Week 5 7 Planning and Scheduling
Week 5 7 Planning and Scheduling
SCHEDULING
(TIME MANAGEMENT)
• The schedule derives the earliest and the latest times for
their start and finish.
• Resource estimates
• Excavation
• 1
•
• 3
• Fabrication of Forms Pouring Footing Slab
•
• Pouring of
• conc. for WF
A
1 2
• C 4
1
b d f
• 3 5 6 end
• Illustration 2
• A
• C
• B
• Illustration 3
•
• B
• A
• C
•
A C
• B D
B C
• When two activities have the same start and ending nodes,
a dummy node and activity is used to preserve the different
identity of each activity. Activity A and activity B must be
completed first before activity C begins.
•
B D
2 C 4
A
E
1 dummy
B D
• 3 5 end
aeg
• a
• e
• g
•
•
•
Determine also the Critical Path and the expected duration of the
project.
Determine also the Critical Path and the expected duration of the
project.
c e 8
d end 5
e end 3
•
•
•
Engr. Nelia V. Aman, Ed.D.
•
• Latest Finish of an activity cannot be later than the latest
event time of its j-node. All activities with the same J-
node have the same late finish which is the same as the
latest event time at their common node.
•
• Latest Finish equals Latest Start plus Duration
•
• LF = LS + D or LS = LF – D
•
•
•
Engr. Nelia V. Aman, Ed.D.
• Activity Total Float or Activity Total Slack is the span of
time an activity can be delayed after its earliest time
without delaying the project completion.
• It is equal to the total time for the activity minus the activity
duration.
•
• TF = LF – EF or TF = LS + D – (ES +D) or
• TF = LS – ES
•
• 10 8
• 1 2 4
• 6 13 4
• 12 2
• 3 5 6 end
• 8 7 11 I
• B 3 5
• F
• 2-4-6
• 2-3-4 a b c 1-3-4
• d e f
• 3-4-5 3-5-7 5-7-9
• 2-4-5 g h i 3-4-6
• 4-5-6
a-b-c a 2 3 4 3 =3+4+2.83
9.83
b 2 4 6 4
c 1 3 4 2.83
d-e-f d 3 4 5 4 =4+5+7
16
e 3 5 7 5
f 5 7 9 7
i 3 4 6 4.17
b 2 4 6 16/36
c 1 3 4 9/36
e 3 5 7 16/36
f 5 7 9 16/36
h 4 5 6 4/36
i 3 4 6 9/36
• Additional personnel
• Have more efficient equipment
• Relaxing of some work specifications
•
• Note: Those activities on the critical path are
potential activities for crashing.
F-4
1 5 6
C-7 3 4
D-6 E-9
A 3 P8,000
B 3 first week 3,000
2nd week 4,000
C 2 5,000
D 1 1,000
E 3 5,000
F 1 2,000
C-11 D-6
1 3 5
E-14 F-7
4
Path N =0 1 2 3
A-B 22 21 20 19
C-D 17 17 17 17
E-F 21 21 20 19
Activity crashe17d B B,F B,E
Crashing costs 3,000 6,000 9,000
The activities and other conditions for a certain project are as follows:
Activity Normal Normal Accelerated Accelerated
Duration Cost Duration Cost
A (0-1) 5 days P1,000 3 days P1,600
B (0-2) 5 days P3,000 3 days P4,000
C(1-2) 7 days P3,000 5 days P3,500
D(0-3) 3 days P12,000 2days P12,000
E (2-3) 4 days P1,000 3 days P1,500
F (3-4) 5 days P1,000 3 days P1,800
D-3
D-3
•
Engr. Nelia V. Aman, Ed.D.
THANK YOU