Nitrogen Handling Purging
Nitrogen Handling Purging
Since the operation involves potential hazards of over pressurization since high pressure
gas is being introduced into a tank which is not designed to withstand internal pressure,
and whose structure may fail at less than 0.5bar overpressure and for some vessels less
than 0.7 bar overpressure, a clear understanding of the risks and controls in place should
therefore be thoroughly understood. Masters should ensure that procedures are strictly
being followed and all personnel involved should be made conversant with those
procedures.
When liquid is being loaded through the cargo manifold and pipelines system on a
chemical carrier, the existing atmosphere in the tank can escape through a vent system
that is notably smaller than the liquid filling line, because friction and turbulence are far
greater impediments to liquid flow than to gas flow, ships are designed with this in mind.
However, when a gas is being introduced through the liquid filling line, especially a gas
under pressure that will expand within the tank, the same condition does not apply, and
the disparate sizes between the inlet and outlet can allow an overpressure to develop. To
avoid such an eventuality, the outlet for the existing atmosphere in the tank should be as
big as or bigger than the pipeline supplying the gas. That is achieved by having the cargo
tank lid or a tank washing hatch open.
When vapour control and emission regulations require a closed operation (with the
existing tank atmosphere forced to exhaust to shore), the incoming flow of nitrogen must
be restricted to a rate equal to or less than the maximum flow of vapour possible through
the venting system after allowing for vapour density and pipe line frictional forces (see
ships VECS manual for details). If the capacity of the vapour return system is exceeded
by the flow of nitrogen into a closed cargo tank, then the only other outlet is through the
P/V valve, which will prevent over pressurization (though contravening the vapour
emission control regulations). However, if the capacity of both outlets is exceeded, then
over pressurization will occur and damage to the tank structure may follow along with the
emission hazards. The pressure and the flow rate of the incoming nitrogen must therefore
be controlled. Use of a small hose or a reducer and a gas control valve prior to the
manifold will restrict the flow rate, where such reducer and gas control valve is not fitted
at the ships end before the manifold, then the only solution is to request the loading
Master to control the shore N2 pressure/flow rate. The gauge fitted at the manifold will
allow the ship to monitor the pressure. It is not appropriate or sufficient to attempt
throttling a gas flow by using the ship’s manifold valve that is designed to control liquid
flow. However manifold valve can and should be used as a rapid safety stop in an
emergency- pressure surge in a gas is not as violent as in liquid. Care should be taken
when using cargo lines to carry out N2 padding, when changing over tanks since the lines
of the next tank/s will be filled with cargo it is essential than the valves be operated(i.e.
closed) slowly to avoid damage due to pressure surges. A risk assessment is required
when ever such an operations are performed where vapour control and emission
regulations require a closed operation and multiple hazards exist.
When a cargo is required to be carried under a pad of nitrogen, and it is necessary to use
nitrogen supplied from shore, it is better to purge the entire tank before loading if this is
acceptable with the terminal/charterers rather than bubbling the N2 through cargo. After
such purging is completed, loading the cargo in a closed condition will create the needed
pad within the tank. The risk of over pressurization can be substantially reduced by
avoiding padding with shore supplied nitrogen as a separate procedure on completion of
loading.
If padding with shore nitrogen has to be performed after loading, planning and good
communication are essential. The N2 supply should be through a small diameter
connection to restrict the flow, and the rate must not exceed the vent capacity of the cargo
tank, this can be achieved by keeping the tank dome open where vapour emission to
atmosphere is not restricted due to pollution or health concerns. The operation should be
stopped when a slight overpressure exists in the ullage space, but which is less than the
tank pressure relief valve setting. The vapour space in a loaded tank is usually small, so
over pressurization can occur very suddenly, especially if cargo is forced into the vent
lines which then become restricted or blocked and add to the rapid increase in tank
pressure.
Inerting/Padding/Purging restriction:
Padding a cargo tank after loading i.e. when bubbling the N2 through cargo is only
permitted for cargoes where restriction to vapour emission to atmosphere does not exist
(i.e. No restriction due to pollution or health concerns) and hence which can be vented
through a large enough opening such as the tank dome since due to limited ullage space
clearly the P/V valve will not be able to cope with such high flow rates. Where the cargo
to be loaded is such that vapour emission to atmosphere is restricted then the whole tank
should be inerted when empty and gas free and loading carried out using the vapour
recovery system with the vapours being sent to shore and pad by the remaining N2. The
positive pressure required during the voyage can be achieved by the ships N2 facility just
before sailing out of port/berth and subsequently during the voyage.
Where cargoes are inhibited and such inhibitor requires a certain level of oxygen to be
maintained then such cargo tanks should not be inerted or care should be taken to ensure
that the minimum oxygen levels are not breached.
Table 1 shows the volume of nitrogen that can be received in one minute through a
known size of pipe at a known pressure. (The second figure in brackets indicates the
associated hourly rate which should be mentally compared to a liquid loading rate. Note
that these tables are intended to be indicative only, and any discrepancies are due to
rounding of figures.)
Table 2: Illustrates the time taken to receive gas into a tank at different pressures and
hose sizes. The example used assumes a cargo tank of 1,250 cubic metres requiring four
atmosphere changes, i.e. 5,000 cubic metres of nitrogen, to flow through.
a) Tank over-pressurization may result if the supplied volumetric flow of gas exceeds the
maximum venting capacity of the tank vessel outlet being open.
b) Tank over-pressurization may result even if the maximum venting capacity of the tank
is not realized due to failure of equipment such as vents, valves, and blocked vent lines
and due to operation errors.
c) An oxygen deficient atmosphere may develop in the vicinity of open hatches in some
weather conditions.
d) Failure to communicate: Although pre-transfer conferences are being conducted, the
outcome of there ship shore meetings does not filter down to the crew engaged in the
operations causing gaps in what is required of the crew members and what he thinks is
expected of him. Details of the operation including individual roles are to be discussed in
the pre-operation safety meeting.
e) When padding is carried out in a loaded tank, the cargo vapors from low pour point
cargoes can cause additional hazards such as vent line and vent valve blockage.
f) Personnel may be exposed to liquid cargo or cargo vapors if tank integrity is lost.
g) The valve at the supply side or manifold valve may inadvertently open or close due to
pressure or vibration if unattended. The manifold valves are designed for liquid flow and
are largely ineffective as a means to control gas flow.
When preparing to receive nitrogen from shore special emphasis should be placed on the
following points:
1. Ship and shore should agree in writing on the gas supply, specifying the volume
required, the flow rate in standard cubic meters per minute or hour, and the
minimum rate at which N2 that can be supplied by the terminal, the maximum
rate at which N2 can be received by the vessel and the notice required for
reducing/stopping the N2 flow to the vessel.
2. Care should be taken to ensure that the valves on the loading line between the
shore manifold and the ship’s tank are operated in the correct sequence, so that
the ship is in control of the nitrogen flow.
3. The ship should station a crew member at the loading manifold valve during the
operation, even where remotely operated valves can be closed more quickly by
person in the cargo control room who is monitoring tank pressures. The crew
member at the manifold is in the best position to react promptly to any other
external indication of trouble.
4. The tank pressure should be closely monitored during the operation.
5. Primary and secondary communications between terminal and ship established
and in use.
6. The tank(s) should be tagged (taped off) with warning sign.
7. All personnel working in the deck area should be made aware of the inerting
operation and instructed to remain clear.
Note: The above precautions also apply where applicable when using ship N2 plant.
The said precautions relates to inerting on a chemical tanker. The tanks are clean and gas
free in all respects before the inerting process and inerting is done with pure nitrogen.
The precautions do not address other forms of inert gas or purging of tanks which may
contain previous cargoes and which will require additional precautions relating to their
toxicity and flammability hazard. The padding in this case is achieved by inerting the
entire tank before loading and then creating the padding through loading operations.
This is only permitted for cargo vapors where restriction to vapor emission to atmosphere
does not exist and where the inert gas does not cause reaction with the cargo. During such
an operations the N2 is directed through the tank drop line and bubbled through the cargo
and the displaced air is vented through the tank dome (OTH) until the oxygen content
reduces to the figure so designated by the shippers/charterers (usually 3%). The tank
atmosphere i.e O2 is to be monitored using a portable oxygen analyzer fitted with an
extension hose, where as the said crew member doing the monitoring is to be positioned
90 degrees towards the leeward side near the tank dome (OTH) wearing a personal
multigas detector to monitor the oxygen content at his location. Where terminal
requirements restrict the efflux of nitrogen on deck, the flow rate should be kept to 80%
of the flow rate of the P/V valve.(Refer to the VECS manual and the PV valve manual )
The oxygen content will have to be monitored from the sampling cock fitted on the vent
line.
Not withstanding above procedure the health hazards of oxygen deficiency (asphyxia)
during the Nitrogen purging/padding/inerting operations to be briefed to the crew and
their understanding confirmed prior such operations are planned. The above procedure
contains brief safety procedures for the said operations and not to be construed as to
replace any thing contained in the IBC code, the Tanker safety guide-Chemicals or other
safety and operational guide which must be consulted for more detailed information.
Risk Assessment
Risk Assessment must be carried out prior every inerting, purging and padding
operations.
Related Documents
1. T -125 Nitrogen Handling Checklist
2. Nitrogen Handling Safety Video
3. Danger Warning Signs
4. Form S-132 Initial Risk Assessment
5. Form S -133 Detailed Risk Assessment