Invitation of Comments Solar Park Transformer-1
Invitation of Comments Solar Park Transformer-1
Invitation of Comments Solar Park Transformer-1
1.3 The design and workmanship shall be in accordance with the best
engineering practices to ensure satisfactory performance throughout
the service life.
1.4 Any material and equipment not specifically stated in this specification
but which are necessary for satisfactory operation of the equipment
shall be deemed to be included unless specifically excluded and shall
be supplied without any extra cost.
5.0 PERFORMANCE
5.6 The hotspot temperature in any location of the tank shall not
exceed 110 degree Celsius at rated MVA. This shall be measured
during temperature rise test at manufacturer’s works.
5.7 The maximum flux density in any part of the core and yoke at the
rated MVA, voltage and frequency shall be 1.7 T and under 10 %
continuous over-voltage condition it shall be 1.9 Tesla at all tap
positions.
5.8 The current density in any of the windings shall not exceed 3.5
A/sq.mm at all tap positions.
5.9 The transformer and all its accessories including bushing/built in CTs
etc. shall be designed to withstand the thermal and mechanical effects
of any external short circuit to earth and of short circuits at the
terminals of any winding without damage. The transformer shall be
designed to withstand the thermal stress due to short circuit for a
duration of 2 seconds and the same shall be verified during design
review.
5.10 The following short circuit level shall be considered for the HV & IV
System to which the transformers will be connected:
110 % continuously
125 % for 1 minute
140 % for 5 seconds
Withstand time for 150% & 170% over fluxing condition shall be
indicated. Over fluxing characteristics up to 170 % shall be
submitted.
The maximum permissible losses (No load loss, auxiliary loss and
load loss) at rated voltage/current (at 75 deg C) have been specified
in Annexure-A for various ratings of transformers covered under
this specification. Following penalties shall be levied on the
Chapter-1:Technical Specification for Power Transformers for Solar parks Page 5
manufacturer/contractor (as the case may be) if losses measured
during routine test are found to be within +2% tolerance of the losses
specified in Annexure–A, beyond which the transformer/ shall be
liable for rejection. No benefit shall be given for supply of transformer,
with losses (measured during routine tests) less than the losses
specified in Annexure –A.
Note: For a fraction of a kW, the penalty shall be applied on pro rata
basis.
11.1.1 The tank shall be of proven design of either Bell type with bolted/
welded joint or conventional (preferable) with bolted/welded top
cover. Bell type tank, if provided, shall have joint as close as
possible to the bottom of the tank.
11.1.2 The tank shall be designed in such a way that the transformer can
be rested on concrete plinth foundation directly or on roller
assembly.
11.1.3 Tank shall be fabricated from tested quality low carbon steel of
adequate thickness. Unless otherwise approved, metal plate, bar and
sections for fabrication shall comply with IS 2062.
11.1.4 The base of each tank shall be so designed that it shall be possible to
move the complete transformer unit by skidding in any direction
without damage when using plates or rails and the base plate shall
have following minimum thickness.
11.1.6 All seams and joints which are not required to be opened at site, shall
be factory welded, and shall be double welded [i.e. with a continuous
cord on both sides of the plate (inside and outside of the tank), bottom
& cover of the tank, turrets, flanges, etc.] to ensure adequate strength.
11.1.7 The welded joint shall be provided with flanges suitable for repeated
welding. The joint shall be provided with a suitable gasket to prevent
weld splatter inside the tank. Proper tank shielding shall be done to
prevent excessive temperature rise at the joint.
11.1.8 Tank stiffeners shall be provided for general rigidity and welded to the
tank continuously along its ends and sides (Intermittent welds will not
be accepted). These shall be designed to prevent retention of water.
Sharp edges on stiffeners should be avoided for better paint adhesion.
11.1.11 Suitable guides shall be provided for positioning the various parts
during assembly or dismantling. Adequate space shall be provided
between the covers & windings and the bottom of the tank for collection
of any sediment.
11.1.12 Tank should be provided with adequately sized inspection covers, either
in circular shape or in rectangular shape, preferably at diagonally
opposite sides of the tank to access the active part and one at each
end of the tank cover for easy access of the lower end of the
bushings, earthing connections and tap changers etc. for inspection.
Inspection covers shall be bolted type and shall not weigh more than
25 kgs. Handles shall be provided on the inspection cover to facilitate
its lifting.
11.1.13 The tank cover shall be provided with pockets for oil and winding
temperature indicators. The location of pockets (for OTI, WTI & RTDs
including two spare pockets) shall be in the position where oil reaches
maximum temperature. Further, it shall be possible to remove
bulbs/probes of OTI/WTI/RTD without lowering the oil in the tank. The
thermometer shall be fitted with a captive screw to prevent the ingress
of water.
11.1.15 The tank cover shall be designed to prevent retention of rain water
Bushing turrets, covers of inspection openings, thermometer pockets
etc. shall be designed to prevent ingress of water into or leakage of oil
from the tank.
11.1.16 Minimum four symmetrically placed lifting lugs of adequate size shall
be provided so that it will be possible to lift the complete transformer
when filled with oil & without structural damage to any part of the
transformer. The factor of safety at any lug shall not be less than 2.
Suitable haulage holes shall also be provided.
11.1.17 A minimum of four jacking pads (not fouling with rail, rollers or
other accessories) shall be provided in accessible position to enable
the transformer complete with oil to be raised or lowered using
hydraulic jacks. The location shall be such that it should not interfere
with loading & unloading from trailer.
11.1.19 The tank shall be provided with suitable valves as specified in Clause
18: Valves and Clause 26: “Fittings and accessories” of this chapter.
Location of valves shall be finalized during design review.
11.1.20 The tank cover and bushing turret shall be fixed to the transformer
using copper links in such a way that good electrical contact is
maintained around the perimeter of the tank and turrets.
11.1.21 The transformer shall be provided with a suitable diameter pipe flange,
butterfly valve, bolted blanking plate and gasket at the highest point of
the transformer for maintaining vacuum in the tank.
11.1.22 Gas venting : The transformer cover and generally the internal spaces
of the transformer and all pipe connections shall be designed so as to
provide efficient venting of any gas in any part of the transformer to the
Buchholz relay. The space created under inspection/manhole covers
shall be filled with suitable material to avoid inadvertent gas pockets.
The Covers shall be vented at least at both longitudinal ends. The
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
11
design for gas venting shall take into accounts the slopes of the plinth
(if any) on which the transformer is being mounted.
11.3.6 For support of cooler pipes, Buchholz pipe (if required) and fire-fighting
pipe pylon supports, Pre-fabricated metallic support from pit shall be
provided which shall be further encased with concrete to prevent
rusting.
11.3.7 All control cubicles shall be mounted at least one meter above Finished
Ground Level (FGL) to take care of water logging during flooding.
Suitable arrangement (ladder and platform) shall be provided for safe
access to control cubicles.
11.4 Conservator
11.4.1 The conservator of main tank shall have air cell type constant oil
pressure system to prevent oxidation and contamination of oil due to
contact with moisture. Conservator shall be fitted with magnetic oil
level gauge with potential free high and low oil level alarm contacts
and prismatic oil level gauge.
11.4.2 The conservator shall preferably be on the left side of the tank
while viewing from HV side.
11.4.3 Conservator tank shall have adequate capacity with highest and lowest
visible-levels to meet the requirements of expansion of total cold oil
volume in the transformer and cooling equipment from minimum
ambient temperature to top oil temperature of 100 deg C. The capacity
of the conservator tank shall be such that the transformer shall be able
to carry the specified overload without overflowing of oil.
11.4.4 The conservator shall be fitted with lifting lugs in such a position so
that it can be removed for cleaning purposes. Suitable provision shall
be kept to replace air cell and cleaning of the conservator as applicable.
11.4.6 Contact of the oil with atmosphere is prohibited by using a flexible air
cell of nitrile rubber reinforced with nylon cloth. The temperature
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
13
of oil in the conservator is likely to raise up to 100 Deg C during
operation. As such air cell used shall be suitable for operating
continuously at this temperature.
11.4.7 The connection of air cell to the top of the conservator is by air proof
seal preventing entrance of air into the conservator. The main
conservator tank shall be stencilled on its underside with the words
“Caution: Air cell fitted”. Lettering of at least 150 mm size shall be
used in such a way to ensure clear legibility from ground level when the
transformer is fully installed. To prevent oil filling into the air cell, the
oil filling aperture shall be clearly marked. The transformer rating and
diagram plate shall bear a warning statement that the “Main
conservator is fitted with an air cell”.
11.4.8 The transformer manual shall give clear instructions on the operation,
maintenance, testing and replacement of the air cell. It shall also
indicate shelf life, life expectancy in operation, and the recommended
replacement intervals.
11.4.9 The conservator tank and piping shall be designed for complete
vacuum/ filling of the main tank and conservator tank. Provision
must be made for equalising the pressure in the conservator tank and
the air cell during vacuum/ filling operations to prevent rupturing of
the air cell.
11.4.10 The contractor shall furnish the leakage rates of the rubber bag/ air
cell for oxygen and moisture. It is preferred that the leakage rate for
oxygen from the air cell into the oil will be low enough so that the oil
will not generally become saturated with oxygen. Air cells with well
proven long life characteristics shall be preferred.
11.5.1 Pipe work connections shall be of adequate size preferably short and
direct. Only radiused elbows shall be used.
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
14
11.5.2 The feed pipe to the transformer tank shall enter the cover plate at its
highest point and shall be straight for a distance not less than five times
its internal diameter on the transformer side of the Buchholz relay, and
straight for not less than three times that diameter on the conservator
side of the relay. This pipe shall rise towards the oil conservator,
through the Buchholz relay, at an angle of not less than 3 degrees.
The feed pipe diameter for the main conservator shall be not less than
80mm. The Gas-venting pipes shall be connected to the final rising pipe
between the transformer and Buchholz relay as near as possible in an
axial direction and preferably not less than five times pipe diameters
from the Buchholz relay.
11.5.5 Pipe work shall neither obstruct the removal of tap changers for
maintenance or the opening of inspection or manhole covers.
PRD shall be provided with special shroud to direct the hot oil in
case of fault condition. It shall be provided with an outlet pipe which
shall be taken right up to the soak pit of the transformer. The size
(Diameter) of shroud shall be such that it should not restrict rapid
release of any pressure that may be generated in the tank, which may
result in damage to equipment. Oil shroud should be kept away from
control cubicle and clear of any operating position to avoid injury to
personnel in the event of PRD operation.
The device shall maintain its oil tightness under static oil pressure
equal to the static operating head of oil plus 20 kPa.
Double float, reed type Buchholz relay complying with IS:3637 shall
be connected through pipe between the oil conservator and the
transformer tank with minimum distance of five times pipe diameters
between them. Any gas evolved in the transformer shall be collected in
this relay. The relay shall be provided with a test cock suitable for a
flexible pipe connection for checking its operation and taking gas
sample. A copper tube shall be connected from the gas collector to a
valve located about 1200 mm above ground level to facilitate sampling
while the transformer in service. Suitable canopy shall be provided to
prevent ingress of rain water. It shall be provided with two potential
free contacts (Plug & socket type arrangement), one for alarm/trip
on gas accumulation and the other for tripping on sudden rise of
pressure.
The thermometer shall have adjustable, potential free alarm and trip
contacts besides that required for control of cooling equipment (if any),
maximum reading pointer and resetting device, switch testing knob &
anti-vibration mounting grommets (for projection mounting). Type of
switch (NO/NC) shall be heavy duty micro switch of 5A at 240V AC/DC.
Adjustable range shall be 20-90% of full scale range. The instruments
case should be weather proof with epoxy coating at all sides.
Instruments should meet degree of protection of IP55 as per IS/IEC-
60529. A temperature sensing bulb located in a thermometer pocket
on tank cover should be provided to sense top oil. This shall be
connected to the OTI instrument by means of flexible stainless steel
armour to protect capillary tubing. Temperature indicator dials shall
have linear gradations to clearly read at least every 2 deg C. The setting
of alarm and tripping contacts shall be adjustable at site.
The OTI shall be so mounted that the dials are about 1200 mm from
ground level. Glazed door of suitable size shall be provided for
convenience of reading.
In addition to the above, the following accessories shall be provided for
remote indication of oil temperature:
The transformer shall be provided with a dial type hot spot indicator of
about 150mm diameter for measuring the hot spot temperature of
each winding [HV, LV or LV1/LV2, Tertiary (if applicable)]. It shall have
angular sweep of 270o. Range of temperature should be 0-150°C
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
18
with accuracy of ±1.5% (or better) of full scale deflection. The
instruments should be capable of withstanding high voltage of 2.5kV
AC rms, 50Hz for 1 minute. The terminal provided for auxiliary wiring
should be Press-fit type.
The WTI shall be so mounted that the dials are about 1200 mm from
ground level. Glazed door of suitable size shall be provided for
convenience of reading.
11.12.1 Two (2) earthing pads (each complete with two (2) nos. holes, M16
bolts, plain and spring washers) suitable for connection to 75 x 12
mm galvanised steel grounding flat shall be provided each at
position close to earth of the two (2) diagonally opposite bottom
corners of the tank.
11.12.4 Each transformer unit should have provision for earthing and
connection to grounding mat when not in service.
11.13 Core
11.13.1 The core shall be constructed from non-ageing, cold rolled high
permeability grade or better grain oriented silicon steel
laminations. Indian transformer manufacturers shall use core
material as per above specification with BIS certification.
11.13.2 The design of the magnetic circuit shall be such as to avoid static
discharges, development of short circuit paths within itself or to the
earthed clamping structure and production of flux component at right
angles to the plane of laminations which may cause local heating. The
step-lap construction arrangement is preferred for better performance
in respect of noise, no-load current and no-load loss.
11.13.4 Core and winding shall be capable of withstanding the shock during
transport, installation and service. Adequate provision shall be made
to prevent movement of core and winding relative to tank during these
conditions.
11.13.5 All steel sections used for supporting the core shall be thoroughly
sand/ shot blasted after cutting, drilling and welding.
11.13.6 Each core lamination shall be insulated with a material that will not
deteriorate due to pressure and hot oil.
11.13.7 The supporting frame work of the core shall be so designed as to avoid
presence of pockets which would prevent complete emptying of tank
through drain valve or cause trapping of air during oil filling.
11.13.8 Adequate lifting lugs shall be provided to enable lifting of active part
(core & winding).
11.13.11 In case core laminations are divided into sections by insulating barriers
or cooling ducts parallel to the plane of the lamination, tinned copper
bridging strips shall be inserted to maintain electrical continuity
between sections.
11.14 Windings
11.14.1 The manufacturer shall ensure that windings of all transformers are
made in clean, dust proof (Cleanroom class ISO 9 or better as per ISO
14644-1), humidity controlled environment with positive
atmospheric pressure.
11.14.2 The conductors shall be of electrolytic grade copper free from scales
and burrs. Oxygen content shall be as per IS 12444.
11.14.4 The conductor insulation shall be made from high-density (at least
0.75 gm/cc) paper having high mechanical strength. The
characteristics for the paper will be reviewed at the time of design
review.
11.14.7 The coils would be made up, shaped and braced to provide for
expansion and contraction due to temperature changes.
11.14.10 Wherever required, electrostatic shield, made from material that will
withstand the mechanical forces, will be used to shield the high voltage
windings from the magnetic circuit.
11.14.12 All winding insulation shall be processed to ensure that there will be
no detrimental shrinkage after assembly. All windings shall be pre-
sized before being clamped.
11.16.2 The winding end termination, insulation system and transport fixings
shall be so designed that the integrity of the insulation system generally
remains intact during repeated work in this area.
11.16.5 Suitable inspection and access facilities into the tank in the bushing
oil-end area shall be provided to minimize the possibility of creating
faults during the installation of bushings.
Oil used for first filling, testing and impregnation of active parts at
manufacturer's works shall be of same type of oil which shall be
supplied at site and shall meet parameters as per specification.
13.1 Particles in the oil (For 400 kV transformer)
The particle analysis shall be carried out in an oil sample taken before
carrying out FAT at manufacturer’s works and after completion of
the oil filtration at site. The procedure and interpretation shall be in
accordance with the recommendation of CIGRE report WG-12.17-
“Effect of particles on transformer dielectric strength”. Particle limit as
shown below shall be ensured by manufacturer, implying low
contamination, as per CIGRE Brochure 157, Table 8. After filtration the
oil is to be flushed and particle count to be measured.
Limiting value for the particle count are 1000 particle/100 ml with
size ≥ 5 μm; 130 particle/100 ml with size ≥ 15 μm.
14.0 BUSHINGS
14.3 Oil filled condenser type bushing shall be provided with at least
following fittings:
14.5 Bushing shall be provided with tap for capacitance and tan delta
test. Test taps relying on pressure contacts against the outer earth
layer of the bushing is not acceptable.
14.9 End fittings shall be free from cracks, seams, shrinks, air holes and
rough edges. End fittings should be effectively, sealed to prevent
moisture ingress, effectiveness of sealing system must be supported by
test documents. All surfaces of the metal parts shall be perfectly
smooth with the projecting points or irregularities which may cause
corona. All load bearing surfaces shall be smooth and uniform so as to
distribute the loading stresses uniformly.
14.10 The hollow silicone composite insulators shall comply with the
requirements of IEC-61462 and the relevant parts of IEC-62217. The
design of the composite insulators shall be tested and verified according
to IEC-61462 (Type & Routine test).
14.12 Bushing turrets shall be provided with vent pipes, to route any gas
collection through the Buchholz relay.
14.15 Bushing shall be specially packed to avoid any damage during transit
and suitable for long storage, with non-returnable packing wooden
boxes with hinged type cover. Without any gap between wooden planks.
Packing Box opening cover with nails/screws type packing
arrangement shall not be acceptable. Manufacturer shall submit
drawing/ documents of packing for approval during detail engineering.
Detail method for storage of bushing including accessories shall be
brought out in the instruction manual.
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
27
14.16 Oil end portion of RIP/RIS type bushings shall be fitted with metal
housing with positive dry air pressure or oil filled metal housing and a
suitable pressure monitoring device shall be fitted on the metal housing
during storage to avoid direct contact with moisture with epoxy. The
pressure of dry air need to be maintained in case of leakage.
14.17 The terminal marking and their physical position shall be as per IS
2026.
15.0 Air insulated dry Cable Box for 33 kV XLPE cable (if applicable):
15.1 Cable boxes shall be of phase segregated air insulated type & shall be
of sufficient size to accommodate Purchaser’s cable & termination.
Phase segregation shall be achieved by insulating barriers.
15.2 Cable boxes shall have bus bars / terminal connectors of adequate size
& bolt holes to receive cable lugs.
15.3 Cable boxes shall be designed to accommodate all the cable joint
fittings or sealing ends required by the manufacturers of the cables,
including stress/cones or other approved means for grading the voltage
stress on the terminal insulation of cables operating at voltages of 33
kV between phases.
15.4 The cable boxes shall be fitted with suitable non-ferrous wiping glands
with combined armour and earthing clamps. The ends of all wiping
glands shall be tinned before dispatch to site. Wiping glands for single
core cables shall be insulated from the box. Wiping glands insulation
shall be capable of withstanding a dry high voltage test of 2 kV AC for
one minute. Sufficient wiping glands shall be provided for the
termination of required number of cables.
15.7 The support from base for the cable box shall be of galvanized iron.
15.8 The contractor shall provide earthing terminals on the cable box, to suit
Purchaser’s GI flat.
Creepage
over Creepage
Highest Clearance Clearance
porcelain over
System Insulating between to earth
to cable
Voltage medium phases direct
similar surface
kV (mm) (mm)
material (mm)
(mm)
36 Air 351 222 576 576
15.11 Cable boxes shall have removable top cover & ample clearance shall be
provided to enable either transformer or each cable to be subjected
separately to high voltage test.
15.12 The minimum length provided for terminating 33kV cable shall be 1000
mm (from cable gland plate to the cable lug) for the cable boxes. The
final cable size, number & length of terminating XLPE cable shall be
furnished during detailed engineering.
15.13 Cable boxes shall be designed such that it shall be possible to move
away the transformer without disturbing the cable terminations,
leaving the cable box on external supports. Cable box shall have IP-55
protection as per IS:13974.
15.14 Unless otherwise specified main cabling jointing and filling of cable
boxes will be carried out by the purchaser or his Contractor as the case
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
29
may be.
17.1.3 The radiator shall be of sheet steel complying with IS 513 and
minimum thickness 1.2 mm. Each radiator bank shall be provided
with the following accessories:
(a) Cooling Fans, Oil Pumps, Oil Flow Indicator (as applicable)
(b) Top and bottom shut off valve of at least 80mm size
(c) Drain Valve and sampling valve
(d) Top and bottom oil filling valves
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
30
(e) Air release plug at top
(f) Two grounding terminals suitable for termination of two (2) Nos.
75x12 mm galvanised steel flats.
(g) Thermometer pockets fitted with captive screw caps at cooler inlet
and outlet.
(h) Lifting lugs
17.1.4 Each radiator bank shall be detachable and shall be provided with
flanged inlet and outlet branches. Expansion joint (for separately/
ground mounted cooler banks) shall be provided on top and bottom
cooler pipe connection.
17.1.5 One number standby fan shall be provided with each radiator bank.
17.1.7 Two (2) nos., 100% centrifugal or axial in line oil pumps, if
applicable, (out of which one pump shall be standby) shall be provided
with each radiator bank. Measures shall be taken to prevent mal-
operation of Buchholz relay when all oil pumps are simultaneously
put into service. The pump shall be so designed that upon failure of
power supply to the pump motor, the pump impeller will not limit the
natural circulation of oil.
17.1.8 The changeover to standby oil pump in case of failure of service oil
pump shall be automatic.
17.1.9 An oil flow indicator shall be provided for the confirmation of the oil
flow direction. An indication in the flow indicator and potential free
contacts for remote alarm shall be provided.
17.1.10 Valves shall be provided across the pump and oil flow indicator to avoid
oil drain and long outage during maintenance / replacement of pump
and oil flow indicator.
17.1.11 Cooling fans and oil pump motors shall be suitable for operation from
415 volts, three phase 50 Hz power supply and shall be of premium
efficiency class IE3 conforming to IS: 12615. Each cooling fan and oil
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
31
pump motors shall be provided with starter, thermal overload and short
circuit protection. The motor winding insulation shall be conventional
class 'B' type. Motors shall have hose proof enclosure equivalent to IP:
55 as per IS/IEC 60034-5.
17.1.12 The cooler pipes, support structure including radiators and its
accessories shall be hot dip galvanised or corrosion resistant paint
should be applied to external surface of it.
17.1.13 Air release device and oil plug shall be provided on oil pipe connections.
Drain valves shall be provided in order that each section of pipe work
can be drained independently.
17.1.15 Suitable manual control facility for cooler fans and oil pumps shall be
provided. Selector switches and push buttons shall also be provided in
the cooler control cabinet to disconnect the automatic control and
start/stop the fans and pump manually.
17.1.16 Following lamp indications shall be provided in cooler control cabinet:
One potential free initiating contact for all the above conditions shall
be wired independently to the terminal blocks of cooler control cabinet
and for single phase unit connection shall be extended further to
Common Marshalling Box.
17.1.17 The Cooler Control Cabinet/ Individual Marshalling Box shall have all
necessary devices meant for cooler control and local temperature
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
32
indicators. All the contacts of various protective devices mounted on
the transformer and all the secondary terminals of the bushing CTs
shall also be wired up to the terminal board in the Cooler Control
Cabinet/Individual Marshalling Box. All the CT secondary terminals in
the Cooler Control Cabinet shall have provision for shorting to avoid CT
open circuit while it is not in use.
17.1.19 AC power for Cooler Control Circuitry shall be derived from the AC
feeder. In case auxiliary power supply requirement for Cooler Control
Mechanism is different than station auxiliary AC supply, then all
necessary converters shall be provided.
18.0 VALVES
18.1 Type of valves shall be used for transformer as per following table. The
location and size of valves for other application shall be finalised during
design review. Utility may specify any other valve required for some
other applications.
18.3 Suitable means shall be provided for locking the valves in the open and
close positions. Provision is not required for locking individual radiator
valves.
18.4 Each valve shall be provided with the indicator to show clearly the
position (open/close) of the valve.
18.6 Drain valves/plugs shall be provided in order that each section of pipe
work can be drained independently.
18.7 All valves in oil line shall be suitable for continuous operation with
transformer oil at 115 deg C.
18.8 After testing, inside surface of all cast iron valves coming in contact
with oil shall be applied with one coat of oil resisting paint/varnish with
two coats of red oxide zinc chromate primer followed by two coats of
fully glossy finishing paint conforming to IS: 2932 and of a shade
(Preferably red or yellow) distinct and different from that of main tank
surface. Outside surface except gasket setting surface of butterfly
valves shall be painted with two coats of red oxide zinc chromate
18.9 The oil sampling point for main tank shall have two identical valves
put in series. Oil sampling valve shall have provision to fix rubber hose
of 10 mm size to facilitate oil sampling.
18.10 Valves or other suitable means shall be provided to fix various on line
condition monitoring systems, if specified, to facilitate continuous
monitoring. The location & size of the same shall be finalised during
detail design review.
b) When the flow from conservator to main tank is more than the
normal operating conditions, the valve shall shut off by itself
and will have to be reset manually. It shall be provided with valve
open/close position indicator along with alarm contact
indication in control room during closing operation of valve. This
valve shall be provided with locking arrangement for normal position
and oil filling / filtration position. A suitable platform or ladder (if
required) shall be provided to approach the valve for manual reset.
19.0 CABLING
19.1 All interconnecting control and power cables emanating from various
parts of transformer like turret CT, MBs, Fans, pumps, Buchholz, PRD
etc. shall be routed through covered cable tray or GI conduit and shall
be properly dressed. All cables shall be armoured type. Un-armoured
cables (if provided) in any circuitry, shall be through GI conduit and no
part shall be exposed. Cable terminations shall be through stud type
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
35
TB and ring type lugs. Type tested cables from approved sources shall
be provided. Both ends of all the wires (control & power) shall be
provided with proper ferrule numbers for tracing and maintenance.
Further, any special cables (if required) shall also be considered
included in the scope. All cable accessories such as glands, lugs, cable
tags/ numbers etc. as required shall be considered included in the
scope of supply. Typical technical specification for cables is
attached at Annexure-O. The cross section of “control cable” shall be
1.5 sq.mm (minimum) except for CT circuits which should be 2.5
sq.mm (minimum).
20.2.1.2 The OLTC shall be of high speed transition resistor type. OLTC shall
be motor operated suitable for local as well as remote operation. The
diverter switch or arcing switch s
20.2.1.4 The voltage class, maximum tapping current, step voltage of OLTC shall
have adequate design margin for safe & reliable service life of both
OLTC and transformer. OLTC shall have long contact life, quick & easy
to disassemble diverter switch inserts, simple to adjust & control and
easy to replace diverter’s contacts etc.
20.2.1.6 The OLTC oil chamber shall have oil filling and drain valve, oil sampling
valve, relief vent and level glass. Oil sampling valve, accessible from
ground, shall be provided to take sample of oil from the OLTC chamber.
It shall also be fitted with an oil surge relay which shall be connected
between OLTC oil chamber and OLTC conservator tank. Provision
of a suitable device like tie-in-resistor has to be made, wherever
required, to limit the recovery voltage to a safe value. The use of
tie-in-resistor (if used) shall be clearly marked in rating and diagram
plate of the transformer. The whole of the driving mechanism shall be
of robust design and capable of giving satisfactory service without
undue maintenance.
20.2.1.7 Tap changer shall be so mounted that bell cover of transformer can be
lifted without removing connections between windings and tap changer.
20.2.2.1 OLTC shall be suitable for manual (handle operated) and electrical
(motor operated) operation. For local manual operation from Local
OLTC Control cabinet (Drive Mechanism Box), an external handle shall
be provided.
20.2.2.3 For electrical operation from local as well as remote, motor operated
mechanism shall be provided. It shall not be possible to operate the
electric drive when the manual operating gear is in use. It shall not be
possible for any two controls to be in operation at the same time.
Transfer of source in the event of failure of operating AC supply shall
not affect the tap changer. Thermal device or other means shall be
provided to protect the motor and control circuit.
20.2.2.4 The Local OLTC Drive Mechanism Box shall house all necessary devices
meant for OLTC control and indication. It shall be complete with the
following:
20.2.2.5 In case auxiliary power supply requirement for OLTC Drive Mechanism
(DM) Box is different than station auxiliary AC supply, then all
necessary converters shall be provided.
20.2.2.8 OLTC local control cabinet shall be provided with tap position
indication for the transformer. Drive Mechanism shall be equipped with
a fixed resistor network capable of providing discrete voltage steps or
provide 4-20mA transducer outputs for tap position indication in
Common Marshalling Box (CMB) (for single phase unit) and input to
digital RTCC/relevant BCU (as applicable)/SCADA system. The tap
position indicator shall also be provided in control room.
(a) INCOMPLETE STEP which shall not operate for momentary loss
of auxiliary power.
(b) OLTC motor overload protection
(c) Supply to DM Motor fail
(d) OLTC IN PROGRESS
(e) Local/Remote Selector switch position
(f) OLTC upper/lower limits reached
20.2.2.12 All relays, switches, fuses etc. shall be mounted in the OLTC local
control cabinet and shall be clearly marked/ labelled for the purpose of
identification. Both ends of all the wires (control & power) connected to
Drive Mechanism Box must be provided with proper ferrule nos. for
tracing and maintenance.
20.2.3.1 The digital RTCC relay shall have Automatic Tap Changer control and
monitoring relay with Automatic Voltage Regulating features to
remotely control and monitor OLTC.
20.2.3.2 Each digital RTCC relay shall be used to control one unit of
transformer. No. of relays including spare relay, if any, shall be
specified by the utility as per requirement.
20.2.3.4 Digital RTCC relay shall be microprocessor based adopting the latest
state of the art design & technology with in-built large LCD (or better)
display for ease of programming and viewing. The unit supplied shall
be field programmable so that in the event of change in transformer
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
41
location, it could be customized to suit site conditions without sending
back to works. The programming shall be menu driven and easily
configurable. If it is designed with draw out type modules, it should
take care of shorting all CT inputs automatically while drawing out. The
CT/VT ratio shall be field programmable and Relay shall display the
actual HV Voltage and current considering suitable multiplying factors.
The system shall be self-sufficient and shall not require any additional
devices like parallel balancing module etc.
20.2.3.6 The digital RTCC relay shall have Raise/Lower push buttons, Manual/
Automatic mode selection feature, Local/Remote selection feature,
Master / Follower/ Independent/ Off mode selection feature for control
of OLTC. Touch screen option in the relay (instead of electrical push
button/switch) is also acceptable.
20.2.3.7 The digital RTCC Relay shall have multiple selectable set point voltages
and it shall be possible to select these set points from SCADA/ SAS,
with a facility to have the possibility of additional set points command
from SCADA/ SAS.
20.2.3.8 In Manual Mode: In this mode, power system voltage based automatic
control from digital RTCC relay shall be blocked and commands shall
be executed manually by raise/lower push buttons.
20.2.3.9 In Auto Mode: In Auto mode, digital RTCC relay shall automatically
control OLTC taps based on power system voltage and voltage set
points. An interlock shall be provided to cut off electrical control
automatically upon recourse being taken to the manual control in
emergency.
20.2.3.12 Digital RTCC relays shall communicate with SCADA using IS/IEC
61850 through fibre optic port to monitor, parameterise and control the
OLTC. Any software required for this purpose shall be supplied. The
supplied software shall not have restriction in loading on multiple
computers for downloading and analyzing the data. Software shall
indicate the current overview of all measured parameters of the
connected transformer in real time.
20.2.3.14 The Digital RTCC relay shall have additional programmable Binary
Inputs (minimum 7 Nos.) and Binary outputs (minimum 7 Nos.) for
future use. It shall be possible to have additional module for Binary
Input / output as well as Analogue input module depending upon
requirement.
20.2.3.15 The relays shall ensure completion of lowering/raising of the OLTC tap,
once the command is issued from the relay. "Step-by-Step" operation
shall be ensured so that only one tap change from each tap changing
20.2.3.16 The relay shall incorporate an under voltage / over voltage blocking
facility which shall make the control inoperative if voltage falls/ rises
by percentage value of set point value with automatic restoration of
control when nominal voltage rises / falls to value.
20.2.3.17 The relay shall have facility to monitor operating hours of tap changer
and register the tap changer statistics. In the statistics mode, the relay
shall display the no. of tap changing operations occurred on each tap.
20.2.3.18 The relay shall have self-check of power on and shall continually
monitor all functions and the validity of all input values to make sure
the control system is in a healthy condition. Any monitoring system
problem shall initiate the alarm.
20.2.3.20 In case of parallel operation, OLTC out of step alarm shall be generated
in the digital RTCC relay for discrepancy in the tap positions.
22.1 Each transformer unit shall be provided with local OCTC/OLTC Drive
Mechanism Box (DMB), Cooler Control Cabinet/Individual Marshalling
Box, and Digital RTCC panel (as applicable).
22.2 Individual Marshalling Box (IMB) and Cooler Control Box shall be
tank mounted or ground mounted. All cabinets except CMB & Digital
RTCC panel shall be tank mounted. All separately mounted cabinets
and panels shall be free standing floor mounted type and have domed
or sloping roof for outdoor application. The gland plate shall be at least
450 mm above ground level.
22.4 The degree of protection shall be IP: 55 for outdoor and IP: 43 for
indoor in accordance with IS/IEC: 60947.
22.5 All doors, removable covers and plates shall be gasketed all around with
suitably profiled. All gasketed surfaces shall be smooth straight and
reinforced if necessary to minimize distortion to make a tight seal. For
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
45
Control cubicle/Marshalling Boxes etc. which are outdoor type, all the
sealing gaskets shall be of EPDM rubber or any other (approved)
material of better quality, whereas for all indoor control
cabinets/Digital RTCC panel, the sealing gaskets shall be of
neoprene rubber or any other (approved) material of better quality.
The gaskets shall be tested in accordance with approved quality plan
and IS: 3400.
22.7 Ventilating Louvers, if provided, shall have screen and filters. The
screen shall be fine wire mesh of brass. All the control cabinets shall
be provided with suitable lifting arrangement. Thermostat controlled
space heater and cubicle lighting with ON-OFF switch shall be provided
in each panel.
23.1 Two auxiliary power supplies of 415 volt, three phase four (4) wire
shall be provided by the Purchaser at Cooler Control Cabinet /
Marshalling Box. All loads shall be fed by one of the two sources
through an electrically interlocked automatic transfer scheme housed
in the Cooler Control Cabinet/Marshalling Box.
23.5 Design features of the transfer scheme shall include the following:
a) Provision for the selection of one of the feeder as normal source and
other as standby.
b) Upon failure of the normal source, the loads shall be automatically
transferred after an adjustable time delay to standby sources.
c) Indication to be provided at cooler control cabinet/Individual
Marshalling Box for failure of normal source and for transfer to
standby source and also for failure to transfer.
d) Automatic re-transfer to normal source without any intentional
time delay following re-energization of the normal source.
e) Both the transfer and the re-transfers shall be dead transfers and
AC feeders shall not be paralleled at any time.
24.1 Current transformers shall comply with IS 16227 (Part 1 & 2)/IEC 61869 (part
1 & 2).
24.4 Technical Parameters of Bushing CTs and Neutral CTs are provided at
Annexure–B. The CTs used for REF protection must have the identical
parameters in order to limit the circulating current under normal
condition for stability of protection. Bushing Current Transformer
parameters indicated in this specification are tentative and liable
to change within reasonable limits. Purchaser's approval shall be
obtained before proceeding with the design of bushing current
transformers.
Each transformer shall be supplied with a full kit of tools & spanners
of required sizes; bushing handling & lifting tools with nylon rope/belt,
with a rack for holding them; required numbers of hydraulic jacks for
lifting the transformers, and for changing the plane of rotation of
wheels. All spanners shall be single ended and case hardened. Tirfors
with wire rope and slings with grippers etc. for hauling the transformer
to the plinth are to be supplied along with each transformer. Utility may
add/remove tools as per their requirement.
For Transformer:
(a) Conservator for main tank with aircell, oil filling hole and cap,
isolating valves, drain valve, magnetic oil level gauge, prismatic oil
level gauge and dehydrating silica gel filter breather with flexible
connection pipes to be used during replacement of any silica gel
breather.
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
48
(b) Conservator for OLTC (for transformer) with drain valve, oil surge
relay, filling hole with cap, magnetic oil level gauge, prismatic oil
level gauge and dehydrating breather (for transformer only) with
flexible connection pipes to be used during replacement of any
silica gel breather.
(c) Pressure relief devices with special shroud to direct the hot oil
(d) Sudden pressure relief relay (for 220 kV and above Transformer)
(e) Buchholz relay (double float, reed type) with isolating valves on
both sides, bleeding pipe with pet cock at the end to collect gases
and alarm/trip contacts.
(i) Bushing of each type with metal parts and gaskets to suit the
termination arrangement
(k) Cover lifting eyes, transformer lifting lugs, jacking pads, towing
holes and core and winding lifting lugs
(m) Rating and diagram plates (in English & Hindi or as specified by
the utility) on transformers and auxiliary apparatus
(o) One complete set of all metal blanking plates & covers
(p) On load tap changing gear, OLTC/Off Circuit Tap Changer (OCTC)
DM Box, individual marshalling box, Cooler control cabinet, and
Digital RTCC Panel as applicable
(v) Bottom oil sampling valve, Drain valves (provided to drain each
section of pipe work independently), Filter valves at top and
bottom with threaded male adaptors, Shut off valves on the pipe
connection between radiator bank & the main tank, Shut off
valves on both sides of Buchholz relay, Sampling gas collectors for
Buchholz relay at accessible height, Valves for Radiators, Valve
for vacuum application, Valves for cable box (if applicable), Valve
for on line DGA (if applicable), valves for Drying out system (if
applicable), Flow sensitive Conservator Isolation Valve (if
applicable), Gate Valve (4 Nos. of min. 50 NB) for UHF sensors for
PD Measurements (applicable for 400kV voltage class
Transformer only), valves for firefighting system (as applicable)
and other valves as specified in the specification.
(x) Suitable platform for safe access of flow sensitive non-return valve
and buchholz relay shall be provided, in case these are not
accessible from transformer top.
28.0 DRAWINGS/DOCUMENTS/CALCULATIONS
30.3 As can be seen from the Bath Tub curve, the “Infant mortality” failures,
which are caused due to manufacturing related defects/issues that
occur in the first few years of service (say 1 or 2 years). But continued
successful operation of transformer primarily depends on operating
conditions and O&M practices being followed by utilities. Improper
maintenance or negligence on the part of user e.g. non-replenishment
of saturated silica gel, non-release of air trapped after air-cell
commissioning, oil seepages, lack of routine maintenance, failure to
check tan-delta & capacitance of winding and bushing, absence of
thermal scanning of terminal interfaces, lack of DGA monitoring etc.,
can also lead to serious consequences. It can therefore be said that the
responsibility of manufacturer and maintenance & monitoring
obligations of the end user are equally important for a long and trouble
free service life of transformer. Moreover, any abnormality observed
during operation needs to be addressed immediately. The transparency
in sharing of information, mutual co-operation and discussion on
30.4 The utilities should create their maintenance plans so that they adhere
to the recommended O&M procedures of the OEMs.
The transformer with DGA Status-3 does not necessarily give any
conclusive information regarding health of transformer or indicate
that transformer is faulty. It can only be concluded that its
behaviour is somewhat unusual and warrants additional
investigation and/or precautions. The transformer should be placed
under increased surveillance. Other diagnostic tests should also be
conducted to supplement the DGA for taking further course of action
in consultation with manufacturer.
Chapter-1:Technical Specification for Power Transformers for Solar parks Page
56
c) In case, the winding tan delta goes beyond 0.005 or increases more
than 0.001 per annum w.r.t. pre-commissioning values, the utility
is to inform manufacturer for advice and for further course of action.
h) The utility shall carryout all diagnostic tests just before completion
of warranty period to ensure the healthiness of transformer and any
abnormality in test results shall be informed to the manufacturer
for immediate action and advice.
DESIGN REVIEW
1.0 Introduction
The design review shall be carried out for the offered design of
transformer under the scope and Manufacturer shall submit all design
documents and drawings required for the purpose.
For the benefit of the utility the formula for calculation of No-Load loss
and Load loss, weight of core and current density of winding conductor
has been provided below. In addition, a typical example of calculation of
flux density, core quantity/ weight, no-load loss and weight of copper
has been provided in Annexure-F.
Flux density (T) = rated voltage (v) x104/ (4.44 x no. of turns x net
core area (cm2) x frequency (Hz))
Load loss at principal tap = I2R loss + Winding Eddy loss + Structural
stray losses
RW = W x D x π / (k x S)
RL = L / (k x S)
Where,
W= Number of turns
D= mean winding diameter
S= cross section area of all parallel conductor
K= Electrical conductivity of conductor/leads for reference
temperature of 75°C.
L= Length of lead
5.0 References:
(a) CIGRE Technical Brochure No. 529 -2013 Guide lines for
conducting design reviews for Power Transformers
(b) CIGRE Technical Brochure No. 673-2016 Guide on Transformer
Transportation
(c) IEEE Standard C57.156-2016 Guide for tank rupture mitigation
of oil immersed transformers
(d) CIGRE Technical Brochure No. 530-2013 Guide for conducting
factory capability assessment for Power Transformers
(e) IEEE Standard C57.150-2012 Guide for Transformer
Transportation
(f) IS 2026 Power Transformers-Part 5 Ability to withstand short
circuit
1.0 INTRODUCTION
2.9 Purchaser reserves the right to carry out quality audit and quality
surveillance of the systems and procedures of the manufacturer’s
or their sub-supplier’s quality management and control activities.
The manufacturer shall provide all necessary assistance to enable
the Purchaser carry out such audit and surveillance.
2.16 All welding and brazing shall be carried out as per procedure
drawn and qualified in accordance with requirements of ASME
Section IX/BS-4870 or other International equivalent standard
acceptable to the Purchaser. All welding / brazing procedures
adopted/used at shop, will be made available to purchaser during
audit / inspection. Procedures to be adopted at site will be
submitted to purchaser for approval.
4.2 The Inspector shall have access at all reasonable times to inspect
and examine the materials and workmanship of the works during
its manufacture or erection and if part of the works is being
manufactured or assembled on other premises or works, the
Manufacturer shall obtain for the Inspector permission to inspect
as if the works were manufactured or assembled on the
Manufacturer’s own premises or works.
4.3 The Manufacturer shall give the Inspector ten (10) days written
notice of any material being ready for testing. Such tests shall be
to the Manufacturer’s account. The Inspector, unless the
witnessing of the tests is virtually waived and confirmed in writing,
(h) Different sections like Core - coil assembly area, winding area,
tank inspection area etc. shall be provided with adequate no.
of cameras or portable cameras can be used for clear and
proper visualisation of the test object.
(c) The Date and time and arrangement for online stage
inspection/FAT shall be finalised in consultation with the
utility/purchaser.
(h) The Test circuits and Test procedure shall be shared with
utility’s/purchaser’s inspector for clarity & better
understanding.
(j) While conducting remote FAT, due care must be taken to keep
the data safe while transmitting from factory to utility’s/
purchaser’s inspector through a web-based application. There
are various Cybersecurity requirements and InfoSec protocols,
which should be adhered to for safety like Database Security,
Strong Password Policy, Access Control, Restricted Access via
2-Factor Authentication for utility/purchaser, Single Session
or Timed Sessions, Resetting Passwords, Password Expiry
Policy, Validations for 3rd Party participants, Authentication
for users/test engineers etc.
(n) The image quality shall be good enough for assessment of the
condition of the transformer which may affect the quality &
performance of transformer. The factors affecting image
quality include:
Poor image resolution.
Image out of focus.
Inadequate lighting /Glare from strong light
source/shadows
Frequent loss of connectivity between the Inspection team
and the onsite Video monitors.
4.5 The Inspector shall within ten (10) days from the date of inspection
as defined herein give notice in writing to the Manufacturer, or any
objection to any drawings and all or any equipment and
workmanship which is in his opinion not in accordance with the
contract. The manufacturer shall give due consideration to such
objections and shall either make modifications that may be
necessary to meet the said objections or shall inform in writing to
the Inspector giving reasons therein, that no modifications are
necessary to comply with the contract.
4.6 When the factory tests have been completed successfully at the
manufacturer’s or sub-supplier’s works, the Inspector shall issue
a certificate to this effect within ten (10) days after completion of
tests but if the tests are not witnessed by the Inspector, the
certificate shall be issued within ten (10) days of the receipt of the
Manufacturer’s test certificate by the Inspector.
4.7 In all cases where the contract provides for tests whether at the
premises or works of the Manufacturer or any sub-suppliers, the
Manufacturer, except where otherwise specified shall provide free
of charge such items as labour, material, electricity, fuel, water,
stores, apparatus and instruments as may be reasonably
demanded by the Inspector to carry out effectively such tests on
the equipment in accordance with the Manufacturer and shall give
facilities to the Inspector to accomplish testing.
5.1.1 The manufacturer shall carry out all type & routine tests specified
in “Annexure-D and Annexure-E”. All tests shall be done in line
with latest IS: 2026/IEC 60076 or as per procedure specified in
5.1.3 The manufacturer shall bear all additional costs related to tests
which are not possible to carry out at his own works.
All tanks and oil filled compartments shall be completely filled with
air or oil of a viscosity not greater than that of insulating oil
conforming to IEC 60296 at the ambient temperature and
subjected to a pressure equal to normal head of oil plus 35
kN/sq.m (5 psi) measured at the base of the tank. This pressure
shall be maintained for a period of not less than 12 hours for oil
and 1 hour for air during which no leakage shall occur.
5.2.3 The manufacturer will offer the core for stage inspection and get
approval from purchaser during manufacturing stage. The BIS
certified prime core materials are only to be used. The
manufacturer has to produce following documents at the time of
stage inspection for confirmation of use of prime core materials.
a) Invoice of supplier
b) Mills’ approved test certificates
c) Packing list
d) Bill of lading
e) Bill of entry certificate by custom.
f) Description of material, electrical analysis, physical inspection,
certificate for surface defects, chemical composition certificate,
thickness and width of the materials
g) Place of cutting of core materials
5.2.4 Typical example for calculation of flux density, core quantity, no-
load loss and weight of copper during stage inspection is given in
the Annexure-F.
Following fittings shall conform to type tests and the type test
reports shall be furnished along with drawing of the
equipment/fittings.
6.4 Check for proper provision for bracing to arrest the movement of
core and winding assembly inside the tank.
6.5 Gas tightness test to confirm tightness and record of dew point of
dry air inside the tank. Derivation of leakage rate and ensure the
adequate reserve dry air capacity.
TRANSFORMERS
1.0 250 MVA & 315 MVA, 400/33 kV 3-Phase Power Transformer
2. Rated Capacity
HV MVA 250 315
LV1 MVA 125 157.5
LV2 MVA 125 157.5
Tertiary MVA Tertiary winding may be
provided if transformer is of 5
limbs construction.
3. No of phases 3-phase
4. No of Secondary windings Two windings
5. Vector Group YNynyn0
6. Type of transformer Power transformer
7. Applicable Standard IEC 60076/ IS 2026
8. Cooling type ONAN / ONAF / ODAF (or
OFAF)
9. Rating at different cooling % 60 / 80 / 100
10. Cooler Bank Arrangement 2 X 50%
11. Frequency Hz 50
12. Tap Changer (OLTC) / OCTC -5% to +5% in steps of 1.25%
for HV variation
13. Location of tap changer On HV neutral end
Principal tap % 28
S.
Description Unit Technical Parameters
No.
1. Voltage ratio (Line-to-Line) kV 400/33
2. Rated Capacity (HV & LV) MVA 125 160
3. No of phases 3-phase
4. No of secondary windings One winding
5. Vector Group YNyn0
6. Type of Transformer Power Transformer
7. Applicable Standard IEC 60076 / IS 2026
8. Cooling ONAN / ONAF
9. Rating at different cooling % 70 / 100
10. Cooler Bank Arrangement 2 X 50%
11. Frequency Hz 50
-5% to +5% in steps of 1.25%
12. Tap Changer (OLTC)/OCTC
for HV variation
13. Location of tap change On HV neutral end
Impedance at 75°C at highest MVA
14.
base
Max. Voltage tap % 16.2
Principal tap % 15
Min. Voltage tap % 14
As per IEC, unless specified
15. Tolerance on Impedance %
otherwise
16. Service Outdoor
17. Duty Cyclic
18. Overload Capacity IEC-60076-7
Temperature rise over 50°C
19.
ambient temp
i) Top oil measured by thermometer O C 45
Average winding measured by
ii) O C 50
resistance method
Winding hot spot rise over yearly
20. O C 61
weighted temperature of 32°C
21. Tank Hotspot Temperature O C 110
Maximum design ambient
22. O C 50
temperature
23. Windings
Lightning Impulse withstand
i)
Voltage
HV kVp 1300
LV kVp 250
HV Neutral kVp 95
S.
Description Unit TECHNICAL PARAMETERS
No.
3. No of phases 3 (Three)
S.
Description Unit TECHNICAL PARAMETERS
No.
3. No of phases 3 (Three)
Application
CORE 1 Restricted Earth REF REF REF
Fault (REF)
CORE 2 Metering - - -
Maximum magnetization current (at knee point voltage)
CORE 1 60 mA 60 mA 30 mA 30 mA
-
CORE 2 - - -
Notes:
1. Parameters of WTI CT for each winding shall be provided by the
manufacturer / contractor.
2. The CTs used for REF protection must have the identical parameters in
order to limit the circulating current under normal condition for stability
of protection.
Application
CORE 1 Restricted Earth REF REF REF
Fault (REF)
CORE 2 Metering - - -
Maximum magnetization current (at knee point voltage)
CORE 1 60 mA 60 mA 30 mA 30 mA
-
CORE 2 - - -
Notes:
1. Parameters of WTI CT for each winding shall be provided by the
manufacturer / contractor.
2. The CTs used for REF protection must have the identical parameters in
order to limit the circulating current under normal condition for stability
of protection.
Application
CORE 1 Restricted Earth REF REF REF
Fault (REF)
CORE 2 Metering - - -
Maximum magnetization current (at knee point voltage)
Notes:
1. Parameters of WTI CT for each winding shall be provided by the
manufacturer / contractor.
2. The CTs used for REF protection must have the identical
parameters in order to limit the circulating current under normal
condition for stability of protection.
Application
CORE 1 Restricted REF REF REF
Earth Fault
(REF)
CORE 2 Metering - - -
Maximum magnetization current (at knee point voltage)
Notes:
1. Parameters of WTI CT for each winding shall be provided by the
manufacturer / contractor.
2. The CTs used for REF protection must have the identical parameters in
order to limit the circulating current under normal condition for stability
of protection.
Application
CORE 1 Restricted REF REF REF
Earth Fault
(REF)
CORE 2 Metering - - -
Maximum magnetization current (at knee point voltage)
Notes:
1. Parameters of WTI CT for each winding shall be provided by the
manufacturer / contractor.
2. The CTs used for REF protection must have the identical parameters in
order to limit the circulating current under normal condition for stability
of protection.
Application
CORE 1 Restricted REF REF REF
Earth Fault
(REF)
CORE 2 Metering - - -
Maximum magnetization current (at knee point voltage)
Notes:
1. Parameters of WTI CT for each winding shall be provided by the
manufacturer / contractor.
2. The CTs used for REF protection must have the identical parameters in
order to limit the circulating current under normal condition for
stability of protection.
A. GENERAL
i) Supplier
ii) Name of Manufacturer
iii) Place of Manufacture (Country & City)
iv) Type of transformer (Core/Shell)
2. Applications
i) Indoor/Outdoor
ii) 2wdg/3wdg
iii)
3. Corrosion Level at Site
7. Applicable Standards
i) IEC: 60076
ii) IS : 2026
iii) Any other, please specify
8. Rated Capcity / Full load rating (HV/LV (or MVA
LV1/LV2)
9. 3-Phase
10. Rated No Load Voltages (HV/LV (or LV1/LV2)/ kV
Tertiary
11. Currents at normal tap (HV/LV(or LV1/LV2)/ Amp
tertiary
12. Rated Frequency Hz
13. Connections and phase displacement symbols
(Vector Group)
14. Weight Schedules (Minimum with no negative
110%
125%
Annexure-C: Guaranteed & Other Technical Particulars Page 3 of 13
140%
150%
170%
29. Free space required above the tank top for removal
of core
30. Maximum Partial discharge level at 1.58 Ur/√3 pC
B. MAGNETIC SYSTEM
Sl. Description Unit Specif Offered
No. ied by by
Buyer manufa-
cturer
1. Core Type:
i) 3 Phase 3 Limb (3 wound limbs)
ii) 3 Phase 5 Limb (3 wound limbs)
iii)
3. CRGO :
i) Make & Country of Origin
ii) Thickness, mm
iii) Max. Specific loss at 1.7 T, 50Hz, in Watts/kg
iv) Grade of core as per BIS
v) Insulation between core lamination
vi) BIS certified (Yes/No)
4. Minimum Gross & Net Area of: cm2
i) Core
ii) Limb
iii) Yoke
iv) Unwound limb
(May be verified during manufacturing stage – at
the discretion of buyer)
5. Stacking Factor %
6. Voltage per turn V
7. Apparent Core Density for Weight Calculation
8. Minimum Net Weight of Silicon Steel Lamination kg
CRGO (may be verified during manufacturing stage
by calculation)
9. Maximum Flux density at 90%, 100% and 110% T
voltage and frequency (may be verified during
manufacturing stage by calculation)
10. W/kg at working flux density
11. Building Factor Considered
C. CONDUCTING SYSTEM
Sl. Description Unit Offered
No. by manufacturer
HV IV LV Reg
ulat
ing
1. Type of Winding
Helical/Disc/Layer/inter wound
2. Type of Conductor
PICC/CTC/CTCE/CTCEN/BPICC
i) HV
ii) Tertiary
iii)LV (or LV1/LV2)
6. Bare Weight of copper without paper Kg
insulation and lead (Minimum)
7. Per Phase Maximum resistance of winding ohm
at rated tap at 75 OC
8. Number of Turns/Phase
9. Insulating material used for HV/IV/LV
winding
Annexure-C: Guaranteed & Other Technical Particulars Page 5 of 13
10. Insulating material used between :
i) HV and IV winding
ii) IV and LV winding
iii) LV winding and core
iv) Regulating winding and adjacent
winding/core
11. Details of special arrangement provided to
improve surge voltage distribution in the
winding
12. Dielectric Shielding used:
i) Interleaved winding
ii) Wound in Shield
iii) Others
13. Magnetic Shielding used:
D. COOLING SYSTEM
Sl. Description Unit Speci Offered
No. fied by
by manufa
Buyer c-turer
1. Type of Cooling
[ ONAN/ONAF (or) ONAN / ONAF / OFAF (or ODAF)]
2. Percentage Rating Corresponding to Cooling Stages
(HV/Tertiary/LV (or LV1/LV2)
3. No. of Cooler banks (2x50% / 1x100% etc.)
4. Temperature gradient between windings and oil
5. Time in minutes for which the transformer can run at min
full load without exceeding maximum permissible
temperature at reference ambient temperature when
supply to fans is cut off
6. Guaranteed Maximum Temperature rise at 1000 mts. 0C
altitude and at actual altitude at site at ambient
temperature at cooling specified at sl. No. 1:
i) Radiator Bank
ii) )
iii) Tank Mounted
iv) Header Mounted
v) Separately Mounted
vi) Degree of Protection of terminal box
8. Cooling Fans:
i) Type
ii) Size
iii) Rating (kW)
iv) Supply voltage
v) Quantity (Running + Standby) per cooler bank
vi) Whether fans are suitable for continuous operation
at 85% of their rated voltage calculated time
constant:
natural cooling
forced air cooling
vii) Degree of Protection of terminal box
9. Oil Pumps:
i) Type
ii) Size
iii) Rating (lpm and kW)
iv) Supply voltage
v) Quantity (Running + Standby) per cooler bank
vi) Efficiency of motor at full load
vii) Temperature rise of motor at full load
viii) BHP of driven equipment
Coolers (Oil to Air):
10.
i) Quantity (Running + Standby)
ii) Type and Rating
11. Coolers (Oil to Water):
E. DIELECTRIC SYSTEM
Sl. Description Unit Offered by
No. manufacturer
1. Geometric Arrangement of winding with
respect to core
e.g: Core-Tertiary-LV-HV-Reg Coarse-Reg Fine
2. Regulating Winding:
i) Body Tap
ii) Separate
3. HV Line Exit point in winding:
i) Top
ii) Center
4. Varistors used across Windings Yes/
If yes, Details No
F. ACCESSORIES
Sl. Description Unit Offered Spe
No. by manufacturer cifie
d by
Buy
er
1. Tap Changers
i) Control
a-Manual b-Automatic
c-Remote d-Local
ii) Voltage Class and Current Rating of Tap
Changers
iii) Make and Model
iv) Make and Type of Automatic Voltage
Main Conservator
OLTC Conservator
vi) Oil Sight Window:
Main Tank
Main Conservator
OLTC Conservator
6. Conservator:
i) Total volume
ii) Volume between highest and lowest
visible oil levels
7. Conservator Bag (air cell)
i) Material of air cell
ii) Continuous temperature withstand
capacity of air cell
8. Air cell rupture relay provided Yes
/ No
Annexure-C: Guaranteed & Other Technical Particulars Page 10 of 13
9. Pressure Relief Device:
i) Voltage class kV
ii) No. of cores
iii) Ratio
iv) Accuracy class
v) Burden VA
vi) Accuracy limit factor
vii) Maximum resistance of secondary winding Ω
viii) Knee point voltage V
ix) Current rating of secondaries A
16. Neutral CTs:
i) Voltage class kV
ii) No. of cores
iii) Ratio
iv) Accuracy class
v) Burden VA
vi) Accuracy limit factor
vii) Maximum resistance of secondary winding Ω
viii) Knee point voltage V
ix) Current rating of secondaries A
17. Transformer Oil
i) IS 335 / IEC60296 / as per specification
ii) Inhibited/ un-inhibited
iii) Mineral / Natural Ester / Synthetic Ester
iv) Spare oil as percentage of first filling
v) Manufacturer
vi)Quantity of oil (before filling and before
commissioning)
vii)Moisture content (mg/L or ppm)
viii) Tan delta (Dielectric Dissipation Factor) at
90oC
i) Make
ii) type
19. Conductor Insulating Paper
i) Kraft paper
ii) Thermally upgraded Kraft paper
iii) Nomex
20. Provision for fire protection system (as per Y/N
spec), if yes, provide details
21. Insulation of core bolts, washers, end plates
etc.
22. Weights and Dimensions:
i) Weights:
a. Core
b. Windings
c. Tank
d. Fittings
e. Oil
f. Total weights of complete transformers
with oil and fittings
ii) Dimensions;
a. Overall Height above track
b. Overall length
c. Overall breadth
No. Test Um Um
≤ 170kV 170kV
1. Measurement of winding resistance at all taps Routine Routine
2. Measurement of voltage ratio at all taps Routine Routine
3. Check of phase displacement and vector group Routine Routine
4. Measurement of no-load loss and current Routine Routine
measurement at 90%, 100% & 110% of rated voltage
and rated frequency
5. Magnetic balance test (for three phase Transformer Routine Routine
only) and measurement of magnetizing current
6. Short Circuit Impedance and load loss measurement Routine Routine
at principal tap and extreme taps
7. Measurement of insulation resistance & Polarization Routine Routine
Index
8. Measurement of insulation power factor and Routine Routine
capacitance between winding to earth and between
windings
9. Measurement of insulation power factor and Routine Routine
capacitance of bushings
10. Full wave lightning impulse test for the line terminals Type -
(LI) (for Um<=
72.5kV)
Routine
(for
72.5kV<
Um≤170
kV)
11. Chopped wave lightning impulse test for the line Type Routine
terminals (LIC)
12. Lightning impulse test for the neutral terminals (LIN) Type Type
*The requirements of the IVW test can be incorporated in the IVPD test so that
only one test is required.
General
After assembly each core shall be tested for 1 minute at 2000 Volts between
all yoke clamps, side plates and structural steel work (core to frame, frame to
tank & core to tank).
The insulation of core to tank, core to yoke clamp (frame) and yoke clamp
(frame) to tank shall be able to withstand a voltage of 2 kV (DC) for 1 minute.
Insulation resistance shall be minimum 1 GΩ for all cases mentioned above.
After the transformer has been under liquid without excitation for at least 3
h, the average liquid temperature shall be determined and the temperature of
the winding shall be deemed to be the same as the average liquid temperature.
The average liquid temperature is taken as the mean of the top and bottom
liquid temperatures. Measurement of all the windings including compensating
(in case terminal is available at outside) at normal and extreme taps.
The short-circuit impedance and load loss for a pair of windings shall be
measured at rated current & frequency with voltage applied to the terminals
of one winding, with the terminals of the other winding short-circuited, and
with possible other windings open circuited. The difference in temperature
between the top and bottom liquid shall not exceed 5 K. To obtain this result
5. Short term heat run test (Not Applicable for unit on which temperature
rise test is performed)
In addition to the type test for temperature rise conducted on one unit, each
cooling combination shall routinely be subjected to a short term heat run test
to confirm the performance of the cooling system and the absence of
manufacturing defect such as major oil flow leaks that may bypass the
windings or core.
For ODAF or OFAF cooling, the short term heat run test shall be done with
the minimum number of pumps for full load operation in order to shorten the
temperature build up. Each short term heat run test is nevertheless expected
to take about 3 hours.
This test is applicable for the Transformer without Pump also (ONAN or ONAF
rating). For such type of transformer test may be carried out with the following
sequence:
The temperature rise test shall be conducted at a tap for the worst
combination of loading (3-Winding Loss) for the Top oil of the transformer.
The Contractor before carrying out such test shall submit detailed calculations
showing losses on various taps and for the three types of ratings of the
transformer and shall recommend the combination that results in highest
temperature rise for the test.
The Temperature rise type test results shall serve as a “finger print” for the
units to be tested only with short term heat run test.
Oil sample shall be drawn before and after heat run test and shall be tested
for dissolved gas analysis. Oil sampling to be done 2 hours prior to
commencement of temperature rise test. Keep the pumps running for 2 hours
before and after the heat run test. Take oil samples during this period. For
ONAN/ONAF cooled transformers, sample shall not be taken earlier than 2
hours after shut down. The acceptance norms with reference to various gas
generation rates shall be as per IEC 61181.
This test shall be generally carried out in accordance with IEC 60076-2
For each cooling combination with cooler bank, tests shall be done on
the maximum current tap for a minimum of 12 hours for ONAN/ONAF
and 24 hours for ODAF or OFAF with saturated temperature for at least
4 hours while the appropriate power and current for core and load losses
are supplied.
The total testing time, including ONAN heating up period, steady period
and winding resistance measurements is expected to be about 48 hours.
iii. General:
time
Voltage between phases
Current in each phase and total power
Power in each phase and total power
Ambient temperature
Top oil temperature
Cooler inlet and outlet oil temperatures
Hot spot temperatures (make use of probes) (if applicable)
Colour photographs of the four sides and top of the transformer together
with the corresponding series of thermal images (colour) during starting
of the test then after every four hours till the temperature stabilised and
finally during temperature stabilised for each rating
(ONAN/ONAF/ODAF (or OFAF); ONAN/ONAF).
Record the ‘cold’ resistance of each winding and the simultaneous top
oil and ambient air temperatures, together with the time required for
the effect to disappear.
Record the thermal time constant of the winding.
Log the half-hourly readings of the quantities as for the top oil
temperature rise test.
Provide a table of readings, after shut-down of power, giving the
following information;
7. Dielectric Tests
Following Test shall be performed in the sequence given below as per IEC
60076-3:2013 clause 7.2.3 shall be followed:
Following tests shall be carried out with applying 20% to 80% of rated
Impulse & Switching impulse (upto 60% for IV, Sr. No. 7 & 8 of below table)
voltage. Finally, measured value shall be extrapolated for 100% rated
voltage.
Table for Transfer surge (Impulse) at Max, Nor. and Min. Voltage Tap
Acceptance criteria
Transfer surge at Tertiary should not exceed 250kVp at any conditions for
400kV Voltage class Transformer. For other transformer it shall be below
the impulse level of LV winding.
9. Chopped wave & full wave lightning impulse test for the line terminals
(LIC & LI) and Switching impulse test
Losses of each fan and pumps including spare shall be measured at rated
voltage and frequency. Fans and Pumps shall be mounted with cooler bank
as per approved drawing during measurement. Serial No, Applied voltage,
measured current, frequency and make shall be furnished in the test report.
The test shall be carried out as per IEC 60076-5. Dynamic short circuit
test shall be carried out in HV-LV combination at nominal & extreme tap
positions. For LV winding, dynamic short circuit shall be carried out on
HV. Type tests shall be carried out before short circuit test. Following shall
also be conducted before and after Short Circuit test:
********************************************************
1. Winding Conductor (PICC)/ (a) Visual & Dimensional check of Conductor: One IS 1897 Bare conductor: P V W/V
(CTC)/ Lead wires Thickness & width of bare conductor, sample per IS 13730
thickness of paper, surface covering, no. of type per lot As per Width(mm) Tolerance (in ± mm)
conductors, finish of conductor and finish approved Up to 3.15 - 0.03
of PICC/CTC drawing 3.16 to 6.30 - 0.05
6.31 to 12.5 - 0.07
12.51 to 16 - 0.10
> 16 - 0.13
Insulated conductor:
Paper Covering Tolerance (%)
thickness (mm)
0.25 to 0.5 - 10
Over 0.5 to 1.3 - 7.5
Over 1.3 - 5
(c) Insulation test for bunched IS 13730 Maximum Charging current 1A at P V W/V
conductor/between strands of CTC (if 250V AC/ 500V DC for 1 minute.
applicable)
(d) Elongation test for annealed conductors (if IS 7404 Thickness elongation P V -
applicable) IS 13730 (mm) %
Up to 2.5 30 ( min.)
>2.5-5.6 32 (min.)
(e) Proof strength of work hardened conductor IS 7404 As per design requirement P V -
IS 13730
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 1 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
4. (i) CRGO Mother coil / Check following documents Each Lot IS 3024 As per approved design P V V
Laminations (a) Invoice of Supplier (100% of IS 649
(b) Mill’s Test certificate coils) IEC 60404
(c) Packing List ASTM 4343
(d) Bill of Lading
(e) Bill of Entry
(f)manufacturer’s identification
slip/unique numbering of prime
CRGO coil
Check points:
(a) Visual check, check for coil width & 10% of coils Visually defect free, as per design
thickness from nameplate requirement
(b) Cutting Burr One sample Less than 20 micron burr/ As per IS/
per lot mutual agreement while ordering
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 3 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
Test Method
IS 3024/ IS
649
(k) Compliance to Quality Control Order of IS 3024 P V V
DHI
5. Pre-compressed (a) Visual & dimensional check, thickness, One sample IEC 60641-3-1 No surface defects P V V
Press Board/ Laminated width and length of each size
IEC60763-3-1
pre-compressed (b) Apparent Density (g/cm3 ) (thickness) Up to 1.6 mm TK - 1.0-1.2
IEC 60641-2,
pressboard per lot of >1.6-3 mm - 1.1-1.25
pressboar IEC60763-2
>3-3.6 mm - 1.15-1.30
d Methods of Test >6-8 mm - 1.2-1.3
(c) Compressibility in air (C) (in %) Up to 1.6 TK - 10 %
>1.6-3 mm - 7.5 %
>3-3.6 mm - 5%
>6-8 mm - 4%
(d) Reversible part Compressibility in air Up to 1.6 TK - 45 %;
(Crev) (in %) >1.6-3 mm - 50 %
>3-3.6 mm - 50 %;
>6-8 mm - 50 %
(e) Oil Absorption Up to 1.6 mm TK - 11 min
> 1.6-3 mm - 9 min
> 3 - 3.6 mm - 7 min
> 6-8 mm - 7 min
(f) Moisture Content 6% max. / As per relevant std. &
Manufacturer’s std. practice
(g) Shrinkage in air (MD, CD & PD) MD - 0.5 % max, CD- 0.7 % max, Thick
– 5 % max
(h) pH of aqueous extract 6-9 for solid boards
Up to 1.6 - 3 % 4 %
>1.6-3 mm - 3 % 4 %
>3-3.6 mm - 3% 4%
>6-8 mm TK - 3 % 4 %
(n) Tensile strength (MD, CD) As per relevant std./ Manufacturer’s std.
practice
(o) Internal Ply Bond strength (for laminated As per relevant std./ Manufacturer’s std.
pre compressed boards) practice
Dried (tested at 23°C)
Dried (tested at 120°C retention)
Oil impregnated (tested at 23°C)
Aged for 1 week at 120°C in oil
(tested at 23°C retention)
(p) Flexural strength (MD, CD) (for Laminated As per relevant std./ Manufacturer’s std.
pre compressed Boards) (MPa) practice
(q) Contamination Dielectric Liquids (for As per relevant std./ Manufacturer’s std.
laminated pre compressed press boards) practice
Neutralization value (mg KOH/g)
Sludge content (mg/l)
Dissipation factor
6. Perma-wood (a) Visual & dimensional check, thickness, One IS 3513 Shall be free from surface defect P V V
width & length sample of IS 1708
(b) Density each size IS 1736 0.8 to 1.3 gm/cc
(c) Moisture content per lot IS 1998 IS 3513/IS 1708
(d) Oil Absorption at 90 °C IEC 61061 Min 5%
(e) Dielectric Strength at 90 °C Min 60 KV
(f) Tensile strength Approved Min for LD - 700 KV /cm2
(g) Compressive strength test document Min for LD - 1400 KV /cm2
(h) Shear strength age-wise Min for LD - 450 KV /cm2
(i) Thickness Thickness (mm) Tolerance
(±mm)
10 to 25 - 1.2
26 to 50 - 1.4
51 to 150 - 2.0
IEC
8. Polyester Resin (a) Visual Check One sample IS 15208 Free from visual defect P V --
Impregnated Glass Fiber per lot per
Tape size To be used within self-life period not to
(b) Verification of shelf life
be used after expiry of period
13. Marshalling Box/ Cooler (a) Dimensional & Visual check 100% Approved As per approved drawing P P/W W/V
Control Cabinet (workmanship, clearances, ferruling, drawing and
labeling, accessories, earthing terminals, specification
mounting/ lifting details, 20% spare TBs
etc.)
(b)Verification of paint shade, thickness & As per approved drawing
adhesion
(c) All Functional Check at max & min rated As per approved drawing
operating voltage, electrical control
operations, alarms, interlocks and
sequential operations
(d)BOM check for Component type, make & As per approved drawing
rating
(e) DOP check by thin paper insertion As per technical specification
method
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 7 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
(f) Degree of Protection (IP Class) As per type test report / approved
verification drawing
(g) Check for sealing gasket (EPDM rubber Free form defects
for outdoor/ neoprene rubber for indoor)
Routine test
a. HV test at 2kV (for 1 min) for 1 min withstand
auxiliary winding
b. Verification of wiring and its routing Firm and aesthetic
c. IR test at 500 V for 1 min 1 min withstand
14. Remote Tap Changer (a) Dimension & Visual Check 100% Approved As per approved drawing P P/W W/V
Control Panel (if drawing and
applicable) specification 1 min withstand
(b)2kV test for Auxiliary wiring
(c) Paint shade & Thickness As per approved drawing
(d)Wiring routing check Firm and aesthetic
(e) Functional Check As per approved drawing
(f) Verification of BOQ As per approved drawing
15. Air cell (Flexi Air Make, Visual check of surface finish of 100% IS 3400 No surface defects. P W V
Separator) complete air cell & Dimensions As per approved drawing
Routine test
(a) Pressure test at 0.105 Kg /cm2 (10Kpa) No leakage for 24 hours P W V
for 24 hrs
(b) 10 times inflation and deflation test at No deformation P W V
0.105 Kg /cm2
Type tests on basic fabric One Tensile strength & elongation at P W V
i. Oil side coating compound sample per break: ISO 1421
ii. Air side inner/outer coating lot of raw Tear resistance: ISO 4674-1
material
iii. Rubber coating (inner/outer) Coating adhesion: ISO 2411
iv. Coated fabric Gas permeability: ISO 7229
16. Roller Assembly (a) Visual & Dimensions.
One sample IS 5517 Free from surface defect P V --
per lot IS 2004
(b) Mechanical Properties & Chemical One IS 28 For shaft as per MS EN8, BS 970-1
composition of raw material used sample per IS 2026 For roller wheel of cast iron IS 210
for shaft & roller forging melt/heat For roller wheel of Cast steel IS 1030
treatment
batch
17. Oil & Winding Temperature (a) Type & make 100% -- As per approved drawing P P/W V
Indicator (b) Accuracy ± 1.5% of FSD
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 8 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
(c) HV test at 2kV for 1 min between all Withstand for 1 min
terminals & earth
(d) Switch contact operation test Operation within ± 2.5° C of setting
20. Valves (a) Type, make & visual check for material of 100% IS 778 As per approved drawing & no visible P W V
(Gate, Globe & Butterfly) valve body, gate wedge, spindle and gland defect
(b) Dimension check
(c) For Gate & Globe Valve: No leakage
(i) Body test at 1.5 MPa (2 minutes)
(ii) Seat test at 1.0 MPa (2 minutes)
(iii) Seepage test at 2 kg/cm 2 for 12 hrs.
(d) For Butterfly valve:
(i) Pressure test through body and spindle
(i) No leakage at 5 kg/cm2 for 10 minutes
(ii) Pressure test for diaphragm
(iii) Oil seepage test (oil 105± 5 oC, pressure (ii) Max 6 drops/min at 1.5 kg/cm2
of 1.5 kg/cm2 for 24 hrs.) (iii) No leak in body and spindle
Max 6 drops/min through disc
21. Transformer Oil Routine Test 100% IS: 335 As per technical specification P W W
IEC 60296
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 9 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
IS 6855
22. Tank, Tank-cover, Turret, (a) Visual check of welding joints including 100% CBIP Free from defect P W V
Conservator & Accessories earthing connection, matching of tank with One per Manual on
cover& Dimensional check after final design Transformer
welding 2013
(b) Visual Check for a fit up for butt welds on Check for proper welding
tank walls, base & cover
(c) DP test on Butt welds after fit up & load Check for proper welding
bearing welds (lifting logs, bollards, jacking
pads)
(d) Air leakage test on assembled tank with No leakage
turrets & on conservator
(e) Visual check of paint shade, paint film Paint thickness
thickness (inside & outside) & film Outside: 155 micron
adhesion, primer application Inside: 30 micron
No peel-off
Or
As per approved drawing
(f) WPS (Weld procedure specification) Details to be furnished As per
approval Specification/ASME Sec IX
(g) PQR (Process Qualification Record) Details to be furnished As per
Specification/ASME Sec IX
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 10 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 11 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
25. Digital RTCC Relay/ Automatic (a) Check of Binary input and output 100% as per specification/manufacturer’s
Voltage Regulating Relay (AVR) signal along with HMI display standard
(if applicable) nomenclature
(b) Check availability of spare binary
input and output terminal
(c) Check communication interface
(d) Test for complete function include
tap position indication, raise and
lower command execution
26. Cooling Fans & motor (a) Type, Make & visual check 100% IS 2312 As per approved drawing, no visual P W V
damage/ defect
(b) Power consumption, rating test As per approved drawing
(c) HV test (3kV Power frequency Should withstand
withstand test for 1 min)
(d) Insulation resistance value 2 MΩ (minimum) with 500 V DC
megger
27. Nitrile Rubber (a) Visual check 1 sample/ ISO 7619-1 Free from cracks and pin holes P W V
Gasket (b) Dimensions Lot ISO 815
ISO 37 Within tolerance
(c) Shore Hardness ISO 3865 70 ± 5 IRHD
(d) Tensile Strength IS 11149 12.5 N/mm2 min
(e) Compression set test 35% ( max) at 70 ± 1° C
(f) Elongation at break 250% min
(g) Accelerated aging in air (at 100 ± 2° C Change in harness: ±15 IRHD
for 72 hours) Tensile strength change: 20% (max)
Elongation change: max +10%/ -25%
(h) Accelerated aging in oil (at 100 ± 2° C Change in hardness: ±8 IRHD
for 72 hours) Tensile strength change: 35% (max)
Volume change: +20%/ -8%
(i) Time period between manufacturing To be used within self-life period, not
of gasket and its use to be used after expiry period
28. EPDM Gasket for Marshalling (a) Visual Check 1 sample/ IS 11149 Free from cracks & pinholes P W V
Box (b) Dimensional check (Thickness & Lot Within tolerance
Width)
(c) Tensile Strength As per IS 11149
(d) Elongation at break As per IS 11149
(e) Shore Hardness check as per DIN- As per IS 11149
53505
(f) Compression test (in air) as per DIN, As per IS 11149
ISO 815
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 12 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
29. Bushing CT Dimensions (Visual check for ID/OD, 100% IS 16227 As per approved drawing
thickness) IEC 61869-2
Routine test
(a) Verification of terminal marking & As per IS 16227/ IEC 61869-2
polarity
(b) Overvoltage inter-turn test Rated current withstand for 1 min
(c) Determination of error As per IS 16227/ IEC 61869-2
(d) HV Test (Dry power frequency 3 kV AC for 1 min withstand
withstand test on secondary winding)
(e) Accuracy Ratio As per IS 16227/ IEC 61869-2
(f) Secondary winding resistance for As per IS 16227/ IEC 61869-2
PS/PX class
(g) Knee point voltage & excitation
current for PS/PX class
30. Oil circulating pump (a) Visual check 100% IS 9137 no visual damage/ defect P P/W V
(as applicable) (b) No load running test (rpm, input Satisfactory performance & no load
power and current) losses within limit
(c)
(d) HV test (2kV power frequency Should withstand
withstand voltage test for 1 min)
(e) Oil pressure test on pumps at No leakage
5kg/cm2 for 30 min
(f) Locked rotor test Satisfactory operation of protection
31. Oil flow Indicator (a) Type, Make & Visual check 100% -- (a) As per standard document, no visual P P/W V
(as applicable) (b) Dial & Calibration damage/defect
(c) Contact Rating (b) As per standard document
(d) Dielectric Test between terminals (c) As per standard document
and earth (d) Shall withstand 2 kV for 1 min
(e) Leak test at 7 kg/cm2 for 2 min (e) No leak
(f) Alarm & trip operation check
(g) Full flow check
32. Power/Control Cable Review of Supplier’s TC for physical & Random -- As per standard document P P V
electrical tests as per
specification/drawing.
33. Silica Gel Breather (a) Dimension, Type and model check 100% - (a) Within tolerance, Type and model as P W -
(b) Check of healthiness & colour of per drg
Silica gel (b) No visible defect, Gel colour is
(c) Pressure test by blanking oil cup blue/Orange
end (c) No leak at 0.35 kg/cm2
(for 30 Min)
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 13 of 23
Annexure-E
Sr. No. Item/Components List of Tests Sampling Reference/ Acceptable Value Category of Responsibility*
rate Standard Sub- Manufacturer Customer
Vendor
34. Drum for insulating oil (a) Visual check of inside cleanliness 100% IS 1783 –1 As per specifications/ IS 1783-1
and outside coat
(b) Dimensional check (thickness, height
& diameter)
(c) Leakage test on drum
(d) Drop test
(e) Hydraulic test
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 14 of 23
Annexure-E
Sr. No. Item/Process Sampling Reference / Acceptable Value Category of Responsibility*
rate Standard Sub- Vendor Manufacturer Customer
B IN-PROCESS INSPECTION
1. Visual check, check length & slitting One sample IS 3024 Prime CRGO and Free from defect -- P V
dimension of each lot
2. Dimensional check of CRGO As per design Drawings -- P V
3. Check for burr Less than 20 micron -- P V
4. Check for Edge bow As per IS 3024 -- P V
L< 250mm, H<= 2mm
L>= 250 mm, H<= 3mm
II Core Building
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 15 of 23
Annexure-E
Sr. No. Item/Process Sampling Reference / Acceptable Value Category of Responsibility*
rate Standard Sub- Vendor Manufacturer Customer
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 18 of 23
Annexure-E
Sr. No. Item/Process Sampling Reference / Acceptable Value Category of Responsibility*
rate Standard Sub- Vendor Manufacturer Customer
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 19 of 23
Annexure-E
Sr. No. Test Sampling Reference / Acceptable Value Category of Responsibility*
rate Standard Manufacturer Customer
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 21 of 23
Annexure-E
Sr. No. Test Sampling Reference / Acceptable Value Category of Responsibility*
rate Standard Manufacturer Customer
B. Type Tests/Special test One from Lot Specification/ Specification/ IS:2026 / IEC
For Transformers: IS:2026 / IEC 60076/other applicable standard
1. Measurement of transferred surge on 60076/other P W
Tertiary due to HV lightning impulse applicable
2. Measurement of transferred surge on standard P W
Tertiary due to HV switching impulse
3. Full wave lightning impulse test for P W
the line terminals (LI)
(for Um<= 72.5kV)
4. Chopped wave lightning impulse test P W
for the line terminals (LIC) (for
transformer with Um≤170 kV)
5. Lightning impulse test for the neutral
terminals (LIN)
6. Switching impulse test for the line P W
terminal (SI)
(applicable for Um>72.5 kV & ≤170
kV)
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 22 of 23
Annexure-E
Sr. No. Test Sampling Reference / Acceptable Value Category of Responsibility*
rate Standard Manufacturer Customer
TC --- Test Certificate PD- Perpendicular Direction CD- Cross Direction MD- Machine Direction PICC-Paper Insulated Copper Conductor CTC- Continuously Transposed Conductor
* Category of Responsibility: P - Actual Test Performance V - Verify and Accept W - Witness Actual testing, verify and accept
Annexure-E: Manufacturing Quality Plan Page 23 of 23
RAtRating
Annexure–F
Calculation of flux density, core quantity, no-load loss and weight of copper for a
specific transformer has been given below. Similar calculations for any rating of
transformer can be carried out and relevant data may be obtained from the
manufacturer.
Example: 75 MVA, 220/11, YNd11, 3 Phase, Power transformer,
Tap Range: -2.5% to +7.5% , Off-circuit Switch (Linear) connection
D h
L H
Referring to supplier's curves for core losses against working flux density
The value of watts/kg at 1.7 Tesla. = 0.78 approx
No load loss = Core weight x Watts/kg at 1.7 Tesla x Building Factor x 10-3 kW
= 42452.3 x 0.78 x 1.11x 10-3= 36.755 kW
(Where the value of building factor taken is 1.11)
Mean
Periphery Outer Dia (OD) Radial Dia (OD-
(P) =P/3.14 depth (RD) RD)
(mm) (mm) (mm) (mm)
LV Winding 3035 966.1 77.60 888.5
HV Winding 4585 1459.5 169.50 1290.0
Regulating 4585 1459.5 169.50 1290.0
(Tap) Winding
No. of Turns:
LV Winding: 72 HV Winding: 811 Tap Winding : 84
No. of phases = 3
So Total Measured Resistance per Stand of each HV coil (50 disc from HV centre)
= 3.121 + 0.26834
=3.38934 ohm
So Total Measured Resistance per Cable of each HV coil (50 disc from HV centre)
= 3.38934/2 = 1.69467 ohm
Measured Resistance per cable of each Tap coil (2 disc of Tap coil) = 0.067465 ohm
So, Total Measured Resistance per cable of each Tap coil (8 disc of Tap coil)
= 0.067465 x 8/2 =0.26986
LV winding:
Current = 2272.73 A; Conductor area = 656.27x2= 1312.54 mm2
Current density = 2272.73 / 1312.54 = 1.73 A/mm2
1. Insulation storage
2. Core storage
3. Glue stacking area
4. Core cutting line
5. Winding manufacturing bay
6. Core building area
7. Core coil assembly area
8. Testing lab
9. Packing & dispatch area
2.0 In addition to any other drawings which the manufacturer may like
to supply, the following drawings/ calculations/ documents/
catalogues shall be submitted in hard and soft copy:
Same conceptual design, for example dry type, oil-immersed type, core
type with concentric windings, sandwich type, shell type, circular coils,
non-circular coils;
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit
withstand test Page 1 of 27
DATE : Format for determining similar reference Manufacturer NAME
DOC No.: transformer for short Circuit withstand
Page: -- of -- Strength
General Information
Customer and Purchase
Order No.:
Project Name:
Transformer General
Rating Description
315MVA, 400/220/33KV
(MVA, Voltage Ratio,
AUTOTRANSFORMER, 3 phases, --kA
tested short circuit
current):
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 2 of 27
Unit number/ Serial no:
Short circuit test -NA-
KEMA, Netherland
laboratory detail:
Short circuit test report -NA-
reference No. & Date:
Characteristics as per IEC 60076-5 :2006
1 Type of Transformer AUTO transformer Yes/No Reference:
based on operation: 1. *Rating & Diagram plate
2. Approved GTP
e.g. Generator Step up
unit; Distribution;
Interconnecting; Auto;
Station auxiliary etc.
2 Factory of production, Reference:
material used (Material Short circuit test report
of conductor, cellulose
insulating material,
oil, grade of CRGO
material), and as built
Drawing
3 Tested Short Circuit Reference:
Current and duration Short circuit test report along
of Dynamic short with as built drawing
circuit current (250ms
/ 500ms)
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 3 of 27
4 Conceptual design OIL-IMMERSED, CORE TYPE, Yes/No Reference:
CONCENTRIC WINDINGS, CIRCULAR 1. Rating & Diagram plate
e.g. Dry / oil-immersed
COILS 2. Approved GTP
type ; Core type with
concentric windings /
sandwich type, shell
type, Circular coils /
non-circular coils
5 Arrangement and CORE - LV (TER) – REG – IV - HV Yes/No Reference:
geometrical sequence 1. Winding assembly drawing
of main windings in Short circuit test report if
available
e.g.; Core-LV-HV-T
2. *Or Representative Coil
assembly drawing reference
6 Type of conductors for LV Tap IV HV Yes/No Reference:
each winding 1. *Test Certificates submitted
Condu COPP COPPE COPP COPP by the conductor Vendor for
e.g aluminium / ctor ER R ER ER each winding
aluminium alloy,
Type CTC CTC CTC CTC 2. Approved GTP
annealed or work-
hardened Copper; metal Epoxy Yes
foil / wire / flat Yes Yes Yes
coated
conductor /
Continuously Proof
Transposed conductor; stress
Epoxy bonding (Yes/No); N/mm
work hardened Proof (min)
stress (min) N/mm2
7 Type of each windings Wind LV Tap IV HV Yes/No Reference:
ing 1. In case Short ckt. test report
is inclusive of detail on
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 4 of 27
5a e.g. Helical- Type Layer Multi- Disc Dis Winding type
/Layer- / /Disc start c Lead entry detail
Disc- type / Layer 2. Representative Coil assembly
pancake coils drawing reference
Line Top/B Top/Bott Top/Bo Cen
e.g. Line lead Lead ottom om ttom ter
entry (top, entry entr
5b y
bottom ,
Center, Edge )
8 Absorbed power at Sc. Max Min Nor Yes/No Reference:
Short Circuit Tested Voltage Voltage Voltag 1. Short ckt test report
Transfor Tap Tap e Tap inclusive of Routine test
(= Rated Power/per unit
mer Impedance values
short circuit impedance)
Rated 315 315 315
[The ratio shall be
MVA
between 70 % to 130% of
that rating of the Impedan 10.4% 12.5% 15.4%
reference transformer] ce
measure
d after
sc. test
Absorbe
d power 3028.8 2045.4
(MVA) 5 2520.00 5
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 5 of 27
9 Axial force and As per Table given in IS 2026-5/IEC Yes/No Reference:
winding stresses 60076-5.
occurring at short
(A typical example with data of forces
circuit as per IS table 1. As per calculation made /
and stresses has been provided at the
results of the simulation
(Simulated as in Same end of this Annexure-J.)
software used
Declared Program or (Name of software used
same Calculation
:…….)
method used)
[The axial forces and
winding stresses
occurring at SC shall not
exceed 120% of that of
reference transformer]
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 6 of 27
11 Same clamping and General conceptual description to be Yes/No Reference:
winding support provided 1. Clamping arrangement:
arrangement Provide basic details
1. Core clamping drawing with support 2. Winding bottom support
[Core Clamping arrangement and calculation of SC
structure and cleat & lead
principle, winding radial force withstand by clamping
arrangement: Adequacy has
& axial support system, structure. been validated by the
cleats & lead support 2. Winding drawing with axial and
simulation software…..
arrangement] radial support details, lead exit
details
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 7 of 27
Representative Coil assembly reference Winding Arrangement
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 8 of 27
The detail comparison of technical parameters of typical offered & reference short circuit tested
transformer is given below. The data is for reference and guidance purpose only.
2.00 Rating
2.01 HV / LV 315 MVA 500 MVA
2.02 TV 105 MVA 167 MVA
2.03 Cooling ONAN/ONAF/ODAF ONAN/ONAF/ODAF
2.04 Rating at Different cooling 189/252/315MVA (60%/80%/100%) 300/400/500MVA (60%/80%/100%)
2.05 Voltage ratio 400/220/33 kV 400/220/33 kV
2.06 Voltage / Turn 200 280
2.07 Frequency 50 Hz 50 Hz
2.08 Phases 3 3
Max. Partial discharge at 1.58
2.09 <100 pC <100 pC
Um/3
2.10 Design of Power Frequency Level 570 kVrms 570 kVrms
2.11 Noise Level 80 dB 80 dB
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 9 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
2.12 Neutral (Solidly Earthed) Solidly Earthed Solidly Earthed
2.13 Service Outdoor Outdoor
2.14 Duty Continuous Continuous
2.15 Overload capacity As per IEC 60076-7 As per IEC 60076-7
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 10 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
4.02 Winding 40 Deg C 50 Deg C
4.03 Winding hot spot rise 66 Deg C 61 Deg C
4.04 Core hot spot rise 61 Deg C 55 Deg C
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 11 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
8.03 LV (LI/LIC/AC) 250kVp/275kVp/95kVrms 250kVp/275kVp/95kVrms
8.04 N (LI/AC) 170kVp/38kVrms 170kVp/38kVrms
9.00 Bushing Ratings
9.01 HV 420kV/2000A, OIP Condenser 420kV/1250A, RIP Condenser
9.02 LV 245kV/1250A, OIP Condenser 245kV/2000A, RIP Condenser
9.03 TV 72.5kV/3150A, OIP Condenser 52kV/3150A, RIP Condenser
9.04 Neutral 36kV/2000A, Oil Communicating 36kV/2000A, Oil Communicating
9.05 Impulse level (HV/IV/LV/N) 1425kVp/1050kVp/250kVp/170kVp 1425kVp/1050kVp/250kVp/170kVp
9.06 Switching impulse level (HV/IV) 1050kVp/850kVp 1050kVp/850kVp
Power Frequency (Dry) 695kVrms/505kVrms/105kVrms/77 695kVrms/505kVrms/105kVrms/77
9.07
(HV/IV/LV/N) kVrns kVrns
10.0
CORE
0
10.0
Flux Density at Rated Voltage 1.722 T 1.72 T
1
10.0 Core Construction
3 Main Limbs / 2 Return Limbs 3 Main Limbs / 2 Return Limbs
2 [main limb / return limb]
Cross-section ratio -
10.0 100% & 53% 100% & 53%
Main & Return limb
3 100% & 53% 100% & 53%
Main limb & Yoke
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 12 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
10.0
Core Diameter 815 1015
4
10.0 Window Height (top of Bottom yoke
2500 2400
5 to bottom of top yoke)
10.0
Phase center /Phase - Return limb 2315 / 1420 2610/1650
6
10.0
Grade HP Grade HP Grade
7
10.0
Building factor 1.17 1.18
8
10.0
Weight 67500 kgs Approx. 108500 kgs Approx.
9
11.0
Winding
0
11.0 Winding arrangement sequence Core - LV - Reg. - Common - Series Core - LV - Reg. - Common - Series
1 (Core - LV - Reg. - Common - Series)
11.0
Winding Type & Material
2
11.0
LV Helical, Electrolytic Copper Helical, Electrolytic Copper
3
11.0
REG Multi Helical, Electrolytic Copper (Tap) Multi Helical, Electrolytic Copper (Tap)
4
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 13 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
11.0
IV Disc, Electrolytic Copper Disc, Electrolytic Copper
5
11.0
HV Shielded disc, Electrolytic Copper Shielded disc, Electrolytic Copper
6
13.0
Proof Stress Value in Mpa
0
13.0
LV 180 200
1
13.0
REG 160 200
2
13.0
IV 200 200
3
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 14 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
13.0
HV 160 200
4
13.0
ID / OD / Height
0
13.0
LV 875/955/1900 1075/1160/1780
1
13.0
REG 1115/1155/1780 1320/1365/1700
2
13.0
IV 1305/1575/1950 1515/1845/1790
3
13.0
HV 1755/2100/1950 2069/2430/1790
4
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 15 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
15.0
Winding weight Bare Copper Bare Copper
0
15.0
LV 3440 kg 4300 kg
1
15.0
REG 2100 kg 2300 kg
2
15.0
IV 16450 kg 20700 kg
3
15.0
HV 22400 kg 27500 kg
4
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 16 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
17.0
I2R 385 / 344 / 415 441 / 394 / 471
1
17.0
Stray 39/ 45 / 56 47 / 54 / 117
2
17.0
Eddy 30/ 37 / 55 37 / 47 / 67
3
17.0
Stray+Eddy 69 / 82 / 111 84 / 101 / 184
4
17.0
Total Load Loss 454 / 426 / 526 525 / 495 / 655
5
17.0
% (Stray+Eddy) of Load loss 15.2 / 19.3 / 21 16 / 20.5 / 28
6
17.0
Core loss 84.5 88.4
7
18.0
GAP (mm)
0
18.0
CORE - LV or CORE-TV 30 30
1
18.0
LV - REG 80 80
2
18.0
REG - IV 75 75
3
18.0
IV-HV 90 112
4
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 17 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
18.0
PH - PH 175 177
5
18.0
PH - RETURN LIMB 160 166
6
19.0
Spacers / Circle (Nos. x Width)
0
19.0
LV 24 x 35W 36 X 30W
1
19.0
REG 24 x 45W 36 X 40W
2
19.0
IV 36 X 40W 36 X 45W
3
19.0
HV 36 X 50W 36 X 60W
4
Supporting Area
20.0
((No of spacer x width) *100/Mean
0
dia)
20.0
LV 29.20% 31.0%
1
20.0
REG 30.3% 34.1%
2
20.0
IV 32.0% 31.0%
3
20.0
HV 30.0% 30.5%
4
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 18 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
21.0
Top Ring Thickness & Material 100 mm & Laminated Press Board 130 mm & Laminated Press Board
0
22.0
Bottom Ring Thickness & Material 80 mm & Laminated Press Board 90 mm & Laminated Press Board
0
23.0
Oil Quantity during first filling 100 kL 115 kL
0
24.0
Tank Thickness
0
24.0
Side 12 mm 12 mm
1
24.0
Top 25 mm 25 mm
2
24.0
Bottom 20 mm + Box Stiffener 20 mm + Box Stiffener
3
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 19 of 27
Technical parameter of Offered & Short circuit tested Transformer
Sr. Technical Parameters Short Circuit Tested Unit Rating Offered Transformer
No
Internal clearance in oil (Active part
27.0 Similar/No change w.r.t short circuit
- Tank) -
0 tested unit.
Change (Yes / No)
Cooling System (Radiator, Fans,
Pumps)
28.0 Same / Fans & pumps are suitably
Change (Yes / No), If yes, submit -
0 considered to dissipate total losses
detailed design calculation for
supporting documents)
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 20 of 27
DOC No : ______________
Comparison Table - Forces & Electric Field Stress Summary
REV : _________________
Sr. Technical Parameters 315MVA, 400/220/33 kV 500MVA, 400/220/33 kV
No Short Circuit Tested Offered Transformer
1.0 NOA Ref No. ----- -----
1.1 Package & Substation ----- -----
Radial Forces (Actual / Permissible)
2.0
(N/mm2 or Mpa)
2.1 LV 57.05/180 Mpa 47.5/200 Mpa
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 21 of 27
3.3 IV 1436/129384 kN 1819/111123 kN
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 22 of 27
7.4 Oil Stress (IV- HV) < 6.5 kVrms/mm
7.5 Max Oil Stress Location & Value IV - HV winding < 6.5 kVrms/mm
7.11 Stress at Normal Service condition Less than half of above values
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 23 of 27
Comparison of forces and stresses of 500MVA,400/220/33kV,3-Phase Auto Transformer with SC tested Doc. No: _________________;
315MVA,400/220/33kV, 3-Phase Auto Transformer as per IEC-60076-5 Rev_________
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 24 of 27
Stress due
to radial
bending of
conductor
s between 70.5 642 211.5 - 69.6 14.63 123.8 - 201.9 22.66 278.6 - -
axial
sticks and
spacers
(Mpa)
Stress
due to
axial
bending
of
305.44 1375 1460 - 177.8 134.8 1146.8 - 2574.08 1114 8597.4 - 2336.2 5160 11120.4 -
conductor
s between
radial
spacers
(Mpa)
Thrust
force
acting on
the
low
18.29 310.36 61.6 - Not Applicable Not Applicable Not Applicable
voltage
winding
lead
exists
(kN)
Maximum
axial
compressi
on
force on 485 3954 1421 - 398 296 796 - 1819 1436 4075 - 2405 1105 4642 -
each
physical
winding
(kN)
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 25 of 27
Maximum
axial
compressi
on
force on
winding 485 3954 - 105686 398 296 - 3164 1819 1436 - 111123 2405 1105 - 349302
compared
to crit.
Force for
tilting
(kN)
Maximum
end
thrust
force on
201/ 2429/ 101/ 572/ 531/ 785/ 732/
physical - - 82/59 - - - - - -
165 3316 97 744 508 877 750
winding :
- UP (kN)
- DOWN
(kN)
Compress
ive stress
on
conductor
paper
11.25 20.1 80 - 17.66 16.77 80 - 8.78 12.56 80 - 10.55 5.78 80 -
Insulatio
n and
radial
spacers
(Mpa)
Compress
ive stress
on end
stack
4.66 12.35 80 - 4.48 4.64 80 - 2.76 4.63 80 - 3.44 3.83 80 -
insulation
structure
s and end
ring (Mpa)
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 26 of 27
Actual Reference Allowable Critical
Compress
ive stress
on
common 59.21 60.27 80 -
press
rings
(Mpa)
Tensile
stress on
Not Applicable Not Applicable Not Applicable Not Applicable
tie rods
(Mpa)
Clamping
force per 1723 1912 -
limb (kN)
Annexure-J: Criteria for selection of similar reference transformer for dynamic short circuit withstand test Page 27 of 27
Annexure-K
PAINTING PROCEDURE
Note:
(*) indicates Sa 2 ½ as per Swedish Standard SIS 055900 of ISO 8501 Part-1.
NB: Nominal Bore
Annexure–L
I. UNUSED INHIBITED HIGH GRADE INSULATING OIL PARAMETERS
Note: Supplier shall declare the chemical family and function of all additives
and the concentrations in the cases of inhibitors, antioxidants and passivators.
Note: Supplier shall declare the chemical family and function of all additives
and the concentrations in the cases of inhibitors, antioxidants and passivators.
III. Oil used for first filling, testing and impregnation of active parts at
manufacturer's works shall meet parameters as mentioned below
IV. Each lot of the oil shall be tested prior to filling in main tank at site
for the following:
V. After filtration & settling and prior to energization at site oil shall
be tested for following:
* Separate oil sample shall be taken and test results shall be submitted
within 45 days after commissioning for approval of the utility
Symbol Description
L2 Length between bottom seat of flange and bottom of the oil end shield/ stress relieving
electrode/ oil end terminal whichever is the longest
L6 Length for accommodating Bushing Current Transformer (BCT)
D2 Maximum diameter of oil immersed end
D3 Outside diameter of fixing flange
D4 Pitch Circle Diameter of fixing holes of flange
D5 Diameter of fixing hole
N Number of fixing holes
D6 Maximum diameter of oil end shield/stress relieving electrode
L11 Horizontal Distance between holes for bushing bottom connection for 4 hole connection
L12 Vertical Distance between holes for bushing bottom connection for 4 hole connection
L13 Vertical Distance between holes for bushing bottom connection for 2 hole connection
D7 Diameter of hole for bushing bottom connection for 2 hole connection
D8 Diameter of hole for bushing bottom connection for 4 hole connection
Annexure-M : Standard dimensions for condenser bushings Page 1 of 3
Annexure-M
3.0 The foundation design should take into account the following points:
e) An oil soak pit of adequate capacity should be provided below each oil
filled transformer to accommodate at least 150% of full quantity of oil
contained in the transformer and minimum 300 mm thick layer of
gravels/pebbles of approximately 40 mm size (spread over a steel iron
grating/trans rack) providing free space below the grating.
Alternatively, an oil soak pit should be provided below each
transformer/reactor to accommodate 1/3rd of total quantity of oil
contained in the transformer and minimum 300 mm thick layer of
gravels/pebbles of approximately 40 mm size (spread over a steel iron
grating/trans rack) providing free space below the grating provided a
common remote oil collecting pit of capacity at least equal to oil
quantity in the largest size transformer/reactor is provided for a group
of transformers. Bottom of the soak pit below the transformer/reactor
should be connected to the common oil collecting pit with drain pipe
(two or more Hume/concrete pipes) of minimum 150 mm diameter
with a slope not less than 1/96 for fast draining of oil and water
through gravity from soak pit to the burnt oil collecting pit, which is
generally located away from transformers/reactors.
g) The common remote oil collecting pit and soak pit (when remote oil
collecting pit is not provided) should be provided with suitable
automatic pumping facility, to always keep the pit empty and
available for an emergency.
4.0 It is a fact that maximum weight of transformer (with oil and all fittings &
accessories) and outline dimension do not vary much from manufacturer
to manufacturer for same rating. Hence a common foundation layout plan
with soak pit (with oil and all fittings & accessories) with loading details
would facilitate the interchangeability of transformers/reactors of different
make of similar/same ratings. The utilities shall strive to standardize the
foundation plan for different rating of transformers so that transformers
of different makes could be accommodated in the same space with minor
modification / without any modification in the existing foundation
resulting in reduction in the outage time of replacement of old transformer
or reactor.
5.0 The rail track gauge shall be 1676 mm. All voltage class transformers shall
have two (2) rails..
1.3 At least one (1) core shall be kept as spare in each copper control cable of
4C, 5C or 7C size whereas minimum no. of spare cores shall be two (2) for
control cables of 10 core or higher size.
1.5 The fillers and inner sheath shall be of non-hygroscopic, fire retardant
material, shall be softer than insulation and outer sheath shall be suitable
for the operating temperature of the cable.
1.7 Strip wire armouring method (a) mentioned in Table 5, Page-6 of IS: 1554
(Part 1) – 1988 shall not be accepted for any of the cables. For control
cables only round wire armouring shall be used.
1.8 The cables shall have outer sheath of a material with an oxygen index of
not less than 29 and a temperature index of not less than 250°C.
1.9 All the cables shall conform to fire resistance test as per IS: 1554 (Part -
I).
1.10 The normal current rating of all PVC insulated cables shall be as per IS:
3961.
1.12 Allowable tolerance on the overall diameter of the cables shall be ± 2 mm.
1.13.1 The PVC insulated 1100V grade power cables shall be of Fire Retardant
Low Smoke Halogen (FRLSH) type, C2 category, conforming to IS: 1554
1.14.1 The 1100V grade control cables shall be of FRLSH type, C2 category
conforming to IS: 1554 (Part-1) and its amendments, read along with this
specification. The conductor shall be stranded copper. The insulation shall
be extruded PVC of type A of IS: 5831. A distinct inner sheath shall be
provided in all cables whether armoured or not. The outer sheath shall be
extruded PVC of type ST-1 of IS: 5831 and shall be grey in colour except
where specifically advised by the purchaser to be black.
1.14.2 Cores shall be identified as per IS: 1554 (Part-1) for the cables up to five
(5) cores and for cables with more than five (5) cores the identification of
cores shall be done by printing legible Hindu Arabic Numerals on all cores
as per clause 10.3 of IS : 1554 (Part - 1).
LIST OF CODES/STANDARDS/REGULATIONS/PUBLICATIONS
IS 2074 : Part 1 : 2015 - Ready Mixed Paint, Air Drying, Red Oxide -
Zinc Chrome, Priming - Specification