
3-5 6 8-9 1
4-9 5 8-10 8
9-10 7
(i) Construct the PERT network
(ii) Compute E and L for each event;
(iii) Float for each activity; and
(iii) Find critical path and its duration. (10 Marks) May/2000
[Note: Float is to be calculated only after going through below text]
[Ans.: Critical path is 1-3-5-7-8-10 with 25 weeks]
The total float time for an activity is the time between its earliest and latest start time, or between its earliest and
latest finish time. It is the amount of time that an activity can be delayed past its earliest start or earliest finish
without delaying the project. = LST-EST or LFT-EFT = LFT-EST-tij = LFT- (EST+tij)
The slack time or slack of an event in a network is the difference the latest event time & earliest event time i.e. Li-
Ei
The free float time of an activity is equal to the amount by which its duration can be increased without affecting
either the project time or the time available for the subsequent activities. It indicates the value by which an activity
can be delayed beyond the earliest starting point without affecting the earliest start, & therefore, the total float of
the activities following it. = Total Floatij – (Slack of event j)
The independent float time of an activity is the amount by which the duration of an activity could be extended
without affecting the total project time, the time available for subsequent activities or the time available for the
preceding activities. = [Free Floatij – (Slack of event i)] or ZERO, whichever is higher. Also EST of following
activity – LFT of preceding activity – Duration of current activity or Zero, whichever is higher.
The interfering float time is the part of total float which causes a reduction in the float of successor activities. It is
that portion of the activity float which cannot be consumed without affecting adversely the float of the subsequent
activity or activities. = LFT – (EST of following activity) or ZERO, whichever is higher.
While calculating floats, for just for our simplifying computations, we can write values of Slack of event j in
column wherein we are supposed to write interfering float.
Subcritical Activity: Activity having next higher float than the critical activity.
Supercritical Activity: These Activities have negative float. It results when activity duration is more than time
available. It indicates abnormal situation requiring as to how to compress the activity.
Subcritical path: The path with the next least floats than critical path is subcritical path.
Float Calculation
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
-7-
Question 12 (Floats): The utility data for a network are given below. Determine the total, free, independent and
interfering floats and identify the critical path.
Activity: 0-1 1-2 1-3 2-4 2-5 3-4 3-6 4-7 5-7 6-7
Duration: 2 8 10 6 3 3 7 5 2 8
[Ans.: Critical Path is 0-1-3-6-7 with 27]
Question 13: For the network given below, compute E and L for each event & determine the total, free,
independent and interfering floats and identify the critical path.
Question 14: The following table gives the activities in a construction project and the time duration of each
activity:
Activity Preceding activity Normal Time (Days)
A - 16
B - 20
C A 8
D A 10
E B, C 6
F D, E 12
Required:
(i) Draw the activity network of the project.
(ii) Find critical path.
(iii) Find the total float and free-float for each activity. (6 Marks) Nov/07
[Ans.: (ii) A-C-E-F = 42 days.(iii) Total Float A-0, B-4, C-0, D-4, E-0, F-0; Free Float A-0, B-4, C-0, D-4, E-0, F-0]
Question 15: Given is the following information regarding a project:
Activity A B C D E F G H I J K L
Dependence - - - AB B B FC B EH EH CDFJ K
Duration (days) 3 4 2 5 1 3 6 4 4 2 1 5
Draw the Network Diagram and identify the Critical Path and Project Duration. (Nov/94)
Find the three types of float (viz. Total, Free and Independent) for each activity.
[Ans.: B-H-J-K-L = 16 days]
Probability Estimate: It is used to calculate the probability of completing the time within given duration (Using
Normal Distribution):
Z = (T1 – Tcp)/σt
Where, Z = Standard Normal Variate
T1 = Duration in which we wish to complete the project
Tcp = Duration on critical path
σt = Standard Deviation of the earliest finish of network = Square root of sum of variance of all activity
durations of critical path, where
Variance Distribution (σ2t) = [(tp – to)/6]2
• In case there are two critical paths, variance of separate activities of both of them shall be added for
calculating σt, but for calculating Z, we will take higher of two σt taken above.
• In case of event variance, if there are two longest paths, higher of the two would picked up.
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
-8-
Question 16: If the critical path of a project is 20 months alongwith a standard deviation of 4 months, what is the
probability that the project will be completed within: (a) 20 months (b) 18 months (c) 24 months?
[Ans.: 0.50, 0.31, 0.84]
Question 17: PERT calculation yield a project length of 60 weeks with variance of 9. Within how many weeks
would you expect the project to be completed with probability of 0.99? (That is the project length that you would
expect to be exceeded only by 1% of time if the project were repeated many time in an identical manner).
[Ans.: 67 weeks]
Question 18: Consider the network shown below. The three time estimates for the activities are given along the
arrows. Determine the critical path. What is the probability that the project will be completed in 20 days?
[Ans.: 0.6844]
Question 19: Consider the schedule of activities and related information as given below, for the construction of a
plant:
Activity Expected Time Variance Expected Cost
(Months) (Millions of Rs.)
1-2 4 1 5
2-3 2 1 3
3-6 3 1 4
2-4 6 2 9
1-5 2 1 2
5-6 5 1 12
4-6 9 5 20
5-7 7 8 7
7-8 10 16 14
6-8 1 1 4
Assuming that the cost and time required for one activity is independent of the time an cost of any other activity
are expected to follow normal distribution.
Draw a network based on the above data and calculate:
(a) Critical path
(b) Expected cost of construction of the plant.
(c) Expected time required to build the plant.
(d) The standard deviation of the expected time. (10 Marks) May/01
[Ans.: (a) 1-2-4-6-8; (b) Rs. 80 millions; (c) 20 months; (d) 3 months]
Question 20: A project consists of seven activities and the time estimates of the activities are furnished as under:
Activity Optimistic Most likely Pessimistic
Days Days Days
1-2 4 10 16
1-3 3 6 9
1-4 4 7 16
2-5 5 5 5
3-5 8 11 32
4-6 4 10 16
5-6 2 5 8
Required:
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
-9-
(8 Marks) Nov./04
[Hint: Critical Path is 1-2-4-5-7 and probability = 7.93%]
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
- 10 -
Question 23: A small project is composed of seven activities, whose time estimates are listed below. Activities
are identified by their beginning (i) and (j) node number.
Activity Estimated durations (in days)
(i-j) Optimistic Most Likely Pessimistic
1-2 2 2 14
1-3 2 8 14
1-4 4 4 16
2-5 2 2 2
3-5 4 10 28
4-6 4 10 16
5-6 6 12 30
(a) Draw the project network.
(b) Find the expected duration and variance for each activity. What is the expected project length.
(c) What is the probability that project will be completed at least 8 days earlier than expected?
(d) If the project due date is 38 days, what is the probability of not meeting the due date?
Given: z 0.50 0.67 1.00 1.33 2.00
P 0.3085 0.2514 0.1587 0.0918 0.0228
[Hint: The expected duration of the project = 34 days; Probability of meeting the due date is 9.18%; Probability
not meeting the due date is 25.14%] (7 Marks) Nov/05
Question 24: A project consists of the following activities, whose time estimates are given against each as under:
Estimated duration (weeks)
Activity Optimistic Most likely Pessimistic
1-2 3 6 15
1-3 2 5 14
1-4 6 12 30
2-5 2 5 8
2-6 5 11 17
3-6 3 6 15
4-7 3 9 27
5-7 1 4 7
6-7 4 19 28
Required :
(i) Draw the project net work.
(ii) Find the expected duration and variance of each activity.
(iii) Determine the critical path and the expected project duration.
(iv
What is the probability that the project will be completed in 38 weeks?
)
(v) What project duration will have 95% chance of completion. (Z0.95 = 1.65)
Given : Z 0.21 0.41 0.82
0.0832 0.1591 0.2939 (8 Marks) May/03
[Ans.: (iii) Critical path 1→2→6→7, Expected project duration is 36 weeks. (iv) 66% (v) 44 weeks]
Question 25: An Engineering Project has the following activities, whose time estimates are listed below:
Activity Estimated Duration (in months)
(i-j) Optimistic Most Likely Pessimistic
1-2 2 2 14
1-3 2 8 14
1-4 4 4 16
2-5 2 2 2
3-5 4 10 28
4-6 4 10 16
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
- 11 -
5-6 6 12 30
(a) Draw the project network and find the critical path.
(b) Find the expected duration and variance for each activity. What is the expected project length?
(c) Calculate the variance and standard deviation of the project length.
(d) What is the probability that the project will be completed at least eight months earlier than expected time?
(e) If the project due date is 38 months, what is the probability of not meeting the due date? Given:
Given: z 0.50 0.67 1.00 1.33 2.00
P 0.3085 0.2514 0.1587 0.0918 0.0228
[Ans.: (i) Critical path 1-3-5-6; (ii) Expected project length 34 months; (iii) Variance 36 months, Standard
Deviation 6; (iv) 9.18%; (v) 25.14%] (10 Marks) Nov./01
Question 26: A civil engineering firm has to bid for the construction of a dam. The activities and their time
estimates are given below:
Activity Optimistic Most likely Pessimistic
1-2 14 17 25
2-3 14 18 21
2-4 13 15 18
2-8 16 19 28
3-4 (dummy) 0 0 0
3-5 15 18 27
4-6 13 17 21
5-7 (dummy) 0 0 0
5-9 14 18 20
6-7 (dummy) 0 0 0
6-8 (dummy) 0 0 0
7-9 16 20 41
8-9 14 16 22
The policy of the firm with respect to submitting bids is to bid the minimum amount that will provide a 95% of
probability of at best breaking-even. The fixed costs for the project are eight lakhs and the variable costs are 9000
every day spent working on the project. The duration is in days and the costs are in rupees.
What amount should the firm bid under this policy? (You may perform the calculations on duration etc., up to two
decimal places) [May 1990]
[Ans.: Rs. 1574000]
Question 27: The optimistic, most likely and pessimistic times of the activities of a project are given below.
Activity 40-50 must not start before 22 days, while activity 70-90 must end by 35 days. The scheduled completion
time of the project is 46 days. Draw the network and determine the critical path. What is the probability of
completing the project in scheduled time?
Activity to-tm-tp Activity to-tm-tp
10-20 4-8-12 50-70 3-6-9
20-30 1-4-7 50-80 4-6-8
20-40 8-12-16 60-100 4-6-8
30-50 3-5-7 70-90 4-8-12
40-50 0-0-0 80-90 2-5-8
40-60 3-6-9 90-100 4-10-16
[Ans.: 10-20-40-50-70-90-100 = 46 days; Probability is 50%]
Question 28[Calculation for this question is lengthy but probability of non-critical event is a good point]:
A PERT network is shown below. The activity times in days are given along with the arrows. The scheduled times
for some important events are given along the nodes. Determine the critical path and probabilities of meeting the
scheduled dates for the specified events. Tabulate the results and determine the slack and for each event.
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
- 12 -
[Ans.: Critical Path is 1-3-4-8-11-12 with project completion time as 26.51 days, Probability of completing the
project in the scheduled completion time of 24 days is 29.54%, Probability that event 3 will occur on scheduled
date is 20.44% & Probability of meeting schedule date of event 5 is less than or equal to 54.89% with minimum of
1.8%]
Question 29: Distinction between PERT and CPM (5 Marks) Nov/98 & (5 Marks) Nov/07
PERT CPM
1. PERT is used for non-repetitive jobs like planning the 1. CPM is used for repetitive job like building a house
assembly of the space. 2. It is a deterministic model.
2. it is a probabilistic model. 3. It is activity-oriented as the result or calculations are
3. It is event-oriented as the results of analysis are considered in terms of activities or operations of the
expressed in terms of events or distinct points in time project.
indicative of progress. 4. It is applied mainly for construction and business
4. It is applied mainly for planning and scheduling problems.
research programmes. 5. CPM does not incorporate statistical analysis in
5. PERT incorporates statistical analysis and thereby determining time estimates, because time is precise
determines the probabilities concerning the time by and known.
which each activity or entire project would be 6. It is difficult to use CPM as a control device for the
completed. simple reason that one must repeat the entire
6. PERT serves as useful control device as it assists evaluation of the project each time the changes are
management in controlling a project by calling attention introduced into the network.
to such delays
Project Crashing: There are usually compelling reasons to complete the project earlier than the originally
estimated duration of critical path computed on the normal basis of a new project.
Direct Cost: This is the cost of the materials, equipment and labour required to perform the activity. When the time
duration is reduced the project direct cost increases.
Activity Cost Slope = (Cc- Nc)÷(Nt-Ct)
Where, Cc = Crash Cost = Direct cost that is anticipated in completing an activity within crash time.
Nc = Normal Cost = This is the lowest possible direct cost required to complete an activity
Nt = Normal Time = Min. time required to complete an activity at normal cost.
Ct = Crash Time = Min. time required to complete an activity.
Indirect Cost: It consists of two parts: fixed cost and variable cost. The fixed cost is due to general and
administrative expenses, insurance, etc. Variable indirect cost consists of supervision, interest on capital, etc.
The total project cost is the sum of the direct & the indirect costs.
Optimum duration is the project duration at which total project cost is lowest.
Question 30: A project is composed of seven activities as per the details given below:
Activity Normal Time Crash Time Normal Cost Crash Cost
(Days) (Days) (Rs.) (Rs.)
1-2 4 3 1500 2000
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
- 13 -
Question 33: The following table gives data on normal time and cost and crash time and cost for a project.
(d) Draw the network and identify the critical path.
(e) What is the normal project duration and associated cost?
(f) Find out total float for each activity.
(g) Crash the relevant activities systematically and determine the optimum project time and cost.
Activity Normal Crash
Time Cost Time Cost
(Week) (Rs.) (Week) (Rs.)
1-2 3 300 2 400
2-3 3 30 3 30
2-4 7 420 5 580
2-5 9 720 7 810
3-5 5 250 4 300
4-5 0 0 0 0
5-6 6 320 4 410
6-7 4 400 3 470
6-8 13 780 10 900
7-8 10 1000 9 1200
4220
Indirect costs are Rs. 50 per week.
[Ans.: (b) Normal Project Duration is 32 weeks with cost of Rs. 5820; (d) Optimum Project Duration is 29 weeks
with cost of Rs. 5805]
Question 34: A small project is having seven activities. The relevant data about these activities is given below:
Activity Dependence Normal Crash duration Normal cost Crash Cost
duration (Days) (Rs.) (Rs.)
(Days)
A - 7 5 500 900
B A 4 2 400 60000
C A 5 5 500 500
D A 6 4 800 1000
E B,C 7 4 700 1000
F C,D 5 2 800 1400
G E,F 6 4 800 1600
(i) Find out the normal duration and the minimum duration.
(ii) What is the percentage increase in cost to complete the project in 21 days? (10 Marks) Nov./97
[Ans.: (i) Normal duration 25 days, minimum duration 18 days; (ii) 15.5%]
Miscellaneous Topics:
Question 35: Write short notes on resource smoothing and resource leveling.
(5 Marks each) May/99, May/00, May/02, Nov./02, May/05
Resource smoothing is a resource scheduling technique used for smoothing peak resource requirement during
different periods of project network. Under this technique, the constraint may be the total project duration. It helps
to estimate the resource requirements for various projects. In resource smoothing, time scaled diagram of various
activities of project and their floats along with their resource requirements are used. Floats on non critical activities
are utilized & these activities are rescheduled or shifted (while the project duration remains unchanged) so that a
uniform demand on resources is achieved.
Resource Levelling (a.k.a. resource allocation) is an operation of resource scheduling wherein constraint may be
availability of certain resources. Here project time is varied for maximum utilization of resources i.e. project
duration is not treated as an invariant, but the demand on certain specified resources should not go beyond a
specified level. The maximum demand of a resource should not exceed the available limit at any point of time.
Non critical activities are rescheduled by utilizing their floats.
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
- 15 -
Points which are worth noting for developing the algorithm for resource allocation:
1. Halt when both resources and activities are available.
2. Prior to allocation at a halt, up date the E.S.T., E.F.T. and float of the activities not allocated at earlier halt
time and their succeeding activities. The repercussions may have to be traced right up to the last event.
3. (a) priorities are assigned on the basis of floats e.g. 1st priority to activity with least float, 2nd to the activity
with the next higher float and so on.
(b) In case of tie in floats, assign priorities on the basis of man-days if the activities e.g., 1st priority to the
activity with highest M × D.
(c) In case of tie in man-days even, assign 1st priority to the activity with highest M (gang size).
(d) In case of tie in M’s even, assign 1st priority to the activity with lower i, where i is the tail event number
of the activity.
4. When an activity requires more than one man, it may so happen during allocation that the activity requires
more number of persons than that available at the halt time under consideration. In such cases, the
resources are allocated to the job with next priority for which they are sufficient.
5. During the floating out of activities, the float of an activity may go negative which means that the project
duration is going to be extended beyond the critical path. Once the float of an activity becomes negative,
there from the float criterion for ascertaining priorities is invalidated. The priorities are then fixed on the
basis of M x D, gang size and lower i criteria respectively.
Question 36: The Madras Construction Company is bidding on a contract to install a line of microwave towers. It
has identified the following activities, along with their expected time, predecessor restrictions, and worker
requirements:
Activity Duration, Weeks Predecessor Crew size, workers
A 4 None 4
B 7 None 2
C 3 A 2
D 3 A 4
E 2 B 3
F 2 B 3
G 2 D,E 3
H 3 F,G 4
The contract specifies that the project must be completed in 14 weeks. This company will assign a fixed number
of workers to the project for its entire duration, and so it would like to ensure that the minimum number of workers
is assigned and that the project will be completed in 14 weeks. Find a schedule which will do this.
[Hint.: The maximum number of workers to be assigned to the project is 6] (10 Marks) May/95
Question 37 (Resource Smoothing): A network with the following activity durations and manpower requirement
is given. Analyze the project from point of view of resources to bring out the necessary steps involved in the
analysis and smoothing of resources.
Activity: 1-2 2-3 2-4 3-5 4-6 4-7 5-8 6-8 7-9 8-10 9-10
Duration (weeks): 2 3 4 2 4 3 6 6 5 4 4
No. of Men required: 4 3 3 5 3 4 3 6 2 2 9
[Ans.: Demand for men will decrease to 15 to 11]
Question 38 (Resource Smoothing): Consider a project consisting of 14 activities having the duration and
resource requirement shown below. Analyze the project and smoothen the requirement of the resources.
Activity Duration (Weeks) Masons (M) Labourers (L)
1-2 2 1 2
2-3 3 2 2
2-4 4 3 2
2-5 2 1 3
3-10 4 2 2
4-6 2 3 2
4-7 4 3 3
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
- 16 -
5-9 4 5 3
6-8 2 1 2
7-9 5 1 3
8-9 3 - 4
9-11 2 1 1
10-11 3 1 2
11-12 2 1 2
[Ans.: Demand for masons will decrease to 8 & 10 for Labourers]
Question 39 (Resource Allocation): The following information is available:
Activity No. of days No. of men reqd. per day
A 1-2 4 2
B 1-3 2 3
C 1-4 8 5
D 2-6 6 3
E 3-5 4 2
F 5-6 1 3
G 4-6 1 8
(a) Draw the network and find the critical path.
(b) What is the peak requirement of Manpower? On which day(s) will this occur?
(c) If the maximum labour available on any day is only 10, when can the project be completed?
[Ans.: (i) Critical Path is AD = 10 days (ii) Peak requirement is 11 men, required on days 7 and 9 (iii) the project
can be completed in 11 days.] (9 Marks) May/08
Question 40 (Resource Allocation): For a project consisting of several activities, the durations and required
resources for carrying out each of the activities and their availabilities are given below:
(a) Draw the network, identify critical path and compute the total float for each of the activities.
(b) Find the project completion time under the given resource constraints.
Resources required
Activity Equipment Operators Duration (Days)
1-2 X 30 4
1-3 Y 20 3
1-4 Z 20 6
2-4 X 30 4
2-5 Z 20 8
3-4 Y 20 4
3-5 Y 20 4
4-5 X 30 6
Resource availability:
No. of operators = 50, equipment X = 1, equipment Y = 1, equipment Z = 1
[Ans.: Critical Path is 1-2-4-5 with duration of 14 days, Project requires 21 days for completion under given
constraints] (Nov./85)
Questions on Resource Smoothing and Resource Levelling are rarely being asked in Examination.
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
- 18 -
z 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09
0.0 0.0000 0.0040 0.0080 0.0120 0.0160 0.0199 0.0239 0.0279 0.0319 0.0359
0.1 0.0398 0.0438 0.0478 0.0517 0.0557 0.0596 0.0636 0.0675 0.0714 0.0753
0.2 0.0793 0.0832 0.0871 0.0910 0.0948 0.0987 0.1026 0.1064 0.1103 0.1141
0.3 0.1179 0.1217 0.1255 0.1293 0.1331 0.1368 0.1406 0.1443 0.1480 0.1517
0.4 0.1554 0.1591 0.1628 0.1664 0.1700 0.1736 0.1772 0.1808 0.1844 0.1879
0.5 0.1915 0.1950 0.1985 0.2019 0.2054 0.2088 0.2123 0.2157 0.2190 0.2224
0.6 0.2257 0.2291 0.2324 0.2357 0.2389 0.2422 0.2454 0.2486 0.2517 0.2549
0.7 0.2580 0.2611 0.2642 0.2673 0.2704 0.2734 0.2764 0.2794 0.2823 0.2852
0.8 0.2881 0.2910 0.2939 0.2967 0.2995 0.3023 0.3051 0.3078 0.3106 0.3133
0.9 0.3159 0.3186 0.3212 0.3238 0.3264 0.3289 0.3315 0.3304 0.3365 0.3389
1.0 0.3413 0.3438 0.3461 0.3485 0.3508 0.3531 0.3554 0.3577 0.3599 0.3621
1.1 0.3643 0.3665 0.3686 0.3708 0.3729 0.3749 0.3770 0.3790 0.3810 0.3830
1.2 0.3849 0.3869 0.3888 0.3907 0.3925 0.3944 0.3962 0.3980 0.3997 0.4015
1.3 0.4032 0.4049 0.4066 0.4082 0.4099 0.4115 0.4131 0.4147 0.4162 0.4177
1.4 0.4192 0.4207 0.4222 0.4236 0.4251 0.4265 0.4279 0.4292 0.4306 0.4319
1.5 0.4332 0.4345 0.4357 0.4370 0.4382 0.4394 0.4406 0.4418 0.4429 0.4441
1.6 0.4452 0.4463 0.4474 0.4484 0.4495 0.4505 0.4515 0.4525 0.4535 0.4545
1.7 0.4554 0.4564 0.4573 0.4582 0.4591 0.4599 0.4608 0.4616 0.4625 0.4633
1.8 0.4641 0.4649 0.4656 0.4664 0.4671 0.4678 0.4686 0.4693 0.4699 0.4706
1.9 0.4713 0.4719 0.4726 0.4732 0.4738 0.4744 0.4750 0.4756 0.4761 0.4767
2.0 0.4772 0.4778 0.4783 0.4788 0.4793 0.4798 0.4803 0.4808 0.4812 0.4817
2.1 0.4821 0.4826 0.4830 0.4834 0.4838 0.4842 0.4846 0.4850 0.4854 0.4857
2.2 0.4861 0.4864 0.4868 0.4871 0.4875 0.4878 0.4881 0.4884 0.4887 0.4890
2.3 0.4893 0.4896 0.4898 0.4901 0.4904 0.4906 0.4909 0.4911 0.4913 0.4916
2.4 0.4918 0.4920 0.4922 0.4925 0.4927 0.4929 0.4931 0.4932 0.4934 0.4936
2.5 0.4938 0.4940 0.4941 0.4943 0.4945 0.4946 0.4948 0.4949 0.4951 0.4952
2.6 0.4953 0.4955 0.4956 0.4957 0.4959 0.4960 0.4961 0.4962 0.4963 0.4964
2.7 0.4965 0.4966 0.4967 0.4968 0.4969 0.4970 0.4971 0.4972 0.4973 0.4974
2.8 0.4974 0.4975 0.4976 0.4977 0.4977 0.4978 0.4979 0.4979 0.4980 0.4981
2.9 0.4981 0.4982 0.4982 0.4983 0.4984 0.4984 0.4985 0.4985 0.4986 0.4986
3.0 0.4987 0.4987 0.4987 0.4988 0.4988 0.4989 0.4989 0.4989 0.4990 0.4990
3.1 0.4990 0.4991 0.4991 0.4991 0.4992 0.4992 0.4992 0.4992 0.4993 0.4993
3.2 0.4993 0.4993 0.4994 0.4994 0.4994 0.4994 0.4994 0.4995 0.4995 0.4995
3.3 0.4995 0.4995 0.4995 0.4996 0.4996 0.4996 0.4996 0.4996 0.4996 0.4997
3.4 0.4997 0.4997 0.4997 0.4997 0.4997 0.4997 0.4997 0.4997 0.4997 0.4998
3.5 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998
3.6 0.4998 0.4998 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999
3.7 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999
CA. Parag Gupta Ph.: +91 9891 432 632 [email protected] Costing & O.R.
For notes/updates/amendments on all subjects log on: http://groups.yahoo.com/group/costingbyparaggupta
Arch. Developments
Alphabetical List of some of the key buildings and structures in the world:
photo © webbaviation
National Gallery Building Berlin, Germany
picture © AW
St Peter’s Basilica, Rome
Sphinx, Egypt
Statue of Liberty, New York
Taj Mahal, India
Tower Bridge, London
The Tower, London
Uffizi Palace, Florence
Victoria & Albert Museum, London
Washington Monument, Washington DC
Washington National Cathedral, Washington DC
White House, Washington DC
Windsor Castle, England
Suggestions for Famous Buildings welcome: info(at)e-architect.co.uk
Global Architecture
Famous World Architects
World Architects – Complete A-Z list
New York Buildings
Stone Construction
ashlar
hewn stone blocks with straight-cut edges
coursing
a continuous layer of material, a row
fieldstone
building stone collected from a field
finish
the surface texture; common finishes are
rock-faced, rusticated and vermiculated
rustication
stonework emphasized by roughly cut block
faces
rubble
construction with fragments of broken stone
vermiculated
ornamentation in stone created with winding,
wavy lines, as if caused by worms
Windows and Doors
The openings in the walls of a building—the
windows and the doors—are the source of great
attention in a design. (The technical name for
the placement of openings in the walls of a
building is fenestration, from the French,
“fenêtre,” meaning window). The placement and
the detail work that comprises windows and
doors can be the source of great attention.
Window
Types
bay
double hung
casement
Palladian
Shapes of Openings
round arch (below left)
pointed arch (bottom left)
flat top
segmental arch (right)
triangular
Tudor arch (below right)
trim around a window or door opening
tracery
a pattern of interlocking muntins in the upper
part of a Gothic pointed window (see pointed
arch drawing, page 5)
transom light
a window located above a door (door
drawing)
capital
the decorative feature at the top of a column or
pilaster
column
an upright post, usually a tapered cylinder, used
for support or decoration; in classical
Elements and Details architecture a column consists of a base, shaft
The elements and details that either are part of a and capital
building’s structure (like the parts of a window)
or are applied to it (like cresting or brackets) are corbel
often what creates visual delight. The following a masonry unit or series of masonry units that
list of words is only a brief catalogue of the progressively step out from a supporting wall or
hundreds of technical terms that have been column
developed over centuries to describe the many
and marvellous details of a building. corbel table
a projecting line of masonry or belt courses
supported by corbels
arch
a curved structure spanning across the top of an cornice
opening in a vertical surface (such as a wall) a horizontal, projecting decorative moulding
along the top of a wall or building, or the top
balcony portion of an entablature
a structural platform extending from the wall of
a building and enclosed with a balustrade; crenellation
supported from below or cantilevered from a a series of square indentations in a parapet
supporting wall giving a castle-like appearance
baluster/balustrade cresting
balusters are upright posts or spindles that ornamental ridge, like a miniature fence, along
support a handrail/a balustrade is a series of the top of a roof
balusters under a handrail
cupola
bargeboard a small domed structure on top of a roof or
a board, often decorative, covering the larger dome
projecting edge of a gable roof
dentils
belt course band of small, tooth-like blocks usually used in
a slender, horizontal band that projects from an Classical architecture
exterior wall often at window sill or interior
floor levels dome
a roof structure in the shape of a portion of a
bracket sphere
an angular support for a horizontal element that
projects from a wall dormer
a roofed projection from a sloping roof often
with a window
pediment
in classical architecture, the triangular end of a
low-pitched gable; a triangular element used
over doors and windows
pendant
an ornamental feature that hangs down from a
supporting structure or architectural feature
pier
eaves a massive vertical support of masonry, placed
the part of a sloping roof that overhangs a wall under columns, arches or walls to support a
concentration of loads
entablature
the upper horizontal part of a Classical order, pilaster
consisting of the cornice, frieze and architrave; a shallow pier or post, often decorative,
similar to a beam projecting slightly from the surface of a wall;
resembles a square post attached to a wall
gable
the triangular upper portion of a wall formed by pinnacle
the slopes of a pitched roof a small vertical ornament with a spire-like
pyramidal or conical shape, usually used to
half-timbering crown buttresses or the corners of parapets and
a method of construction where the spaces in a towers
timber-frame wall are filled with rubble or
brickwork pitch
the angle at which a roof slopes from its peak to
finial its eaves
an ornament at the top of a roof gable, spire or
other architectural feature porch
a structure projecting from a building and
frieze located in front of an entrance; usually roofed,
the central band in a classical entablature above often open-sided and occasionally supporting a
the architrave and below the cornice; or often a balcony above
decorative band running under the cornice of an
interior or exterior wall portico
an open-sided porch with a column-supported
keystone roof
the central uppermost member of an arch
quoins
massing stones or bricks used to decoratively emphasize
the organization of three-dimensional volumes the outside corners of a building
or spaces into a coherent composition
shingles
moulding wood or asphalt tiles for covering roofs and
a decorative element that defines edges, joints or walls
surfaces through the use of a continuous profile
spindle
parapet lathe-turned wood elements, often used as
the portion of an exterior wall that projects balusters and porch decoration
above the edge of a roof area
spire
a tall, narrow, steep roof structure ending in a
point, rising from a tower or roof peak
terra cotta
fired clay cast in moulds, often used for
decorative elements or to clad a building exterior
tower
a building, either freestanding or attached as a
prominent element of another building, of great
height compared to its floor area; a slender, tall
structure usually rising above the building to
which it is attached
turret
a small, slender tower characteristically
projecting from the corner of a building
vault
a roof or ceiling structure over an area that is
based on the form of an arch
verandah
a roofed porch or balcony attached to the
elevation of a building
Classical Greek and Roman architecture is
defined by a great many technical terms, only a
few of which are noted here.
Grade (slope)
From Wikipedia, the free encyclopedia
This article is about the grade of a topographic feature or constructed element. For other uses,
see Slope (disambiguation).
d = run
Δh = rise
l = slope length
α = angle of inclination
The grade (also called slope, incline, gradient, pitch or rise) of a physical feature, landform or
constructed line refers to the tangent of the angle of that surface to the horizontal. It is a special
case of the gradient in calculus where zero indicates gravitational level. A larger number
indicates higher or steeper degree of "tilt". Often slope is calculated as a ratio of "rise" to "run", or
as a fraction ("rise over run") in which run is the horizontal distance and rise is the vertical
distance.
The grades or slopes of existing physical features such as canyons and hillsides, stream and
river banks and beds are often described. Grades are typically specified for new constructions
(such as roads, landscape grading, roof pitches, railroads, aqueducts, and pedestrian or bicycle
circulation routes).
Nomenclature[edit]
1. as an angle of inclination to the horizontal. (This is the angle α opposite the "rise" side of
a triangle with a right angle between vertical rise and horizontal run.)
2. as a percentage, the formula for which is which could also be expressed as the
tangent of the angle of inclination times 100. In the U.S., this percentage "grade" is the
most commonly used unit for communicating slopes in transportation (streets,
roads, highways and rail tracks), surveying, construction, and civil engineering.
3. as a per mille figure, the formula for which is which could also be expressed
as the tangent of the angle of inclination times 1000. This is commonly used in Europe to
denote the incline of a railway.
4. as a ratio of one part rise to so many parts run. For example, a slope that has a rise of 5
feet for every 100 feet of run would have a slope ratio of 1 in 20. (The word "in" is
normally used rather than the mathematical ratio notation of "1:20"). This is generally the
method used to describe railway grades in Australia and the UK.
Any of these may be used. Grade is usually expressed as a percentage, but this is easily
converted to the angle α from horizontal or the other expressions.
Slope may still be expressed when the horizontal run is not known: the rise can be divided by
the hypotenuse(the slope length). This is not the usual way to specify slope; it follows
the sine function rather than the tangent function, so it calls a 45-degree slope a 71-percent
grade instead of a 100-percent. But in practice the usual way to calculate slope is to measure the
distance along the slope and the vertical rise, and calculate the horizontal run from that. When
the angle of inclination is small, using the slope length rather than the horizontal displacement
(i.e. using the sine of the angle rather than the tangent) makes only an insignificant difference.
Railway gradients are usually expressed in terms of the rise in relation to the distance along the
track as a practical measure. In cases where the difference between sin and tan is significant,
the tangent is used.
In Europe, road gradients are signed as a percentage, the exception being Britain, where
for road signs, maps and construction work, the gradient was traditionally expressed as a ratio
such as 1 in 12, but signs showing gradient as a percentage are becoming more common.[1]
Equations[edit]
Grades are related using the following equations with symbols from the figure at top.
Tangent as a ratio
Green buildings have been in the limelight for a long time. Have you ever wondered what a
green building is? How it differs from other buildings? How can a building be rated green?
Who gives this rating?
A structure that makes efficient use of natural resources like water, energy, building materials
and other resources for sustainable development of environment is called a green building.
Using energy efficient lighting system like CLFs and LEDs, technologies like sensor system
for air conditioning and lighting to save energy and reduce emission of carbon dioxide,
appliances that consumes less energy and reduce the usage of water and other water saving
technologies makes a building green and make it different from other conventional buildings.
GRIHA (Green Rating for Integrated Habitat Assessment): GRIHA is jointly developed
by TERI and the Ministry of New and Renewable Energy, Govt. of India. It is India’s own
rating system. It consists of 34 criteria divided in four sections namely site selection and site
planning, Conservation and efficient utilization of resources, Building operation and
maintenance, and Innovation. GRIHA has a three tier process for rating any building.
IGBC (Indian Green Building Council): IGBC is a non-profit research institution formed
by Confederation of Indian Industry (CII) in 2001. IGBC has licensed the LEED green
building rating standard from USGBC. LEED-INDIA approach for green building is divided
into five key areas namely, 1) Sustainable site development, 2) Water saving, 3) Energy
efficiency, 4) Material selection and 5) Indoor environment quality.
BEE (Bureau of Energy Efficiency): BEE has developed a rating system of its own. It gives
rating on a scale of 1 to 5 stars on the basis of energy efficiency of a building. The unit of
Kilo watt hours per square meter per year is the Energy Performance Index (EPI) for rating
any building.
There are several parameters on which a building is evaluated before being given a green
rating:
5. Columnar & trabeated style evolved from wooden hut of up right posts &
supporting beam & sloping rafters.
6. two periods-Hellenic period, Hellenistic period.
7. Arches, domes, vaults were not used by the Greeks.
8. Greek used timber & after built.
9. In 600BC - Masonry from coursed rubble to fine ashlars.
- no mortar was used.
- Minimized the joints by using large sized stones.
Medieval period
renaissance periods
1. 5000 yrs ago, people from Sumerian origin came and settled nearest river
Indus.
2. Is a contemporary of ancient Mesopotamia.
3. cities were systematic and divided into 12 blocks (365*244m each)
4. English bonds in walls.
5. Streets-9m wide.
6. Under ground drainage lines with inspection chambers at regular
intervals.
7. houses consisted of rooms around a courtyard and staircase.(kiln burnt
bricks)
8. Ox- driven carts of large solid whets for transportation.
9. Tools of stone and copper were in use.
10. Pots were made of clay, wood.
Vedic (1500-1000BC)
1. Dravidians-The builders of the city civilization of Indus valley.
Indo-Aryan (1500BC)
Concept of shelter
1. Agglomeration – An urban region whose boundaries may exceed those of one,
usually large city.
2. Primary city – One or more of the largest cities in a country that holds a relatively
high percentage of the total urban population.
3. Urban population growth – refers to the increase in the absolute number of people
residing in cities.
4. Urbanization – refers to the proportion of the overall population that resides in
urban areas.
5. Decentralization – the process where by growth in urban population and
employment takes place in secondary cities that may be 150 km away from the
metropolitan area and beyond
6. Deconcentration – the expansion of employment and population in peripheral
areas around a city.
7. Housing is a medium for self expression as well as a sanctuary for old age.
Concrete
1. Cement concrete – is a mixture of cement, water, fine aggregate, course
aggregate.
2. the proportion of cement, sand and aggregates is 1:2 or 3:4 or 6
3. Lime concrete – mixture of slaked lime, fine aggregate, course aggregate. (1:2:4),
water.
4. R.C.C – the concrete and reinforcing metal.
Timber
1. Timber is derived from Timbrian means ‘built’.
2. Timber is obtained from trees not less than 600 mm in circumference.
3. Three types of timber
a. Converted – is sawn and cut into suitable sizes
b. Rough – after felling of trees
c. Standing – living tree
4. Properties of good timber
Low heat conductivity
Amenability
Small bulk density
Relatively high strength
5. Drawbacks of timber
Susceptibility to decay
Inflammability
Fluctuations due to moisture content
Variations in strength, length
6. Wood waste – saw dust, shavings are used with admixture of organic glues
to make fiber-slabs, fiber boards.
7. Other uses of wood – organic acids, rosin, paper, cardboard, cellulose.
8. Age of the wood capable of producing quality timber with adequate girth is
50 yrs.
9. Babul, Eucalyptus, poplar, sissioo (20 yrs).
10. A single tree can cool the summer heat for an entire day and night and is
found better than 20 ACs running for 20 Hrs.
11. A hectare of trees produce about 10 times of O2 (for 45 persons for 1 year)
Bricks
1. Prepared by moulding clay in rectangular blocks of uniform size.
2. Bricks are durable and having strength, reliability, low cost, easy
availability.
3. Great Wall of China (210 BC) by burnt and sun dried bricks.
4. India has production capacity to manufacture over 10000 crores.
5. Compositions of good brick earth
Use
20-30% alumina (plasticity for moulding)
50-60% silica (prevents cracks, shrinks, wrapping)
5% lime (prevents shrinkage)
5-6% oxide of iron (as lime to fuse sand and provides red color
Magnesia (yellow tint, decrease shrinkage)
6. Harmful ingredients
Effect
Excess of lime (lumps)
Iron pyrites (crystallized and disintegrated)
Alkalies (cause bricks fuse, twists, wrap)
Pebbles (unregulations)
Vegetation & (porous)
Organic matter
Concrete
1. The tensile and shear strengths are about 8 to 12 % and 8 to 10 % of their
compressive strengths respectively.
2. The comprehensive strength of concrete is influenced by
Quality of materials
Water
Water – cement ratio
Age of concrete
Cement content
Methods of mixing placing, curing
Glass
1. Is a mixture of number of metallic silicates, one of which is usually that of
an alkali metals
2. it is basically a hard, brittle, trans par cut material
3. Not effected by ordinary chemical reagents, air or water.
4. Possible to weld pieces of glass by fusion
5. Affected by alkalis but can take up high polish
6. Provides excellent electric insulation due to uncertain crystalline structure
7. Absorbs, refracts or transmits light
8. Available in colors, no sharp melting points
Wood
Steel
1. Plats may be of any size or thickness butt generally they are not rolled to
thickness <5 mm and> 28 mm
2. Maximum area of rolled plates is limited to 30 sq.m
3. plates < 4mm in thickness are sheets
4. Flats are rolled as in the case of plate but are much longer in lengths and
have shorter widths
5. Widths vary from 18mm to 50 mm, thickness – 3 mm to 8 mm
6. Angles
Structural members
1. Steel beams – include girders, lintels etc
2. Simplest beam consists of a single rolled steel joint section or an angle
section
3. To take greater loads, compound sections are used
4. plate girders are used when very large loads have to be carried
5. Beams carrying light loads and where the shearing forces are not excessive,
open web beams are used.
6. If the beam is accommodated below the top flange of the girder the
connection is called under girder flange.
7. If the top flange of the beam and portion of the web is cut off so as to
accommodate the top flange of the order that is called top flush.
8. When a beam at a lower level is to be connected to a girder at a higher level
that is called blocked connection.
9. Beams meeting at higher levels with the girder are called blocked and
elevated connection.
10. If beams and girders are connected at different levels, is called hanger
connections.
Architecture GATE Solution GATE 2017
Onsite Sanitation
Rural areas and the outskirts of the urban areas may have insufficient population and
infrastructure to support the sewer system and central treatment plant. Hence, onsite
sanitation becomes necessary to maintain hygienic living conditions. For environmentally
safe onsite sanitation, satisfactory wastewater management techniques should ensure that:
water body used for water supplies are not contaminated;
flies and vermin have no access to excreta;
surface water bodies are not polluted by runoff; and
nuisance conditions such as odour are minimized.
Acceptable onsite sanitation systems, depending on circumstances, include septic tanks and
surface percolation; extended aeration, alone or following a septic tank; and in some area
without running water the pit privy is still used.
The ratio of peak flow to average flow may be very high for the small septic tanks, and can
disturb the functioning of the tank due to flow surges, leading to washout of the settled solids.
The liquid depth of the tank is 1 to 2 m and the length to the width ratio is in the range of 2:1
to 4:1 (Figure 24.1). The sludge accumulated in the tank is cleaned at the frequency of once
in 2 to 3 years. Minimum of 300 mm of free board should be provided in the tank. The
effluent of the septic tank is offensive and potentially dangerous. Hence, further treatment for
septic tank effluent is necessary to protect the receiving environment. Due to inadequate
treatment offered to the sewage, septic tanks are recommended for individual houses and for
cluster of houses or institutes where contributing population is not exceeding 300 persons.
Table 24.1 Characteristics of household wastewater to be considered for septic tank design
Post treatment can be achieved by aerobic treatment or subsurface disposal. Diffused air
aeration with solids recycling (extended aeration), sand filter or synthetic media filter
(attached growth process) can be used for treatment of septic tank effluent. Filter bag
equipment and hypochlorite addition will also be suitable for treatment. However, frequent
replacement of filter bag and hypochlorite addition makes it costly.
Sewage flow: The flow of sewage is considered to be proportional to the number of fixture
units discharging simultaneously. One fixture unit is treated as equivalent to the flow of 10
L/min. This is equivalent to the discharge generated from one water closet (WC) when
flushed. The number of fixtures discharging simultaneously depends on the population
served. For example for the population of 5 persons, number of fixtures will be one and
probable peak discharge will be 10 L/min. Similarly for population of 10, 20, and 30 numbers
of fixtures will be 2, 3, and 4, and probable peak discharge will be 20 L/min, 30 L/min, and
40 L/min, respectively.
Detention time: The detention time of 24 to 48 h is provided for average flow conditions.
However, the flow variation is substantial from tank to tank depending upon water usage; and
it is not important design criteria.
Capacity of the Tank: The total capacity of the septic tank is worked out using following
considerations.
1. Sedimentation: An area of 0.92 m2 is required for every 10 L/min peak flow rate to
support adequate sedimentation of suspended solids. This will favour sedimentation of solids
with 0.05 mm size and sp. gravity of 1.2. A minimum of 0.25 to 0.30 m depth is necessary for
sedimentation.
2. Sludge digestion: The SS per capita may be considered as 70 g/day. It is assumed that that
60% of the solids will be removed in the tank, out of which 70% solids will be volatile, with
5% solid content i.e., 94% water content. The volume of fresh sludge = 0. 84 L/Capitaday.
Considering that 2/3 of the volatile matter is destroyed of which ¼ is mineralized during
digestion and solids content of 13 % in digested sludge, the volume of total digested sludge,
i.e., mineralized sludge with 13% solids plus undigested sludge with 5% solids, will be 0.234
L/Capita-day. The digestion zone contains both the fresh sludge (which is simultaneously
getting destroyed by 2/3 of its volume) and digested sludge; hence volume of both of these
will work out to be (0.848*1/3+0.234) = 0.516 L/Capita-day. At 25 0C the typical time
required for digestion will be 63 days. Hence, capacity of digestion zone works out to be 63 *
0.0005 = 0.032 m3/capita.
3. Volume required for sludge and scum storage: For interval of 1 year of sludge cleaning,
a sludge storage capacity of 0.0002*365 = 0.073 m3/cap is required. The 25 to 50 mm of
seed volume should be considered, and care should be taken while withdrawing the sludge to
leave this volume of sludge to act as seed. No separate depth is provided for this.
Total Capacity: Hence the total capacity of the septic tank will be equal to sum of the above
three requirements, plus a minimum free board of 0.3 m should be provided. Therefore for
20 persons the total capacity of the septic tank will be
1. Sedimentation: Considering peak flow of 30 L/min for 20 persons, the area required =
0.92*30/10 = 2.76 m2. Keeping depth of min. 0.3 m for sedimentation, the volume =
2.76*0.3 = 0.828 m3
3
2. Digestion: 0.032 * 20 = 0.64 m
3. Sludge storage: 0.073 * 20 = 1.46 m3 for one year. For 2 year cleaning frequency
sludge storage volume required = 1.46 * 2 = 2.92 m3
4. Free board = 2.76 * 0.3 = 0.828 m3.
Hence, total volume of septic tank for 20 person = 0.828 + 0.64 + 2.92 + 0.828 = 5.216 m3.
Height of the septic tank = 0.3 + 0.231 + 1.05 + 0.3 m = 1.881 m, and provide length to the
width ratio of 3; hence L = 2.88 m and W = 0.96 m
If the subsidence rate is over 0.5 mm/min, then a septic tank and the disposal system will
work satisfactorily. The disposal field is constructed by using short length open joined pipe
(100 mm dia.) or perforated plastic or fiber pipe. The length of individual pipe is up to 30 m
and laid with the slope of 0.017 to 0.33%. The pipe is placed in a ditch (300 to 900 mm
width) and minimum 500 mm depth (or it has been excavated to the depth of permeable
stratum). The ditch is backfilled with gravel for a depth of 300 to 400 mm and over which
pipes are placed. An additional 50 mm gravel cover is given to the pipe before the soil
backfilling material is placed. The total length of pipe depends on the trench width, since the
product of this, i.e., the plan area of the trench, should be equal to the area required to be
provided as per the percolation test. Laterals (pipes) are placed about 2 m c/c.
Example: Determine the size of the septic tank and percolation field for hostel which has 200
residents. The average percolation rate has been determined to be 5 mm/min. Consider rate of
wastewater generation 120 L/capita.day.
Solution:
Total wastewater volume per day = 120 x 200 x 10-3= 24 m3
Hence, for 24 hr HRT the volume of Septic tank = 24 m3 + volume for sludge accumulation
@ 0.073 m3/capita.year = 24 + 0.073 * 200 = 38.6 m3
(The exact volume requirement for the septic tank can be worked out using peak discharge of
480 L/min for 200 persons)
The percolation rate (time to fall water to the depth of 25 mm) is = 25/5 = 5 min.
Hydraulic loading applicable = Q = 130/ (t0.5) = 58 L/m2.day
Therefore, total trench area = 24/ 0.058 = 413.8 m2
If width of trench is 900 mm, length of trench = 414/0.9 = 460 m
Provide 15 laterals of 30.7 m length each, placed at 2 m c/c.
The area dedicated to the field would be = 30 x 30.7 = 921 m2.
Mounds may be constructed above the surface of the ground where the parent soil
permeability is poor by bringing pervious material. The area of mounds depends on
evapotranspiration rate for disposal of the bulk liquid. The remainder may be able to
percolate below. Grass cover and proper shaping of the mound are important to ensure that
rainfall will run-off and that evapo-transpiration of wastewater will be maximized.
Sand filters or buried filters or intermittent sand filters may be provided when soils are
relatively impermeable. Loading rates on intermittent sand filters treating septic tank effluent
ranged from 0.16 to 0.20 m3/m2.day.
Subsurface sand filters are installed in place of permeable material in a suitable excavation
(Figure 24.2). Loading rate of about 0.04 m3/m2.day can be applied, when relatively coarse
sand (1 mm) and uniform size is used (McGhee, 1991). The effluent from either filtration
process must be collected and discharged after disinfection as per the requirements.
Figure 24.2 Subsurface filter (a) Sand filter trench (b) sand filter
Onsite wastewater treatment systems have a potential to provide excellent effluent quality if
they are properly designed and operated. Constructed Wetland system can also be used for
removal of nitrogen along with other contaminant such as heavy metal removal.
Question 81- find the total volume of liquid in a septic tank with the following criteria,
i. No. of users = 20
ii. Cleaning interval = 365 Days
iii. The capacity required for sludge digestion = 0.033 m3 per capita at 25 0c
iv. Volume of digested sludge = 0.0002 m3 per capita per day.
(A) 4080 liters (B) 2580 liters (C) 5250 liters (D) 3289 liters
Solution
Total Capacity: Hence the total capacity of the septic tank will be equal to sum of the above
three requirements, plus a minimum free board of 0.3 m should be provided. Therefore for
20 ersons the total capacity of the septic tank will be
Hence, total volume of septic tank for 20 persons = 0.69 + 0.66 + 1.46 + 0.69 = 3.5 m3.
Now in question it asked the total volume of liquid in septic tank,
We know that 94% of water present in total waste,
So volume of water in septic tank = 94 % of 3.5 m3
= 3.29 m3
= 3290 litre.
The Pritzker Architecture Prize is awarded annually "to honor a living architect or architects whose built work
demonstrates a combination of those qualities of talent, vision and commitment, which has produced consistent
and significant contributions to humanity and the built environment through the art of architecture. Founded in
1979 by Jay A. Pritzker and his wife Cindy, the award is funded by the Pritzker family and sponsored by
the Hyatt Foundation and is considered to be one of the world's premier architecture prizes, it is often referred to
as the Nobel Prize of architecture.
Luis Barragan
2 1980 Mexico
41 2019
Q 56 (Gate 2010)- 25 person are in room. 15 of them play hokey, 17 of them play football
and 10 of them play both hockey and football. then the number of person playing neither
hockey nor football is.
(A) 2 (B) 17 (C) 13 (D) 3
SOLUTION:
15 - plays hockey
17 - plays football
10 - plays hockey and football
25 - people all in all
Now, since there are people who are into both sports, we're going to try to figure out
how many people are into just one sport (hockey or football).
The subtraction above tells us how many of the people are into hockey, alone. Since
10 of those 15 people who play hockey also play football, then 15 - 10 = 5 of them
are those which are just into hockey. Similarly, we have
Right now, you've already considered 5 + 7 + 10 = 22 people. Since there are only
25 people in the room, then those who neither play hockey, nor football is 25 - 22 = 3
people.
ARCHITECTURE
GATE
SOLUTION
GATE PREPRATION SERIES
This set of Construction and Building Materials Multiple Choice Questions & Answers
(MCQs) focuses on “Planning Regulations and Bye-Laws”.
1. Subdivision/layout plan which shall be drawn on a scale of not less than _______
a) 1:100
b) 1:500
c) 1:1000
d) 1:50
Answer: b
Explanation: As per National Building Code, scale for Layout plan is specified as 1:500. In this plan,
location of all proposed and existing roads, dimensions of plot along with building line, locations of sewer
and drainage line etc. are mandatory.
2. The plan of the buildings and elevations and sections accompanying the notice
shall be drawn to a scale _____
a) 1:10
b) 1:50
c) 1:100
d) 1:500
Answer: c
Explanation: This plan includes floor plans which shows the use or occupancy of all parts of the building.
Hence this parts needs to be large enough for the Engineers to understand well. Therefore NBC have
specified scale of 1:100.
3. A _____ line usually parallel to the plot boundaries and laid down in each case by the Authority, beyond
which nothing can be constructed towards the site boundaries.
a) Building line
b) Control line
c) Property line
d) Plot line
Answer: a
Explanation: Building line or Set-back is provided to avoid traffic congestion in front of the building.
Buildings like mall, multi-complexes, factories, etc. which attract large number of vehicles, should have
be set-back a further distance apart from the building line. This line after this extra margin is called as
Control Line.
4. The ratio of the total floor area inclusive of all the floors to the area of the plot on which building stands is
known as _____
a) Groundage
b) Plot area
c) Floor area
d) Built-up area
5. The aggregate area of doors and windows shall not be less than _____ of the floor area of room.
a) 1/10
b) 1/9
c) 1/7
d) 1/6
Answer: c
Explanation: As per IS code, if the area is less than the specified area, occupants of the building will not
receive enough lighting and ventilation. The area of such openings excluding area of doors should be
minimum 1/10 of the floor area for dry-hot climate and minimum 1/6 of the area for wet-hot climate.
6. The placing of various rooms or units of a structure in proper correlation of their functions and in due
proximity with each other is known as _____
a) Aspect
b) Prospect
c) Circulation
d) Grouping
Answer: d
Explanation: Grouping is the proper arrangement of rooms according to their functions leads to better
planning of a building. It is observed that grouping leads to saving in unnecessary movements, proper
correlation, easy control and overall economy.
7. The term ______ is used to mean the external views as seen from certain rooms of the building.
a) Aspect
b) Prospect
c) Elegance
d) Roominess
Answer: b
Explanation: Prospect is dictated by the surrounding peculiarities of the site of the project. This can help
us to conceal some unwanted views and reveal the beauty of the building.
8. The area on the earth which lies between the zones of cancer and Capricorn is known as the _______
a) Tropic zone
b) Frigid zone
c) Torrid zone
d) Arctic zone
Answer: a
Explanation: Topic zone lies between zone of cancer (i.e. 231/2 degree north latitude) and Capricom
(i.e. 231/2 degree south latitude). The typical features of tropical countries are burning sun, fixed
seasons and rainfall which is heavy, moderate and with storm.
This set of Construction and Building Materials Multiple Choice Questions &
Answers (MCQs) focuses on “Climate and its Effects”
1. Burnings sun, fixed seasons and rainfall which is heavy, moderate and with storm are the typical
features of _______
a) Cancer zone
b) Capricorn zone
c) Torrid zone
d) Tropical zone
Answer: d
Explanation: The area on earth which lies between the zone of cancer and Capricorn is known as
the tropics. Whole part of India is considered to be typically tropical climate.
2. The tropical climate which consists of heat waves hot winds and low humidity comes under which
climatic conditions?
a) Hot-wet
b) Hot-dry
c) Cool-dry
d) Rainy
Answer: b
Explanation: Hot-dry places are cool in winter. The maximum day temperature in summer will be
about 27°C to 42°C and the night temperature will be moderate say about 15°C to 25°C.
4. Which type of climate consists of high humidity throughout the year and even in the dry season with
variations in day and night temperatures?
a) Hot wet
b) Hot dry
c) Cool dry
d) Rainy
5. The data regarding temperature, moisture, timings of sunset and sunrise and direction of wind are
collected and preserved by ____________
a) Bureau of Indian Standards, New Delhi
b) Meteorological Department of the Ministry of Commerce, Govt. of India
c) Indian Institute of Weather Forecasting and Research Centre
d) National Institute of Technology
Answer: b
Explanation: Meteorological Department of the Ministry of Commerce, Govt. of India works
throughout the year and records every data possible. They predict the future climatic conditions by
comparing the past records of 10 to 15 years. This department has recognized the following four
seasons of the year: Cool-dry, Hot-dry season, General Rainy season, Season of the Retreating
South-West Monsoon.
6. From the given climatic conditions which have its worst effects on the building structure in India.
a) Dust storm
b) Humidity
c) Heavy rain
d) Hot summer days
Answer: c
Explanation: Every year due to heavy rain huge destruction of building materials takes place.
Mumbai itself invests more than Rs.10000 crore maintenance and repair of buildings
7. Which building material has high Seismic resistance and flexibility of nailed joints?
a) Bamboo
b) Timber
c) Ply
d) Husk
Answer: b
Explanation: As long has materials and workmanship are of good quality, timber structures can
perform very well in an earthquake. A wooden frame is usually considered to have medium to low
vulnerability towards earthquake.
9. Which is the most important advanced technique of earthquake resistant design and construction?
a) Flexible steel form
b) Reinforced concrete
c) Base Isolation
d) Steel strengthening Treatment
Answer: c
Explanation: Along with energy dissipation devices, Base Isolation technique is most advanced
which isolates the structure by a series of bearing pads. This bearing pads absorbs maximum
shocks develop due to seismic activity.
10. The temperature at the _______ is the highest and it is lowest at the ______
a) longitude, latitude
b) poles, equator
c) north, south
d) equator, poles
Answer: d
Explanation: India is in the Tropics zone and hence there is a temperature gradient from equator to
poles and depending upon the latitude of the locality, its temperature range can be decided.
1. _______ used to mean the regulation of admitting more or less sunshine in the room.
a) Elegance
b) Roominess
c) Circulation
d) Aspect
Answer: d
Explanation: The meaning of aspect has now been given wider scope and it includes the
arrangement of doors and windows in the external walls of buildings particularly of residential
buildings, so as to fully enjoy the natural gifts of sunshine, Breeze, scenery, etc.
2. The term ______ is used to mean the link or access or movement between the various rooms and
floors of building.
a) Flexibility
b) Prospect
c) Circulation
d) Elegance
Answer: c
Explanation: The proper provision of circulation makes the building comfortable and convenient. The
circulation in a building is of two types- Horizontal circulation and Vertical circulation.
3. _________ is used to indicate the architectural effect produced by elevation in relation to width,
height position of doors and windows, materials employed in the construction of external walls, etc.
a) Furniture requirements
b) Elegance
c) Roominess
d) Grouping
Answer: c
Explanation: The proper provision of circulation makes the building comfortable and convenient. The
circulation in a building is of two types- Horizontal circulation and Vertical circulation.
4. The placing of various rooms or units of a structure in a proper correlation of their functions and in
due proximity with each other is known as ________
a) Sanitation
b) Prospect
c) Economy
d) Grouping
Answer: d
Explanation: Correct grouping grants the status of a balanced design. For instance, in a residential
building, kitchen and dining room should be grouped close to each other. It is observed that grouping
leads to saving in unnecessary movement’s proper correlation easy control and overall economy.
6. The term _______ is used to refer the effect derived from space of a room that is its length, width
and height.
a) Prospect
b) Sanitation
c) Privacy
d) Roominess Answer: d
Explanation: Roominess is nothing but the feeling of spaciousness. The planning of room should be
such that maximum benefit is obtained from the minimum dimensions of the room. For example
rectangle shaped room looks more spacious than square shaped room of same area.
8. Due to improper ventilation, which gas gets stuck into house and develops dizziness to the
occupants.
a) Oxygen
b) Nitrogen
c) Carbon dioxide
d) Hydrogen
Answer: c
Explanation: If the room is not properly ventilated, there will be excessive quantity of carbon dioxide
in the air. The more the amount of carbon dioxide, the more difficult is the breathing. For comfortable
working, the carbon dioxide content should be limited to about 0.6% by volume.
Answer: a
Explanation: The difference of temperature between the outside air and the inside air tends to the
deposition of moisture on the room surfaces. This is known as the condensation and it can be
effectively controlled by the provision of suitable ventilation of the room.
10. The ________ is required to control dust and other impurities in the air.
a) Circulation
b) Sanitation
c) Ventilation
d) Purification
Answer: c
Explanation: Controlling dust and other impurities from coming into the building is the main cause of
insisting proper ventilation in the commercial buildings. The ventilation is also required to suppress
odors, smoke, concentration of bacteria, etc.
This set of Building Materials Interview Questions and Answers focuses on “Basic
Functional Requirements of a Building”
1. Construction of cavity walls as external walls to protect the building from outside heat or cold as the
hollow space between two walls act as an________
a) Burning material
b) Insulating material
c) Destructive material
d) Building material
Answer: b
Explanation: Properly insulated building cuts down the cost of electric burning in summer as well as in
winter. A cavity wall is one of the types of thermal insulation which consists of two walls with cavity in
between them.
3. Which gas leads to suffocation and dizziness to the occupants when increase in its quantity in the air.
a) Carbon monoxide
b) Hydrogen
c) Nitrogen
d) Carbon dioxide
Answer: d
Explanation: If the room is not properly ventilated, there will be excessive quantity of carbon dioxide in
the air. It is observed that breathing is difficult when the amount of carbon dioxide by volume is about 6%
and a man loses consciousness when it reaches about 10% or so.
4. The termite, which are responsible for the destruction of wooden materials, are popularly known as
_______
a) Red ants
b) White ants
c) Black ants
d) Big ants
5. The science which deals with the sound insulation in a building is known as _____
a) Reverberation
b) Transmission
c) Acoustic
d) Air borne
Answer: c
Explanation: The terms sound insulation all soundproofing is used to indicate the reduction in the level of
sound when it passes through a building component. Acoustics becomes very essential in some
buildings like cinema hall, Auditorium, Opera House, etc.
6. Fire extinguisher extinguishes the small fires in the house by using _____
a) Carbon dioxide
b) Nitrogen gas
c) Water
d) Foam
Answer: a
Explanation: Standards of fire safety or fire extinguishers are specified in the Building Code should be
provided with sufficient and quick fire exit. Fire extinguishers are one of the important building
requirements which help in extinguishing small fires.
7. The process in which the difference of temperature between the outside air and the inside air tends to
the deposition of moisture on the room surfaces is known as ______
a) Saturation
b) Accumulation
c) Precipitation
d) Condensation
Answer: d
Explanation: The temperature difference which leads to condensation can be effectively controlled by
the provision of suitable ventilation of a room.
8. The treatment given to the roof of a building to prevent the roof from the leakage of water is known as
_________
a) Fire proofing
b) Damp proofing
c) Termite proofing
d) Sound proofing
Answer: b
Explanation: One of the basic requirements in case of all the buildings is that the structural should
remain dry as far as possible. If this condition is not satisfied, it is likely that the building may become
inhabitable and hence damp proofing or water proofing is required.
9. _________ is a flexible material which is commonly used for the damp proofing.
a) Hot bitumen
b) Bituminous felts
c) Mastic asphalt
d) Metal sheets
Answer: a
Explanation: Due to its physical nature, hot bitumen remain flexible even after cooling and it is placed on
the bedding of concrete or mortar. This material should be applied with the minimum thickness of 3 mm.
whereas Mastic Asphalt is a semi rigid material and it forms and excellent impervious layer for damp
proofing.
10. Which one of the given below is a chemical insecticide for termite proofing.
a) Dieldrin
b) Sulphuric acid
c) Rodenticide
d) Pyrethrins
Answer: a
Explanation: Dieldrin is a chlorinated hydrocarbon. The application of this chemical serve as a chemical
barrier between the building and the ground and this method has proved to be most effective method of
termite proofing. Whereas, Rodenticide is used for killing rats.
5. FOUNDATION
This set of Construction and Building Materials Multiple Choice Questions & Answers
(MCQs) focuses on “Foundation
3. For loose soil, the formula used to find the minimum depth of foundation is given by _______
a) Rankine’s formula
b) Hiley formula
c) Bernoulli’s formula
d) Newtonian formula
Answer: a
Explanation: The depth of foundations can also be obtained by drawing the lines of angles 45 degree
and 60 degree from the base of the foundation towards ground level. Hence to simplify the method,
Rankine formula is used.
4. The foundation in which the loading on the soil remains practically the same after the construction of the
building is known as _______
a) Step foundation
b) Grillage foundation
c) Raft foundation
d) Inverted arch foundation
Answer: b
Explanation: Grillage foundation or Floating foundation is so adjusted that the weight of the excavated
earth is just equal to the total load of the building. In such case, the settlement is reduced to a minimum
extent.
5. _________ method of increasing the bearing power of soil becomes very useful when the load coming
on the soil is practically uniform.
a) Raft foundation
b) Grillage foundation
c) Mat foundation
d) Inverted arch foundation
Answer: a
Explanation: Raft foundations are very useful in the soil which is of yielding nature that is soft clay or
reclaimed soil. The raft is designed as an inverted RCC roof with uniformly distributed load of the soil
pressure and supported by walls, beams and columns.
6. When the ground is sloping, _______ foundations are used to correct the levels of the sloping ground on
which the building is to be constructed.
a) Shallow foundation
b) Combined foundation
c) Cantilever foundation
d) Steeped foundation
Answer: d
Explanation: Stepped foundation is adopted when the construction becomes uneconomical to provide
foundations at the same level. In this, minimum depth of 800 mm should be provided at all the points.
7. Which type of foundation is used for the construction of building on black cotton soil.
a) Inverted arch foundation
b) Floating foundation
c) Mat foundation
d) Grillage foundation
Answer: c
Explanation: Black cotton soil is a clay or loose type of soil and is considerably swells and shrinks by
variation in moisture content. The variation in the volume of the soil is to the extent of 20 to 30% of the
original volume. Hence, Raft Foundation or Mat Foundation plays important role in uniform distribution of
the load of structure over black cotton soil.
8. ________ is applied to the process of laying down certain lines and marks on the ground before the
excavation of foundation trenches.
a) Ground tracing
b) Surveying
c) Dumpy level
d) Digging
Answer: a
Explanation: The sitting out or Ground tracing is mainly done for two purposes- firstly, the excavation of
foundation trenches can be started immediately after this process is completed and secondly, the lines
and marks established by this process serve as a guide.
9. If the foundation of the structure is to be divided into two or more independent units, ________ are
provided to take care of unequal settlement.
10. A common footing provided for two or more columns is known as _________
a) Continues footing
b) Combined footing
c) Cantilever footing
d) Eccentric footing
Answer: b
Explanation: Combined footing becomes useful when an exterior column is situated near the boundary
line of the plot and it is not possible to project its footing symmetrically on both the sides.
6. PLINTH
This set of Construction and Building Materials Multiple Choice Questions & Answers
(MCQs) focuses on “Plinth”
1. The part of the building above the ground level and up to the floor level immediately above the ground is
known as __________
a) Plinth area
b) Formation level
c) Ground level
d) Plinth
Answer: d
Explanation: Plinth is therefore defined as the portion of the structure between the surface of the
surrounding ground and surface of the floor, immediately above the ground. Plinth is an important
component of building which prevents crawling animals, water and other insects from coming inside the
building.
2. The built up area measured and the plinth level is known as __________
a) Total area
b) Plinth area
c) Plot area
d) Floor area
Answer: b
Explanation: Plinth area is nothing but the build-up covered area measured at the floor level.
4. In a market area, the plinth area should not exceed ____ of the area of site.
a) 75%
b) 25%
c) 95%
d) 55%
Answer: a
Explanation: As per regulations, the plinth area should not exceed 75% of the area of commercial sites,
provided sufficient off-street parking facilities for loading and unloading of vehicles are provided on the
same plot as the building.
5. The ______ provides support to the occupants, furniture, fixtures and equipment’s of a building.
a) Plinth
b) Ramp
c) Floor
d) Lifts
Answer: c
Explanation: Different floors divide the building in two different levels to provide more accommodation on
a given plot of land. The floor of a building immediately above the ground is known as ground floor.
7. SUPERSTRUCTURE
This set of Construction and Building Materials Multiple Choice Questions & Answers
(MCQs) focuses on “Superstructure”.
2. In order to secure superstructure from earthquake, _________ technique is most preferred and used
worldwide.
a) Reinforcement
b) Base Isolation
c) Energy Dissipation
d) Seismic Dampers
Answer: b
Explanation: Base Isolation technique separates the building from the building foundation by wearing
pads. It consists of lead rubber bearing or spherical sliding isolation system. In case of an earthquake,
fix base building deform and damaged, whereas base isolated building rocks back and forth like a boat
and reduce the shock by 60%.
3. In old times, the construction of superstructure was done by using _________ building material.
a) Rubber
b) Bamboo
c) Mud
d) Timber
Answer: d
Explanation: Timber floor consists of Plank of wood with 25 mm thickness which is supported by joist
with size of 50 mm×75 mm to 100 mm. Timber was most preferred building material as compared to
bamboo as Timber was cheap and easily available.
4. __________ wall is constructed in order to support load other than its own.
a) Load supporting
b) Load distributing
c) Load bearing
d) Load releasing
Answer: c
Explanation: Load bearing walls support all loads before transferring them to the foundation the wall
5. In architecture, _________ refers to such super-structural element that also has certain proportional and
decorative features.
a) Beam
b) Column
c) Lintels
d) Sills
Answer: b
Explanation: Early columns were constructed of stone, some out of a single piece of stone, usually by
turning on a lathe-like apparatus. Single piece columns are among the heaviest stones used in
architecture. Modern columns are constructed out of Steel, precast concrete, or brick.
6. ________ are structural members design to carry and transfer transverse loads across space to support
elements.
a) Beams
b) Columns
c) Lintels
d) Sills
Answer: a
Explanation: A beam is a structural element that is capable of withstanding load primarily by resisting
bending. The bending force introduced into the material of the bean as a result of external loads, own
weight and external reactions to these loads is called a bending moment.
7. In architecture, a _________ is generally the lower horizontal surface of a room, and/or the supporting
structure underneath it.
a) Sill
b) Basement
c) Ramp
d) Floor
Answer: d
Explanation: A floor typically consists of a support structure called a sub-floor on the top of which is laid
a floor covering to provide a working surface. The floor is actually constructed above the plinth.
8. ______ is the top most part of building which provides covering to the entire assembly and the
occupants.
a) Roof
b) Ceiling
c) Coping
d) Parapet wall
Answer: a
Explanation: Roof is one of the most important building structures which provides safety and protect
occupants from sun light, storms and rain. Basic types of a room designs are Flat roof, Shed roof, Gable
roof, Hip roof, etc.
9. __________ is special material used to make sure that no moisture leaks in those areas of a roof that
are particularly vulnerable to penetration.
a) Dampers
b) Flashing
c) Ceramic
d) Wax
Answer: b
Explanation: Flashing is a strip of metal used to stop water penetrating the junction of a roof with another
surface. Areas where flashing is commonly used: where roofs meet walls, wherever the roof is pierced
by a Chimney, skylight, air or plumbing vent.
10. ________ is the structural method to maintain the favorable room temperature in every season of the
year.
a) Condensation
b) Damping
c) Air conditioning
d) Insulation
Answer: d
Explanation: Because hot air rises, roof lose more heat than walls and does require greater degree of
insulation. There is a multitude of different locations for the insulation in a roof such as resting above
ceiling, attached between rafters, between substrate and roofing, etc.
This set of Construction & Building Materials Multiple Choice Questions & Answers focuses on
“Methods of Site Exploration”.
1. A square pit, known as _________ with side as about 1.50 m, is excavated upto a depth at which
sufficiently hard soil is available.
a) Test pits
b) Probing
c) Test piles
d) Deep boring
Answer: a
Explanation: Using Trail pits or Test pits, various Tata of the soil can be inspected, studied and classified
accordingly. This method is useful when hard soil is available within a maximum depth of 1.50 meter.
2. _________ consists of driving either a hollow tube or a steel rod or an iron rod into the ground.
a) Trail pits
b) Test piles
c) Probing
d) Digging
Answer: c
Explanation: In Probing, a hollow tube of diameter 35 mm to 50 mm is taken. The tube is driven into the
ground 300 mm or so at a time. It is then withdrawn and the material caught in the slit is inspected.
3. The ____________ is the term used to denote a method in which case is driven into the ground and the
material inside the casing is washed out and brought to the surface for inspection.
a) Deep boring
b) Percussion boring
c) Rotary drilling
d) Wash boring
Answer: d
Explanation: The process of wash boring consists in driving an inner tube of diameter 25 mm to 50 mm,
inside an outer tube of diameter 100 mm to 150 mm. Whereas, percussion boring and rotary drilling are
the types of Deep boring.
a) Percussion machine
b) Rotary drilling machine
c) Electrical resistivity method
d) Seismogram
Answer: b
Explanation: In this process, a hollow tube is driven by rotary motion which cuts solid core. The water is
used to facilitate the cutting process. The machine can be used either for soft or hard material.
5. The method in which 4 electrons are driven in the ground at equal distance apart and in a straight line up to
a depth which the ground distance is to be measured.
a) Seismic refraction method
b) Geophysical method
c) Electrical resistivity method
d) Current extraction method
Answer: c
Explanation: This method is based on the principle that each soil has different electrical resistivity,
depending upon its water content, compaction and composition. For instance, the saturated soil will have
lower electrical resistivity as compared to the loose dry gravel or solid rock.
6. The number of blows required to drive the penetrometer into the ground through a distance of 300 mm is
measured which is known as _____________ of the soil.
a) Standard penetration resistance
b) Bearing power of soil
c) Maximum safe bearing capacity
d) Allowable bearing pressure
Answer: a
Explanation: The bearing capacity and the other engineering properties of certain types of soil are they
known by referring to the curves correlating Standard Penetration Resistance or SPT and the corresponding
characteristics of soil. The values of SPT of soil and different depths are determined.
7. The resistance of the soil with depth is measured by means of a tool known as the _______
a) Seismometer
b) Potentiometer
c) Penetrometer
d) Ammeter
Answer: c
Explanation: The penetrometer is used under static or dynamic loading which may consist of a sampling
spoon, a cone or tool of other shape. The penetrometer is driven in the ground with the help of blows from a
650 N weight falling from a height of 750 mm.
a) Post-hole auger
b) Screw auger
c) Shell auger
d) Rod
Answer: a
Explanation: The length of the tube is about 1.50 M and it is provided with a Jaws at the end so that it can be
suitably explore or dig the ground easily. The auger is work by applying leverage at the top.
9. The shock waves so produced travel down in the sub soil strata and get reflected after striking a hard rock
surface below and recorded by the instrument known as _____
a) Microphone
b) Geophone
c) Receiver
d) Sensors
Answer: b
Explanation: A number of geophones are arrange along a line. Some of the waves, known as direct or
primary waves are picked first buy Geophones. The Other waves which travel down through the soil get
reflected after striking a hard rock surface below.
1. _________ is used to indicate the maximum load per unit area which the soil will resist safely without
displacement.
a) Bearing power
b) Maximum safe bearing capacity
c) Strength of soil
d) Allowable bearing pressure
Answer: a
Explanation: The Load of the structure is ultimately coming on the soil and hence it is of utmost
importance to know the strength and behavior of the soil. Dividing the ultimate bearing power of soil by a
factor of safety, the safe bearing capacity of soil is obtained.
2. The term _________ on soil is used to indicate the maximum pressure which can be exerted on soil
while taking into account shear failure, settlement and the ability of structure to resist settlement.
a) Bearing capacity
b) Net pressure intensity
c) Allowable bearing pressure
d) Maximum safe bearing capacity
Answer: c
Explanation: The value of Allowable Bearing Pressure on soil depends on the nature of ground and the
type of building. The maximum safe bearing capacity of soil is generally more than the allowable bearing
pressure on soil.
3. The maximum differential settlement should not exceed _____ mm in case of foundation on sandy soil.
a) 100
b) 40
c) 50
d) 25
Answer: d
Explanation: The total amount of settlement should be generally limited between 40 mm and 100 mm.
The term differential settlement indicates the relative settlement of the adjacent portion of the structure.
4. The maximum differential settlement should not exceed ____ mm in case of foundation on clayey soil.
a) 40
b) 25
c) 100
d) 50
Answer: a
Explanation: For ordinary frame structures of concrete, the permissible angular distortion is 1/500 i.e.
one horizontal to 500 vertical and the desirable value is 1/1000 i.e. one horizontal to 1000 vertical. The
term angular distortion is used to indicate the deformation of the structure in a vertical plane.
5. The maximum safe bearing capacity of hard rocks with defects and lamination such as granite, diorite
and trap is _____ kN/m2.
a) 1650
b) 3300
c) 250
d) 100
Answer: b
Explanation: The term maximum safe bearing capacity of soil is used to indicate the maximum pressure
that is soil can be here without any risk of shear failure only, irrespective of any settlement that may
occur.
6. The maximum safe bearing capacity of very soft, wet, pasty or muddy clay is ____ kN/m2.
a) 150
b) 100
c) 50
d) 25
Answer: c
Explanation: As the given soil is very soft, wet, muddy clay, the soil possess very least minimum safe
bearing capacity. This is because, this soil possess very less intermolecular attraction between the
molecules hence it has low bearing capacity.
7. In case of non-cohesive soils such as sand and gravel, ___% reduction in allowable bearing capacity of
the soil should be applied, if the water table is situated below or near the bearing surface of the soil.
a) 20%
b) 50%
c) 80%
d) 100%
Answer: b
Explanation: However, if water table is situated below the bearing surface of the soil at a depth equal to
the width of the foundation trench, no such reduction should be applied. But in this case, 50% reduction
is applied. For intermediate depths of the water table, the proportion and percentage reduction should be
applied.
8. Identify the method given below for the determination of the bearing power of soil.
a) Plate load test method
b) Electrical resistivity method
c) Seismic refraction method
d) Geophysical method
Answer: a
Explanation: Plate load test method is one of the methods of determination of bearing power of soil.
Plate load test method is the improved point method and it is widely used for determination of the
bearing capacity. Other methods for determination are: method of loading, method of dropping a weight,
analytical methods and Presumptive method.
9. In which method, a square steel plate is used to determine the bearing power of soil.
a) Plate load test
b) Method of loading
c) Analytical method
d) Penetration test
Answer: b
Explanation: In method of loading, a square steel plate is used whose size depends on practical
conditions and it generally varies from 3000 mm2 to 7500 mm2. The plate should have sufficient
thickness to with stand the maximum bending stresses due to probable loading.
1. For determining the bearing capacity of soil, in method of loading the size for a square steel plate used
is about ________
a) 300 mm2 to 750 mm2
b) 3000 mm2 to 7500 mm2
c) 3 m2 to 75 m2
d) 3 mm2 to 75 mm2
Answer: b
Explanation: In method of loading comma the size of square steel plate generally variance from 3000
mm2 to 7500 mm2. The plates should have sufficient thickness to with stand the maximum bending
stresses due to probable loading. But in no case, it should be less than 25 mm.
3. The bearing capacity of sandy soil and gravelly soils is affected to the extent of _____% by the presence
of water table.
a) 50
b) 10
c) 25
d) 80
Answer: a
Explanation: If the water table is above the foundation level, the water should be pumped out before
placing the steel plate. If water is made with at a depth of one metre below the level of the foundation
level, the load test should be carried out at that level.
4. Due to the adjustment of soil particles under the action of loading, there is some settlement at zero
loading, this is known as the ___________
a) Bearing capacity
b) Safe bearing capacity
c) Vibroflotation
d) Zero correction
5. The loading to the test plate is applied with the help of ______
a) Sand bags
b) Hydraulic jack
c) Wooden pegs
d) Hard rocks
Answer: b
Explanation: In plate load test, the hydraulic Jack is preferably provided with the remote control pumping
unit. The reaction of the hydraulic jack is borne either by the gravity loading platform method or by the
reaction truss method.
6. In analytical methods, which soil parameters used to determine the ultimate bearing capacity of soil.
a) Angle of internal friction
b) Permeability
c) Adhesion
d) Porosity
Answer: a
Explanation: Angle of internal friction and Cohesion are the soil parameters which are used in analytical
method to determine the ultimate bearing capacity of soil. The samples, preferably of undisturbed soil,
are collected from the bore holes or test pits and various test are then carried out in the soil testing
laboratory for the purpose of analytical analysis of the soil.
7. In Penetration test, the formula obtained for the safe bearing capacity of soil per unit area is given by:
a) R÷{A×F}
b) R-{A×F}
c) R+{A×F}
d) R×{A×F}
Answer: a
Explanation: Safe bearing capacity of soil per unit area = R÷{A×F} where R is equals to ultimate
resistance of soil, A = 2 cross sectional area of the substance, F equals two factor of safety. The results
obtained by this method are approximate and hence this method is used for minor engineering
structures.
a) Penetration test
b) Method of loading
10. Which method for determining the bearing power of soil is most preferred among the given below:
a) Method of loading
b) Plate load test
c) Penetration test
d) Analytical method
Answer: b
Explanation: Plate load test is the improved refined method and it is widely used for determining the
bearing capacity of soil for important civil engineering structures. This method can be carried out in two
ways: gravity loading platform method and reaction Truss method.
This set of Construction Materials Questions and Answers for Fresher’s focuses on
“Increasing the Bearing Capacity of Soil”.
2. 2. The construction of which piles proves to be very useful in case of sandy soil or soft.
a) Cast iron pile
b) Sand pile
c) Steel pile
d) Timber pile
Answer: b
Explanation: These piles are formed by making holes in the ground and then filling the holes by
sand. If sand is kept confined, it possesses great crushing strength and becomes incompressible.
3. The movement of soil under the action of load can be prevented by confining the ground by use of
_________
a) Steel pile
b) Sand pile
c) Timber pile
d) Sheet pile
Answer: d
Explanation: When the sheet piles are used in such ground, it will result in the increase of bearing
power of soil. The wooden sheet piles are commonly used for the temporary work such as
cofferdams. They usually consists of wooden boards 80 mm to 150 mm thick, 200 mm to 300 mm
wide and 2 metres to 4 metres long.
a) Steep pile
b) Sand pile
c) Sheet pile
d) Timber pile
Answer: b
Explanation: Shown above is a typical sand pile. The sand piles are placed at 2 metres to 3 meters,
usually under the column of the structure. Load test should be carried out to determine the bearing
capacity of sand pile.
a) Sand pile
b) Sheet pile
c) Timber pile
d) Steel pile
Answer: c
Explanation: Figure given above is a Timber pile. At the bottom, a cast iron shoe is provided at the
top, a steel plate is fixed. If a group of timber piles is driven, the top of each member of the group is
brought at the same level and then, a concrete cap is provided to have a common platform.
Ar. Deepak Kumar Singh (IIT-ROORKEE) Page 34
ARCHITECTURE GATE SOLUTION 2020
a) Timber pile
b) Concrete pile
c) Composite pile
d) Screw pile
10. The commercial method which combines the effect of vibration with jetting is known as _______
a) Flooding
b) Ramming
c) Vibration
d) Vibroflotation
Answer: d
Explanation: Vibroflotation is very useful especially when the foundation is required to support heavy
loads spread over a great area. In this method, a heavy cylinder known as Vibroflot is inserted in the
ground while the cylinder vibrates due to a Rotary eccentric weight.
-----------------------------------------------------------------------------------------------------------------
Design speed of major road min. visibility distance along a major road
In K.P.H
100 220
80 180
65 145
50 110
3. Industrial premises
5. Restaurants
y
30 ºangle N=L-1.25/5
1.25
1. Traffic regulations deals with control of vehicles, drivers and road users.
2. Control of vehicles deals with registration, weight, size, design,
construction, and maintenance.
3. Driver regulations deal with licensing, operation of vehicles.
4. Road user regulations deal with rules of pedestrians, cyclists, motor
cyclists.
5. Speed limits in urban areas – Indian conditions
Chapter I – preliminary
Chapter II – licensing of drivers of motor vehicles
Chapter III – licensing of conductors of stage carriages
Chapter IV – control of transport vehicles
Chapter V – construction, equipment and maintenance of motor vehicles.
Chapter VI – control of traffic
Chapter VII – motor vehicles temporary leaving or visiting India
Chapter VIII – insurance f motor vehicles against third party riska
Chapter IX – offences, penalties and procedures.
Chapter X – miscellaneous
Principles of traffic engineering and transportation planning
1. Traffic engineering
Deals with the planning and geometric design of streets, highways
and abutting lands, and with traffic operation thereon, as their use is related to
the safe, convenient and economic transportation of persons and goods.
2. functions of traffic engineering
a. collection, analysis, and interpretation of data pertaining to
traffic
i. OD survey
ii. Volume counts
iii. Speed, delay and travel time measurements
iv. Accident statistics
v. Parking characteristics
vi. Pedestrian behavior and use of streets
vii. Capacity studies
viii. Economic loss caused by inferior traffic facilities
b. Traffic and transportation planning
i. To ensure a safe, orderly and fully integrated transport
system.
ii. Related to land use
iii. Selection and implementation of alternative solutions
c. Traffic design
i. Geometric design of high ways and streets
ii. Intersection design
iii. Schemes for grade separated interchanges
iv. Design of off street and on street parking
v. Design of terminals
d. Measures for operation of traffic
i. Legislation and enforcement measures – drivers , road users
ii. Management measures – one way streets, turnings at
junctions, tidal flow,
iii. Measures for parking
iv. Traffic control devices
e. Administration
i. Programs intended to safe and efficient traffic
ii. Education, legislation and enforcement measures
3. transportation planning
To under stand the nature of the problems of traffic and formulate
proposals for the safe and efficient movement of goods and people from one
place to another.
4. stages of transport planning
a. survey and analysis of existing conditions
b. forecast, analysis of future conditions and plan synthesis
c. evaluation
d. program adaptation and implementation
e. continuing study
Journey speed is known as over all travel speed including all delays incurred en-
route.
Journey speed = distance
Total journey time (including delays)
Survey methods
a) Home interview survey
i. Full interview technique
ii. Home questionnaire technique
b) Road side interview survey
c) Post card questionnaire survey
d) Registration number plate survey
e) Tags on vehicles.
Parking surveys
Parking is one of the serious problems that confront the urban planner and
the traffic engineer. Before any measure for the betterment of the conditions can
be formulated, basic data pertaining to the availability of parking space, extent of
its usage and parking demand are essential.
Parking accumulation: the total number of vehicles parked in an area at specified
moment.
Parking volume: the number of vehicles parked in a particular area over a given
period of time.
Parking load: the area under the parking accumulation curve during a specified
period.
Parking duration: the length of time spent in a parking space.
Parking index: percentage of the theoretically available number of parking bays
actually occupied by parked vehicles.
Parking index = no of bays occupied x 100
Theoretical number of bays available
1. transport modes
a. railways
surface
underground
elevated
b. road transport
c. air transport
d. water transport
coastal shipping
international shipping
inland water transport
e. pipe lines
f. rope ways
2. speed
3. safety
4. Adequacy
4. Color theory –
Primary hues - RED, YELLOW, BLUE
Complementary colors: Red and Green
Harmonizing colors – hues adjacent on the color wheel.
Hue – (first dimension), by definition it is pure color, containing no white,
black or grey.
Value – (2” dimension), it is the degree of colors luminosity
Yellow - the lightest color of spectrum wheel- higher value
Violet – the lowest value.
Intensity – (3” dimension), give some measure of quality of relative
colorfulness or grey ness. Also known as chroma, purity or saturation. As
spectral hues become greyer they are called as tones. Red is the most
advancing color.
5. VIBGYOR
cold
6. Effects of hue
Effect hue contrast
Exciting bright, red, orange high
Stimulating red, orange moderate
Cheering light orange yellow, light grey moderate
Neutralizing grey, white/off white low
Retraining cool grey, light green, light blue low
Relaxing blue, green
low
Subduing purple moderate
Depressing black low
7. color time size weight volume
Warm overestimated things seem heavier decreases
Cool under estimated things seem lighter increases
8. Use cool colors shorter & for areas where smaller routine or monotonous
tasks are performed.
9. Natural color system – Edward Herings theory
10. Sven Hassel prepared a color atlas.
11. We can’t see an object if beyond a distance of 3500times its size.
12. range of conventional distance – 30’
13. to make out facial expressions – 40’
14. to make recognize a face – 80’
15. Max. Distance for discovering action – 450’ for seeing people – 4000.
16. 450° (1:1) full enclosure
17. 300° (1:2) threshold of enclosure
18. 180° (1:3) minimum enclosure
19. 140° (1:4) loss of enclosure
20. shape is 2-dimensional
21. form is 3-D
22. color – hue or chroma
23. intensity – graying effect
24. value – tint (adding white) (high key)
25. shading (adding black) (low key)
26. tone – range of tints and shades
https://www.facebook.com/Architecture-GATE-Solution-818266061628451/?ref=hl ar. Deepak singh
IIT Roorkee
5
Architecture GATE Solution GATE 2016
4. principles of design
unity – repetition of identical elements
Head of well proportioned human figure = 1/7 oxf total body height.
Proportion – golden mean is a ratio 1:1.618 standard.
Certain proportions are more pleasing than others.
Subliminal effect.